Ogden Fire Co No 1 v. Upper Chichester Twp ( 2007 )


Menu:
  •                                                                                                                            Opinions of the United
    2007 Decisions                                                                                                             States Court of Appeals
    for the Third Circuit
    10-4-2007
    Ogden Fire Co No 1 v. Upper Chichester Twp
    Precedential or Non-Precedential: Non-Precedential
    Docket No. 06-2297
    Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_2007
    Recommended Citation
    "Ogden Fire Co No 1 v. Upper Chichester Twp" (2007). 2007 Decisions. Paper 315.
    http://digitalcommons.law.villanova.edu/thirdcircuit_2007/315
    This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova
    University School of Law Digital Repository. It has been accepted for inclusion in 2007 Decisions by an authorized administrator of Villanova
    University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.
    PRECEDENTIAL
    UNITED STATE COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    06-2297/07-1694
    OGDEN FIRE COMPANY NO. 1;
    SPRINT SPECTRUM, L.P.
    Appellees
    v.
    UPPER CHICHESTER TOWNSHIP; ZONING HEARING
    BOARD OF UPPER
    CHICHESTER TOWNSHIP,
    Appellants
    Appeal from the United States District Court
    for the Eastern District of Pennsylvania
    (05-cv-01031)
    District Judge: Hon. John R. Padova
    Argued: May 21, 2007
    Before: McKee, Ambro, Circuit Judges and
    Ackerman,* District Judge
    *
    The Honorable Harold Ackerman, Senior District Judge
    of the United States District Court for the District of New
    Jersey, sitting by designation.
    1
    (Opinion filed: October 4, 2007 )
    JOHN J. RENDEMONTI, ESQ. (Argued)
    14 Regency Plaza
    Glenn Mills, PA 19342
    HOWARD J. GALLAGHER, III, ESQ.
    Gallagher & Gallagher
    18 East Second Street
    P.O. Box 348
    Media, PA 19063
    Attorneys for the Appellants
    RUDOLPH GARCIA, ESQ. (Argued)
    Buchanan, Ingersoll & Rooney PC
    1835 Market Street, 14th Floor
    Philadelphia, PA 19103
    JOHN JAY WILLS, ESQ.
    4124 Chichester Avenue
    Boothwyn, PA 19061
    Attorneys for the Appellees
    OPINION
    McKEE, Circuit Judge.
    Upper Chichester Township and the Zoning Hearing
    Board of Upper Chichester Township appeal two orders of the
    district court reversing a determination of the Zoning Hearing
    2
    Board based upon the district court’s conclusion that the denial
    of requested zoning approvals and a building permit violated
    the Telecommunications Act of 1996. For the reasons that
    follow, we will affirm.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    Ogden Fire Company No. 1 (“Ogden”), is a volunteer
    fire company that provides fire, ambulance, and rescue services
    to the residents of Upper Chichester Township, Delaware
    County, Pennsylvania and surrounding areas. It responds to
    approximately 550 requests for assistance per year. Ogden’s
    firehouse is located in a zoning district that is classified as an R-
    2 Medium Density Residential District.            Ogden uses the
    Delaware County Emergency Radio Center radio service (the
    “County System”), which is a 500 MHZ system with three
    repeaters located throughout Delaware County. This system is
    associated with the 911 system. Ogden experiences coverage
    3
    problems in certain areas of the Township. To make matters
    worse, the County System is not accessible to all public-safety
    personnel.
    Ogden also shares a 150 MHZ radio system (the “Local
    System”) within the Township with other fire companies, local
    police, school crossing guards and street maintenance crews.
    However, the Local System does not have repeaters and cannot
    reach all areas of the Township. The resulting gap in coverage
    over the Local System has resulted in problems that include fire
    fighters not being able to communicate with police. The
    problems have been building for the last ten years and occur on
    an almost daily basis. In fact, according to testimony on this
    record, poor radio communication has contributed to the deaths
    of two people.
    Sprint Spectrum, L.P .(“Sprint”), provides personal
    communications services (“PCS”) over a network of wireless
    4
    telecommunications facilities (“WCF”) pursuant to a license
    from the Federal Communications Commission (“FCC”).
    Portable telephones and devices using PCS technology operate
    by sending and receiving radio signals transmitted between the
    telephone or device and antennas mounted on towers, poles,
    buildings or other structures. The antennas are connected to
    transmitters that transmit the signals over landlines that are part
    of the national telephone network. These antennas and the
    related equipment are commonly known as a “cell site,” and the
    surrounding area serviced by the antenna, and its associated
    equipment, is commonly referred to as a “cell.”
    Telecommunication providers cannot provide reliable
    service to mobile customers unless there is a continuous series
    of overlapping cells arranged in a honeycomb-like grid. Absent
    such interwoven fields of coverage, a user experiences
    unreliable service upon entering an area without a functioning
    5
    cell. These problems include the inability to make or receive
    calls as well as dropped, interrupted, and/or unintelligible calls.
    Because portable telephones have very little power, they
    need to be within two miles of a cell site to function properly,
    and, the quality of the communication decreases as the distance
    to the cell site approaches the two mile perimeter. Accordingly,
    the cells must be closely placed.        Sprint’s engineers use
    complex computer programs to determine appropriate locations
    for cell sites based upon such variables as the boundaries of the
    cell, topography, and any physical obstructions within the area
    of coverage.
    In order to correct the problems it has encountered with
    its communications system, Ogden proposed building a radio
    operations center inside its firehouse at 4300 Naamans Creek
    Road and a 130 foot radio tower in the rear yard of the
    firehouse. It is, however, difficult for a volunteer fire company
    6
    to afford the construction costs of such a project. Accordingly,
    Ogden and Sprint entered into an agreement that would have
    addressed Ogden’s communications problem and safety
    concerns while alleviating Sprint’s problems with the gaps in its
    coverage in the vicinity of Ogden’s firehouse.
    Pursuant to that agreement, Ogden and Sprint
    (hereinafter referred to jointly as “Ogden/Sprint”) filed a joint
    application with the Zoning Board on August 31, 2004, for
    approval of the erection of a steel monopole 130 feet high for
    mounting emergency service and wireless telecommunications
    antennas. With Sprint’s antennas on the top of the monopole
    would increase the total height of the tower to 133 feet. Sprint
    was to install the tower to meet both its needs and Ogden’s
    needs and then pay monthly rent to Ogden. The Zoning
    application asked the Board to:
    (1) find that the proposed monopole and related
    7
    radio equipment are permitted as an accessory use
    to the permitted fire company use on the subject
    property pursuant to § 303.1 or § 304 of the
    Zoning Ordinance;1 (2) grant a variance from the
    height limitation of § 305.8 of the Zoning
    Ordinance; (3) approve a special exception for
    Sprint's proposed wireless communications
    facility pursuant to §§ 303.7, 1814 and 2106(2) of
    the Zoning Ordinance; or, in the alternative, (4)
    grant a variance from the use provisions of § 302
    of the Zoning Ordinance to allow the proposed
    monopole, equipment and use.
    Ogden Fire Co. No. 1 v. Upper Chichester Twp., No. 05-1031,
    
    2006 WL 851391
    , *2 (E.D. Pa. Mar. 30, 2006) (“Ogden I”).
    During the zoning hearings that followed, Ogden/Sprint
    presented the testimony of several witnesses to establish that:
    the tower and equipment were necessary, the tower was an
    1
    In 1969, the Township Zoning Hearing Board had
    granted a special exception to Ogden to use its property as a
    “public use” under § 303.1 of the Township’s Zoning
    Ordinance.
    8
    accessory use to the firehouse,2 Ogden’s use of the tower would
    be “a municipal or public use,” the tower would satisfy the
    special exception criteria regarding the height of the monopole
    as an “accessory structure,” and, if not, that Ogden/Sprint were
    entitled to a variance. They also asked the Board to recognize
    that other carriers providing functionally equivalent services
    have been granted greater relief than that requested by
    Ogden/Sprint, and that the proposed monopole/tower was the
    least intrusive means of addressing Sprint’s gap in coverage in
    the Township.
    A. The Zoning Board’s decision.
    On February 10, 2005, the Zoning Board denied the
    2
    The Zoning Ordinance defines “accessory uses” to
    include: “any accessory use on the same lot with and
    customarily incident to any of the uses permitted above and not
    detrimental to the neighborhood.” Zoning Ordinance, §§ 204,
    304.
    9
    application in a written opinion that treated the joint application
    of Ogden/Sprint as one filed solely by Sprint. According to that
    interpretation, Sprint was requesting Zoning Board approval to
    construct its own WCF tower, and Ogden would thereafter
    attach its radio antenna to the tower to enhance Ogden’s
    communication systems. The Zoning Board concluded that
    Sprint had not established the propriety of erecting a stand-
    alone WCF tower in an R-2 Residential District. The Board
    concluded that the WCF was not an accessory structure to the
    firehouse because it was not a use “customarily incidental and
    subordinate to the principal use of the land or building and
    located on the same lot with such principal use.” Ogden I, 
    2006 WL 851391
    at *3. The Board also refused to grant the special
    exception required to build a tower taller than 15 feet because
    the WCF is not an accessory use or structure to the firehouse.
    The Board refused to grant a special exception to build the
    10
    WCF because stand-alone WCF towers are not permitted in R-2
    Residential Districts.   Finally, the Board also rejected the
    alternate request for a variance because a 133 foot stand-alone
    WCF tower is not a structure permitted in an R-2 Residential
    District and because Sprint had not satisfied the requirements
    for a variance under the Pennsylvania Municipal Planning
    Code.
    II. DISTRICT COURT PROCEEDINGS
    Ogden/Sprint responded by filing a joint complaint
    against the Township and Zoning Board (hereinafter
    collectively referred to as the “Township”) in district court
    alleging violations of the Telecommunications Act of 1996
    (“TCA”), 47 U.S.C. § 332, and related claims. In Count I,
    Ogden/Sprint alleged that the Township violated 47 U.S.C. §
    332(c)(7)(B)(i)(I) by unreasonably discriminating among
    providers of functionally equivalent services in denying
    11
    Ogden/Sprint’s joint application despite having previously
    approved a similar application filed by Reliance Hook and
    Ladder Co. No. 1 and Metro Phone in an R-2 Residential
    District, and having also previously approved the application of
    AT&T Wireless to build a telecommunications tower in an R-1
    Residential District.   Count II alleged that the Township
    violated 47 U.S.C. § 332(c)(7)(B)(iii) because the denial of the
    Ogden/Sprint application was not supported by substantial
    evidence. Count III asserted various causes of action under
    state law that we need not address.
    After the close of discovery, the parties filed cross-
    motions for summary judgment. In a very thorough and well
    reasoned Memorandum Opinion, the district court granted
    summary judgment in favor of Ogden/Sprint on their claims
    under the TCA. See Ogden I, 
    2006 WL 851391
    . In ordering
    relief, the court ordered the Township:
    12
    to grant the application of Ogden Fire Co. No. 1
    and Sprint Spectrum, L.P., to build a 130 foot
    monopole radio tower and related radio
    equipment as an accessory use to Ogden’s use of
    its property as a firehouse and to issue the
    Plaintiffs the requested special exceptions in
    accordance with Zoning Ordinance §§ 1706 and
    303.7. Upper Chichester Township shall issue
    any and all zoning permits for the proposed tower
    and supporting structures within 30 days of the
    date of this Order.3
    
