Great Basin Resource Watch v. Blm , 844 F.3d 1095 ( 2016 )


Menu:
  •                 FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    GREAT BASIN RESOURCE WATCH;               No. 14-16812
    WESTERN SHOSHONE DEFENSE
    PROJECT,                                    D.C. No.
    Plaintiffs-Appellants,      3:13-cv-00078-
    RCJ-VPC
    v.
    BUREAU OF LAND MANAGEMENT;                  OPINION
    U.S. DEPARTMENT OF THE INTERIOR;
    AMY LUEDERS, BLM State Director;
    CHRISTOPHER J. COOK, BLM Mt.
    Lewis Field Manager,
    Defendants-Appellees,
    EUREKA MOLY, LLC,
    Intervenor-Defendant-Appellee.
    Appeal from the United States District Court
    for the District of Nevada
    Robert Clive Jones, District Judge, Presiding
    Argued and Submitted October 18, 2016
    San Francisco, California
    Filed December 28, 2016
    2          GREAT BASIN RESOURCE WATCH V. BLM
    Before: Susan P. Graber and Mary H. Murguia, Circuit
    Judges, and Mark W. Bennett,* District Judge.
    Opinion by Judge Graber
    SUMMARY**
    Environmental Law
    The panel affirmed in part, reversed in part, and vacated
    in part the district court’s judgment, and remanded for further
    proceedings in an action brought by plaintiffs challenging the
    Bureau of Land Management’s approval of the Mt. Hope
    Project, a proposed molybdenum mining operation near
    Eureka, Nevada.
    Addressing plaintiffs’ challenge to several aspects of the
    BLM’s analysis of the Project under the National
    Environmental Policy Act, the panel held that the BLM’s
    selection of baseline levels of certain air pollutants was
    unreasonable, that the BLM’s analysis of cumulative air
    impacts was deficient, that the BLM took the required “hard
    look” at the potential impacts of poor pit-lake water quality
    on ground water, and that the BLM’s discussion of long-term
    mitigation and reclamation in the Final Environmental Impact
    Statement was “reasonably complete.”
    *
    The Honorable Mark W. Bennett, United States District Judge for
    the Northern District of Iowa, sitting by designation.
    **
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    GREAT BASIN RESOURCE WATCH V. BLM                     3
    The panel declined to address plaintiffs’ claim that the
    BLM violated its duty to protect lands “withdrawn from
    settlement, location, sale or entry” under Executive Order
    Public Water Reserve No. 107 (Apr. 17, 1926). First, the
    panel held that the BLM should be given an opportunity to fix
    the errors in its analysis of the Project under NEPA before
    challenges to the approval of the Project itself are entertained.
    Second, the panel held that the proper analysis of the claim
    turned in large part on whether four springs in the area of the
    Project were “covered” by the Executive Order, but the
    BLM’s position on that question was unclear. The panel
    remanded for clarification.
    COUNSEL
    Roger Flynn (argued) and Jeffrey C. Parsons, Western
    Mining Action Project, Lyons, Colorado; Julie Cavanaugh-
    Bill, Cavanaugh-Bill Law Offices LLC, Elko, Nevada; for
    Plaintiffs-Appellants.
    Robert J. Lundman (argued) and Mark R. Haag; John C.
    Cruden, Assistant Attorney General; Environment & Natural
    Resources Division, United States Department of Justice,
    Washington, D.C.; Luke Miller, Office of the Solicitor,
    United States Department of the Interior, Washington, D.C.;
    for Defendants-Appellees.
    Francis M. Wilkstrom (argued), Salt Lake City, Utah, for
    Intervenor-Defendant-Appellee.
    4        GREAT BASIN RESOURCE WATCH V. BLM
    OPINION
    GRABER, Circuit Judge:
    Plaintiffs Great Basin Resource Watch and the Western
    Shoshone Defense Project challenge Defendant Bureau of
    Land Management’s (“BLM”) approval of the Mt. Hope
    Project (“Project”), a proposed molybdenum mining
    operation near Eureka, Nevada. Plaintiffs argue that the
    BLM’s review of the Project under the National
    Environmental Policy Act of 1969 (“NEPA”) was inadequate
    and that the approval of the Project violated the Federal Land
    Policy and Management Act of 1976 (“FLPMA”) and the
    laws governing lands withdrawn under the executive order
    known as Public Water Reserve No. 107 (“PWR 107”).
    Because we conclude that the BLM’s environmental review
    of the Project violated NEPA in several ways, we affirm in
    part the district court’s judgment, reverse in part, vacate in
    part, and remand for further proceedings.
    BACKGROUND
    A. The Mt. Hope Project
    The Mt. Hope Project “will be located in Eureka County,
    Nevada approximately 23 miles northwest of the town of
    Eureka . . . and will consist of a proposed molybdenum mine
    including a power transmission line, a water well field, and
    all associated facilities to be located on public land
    administered by the BLM . . . and on private land controlled
    by [Eureka Moly, LLC, the Project’s operator]. The Project
    will utilize an open pit mining method and will process the
    mined ore using a flotation and roasting process. A total of
    8,355 acres of disturbance is proposed within the 22,886-acre
    GREAT BASIN RESOURCE WATCH V. BLM                   5
    Project Area.” Bureau of Land Mgmt., U.S. Dep’t of Interior,
    Mount Hope Project Record of Decision, Plan of Operations
    Approval, and Approval of Issuance of Right-of-Way Grants,
    p. i (Nov. 2012). Of those 22,886 acres, 22,608 are public
    lands administered by the BLM. Id. at 6. “The 80-year
    project will have an 18- to 24-month construction phase, 44
    years of mining and ore processing, 30 years of reclamation,
    and five years of post-closure monitoring. . . . Additionally,
    long-term post-reclamation obligations will follow final
    reclamation.” Id. at 1.
    The active mining phase of the Project will last 32 years,
    during which time the mine will produce approximately 1.7
    billion tons of waste rock. During that phase, pumps will be
    used to extract water from the open mining pit; at the end of
    the active mining phase, the pit will be allowed to fill slowly
    with ground water, forming a mine-pit lake that is expected
    to reach a depth of 900 feet. Pumping of ground water will
    also take place in the Kobeh Valley, which is adjacent to Mt.
    Hope, to provide fresh water for various mining and ore
    extraction purposes.
    B. Environmental Review of the Project
    Eureka Moly filed its first plan of operations for the
    Project with the BLM in June 2006. The BLM determined
    that approval of the Project was a “major Federal action”
    under NEPA, 
    42 U.S.C. § 4332
    , and thus required the
    preparation of an environmental impact statement (“EIS”).
    The BLM released a draft EIS (“DEIS”) in December 2011.
    After receiving nearly 2,000 comments on the DEIS, the
    BLM prepared a final EIS (“FEIS”), which was released in
    October 2012.
    6        GREAT BASIN RESOURCE WATCH V. BLM
    Throughout the NEPA review process, Plaintiffs raised
    concerns about several aspects of the Project. Many of those
    concerns related to the adequacy of the BLM’s analysis of
    environmental impacts in the DEIS and FEIS. In comments
    on the DEIS, Plaintiffs criticized the BLM’s analysis of the
    Project’s cumulative impacts, impacts to water quantity and
    quality, and impacts to cultural, religious, and historical
    resources. Plaintiffs renewed those criticisms in their
    comments on the FEIS, and they offered fresh criticisms
    concerning, among other things, the FEIS’ discussion of
    funding for long-term mitigation and reclamation.
    In addition to criticizing the BLM’s analysis of
    environmental impacts under NEPA, Plaintiffs expressed
    their view to the BLM that approval of the Project would
    violate the agency’s duties under the FLPMA and PWR 107.
    In comments on both the DEIS and FEIS, Plaintiffs opined
    that approval of the Project would violate FLPMA’s
    requirement that the BLM “prevent unnecessary or undue
    degradation of the lands” that it administers, 
    43 U.S.C. § 1732
    (b). Plaintiffs also pointed out that the Project would
    affect some springs and water holes located on lands that they
    claimed had been withdrawn by PWR 107.
    Plaintiffs were not alone in criticizing the BLM’s analysis
    of the Project’s environmental effects. The Environmental
    Protection Agency (“EPA”) reviewed the FEIS and found that
    the BLM’s analyses of air impacts, water quantity impacts,
    and the funding aspects of long-term mitigation were lacking.
    Eureka County also criticized several aspects of the BLM’s
    NEPA review, including the agency’s analysis of air impacts.
    GREAT BASIN RESOURCE WATCH V. BLM                   7
    C. Approval of the Project
    In November 2012, a little more than a month after
    releasing the FEIS, the BLM issued a record of decision
    approving the Project. Plaintiffs petitioned for review of that
    decision with the BLM’s State Director for Nevada, who
    rejected the petition in January 2013. Plaintiffs then brought
    this action in the district court under the Administrative
    Procedure Act, alleging that the BLM’s review of the Project
    under NEPA was deficient and that its approval of the Project
    violated FLPMA and PWR 107. Soon after Plaintiffs filed
    suit, the district court granted Eureka Moly leave to intervene
    on the side of the BLM.
    The district court denied Plaintiffs’ motion for summary
    judgment and granted the parties’ joint motion for entry of
    judgment in favor of the BLM. Plaintiffs timely appeal from
    that judgment.
    DISCUSSION
    A. NEPA Claim
    “A district court’s determination on summary judgment
    that the BLM complied with NEPA is reviewed de novo.”
    Klamath-Siskiyou Wildlands Ctr. v. BLM, 
    387 F.3d 989
    , 992
    (9th Cir. 2004) (internal quotation marks omitted). “The
    agency’s actions, findings, and conclusions will be set aside
    if they are arbitrary, capricious, an abuse of discretion, or
