Winding Creek Solar LLC v. Carla Peterman , 932 F.3d 861 ( 2019 )


Menu:
  •                 FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    WINDING CREEK SOLAR LLC,                Nos. 17-17531
    Plaintiff-Appellant/          17-17532
    Cross-Appellee,
    D.C. No.
    v.                     3:13-cv-04934-
    JD
    CARLA PETERMAN; MARTHA
    GUZMAN ACEVES; LIANE RANDOLPH;
    CLIFFORD RECHTSCHAFFEN;                    OPINION
    MICHAEL PICKER, in their official
    capacities as Commissioners of the
    California Public Utilities
    Commission,
    Defendants-Appellees/
    Cross-Appellants.
    Appeal from the United States District Court
    for the Northern District of California
    James Donato, District Judge, Presiding
    Argued and Submitted February 13, 2019
    San Francisco, California
    Filed July 29, 2019
    Before: M. Margaret McKeown, William A. Fletcher,
    and Mary H. Murguia, Circuit Judges.
    Opinion by Judge McKeown
    2           WINDING CREEK SOLAR V. PETERMAN
    SUMMARY *
    Public Utilities
    The panel affirmed the district court’s judgment after a
    bench trial and summary judgment in favor of the plaintiff
    in an action brought under the Public Utility Regulatory
    Policies Act against Commissioners of the California Public
    Utilities Commission.
    PURPA requires electric utilities to buy all the power
    produced by alternative energy generators known as
    Qualifying Cogeneration Facilities (“QFs”) and to pay the
    same rate they would have if they had obtained that energy
    from a source other than the QFs. QFs are guaranteed their
    choice of this “avoided cost” rate as calculated either at the
    time of contracting or the time of delivery. Plaintiff was a
    QF that wanted to develop a solar generating facility in
    California.
    To regulate the terms under which electric utilities
    purchase power from QFs, the CPUC established the
    Renewable Market Adjusting Tariff (“Re-MAT”) program.
    The panel held that Re-MAT violated PURPA’s
    requirements because it capped the amount of energy
    utilities were required to purchase from QFs and because it
    set a market-based rate, rather than one based on the utilities’
    avoided cost. California did not offer a PURPA-compliant
    alternative. The panel held that, with no PURPA-compliant
    program available, PURPA preempted Re-MAT.
    *
    This summary constitutes no part of the opinion of the court. It
    has been prepared by court staff for the convenience of the reader.
    WINDING CREEK SOLAR V. PETERMAN                     3
    The panel further held that the district court did not abuse
    its discretion to fashion equitable relief when it declined to
    award plaintiff its preferred remedy of a particular contract.
    COUNSEL
    Eric Lee Christensen (argued), Beveridge & Diamond,
    Seattle, Washington; Thomas Melone, Allco Renewable
    Energy Ltd., New York, New York; for Plaintiff-Appellant.
    Christine Jun Hammond (argued), Pouneh Ghaffarian, and
    Arocles Aguilar, California Public Utilities Commission,
    San Francisco, California, for Defendants-Appellees.
    David Bender, Earthjustice, Madison, Wisconsin, for Amici
    Curiae Montana Environmental Information Center, Idaho
    Conservation League, and Vote Solar.
    Gregory M. Adams, Richardson Adams PLLC, Boise,
    Idaho; Irion Sanger, Sanger Law PC, Portland, Oregon; for
    Amici Curiae Community Renewable Energy Association,
    and Northwest and Intermountain Power Producers
    Coalition.
    4          WINDING CREEK SOLAR V. PETERMAN
    OPINION
    McKEOWN, Circuit Judge:
    The district court observed that “[d]espite the complex
    regulatory and factual background” in this case, “the key
    legal issues turned out to be straightforward.” We agree.
    The result here follows from straightforward application of
    a handful of regulatory requirements.
    The Public Utility Regulatory Policies Act of 1978
    (“PURPA”), 
    16 U.S.C. § 2601
     et seq., requires electric
    utilities to buy all the power produced by alternative energy
    generators known as Qualifying Cogeneration Facilities
    (“QFs”). 
    18 C.F.R. § 292.303
    (a). And it requires these
    utilities to pay the same rate they would have if they had
    obtained that energy from a source other than the QFs.
    