    Id. at *21.
    The Township has appealed that Order. That appeal
    is No. 06-2297.
    On May 3, 2006, the Zoning Board granted the special
    exceptions to Ogden/Sprint.         However, Ogden/Sprint’s
    3
    In Cellular Tel. Co. v. Town of Oyster Bay, 
    166 F.3d 490
    , 497 (2d Cir. 1999), the Court of Appeals for the Second
    Circuit commented that “[t]he TCA does not specify a remedy
    for violations of the cellular siting subsection.” 
    Id. However, “[t]he
    majority of district courts that have heard these cases
    have held that the appropriate remedy is injunctive relief in the
    form of an order to issue the relevant permits.” 
    Id. (citations omitted).
    In Omnipoint Corp. v. Zoning Hearing Bd. of Pine
    Grove Twp. (“Pine Grove II”), 
    181 F.3d 403
    , 410 (3d Cir.
    1999), we held that “[i]njunctions are proper forms of relief
    under § 332(c)(7)(B)(v).” Inasmuch as the district court’s
    order was in the form of an injunction, it remains in effect and
    must be complied with during the pendency of this appeal. See
    Fed.R.Civ.P. 62(a).
    13
    application for a building permit in order to build the radio
    tower was denied by the Township’s Building Inspector
    because the Building Inspector determined that the lease4 of that
    portion of Ogden’s rear yard to Sprint where the radio tower
    was to be built was the division or allocation of land by means
    of a leasehold. According to the Building Inspector, it therefore
    required the approval of a Subdivision and Land Development
    Application pursuant to the Township’s Subdivision and Land
    Development Ordinance and Section 107(a) of the Pennsylvania
    Municipalities Planning Code (“MPC”).             Ogden/Sprint
    thereafter filed a motion to compel the issuance of a building
    permit in district court and requested monetary sanctions.
    On January 17, 2007, the district court issued an Order-
    Memorandum. Ogden Fire Co. No. 1 v. Upper Chichester
    Twp., No. 05-1032, 
    2007 WL 137848
    (E.D. Pa. Jan. 17, 2007)
    4
    Rather than assigning Sprint a position on the radio
    tower, Ogden leased 2,500 square feet of its real property to
    Sprint for the purpose of constructing, operating and
    maintaining the tower and related equipment.
    14
    (“Ogden II”). It noted that under Pennsylvania law, leases
    which allocate land, as opposed to assigning positions on a pole
    or tower, constitute a subdivision or allocation of land pursuant
    to § 107(a) of the MPC. 
    Id. at *2
    (citing Upper Southampton
    Twp. v. Upper Southampton Twp. Zoning Hearing Board, 
    885 A.2d 85
    , 92 (Pa. Commw. Ct. 2005), appeal granted, 
    895 A.2d 1265
    (Pa. 2006)). However, the district court reasoned that
    there was nothing in the record before it that would support the
    denial of a Subdivision and Land Development Application or
    the issuance of a building permit. 
    Id. at *3.
    Therefore, it
    reasoned that a remand to the Township for consideration of a
    Subdivision and Land Development Application and for a
    building permit would frustrate the intent of the TCA. 
    Id. Accordingly, the
    court directed the Township to show cause
    why an injunction should not be entered requiring the grant of
    land development and subdivision approval and issuance of a
    building permit. 
    Id. After more
    briefing, on February 15, 2007,
    the court ordered the Township to “issue all necessary approvals
    15
    and permits for the building of the 130 foot monopole radio
    tower and related radio equipment in accordance with the
    Application for Plan Examination and Building Permit of Sprint
    Spectrum, L.P., dated August 31, 2006.”
    The Township has filed an appeal from that order. That
    appeal is No. 07-1694. On March 9, 2007, at our direction, the
    Clerk consolidated the Township’s appeals for purposes of
    scheduling and disposition.        Each appeal is discussed
    separately below.
    III. THE TELECOMMUNICATIONS ACT OF 1996
    Congress enacted the TCA to “provide ‘a pro-
    competitive, de-regulatory national policy framework designed
    to rapidly accelerate private sector deployment of advanced
    telecommunications and information technologies and services
    to all Americans by opening all telecommunications markets to
    competition.’” APT Pittsburgh Ltd. P’ship v. Penn Twp., 
    196 F.3d 469
    , 473 (3d Cir. 1999) (quoting H.R. Rep. No. 104-458
    (1996) (Conf. Rep.), reprinted in 1996 U.S.C.C.A.N. 10, 1124).
    16
    In order to achieve that goal without interfering with the
    traditional right of local governments to regulate land use,
    “Section 322(c)(7) of the TCA expressly preserves the
    traditional authority enjoyed by state and local government to
    regulate land use and zoning, but places several substantive and
    procedural limits upon that authority when it is exercised in
    relation to personal wireless service facilities.” 
    Id. The cellular
    siting subsection of the TCA provides as
    follows:
    (7) Preservation of local zoning authority.
    (A) General authority. Except as provided in this
    paragraph, nothing in this Act shall limit or affect
    the authority of a State or local government or
    instrumentality thereof over decisions regarding
    the placement, construction, and modification of
    personal wireless service facilities.
    (B) Limitations.
    (i) The regulation of the placement, construction,
    and modification of personal wireless service
    facilities by any State or local government or
    instrumentality thereof --
    (I) shall not unreasonably discriminate among
    providers of functionally equivalent services; and
    (II) shall not prohibit or have the effect of
    prohibiting the provision of personal wireless
    services.
    17
    (ii) A State or local government or
    instrumentality thereof shall act on any request
    for authorization to place, construct, or modify
    personal wireless service facilities within a
    reasonable period of time after the request is duly
    filed with such government or instrumentality,
    taking into account the nature and scope of such
    request.
    (iii) Any decision by a State or local government
    or instrumentality thereof to deny a request to
    place, construct, or modify personal wireless
    service facilities shall be in writing and supported
    by substantial evidence contained in a written
    record.
    (iv) No State or local government or
    instrumentality thereof may regulate the
    placement, construction, and modification of
    personal wireless service facilities on the basis of
    the environmental effects of radio frequency
    emissions to the extent that such facilities comply
    with the Commission’s regulations concerning
    such emissions.
    (v) Any person adversely affected by any final
    action or failure to act by a State or local
    government or any instrumentality thereof that is
    inconsistent with this subparagraph may, within
    30 days after such action or failure to act,
    commence an action in any court of competent
    jurisdiction. The court shall hear and decide
    such action on an expedited basis. Any person
    adversely affected by an act or failure to act by a
    State or local government or any instrumentality
    thereof that in inconsistent with clause (iv) may
    petition the Commission for relief.
    18
    47 U.S.C. § 332(c)(7).
    “Traditionally, the federal courts have taken an extremely
    deferential stance in reviewing local zoning decisions, limiting
    the scope of inquiry to the constitutionality of the zoning
    decision under a standard of rational review.” Cellular Tel. Co.
    v. Town of Oyster Bay, 
    166 F.3d 490
    , 493 (2d Cir. 1999) (citing
    Schad v. Borough of Mount Ephraim, 
    452 U.S. 61
    , 68 (1981)).
    However, the TCA altered that traditional deference in very
    important ways insofar as local decisions interfere with, or
    impact upon, telecommunications facilities. Thus, “[a]lthough
    Congress explicitly preserved local zoning authority in all other
    respects over the siting of wireless facilities, § 332(c)(7)(A), the
    method by which siting decisions are made is now subject to
    judicial oversight, § 332(c)(7)(B)(v).” 
    Id. Moreover, “denials
    subject to the TCA are reviewed by [the] court [of appeals]
    more closely than standard local zoning decisions.” 
    Id. With this
    framework as our guide, we address the issues that arise
    from the Township’s decisions here.
    19
    IV. THE TOWNSHIP’S APPEAL (No. 06-2297)
    The Township’s appeal of the district court’s order
    reversing the decision of the Zoning Board and granting
    summary judgment to Ogden/Sprint is subject to plenary
    review. See, e.g., Jensen v. Potter, 
    435 F.3d 444
    , 448 (3d Cir.
    2006). We limit our review of the claim that the Zoning
    Board’s rejection of the joint application was not supported by
    “substantial evidence” to the record as it existed when the
    zoning decision was made. See Nat’l Tower, LLC v. Plainville
    Zoning Bd. of Appeals, 
    297 F.3d 14
    , 22 (1st Cir. 2002).
    However, we review Ogden/Sprint’s claim of unreasonable
    discrimination under the TCA on the record as supplemented in
    the district court. See Nextel West Corp. v. Unity Twp., 
    282 F.3d 257
    , 266-67 (3d Cir. 2002).
    A. Substantial Evidence
    As noted previously, the TCA requires that a decision “to
    deny a request to place, construct, or modify personal wireless
    service facilities shall be in writing and supported by substantial
    20
    evidence contained in a written record.”          47 U.S.C. §
    332(c)(7)(B)(iii). “Substantial evidence is a legal term of art.”
    Omnipoint Commc’ns Enters, L.P. v. Zoning Hearing Bd. of
    Easttown Twp., 
    248 F.3d 101
    , 106 (3d Cir. 2001). “It does not
    mean a large or considerable amount of evidence, but rather
    such evidence as a reasonable mind might accept as adequate to
    support a conclusion.” 
    Id. (citation and
    internal quotations
    omitted). In reviewing a record for substantial evidence, we do
    not “weigh the evidence contained in [the] record or substitute
    [our] own conclusions for those of the fact finder, but rather
    [we are] to determine whether there is substantial evidence in
    the record as a whole to support the challenged decision.” 
    Id. (citation and
    internal quotations omitted). “[We] view[] the
    record in its entirety and take[] account of evidence unfavorable
    to the agency’s decision.” Omnipoint Corp. v. Zoning Hearing
    Bd. of Pine Grove Twp. (“Pine Grove II”), 
    181 F.3d 403
    , 408
    (3d Cir. 1999) (citation omitted). “The substantial evidence test
    applies to findings made by a zoning hearing board under the
    21
    locality’s own zoning requirements.” 
    Id. The district
    court found that the Township’s denial of
    Ogden/Sprint’s application was not supported by substantial
    evidence on two distinct, but related grounds. The court granted
    summary judgment to Ogden/Sprint because the Township
    treated their joint application as the sole application of Sprint
    for a stand-alone WCF tower, rather than as the joint
    application of Ogden and Sprint to allow Ogden to erect a radio
    tower for its own benefit, with Sprint thereafter attaching an
    antenna by special exception. Ogden I, 
    2006 WL 851391
    at
    *12. The court also concluded that the denial of the special
    exception was not supported by substantial evidence in the
    written record. 
    Id. at *19.
       The Township challenges both
    findings.
    (1). Joint Application of Ogden and Sprint versus Sole
    Application by Sprint
    The Zoning Board explained its insistence on treating the
    zoning application as Sprint’s application rather than a joint
    22
    application filed by Ogden and Sprint as follows:
    This appeal by Sprint is and can only be a request
    for approval of a Wireless Communication
    Facility, and not solely as a tower to improve the
    radio signal of the fire company. There is no
    doubt that the appeal is for a permit to erect a
    WCF tower and to operate a WCF by a FCC
    licensed provider of cellular telephone service.
    The board cannot ignore that the appeal is by
    Sprint Spectrum LP, and that the testimony
    offered by Sprint on the record relates to a
    cellular telephone service. Although there was
    testimony that the fire company would be
    permitted to place its radio transmission
    equipment on the WCF, that does not convert this
    application into anything other than a Wireless
    Communication Facility for the transmission of
    cellular telephone service. In fact, section 1814
    5.E of the ordinance requires that local police,
    fire, and ambulance companies be specifically
    offered co-location on a WCF tower.
    Joint Appendix (JA) at 553.
    As the district court observes, this finding was fatal to
    the zoning application because the zoning ordinance clearly
    prohibits the siting of a stand-alone WCF tower in an R-1 or R-
    2 Residential District. See Ogden I, 
    2006 WL 851391
    at *11
    (citing Zoning Ordinance §§ 203, 303.7, 803, 903, 1003, 1103).
    23
    In explaining its decision to ignore Ogden’s interest in
    the application, the Township insisted, according to the district
    court, that “no matter how cleverly . . . worded, the Application
    is an application for Sprint to build a WCF as a stand-alone
    tower on Ogden’s property, a use which is not permitted in an
    R-2 Residential District under the Zoning Ordinance.” 
    Id. at *10.
    The district court disagreed. The court held that the
    application “was submitted to the Zoning Board as a joint
    application [by Ogden and Sprint] to build a radio tower for
    Ogden as an accessory use to Ogden’s use of the property as a
    firehouse and for Sprint to attach a WCF antenna to that tower.”
    
