Bering Strait Citiz v. Usace , 524 F.3d 938 ( 2008 )


Menu:
  •                   FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    BERING STRAIT CITIZENS FOR              
    RESPONSIBLE RESOURCE
    DEVELOPMENT; SUSAN STEINACHER;
    JANA VARRATI,
    Plaintiffs-Appellants,         No. 07-35506
    v.
           D.C. No.
    CV-07-00057-RRB
    UNITED STATES ARMY CORPS OF
    ENGINEERS; KEVIN J. WILSON,                    OPINION
    District Engineer, U.S. Army
    Corps of Engineers; ALASKA GOLD
    COMPANY,
    Defendants-Appellees.
    
    Appeal from the United States District Court
    for the District of Alaska
    Ralph R. Beistline, District Judge, Presiding
    Argued and Submitted
    September 26, 2007—Seattle, Washington
    Filed January 3, 2008
    Before: Betty B. Fletcher, Andrew J. Kleinfeld, and
    Ronald M. Gould, Circuit Judges.
    Opinion by Judge Gould
    59
    64            BERING STRAIT CITIZENS v. USACE
    COUNSEL
    Victoria Clark, Brian Litmans, Trustees for Alaska, Anchor-
    age, Alaska; Roger Flynn, Jeffrey C. Parsons, Western Min-
    ing Action Project, Lyons, Colorado, for plaintiffs-appellants
    Bering Strait Citizens for Responsible Resource Develop-
    ment, Susan Steinacher and Jana Varrati.
    Ronald J. Tenpas, Acting Assistant Attorney General, Ryan
    D. Nelson, Deputy Assistant Attorney General, Dean K.
    Dunsmore, Luther L. Hajek, Daniel Pinkston, Jennifer L.
    Scheller, Lisa E. Jones, Attorneys, United States Department
    BERING STRAIT CITIZENS v. USACE               65
    of Justice, Environment & Natural Resources Division, Wash-
    ington, D.C., for defendant-appellees United States Army
    Corps of Engineers and Colonel Kevin J. Wilson.
    Michael A. Grisham, Dorsey & Whitney LLP, Anchorage,
    Alaska, for defendant-intervenor Alaska Gold Company.
    OPINION
    GOULD, Circuit Judge:
    This appeal concerns a permit issued to Defendant-
    Appellee Alaska Gold Company (“AGC”), by Defendant-
    Appellee Army Corps of Engineers (“the Corps”) for a major
    gold-mining project near Nome, Alaska. The permit was
    issued pursuant to Section 404 of the Clean Water Act
    (“CWA”), 
    33 U.S.C. § 1344
    , which authorizes the Corps to
    issue permits for the discharge of dredged or fill material into
    the navigable waters of the United States.
    The project, known as the “Rock Creek Mine Project,”
    would consist of two open-pit gold mines at separate locations
    outside of Nome, plus facilities built for recovering and pro-
    cessing gold ore. Once the project is commenced, about
    15,592,411 cubic yards of fill from the mine will be placed in
    wetlands totaling 346.5 acres.
    Plaintiffs-Appellants Bering Strait Citizens for Responsible
    Resource Development, Susan Steinacher, and Jana Varrati
    (collectively, “BSC”), allege that the Corps violated the CWA
    and the National Environmental Policy Act (“NEPA”) by
    granting a permit for the Rock Creek Mine Project. BSC
    appeals the district court’s denial of its motion for a tempo-
    rary restraining order and a preliminary injunction, and the
    district court’s dismissal of the suit on summary judgment.
    We conclude that the Corps complied with the requirements
    66             BERING STRAIT CITIZENS v. USACE
    of the CWA and NEPA, and affirm the judgment of the dis-
    trict court.
    I
    A
    The Rock Creek Mine Project is a project of Defendant-
    Appellee AGC. It has a projected life of four to five years and
    is expected to process 7,000 tons of gold ore per day when
    operable. The complete project consists of two sites. The first,
    the “Rock Creek Mine/Mill,” lies six miles north of Nome,
    Alaska in the Snake River watershed. When completed, the
    Rock Creek Mine/Mill site would consist of a fifty-acre open
    pit gold mine, a gold recovery plant, a paste tailings storage
    facility, two non-acid generating development rock stockpiles,
    a facility for crushing and processing the gold ore, and build-
    ings used for storage and maintenance purposes.
    The second facility, the “Big Hurrah Mine,” lies 42 miles
    east of Nome, Alaska. When completed, the Big Hurrah Mine
    would consist of a 22-acre open pit gold mine, ore stockpiles,
    and additional buildings for storage and maintenance pur-
    poses. Ore from the Big Hurrah Mine would be trucked to the
    Rock Creek Mine/Mill site for processing, so the Big Hurrah
    Mine would not include processing or tailings storage facili-
    ties. Both sites are controlled by AGC, through outright own-
    ership or through leases from local Native corporations.
    The sites of both the Rock Creek Mine/Mill and the Big
    Hurrah Mine were historically mined and contain debris and
    tailing piles from earlier mining activities. At the Rock Creek
    Mine/Mill site, rock stockpiles from previous mining opera-
    tions now occupy 62 acres of wetlands. At the Big Hurrah
    Mine, the area that would become the open pit mine at this
    time contains tailings from previous gold mining activities,
    and Big Hurrah Creek (adjacent to the Big Hurrah Mine) con-
    BERING STRAIT CITIZENS v. USACE                  67
    tains tailings that have diverted the creek from its natural
    path.
    Both sites figured prominently in Alaska’s early “gold
    rush” history, commencing late in the nineteenth century.
    Technological advances and current gold prices have rendered
    the mining claims economic once more, and impelled the
    evaluation of prospective development combined with reha-
    bilitation of the sites. The Corps and AGC hope for an eco-
    nomic advantage and environmental improvement as a result.
    AGC observes that Nome has unemployment rates over twice
    the state average and that the region currently offers limited
    opportunities for economic development, and the Corps con-
    sidered the region’s economic conditions when assessing the
    permit.
    The construction and operation of the Rock Creek Mine
    Project will result in the permanent destruction of 346.5 acres
    of existing wetlands. Most of these wetlands are located at the
    Rock Creek Mine/Mill site, where two rock stockpiles, the
    tailings storage facility, and other facilities would be con-
    structed in existing wetlands. Development of the Big Hurrah
    Mine would destroy five acres of existing wetlands to widen
    and improve the existing road to the Big Hurrah Mine.
    The permit issued by the Corps requires measures to miti-
    gate environmental damage from this project and earlier min-
    ing activities at the sites. At the Rock Creek Mine/Mill, these
    measures include the removal of the rock stockpiles from
    existing wetlands for placement in newly-constructed storage
    facilities, the reclamation of wetlands disturbed by previously
    constructed water-management systems, and the conversion
    of the mining pit to a pit lake (i.e. the mining pit will be filled
    with water). At the Big Hurrah Mine, these measures include
    the use of historic waste rock for improvements to the Big
    Hurrah access road, the removal of tailings from the Big Hur-
    rah Creek flood plain to restore the natural flow of the creek,
    and the conversion of the mining pit to a pit lake. The Corps
    68             BERING STRAIT CITIZENS v. USACE
    calculates that these mitigation measures will result in the rec-
    lamation of 106 acres of previously-disturbed wetlands and
    the creation of 70 acres of new wetlands. Taking these mitiga-
    tion measures into account, the Rock Creek Mining Project
    will result in a net loss of 170.5 acres of wetlands.
    B
    AGC applied for a permit from the Corps for the Rock
    Creek Mine Project in May, 2006. The Corps posted a public
    notice describing the project on its website on June 1, 2006.
    The notice included information about a public meeting to be
    held in Nome on June 26, 2006, and the notice was delivered
    in electronic or hard-copy format to federal, state, and local
    agencies, the community of Native Alaskans residing in or
    near Nome, the City of Nome, the neighboring community of
    Solomon, adjacent property owners, the Nome Postmaster,
    and any member of the community who requested a copy.
    In response to the Corps’ request for comment, the Envi-
    ronmental Protection Agency (“EPA”) requested a thirty-day
    extension of the comment period. The Corps responded by
    granting a twenty-day extension. EPA said that it did not have
    sufficient information to conclude that the project met the
    requirements of the CWA. Specifically, EPA argued that the
    project did not appear to be the least damaging practicable
    alternative, that information regarding mitigation measures
    and the closure of the site provided by AGC was incomplete,
    that the Corps had not adequately considered the cumulative
    effects of all potential mining activities in the area, and that
    the project did not adequately consider naturally-occurring
    damage to wetlands in the area. EPA’s response also included
    a list of seven conditions that it wanted included in any permit
    for the project.
    The U.S. Fish and Wildlife Service (“USFWS”) joined
    EPA’s request for an extension of the comment period and
    gave proposed conditions to be added to the permit. Along
    BERING STRAIT CITIZENS v. USACE                        69
    with a series of highly specific site-design conditions,1
    USFWS proposed a permit condition that requires AGC to
    “work with the Corps, the [USFWS], the EPA, and the
    [Alaska Department of Natural Resources] to identify addi-
    tional mitigation opportunities in the project area that will
    benefit birds.”
    Local agencies, organizations, and individuals also
    responded to the request for comment. The City of Nome2
    asked for additional study of the project. Business organiza-
    tions, including the Nome Chamber of Commerce, supported
    the project, while many scientific and environmental organi-
    zations opposed the project or requested additional study.3 In
    addition to these agencies and organizations, thirty-four com-
    panies and forty-five individuals wrote in support of the proj-
    ect, while seven individuals opposed it.
    In August, 2006, the Corps issued a permit for the Rock
    Creek Mine Project. Thereafter, Plaintiff-Appellants BSC
    filed suit in the United States District Court for the District of
    Alaska challenging the permit. In December 2006, the Corps
    withdrew the permit, informing AGC that the Corps needed
    additional time to confirm that the Permit Evaluation and
    Decision Document (“PEDD”)—the document on which per-
    1
    For example, condition three concerns the culvert size used in the con-
    struction of the mine access road, and condition 6 concerns the use of
    “bird diverter devices” on power lines in the project area.
    2
    The City of Nome, Alaska has a population of about 3,500 people.
    3
    The Resource Development Counsel and the Alaska Miners Associa-
    tion, Inc. both supported the project on account of its expected economic
    benefits. The Center for Science and Public Participation expressed con-
    cerns about the reclamation plan for the project and made specific recom-
    mendations about the reclamation plan. Trustees for Alaska, on behalf of
    the Northern Alaska Environmental Center, the Alaska Center for the
    Environment, and others, argued that the Corps’ public notice procedures
    were inadequate and that the environmental impacts of the project were
    both understated and more significant than the economic benefits of the
    project.
    70             BERING STRAIT CITIZENS v. USACE
    mitting decisions are based—was factually complete, accu-
    rate, and consistent with applicable law. The Corps then
    moved for a voluntary remand, which the district court
    granted.
    C
    In February 2007, the Corps issued a revised PEDD for the
    Rock Creek Mine Project. The revised PEDD reviewed the
    comments received on the project, the environmental conse-
    quences of the project, and the alternative project designs con-
    sidered. The Corps adopted the seven conditions proposed by
    the EPA, but dismissed the EPA’s concerns about the analysis
    of alternatives, cumulative impacts, and natural events. The
    Corps also adopted USFWS’s recommendations, including
    the requirement that AGC discuss additional mitigation
    opportunities with the Corps and USFWS after the project is
    underway. An Environmental Assessment (“EA”) and a
    “Finding of No Significant Impact (“FONSI”) are also
    included in the PEDD pursuant to 
    40 C.F.R. § 1508.9
    .
    Because of the FONSI, the Corps determined that it was not
    required to prepare an Environmental Impact Statement
    (“EIS”) for the project.
    On March 13, 2007, the Corps issued a new permit for the
    project. On April 18, 2007, BSC filed a second complaint in
    the district court challenging the Rock Creek Project and
    seeking a preliminary injunction and a temporary restraining
    order to prevent the project from moving forward. The district
    court denied the motions for a preliminary injunction and for
    a temporary restraining order, and dismissed the suit with
    prejudice in a June 8, 2007, opinion. The district court con-
    cluded that the Corps properly considered the relevant factors
    required under the CWA and NEPA, and that it was unlikely
    that additional study would have changed the Corps’ view on
    the project. Also, the district court concluded that no injunc-
    tive relief was justified because most of the relevant wetlands
    were filled during the weeks that passed between the Corps’
    BERING STRAIT CITIZENS v. USACE                        71
    issuance of the second permit and the filing of BSC’s second
    complaint.
    On June 14, 2007, the district court issued an amended
    opinion clarifying its intention to convert the plaintiffs’
    motion for a temporary injunction and for a temporary
    restraining order into a motion for summary judgment, and
    correcting a factual error in the June 8, 2006 opinion.4
    On July 5, 2007, BSC filed an emergency motion for an
    injunction pending appeal. That motion was denied on July
    27, 2007. This appeal followed.
    II
    We review de novo a district court’s decision to grant sum-
    mary judgment. Blue Mtns. Biodiversity Proj. v. Blackwood,
    