    18 C.F.R. § 292.304
    . QFs are guaranteed their choice of this
    “avoided cost” rate as calculated either at the time of
    contracting or the time of delivery.              
    18 C.F.R. § 292.304
    (d)(2). Winding Creek Solar LLC is a QF that
    wants to develop a 1 MW solar generating facility in Lodi,
    California.
    To regulate the terms under which electric utilities
    purchase power from QFs, the California Public Utilities
    Commission (“CPUC”) established the Renewable Market
    Adjusting Tariff (“Re-MAT”) program. Re-MAT violates
    PURPA’s requirements, because it caps the amount of
    energy utilities are required to purchase from QFs and
    because it sets a market-based rate, rather than one based on
    the utilities’ avoided cost. California does not offer a
    PURPA-compliant alternative. With no PURPA-compliant
    program available, PURPA preempts Re-MAT.
    WINDING CREEK SOLAR V. PETERMAN                     5
    BACKGROUND
    I. THE PUBLIC UTILITY REGULATORY POLICIES ACT
    In an effort to reduce American dependence on fossil
    fuels, Congress enacted Title II of PURPA to facilitate
    development of alternative energy sources. PURPA aims to
    eliminate “(1) the reluctance of traditional electric utilities to
    purchase power from and sell power to non-traditional
    facilities, and (2) the financial burdens imposed upon
    alternative energy sources by state and federal utility
    authorities.” Indep. Energy Producers Ass’n, Inc. v. Cal.
    Pub. Utils. Comm’n (IEP), 
    36 F.3d 848
    , 850 (9th Cir. 1994).
    Congress directed the Federal Energy Regulatory
    Commission (“FERC”) to adopt “such rules as it determines
    necessary to encourage cogeneration and small power
    production.” 16 U.S.C. § 824a-3(a). FERC’s regulations
    under PURPA define the criteria for certifying alternative
    energy producers as QFs. IEP, 
    36 F.3d at 851
    ; 
    18 C.F.R. §§ 292.201
    –.211. The regulations benefit QFs by requiring
    utilities to purchase the energy produced by QFs. IEP,
    
    36 F.3d at 851
    ; see also 16 U.S.C. § 824a-3(a). Two features
    of this regulatory scheme are relevant here.
    First, the so-called “must take” provision requires
    utilities to purchase all of the energy a QF provides. The
    regulations mandate that “[e]ach electric utility shall
    purchase . . . any energy and capacity which is made
    available from a qualifying facility . . . [d]irectly to the
    electric utility.” 
    18 C.F.R. § 292.303
    (a)(1).
    Second, the pricing scheme requires utilities to pay QFs
    a rate derived from the utility’s “avoided costs.” “Avoided
    costs” are the costs a utility would have incurred but for the
    purchase from a QF, either by purchasing the energy from
    6          WINDING CREEK SOLAR V. PETERMAN
    some other source or by generating the energy itself.
    