    otherwise not in accordance with law.” 
    Id.
     (internal quotation
    marks omitted).
    NEPA “is a procedural statute that requires . . . Federal
    agencies to assess the environmental consequences of their
    8        GREAT BASIN RESOURCE WATCH V. BLM
    actions before those actions are undertaken.” 
    Id. at 993
    . “For
    major federal actions significantly affecting the quality of the
    human environment, the agency is required to prepare an
    [EIS]. An EIS is a thorough analysis of the potential
    environmental impacts that provides full and fair discussion
    of significant environmental impacts and informs
    decisionmakers and the public of the reasonable alternatives
    which would avoid or minimize adverse impacts or enhance
    the quality of the human environment.” 
    Id.
     (citations,
    internal quotation marks, and alterations omitted).
    “[I]n reviewing the adequacy of an EIS, this circuit
    employs a ‘rule of reason’ that asks whether an EIS contains
    a reasonably thorough discussion of the significant aspects of
    the probable environmental consequences. Under this
    standard, once satisfied that a proposing agency has taken a
    ‘hard look’ at a decision’s environmental consequences, the
    review is at an end.” Or. Nat. Res. Council v. Lowe, 
    109 F.3d 521
    , 526 (9th Cir. 1997) (per curiam) (citations, internal
    quotation marks, and alterations omitted).
    Plaintiffs challenge several aspects of the NEPA analysis.
    They assert that the BLM’s selection of baseline levels of
    certain air pollutants was unreasonable and that the BLM’s
    analysis of cumulative impacts was deficient. As we will
    explain below, we agree. Plaintiffs also challenge the
    adequacy of the BLM’s consideration of various mitigation
    measures. With respect to those arguments, we either are not
    persuaded or need not reach the issues.
    1. Air Pollution Baselines
    Plaintiffs first argue that the BLM did not assess
    adequately the baseline levels of certain air pollutants when
    GREAT BASIN RESOURCE WATCH V. BLM                   9
    conducting the air impacts analysis. Establishing appropriate
    baseline conditions is critical to any NEPA analysis.
    “Without establishing the baseline conditions which exist . . .
    before [a project] begins, there is simply no way to determine
    what effect the [project] will have on the environment and,
    consequently, no way to comply with NEPA.” Half Moon
    Bay Fishermans’ Mktg. Ass’n v. Carlucci, 
    857 F.2d 505
    , 510
    (9th Cir. 1988). An agency need not conduct measurements
    of actual baseline conditions in every situation—it may
    estimate baseline conditions using data from a similar area,
    computer modeling, or some other reasonable method. See
    Or. Nat. Desert Ass’n v. Jewell, 
    840 F.3d 562
    , 570 (9th Cir.
    2016) (holding that it would not necessarily be impermissible
    for the BLM to estimate baseline conditions in one area by
    extrapolating from another area). But whatever method the
    agency uses, its assessment of baseline conditions “must be
    based on accurate information and defensible reasoning.” 
    Id.
    When determining baseline air pollution levels for the
    Project, the BLM did not use actual measurements from the
    Project site because none were available. In the DEIS, the
    BLM used baseline values taken from measurements in Clark
    County, Nevada—the county in which Las Vegas is
    located—for some pollutants, and used the “default values”
    for unmonitored rural areas suggested by the Nevada
    Department of Environmental Protection’s (“NDEP”) Bureau
    of Air Pollution Control for some other pollutants. The DEIS
    noted that the baseline numbers drawn from the Clark County
    measurements were “conservatively high” given the relatively
    urban character of the monitoring locations.
    10         GREAT BASIN RESOURCE WATCH V. BLM
    In preparing the FEIS, the BLM instructed Eureka Moly1
    “to follow NDEP’s guidance in selecting the background
    concentrations for the air quality analysis.” A permitting
    supervisor from the NDEP’s Bureau of Air Pollution Control
    had previously advised (by means of a short email) that the
    agency “assumed” a baseline of zero for all pollutants other
    than 10-micron particulate matter, and the FEIS adopts most
    of those baseline values in place of the “conservatively high”
    baseline values used in the DEIS. Specifically, the FEIS uses
    baseline values of zero for carbon monoxide, nitrogen
    dioxide, one- and three-hour time-averaged sulfur dioxide,
    and lead, while the DEIS had used measured values from
    Clark County for those pollutants. The FEIS continues to use
    the same Clark County data for the two longest time-averaged
    sulfur dioxide baselines, and it uses measurements taken at
    Great Basin National Park2 for 2.5-micron particulate matter
    baselines.
    Plaintiffs first argue that it was unreasonable for the BLM
    to use data from Great Basin National Park, a pristine area
    more than 100 miles away from the Project, to establish
    baselines for 2.5-micron particulate matter. Although it is
    true that this choice may have caused the agency to
    underestimate the baselines for 2.5-micron particulate matter,
    the BLM explained its choice adequately, and its explanation
    is reasonable. The Project is located in a rural area, and the
    BLM used data from a different rural area to estimate
    1
    Eureka Moly contracted with an air quality consulting firm, Air
    Sciences, Inc., to conduct the air impacts analysis. That analysis, in turn,
    was submitted to the BLM, which relied on it when preparing the FEIS.
    2
    The FEIS cites a different NDEP official as the source of the
    baseline values for 2.5-micron particulate matter concentrations.
    GREAT BASIN RESOURCE WATCH V. BLM                   11
    baseline conditions. Plaintiffs have not shown that this
    choice rested on inaccurate information or indefensible
    reasoning. Or. Nat. Desert Ass’n, 840 F.3d at 570.
    Plaintiffs’ arguments concerning the baseline choices for
    10-micron particulate matter and the two longest time-
    averaged sulfur dioxide concentrations are similarly
    unconvincing. Like the baselines for 2.5-micron particulate
    matter, the baselines for 10-micron particulate matter relied
    on measurements taken at Great Basin National Park. The
    baselines for the two sulfur dioxide concentrations were
    “conservatively high,” as the BLM noted in the DEIS. By
    acknowledging the shortcomings in its data while using those
    data to make an estimate of baseline conditions, the BLM
    complied with NEPA. See Lands Council v. Powell, 
    395 F.3d 1019
    , 1032 (9th Cir. 2005) (noting that “NEPA . . . requires
    up-front disclosures of relevant shortcomings in the data or
    models”).
    Finally, Plaintiffs argue that the BLM’s use of a zero
    baseline value for the remaining pollutants was unreasonable.
    The BLM and Eureka Moly respond that the choice of a zero
    baseline for those pollutants was reasonable because it was
    “based on recommendations from the [NDEP’s Bureau of Air
    Pollution Control], the agency with Nevada-specific
    expertise.” The FEIS similarly invokes the expertise of the
    NDEP’s Bureau of Air Pollution Control (“BAPC”),
    prefacing the table of baseline values with the note that “[t]he
    BAPC was contacted to obtain representative background
    concentrations for the modeling analysis.” And the air
    impacts analysis prepared for Eureka Moly and submitted to
    the BLM—the study that underlies the FEIS’ air impacts
    analysis—also notes that the “NDEP-BAPC recommends
    assuming zero background for” the remaining pollutants.
    12         GREAT BASIN RESOURCE WATCH V. BLM
    It turns out, though, that the only “expert
    recommendation” in the record is a short email from an
    NDEP official—the email is, in fact, cited in the FEIS as the
    sole source of the zero baseline value. That email reads, in
    relevant part, as follows:
    In an un-monitored area, BAPC uses 10.2
    ìg/m^3 for a 24-hour average background and
    9.0 ìg/m^3 for an annual average background
    for PM10. All other pollutants are assumed
    to be 0. If there is on-going quality assured
    monitoring representative of an area, we can
    rely on that data to set a different background.
    I’m not aware of any monitoring being
    performed by BAPC in the area you propose.
    (Emphasis added.) Crucially, this email does not explain how
    or why the NDEP arrived at zero. Such a bare assertion of
    opinion3 coming from an expert within the BLM, without any
    supporting reasoning, would not pass muster in an EIS. See
    Idaho Sporting Cong. v. Thomas, 
    137 F.3d 1146
    , 1150 (9th
    Cir. 1998) (“NEPA requires that the public receive the
    underlying environmental data from which a [reviewing
    agency] expert derived her opinion.”), overruled on other
    grounds by Lands Council v. McNair, 
    537 F.3d 981
     (9th Cir.
    2008) (en banc); see also Tri-Valley Cares v. U.S. Dep’t of
    3
    What value to use as a baseline concentration for a particular air
    pollutant, in the absence of data, is a question of expert judgment, not one
    of fact. There is no doubt that the baseline pollutant levels are not, as a
    factual matter, zero; the question is what to use as an estimate of baseline
    levels for purposes of modeling. In fact, the email to the NDEP official
    asked for “some guidance on what background concentration values . . .
    to use for a modeling analysis in [the] Mount Hope area.” (Emphasis
    added.)
    GREAT BASIN RESOURCE WATCH V. BLM                   13
    Energy, 
    671 F.3d 1113
    , 1124 (9th Cir. 2012) (“At a
    minimum, an agency must support its conclusions with
    studies that the agency deems reliable.”). The fact that it
    comes from an expert at a state agency is of no significance
    to the analysis. Cf. Nat. Res. Def. Council, Inc. v. Herrington,
    