    161 F.3d 1208
    , 1211 (9th Cir. 1998). The Corps’ factual
    determinations are reviewed under the arbitrary and capri-
    cious standard. See Friends of the Earth v. Hintz, 
    800 F.2d 822
    , 831 (9th Cir. 1986) (addressing Clean Water Act
    claims); Nw. Env’tl Def. Ctr. v. Bonneville Power Admin., 
    117 F.3d 1520
    , 1536 (9th Cir. 1997) (addressing NEPA claims).
    III
    [1] The permit at the center of this dispute was issued by
    the Corps pursuant to Section 404 of the CWA, 
    33 U.S.C. § 1344
    , which authorizes the Corps to issue permits for the
    discharge of dredged or fill material into the navigable waters
    of the United States if certain conditions are met. 
    33 U.S.C. § 1344
    (d). “The Section 404 permit process is governed
    simultaneously by Corps Regulations, 33 C.F.R. Parts 320-29,
    4
    The June 8, 2007 opinion stated that “the draft EA was distributed to
    the agencies involved and distributed on the web.” In fact, none of the par-
    ties claim that a draft EA was circulated before the second PEDD and the
    EA were complete. This was corrected in the amended opinion.
    72              BERING STRAIT CITIZENS v. USACE
    and by EPA guidelines, 40 C.F.R. Part 230. Both sets of rules
    must be observed.” Hintz, 800 F.2d at 829.
    [2] The Section 404 permitting process is also governed by
    NEPA. NEPA was enacted in pursuit of two objectives:
    “First, it places upon an agency the obligation to consider
    every significant aspect of the environmental impact of a pro-
    posed action. Second, it ensures that the agency will inform
    the public that it has indeed considered environmental con-
    cerns in its decisionmaking process.” Baltimore Gas & Elec.
    Co. v. Nat’l Res. Def. Coun., Inc., 
    462 U.S. 87
    , 97 (1983)
    (internal citations and quotation marks omitted). Unlike the
    CWA, NEPA does not contain substantive environmental
    standards, nor does the Act mandate that agencies achieve
    particular substantive environmental results. Ctr. for Biologi-
    cal Diversity v. U.S. Forest Serv., 
    349 F.3d 1157
    , 1166 (9th
    Cir. 2003). Judicial review of agency decision-making under
    NEPA is limited to the question of whether the agency took
    a “hard look” at the proposed action as required by a strict
    reading of NEPA’s procedural requirements. Churchill
    County v. Norton, 
    276 F.3d 1060
    , 1072 (9th Cir. 2001).
    IV
    We first address BSC’s claims under the CWA.
    A
    1
    [3] A key issue under the CWA presented by BSC is
    whether the Corps adequately considered practicable alterna-
    tives to the Rock Creek Mining Project design that was ulti-
    mately approved. 
    40 C.F.R. § 230.10
    (a) provides that “no
    discharge of dredged or fill material shall be permitted if there
    is a practicable alternative to the proposed discharge which
    would have less adverse impact on the aquatic ecosystem, so
    long as the alternative does not have other significant adverse
    BERING STRAIT CITIZENS v. USACE                73
    environmental consequences.” A practicable alternative is one
    that is “available and capable of being done after taking into
    consideration cost, existing technology, and logistics in light
    of overall project purposes.” 
    Id.
     “In evaluating whether a
    given alternative site is practicable, the Corps may legiti-
    mately consider such facts as cost to the applicant and logis-
    tics. In addition, the Corps has a duty to consider the
    applicant’s purpose.” Sylvester v. U.S. Army Corps of Engi-
    neers, 
    882 F.2d 407
    , 409 (9th Cir. 1989) (citation omitted).
    [4] Where a proposed project does not require access to
    water, i.e., it is not “water dependent,” the availability of
    practicable alternatives is presumed. 
    40 C.F.R. § 230.10
    (a)(3).
    The parties agree that the Rock Creek Mining Project is not
    water dependent.
    [5] The record shows that the Corps extensively and prop-
    erly considered alternatives to the design of the Rock Creek
    Mining Project that was ultimately approved. The PEDD
    reflects the Corps consideration of 24 different alternatives,
    including different placements of the mine pits and related
    facilities, alternative designs for the pits and tailings storage
    facilities, “co-disposal” of tailings and development rock
    together, and relocation of access roads. After extensive con-
    sultation with AGC, the Corps determined that all alternatives
    were impracticable because the nearby uplands were too steep
    to stabilize the facilities, because the alternative designs
    would require the destruction of higher value wetlands, or
    would expand the project’s footprint, or because alternatives
    were cost prohibitive or undesirable for other reasons. This
    rationale is acceptable under the CWA.
    BSC challenges this result on several bases. First, BSC
    argues that the Corps failed to apply the correct presumption
    of practicable alternatives for projects that are not water
    dependant. However, the PEDD reflects that the Corps explic-
    itly concluded that the project “is not a water dependant activ-
    ity” and that therefore “pursuant to 40 C.F.R. 230.10(a)(3),
    74               BERING STRAIT CITIZENS v. USACE
    practicable alternatives not involving special aquatic sites are
    presumed to be available.” The Corps applied the proper pre-
    sumption.
    Second, BSC argues that the Corps improperly rejected all
    possible upland relocation options for the individual mine
    facilities by evaluating only an “all uplands” alternative, i.e.,
    the placement of the entire project in uplands, without consid-
    ering the relocation of individual facilities. Specifically, BSC
    argues that the Corps failed to consider the option of relocat-
    ing only the North waste dump at the Rock Creek Mine/Mill
    site to an upland site. In support of this claim, BSC cites to
    the PEDD’s rejection of an alternative design that would
    place all facilities in uplands and claims that the Corps failed
    to consider the relocation of some, but not all, of the facilities.
    [6] This is incorrect. The Corps considered and rejected the
    “all uplands” alternative but, contrary to BSC’s assertion, that
    was not the only alternative design considered. Although the
    PEDD does not discuss the relocation of the north dump
    alone, it reflects the Corps consideration of 24 different
    design alternatives. “While an argument can be made that one
    of these sites was suitable, it would not be appropriate for [the
    Court] to overturn the Corps’ contrary finding.”5 Hintz, 800
    F.2d at 834. The PEDD also reflects the Corps’ careful review
    of the data collected by AGC’s consultants before the Corps
    issued the permit, and the PEDD notes that representatives
    from AGC discussed alternative sites with the Corps and/or
    state officials on at least 59 occasions. The Corps reasonably
    5
    Similar analysis applies to BSC’s claim that the Corps improperly
    rejected a “dry stack” tailings facility as cost prohibitive. The record
    shows that the Corps considered the four alternatives presented by AGC’s
    consultants in a “Tailings Alternative Report,” which were incorporated
    by reference in the PEDD. See Hintz, 800 F.2d at 834 (“The Corps’ regu-
    lations do not require the Corps to undertake an independent investigation
    or to gather its own information upon which to base an EA.”). The Corps
    concluded, in agreement with the Tailings Alternative Report, that the dry
    stack method was prohibited by costs.
    BERING STRAIT CITIZENS v. USACE                75
    reviewed the feasible options and reasonably concluded that
    the proposed design was the best design alternative.
    2
    [7] BSC next argues that the Corps did not properly weigh
    the public interest as required by 
    33 C.F.R. § 320.4
    (b)(4).
    That section provides that “[n]o permit will be granted . . .
    unless the district engineer concludes, on the basis of the anal-
    ysis required in paragraph (a) of this section, that the benefits
    of the proposed alteration outweigh the damage to the wet-
    lands resource.” 
