Montana Environmental Info. v. Debra Thomas , 902 F.3d 971 ( 2018 )


Menu:
  •                 FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    MONTANA ENVIRONMENTAL                    No. 16-71933
    INFORMATION CENTER,
    Petitioner,
    OPINION
    v.
    DEBRA H. THOMAS, in her capacity
    as Acting Regional Administrator,
    United States Environmental
    Protection Agency, Region 8; U.S.
    ENVIRONMENTAL PROTECTION
    AGENCY,
    Respondents,
    MONTANA DEPARTMENT OF
    ENVIRONMENTAL QUALITY; TALEN
    MONTANA, LLC,
    Respondents-Intervenors.
    On Petition for Review of an Order of the
    Environmental Protection Agency
    Argued and Submitted February 14, 2018
    San Francisco, California
    Filed August 30, 2018
    2          MONTANA ENVTL. INFO CTR. V. THOMAS
    Before: Mary M. Schroeder and Johnnie B. Rawlinson,
    Circuit Judges, and William K. Sessions III,* District
    Judge.
    Opinion by Judge Rawlinson
    SUMMARY**
    Environmental Law
    The panel denied a petition for review challenging an
    action of the United States Environmental Protection Agency
    approving a 1994 revision to Montana’s State Implementation
    Plan.
    Petitioner alleged that the EPA’s approval was arbitrary
    and capricious because the Montana Department of
    Environmental Quality (“DEQ”) interpreted “actual
    emissions” less stringently than the Clean Air Act would
    allow. The DEQ’s interpretation was advanced in unrelated
    litigation (the “Talen case”). Petitioner further alleged that
    Montana’s 1994 Revised State Implementation plan was
    deficient, and the EPA should not have approved the 2008-
    2015 revisions until the state definition of “actual emissions”
    complied with federal standards. Petitioner submitted a
    comment during the EPA’s notice and comment period
    *
    The Honorable William K. Sessions III, United States District Judge
    for the District of Vermont, sitting by designation.
    **
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    MONTANA ENVTL. INFO CTR. V. THOMAS                3
    following Montana’s submission on December 17, 2015 of its
    final implementation plan.
    The panel held that the language of the Implementation
    Plan concerning the “two year period” in determining a
    source’s actual emissions was ambiguous where the DEQ and
    the EPA reasonably interpreted the phrase to mean two
    different things. The panel further held that it was
    appropriate to give deference to the EPA’s reasonable
    interpretation, consistent with the deference given under
    Chevron to the EPA’s rulemaking authority. The panel
    agreed with the EPA that petitioner’s comment raised a
    question of implementation of a program rather than approval
    of a plan, and as such, DEQ’s statements in the Talen case
    need not be resolved at the approval phase of the state plan.
    The panel held that because the EPA’s interpretation of
    ambiguous text in the 1994 Revised Implementation Plan was
    a permissible one, and because the EPA’s interpretation
    controlled, its approval of the succeeding 2015
    Implementation Plan was not arbitrary or capricious. The
    2015 Implementation Plan was otherwise in conformance
    with the EPA’s Prevention of Significant Deterioration
    program under the Clean Air Act.
    4        MONTANA ENVTL. INFO CTR. V. THOMAS
    COUNSEL
    George E. Hays (argued), San Francisco, California; Derf
    Johnson, Montana Environmental Information Center,
    Helena, Montana; for Petitioner.
    Sheila Baynes (argued) and Jeffrey H. Wood, Acting
    Assistant Attorney General; Environmental Defense Section,
    Environment & Natural Resources Division, United States
    Department of Justice, Washington, D.C.; Kristi M. Smith,
    Brian Doster, Zach Pilchen, and Melina Williams, Office of
    General Counsel, Environmental Protection Agency,
    Washington, D.C.; for Respondents.
    Norman J. Mullen (argued), Montana Department of
    Environmental Quality, Helena, Montana, for Respondent-
    Intervenor Montana Department of Environmental Quality.
    Joshua Frank (argued), Baker Botts LLP, Washington, D.C.,
    for Respondent-Intervenor Talen Montana LLC.
