Cathay Enterprises, Inc. v. Design Trend International Interiors Ltd. (In Re Cathay Enterprises, Inc.) , 566 F. App'x 590 ( 2014 )


Menu:
  •                             NOT FOR PUBLICATION
    UNITED STATES COURT OF APPEALS                            FILED
    FOR THE NINTH CIRCUIT                             MAR 31 2014
    MOLLY C. DWYER, CLERK
    U.S. COURT OF APPEALS
    In the Matter of: CATHAY                         No. 12-15650
    ENTERPRISES, INC.,
    D.C. No. 2:10-cv-01079-NVW
    Debtor,
    MEMORANDUM*
    CATHAY ENTERPRISES, INC., an
    Arizona corporation,
    Appellant,
    v.
    DESIGN TREND INTERNATIONAL
    INTERIORS LIMITED, an Arizona
    corporation,
    Appellee.
    Appeal from the United States District Court
    for the District of Arizona
    Neil V. Wake, District Judge, Presiding
    Argued and Submitted March 11, 2014
    San Francisco, California
    Before: WALLACE, McKEOWN, and GOULD, Circuit Judges.
    *
    This disposition is not appropriate for publication and is not precedent
    except as provided by Ninth Circuit Rule 36-3.
    Cathay Enterprises, Inc. (“Cathay”) appeals from the district court’s reversal
    of the bankruptcy court’s judgment. The district court found that Cathay had
    waived any material breach by Design Trend International Interiors, Ltd. (“Design
    Trend”) based on timeliness of performance on a construction contract for
    renovations to a hotel owned by Cathay. We have jurisdiction under 28 U.S.C. §§
    158(d), 1291, and we affirm the district court’s decision as to waiver and
    substantial performance in favor of Design Trend, but reverse and remand the
    issues of prejudgment interest calculation and attorneys’ fees.
    This case has an extensive history that we will not recount. We simply note
    that after Design Trend missed the final completion date of the construction
    contract, Cathay repeatedly insisted that it continue to perform, communicating
    through letters and two administrative enforcement actions enlisting the help and
    authority of the Arizona Registrar of Contractors. An ALJ found that Design
    Trend had substantially completed the project, but the bankruptcy court relieved
    Cathay of responsibility to pay the amount outstanding because Design Trend had
    materially breached the contract with its untimely performance. The district court
    reversed the bankruptcy court, but offset the amount owed to Design Trend with
    expenses incurred by Cathay.
    2
    The district court correctly addressed the issue of waiver because it was
    raised to the bankruptcy court, which implicitly rejected the waiver argument when
    it ruled against Design Trend. See Vance v. Am. Hawaii Cruises, Inc., 
    789 F.2d 790
    , 792–93 (9th Cir. 1986); Carr v. Yokohama Specie Bank, Ltd., 
    200 F.2d 251
    ,
    255 (9th Cir. 1952) (“It is sufficient if the special affirmative facts found by the
    court, construed as a whole, negat[e] each rejected contention.”).
    Under Arizona law, “once a material breach in a partially-performed
    construction contract has occurred, the non-defaulting party must elect to . . . waive
    the breach and continue performance, or terminate the contract and sue for
    damages; and if the innocent party elects to continue performance he thereby
    waives the breach and he may not recover damages therefor.” Hunter Contracting
    Co. v. Sanner Contracting Co., 
    492 P.2d 735
    , 740 (Ariz. Ct. App. 1972). We agree
    with the district court that Cathay’s repeated insistence that Design Trend continue
    to work after the contractual deadlines for performance had passed acted as a
    waiver of Cathay’s right to sue Design Trend for a material breach based on
    untimely performance. Further, Cathay offers insufficient evidence to show that
    the district court erred in concluding that Design Trend substantially performed the
    contract. See Cracchiolo v. Carlucci, 
    157 P.2d 352
    , 356 (Ariz. 1945); Homes &
    Son Constr. Co., Inc. v. Bolo Corp., 
    526 P.2d 1258
    , 1262–63 (Ariz. Ct. App.
    3
    1974). The district court correctly applied the remaining damages sustained by
    Cathay to offset some of the amount owed to Design Trend.
    However, the district court erred in using the equitable remedy of nunc pro
    tunc to backdate its order for the purpose of calculating prejudgment interest.
    Nunc pro tunc should be applied in limited circumstances when it is necessary to
    “mak[e] the record reflect what the district court actually intended to do at an
    earlier date, but which it did not sufficiently express or did not accomplish due to
    some error or inadvertence.” United States v. Sumner, 
    226 F.3d 1005
    , 1009–10
    (9th Cir. 2000). There is no indication here that the district court meant to include
    prejudgment interest in its original order dated March 28, 2011, and so we reverse
    its application of nunc pro tunc and remand for recalculation of prejudgment
    interest.
    While a trial court may award the prevailing party reasonable attorneys’ fees
    at its “broad discretion” under Arizona law, A.R.S. § 12-341.01; State Farm Mut.
    Auto. Ins. Co. v. Arrington, 
    963 P.2d 334
    , 340 (Ariz. Ct. App. 1998), at the very
    least there must be proof supporting what is “reasonable,” Crouch v. Pixler, 
    320 P.2d 943
    , 946 (Ariz. 1958). The district court did not give enough information to
    determine whether the attorneys’ fees award was reasonable. Further, there is no
    indication that the district court excluded fees that could be attributed to work
    4
    performed during the bankruptcy proceedings unrelated to the contract dispute.
    See Zeagler v. Buckley, 
    219 P.3d 247
    , 249 (Ariz. Ct. App. 2009). For these
    reasons, we reverse the award of attorneys’ fees to Design Trend and remand for
    further explanation and, if necessary, recalculation.
    AFFIRMED IN PART, REVERSED AND REMANDED IN PART.
    5