    Id.
     Paragraph (a) of § 320.4 includes factors
    to be considered, including, without limitation:
    conservation, economics, aesthetics, general envi-
    ronmental concerns, wetlands, historic properties,
    fish and wildlife values, flood hazards, floodplain
    values, land use, navigation, shore erosion and accre-
    tion, recreation, water supply and conservation,
    water quality, energy needs, safety, food and fiber
    production, mineral needs, considerations of prop-
    erty ownership and, in general, the needs and welfare
    of the people.
    Id.
    [8] BSC’s argument is unavailing. The PEDD reviews
    many relevant factors under 
    33 C.F.R. § 320.4
    (a) in a discus-
    sion spanning more than twenty pages. In addition to the sig-
    nificant environmental considerations included in the PEDD,
    the Corps also properly considered the significant economic
    benefits that are expected to result from the project. Given the
    relatively poor condition of the local economy in relation to
    the state overall, we agree that these benefits are weighty in
    this case. BSC may disagree with the Corps’ determination,
    but in making that determination the Corps did not arbitrarily
    or capriciously evaluate the public’s interest.
    76                BERING STRAIT CITIZENS v. USACE
    B
    [9] In a related claim under the CWA, BSC argues that the
    Corps did not properly consider whether the Rock Creek Min-
    ing Project would “cause or contribute to significant degrada-
    tion of the waters of the United States” as required by 
    40 C.F.R. § 230.10
    . Under this section, the Corps is directed to
    consider the effects of the project while placing “special
    emphasis on the persistence and permanence of the effects” of
    the project.6 Much briefing on this issue relates to the substan-
    tive merits of the Corps’ scientific and factual conclusions on
    the ecological effects of the project. However, the issues
    properly considered here are whether the Corps’ “decision [to
    issue the permit] was based on a consideration of the relevant
    factors and whether there has been a clear error of judgment.”
    Marsh v. Oregon Nat’l Res. Council, 
    490 U.S. 360
     (1989).
    [10] We conclude that the Corps acted properly. The PEDD
    demonstrates that the Corps correctly considered a variety of
    impacts from the project, and determined that the impacts
    would be localized or limited in time. Moreover, the Corps
    6
    “Under these Guidelines, effects contributing to significant degradation
    considered individually or collectively, include:
    (1) Significantly adverse effects of the discharge of pollutants on human
    health or welfare, including but not limited to effects on municipal water
    supplies, plankton, fish, shellfish, wildlife, and special aquatic sites;
    (2) Significantly adverse effects of the discharge of pollutants on life
    stages of aquatic life and other wildlife dependent on aquatic ecosystems,
    including the transfer, concentration, and spread of pollutants or their
    byproducts outside of the disposal site through biological, physical, and
    chemical processes;
    (3) Significantly adverse effects of the discharge of pollutants on aquatic
    ecosystem diversity, productivity, and stability. Such effects may include,
    but are not limited to, loss of fish and wildlife habitat or loss of the capac-
    ity of a wetland to assimilate nutrients, purify water, or reduce wave
    energy; or
    (4) Significantly adverse effects of discharge of pollutants on recreational,
    aesthetic, and economic values.” 
    40 C.F.R. § 230.10
    (c).
    BERING STRAIT CITIZENS v. USACE                77
    stressed that the wetlands that would be filled during the proj-
    ect are not unique to the site, and that the USFWS has deter-
    mined that wetlands of the type filled in this project are the
    “common habitat in the Alaska and the Nome region,”
    exceeding forty percent of the land in the State of Alaska.
    Accordingly, the Corps concluded that the Project will likely
    have no impact on the greater ecosystem beyond the project
    site. Because the Corps thoroughly and rationally considered
    the relevant factors under 
    40 C.F.R. § 230.10
    , it cannot be
    said that its determination was arbitrary and capricious, or that
    its conclusion was contrary to law.
    BSC contends that the Corps has not adequately evaluated
    the hydrological impacts of the project, which it claims may
    violate § 401 of the Clean Water Act, 
    33 U.S.C. § 1341
    . How-
    ever, under 
    33 C.F.R. § 320.4
    (d) the Corps may accept a certi-
    fication of compliance with § 401 from the relevant state
    authority in lieu of conducting its own independent analysis.
    This certification was issued by Alaska’s Department of Envi-
    ronmental Conservation on August 9, 2006. Although BSC
    argues that the Alaska Department of Environmental Conser-
    vation’s certification does not include consideration of the
    underground injection system to be used at the site, the certifi-
    cation mentions that system, and the Alaska Department of
    Environmental Conservation was aware of it when issuing the
    certification. Under the Corps’ regulations, the certification is
    conclusive with respect to water quality considerations. Hintz,
    800 F.2d at 834. The Corps was not required to undertake the
    additional analysis that BSC raises, and in any case the Corps
    included a sufficient discussion of water quality effects in the
    PEDD. The Corps’ determination that the Rock Creek Mining
    Project would not “cause or contribute to significant degrada-
    tion of the waters of the United States” was neither arbitrary
    and capricious, nor contrary to law.
    C
    [11] BSC next argues that the Corps did not require the
    appropriate mitigation measures required by the CWA. 40
    78            BERING STRAIT CITIZENS v. USACE
    C.F.R. § 230.10 requires that the Corps include “appropriate
    and practicable” mitigation measures in permits issued under
    § 404 of the CWA. 
    40 C.F.R. § 230.10
    (d); see also 
    33 C.F.R. § 320.4
    (r) (explaining the general mitigation policy).
    [12] BSC contends that the Corps did not implement all of
    the mitigation measures suggested by the EPA. However, the
    record demonstrates that “the Corps considered [EPA’s] ini-
    tial concerns, addressed them, and explained why it found
    them unpersuasive.” Cal. Trout v. Schaefer, 
    58 F.3d 469
    , 475
    (9th Cir. 1995) (internal quotation marks and citation omit-
    ted). The Corps implemented all of the EPA’s concrete condi-
    tions in the permit and rejected only the more general
    statements from EPA, the substance of which were addressed
    elsewhere in the PEDD. The permit includes an array of
    required mitigation measures, and the Corps has explained its
    rejection of the other measures considered.
    BSC also contends that the mitigation measures provided in
    the permit are insufficient because some mitigation measures
    have not been fully developed. Specifically, BSC urges that
    the permit condition requiring that AGC meet with the Corps
    and USFWS within three months of permit issuance to iden-
    tify additional mitigation opportunities shows that the Corps
    has not fully developed the required mitigation plan for the
    project.
    We have not squarely addressed the question of whether
    plans to develop additional mitigation measures in the future
    can satisfy the CWA’s mitigation requirements. However, in
    a related context, we have held that prospective mitigation
    plans satisfied NEPA’s mitigation requirements where the
    plans were “developed to a reasonable degree.” Wetlands
    Action Network v. U.S. Army Corps of Eng’r, 
    222 F.3d 1105
    ,
    1121 (9th Cir. 2000); see also Tillamook County v. U.S. Army
    Corps of Eng’rs, 
    288 F.3d 1140
    , 1144 (9th Cir. 2002) (hold-
    ing that the Corps “was not required [under NEPA] to develop
    a complete mitigation plan detailing the precise nature of the
    BERING STRAIT CITIZENS v. USACE                        79
    mitigation measures nor were the measures required to com-