    Id. at *10.
    The court explained:
    [T]he Zoning Board’s decision to treat the
    Application as an application brought solely by
    Sprint for the siting of a stand-alone WCF tower
    in an R-2 Residential District, rather than as a
    joint application to erect a radio tower to benefit
    Ogden, on which Sprint could attach an antenna
    by special exception, is not supported by
    substantial evidence in the written record. The
    Court further finds that the Zoning Board’s
    decision to ignore Ogden’s request to build the
    tower on its property as an accessory use to the
    24
    firehouse is not supported by substantial evidence
    in the written record.5
    
    Id. at *12.
    Given Judge Padova’s thorough legal analysis, and
    his meticulous review of the Zoning Board’s factual
    5
    Because the Zoning Board viewed the application as
    filed by Sprint alone for Sprint to build a WCF as a stand-alone
    WCF tower on Ogden’s property, the Board did not consider
    that portion of the application in which Ogden sought to erect
    the tower on its property as an accessory use to the permitted
    fire company use. The Board wrote that it “specifically does
    not render any opinion as to whether or not an antenna or tower
    for transmission of radio signals to be used by a fire company
    alone, is an accessory use or constitute [an] accessory
    structure.” JA at 554.
    Ogden/Sprint contend that in construing the application
    as Sprint’s alone and in not deciding that the radio was an
    accessory use to Ogden’s fire station, the Zoning Board failed
    to decide the application as actually submitted and failed to
    decide Ogden’s request at all. Accordingly, they argue that the
    application as submitted is deemed approved under state law.
    There is a considerable force to that argument. Under
    Pennsylvania law, a zoning board “shall render a written
    decision . . . on the application within 45 days after the last
    hearing before the board . . . ,” but “where the board fails to
    render a decision within the period required by this subsection
    . . . , the decision shall be deemed to have been rendered in
    favor of the applicant.” 53 PA. CONS. STAT. ANN. § 10908(9).
    See Relosky v Sacco, 
    523 A.2d 1112
    (1987). Nevertheless,
    because these appeals raise important federal issues under the
    TCA, we are reluctant to resolve this case on that basis, and we
    will address the merits of the arguments that are raised by the
    parties.
    25
    conclusions, we can best dispose of the Township’s challenge
    to the district court’s order by quoting extensively from Judge
    Padova’s Memorandum Opinion. In rejecting the Township’s
    redefinition of the Ogden/Sprint application, the court
    explained:
    [The Township’s] position is belied by the
    Application, which states plainly that it is an
    application filed by Sprint and Ogden for a
    “[s]teel monopole 130 feet in height for mounting
    emergency service (fire company) and wireless
    [t]elecommunications (PCS) antennas.” Indeed,
    the background section of the Application states
    that:
    Ogden currently operates a radio system from its
    property, but that radio system lacks adequate
    coverage in parts of its service area. Installation
    of a repeater radio on a tower of substantially
    greater height will substantially improve its radio
    communications and thus the safety and
    efficiency of this [sic] volunteers. Ogden desires
    to make this improvement. The proposed
    monopole will meet this need.
    