    768 F.2d 1355
    , 1412–14 (D.C. Cir. 1985) (“[I]n a rulemaking
    which must be supported by substantial evidence, [an agency]
    may not rely without further explanation on an unelaborated
    order from another agency. Neither we as a reviewing court
    nor participants in the rulemaking can possibly discover the
    substantive basis of [the second agency’s] edict.”).
    We might reach a different conclusion had the NDEP
    official explained why an estimate of zero was appropriate, or
    had the BLM independently scrutinized that estimate and
    decided that it was reasonable, and then explained why. But
    none of that happened—the BLM simply used baseline
    estimates of zero for some pollutants in reliance on one
    conclusory sentence in an email from an NDEP official, an
    email that itself contained no supporting reasoning. This
    important information, which affects the air impacts analysis,
    was essentially immune from meaningful scrutiny by the
    public because the BLM never provided any data or
    reasoning in support of it. A baseline estimate “must be
    based on accurate information and defensible reasoning.” Or.
    Nat. Desert Ass’n, 840 F.3d at 570. The BLM provided
    neither when it came to its baseline estimates of zero.
    Eureka Moly argues that the FEIS’ air impacts analysis is
    nonetheless adequate because it relies in part on the fact that
    the NDEP’s Bureau of Air Pollution Control issued a Clean
    Air Act permit for the Project. This argument evinces a
    misunderstanding of the nature of NEPA and its relationship
    to “substantive” environmental laws such as the Clean Air
    14       GREAT BASIN RESOURCE WATCH V. BLM
    Act. See S. Fork Band Council of W. Shoshone of Nev. v.
    U.S. Dep’t of Interior, 
    588 F.3d 718
    , 726 (9th Cir. 2009) (per
    curiam) (holding that a failure to discuss mercury emissions
    from a nearby mining facility in an EIS was not excused by
    the fact that the facility “operate[d] pursuant to a state permit
    under the Clean Air Act,” because “[a] non-NEPA document
    . . . cannot satisfy a federal agency’s obligations under
    NEPA”). The failure to explain the zero baseline assumption
    frustrated the BLM’s ability to take a “hard look” at air
    impacts, and the reference to the Project’s Clean Air Act
    permit did nothing to fix that error.
    The BLM argues that it corrected any error in its baseline
    estimates by conducting a “double check” analysis following
    the issuance of the FEIS. The BLM conducted this analysis
    using measured baseline values from an undeveloped area in
    New Mexico that EPA had suggested might have similar air
    quality to the Project area. The BLM claims that those
    measurements confirm that the pollution from the Project
    would not violate air quality standards. Although that
    statement may end up being true, a post-EIS
    analysis—conducted without any input from the public—
    cannot cure deficiencies in an EIS. Ctr. for Biological
    Diversity v. U.S. Forest Serv., 
    349 F.3d 1157
    , 1169 (9th Cir.
    2003). The public never had an opportunity to comment on
    the “double check” analysis, frustrating NEPA’s goal of
    allowing the public the opportunity to “play a role in . . . the
    decisionmaking process.” Robertson v. Methow Valley
    Citizens Council, 
    490 U.S. 332
    , 349 (1989).
    In conclusion, we hold that the BLM’s analysis of air
    impacts in the FEIS was inadequate because the agency did
    not provide any support for its use of baseline values of zero
    for several air pollutants.
    GREAT BASIN RESOURCE WATCH V. BLM                   15
    2. Cumulative Impacts
    Plaintiffs next argue that the BLM’s analysis of
    cumulative impacts was deficient. Plaintiffs point out that,
    although the FEIS mentions that there will be cumulative
    impacts stemming from the Project and nearby mining,
    agricultural, and other activities, “there is no detailed
    discussion about the . . . impacts,” nor is there a “quantified
    assessment” of those impacts.
    The cumulative impact from an action means “the impact
    on the environment which results from the incremental
    impact of the action when added to other past, present, and
    reasonably foreseeable future actions . . . . Cumulative
    impacts can result from individually minor but collectively
    significant actions taking place over a period of time.”
    