    pletely compensate for adverse environmental impacts.”)
    (internal quotation marks omitted).
    [13] The mitigation measures contained in the permit here
    satisfy the CWA’s mitigation requirements. The mitigation
    measures that are to be developed after permit issuance are
    only one part of the overall mitigation requirements included
    in the permit. Where the Corps has undertaken a genuine
    effort to develop a detailed mitigation plan, the mere fact that
    one aspect of the plan is not yet finalized will not necessarily
    lead to the conclusion that the Corps’ decision was arbitrary
    and capricious. Also, the USFWS, not the Corps, suggested
    that the mitigation measures be developed after the permit
    was issued. This belies any suggestion that the Corps was
    attempting to skirt its responsibilities under the CWA by
    delaying the development of a mitigation plan. See also Rob-
    ertson v. Methow Valley Citizens Council, 
    490 U.S. 332
    , 352-
    53 (1989) (“it would be incongruous to conclude that the For-
    est Service has no power to act until the local agencies have
    reached a final conclusion on what mitigating measures they
    consider necessary.”). Finally, the Corps may be perfectly
    reasonable in its belief that additional on-site mitigation
    opportunities will present themselves once the project is
    underway. That the Corps intends to pursue additional mitiga-
    tion opportunities at a later time does not conflict with the
    requirements of the CWA unless the mitigation measures that
    have been fully developed are inadequate. We conclude that
    the Corps’ decisions regarding mitigation measures were not
    arbitrary and capricious, and complied fully with law.7
    7
    BSC makes much of a February 6, 1990 Memorandum of Agreement
    between EPA and the Corps that discusses the mitigation requirements of
    the CWA at length. BSC emphasizes language in the memorandum stating
    that mitigation measures should provide, “at a minimum, one for one func-
    tional replacement (i.e. no net loss of values)” to satisfy the requirements
    of the CWA. See generally Memorandum of Agreement Between The
    Department of the Army and The Environmental Protection Agency, The
    80               BERING STRAIT CITIZENS v. USACE
    V
    We next address BSC’s claims under NEPA.
    A
    [14] BSC argues that the Corps did not provide adequate
    public notice and comment under NEPA because it did not
    circulate a draft EA before the final EA was completed. BSC
    claims that a draft EA must be circulated in order for the
    Corps to comply with 
    40 C.F.R. § 1501
    , which requires the
    Corps to “involve environmental agencies, applicants, and the
    public, to the extent practicable” in the preparation of the EA.
    The Corps and AGC argue in response that NEPA does not
    require the circulation of a draft EA.
    Our law currently does not make clear whether NEPA
    requires the circulation of a draft EA. The regulations do not
    answer the question. 
    40 C.F.R. § 1503.1
     requires the circula-
    Determination of Mitigation Under the Clean Water Act Section 404(b)(1)
    Guidelines, Sept. 6, 1990, available at http://www.epa.gov/owow/
    wetlands/regs/mitigate.html (last accessed Dec. 20, 2007). However, as
    the Corps and AGC point out, the 1990 memorandum is modified by a
    May 13, 1994 memorandum that recognizes that one for one replacement
    of wetlands may be impracticable in Alaska, where “there is a high pro-
    portion of land in a watershed or region which is wetlands.” Accordingly,
    “emphasis is placed on minimizing project impacts to wetlands by reduc-
    ing the footprint of the project, using co-location of facilities whenever
    possible, and seeking to locate the project in lower value wetlands.” The
    memorandum notes, “In Alaska, minimization of impacts has been in
    many circumstances the only mitigation required.” See Alaska Wetlands
    Initiative Summary Report, May 13, 1994, available at http://
    www.epa.gov/owow/wetlands/pdf/alask.pdf (last accessed Dec. 20, 2007).
    The record demonstrates that the Corps minimized the project footprint by
    considering a range of alternative placements, and considered (and imple-
    mented) additional mitigation options. Given the high percentage of land
    proximate to the development that is wetlands, we cannot say that the
    Corps’ approach to minimize impact by selecting low value wetlands for
    project use is unreasonable.
    BERING STRAIT CITIZENS v. USACE                 81
    tion of a draft EIS, but does not speak to the necessity of a
    draft EA. 
    40 C.F.R. § 1506.6
     requires that agencies “[m]ake
    diligent efforts to involve the public in preparing and imple-
    menting their NEPA procedures[,]” but does not expressly
    require the circulation of a draft EA.
    Nor does current Ninth Circuit case law decide the ques-
    tion. In Anderson v. Evans, we stated that “[t]he public must
    be given an opportunity to comment on draft EAs and EISs,
    and public hearings are encouraged to facilitate input on the
    evaluation of proposed actions.” 
    371 F.3d 475
    , 487 (9th Cir.
    2004). However, the dispute in Anderson concerned whether
    the government was required to prepare an EIS, not whether
    there was adequate public notice and comment on the EA—in
    fact, a draft EA was circulated in Anderson. The statement in
    Anderson about the circulation of a draft EA is a dictum.
    In other Ninth Circuit cases we have held that the Ninth
    Circuit has “not established a minimum level of public com-
    ment and participation required by the regulations governing
    the EA and FONSI process.” Citizens for Better Forestry v.
    U.S. Dept. of Agric., 
    341 F.3d 961
    , 970 (9th Cir. 2003). The
    Citizens for Better Forestry opinion quotes Anderson for the
    proposition that a draft EA must be circulated, but the deci-
    sion itself relies not on Anderson’s dictum, but rather on the
    fact that the public was given no notice of the preparation of
    the EA at all. See 
    id. at 970
     (“It is evident, therefore, that a
    complete failure to involve or even inform the public about an
    agency’s preparation of an EA and a FONSI, as was the case
    here, violates these regulations.”) This case presents the first
    opportunity for us to squarely address the question in a case
    where the issue is presented.
    [15] We hold today that the circulation of a draft EA is not
    required in every case. We do not say that it is always
    required or that it is never required. Instead, we stress that the
    regulations governing public involvement in the preparation
    of EAs are general in approach, see 
    40 C.F.R. § 1506.6
    ,
    82              BERING STRAIT CITIZENS v. USACE
    requiring the circulation of a draft EA in every case would
    apply a level of particularity to the EA process that is foreign
    to the regulations. Also, requiring the circulation of a draft EA
    in every case could require the reversal of permitting deci-
    sions where a draft EA was not circulated even though the
    permitting agency actively sought and achieved public partici-
    pation through other means. The regulations do not compel
    such formality. See 
    40 C.F.R. § 1508.9
    .
    Our conclusion is consistent with the views of other cir-
    cuits, which uniformly have not insisted on the circulation of
    a draft EA. See Alliance To Protect Nantucket Sound, Inc. v.
    U.S. Dept. of Army, 
    398 F.3d 105
    , 114-115 (1st Cir. 2005)
    (concluding that “[n]othing in the CEQ regulations requires
    circulation of a draft EA for public comment, except under
    certain ‘limited circumstances,’ ” and rejecting Anderson’s
    contrary language as dicta); Pogliani v. U.S. Army Corps of
    Eng’rs, 
    306 F.3d 1235
    , 1240 (2d Cir. 2002) (holding that a
    draft EA must be circulated only in certain limited circum-
    stances); Greater Yellowstone Coalition v. Flowers, 
    359 F.3d 1257
    , 1279 (10th Cir. 2004) (“NEPA’s public involvement
    requirements are not as well defined when an agency prepares
    only an EA and not an EIS.”); Fund for Animals, Inc. v. Rice,
    