    MONTANA ENVTL. INFO CTR. V. THOMAS                 5
    OPINION
    RAWLINSON, Circuit Judge:
    Petitioner, Montana Environmental Information Center
    (Information Center), challenges an action of the United
    States Environmental Protection Agency (Agency) approving
    a 1994 revision to Montana’s State Implementation Plan
    (Implementation Plan). Information Center asserts that the
    Agency’s approval was arbitrary and capricious because
    Montana interprets one of its provisions less stringently than
    the Clean Air Act would allow. We have jurisdiction to
    review the EPA’s action under 42 U.S.C. § 7607(b)(1), and
    deny the petition for review.
    I. Statutory and Regulatory Background
    A. Clean Air Act
    Congress passed the Clean Air Act to protect and enhance
    the quality of the nation’s air. See 42 U.S.C. § 7401(b)(1).
    To achieve this, “the States and the Federal Government
    partner[ed] in the struggle against air pollution.” General
    Motors Corp. v. United States, 
    496 U.S. 530
    , 532 (1990). We
    have deemed this partnership “a uniquely important system
    of cooperative federalism in the quest for clean air.”
    Committee for a Better Arvin v. EPA, 
    786 F.3d 1169
    , 1173
    (9th Cir. 2015) (citation omitted).
    B. Federal-State Partnership
    One of the Agency’s primary responsibilities under the
    Clean Air Act is to identify air pollutants that endanger the
    public health and welfare. See 42 U.S.C. § 7408(a). Once
    6         MONTANA ENVTL. INFO CTR. V. THOMAS
    identified, the Agency must then set National Ambient Air
    Quality Standards (Air Quality Standards), which specify the
    maximum allowable concentration of those pollutants in the
    atmosphere. See 
    id. § 7409.
    The Air Quality Standards are
    subject to periodic review and revision. See 
    id. In sum,
    the
    federal government’s role in the federal-state partnership is to
    combat air pollution by identifying pollutants and then setting
    (and updating) Air Quality Standards.
    But what of the states? “The [Clean Air Act] requires the
    states to submit State Implementation Plans, or ‘SIPs,’
    showing how the states will attain [Air Quality Standards] . . .
    ” El Comite Para el Bienestar de Earlimart v. EPA, 
    786 F.3d 688
    , 692 (9th Cir. 2015) (citing 42 U.S.C. § 7410(a)(1)); see
    also Whitman v. Am. Trucking Assn’s, Inc., 
    531 U.S. 457
    , 470
    (2001) (“It is to the States that the [Clean Air Act] assigns
    initial and primary responsibility for deciding what emissions
    reductions will be required from which sources. . . .”)
    (citations omitted). These Implementation Plans must “make
    demonstrations (of how attainment, maintenance, and
    progress will be achieved) and [] provide a control strategy
    that will achieve the necessary reductions and otherwise meet
    the requirements of the Act.” Hall v. EPA, 
    273 F.3d 1146
    ,
    1153 (9th Cir. 2001), as amended (citation omitted). Each
    plan must “specify the manner in which [Air Quality
    Standards] will be achieved and maintained within each air
    quality control region.” 42 U.S.C. § 7407(a).
    C. State Implementation Plans
    If the Agency determines that a proposed Implementation
    Plan meets the applicable requirements, then that
    Implementation Plan “bec[o]me[s] federal law, not state
    law.” Safe Air For Everyone v. EPA, 
    488 F.3d 1088
    , 1097
    MONTANA ENVTL. INFO CTR. V. THOMAS                  7
    (9th Cir. 2007), as amended (emphasis in the original). That
    is true in part because Implementation Plans cannot be
    amended without the EPA’s further approval. See 
    id. When the
    Agency updates its Air Quality Standards,
    states have three years to revise their Implementation Plans
    to comply with the new standards. See 42 U.S.C.
    § 7410(a)(1). “These revisions need not be wholesale
    recastings of [Implementation Plans]; instead, the [Clean Air
    Act] allows the states to submit, and [the] Agency to review,
    piecemeal amendments dealing with discrete [Implementation
    Plan] provisions, leaving most of the plan untouched.” Safe
    
    Air, 488 F.3d at 1092
    (citation omitted).