    40 C.F.R. § 1508.7
    . Accordingly, “[i]n a cumulative impact
    analysis, an agency must take a ‘hard look’ at all actions” that
    may combine with the action under consideration to affect the
    environment. Te-Moak Tribe of W. Shoshone of Nev. v. U.S.
    Dep’t of Interior, 
    608 F.3d 592
    , 603 (9th Cir. 2010)
    (emphasis added). Furthermore, simply listing all relevant
    actions is not sufficient. Rather, “some quantified or detailed
    information is required. Without such information, neither
    the courts nor the public . . . can be assured that the [agency]
    provided the hard look that it is required to provide.”
    Neighbors of Cuddy Mountain v. U.S. Forest Serv., 
    137 F.3d 1372
    , 1379 (9th Cir. 1998).
    The BLM completed the first step of the cumulative
    impacts analysis by identifying the relevant “past, present,
    and reasonably foreseeable future actions,” 
    40 C.F.R. § 1508.7
    , that might affect the environment in the area of the
    Project. And the BLM provided a “useful analysis of the
    16       GREAT BASIN RESOURCE WATCH V. BLM
    cumulative impacts” of those actions on some environmental
    resources. Klamath-Siskiyou Wildlands Ctr., 
    387 F.3d at 994
    (internal quotation marks citation omitted). For instance, the
    FEIS includes a relatively thorough discussion of cumulative
    impacts to water quantity, complete with a quantitative
    analysis.
    However, the discussion of cumulative impacts to other
    resources in the FEIS falls short. In particular, the discussion
    of cumulative air impacts is insufficient. That discussion
    reads, in relevant part, as follows:
    Each of the identified individual projects
    within the [study area], including existing and
    proposed mining operations, emit air
    pollutants. With the possible exception of
    motor vehicle emissions, the existing and
    proposed mining operations are the major
    sources of criteria pollutants within the [study
    area]. The modeling for the Proposed Action,
    as well as the Ruby Hill Mine . . . , shows that
    the levels of these pollutants are below the
    applicable standards. The Proposed Action
    would not result in a significant cumulative
    impact to air resources. The [reasonably
    foreseeable future actions] would result in
    additional emissions similar to those currently
    emitted by the existing operations within the
    [study area]. In addition, the major sources of
    pollutants (except for motor vehicle
    emissions) within the [study area] would
    operate under permit conditions established
    by the [NDEP BAPC] and therefore would not
    be significant.
    GREAT BASIN RESOURCE WATCH V. BLM                             17
    That analysis suffers from many of the same
    shortcomings as the BLM’s analysis in Great Basin Mine
    Watch v. Hankins, 
    456 F.3d 955
     (9th Cir. 2006). There, we
    faulted the BLM for failing to include “mine-specific or
    cumulative data” in its analysis of cumulative impacts to air
    resources. 
    Id. at 973
    . The BLM had “merely stat[ed] that
    ambient air quality data for the region currently reflects
    impacts of existing mining operations in the airshed,” but did
    not “identify and discuss the impacts that will be caused by
    each successive project, including how the combination of
    those various impacts is expected to affect the environment.”
    