    85 F.3d 535
    , 548 (11th Cir. 1996) (“[T]here is no legal
    requirement that an Environmental Assessment be circulated
    publicly and, in fact, they rarely are.”).8
    However, a significant question remains. Given our conclu-
    sion that NEPA does not always require the circulation of a
    draft EA, what level of public disclosure is required under
    NEPA before issuance of a final EA? Each EA will be pre-
    pared under different circumstances, and the regulations have
    not specified a formal practice for affected agencies. For this
    8
    One district court in our circuit has commented that an “agency can
    never go wrong by releasing a draft EA, and supporting documents,”
    Sierra Nev. Forest Prot. Campaign v. Weingardt, 
    376 F. Supp. 2d 984
    ,
    991 (E.D. Cal. 2005).
    BERING STRAIT CITIZENS v. USACE               83
    reason, practices have not been uniform, and so we will elabo-
    rate the factors that should guide the agency. In Sierra
    Nevada Forest Protection Campaign v. Weingardt, 
    376 F. Supp. 2d at 991-92
    , the United States District Court for the
    Eastern District of California considered precisely this issue.
    After concluding that the agency (there the United States For-
    est Service) need not circulate a draft EA, the court explained:
    [the regulations] require that the public be given as
    much environmental information as is practicable,
    prior to completion of the EA, so that the public has
    a sufficient basis to address those subject areas that
    the agency must consider in preparing the EA.
    Depending on the circumstances, the agency could
    provide adequate information through public meet-
    ings or by a reasonably thorough scoping notice.
    