    Id. at *11.
    The Township does not directly claim that the district
    court’s finding of a joint application was clearly erroneous.
    26
    Rather, the Township relies upon certain provisions of the lease
    agreement between Ogden and Sprint to support its contention
    that the zoning application was solely Sprint’s application.6
    Ogden/Sprint argue that the Township did not raise the issue of
    their lease in the district court and that it is therefore waived.
    See Delaware Nation v. Pennsylvania, 
    446 F.3d 410
    , 416 (3d
    Cir. 2006) (“Absent exceptional circumstances, this Court will
    not consider issues raised for the first time on appeal.”).
    Assuming arguendo that the argument is not waived, it can
    readily be rejected as meritless.
    The Township’s reliance on the provisions of a lease
    between the two applicants ignores the very nature of the
    zoning application process. Zoning regulations govern the use
    of the land. Frederick v. Zoning Hearing Bd. of Conewago
    6
    The Township refers to a lease agreement that was
    offered as an exhibit at the zoning hearing, and certain
    provisions of the lease which appear to give Sprint the sole
    ownership of, and control over, the monopole tower as well as
    any equipment attached to it. According to the Township, the
    unilateral nature of the terms of that lease can only mean that
    the zoning application was really for the sole benefit of Sprint.
    27
    Twp., 
    713 A.2d 139
    , 141 (Pa. Commw. Ct. 1998) (citation
    omitted). “Zoning regulations concern the physical use to
    which land is put. Zoning laws, enactments under the police
    power, are not concerned with the method of ownership of
    property. . . . [I]f a use is permitted, a municipality may not
    regulate the manner of ownership of the legal estate.” 
    Id. (citation omitted).
      Accordingly, actual ownership of the
    proposed tower is as irrelevant as the relationship between
    Ogden and Sprint insofar as the zoning application is
    concerned.
    Moreover, the Zoning Board’s focus on the nature and
    extent of Sprint’s involvement totally obfuscated the Zoning
    Board’s inquiry and analysis. The question before the Zoning
    Board was whether the proposed use of the radio tower would
    be accessory to the firehouse; the issue was not the respective
    rights of the applicants, nor the nature of the interest of each
    under the terms of their lease. Accordingly, the district court
    correctly rejected the Township’s effort to view the joint
    28
    application of Ogden and Sprint as the sole application of
    Sprint.
    (2). Substantial Evidence
    Ogden/Sprint applied for two special exceptions for the
    siting and construction of the radio tower. Pursuant to § 1706.2
    of the zoning ordinance they sought a special exception to build
    a tower higher than the height limitation for accessory
    structures.7 They also sought a special exception pursuant to §
    303.7 of the zoning ordinance to attach a WCF antenna to that
    tower.8
    A “special exception” in zoning law is “a conditionally
    permitted use, allowed by the legislature if specifically listed
    7
    Zoning ordinance § 1706.2 provides that “[n]o
    accessory structure shall be more than one (1) story or fifteen
    (15) feet in height, except when a greater height is permitted by
    special exception in the case of any accessory to a non-
    residential use.”
    8
    Zoning ordinance § 303.7 allows a WCF “with Antenna
    attached to a nonresidential building or structure of a permitted
    . . . municipal or governmental building or facility, and a
    building or structure owned by a public utility” in an R-2
    Residential District as a use permitted by special exception.
    29
    standards are met.” In re Brickstone Realty Corp., 
    789 A.2d 333
    , 340 (Pa. Commw. Ct. 2001) (citation omitted). Thus, a
    special exception is not really an exception at all. Rather, it is
    “a use permitted conditionally, the application for which is to be
    granted or denied by the zoning hearing board pursuant to
    express standards and criteria.” 
    Id. (citation omitted).
    “Where
    a particular use is permitted . . . by special exception, it is
    presumed that the local legislature has already considered that
    such use satisfies local concerns for the general health, safety,
    and welfare and that such use comports with the intent of the
    zoning ordinance.” 
    Id. (citation omitted).
    Once an applicant for a special exception establishes it
    has complied with the controlling ordinance, the applicant is
    entitled to a presumption that the requested use “is consistent
    with the promotion of health, safety, and general welfare.” 
    Id. (citation omitted).
    Accordingly, “[t]he burden then shifts to
    objectors to prove that the proposed use is not, in fact,
    consistent with the promotion of health, safety, and general
    30
    welfare.” 
    Id. (citation omitted).
    In order to receive approval pursuant to § 1706.2,
    Ogden/Sprint had to satisfy the conditions for special exception
    listed in § 1802 of the zoning ordinance. That section requires
    the Zoning Board to consider, where appropriate, the following
    factors in considering a request for a special exception:
    a. That the proposed use is consistent with the
    statement of community objections per Section
    103 and the statement of purpose for the district
    in which it is proposed.9
    b. That the proposed use is appropriate for the
    site in question in terms of size, topography,
    natural features, [and] drainage, . . . .
    c. That the proposed use is compatible with the
    9
    The statement of community objectives provided in §
    103 state that this “Zoning Ordinance is intended to implement
    the principles, policies and objectives of the Comprehensive
    Plan and to guide and regulate the orderly growth and
    development of Upper Chichester Township.” Zoning
    Ordinance § 103. The statement of purpose for R-2 Residential
    Districts provides that such districts “are to provide for
    continued medium density suburban type, single-family
    residential development; to preserve existing medium density
    development and open space; and to provide for and regulate
    certain uses permitted [by] special exception.” Zoning
    Ordinance § 301.
    31
    character of the surrounding neighborhood, will
    not interfere with or detract from legitimate uses
    and adjacent properties, and that adequate
    measures will be provided through . . . site layout,
    landscaping, [and] planting . . . to minimize any
    adverse impacts caused by noise, lights, glare,
    odors, smoke, fumes, traffic, parking, loading and
    signage.
    d. That the proposed use will serve the best
    interest of the Township, convenience of the
    community and the public health, safety and
    welfare.
    e. That the proposed use is consistent with the
    Township Comprehensive Plan.
    f. That the proposed use promotes orderly
    development, proper population density and the
    provision of adequate community facilities and
    services, including police and fire protection.
    Zoning Ordinance § 1802.1
    In order to receive permission to attach Sprint’s WCF
    antenna to the tower as a special exception pursuant to § 303.7,
    Ogden/Sprint had to satisfy the relevant conditions contained in
    § 1814 of the zoning ordinance. That section required the
    following:
    A.    The applicant shall demonstrate, using
    32
    accepted technological evidence,         that the
    Antenna and Antenna Support Structure must be
    located where proposed in order to satisfy its
    function in the applicant’s grid system.
    B. If the applicant proposes to build a Tower (as
    opposed to mounting the Antenna on an existing
    tall structure), it is required to demonstrate that it
    contacted the owners of tall structures within a
    one-mile radius of the site proposed, requested
    permission to install the Antenna on those tall
    structures and was denied permission for reasons
    other than economic reasons. . . . If the Antenna
    can be physically and legally accommodated on
    an existing tall structure, the Township may deny
    the application to construct a new Tower.
    C. The applicant shall demonstrate that the
    Antenna Height is the minimum required to
    function satisfactorily. . . .
    D. The applicant shall demonstrate that the
    proposed Antenna and Antenna Support Structure
    are safe and the surrounding properties will not
    be negatively affected by Antenna Support
    Structure failure, falling ice or other debris. . . .
    E. [T]he proposed Antenna Support Structure
    shall be required to accommodate, where
    possible, other users including . . . local police,
    fire and ambulance companies. . . .
    F. The applicant must demonstrate that it is
    licensed by the Federal Communication
    Commission (FCC) to provide wireless
    33
    communications. . . .
    G. As the wireless communications facility is
    fully automated, adequate parking shall be
    required for maintenance workers.
    H. Antenna Support Structures shall, to the
    extent possible, be finished so as to reduce the
    visual impact. . . .
    I. A full site plan shall be required for all
    Landsites. . . .
    J. A plan shall be required for all WCF . . . to
    illustrate the relationship between the proposed
    facility and the adjacent structures and property
    lines.
    K. Towers shall be designed and constructed to
    all applicable standards of the American National
    Standards Institute. . . .
    L. A soil report . . . shall be submitted to the
    Township. . . .
    M. Towers and Antenna shall be designed to
    withstand wind gusts of at least 100 miles per
    hour.
    N. An Antenna may not be located on a building
    or structure that is listed on the Township’s
    Historic Resources Map.
    O. No Antenna or its support structure may be
    artificially lighted except when required by the
    34
    Federal Aviation Agency.
    P. Applicant shall maintain with the Township
    the current name, address and emergency
    telephone number of the owner or operator. . . .
    Zoning Ordinance § 1814.5.
    During the hearing before the Zoning Board,
    Ogden/Sprint presented the testimony of a civil engineer, James
    Rudolph, and submitted a plan showing the relationship
    between the proposed tower and the adjacent structures and
    property lines. The plan also showed the vegetation on Ogden’s
    property, including existing stands of mature trees, which,
    according to Rudolph, would act as buffers. Rudolph testified
    that the tower and antenna would be designed by a licensed
    professional engineer consistent with all applicable codes.
    Rudolph also stated that the completed tower would withstand
    wind gusts of up to 100 miles per hour, not pose any safety
    concerns, provide for adequate storm water management,
    comply with landscaping and soil requirements, and would not
    affect the use of adjacent properties. Furthermore, the tower
    35
    and necessary communications equipment would not affect
    traffic conditions or generate noise and would be unlighted
    except for a work light that could be turned on when needed,
    and that there was already adequate parking at the site for
    maintenance personnel. The distance from the radio tower to
    each of the neighboring properties would be greater than the
    tower’s height, preventing damage to neighboring properties
    caused by the tower’s falling or dropping ice and that there
    would be a multi-agency 911 cabinet for Upper Chichester. He
    testified that Ogden/Sprint would install additional trees to add
    to the existing buffer along Ogden’s property lines and that the
    proposed tower would not alter the essential character or
    essence of the surrounding neighborhood.
    Ogden/Sprint also submitted the expert report of Dr. Ken
    Foster, an expert on the health effects of radio frequencies. He
    opined that the tower and communications facility would
    comply with all applicable FCC standards regarding
    electromagnetic radiation. In addition, Clement Poole, a radio
    36
    frequency engineer, testified about studies he performed
    regarding Sprint’s weak wireless communications service in the
    area of Naamans’s Creek Road, where the Ogden firehouse is
    located. These studies included testing PCS coverage at nearby
    tall towers to see if Sprint could solve its service problems by
    attaching an antenna to an existing tower. He determined that
    the Ogden location was the best one. He also concluded that if
    Sprint were not permitted to attach an antenna to the proposed
    tower, Sprint would have poor to no service in that area, and
    that the proposed tower was the minimum required to alleviate
    Sprint’s coverage problems.
    William T. Robinson, former Township Police Chief and
    Vice President of Ogden, testified that the facility would benefit
    the public health, safety and welfare by enhancing
    communications between the fire company, the Township,
    School District and community.
    As the district court observed, “[d]espite the evidence
    presented by [Ogden/Sprint] in support of their Application,
    37
    which satisfies the relevant requirements of §§ 1802 and 1814
    of the Zoning Ordinance, the Zoning Board found that the
    proposed tower did not satisfy these factors.” Ogden I, 
    2006 WL 851391
    at *16. The Zoning Board concluded:
    (1) That the proposed use is not consistent with
    the statement of community objectives per
    Section 103 and the statement of purpose for the
    district in which the use is proposed.
    (2) That the proposed use is not appropriate for
    the site in question in terms of size, topography,
    natural features, and that adequate provisions
    were not provided to protect sensitive
    environmental features.
    (3) That the proposed use is not compatible with
    the character of the surrounding neighborhood,
    will interfere with or detract from legitimate uses
    and adjacent properties.
    (4) That the proposed use will not serve the best
    interest of the Township, convenience of the
    community and the public health, safety and
    welfare.
    (5) That the proposed use is not consistent with
    the Township Comprehensive Plan.
    (6) That the proposed use will not reflect
    effective site planning and design in terms of
    energy efficiency, environmental protection and
    38
    aesthetic composition.
    The Zoning Board based these conclusions on the
    following findings of fact:
    1. That Appellant proposes to erect a 133 foot
    stand alone WCF tower for transmission and/or
    reception of Wireless Communication Services as
    defined in the Ordinance and that the tower will
    accommodate the needs of Ogden Fire Company
    with respect to enhancing the Fire Company’s
    radio signal.
    2. That the principal use of the proposed tower is
    to operate as a WCF Antenna.
    3. That Appellant is located in an R-2, Medium
    Density Residential District.
    4. That the Appellant, the Ogden Fire Company
    [,] is an existing non-conforming use pursuant to
    the ordinance.
    5. That a single 133 foot tower is not the only
    means by which Appellant could ameliorate or
    correct its alleged lack of adequate service in the
    area around the Ogden Fire Company.
    6. That there exist other solutions to help
    ameliorate the alleged lack of service other than
    to erect a single 133 foot stand along WCF tower
    at Appellant’s location.
    7. That there is adequate wireless communication
    39
    service in the area around Ogden Fire Company
    provided by other providers of Wireless
    Communication Services.
    8. That Appellant did not propose a WCF
    antenna to be “attached to a nonresidential
    building or a structure of a permitted church,
    educational, public, municipal or governmental
    building or facility, and a building or structure
    owned by a public utility regulated by the
    Pennsylvania Utility Commission” which is
    permitted as a Special Exception in an R-2
    Residential District.
    9. That Appellant did not produce evidence from
    the owners of other structures and tall structures
    in the area around Ogden Fire Company refusing
    to allow Appellant to attach an antenna to their
    existing structures and tall structures.
    10. That a 133 foot stand alone tower will
    adversely affect the property values of the
    immediately adjacent residential properties.
    The district court properly rejected most of the Board’s
    findings out of hand. The court ruled that Findings of Fact 1,
    2 and 8 were based on the Zoning Board’s mischaracterization
    of the application as solely Sprint’s request to build a stand-
    alone tower. Those three findings were irrelevant to whether
    Ogden/Sprint’s joint application satisfied the requirements for
    40
    special exceptions contained in zoning ordinance §§ 1802 and
    1814. 
    Id. at *17.
    Similarly, Finding of Fact 9 concerns a
    condition that must be met only if the applicant wants to build
    a stand-alone WCF tower.         Thus, the district court also
    considered Finding of Fact 9 irrelevant to the issue of whether
    the application met the requirements for the special exceptions
    actually requested. 
    Id. The court
    concluded that Finding of
    Fact 3 (the application involved an R-2, Medium Density
    Residential District) was correct. 
    Id. Indeed, this
    was not
    contested. However, the court then noted that Finding of Fact
    7 (adequate wireless communication service in the area of
    Ogden’s property provided by other wireless providers) was not
    at all responsive to any of the conditions for special exceptions
    listed in §§ 1802 and 1814. 
    Id. That finding
    was, therefore,
    irrelevant to whether the application met the requirements for
    the requested special exceptions. 
    Id. The court
    concluded that
    Finding of Fact 4 was incorrect because the Zoning Board had
    granted Ogden a special exception to locate a firehouse on its
    41
    property as a public use on June 19, 1969, under § 303.1 of the
    Zoning Ordinance. 
    Id. The district
    court explained that the only evidence
    supporting Findings of Fact 5 and 6 (a single 133 foot tower is
    not the only means by which Sprint could correct its service
    problems and there are other solutions for those service
    problems) was the evidence submitted by Karen Beck, an
    objector who appeared before the Zoning Board.         
    Id. She testified
    that Sprint could solve its service problems by
    attaching an antenna to another tall structure in the area or by
    placing a tower somewhere else, but she conceded that she was
    not an expert in telecommunications. 
    Id. Despite her
    lack of
    expertise, she testified about a tower in a neighboring township
    purportedly having a height of 420 feet; 90 feet higher that the
    proposed Sprint tower. 
    Id. Beck also
    submitted pictures of
    some of these structures. She claimed that there was no need
    for the tower described in the Ogden/Sprint application. 
    Id. The district
    court was not convinced by Beck’s testimony
    42
    because there was “no evidence that any of the areas [Beck]
    identified . . . [are] located within one mile of the Ogden
    firehouse, the location where Sprint claims it needs to put a
    WCF antenna in order to close its gaps in service.”            
    Id. Accordingly, it
    found that Findings of Fact 5 and 6 are not
    supported by substantial evidence. 
    Id. The district
    court held that Finding of Fact 10 (a 133 foot
    stand-alone tower will adversely affect the property values of
    the immediately adjacent residential properties) was supported
    only by testimony that the proposed project would lower
    property values of some of the neighbors. 
    Id. at *18.
    That
    testimony was also offered by objectors who testified before the
    Zoning Board. Arthur Sokolove, a spokesman for others living
    near the firehouse, testified about the neighbors’ concerns that
    they will be unable to sell their homes if the tower is built.
    Sokolove testified that he would not have bought his house if
    the proposed tower had been on Ogden’s property. 
    Id. Another objector,
    Linda McDonald, testified about her internet research
    43
    into property values. Her research disclosed that houses in New
    York that were near towers sold for ten to twenty-five percent
    less than houses that were not. 
    Id. McDonald also
    testified that
    she spoke with real estate agents and learned that houses near
    towers take longer to sell and will sell for less when finally sold.
    