    Id.
     at 973–74 (internal quotation marks and alterations
    omitted). For that reason, we held that the FEIS was
    insufficient. 
    Id.
     at 972–73. Similarly, the BLM in this case
    did not provide sufficiently detailed information in its
    cumulative air impacts analysis. The BLM made no attempt
    to quantify the cumulative air impacts of the Project together
    with the Ruby Hill Mine and vehicle emissions. Nor did the
    BLM attempt to quantify or discuss in any detail the effects
    of other activities, such as oil and gas development, that are
    identified elsewhere in the FEIS as potentially affecting air
    resources.
    The cumulative air impacts analysis also suffers from the
    same problem that plagued the air impacts analysis—namely,
    the choice of a baseline value of zero for certain pollutants.
    It was impossible for the BLM to take a “hard look” at
    cumulative air impacts given its unjustified use of a zero
    baseline for those pollutants.4
    4
    Counsel for the BLM conceded during oral argument that if we were
    to conclude that the assumption of a zero baseline for several air pollutants
    rendered the air impacts analysis deficient, we would necessarily have to
    18        GREAT BASIN RESOURCE WATCH V. BLM
    The BLM and Eureka Moly argue that the air impacts
    analysis contained elsewhere in the FEIS suffices because
    that other analysis takes into account existing emissions. But,
    as already discussed, the modeling assumed baseline values
    of zero for many pollutants and, therefore, the analysis
    plainly does not take into account emissions from other
    sources in the area. The BLM and Eureka Moly also argue
    that the reference in the FEIS to the cumulative air impacts
    analysis conducted in connection with the Ruby Hill
    Mine—an unrelated mining project—renders the cumulative
    air impacts analysis in this FEIS adequate. But the analysis
    of the Ruby Hill Mine did not consider the Mt. Hope Project,
    so its cumulative impacts analysis is of very limited
    relevance.
    The cumulative air impacts portion of the FEIS fails to
    “enumerate the environmental effects of [other] projects” or
    “consider the interaction of multiple activities.” Or. Nat. Res.
    Council Fund v. Brong, 
    492 F.3d 1120
    , 1133 (9th Cir. 2007).
    Accordingly, we hold that the cumulative impacts portion of
    the FEIS does not comply with NEPA.
    3. Mitigation: Mine-Pit Lake
    Plaintiffs’ next argument concerns the FEIS’ discussion
    of the lake that will eventually form in the mining pit.
    Plaintiffs argue that the BLM violated NEPA by failing to
    consider mitigation measures aimed at reducing the possible
    adverse environmental effects of poor pit-lake water quality.
    Under NEPA, “an agency must . . . consider appropriate
    mitigation measures that would reduce the environmental
    conclude that the cumulative air impacts analysis suffered from the same
    deficiency.
    GREAT BASIN RESOURCE WATCH V. BLM                   19
    impact of the proposed action.” Protect Our Cmtys. Found.
    v. Jewell, 
    825 F.3d 571
    , 581 (9th Cir. 2016). When reviewing
    an agency’s discussion of mitigation measures, “[w]e need
    only be satisfied that the agency took the requisite ‘hard look’
    at the possible mitigating measures.” Okanogan Highlands
    All. v. Williams, 
    236 F.3d 468
    , 473 (9th Cir. 2000).
    The FEIS states that “[i]nitial pit lake water quality is
    predicted to be good” but that, “[a]s evaporation from the
    lake surface concentrates the dissolved minerals, some water
    quality constituent concentrations would be predicted to
    increase over time relative to baseline concentrations and to
    exceed the present Nevada water quality standards.” The
    FEIS further predicts that “[t]here would be a low potential
    for impacts to ground water quality due to the formation of a
    ground water sink in the open pit,” but that the impact is “not
    considered significant.” The FEIS states that “[a]ccess to the
    open pit by humans and livestock would be restricted” and
    that “[t]he lake is not intended to be a drinking water source
    for humans or livestock or to be used for recreational
    purposes.” Plaintiffs claim that the BLM failed to consider
    any mitigation measures to address the potential effects of
    poor pit-lake water quality. They argue that this omission is
    problematic for two reasons: (1) the FEIS states that there is
    a “low potential” for impacts to ground water quality, rather
    than “no potential” for impacts, and (2) the pit-lake water
    may at some point be needed by “future water users” in the
    area.
    We hold that the BLM complied with NEPA in discussing
    possible mitigation measures to address the effects that would
    flow from poor pit-lake water quality. Although the BLM did
    not include any discussion of possible mitigation measures in
    the portion of the FEIS discussing pit-lake water quality,
    20        GREAT BASIN RESOURCE WATCH V. BLM
    other portions of the FEIS contain discussions of such
    measures. The listing of “applicant committed practices”—
    measures that Eureka Moly has promised to take and that are
    “considered part of the operating procedures” of the
    Project—states that the company will “periodically review
    and update . . . pit lake studies to incorporate new information
    accumulated during operations. . . . These updates would . . .
    provide quantitative predictions of water quality during the
    operational and post-closure period.” Additionally, the
    agency responded to a comment on the DEIS5 by noting that
    it would rely on future monitoring “to further understand the
    ground water and surface water hydraulics and any potential
    impacts to waters of the State. Based on further monitoring
    and evaluation, additional mitigation measures . . . can be
    implemented at any time . . . .”
    This sort of “wait and see” approach to mitigation does
    not always suffice under NEPA. Putting off an analysis of
    possible mitigation measures until after a project has been
    approved, and after adverse environmental impacts have
    started to occur, runs counter to NEPA’s goal of ensuring
    informed agency decisionmaking. See Robertson, 
    490 U.S. at 353
     (“Without [a reasonably complete] discussion [of
    mitigation], neither the agency nor other interested groups
    and individuals can properly evaluate the severity of the
    adverse effects.”). But that approach was reasonable in the
    circumstances given the relatively low probability and
    temporal remoteness of adverse impacts to ground water.
    And though the BLM did not consider any mitigation
    measures for the potential impact of poor pit-lake water
    quality on “future water users,” it was not required to do so,
    5
    The comments on the DEIS and the BLM’s responses thereto are
    included as appendices to the FEIS.
    GREAT BASIN RESOURCE WATCH V. BLM                    21
    because the existence of any such users is speculative. See
    San Luis Obispo Mothers for Peace v. Nuclear Regulatory
    Comm’n, 
    449 F.3d 1016
    , 1030 (9th Cir. 2006) (“[A]n impact
    statement need not discuss remote and highly speculative
    consequences.”) (internal quotation marks omitted).
    To be sure, the BLM’s mitigation analysis in this case
    was not as thorough as that of the agency in Okanogan
    Highlands. In that case, the Forest Service prepared an EIS
    for a mining project that would produce a mine-pit lake much
    like the one here. Okanogan Highlands, 
    236 F.3d at 471
    .
    The agency concluded in the EIS that “seepage from the open
    pit is expected to have a low overall impact on ground water
    quality in the vicinity of the pit,” but it nonetheless discussed
    several mitigation measures, including monitoring. 
    Id.
     at
    474–75. We held that the agency had complied with NEPA
    by considering “extensively the potential effects and
    mitigation processes.” 
    Id. at 477
    .
    In this case, by contrast, the BLM discussed only
    monitoring. But the disparity in the scope and depth of the
    agencies’ discussions in the two cases reflects important
    differences between the projects being analyzed, rather than
    a difference in the adequacy of the agencies’ analyses. The
    mining project in Okanogan Highlands was set to last eight
    to ten years, 
    id. at 471
    , and the pit lake was expected to
    overflow and discharge water that would exceed pollution
    standards, 
    id. at 474
    . Here, by contrast, the pit lake will fill
    slowly, and will not begin to fill at all until after the end of
    open pit mining, some 32 years after the start of the Project.
    Furthermore, the water quality in the pit lake is expected to be
    good at first. Faced with an adverse impact that is predicted
    to be insignificant and that will not occur for decades, the
    22        GREAT BASIN RESOURCE WATCH V. BLM
    BLM in this case reasonably decided to rely on a monitoring
    scheme to develop future mitigation measures.
    In short, we are satisfied that the BLM complied with
    NEPA by taking a “hard look” at the potential impacts of
    poor pit-lake water quality on ground water.
    4. Mitigation: Reclamation Bonding
    Plaintiffs argue that the BLM’s NEPA review was
    deficient because the agency “never reviewed the
    consideration or establishment of [financial guarantees] under
    NEPA.” Plaintiffs argue that this failure rendered the
    discussion of mitigation in the FEIS inadequate and prevented
    the public from providing input into the reclamation bonding
    process. The BLM and Eureka Moly respond that (1) NEPA
    does not require that “third parties should be able to
    participate in the process of determining financial
    guarantees,” and (2) in any event, the FEIS contains an
    adequate discussion of financial guarantees.
    The BLM’s regulations require that an operator who files
    a plan of operations must, “[a]t a time specified by BLM, . . .
    submit an estimate of the cost to fully reclaim [its]
    operations.” 
    43 C.F.R. § 3809.401
    (d).6 Although the “time
    6
    Reclamation means taking measures . . . following disturbance of
    public lands caused by operations to meet applicable performance
    standards and achieve conditions required by BLM at the conclusion of
    operations. . . . Components of reclamation include, where applicable:
    (1) Isolation, control, or removal of acid-forming, toxic,
    or deleterious substances;
    GREAT BASIN RESOURCE WATCH V. BLM                          23
    specified by BLM” need not be the same as the time at which
    the plan of operations is filed, the estimate must be submitted
    and accepted before operations can begin, because “a
    financial guarantee that meets the requirements of this
    subpart [must be provided] before starting operations.” 
    Id.
    § 3809.500. The regulations instruct operators to “estimate
    the cost to reclaim your operations as if BLM were hiring a
    third-party contractor to perform reclamation of your
    operations after you have vacated the project area.” Id.
    § 3809.554(a).7 The financial guarantee provided by the
    operator must cover this estimated cost. Id. § 3809.552(a).
    In addition, the BLM may require “a trust fund or other
    (2) Regrading and reshaping to conform with adjacent
    landforms, facilitate revegetation, control drainage, and
    minimize erosion;
    (3) Rehabilitation of fisheries or wildlife habitat;
    (4) Placement of growth medium and establishment of
    self-sustaining revegetation;
    (5) Removal or stabilization of buildings, structures, or
    other support facilities;
    (6) Plugging of drill holes and closure of underground
    workings; and
    (7) Providing for post-mining monitoring, maintenance,
    or treatment.
    