    Id. at 991
    .
    [16] The district court in Sierra Nevada Forest Protection
    Campaign evaluated this issue soundly, and we commend its
    approach. As that court observed, “The way in which the
    information is provided is less important than that a sufficient
    amount of environmental information—as much as
    practicable—be provided so that a member of the public can
    weigh in on the significant decisions that the agency will
    make in preparing the EA.” 
    Id.
     Stated another way, we now
    adopt this rule: An agency, when preparing an EA, must pro-
    vide the public with sufficient environmental information,
    considered in the totality of circumstances, to permit members
    of the public to weigh in with their views and thus inform the
    agency decision-making process.
    [17] The Corps satisfied this rule here. Information about
    the project was widely disseminated throughout the commu-
    nity and environmental information was reasonably and thor-
    oughly tendered to the public. Indeed, in response, the Corps
    received a high level of public comment from the Nome com-
    84             BERING STRAIT CITIZENS v. USACE
    munity, most of it favoring the project. In addition to these
    significant efforts by the Corps, AGC made substantial efforts
    to provide additional information to the public, including a
    weekly newspaper column on the project’s status that ran for
    about eighteen months, local presentations, radio interviews,
    and joint efforts with state agencies to explain the permitting
    process. The quality of the Corps’ dissemination of environ-
    mental information to the public and its consideration of pub-
    lic comment, before issuing its EA, was reasonable and
    adequate.
    B
    BSC next argues that the EA prepared by the Corps for the
    Rock Creek Mining Project is inadequate by four different
    measures. First, BSC argues that the EA did not adequately
    discuss cumulative impacts. Second, BSC argues that the
    alternatives analysis in the EA is inadequate. Third, BSC
    argues that the Corps reliance on mitigation plans that are not
    yet fully developed is inadequate. Finally, BSC argues that
    the Corps failed to adequately analyze environmental impacts
    in the EA.
    “NEPA requires that an EIS be prepared for all ‘major Fed-
    eral actions significantly affecting the quality of the human
    environment.’ 
    42 U.S.C.A. § 4332
    (2)(C) (1994). However, if,
    as here, an agency’s regulations do not categorically require
    the preparation of an EIS, then the agency must first prepare
    an EA to determine whether the action will have a significant
    effect on the environment.” Metcalf v. Daley, 
    214 F.3d 1135
    ,
    1142 (9th Cir. 2000). The EA is designed to provide sufficient
    evidence and analysis for the agency to determine whether to
    prepare an EIS or to issue a FONSI. 
    Id. at 1145
    ; see also 
    40 C.F.R. § 1508.9
     (describing the purposes of the EA). Here,
    the Corps determined on the basis of the EA that an EIS was
    unnecessary, and BSC challenges the sufficiency of the EA.
    BERING STRAIT CITIZENS v. USACE               85
    1
    [18] BSC contends that the EA did not adequately discuss
    the cumulative impact of the project. “Cumulative impact” is
    defined in the regulations as “the impact on the environment
    which results from the incremental impact of the action when
    added to other past, present, and reasonably foreseeable future
    actions regardless of what agency (federal or non-federal) or
    person undertakes such other actions.” 
    40 C.F.R. § 1508.7
    .
    We have held that:
    [a] proper consideration of the cumulative impacts of
    a project requires some quantified or detailed infor-
    mation . . . [g]eneral statements about possible
    effects and some risk do not constitute a hard look
    absent a justification regarding why more definitive
    information could not be provided. The analysis
    must be more than perfunctory; it must provide a
    useful analysis of the cumulative impacts of past,
    present, and future projects.
    Klamath-Siskiyou Wildlands Center v. Bureau of Land Mng’t,
    