    In addition, Implementation Plans must comply with the
    Clean Air Act’s Prevention of Significant Deterioration
    program (PSD program). See 40 C.F.R. § 51.166(a)(1)
    (“[E]ach applicable State Implementation Plan . . . shall
    contain emission limitations and such other measures as may
    be necessary to prevent significant deterioration of air
    quality.”). The purpose of the PSD program is to ensure that
    major sources of air pollution do not degrade areas that either
    meet Air Quality Standards (also known as “attainment”
    areas) or cannot be classified as meeting—or not meeting—
    Air Quality Standards (also known as “unclassifiable” areas).
    See 42 U.S.C. § 7407(d)(1). The PSD program combats
    degradation of these areas by requiring developers to acquire
    permits before constructing new sources of emissions or
    modifying existing ones. See 40 C.F.R. § 51.166(a)(7). The
    permit requirement applies to existing sources that are
    planned to undergo a “major modification,” 
    id., resulting in
    a “significant emissions increase” and a “significant net
    emissions increase.”         
    Id. § 51.166(a)(1)(7)(iv)(a).
    “Significant emissions increases” are calculated by taking the
    8        MONTANA ENVTL. INFO CTR. V. THOMAS
    “actual emissions” of a source, which establishes a
    representative baseline level of emissions, 
    id. § 51.166(b)(47),
    and comparing that baseline to the projected
    emissions, post-modification. See 
    id. § 51.166
    (a)(7)(iv)(c).
    This formula evokes the question of how to determine a
    source’s “actual emissions.” The answer has evolved over
    time. In 1980, the Agency stated that actual emissions
    shall equal the average rate, in tons per year,
    at which the unit actually emitted the pollutant
    during a two-year period which precedes the
    particular date and which is representative of
    normal source operation. The reviewing
    authority may allow the use of a different time
    period upon a determination that it is more
    representative of normal source operation.
    40 C.F.R. § 51.24(b)(21)(1980).
    In 1992, the Agency clarified that “a 2-year period which
    precedes the particular date” has “historically [meant] the
    2 years immediately preceding the proposed change to
    establish the baseline.” 57 Fed. Reg. 32,314, 32,323 (July 21,
    1992) (citations omitted). Going forward, however, “the
    [Agency] would presume that any 2 consecutive years within
    the 5 years prior to the proposed change is representative.”
    
    Id. Ten years
    later, the Agency formally updated its
    definition of “baseline actual emissions.” This update
    involved creating separate definitions for steam power plants
    and all other stationary sources. As of 2002, the baseline
    actual emissions of steam power plants equaled the average
    MONTANA ENVTL. INFO CTR. V. THOMAS                  9
    rate of a pollutant actually emitted “during any consecutive
    24-month period selected by the owner or operator within the
    5-year period immediately preceding [the] . . . actual
    construction of the project. The reviewing authority shall
    allow the use of a different time period upon a determination
    that it is more representative of normal source operation.”
    40 C.F.R. § 51.166(b)(47)(i). The baseline actual emissions
    of non-steam sources equaled omissions occurring “during
    any consecutive 24-month period . . . within the 10-year
    period immediately preceding” construction of a project. 
    Id. § 51.166(b)(47)(ii).
    Although the Clean Air Act requires each Implementation
    Plan to contain permitting processes that comply with the
    PSD program, the Act does not require verbatim adoption of
    the PSD program. Rather, a state is free to deviate so long as
    it “specifically demonstrates” that those deviations “are more
    stringent than or at least as stringent in all respects as the
    corresponding provisions [of the Clean Air Act.]” 40 C.F.R.
    51.166(a)(7)(iv).
    II. Factual and Procedural Background
    Montana, “like every other state, was first required to
    submit [an Implementation Plan] to the [Agency] within
    thirteen months of the Act’s . . . passage.” Safe 
    Air, 488 F.3d at 1093
    (citing Train v. NRDC, 
    421 U.S. 60
    , 65 (1975). In
    addition, Montana is required to revise its Implementation
    Plan concomitantly with EPA updates to federal standards.