    Id. The district
    court was not convinced by McDonald’s
    testimony because she never identified the source of her internet
    research, nor the agents to whom she spoke. Regina Hartney,
    who does not live near the Ogden property, but who once
    worked as a realtor, testified that the vast majority of people
    would not choose to buy a home with a 100 foot tower in their
    backyard if they have a choice. 
    Id. On appeal,
    the Township
    reasserts the value of Hartney’s testimony by describing her as
    “not paid by any party, but an aggrieved party, [who] was
    qualified to give an opinion on the question as to whether a 130
    foot monopole erected on the property adjacent to the homes in
    the neighborhood would negatively impact the value of these
    homes.” Township’s Br. at 25. However, the district court
    44
    noted that Hartney did not take a poll or perform an actual study
    of the impact of a radio tower on the price of nearby homes. 
    Id. Indeed, she
    explicitly admitted: “I’m not trying to tell you that
    I have documented data. Joint Appendix at 342, ZHB Hearing
    at 318-20.
    Given the district court’s rejection of the Zoning Board’s
    findings, the court held that the Board’s denial of the
    application was not supported by substantial evidence in the
    written record. 
    Id. at *19.
    The Township contends that this
    was error and it advances a number of arguments in support of
    that contention. First, the Township argues that the district
    court improperly substituted its judgment for that of the Zoning
    Board in crediting Rudolph’s testimony “that the proposed
    tower would not alter the essential character or essence of the
    neighborhood.” 
    Id. at *15.
    According to the Township, since
    the Zoning Board rejected Rudolph’s testimony on this point,
    the court could not find that he was credible. However, the
    Township’s argument misconstrues what the district court did.
    45
    It did not find Rudolph’s testimony credible. Rather, it simply
    reiterated his testimony. As Ogden/Sprint note, the issue is not
    whether the district court accepted his testimony despite the
    Zoning Board’s rejection of it. The issue is whether there was
    evidence to refute his testimony, and the Township points to
    nothing in the record to refute it on this point. The Township
    simply says that “it defies common sense to conclude that a one
    hundred thirty (130) foot monopole erected adjacent to homes
    in one particular neighborhood would not ‘alter the essential
    character or essence of the neighborhood.’” Township’s Br. at
    24. However, that simplistic approach does not sufficiently
    consider the impact of the existing fire station.
    As noted, the Township granted a special exception to
    Ogden for a “public use” for its fire station almost forty years
    ago under § 303.1 of the Zoning Ordinance, and the Zoning
    Ordinance allows for an accessory use. See 
    n.1, supra
    . As also
    noted, the Zoning Ordinance defines an “accessory use” as “[a]
    use of land or of a building or portion thereof customarily
    46
    incidental and subordinate to the principal use of the land or
    building and located on the same lot with such principal use.”
    Zoning Ordinance, Appendix (i); see also 
    n.2, supra
    . “Once
    something is defined as an accessory use, it is allowed by right.”
    AWACS, Inc. v. Zoning Hearing Bd. of Newtown Twp., 
    702 A.2d 604
    , 607 (Pa. Commw. Ct. 1997) (citation omitted). “In
    order to establish that right, an applicant must prove that the use
    sought is secondary to a principal use and that the use is usually
    found with that principal use.” 
    Id. (citation omitted).
    The
    Zoning Ordinance also provides for, and allows, an “accessory
    structure.” An “accessory structure” is defined as one that is
    “detached from a principal building on the same lot and
    incidental and subordinate to the principal use of the building
    or use.” Zoning Ordinance, Appendix I.B.
    Here, it is clear that the tower is an accessory
    use/structure to Ogden’s firehouse. Robinson, Ogden’s Vice-
    President, explained the relationship of the proposed tower to
    the firehouse:
    47
    Communications are necessary so, essentially,
    this is an accessory use. If you look at
    communications, without it we are nowhere. We
    look upon redundancy in this age, particularly
    this age after 9/11, as critical to emergency
    operations. As a result we have taken action with
    regard to further alerting people through our cell
    phones, regular pagers in addition to fire pagers
    which we found to be inadequate in certain areas.
    So communication is definitely associated with
    any emergency service.10
    App. 288.     Accordingly, the district court quite correctly
    concluded that Ogden’s use of “a radio tower to enhance its
    existing radio-communications system would be an accessory
    use. . . .” Ogden I, 
    2006 WL 851391
    at *8.
    The Township attempts to rely on AWACS, 
    702 A.2d 604
    , in arguing that the district court erred because the radio
    tower is a commercial use that is not accessory to the firehouse
    and therefore should not be allowed.           In AWACS, a
    telecommunications company (Comcast) applied for a building
    permit to install 12 mobile phone antennae on the roof of an 18
    10
    As we noted earlier, there was evidence that the poor
    quality of Ogden’s emergency communications capabilities has
    contributed to two deaths in the past.
    48
    story apartment building. The application was denied as an
    unpermitted use that was not accessory to any permitted use.
    On appeal, the Commonwealth Court agreed stating:
    [T]he principal use of the apartment building on
    which the antennae were to be erected is, of
    course, residential. The use to which Comcast
    would put these antennae is a business use. The
    antennae would serve Comcast’s customers in the
    area, regardless of where they live, not Newtown
    Towers residents alone. In fact, the antennae
    would not necessarily serve any residents of the
    building, unless they chose to become Comcast
    subscribers. In this sense, the antennae are
    unlike, for example, a television antenna on top
    of an apartment building that serves the tenants of
    that building as an incident to their residential
    use. The antennae may be a necessary part of
    Comcast’s business use, but they are in no
    manner incident, subordinate or secondary to
    Newtown Towers’ use, and may even lack a
    connection at all, if no Comcast subscribers
    reside 
    there. 702 A.3d at 607
    . The Township now claims that the proposed
    Ogden/Sprint tower “would not serve members of the fire
    company unless they also subscribed to the available telephone
    services,” and that it is therefore not a use that is incidental to
    49
    the fire house. Township’s Br. at 40. However, this argument
    is once again tethered to the Board’s attempt to ignore the joint
    nature of the Ogden/Sprint application and the Board’s
    insistence on viewing it as an application of Sprint alone.
    Given that analytical entry point, the Board concluded that
    Sprint wanted to erect a stand-alone wireless communications
    tower solely for its own use to provide service to its cellular
    customers.11
    It is, of course, true that Sprint’s antenna is intended to
    provide service to Sprint’s customers rather than being part of
    Ogden’s emergency communication system. However, that is
    where the strained analogy to AWACS ends. It is abundantly
    clear on this record that the radio tower will be used by Ogden
    pursuant to its responsibility as an emergency responder. The
    11
    “‘It is true also of journeys in the law that the place
    you reach depends on the direction you are taking. And so,
    where one comes out on a case depends on where one goes in.’”
    United States v. Sigal, 
    341 F.2d 837
    , 844 (3d Cir. 1965)
    (quoting, United States v. Rabinowitz, 
    339 U.S. 56
    , 69 (1950)
    (Frankfurter, J. dissenting)).
    50
    Zoning Ordinance allows for telecommunications uses in R-2
    Residential Districts by special exception.        See Zoning
    Ordinance § 303.7. As we have already noted, once something
    is defined as an accessory use, it is allowed by right. Because
    the tower is an accessory use, on this record, Sprint can surely
    attach an antenna to it by special exception.
    While it is certainly conceivable that the proposed tower
    could decrease property values, and that such a decrease would
    qualify as reasonably detrimental to the neighborhood, that
    conclusion is not supported by substantial evidence in this
    record. The Township argues that it “should have been given
    the deference to reject whatever unqualified expert testimony
    was given to support the fantastic notion that [the monopole] .
    . . would not impair aesthetics, the character of the
    neighborhood, or negatively affect the desirability or value of
    the property.” Township’s Br. at 26. The Township fails to
    comprehend, however, that it is given deference in the form of
    the substantial evidence standard, but the Township failed to
    51
    clear even this rather low hurdle; rather, it made conclusory
    statements insufficiently buttressed by generalized notions
    offered by poorly qualified witnesses.
    Second, the Township contends that Regina Hartney’s
    testimony constitutes substantial evidence supporting the
    Zoning Board’s denial of the special exceptions. However, as
    noted earlier, Regina Hartney, did not live near the Ogden
    property, but once worked as a realtor. She testified that the
    vast majority of people would not choose to buy a home with a
    100 foot tower in their backyard if they had a choice. The
    district court rejected her testimony and Finding of Fact 10 that
    was based on it. The court explained:
    Generalized concerns about aesthetics and
    property values are not sufficient to satisfy the
    objectors’ duty of presentation. The duty of
    presentation requires [objectors] to establish their
    objection with a ‘high degree of probability, and
    raise specific issues concerning the proposal’s
    general detrimental effect on the community.
    Indeed, the evidence of objectors must show a
    high probability of an adverse impact that will
    pose a substantial threat to the health and safety
    of the community. Mere speculation as to
    52
    possible harm is insufficient. (citations omitted).
    The United States Court of Appeals for the Third
    Circuit has recognized that [a] few generalized
    concerns about a potential decrease in property
    values, especially in light of [the plaintiff]’s
    contradictory expert testimony, does not
    constitute substantial evidence for the purposes of
    § 332(c)(7)(B)(iii) of the TCA.
    Ogden I, 
    2006 WL 851391
    at *18. (citations, quotation marks
    and footnotes omitted) (brackets in original). Thus, the district
    court dismissed the testimony because it amounted to nothing
    more than generalized expressions about aesthetics and
    decreases in property values that did not rise to the level of
    substantial evidence required under the TCA. See Pine Grove
    