    387 F.3d 989
    , 993-94 (9th Cir. 2004) (internal quotation
    marks and citation omitted).
    BSC relies on Klamath-Siskiyou to support its argument. In
    Klamath-Siskiyou, the plaintiffs challenged the adequacy of
    EAs prepared by the Bureau of Land Management for timber
    sales in the Oregon Cascades. 
    Id. at 992
    . Although that
    agency had received applications for four timber sales in the
    same area, it decided to review the four sales with separate
    EAs. 
    Id.
     We reversed the district court’s judgment for the
    agency, concluding that two of the EAs failed to adequately
    consider the cumulative impacts of the four different projects.
    
    Id. at 994-6
    . Although the EAs contained lengthy sections
    labeled “cumulated impacts,” the discussion was primarily
    limited to the impacts of the individual project covered by
    each EA, with little discussion of the effects of the four sales
    86             BERING STRAIT CITIZENS v. USACE
    combined. 
    Id.
     We held that “the only mention of cumulative
    effects in the two EAs comes in the form of generalized con-
    clusory statements that the effects are not significant or will
    be effectively mitigated.” 
    Id. at 996
    . These were the type of
    “[g]eneral statements about possible effects and some risk
    [that] do not constitute a hard look absent a justification
    regarding why more definitive information could not be pro-
    vided.” 
    Id.
     at 995 (citing Neighbors of Cuddy Mtn. v. U.S.
    Forest Serv., 
    137 F.3d 1372
    , 1380 (9th Cir. 1998)).
    [19] The EA here succinctly but adequately discusses the
    cumulative impacts of the project and points out the Corps’
    determination that the project will leave portions of the drain-
    age in “more natural conditions than currently exist” due to
    mitigation measures included in the permit. To be sure, the
    EA does not discuss at length other projects taking place in
    the Nome region. However, the record indicates—and we
    were assured at oral argument—that this is because there are
    no projects of similar magnitude at this time. Also, BSC has
    pointed to no past, present, or reasonably foreseeable future
    projects comparable in environmental impact to the Rock
    Creek Mine Project. This fairly distinguishes Klamath-
    Siskiyou, because there the agency failed to consider four
    known and comparable projects that were proceeding in the
    permitting process. Compare Kootenai Tribe of Idaho v.
    Veneman, 
    313 F.3d 1094
    , 1123 (9th Cir. 2002) (noting that
    the Corps need not include projects in its cumulative impacts
    analysis that are highly speculative). The impact of isolated
    placer mining, which often involves only small-scale opera-
    tions, in our view is not germane to the cumulative impacts
    assessment of the Rock Creek Mining Project. BSC has not
    identified any comparable project— past, present, or future—
    that could call into question the cumulative impacts analysis.
    Under the total circumstances, we conclude that the Corps’
    cumulative impacts analysis was adequate.
    BERING STRAIT CITIZENS v. USACE                      87
    2
    [20] BSC next argues that the EA does not adequately dis-
    cuss alternatives to the approved project as required by NEPA
    regulations found at 
    40 C.F.R. § 1508.9
    . It is important to rec-
    ognize that NEPA’s requirement to assess alternatives, unlike
    that in the CWA, is a procedural and not a substantive
    requirement. Our law has made clear the nature of NEPA’s
    scope: “Under NEPA, an agency’s consideration of alterna-
    tives is sufficient if it considers an appropriate range of alter-
    natives, even if it does not consider every available
    alternative. An agency need not, therefore, discuss alterna-
    tives similar to alternatives actually considered, or alternatives
    which are infeasible, ineffective, or inconsistent with the basic
    policy objectives for the management of the area[.]” Northern
    Alaska Env’l Center v. Kempthorne, 
    457 F.3d 969
    , 978 (9th
    Cir. 2006) (quotation marks and internal citations omitted).9
    [21] We have already concluded above, in assessing the
    CWA claim, that the Corps considered many alternatives and
    satisfied its obligation to select the least environmentally
    damaging practicable alternative. The CWA analysis is pri-
    marily (but not exclusively) concerned with the aquatic
    ecosystem, 
    40 C.F.R. § 230.10
    (a)(2), while the NEPA analy-
    sis is more broad and procedurally oriented. However, the
    Corps has satisfied both standards with its comprehensive,
    searching, and rational assessment of alternatives. We con-
    clude that the Corps took the “hard look” required by NEPA.
    3
    BSC next contends that the mitigation plans contained in
    the EA are inadequate because the EA relies on plans that are
    to be fully developed after the project begins. “An agency’s
    9
    “[A]n agency’s obligation to consider alternatives under an EA is a
    lesser one than under an EIS.” Env’l Prot. Info. Ctr. v. U.S. Forest Ser-
    vice,
    451 F.3d 1005
    , 1016 (9th Cir. 2006).
    88             BERING STRAIT CITIZENS v. USACE
    decision to forego issuing an EIS may be justified by the pres-
    ence of mitigating measures.” Wetlands Action Network, 
    222 F.3d at 1121
    . However, we have held that an “agency is not
    required to develop a complete mitigation plan detailing the
    precise nature . . . of the mitigation measures[,]” so long as
    the measures are “developed to a reasonable degree.” Nat’l
    Parks & Conservation Ass’n v. Babbitt, 
    241 F.3d 722
    , 734
    (9th Cir. 2001). As discussed more thoroughly in Section C,
    above, the mitigation plans that have not yet been fully devel-
    oped are only a small part of the overall mitigation plan for
    the Rock Creek Mine Project site, on which we conclude that
    mitigation measures were developed to a reasonable degree.
    Because the measures overall are developed to a reasonable
    degree, the Corps could reasonably conclude that additional
    mitigation measures would be developed after work com-
    menced at the site.
    4
    [22] Finally, BSC argues that the Corps did not adequately
    consider the environmental impacts of the Rock Creek Mine
    Project in the EA. BSC first contends that the 2007 EA does
    not discuss air quality issues. This is incorrect. The EA
    requires that AGC develop a plan with the Alaska Department
    of Transportation to minimize dust, the primary air contami-
    nant to be released from the site. The Environmental Informa-
    tion Document, incorporated by reference in the EA, also
    includes specific data on the air quality issues at the site, and
    concludes that there are none that are significant.
    [23] BSC then asserts that the Corps failed to adequately
    address water quality issues. However, as discussed in our
    analysis of the CWA issues above, the Corps was entitled to
    rely upon the certification from the Alaska Department of
    Environmental Conservation that the project meets the rele-
    vant water quality conditions. Moreover, the Corps consid-
    ered water quality issues at length, partly in response to
    comments from EPA, and the Environmental Information
    BERING STRAIT CITIZENS v. USACE              89
    Document, incorporated by reference in the EA, discussed
    water quality issues, including an in-depth analysis of ground-
    water issues.
    [24] BSC further contends that the EA did not adequately
    consider the impact of the project on biological resources.
    This is also incorrect. The EA and accompanying Environ-
    mental Information Document include detailed habitat map-
    ping to determine the wildlife use patterns within the project
    area. The Corps determined that the mine would likely cause
    short-term disruption of wildlife in the area, but that “wildlife
    typically adjusts to this type of disturbance by moving to
    nearby undisturbed areas where similar habitat types exist.”
    Because the Corps found that more than 54,000 acres of simi-
    lar habitat surround the Rock Creek Mine/Mill and Big Hur-
    rah Mine, the Corps concluded that the impacts on wildlife
    would be minimal.
    [25] The Corps adequately considered the environmental
    impacts raised by BSC, its conclusions were not arbitrary and
    capricious, nor were they contrary to law.
    C
    [26] BSC argues that the Corps should have prepared an
    EIS for the Rock Creek Mine Project. “NEPA requires that an
    [EIS] be prepared for all ‘major Federal actions significantly
    affecting the quality of the human environment.’ 
    42 U.S.C.A. § 4332
    (2)(C).” Nat’l Parks & Conservation Ass’n v. Babbitt,
    