    See 42 U.S.C. § 7410. Relevant to this case is a revision
    Montana submitted on March 30, 1994 (1994 Revised
    Implementation Plan). The revision contained the following
    definition of “actual emissions:”
    10       MONTANA ENVTL. INFO CTR. V. THOMAS
    Actual emissions as of a particular date shall
    equal the average rate, in tons per year, at
    which the unit actually emitted the pollutant
    during a two-year period which precedes the
    particular date and which is representative of
    normal source operation. The department may
    determine that a different time period is more
    representative of normal source operation. . . .
    This definition, in large part, mirrors the Agency’s 1980
    definition of actual emissions, see 40 C.F.R. § 51.24(b)(21)
    (1980), and was approved by the Agency in 1995. See
    60 Fed. Reg. 36,715, 36,719 (July 18, 1995).
    Between 2008 and 2012, the Agency updated its Air
    Quality Standards. See 81 Fed. Reg. 4225 (Jan. 26, 2016).
    These updates triggered Montana’s obligation to revise its
    Implementation Plan within three years. See 42 U.S.C.
    § 7410. On December 17, 2015, Montana submitted its final
    Implementation Plan in response to the 2008–2012 updates.
    This Implementation Plan contained the same emissions
    definition that was approved by the Agency in 1995. During
    the Agency’s subsequent notice and comment period,
    Information Center submitted a comment to the effect that
    Montana interpreted the definition of “actual emissions” from
    its 1994 Revised Implementation Plan less stringently than
    the PSD program requires.
    The basis for Information Center’s comment was the
    interpretation of “actual emissions” advanced by the Montana
    Department of Environmental Quality (DEQ) in unrelated
    litigation. See Sierra Club and MEIC v. Talen Montana,
    LLC, CV13-32-BLG-DLC-JCL, 
    2015 WL 13714343
    (D.
    Mont. Dec. 31, 2015). In Talen, the DEQ acknowledged that
    MONTANA ENVTL. INFO CTR. V. THOMAS                    11
    the Information Center and the Agency read the definition of
    “actual emissions” to mean “‘the’ two-year period
    immediately preceding” a modification. DEQ argued that
    “no deference [should be given] to [the Agency’s
    interpretation] because . . . the interpretation that [it is] ‘the’
    two-year period immediately preceding [a modification] is
    inconsistent within the rule language which says . . . ‘a’ two-
    year period.” (emphases added).
    The Agency responded that it “appreciates and takes
    seriously [Information Center’s comment] that Montana has
    adopted ‘policy interpretations’ outside the context of the
    [Implementation Plan] that may undermine the State’s
    implementation of the [Implementation Plan] as approved by
    the [Agency].” Still, the Agency did not find it necessary to
    “evaluat[e] the merits of these assertions concerning
    implementation of the [Implementation Plan] in the context
    of this action” because “this action involves a review of the
    [Implementation Plan] itself.” Accordingly, the Agency
    expressed its “inten[t] to evaluate the merits of these
    assertions, separate from this action, at a future time.” The
    Agency determined that the previously approved 1994
    Revised Implementation Plan and the 2015 Implementation
    Plan “[met] the relevant structural requirements,” and
    approved the 2015 Implementation Plan. Information Center
    timely petitioned this court to review the Agency’s action.
    III. Standard of Review
    We review the approval of an Implementation Plan “by
    considering whether the [Agency’s] decision was arbitrary,
    capricious, an abuse of discretion, or contrary to law.”
    Committee for a Better 
    Arvin, 786 F.3d at 1174
    –75 (citations
    omitted); see also 
    Hall, 273 F.3d at 1155
    . Whether the
    12       MONTANA ENVTL. INFO CTR. V. THOMAS
    Agency acted arbitrarily and capriciously “rests on whether
    it articulated a rational connection between the facts found
    and the choice made.” Friends of Yosemite Valley v. Norton,
    
    348 F.3d 789
    , 793 (9th Cir. 2003) (citation and internal
    quotation marks omitted), opinion clarified, 
    366 F.3d 731
    (9th Cir. 2004). In conducting this review, we may neither
    “rubber-stamp administrative decisions” nor “substitute our
    judgment for that of the agency.” 
    Id. (citation and
    alterations
    omitted).