    II, 181 F.3d at 409
    (“[A] ‘few generalized expressions of
    concerns with aesthetics cannot serve as substantial evidence’
    and ‘a few generalized concerns about a potential decrease in
    property values . . . does not seem adequate to support a
    conclusion that the permits should be denied.’”) (quoting Oyster
    
    Bay, 166 F.3d at 490
    ).
    The Township cites Omnipoint Commc’ns Enters., L.P.,
    53
    v. Zoning Hearing Bd. of Easttown Twp., 
    72 F. Supp. 2d 512
    ,
    515 (E.D. Pa. 1999), reversed, 
    248 F.3d 101
    (3d Cir. 2001), in
    arguing that zoning decisions linking aesthetics to property
    values are acceptable and appropriate. The court there did say
    that “decisions which link aesthetics to property values . . . are
    acceptable.” However, the court’s analysis was driven by
    traditional zoning considerations under Pennsylvania law. It
    was not considering with the application of the TCA, nor that
    federal statute’s impact on the considerations of land use that
    are otherwise left to local regulation.12
    The Township also cites to AT&T Wireless PCS, Inc. v.
    Winston-Salem Zoning Bd. of Adjustment, 
    172 F.3d 307
    (4th
    Cir. 1999), in which a court of appeals reversed the district
    court’s order granting AT&T’s application for a special use
    12
    One could forcefully argue that the erection of any
    telecommunications equipment would have an adverse impact
    on the aesthetics of any residential community. However, under
    the circumstances here, such an unforgiving and absolutist
    approach local to land use regulation would eviscerate the
    national policy of promoting the telecommunications industry
    that is endemic in the TCA.
    54
    permit to erect a 140 foot monopole despite the local zoning
    authority’s rejection of that application.      The substantial
    evidence on the record supporting the denial there included a
    mortgage banker’s testimony that the tower would adversely
    affect the resale value of the homes surrounding it, and have a
    negative impact on the aesthetics of the community where it
    was planned. To that extent, it appears at first blush that the
    Township’s focus on aesthetics does have some support in cases
    applying the TCA. However, AT&T is easily distinguished.
    In AT&T, the tower was to be erected on private property
    that included a house that was listed on the National Register of
    Historic 
    Places, 172 F.3d at 310
    , and there was “no commercial
    property in the neighborhood nor on the [subject] property.” 
    Id. Moreover, the
    setting was described as “a neighborhood of
    ‘excellent quality of life and      . . tranquility[,]’” and “‘an
    unspoiled serene tract of land in the midst of a bustling city.’”
    