    43 C.F.R. § 3809.5
    .
    7
    The requirements of 
    43 C.F.R. § 3809.552
     and 3809.554 apply to
    operators, like Eureka Moly, that plan to use an individual financial
    guarantee, rather than a “blanket” guarantee covering multiple operations,
    § 3809.560, or a pre-existing state-approved guarantee, § 3809.570.
    24       GREAT BASIN RESOURCE WATCH V. BLM
    funding mechanism . . . to ensure the continuation of long-
    term treatment to achieve water quality standards and for
    other long term, post-mining maintenance requirements. The
    funding must be adequate to provide for construction, long-
    term operation, maintenance, or replacement of any treatment
    facilities and infrastructure, for as long as the treatment and
    facilities are needed after mine closure. BLM may identify
    the need for a trust fund or other funding mechanism during
    plan review or later.” Id. § 3809.552(c).
    The BLM and Eureka Moly assert that the details of a
    long-term funding mechanism and the amount of a financial
    guarantee (also called a “reclamation bond”) need not be
    discussed in an EIS because they are “regulatory
    requirement[s] . . . driven by the NEPA-reviewed reclamation
    plan.” For support, they cite the BLM Surface Management
    Manual, which states that “[a]ny decision concerning the
    need, amount, acceptability, and/or forfeiture of a financial
    guarantee . . . do[es] not require an environmental review
    under NEPA and [is] not to be included in NEPA documents
    used to review a proposed operation.” BLM Surface
    Management Manual at 2–6 (2012). They also cite our
    decision in Center for Biological Diversity v. Salazar, 
    706 F.3d 1085
    , 1096 (9th Cir. 2013), for the proposition that
    setting an amount for a financial guarantee does not trigger
    NEPA requirements.
    Salazar does not support the position taken by the BLM
    and Eureka Moly. In Salazar, we held that the BLM’s
    approval of an update to an operator’s financial guarantee
    was not a “major Federal action” for NEPA purposes where
    the reclamation plan being funded by the guarantee had
    already been approved and was not itself being changed. 
    Id.
    at 1095–96. We characterized the BLM’s action as consisting
    GREAT BASIN RESOURCE WATCH V. BLM                  25
    of “the ministerial tasks of feeding reclamation data from the
    [reclamation] plan into [a] software program, comparing [the]
    estimate [from that program] with that of [the operator], and
    then accepting [the operator’s] proposed bond amount, which
    was greater than” the estimate. 
    Id. at 1096
    . We held that
    “[s]uch post-project-approval functions are the type of
    monitoring and compliance activities that . . . do not trigger
    NEPA’s requirements.” 
    Id.
    For two reasons, this case differs from Salazar. First, the
    reclamation plan here is in the process of being approved, and
    determining the contours of the financial guarantee
    (particularly the long-term funding mechanism) at this stage
    is not a mere “ministerial task.” Second, Plaintiffs’ legal
    theory for why NEPA requires a discussion of reclamation
    funding differs from that advanced by the plaintiffs in
    Salazar. In Salazar, the plaintiffs argued that the update to
    the reclamation bond was a “major Federal action” requiring
    the preparation of an EIS. 
    Id. at 1095
    . By contrast,
    Plaintiffs’ argument is that the approval of a plan of
    operations requires an EIS; the EIS should discuss possible
    reclamation and post-closure mitigation measures; and a
    reasonably complete discussion of those measures requires
    some discussion of the long-term funding mechanism and
    reclamation bond.
    We need not address any further the broad argument that
    reclamation bonding need never be discussed in NEPA
    documents. We assume, without deciding, that long-term
    mitigation and reclamation funding issues must be “discussed
    in sufficient detail to ensure that environmental consequences
    have been fairly evaluated.” Robertson, 
    490 U.S. at 352
    .
    Making that assumption, we hold that the FEIS contains an
    adequate discussion of those issues.
    26       GREAT BASIN RESOURCE WATCH V. BLM
    The FEIS discusses several specific long-term mitigation
    measures that the long-term funding mechanism may fund.
    It also states that the funding mechanism “would be reviewed
    annually during the operation phase of the Project and
    potentially increased to meet the monitoring and mitigation
    needs associated with the Project.” Elsewhere, the FEIS
    discusses some of the long-term mitigation measures in more
    detail. For instance, the FEIS considers, in several places, the
    use of evapotranspiration cells to control long-term discharge
    from mining waste.
    The FEIS also contains a relatively thorough discussion
    of possible reclamation measures, complete with a proposed
    timeline. As for the reclamation bond, the FEIS states that,
    “[w]ithin three years following Plan approval and at least
    every three subsequent years, [Eureka Moly] would update
    the guarantee to reflect the actual disturbance and whatever
    additional disturbance is planned for the Project phase
    anticipated over the next three-year period. Changes to
    equipment, consumables, and man power costs would also be
    incorporated during the updates.”
    The BLM’s discussion of long-term mitigation and
    reclamation in the FEIS is “reasonably complete” and does
    not violate NEPA. Although the BLM could have discussed
    its options vis-à-vis the long-term funding mechanism and
    reclamation bond in more detail, its discussion of those
    aspects of the long-term mitigation and reclamation plans is
    not so deficient as to preclude the agency or the public from
    “properly evaluat[ing] the severity of [the Project’s] adverse
    effects” on the environment. Robertson, 
    490 U.S. at 352
    .
    And the reclamation and long-term mitigation discussion,
    taken as a whole, contains an adequate evaluation of the
    effectiveness of possible reclamation and long-term
    GREAT BASIN RESOURCE WATCH V. BLM                 27
    mitigation measures despite the relatively sparse treatment of
    the funding aspects of those measures. See S. Fork Band
    Council, 
    588 F.3d at 727
     (“An essential component of a
    reasonably complete mitigation discussion is an assessment
    of whether the proposed mitigation measures can be
    effective.”).
    5. Mitigation: Surface and Ground Water Quantity
    Plaintiffs next challenge the adequacy of the BLM’s
    discussion of mitigation measures to address impacts to
    surface and ground water quantity. The Project will require
    a great deal of water to support mining and milling
    operations. This water will come from two sources: ground
    water pumped out of wells located in one of the valleys
    surrounding Mt. Hope and water pumped from the open
    mining pit. The predicted effects of the pumping on certain
    stream and spring flows—unlike the predicted effect of the
    pit lake on ground-water quality—are “potentially
    significant.”
    The FEIS discusses several mitigation measures aimed at
    addressing those impacts, including a monitoring scheme to
    keep track of the status of spring and stream segments, water
    hauling, and piping in water from other locations to replace
    lost surface water. In non-technical—but accurate—terms,
    many of the mitigation measures amount to measuring how
    much each spring or stream segment’s flow has been reduced
    and replacing that water. The replacement water—which the
    BLM estimates at about 302 acre-feet of water, or nearly 100
    million gallons, per year—“would at least initially come from
    [Eureka Moly]’s existing water rights if additional water
    rights have not yet been secured.”
    28         GREAT BASIN RESOURCE WATCH V. BLM
    Plaintiffs contend that the discussion of mitigation
    measures is inadequate because “there is no analysis of where
    th[e] [replacement] water will come from, or the impacts
    from its withdrawal.”8 Plaintiffs note that EPA criticized the
    BLM for this omission during the NEPA process and asked
    the BLM to prepare a supplemental EIS. Eureka Moly
    responds that “the FEIS thoroughly analyzed the effect of
    using water from [its] production wells, [so] the effect of
    using some of it as substitute water was necessarily analyzed
    because it is the same water.”
    Although Eureka Moly’s argument is factually
    incorrect—the analysis of ground water pumping in the FEIS
    does not take into account the roughly 200 gallons per minute
    needed to replace depleted spring and stream water—that
    error appears to be quite small, raising questions about
    whether it might be harmless.9 See Idaho Wool Growers
    Ass’n v. Vilsack, 
    816 F.3d 1095
    , 1104 (9th Cir. 2016) (“The
    harmless-error analysis asks whether the [agency’s error]
    materially impeded NEPA’s goals—that is, whether the error
    caused the agency not to be fully aware of the environmental
    consequences of the proposed action, thereby precluding
    informed decisionmaking and public participation, or
    otherwise materially affected the substance of the agency’s
    8
    Plaintiffs also appear to argue that the discussion of mitigation
    measures is deficient because it puts off the development of a mitigation
    plan until after monitoring reveals depletion. This argument is factually
    incorrect—the FEIS includes a map showing the future location of
    pipelines that could be used to bring water to depleted springs.
    9
    The analysis in the FEIS assumes a ground water pumping rate of
    between 6,540 and 7,000 gallons per minute, so failing to include the
    additional 200 gallons per minute needed to replace spring and stream
    flows amounts to a roughly 3% error.
    GREAT BASIN RESOURCE WATCH V. BLM                       29
    decision.”). But no party has briefed the issue of
    harmlessness. And because the BLM’s NEPA analysis is
    deficient in other respects, the ultimate disposition of this
    appeal does not depend on the resolution of this portion of
    Plaintiffs’ NEPA claim. Accordingly, we decline to reach
    this portion of Plaintiffs’ NEPA claim.
    B. PWR 107 Claim
    Plaintiffs’ other major claim is that the BLM violated its
    duty to protect lands “withdrawn from settlement, location,
    sale or entry” under the executive order known as PWR 107,
    Public Water Reserve No. 107 (Apr. 17, 1926). Plaintiffs
    also argue that PWR 107, which withdrew lands surrounding
    certain springs and water holes, created an implied
    reservation of water rights to the federal government in some
    springs in the area of the Project, and that the Project will
    unlawfully interfere with those water rights.
    We decline to address Plaintiffs’ PWR 107 claim, for two
    reasons. First, the BLM should be given an opportunity to fix
    the errors in its analysis of the Project under NEPA before
    challenges to the approval of the Project itself are entertained.
    “Having addressed the problems [with the EIS], the BLM
    may decide to make different choices. NEPA is not a paper
    exercise, and new analyses may point in new directions. . . .
    The problems [with the approval of the Project itself] may
    never arise once the BLM has had a chance to see the choices
    before it with fresh eyes.” Or. Nat. Desert Ass’n v. BLM,
    