    18 C.F.R. § 292.101
    (b)(6). FERC regulations give QFs two
    options for calculating avoided costs. “[T]he rates for
    [energy] purchases shall, at the option of the [QF] . . . be
    based on either: (i) [t]he avoided costs calculated at the time
    of delivery; or (ii) [t]he avoided costs calculated at the time
    the obligation is incurred.” 
    18 C.F.R. § 292.304
    (d)(2)
    (emphasis added). In other words—and key to this appeal—
    PURPA allows QFs to choose whether the avoided-cost rate
    a utility pays will be calculated at the time of contracting or
    the time of delivery.
    II. CALIFORNIA’S PURPA PROGRAMS
    The CPUC implements PURPA programs in California.
    Californians for Renewable Energy v. Cal. Pub. Utils.
    Comm’n, 
    922 F.3d 929
    , 931 (9th Cir 2019). In 2012, the
    CPUC created Re-MAT, one of several California programs
    regulating the terms of utilities’ contracts with alternative
    energy sources, such as wind farms or solar producers. Re-
    MAT was intended to establish competitive market-based
    rates for energy from alternative sources. QFs accepted to
    Re-MAT are assigned to a queue “on a first-come-first-
    served basis.” Every two months, in what is essentially an
    auction, the utility serving a given area offers the QFs at the
    head of the queue contracts at a pre-defined Re-MAT price,
    which QFs can accept or reject. QFs that reject the contract
    keep their place in line until the next offering two months
    later.
    Two additional features of Re-MAT are significant here.
    The amount of energy a utility must buy through Re-MAT
    is capped. California’s three investor-owned utilities are
    obligated to purchase only 750 MW through Re-MAT
    statewide. This amount is divided among the utilities
    according to their customers’ share of peak electricity
    WINDING CREEK SOLAR V. PETERMAN                  7
    demand. And each utility is allowed to subtract from its
    share any generation it is already obligated to purchase under
    prior CPUC programs. As a result, PG&E, which serves the
    Northern California area in which Winding Creek is located,
    is obligated to purchase just 149.848 MW of energy from
    QFs under Re-MAT. That obligation is then divided equally
    among three types of generation: “baseload,” “non-peaking,
    as-available,” and “peaking, as-available” (which includes
    solar facilities such as Winding Creek).
    Additionally, in any given two-month period, PG&E is
    obligated to purchase no more than 5 MW from each
    category of generation. Once PG&E reaches this limit—
    meaning once purchasing the output of the next QF in line
    would put it over the 5 MW cap—it can stop offering Re-
    MAT contracts.
    Also significant is the Re-MAT contract price. The
    CPUC set the initial price at $89.23/MWh for peaking as-
    available facilities like Winding Creek. Every two months
    this price adjusts up, down, or stays the same based on QFs’
    willingness to accept the prior offer price. If QFs will not
    supply at least 1 MW to the regional utility, and there are at
    least five unaffiliated QFs in the queue, the next contract
    price adjusts up. If QFs supply at least 5 MW at the previous
    offer price, the price adjusts down. And if QFs supply
    between 1 and 5 MW at the offer price, or there are fewer
    than five unaffiliated QFs in the queue, the price remains the
    same. The price adjustment follows a formula set by the
    CPUC.
    The CPUC administers another PURPA program, the
    Standard Contract, which is available as an alternative to Re-
    MAT. See Winding Creek Solar LLC, 
    153 FERC ¶ 61027
    ,
    
    2015 WL 6083932
     (Oct. 15, 2015). The Standard Contract
    does not cap the amount of energy a utility is obligated to
    8          WINDING CREEK SOLAR V. PETERMAN
    buy. The Standard Contract offers an avoided-cost rate,
    calculated using a six-variable formula. However, three of
    the six variables (burner tip gas price, market heat rate, and
    a location adjustment factor) are impossible to determine at
    the time of contracting.
    III.   WINDING CREEK’S RE-MAT PARTICIPATION
    Winding Creek was accepted into the Re-MAT program,
    but because it was not placed near the top of the queue, the
    company did not receive a contract offer at the initial
    $89.23/MWh price. By the time Winding Creek received a
    contract offer in March 2014, the price had dropped to
    $77.23/MWh. Winding Creek rejected this offer and later,
    lower offers because it could not develop a facility at such a
    low price.
    Winding Creek initially challenged the Re-MAT
    program before FERC. See Winding Creek Solar LLC,
    
    144 FERC ¶ 61122
    , 
    2013 WL 4053221
     (Aug. 12, 2013);
    Winding Creek Solar LLC, 
    151 FERC ¶ 61103
    , 
    2015 WL 2151303
     (May 8, 2015) ; Winding Creek Solar LLC,
    
    153 FERC ¶ 61027
    . After various orders and notices of
    intent not to act, Winding Creek filed suit in district court.
    Following a one-day bench trial, the district court granted
    summary judgment in favor of Winding Creek but declined
    to grant Winding Creek its preferred remedy: a contract with
    PG&E at the initial $89.23/MWh price.
    ANALYSIS
    We review de novo the district court’s grant of summary
    judgment. FTC v. Stefanchik, 
    559 F.3d 924
    , 927 (9th Cir.
    2009). Findings of fact following a bench trial are reviewed
    for clear error. See Husain v. Olympic Airways, 
    316 F.3d 829
    , 835 (9th Cir. 2002), aff’d 
    540 U.S. 644
     (2004).
    WINDING CREEK SOLAR V. PETERMAN                     9
    Like the district court, we believe the conclusion to be
    drawn from this web of regulations is not complicated:
    California’s Re-MAT program violates, and is therefore
    preempted by, PURPA. See La. Pub. Serv. Comm’n v. FCC,
    
    476 U.S. 355
    , 368–69 (1986) (explaining that state
    regulations that conflict with federal regulations are
    preempted under the Supremacy Clause).
    Re-MAT violates PURPA in two ways. To begin, Re-
    MAT’s cap on the amount of energy utilities must purchase
    from QFs is impermissible under PURPA’s must-take
    provision. Under Re-MAT, PG&E is required to purchase
    no more than 5 MW of energy from each of the three
    categories of alternative energy sources in any two-month
    period. And each utility must purchase only a fraction of the
    750 MW statewide cap from each category of generators.
    As a result, a utility could purchase less energy than a QF
    makes available, an outcome forbidden by PURPA.
    