    Id. As the
    court noted, that testimony was offered “not by the
    homeowners or others opposing the special use permit, but by
    55
    AT&T.” 
    Id. There was
    more. Although AT&T argued that it
    needed the tower to address a gap in its wireless service in the
    city, it conceded that “this particular location was not necessary,
    [and that] others would do.” 
    Id. AT&T’s engineers
    admitted
    that they could “co-locate on an existing tower, . . . [or] build
    another monopole tower at another location;” and that either
    option was satisfactory and would “preclude the necessity of
    having a tower on [the subject] property” while “provid[ing] the
    same level of service.” 
    Id. at n1.
    That is simply not our case.
    Given the circumstances here, the district court correctly
    evaluated the generalized testimony regarding aesthetics, the
    fact that the current use included a firehouse, and the need for
    the specific location where Ogden/Sprint were attempting to
    locate the communications tower.13
    Third, the Township contends that the district court
    13
    We do not, of course, suggest that all testimony
    regarding aesthetics is irrelevant under the TCA. We do,
    however, reiterate that the generalized testimony about the
    impact on the aesthetics of the neighborhood on this record is
    not the “substantial evidence” required under the TCA.
    56
    misinterpreted and/or ignored testimony that clearly established
    that Ogden’s property was not the only site that would remedy
    Sprint’s problem. As noted, in Findings of Fact 5 and 6, the
    Zoning Board found:
    5. That a single 133 foot tower is not the only
    means by which Appellant could ameliorate or
    correct its alleged lack of adequate service in the
    area around the Ogden Fire Company.
    6. That there exist other solutions to help
    ameliorate the alleged lack of service other than
    to erect a single 133 foot stand along WCF tower
    at Appellant’s location.
    As we explained earlier, the district court held that the only
    evidence supporting these findings was the testimony of Beck,
    which we have recited above. The court found that testimony
    insufficient to demonstrate that Sprint could solve its
    communications problems by placing an antenna on another tall
    structure or could build a tower elsewhere. The Township
    claims that holding was in error. According to the Township,
    the testimony of Poole, a radio frequency engineer who testified
    for Sprint, demonstrated that Ogden’s property was not the only
    57
    site that could solve Sprint’s coverage problems. We disagree
    with that summary of Poole’s testimony. Poole testified that
    Sprint must have a tower on Ogden’s property to solve its
    coverage problems even if it erected a tower somewhere else.
    The district court summarized the relevant portions of Poole’s
    testimony as follows:
    Clement Poole . . testified regarding studies which
    he performed regarding Sprint's weak wireless
    telecommunications service in the area of
    Naamans Creek Road where the Ogden firehouse
    is located. These studies included testing PCS
    coverage at nearby tall towers to see if Sprint
    could solve its service problems by attaching an
    antenna to an existing tower. (N.T. Vol. 2 at
    150-68.). He determined that the Ogden location
    was the best location. (Id. at 168.) Poole also
    concluded that if Sprint were not permitted to
    attach an antenna to the proposed tower, Sprint
    would have poor to no service in that area. (Id. at
    176.) He further testified that the proposed height
    of Sprint's antenna on the proposed tower is the
    minimum height necessary to alleviate Sprint's
    coverage problems. (Id. at 177.)
    Ogden I, at * 15.
    Finally, the Township contends that Ogden/Sprint did
    58
    not produce any evidence in the application for a special
    exception under Zoning Ordinance § 1706.2, see 
    n.8, supra
    ,
    that the tower had to be 130 feet tall. In support of that claim,
    the Township excerpts portions of the testimony of Ogden’s
    Vice President Robinson. See Township’s Br. at 31. However,
    the Township ignores Robinson’s testimony that 130 feet would
    be less than the optimum height of 150 feet, but would be close
    enough to fill Ogden’s needs. JA at 289. Moreover, the
    Township completely ignores the fact that Poole stated that the
    proposed height of 130 feet was the minimum height necessary
    to fill Sprint’s coverage gap. JA at 313. Moreover, in its
    submissions to the district court, the Township admitted that
    Odgen’s “communications problems cannot be remedied
    without the proposed Facility at the height requested.” JA at
    50.19 (Township’s Motion for Summary Judgment, Facts
    Established at the Hearings, ¶ 34).
    Accordingly, we agree with the district court’s
    conclusion that the Township’s rejection of the Ogden/Sprint
    59
    application is not supported by substantial evidence.
    B. Did the Township Unreasonably Discriminate Among
    Providers of Functionally Equivalent Services?
    As noted at the outset, Count I of Ogden/Sprint’s
    complaint alleged that the Township’s rejection of their
    application unreasonably discriminated among providers of
    functionally equivalent services in violation of 47 U.S.C. §
    332(c)(7)(B)(i)(I). The Township had previously approved an
    application filed jointly by Reliance Hook and Ladder Co. No.
    1 and Metro Phone.      It had also previously approved an
    application to build a telecommunications tower in an R-1
    District filed by AT&T Wireless. The district court granted
    summary judgment to Ogden/Sprint on that claim, finding that
    the “Zoning Board unreasonably discriminated between the
    Ogden/Sprint Application and the prior applications. . .”.
    Ogden I, 
    2006 WL 851391
    at *9. We agree.
    (1). General legal principles
    “The TCA does not prohibit all discrimination against
    60
    providers, only unreasonable discrimination.” Omnipoint
    Commc’ns Enters., L.P. v. Zoning Hearing Bd. of Easttown
    Twp., 
    331 F.3d 386
    , 395 (3d Cir. 2003) (citation omitted).
    Section 332(c)(7)(B)(i)(I) of the TCA provides: “The regulation
    of the placement, construction, and modification of personal
    wireless service facilities by any State or local government or
    instrumentality thereof . . . shall not unreasonably discriminate
    among providers of functionally equivalent services[.]” The test
    for unreasonable discrimination under the TCA consists of two
    prongs. Nextel West 
    Corp., 282 F.3d at 266
    . “[T]he first prong
    asks whether the relevant providers are ‘functionally
    equivalent.’” 
    Id. (quoting 47
    U.S.C. § 332(c)(7)(B)(i). This
    inquiry focuses on “the telecommunications services the entity
    provides, not on the technical particularities (design,
    technology, or frequency) of its operations. 
    Id. at 267
    n.13. If
    the providers are “functionally equivalent,” the “second prong
    asks   whether    the   governmental     body    ‘unreasonably
    discriminate[d] among providers.’” 
    Id. at 267
    (quoting 47
    61
    U.S.C. § 332(c)(7)(B)(i)).
    Relief under the discrimination provision “will require
    a showing that the other provider is similarly situated, i.e., that
    the structure, placement or cumulative impact’ of the existing
    facilities makes them as or more intrusive than the proposed
    facility.” ATP Pittsburgh Ltd P’ship v. Penn Twp., 
    196 F.3d 469
    , 480 n.7 (1999). “Discrimination may be impermissible
    where a municipality favors one provider by permitting it to
    locate in a particular area at the exclusion of others, thereby
    creating unfair competitive advantage.” Nextel West 
    Corp., 282 F.3d at 267
    .
    (2). The Reliance/Metro Phone application
    On April 1, 1992, the Zoning Board approved the joint
    application that Reliance Hook and Ladder Co. No. 1 and
    AWACS, Inc., d/b/a Metro Phone Co., submitted for a special
    exception. That application had obvious similarities to the one
    Ogden/Sprint submitted. The exception the Board granted there
    allowed     Metro   Phone     to    install and   operate    radio
    62
    communications equipment in the basement of Reliance’s
    firehouse and to construct a 180 foot high radio
    communications tower with antennae in the rear of the
    firehouse. Like Ogden, Reliance is located in an R-2 Residential
    District.
    In granting the special exception, the Zoning Board
    made the following findings: (1) this use was an accessory use
    to the fire company use and the tower was an accessory
    structure to the firehouse building, thus requiring special
    exceptions to use and height limitations; (2) the tower and
    radio communications equipment would facilitate Metro
    Phone’s cellular communications system, which had a dead spot
    in the area of the tower; (3) a tower with a minimum height of
    180 feet was required to provide proper coverage to the service
    area; (4) the base of the 180 foot tower would be 20 feet in
    diameter, tapering to 48 inches at the top; and, (5) the proposed
    tower would provide Reliance with a back-up communications
    system and, therefore, benefit Reliance’s volunteer firefighting
    63
    activities and provide 911 service for Metro Phone’s
    subscribers.
    The Zoning Board also found that the cellular phone
    communication service was an accessory use to the volunteer
    fire company and that the tower was an accessory use to the
    firehouse because the fire company had to depend on radio
    communications. The proposed cellular phone communication
    service provided a back-up communication for Reliance and
    911 service to the cellular subscribers, and allowed the county
    to place its emergency service equipment on the proposed
    tower. Accordingly, the Zoning Board granted the special
    exception to Reliance/Metro Phone pursuant to Zoning
    Ordinance § 1706.2. The application was approved prior to the
    Township’s adoption of Ordinance No. 579.14
    14
    On November 17, 1997, the Township adopted
    Ordinance No. 579, which amended the Township Code to
    provide for the use, construction and siting of WCFs.
    Ordinance No. 579 amended § 303 of the Zoning Ordinance to
    permit “WCF with antenna attached to a nonresidential building
    or structure of a permitted church, educational, public,
    municipal or governmental building or facility” as a special
    64
    In granting summary judgment to Ogden/Sprint on
    Count I, the district court concluded that Ogden would use the
    radio tower in its capacity as an emergency responder. That use
    would enhance Ogden’s existing radio communications and it
    was therefore an “accessory use not a commercial use as the
    Township claimed.” Ogden I, 
    2006 WL 851391
    at *8. The
    Township argued that the differential treatment afforded
    Reliance/Metro Phone and Ogden/Sprint was not unreasonable
    because the Reliance/Metro Phone application was approved
    before Ordinance No. 579. That argument is a non sequitur,
    and the district court properly rejected it because Ordinance No.
    579 regulates the use, construction and siting of a WCF tower.
    The ordinance has nothing to do with deciding whether a radio
    tower is an accessory use to a firehouse. Moreover, rather than
    complicating Ogden/Sprint’s request for an accessory use,
    exception in R-2 Residential Districts. Zoning Ordinance §
    303.7. Ogden/Sprint sought a special exception because the 15
    foot height limitation imposed under § 1706.2 would otherwise
    have precluded erecting a 130 foot tower.
    65
    Ordinance No. 579 should have facilitated it.         Thus, the
    enactment of Ordinance No. 579 does not explain why the
    Township rejected Ogden/Sprint’s application while approving
    the application of Reliance/Metro Phone.        
    Id. Here, the
    Township repeats the argument that it made in the district court
    about Ordinance No. 579. However, the argument is based on
    the improper characterization of the application as one filed
    solely by Sprint to construct a stand-alone WCF tower. The
    district court’s holding that the Township could not rely upon
    Ordinance No. 579 to justify the discrimination was correct.
    The district court also rejected the Township’s attempt
    to claim that the two applications were not functionally
    equivalent because the proposed Ogden/Sprint tower would
    have a greater impact on the surrounding community. The
    Township argued that the area around the Reliance firehouse
    when the Reliance/Metrophone application was approved was
    very rural while the area around Ogden’s property is heavily
    residential. The district court found to the contrary, noting:
    66
    [T]he aerial photographs submitted by the parties
    do not support [the Township’s] contention that
    the area around the Reliance firehouse was quite
    rural in 1990. To the contrary, those photographs
    show that the area around the Reliance firehouse
    contained a school and a sizeable residential
    community in 1990.
    
    Id. The Township
    also repeats its reliance on the distinction
    purportedly shown in the aerial photos here. However, our
    review of those photographs is consistent with the findings of
    the district court.
    Accordingly, the district court correctly held that
    Ogden/Sprint satisfied the first prong of the unreasonable
    discrimination test by establishing that although Metro Phone,
    like Sprint, is a provider of wireless communications services,
    it was treated differently than Sprint.
    The district court ruled that Ogden/Sprint satisfied the
    second prong of the unreasonable discrimination test “by
    demonstrating that the structure, placement or cumulative
    impact of the existing Reliance/Metro Phone facility makes it
    more intrusive than the proposed Ogden/Sprint tower.” 
    Id. 67 The
    “Reliance/Metro Phone tower is both larger in diameter and
    significantly taller than the proposed Ogden/Sprint tower and .
    . . the neighborhoods are residential neighborhoods with
    identical zoning.” 
    Id. On this
    record, the conclusion that the Zoning Board
    unreasonably    discriminated      against   the   Ogden/Sprint
    application compared to its earlier treatment of the
    Reliance/Metro application is inescapable.
    (3). The AT&T Wireless application
    AT&T Wireless also provides wireless communication
    services. On November 1, 2000, after Ordinance No. 579 was
    adopted,15 the Zoning Board approved an application submitted
    by AT&T Wireless. AT&T requested approval of a planned
    180 foot monopole tower to be operated as a PCS cell tower
    antenna on land owned by the Township in an R-1 Low Density
    15
    We stress the timing because of the Township’s
    attempt to suggest that the enactment of Ordinance 579
    somehow justifies the disparate treatment afforded the
    Reliance/Metro application.
    68
    Residential District.
    The Zoning Board approved AT&T’s application for a
    stand-alone WCF after concluding that it was compatible with
    the character of the surrounding neighborhood and in the best
    interest of the Township, convenience of the community and the
    public health, safety and welfare.    The Zoning Board also
    concluded that allowing this special exception would not
    adversely affect the public health, safety and welfare and would
    be in accordance with the Upper Chichester Comprehensive
    Plan.
    In granting summary judgment to Ogden/Sprint, the
    district court observed that the Township had submitted no
    evidence to justify denying Ogden/Sprint’s application while
    approving AT&T’s application. Accordingly, the court held
    that Ogden/Sprint met the first prong of the unreasonable
    discrimination test by showing that it and AT&T are
    functionally equivalent providers. 
    Id. The court
    also held that
    Ogden/Spring met the second prong of the unreasonable
    69
    discrimination test “with respect to the AT&T application by
    demonstrating that the AT&T tower is more intrusive than the
    proposed Ogden/Sprint tower because the AT&T tower is 47
    feet higher than the proposed Ogden/Sprint tower.” 
    Id. Although there
    are some differences between the
    placement of the two towers (the Ogden/Sprint in a R-2 zone,
    and the AT&T in a R-1 zone), since the AT&T pole is much
    higher than the proposed Ogden/Sprint pole, and given the
    Zoning Board’s complete failure to explain why it was willing
    to ignore Ordinance 579 when granting AT&T approval, the
    approval of    the   AT&T application        further supports
    Ogden/Sprint’s claim of unreasonable discrimination.
    V. TOWNSHIP’S APPEAL NO. 07-1694
    As recited at the outset, after the district court granted
    summary judgment to Ogden and Sprint on their claims under
    the TCA, the Zoning Board granted the special exceptions
    Ogden and Sprint were requesting. However, the Township’s
    building inspector thereafter refused to give Ogden/Sprint the
    70
    building permit that was purportedly required before they could
    construct the monopole.      The denial was based upon the
    building inspector’s determination that the lease of the relevant
    portion of Ogden’s rear yard to Sprint for construction of the
    tower constituted a division or allocation of land by means of a
    leasehold. That, in turn, purportedly required the approval of a
    Subdivision and Land Development Application pursuant to the
    Township’s Subdivision and Land Development Ordinance and
    Section 107(a) of the Pennsylvania Municipalities Planning
    Code (“MPC”).
    Apparently not feeling particularly upbeat about again
    trying to survive this administrative gauntlet or their chances of
    getting past the building inspector, Ogden/Sprint returned to
    district court rather than attempt to negotiate the bureaucratic
    rapids cascading between the Zoning Board and the final
    completion of the project. They asked the court to compel the
    issuance of a building permit. Since nothing in the record
    supported the Township’s denial of a Subdivision and Land
    71
    Development Application or the issuance of a building permit,
    the district court ordered the Township to issue the appropriate
    permits for the building of the radio tower and related radio
    equipment, and the Township appealed.
    A. DISCUSSION
    The Township’s first argument is that the district court’s
    order compelling it to issue all necessary approvals and permits
    for the building of the tower, impermissibly expanded the scope
    of its March 30, 2006 order granting summary judgment to
    Ogden/Sprint and ordering the Township to issue zoning
    permits for the tower. As we understand the Township’s
    argument, the Township is claiming that although the TCA
    places limits on a local governmental unit’s zoning authority,
    (i.e., its authority to regulate use of land), the TCA has nothing
    to do with a local governmental unit’s subdivision authority,
    i.e., its authority to regulate land development. Accordingly,
    the Township argues that the district court improperly intruded
    into an area that is strictly a matter of local law in ordering
    72
    building permits for the tower. Thus, the Township claims that
    Ogden/Sprint must submit an application for subdivision/land
    development approval before it can go forward with its project
    even if the district court was correct in ordering the Township
    to issue the zoning approvals.
    The argument is unavailing. It would allow an end run
    around the requirements of the TCA and thereby allow local
    regulatory agencies to subvert a federal policy by elevating
    zoning authority over congressional policy as enacted into law
    via the TCA. In City of Rancho Palos Verdes v. Abrams, 
    544 U.S. 113
    (2005), the Supreme Court explained that
    Congress enacted the Telecommunications Act of
    1996 (TCA), to promote competition and higher
    quality in American telecommunications services
    and to “encourage the rapid deployment of new
    telecommunications technologies.” One of the
    means by which it sought to accomplish these
    goals was reduction of the impediments imposed
    by local governments upon the installation of
    facilities for wireless communications, such as
    antenna towers. To this end, the TCA amended
    the Communications Act of 1934, to include §
    332(c)(7), which imposes specific limitations on
    the traditional authority of state and local
    73
    governments to regulate the location,
    construction, and modification of such facilities.
    