    625 F.3d 1092
    , 1124 (9th Cir. 2010).10
    10
    For this reason, we also decline to address Great Basin’s FLPMA
    claim.
    30         GREAT BASIN RESOURCE WATCH V. BLM
    Second, the proper analysis of the PWR 107 claim turns
    in large part on whether four springs11 in the area of the
    Project are “covered” by PWR 107—that is, whether those
    four springs are located on lands that were withdrawn by
    PWR 107—but the BLM’s position on that question is
    unclear.12 Prudence counsels in favor of remanding to the
    agency to clarify its position, rather than addressing legal
    questions that may end up being irrelevant to the disposition
    of the claim. Cf. Su Hwa She v. Holder, 
    629 F.3d 958
    ,
    963–64 (9th Cir. 2010) (“[W]e lack the clairvoyance
    necessary to confidently infer the reasoning behind the
    [agency]’s conclusion. Rather than countenance a decision
    that leaves us to speculate based on an incomplete analysis,
    we remand the case to the [agency] for clarification.”
    (footnote omitted)).
    11
    The springs at issue are McBride’s Spring, also referred to as SP-1
    or Spring 612; Mt. Hope Spring, also referred to as SP-4 or Spring 619;
    Garden Spring, also referred to as SP-2 or Spring 597; and Lone Mountain
    Spring, also referred to as Spring 742.
    12
    The FEIS is internally contradictory, suggesting in some places that
    the four springs are covered by PWR 107 and in other places that they are
    not. We note that the BLM had previously submitted “Notification of
    Public Water Reserve” forms for the four springs to the State of Nevada.
    Each of those forms lists an amount of water that the United States wishes
    to claim as a federal reserved water right and cites PWR 107 as authority
    for the reservation. The notifications have never been rescinded. If, on
    remand, the BLM decides that the springs are not important, it should at
    the very least explain why it has apparently changed its position. Cf.
    Encino Motorcars, LLC v. Navarro, 
    136 S. Ct. 2117
    , 2126 (2016) (“[A]n
    ‘unexplained inconsistency’ in agency policy is ‘a reason for holding an
    interpretation to be an arbitrary and capricious change from agency
    practice.’” (brackets omitted) (quoting Nat’l Cable & Telecomms. Ass’n
    v. Brand X Internet Servs., 
    545 U.S. 967
    , 981 (2005))).
    GREAT BASIN RESOURCE WATCH V. BLM               31
    AFFIRMED in part, REVERSED in part, VACATED
    in part, and REMANDED with instructions to vacate the
    record of decision and remand to the BLM. The parties shall
    bear their own costs on appeal.
    