    “With respect to the [Clean Air Act], Congress has given
    [the Agency] general rulemaking authority, 42 U.S.C.
    § 7601(a)(1), which, when exercised, requires our deference
    in accordance with Chevron. . . .” Sierra Club v. EPA,
    
    671 F.3d 955
    , 962 (9th Cir. 2012) (citation and internal
    quotation marks omitted).
    IV. Analysis
    A. Montana Department of Environmental Quality
    Statements
    The entirety of Information Center’s appeal rests on the
    DEQ’s statements in the Talen litigation. Information Center
    argues that Montana’s 1994 Revised Implementation Plan did
    not comply with the Clean Air Act, because the DEQ
    interprets “actual emissions” less stringently than federal
    standards would allow.            The DEQ’s interpretation,
    Information Center contends, carries the force of law.
    Information Center maintains that Montana’s 1994 Revised
    Implementation Plan was therefore deficient, and that the
    Agency should not have approved the 2008–2015 revisions
    until the state definition of “actual emissions” complied with
    federal standards.
    MONTANA ENVTL. INFO CTR. V. THOMAS                 13
    Information Center relies on Go v. Holder, 
    744 F.3d 604
    ,
    611 (9th Cir. 2014), to support its argument that the DEQ’s
    statements have the force of law. But reliance on Go is
    misplaced in the circumstances of this case. It is well settled
    that once the Agency approves either an Implementation Plan
    or a Revised Implementation Plan, that plan becomes federal
    law. See Committee for a Better 
    Arvin, 786 F.3d at 1174
    . As
    such, “a state may not unilaterally alter the legal
    commitments of its [Implementation Plan] once [the Agency]
    approves the plan.” Safe 
    Air, 488 F.3d at 1097
    (citation
    omitted). Thus, the DEQ’s interpretation of “actual
    emissions” could not invalidate Montana’s 1994 Revised
    Implementation Plan. And, where the Agency has officially
    interpreted a vague regulatory term, the Agency’s
    interpretation prevails. See Auer v. Robbins, 
    519 U.S. 452
    ,
    461 (1997).
    B. Implementation of Program As Opposed to Approval
    of Plan
    The Clean Air Act “permits the [Agency] to issue ‘partial
    approvals’ [of Implementation Plans]. 
    Hall, 273 F.3d at 1159
    (citation and alteration omitted). In light of this
    circumstance, the question becomes to what extent the
    Agency must consider the DEQ’s statements as part of the
    approval process for an Implementation Plan.
    “In interpreting [an Implementation Plan], we begin with
    a look toward the plain meaning of the plan and stop there if
    the language is clear. . . .” Safe 
    Air, 488 F.3d at 1095
    . The
    language at issue is:
    (1) “Actual emissions as of a particular date
    shall equal . . . a two-year period which
    14        MONTANA ENVTL. INFO CTR. V. THOMAS
    precedes the particular date [of construction,]”
    and
    (2) “The department may determine that a
    different time period is more representative of
    normal source operation.”
    Under Information Center’s theory, the DEQ and the Agency
    reasonably interpreted “a two-year period” to mean two
    different things. Therefore, the language at issue is
    ambiguous. See NRDC v. Cnty. of Los Angeles, 
    725 F.3d 1194
    , 1205 (9th Cir. 2013) (explaining that language is
    ambiguous “if reasonable people could find its terms
    susceptible to more than one interpretation”) (citation
    omitted). And while Safe Air, 488 F.3d at1095–96, provides
    guidance for instances where Implementation Plan language
    is clear, it does not do so for Implementation Plan language
    that is unclear. We do so here: Where the plain meaning of
    an Implementation Plan cannot be readily discerned from the
    text, we think it appropriate to give deference to the Agency’s
    reasonable interpretation. This approach is consistent with
    the deference given under Chevron to the Agency’s
    rulemaking authority, and with how we have reviewed the
    Agency’s interpretation of Implementation Plan-related
    documents. See, e.g., El Comite Para el Bienestar de
    
    Earlimart, 786 F.3d at 696
    (“Because the plain language of
    the relevant documents is ambiguous, we defer to the EPA’s
    interpretation if it is reasonable, i.e., if it ‘sensibly conforms
    to the purpose and wording of the regulations.’”) (citation
    omitted).