    18 C.F.R. § 292.303
    (a)(1).
    Re-MAT’s pricing scheme also runs afoul of PURPA.
    PURPA requires a utility to pay QFs at an avoided-cost rate:
    the rate the utility would have incurred obtaining energy
    from a source other than the QFs.                    
    18 C.F.R. § 292.101
    (b)(6). True, state agencies may take a variety of
    factors into account when calculating avoided cost. See
    
    18 C.F.R. §§ 292.302
    (b), 292.304(e). But the Re-MAT
    price, which is arbitrarily adjusted every two months
    according to the QFs’ willingness to supply energy at the
    pre-defined price, strays too far afield from a utility’s but-for
    costs to satisfy PURPA.
    The CPUC argues that Re-MAT’s noncompliance with
    PURPA is not consequential because QFs may instead sell
    energy to utilities through the Standard Contract. It is true
    that FERC has concluded that an alternative program may
    10         WINDING CREEK SOLAR V. PETERMAN
    exist if a state otherwise satisfies its obligations to QFs under
    PURPA. See Winding Creek Solar LLC, 151 FERC
    at ¶ 61103 (“[A]s long as a state provides QFs the
    opportunity to enter into long-term legally enforceable
    obligations at avoided-cost rates, a state may also have
    alternative programs that . . . limit how many QFs, or the
    total capacity of QFs, that may participate in the [alternative]
    program.”). The Supreme Court has recently reiterated
    when courts must defer to agencies’ interpretations of their
    own regulations. Kisor v. Wilkie, — U.S. —, No. 18-15, slip
    op. at 11–19 (June 26, 2019). But we need not decide if
    FERC’s regulatory interpretation is due deference under
    Auer v. Robbins, 
    519 U.S. 452
     (1997), because, either way,
    the result is the same.
    Even under FERC’s interpretation, the Standard
    Contract cannot save Re-MAT because the Standard
    Contract also violates PURPA. PURPA mandates that QFs
    be given a choice between calculating the avoided-cost rate
    at the time of contracting or at the time of delivery.
    
    18 C.F.R. § 292.304
    (d)(2). The Standard Contract provides
    only one formula for calculating avoided cost, and that
    formula relies on variables that are unknown at the time of
    contracting. The Standard Contract violates PURPA
    because it fails to give QFs the option to calculate avoided
    cost at the time of contracting. This infirmity is plain from
    the face of the regulations, so we do not defer to FERC’s
    unreasoned conclusion to the contrary. See Kisor, slip op. at
    13, 17 (holding that Auer deference is only appropriate if the
    regulation being interpreted is “genuinely ambiguous” and
    the agency’s interpretation “reflect[s] fair and considered
    judgment” (internal quotation marks omitted)).
    The bottom line is that two wrongs don’t make a right.
    Because neither option offered by the CPUC is PURPA-
    WINDING CREEK SOLAR V. PETERMAN                   11
    compliant, California’s regulatory scheme is preempted by
    federal law.
    Finally, the district court did not abuse its broad
    discretion to fashion equitable relief by declining to grant
    Winding Creek a contract with PG&E at the initial
    $89.23/MWh price. See Labor/Cmty. Strategy Ctr. v. L.A.
    Cty. Metro. Transp. Auth., 
    263 F.3d 1041
    , 1048 (9th Cir.
    2001). Indeed, it would be inappropriate to order a non-party
    to contract with Winding Creek under a modified version of
    the very program the court had just determined to be
    preempted by federal regulation. It is not the court’s job to
    fashion a new contract to Winding Creek’s liking. See Allco
    Renewable Energy Ltd. v. Mass. Elec. Co., 
    875 F.3d 64
    , 74
    (1st Cir. 2017) (noting that federal courts are neither
    statutorily authorized nor competent to set avoided-cost
    rates). 1
    AFFIRMED.
    1
    The CPUC’s unopposed motion for judicial notice (Dkt. 47) is
    GRANTED.