Document Info

Docket Number: 14-16812

Citation Numbers: 844 F.3d 1095

Filed Date: 12/28/2016

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (18)

klamath-siskiyou-wildlands-center-an-oregon-non-profit-organization-v , 387 F.3d 989 ( 2004 )

great-basin-mine-watch-and-mineral-policy-center-v-helen-hankins-united , 456 F.3d 955 ( 2006 )

san-luis-obispo-mothers-for-peace-santa-lucia-chapter-of-the-sierra-club , 449 F.3d 1016 ( 2006 )

Tri-Valley CAREs v. US Dept. of Energy , 671 F.3d 1113 ( 2012 )

Su Hwa She v. Holder , 629 F.3d 958 ( 2010 )

Oregon Natural Desert Ass'n v. Bureau of Land Management , 625 F.3d 1092 ( 2010 )

idaho-sporting-congress-and-american-wildlands-v-jack-ward-thomas-and , 137 F.3d 1146 ( 1998 )

the-lands-council-a-washington-nonprofit-corporation-kootenai , 395 F.3d 1019 ( 2005 )

Oregon Natural Resources Council Fund v. Brong , 492 F.3d 1120 ( 2007 )

South Fork Band Council v. United States Department of the ... , 588 F.3d 718 ( 2009 )

Te-Moak Tribe of Western Shoshone v. United States ... , 608 F.3d 592 ( 2010 )

okanogan-highlands-alliance-washington-environmental-council-colville , 236 F.3d 468 ( 2000 )

oregon-natural-resources-council-forest-conservation-council-concerned , 109 F.3d 521 ( 1997 )

The Lands Council v. McNair , 537 F.3d 981 ( 2008 )

half-moon-bay-fishermans-marketing-association-steve-fitz-james-matkin , 857 F.2d 505 ( 1988 )

natural-resources-defense-council-inc-v-john-s-herrington-secretary , 768 F.2d 1355 ( 1985 )

Robertson v. Methow Valley Citizens Council , 109 S. Ct. 1835 ( 1989 )

National Cable & Telecommunications Assn. v. Brand X ... , 125 S. Ct. 2688 ( 2005 )

View All Authorities »