    Id. at 115-16
    (citations omitted). The Township’s position, if
    sustained, would be fatal to telecommunication carriers
    attempting to build facilities in localities that did not want to
    allow it. It would merely shift the battle from the zoning agency
    to another agency charged with subdivision approval whenever
    the relationship between the carrier and the owner of the
    affected land could be viewed as falling under the jurisdiction
    of the latter agency.    It would then remove the reach and
    protection of the TCA from the telecommunications provider
    and place the provider at the mercy of local regulators. Even if
    the local jurisdiction ultimately granted approval, the attendant
    delay, expense and uncertainty could adversely impact the
    provider’s attempt to construct telecommunications facilities
    and subvert the national policy favoring it.16
    16
    We note that the TCA expressly commands that any
    court hearing an action filed by a person adversely affected by
    a decision of a state or local governmental agency that is
    inconsistent with the TCA is to “hear and decide such action on
    74
    Indeed, the Township here is not arguing that
    Ogden/Sprint would not or should not ultimately obtain
    subdivision approval. Rather, the Township appears simply to
    want Ogden/Sprint to jump through the prescribed hurdles on
    its way to ultimate approval. However, as Ogden/Sprint note,
    it would be a pointless exercise to submit a subdivision
    application now because the district court has already
    determined, as a matter of federal law, that the Township must
    permit the tower to be built on Ogden’s property. We conclude
    that the court properly ordered the issuance of the building
    permits as a supplemental remedy to the Township’s violation
    of the TCA. See Omnipoint Corp. v. Zoning Hearing Board of
    Pine Grove Township, 
    20 F. Supp. 2d 875
    (E.D. Pa. 1998)
    (“Pine Grove I”), aff’d 
    181 F.3d 403
    (“Pine Grove II”).17
    an expedited basis.” 47 U.S.C. § 332(c)(7)(B)(v). Congress
    has thus recognized the need to avoid costly and unnecessary
    delays during the approval process before local agencies.
    17
    In Pine Grove I, the district court found the zoning
    board’s denial of a special exception for a wireless
    communications facility was in violation of the TCA. It
    75
    The Township also argues that because subdivision
    issues are matters solely of state law, we must abstain pursuant
    to Burford v. Sun Oil Co., 
    319 U.S. 315
    (1943).18          This
    argument borders on frivolity and requires only the briefest
    discussion. “Burford abstention is appropriate where a difficult
    question of state law is presented which involves important
    state policies or administrative concerns.” Heritage Farms, Inc.
    v. Solebury Twp, 
    671 F.2d 743
    , 746 (3d Cir. 1982) (citation
    omitted). However, there is no difficult question of state law
    here. Rather, the controlling issue is one of federal law. The
    issue is whether the denial of the building permits violates the
    TCA. We agree with the district court’s conclusion that it does.
    considered remanding for further administrative proceedings,
    but concluded that doing so “would frustrate the TCA’s intent
    to provide aggrieved parties full relief on an expedited 
    basis.” 20 F. Supp. 2d at 881
    . Accordingly, it ordered the following
    relief: “The Zoning Officer of Pine Grove Township is hereby
    ORDERED to issue all necessary zoning and building permits
    upon payment of any outstanding fees.” 
    Id. at 882
    (emphasis
    added). We 
    affirmed. 181 F.3d at 410
    .
    18
    The Township did not ask the district court to abstain
    under Burford.
    76
    One matter remains. As recited, the district court noted
    that, under Pennsylvania law, leases that allocate land, as
    opposed to assigning positions on a pole or tower, constitute a
    subdivision or allocation of land in accordance with § 107(a) of
    the MPC. Ogden II, 
    2007 WL 137848
    at *2 (citing Upper
    Southampton Twp. v. Upper Southampton Twp. Zoning
    Hearing Bd., 
    885 A.2d 85
    , 92 (Pa. Commw. Ct. 2005), appeal
    granted, 
    895 A.2d 1265
    (Pa. 2006)). Ogden/Sprint contend that
    it is not all that clear that Pennsylvania law would require
    subdivision approval even in the absence of the TCA. They
    argue that since the Pennsylvania Supreme Court has granted
    leave to appeal the decision in Upper Southampton, there is not
    yet a definitive ruling on that issue under Pennsylvania law.19
    19
    Ogden/Sprint also distinguish Upper Southampton by
    stressing that the Commonwealth Court was there concerned
    with interests in a billboard. They suggest the rationale would
    not apply here because (1) Ogden will occupy both the
    firehouse and the tower, and (2) the tower is an accessory use to
    the firehouse, not a separate business use. See Ogden/Sprint
    Supplemental Br. at 11 
    (citing 885 A.2d at 88
    ).
    77
    However, we need not resolve that issue because our inquiry is
    limited to whether the district court’s order requiring the
    Township to issue building permits for the tower is appropriate
    supplemental and additional relief under federal law for a
    violation of the TCA. We hold that it is.
    VI. CONCLUSION
    For all of the above reasons, the district court’s order of
    March 30, 2006, ordering the Township to issue all required
    zoning permits and variances, and the order of February 15,
    2007, ordering the issuance of any required Building Permits
    will be affirmed.
    78
    

Document Info

Docket Number: 06-2297

Filed Date: 10/4/2007

Precedential Status: Non-Precedential

Modified Date: 10/13/2015

Authorities (23)

National Tower, LLC v. Plainville Zoning Board of Appeals , 297 F.3d 14 ( 2002 )

Cellular Telephone Company, Doing Business as at & T ... , 166 F.3d 490 ( 1999 )

United States v. Meger Sigal, United States of America v. ... , 341 F.2d 837 ( 1965 )

Omnipoint Communications Enterprises, L.P., in No. 99-1990 ... , 248 F.3d 101 ( 2001 )

omnipoint-corporation-linda-genth-v-zoning-hearing-board-of-pine-grove , 181 F.3d 403 ( 1999 )

Anna M. Jensen v. Jack E. Potter, Postmaster General Us ... , 435 F.3d 444 ( 2006 )

nextel-west-corp-a-delaware-corporation-dba-nextel-communications-v , 282 F.3d 257 ( 2002 )

Omnipoint Communications Enterprises, L.P. v. Zoning ... , 331 F.3d 386 ( 2003 )

Upper Southampton Tp. v. Upper Southampton Tp. Zoning ... , 895 A.2d 1265 ( 2006 )

apt-pittsburgh-limited-partnership-in-no-98-3546-v-penn-township-butler , 196 F.3d 469 ( 1999 )

at-t-wireless-pcs-incorporated-v-the-winston-salem-zoning-board-of , 172 F.3d 307 ( 1999 )

heritage-farms-inc-heritage-farm-partnership-concept-plus-inc-and , 671 F.2d 743 ( 1982 )

the-delaware-nation-a-federally-recognized-indian-tribe-in-its-own-name , 446 F.3d 410 ( 2006 )

Relosky v. Sacco , 514 Pa. 339 ( 1987 )

Burford v. Sun Oil Co. , 63 S. Ct. 1098 ( 1943 )

Upper Southampton Township v. Upper Southampton Township ... , 885 A.2d 85 ( 2005 )

Frederick v. Zoning Hearing Board of Conewago Township , 713 A.2d 139 ( 1998 )

In Re Appeal of Brickstone Realty Corp. , 789 A.2d 333 ( 2001 )

Omnipoint Communications Enterprises, L.P. v. Zoning ... , 72 F. Supp. 2d 512 ( 1999 )

Omnipoint Corp. v. Zoning Hearing Board of Pine Grove ... , 20 F. Supp. 2d 875 ( 1998 )

View All Authorities »