    The Agency’s interpretation of the two-year period
    immediately preceding the commencement of construction is
    consistent with the tenor of the regulation to fix a finite
    MONTANA ENVTL. INFO CTR. V. THOMAS                 15
    period for the measurement of baseline emissions. See
    40 C.F.R. § 51.24(b)(2). In any event, we agree with the
    Agency that Information Center’s comment raises a question
    of implementation of a program rather than approval of a
    plan. As such, DEQ’s statements in the Talen case need not
    be resolved at the approval phase of the state plan. As
    explained above, DEQ’s policy interpretations do not carry
    the force of law, contrary to Information Center’s contention.
    See Committee for a Better 
    Arvin, 786 F.3d at 1174
    (“Once
    approved by [the Agency, an Implementation Plan] becomes
    federal law, and cannot be changed unless and until [the
    Agency] approves any change. . . .”) (citation, alterations and
    internal quotation marks omitted). At this point, we are not
    even sure if Montana will adhere to its interpretation of the
    plan language at issue should the occasion arise to implement
    that language. As matters currently stand, Montana still has
    the option to change course and adopt the Agency’s
    interpretation that “a 2-year period which precedes the
    particular date” means “the 2 years immediately preceding
    the proposed change.” 57 Fed. Reg. at 32,323. As a result,
    we cannot say at this juncture that the Agency acted
    arbitrarily in approving the 1994 Revised Implementation
    Plan.
    At bottom, we conclude that the Agency’s interpretation
    of the regulation was a reasonable one. See 
    Auer, 519 U.S. at 461
    . The EPA interpreted “a 2-year period which precedes
    the particular date” to mean “the 2 years immediately
    preceding” the particular date. 57 Fed. Reg. at 32,323. In
    Talen, Montana argued that this interpretation is
    irreconcilable with the text because the text employs the
    indefinite article “a,” not the definite article “the.” Although
    the Agency’s interpretation does incorporate a definite article,
    the fact that the language is ambiguous, as discussed, gave the
    16       MONTANA ENVTL. INFO CTR. V. THOMAS
    Agency leeway to pose a reasonable interpretation of the
    language. See Comite Para el Bienstar de 
    Earlimart, 786 F.3d at 696
    .
    Because the Agency’s interpretation of ambiguous text in
    the 1994 Revised Implementation Plan was a permissible one,
    and because the Agency’s interpretation controlled, its
    approval of the succeeding 2015 Implementation Plan was
    not arbitrary or capricious. See Committee for a Better 
    Arvin, 786 F.3d at 1174
    –75. The 2015 Implementation Plan was
    otherwise in conformance with the Agency’s PSD program
    under the Clean Air Act. See 40 C.F.R. 51.166(a)(7)(iv)
    (requiring Implementation Plan compliance with the
    Agency’s PSD program).
    V. Conclusion
    The Agency’s interpretation of “a 2-year period which
    precedes the particular date” was a permissible one. 57 Fed.
    Reg. at 32,323. DEQ’s contrary interpretation had no effect
    on the Agency’s approval process. Accordingly, the
    Agency’s approval of Montana’s 2015 Implementation Plan
    was neither arbitrary nor capricious, and Information Center’s
    comment regarding Montana’s interpretation of the language
    in question raised a question of implementation, better
    addressed at a different time. As the Agency mentioned in its
    response to Information Center’s comment, “there are
    multiple statutory tools that the [Agency] can use to rectify
    problems with state implementation of its [Implementation
    Plan]. For example, the [Clean Air Act] provides the
    [Agency] the authority to issue [an Implementation Plan] call,
    42 U.S.C. § 7410(k)(5); make a finding of failure to
    implement, 
    id. §§ 7410(m),
    7509(a)(4); and take measures to
    MONTANA ENVTL. INFO CTR. V. THOMAS              17
    address specific permits pursuant to the [Agency’s] case-by-
    case permitting oversight. See, e.g., 
    id. § 7661d(b).”
    PETITION FOR REVIEW DENIED.