    241 F.3d at 730
    . To determine whether an EIS is necessary,
    an EA is prepared.10 Based on the EA, the agency determines
    whether an EIS should be prepared or a FONSI should be
    issued. “An EIS must be prepared if ‘substantial questions are
    raised as to whether a project . . . may cause significant degra-
    dation of some human environmental factor.’ ” Blue Mtns., 61
    F.3d at 1212 (citation omitted). “Whether there may be a sig-
    10
    “Significantly” is defined in 
    40 C.F.R. § 1508.27
    .
    90             BERING STRAIT CITIZENS v. USACE
    nificant effect on the environment requires consideration of
    two broad factors: context and intensity.” Ctr. for Bio. Diver-
    sity v. NHTSA, Nos. 06-71891, 06-72317, 06-72641, 06-
    72694, 06-73807, 06-73826, 
    2007 WL 3378240
    , at * 5 (9th
    Cir. Nov. 15, 2007) (citing Nat’l Parks & Conservation Ass’n,
    
    241 F.3d 720
    , 731 (9th Cir. 2001)); see also Ctr. for Bio.
    Diversity, at *5 (listing additional relevant factors).
    BSC raises issues that it believes demonstrate “substantial
    questions” about the effects of the Rock Creek Mine Project.
    First, BSC raises concerns about air quality, biological
    resources, and water quality. The EA and accompanying
    Environmental Information Document show that the Corps
    undertook a reasonable approach to these issues. “Simply
    because a challenger can cherry pick information and data out
    of the administrative record to support its position does not
    mean that a project is highly controversial or highly uncer-
    tain.” Native Ecosystems Council v. U.S. Forest Serv., 
    428 F.3d 1233
    , 1240 (9th Cir. 2005).
    Second, BSC argues that EPA’s disagreement with the
    Corps regarding mitigation requirements raises a substantial
    question that requires the preparation of an EIS. However, the
    EPA’s objections were limited to the propriety of issuing the
    permit while some details of the mitigation plan were not
    finalized. The Corps reasonably developed a mitigation plan,
    including many measures that are set, and has provided a rea-
    soned explanation for these post-issuance conditions, which
    were suggested by the USFWS. That EPA disagreed with the
    Corps’ assessment does not create a substantial issue requir-
    ing an EIS under these circumstances. “When specialists
    express conflicting views, an agency must have discretion to
    rely on the reasonable opinions of its own qualified experts
    even if, as an original matter, a court might find contrary
    views more persuasive.” Marsh, 490 U.S. at 368.
    [27] We cannot avoid perceiving that the project in its
    required mitigation favorably affects parts of the Nome area
    BERING STRAIT CITIZENS v. USACE             91
    that suffered environmental damage from previously uncon-
    strained resource development. On balance, we conclude that
    the Rock Creek Mine Project has no significant detrimental
    effect on the environment in and near Nome. Accordingly, the
    Corps was not required to prepare an EIS based on the issues
    raised by BSC or by the EPA.
    VI
    The decisions of the Corps relating to the Rock Creek Min-
    ing Project were not arbitrary and capricious. Nor were these
    decisions contrary to law.
    AFFIRMED.
    

Document Info

Docket Number: 07-35506

Citation Numbers: 524 F.3d 938

Filed Date: 1/2/2008

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (22)

Alliance Nan. Sound v. US Dept. of the Army , 398 F.3d 105 ( 2005 )

Greater Yellowstone v. Flowers , 359 F.3d 1257 ( 2004 )

native-ecosystems-council-v-united-states-forest-service-an-agency-of-the , 428 F.3d 1233 ( 2005 )

environmental-protection-information-center-a-california-nonprofit , 451 F.3d 1005 ( 2006 )

walter-pogliani-jacqueline-dunn-stephen-dunn-robert-h-boyle-dimitri , 306 F.3d 1235 ( 2002 )

the-fund-for-animals-inc-defenders-of-wildlife-florida-biodiversity , 85 F.3d 535 ( 1996 )

klamath-siskiyou-wildlands-center-an-oregon-non-profit-organization-v , 387 F.3d 989 ( 2004 )

frederic-d-sylvester-v-us-army-corps-of-engineers-wayne-j-scholl-in , 882 F.2d 407 ( 1989 )

tillamook-county-v-us-army-corps-of-engineers-city-of-mcminnville , 288 F.3d 1140 ( 2002 )

blue-mountains-biodiversity-project-blue-mountain-native-forest-alliance , 161 F.3d 1208 ( 1998 )

national-parks-conservation-association , 241 F.3d 722 ( 2001 )

citizens-for-better-forestry-the-ecology-center-gifford-pinchot-task-force , 341 F.3d 961 ( 2003 )

will-anderson-fund-for-animals-humane-society-of-the-united-states , 371 F.3d 475 ( 2004 )

northwest-environmental-defense-center-northwest-resource-information , 117 F.3d 1520 ( 1997 )

wetlands-action-network-a-california-non-profit-organization-ballona , 222 F.3d 1105 ( 2000 )

jack-metcalf-australians-for-animals-beach-marine-protection-stassawood-of , 214 F.3d 1135 ( 2000 )

churchill-county-city-of-fallon-v-gale-a-norton-in-her-official-capacity , 276 F.3d 1060 ( 2001 )

california-trout-a-california-non-profit-corporation-v-kurt-a-schaefer , 58 F.3d 469 ( 1995 )

Robertson v. Methow Valley Citizens Council , 109 S. Ct. 1835 ( 1989 )

Sierra Nevada Forest Protection Campaign v. Weingardt , 376 F. Supp. 2d 984 ( 2005 )

View All Authorities »