Transwestern Pipeline Company v. 17.19 Acres of Property ( 2008 )


Menu:
  •                       FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    TRANSWESTERN PIPELINE COMPANY,               
    LLC, a Delaware limited liability
    company,
    Plaintiff-Appellant,
    v.
    No. 08-15991
    17.19 ACRES OF PROPERTY
    LOCATED IN MARICOPA COUNTY,                           D.C. No.
    2:08-cv-00033-JWS
    more or less; AGUA FRIA
    INVESTMENTS, LLC, a Delaware                           OPINION
    limited liability company; FIRST
    NATIONAL BANK OF OLATHE, a
    Kansas corporation; J. LAWRENCE
    MCCORMLEY,
    Defendants-Appellees.
    
    Appeal from the United States District Court
    for the District of Arizona
    John W. Sedwick, District Judge, Presiding
    Submitted December 1, 2008*
    Pasadena, California
    Filed December 11, 2008
    Before: Harry Pregerson, Cynthia Holcomb Hall and
    N. Randy Smith, Circuit Judges.
    Opinion by Judge Hall
    *This panel unanimously agrees that this case is appropriate for submis-
    sion without oral argument pursuant to Fed. R. App. P. 34(a)(2).
    16281
    TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY 16283
    COUNSEL
    John C. Lemaster, Ryley Carlock & Applewhite, Phoenix,
    Arizona, and Jeffrey L. Hinds, Bricklemyer Smolker &
    Bolves, P.A., Tampa, Florida, for the appellant.
    16284 TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY
    Steven A. Hirsch, Bryan Cave LLP, Phoenix, Arizona, for the
    appellees.
    Kenneth B. Bley, Cox, Castle & Nicholson LLP, Los Ange-
    les, California, for the amici curiae.
    OPINION
    HALL, Senior Circuit Judge:
    Transwestern Pipeline Co. (Transwestern) appeals the dis-
    trict court’s denial of its preliminary injunction motion seek-
    ing immediate possession of appellee landowners’ parcels of
    land. As a holder of a valid Federal Energy Regulatory Com-
    mission (FERC) certificate, Transwestern claims it is entitled
    to condemn appellees’ land pursuant to § 717f(h) of the Natu-
    ral Gas Act (NGA). The district court denied the injunction,
    holding that, until condemnation proceedings are completed,
    Transwestern maintains no substantive right of possession and
    therefore the district court lacked authority to grant prelimi-
    nary equitable relief. The district court had jurisdiction pursu-
    ant to 15 U.S.C. § 717f(h) and 
    28 U.S.C. § 1331
    . We have
    jurisdiction pursuant to 
    28 U.S.C. § 1292
    (a)(1). We affirm
    and hold that, until an order of condemnation issues pursuant
    to the requirements of 15 U.S.C. § 717f(h), Transwestern has
    no substantive right of possession.
    I.   Background
    Transwestern owns and operates natural gas pipelines serv-
    ing much of the Southwest. Following the review of its appli-
    cation and completion of public hearings, the Federal Energy
    Regulatory Commission (FERC) issued a Certificate of Public
    Convenience and Necessity (the Certificate) approving Trans-
    western’s proposed construction and expansion of a natural
    gas pipeline to meet the demands of a growing Phoenix mar-
    TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY 16285
    ket. The Certificate provided that Transwestern was to com-
    plete the construction within one year of issuance, or by
    November 15, 2008.1
    Several property owners affected by the Certificate, most
    prominently the Town of Buckeye, Arizona, opposed the Cer-
    tificate’s issuance and filed a petition for rehearing of the Cer-
    tificate with FERC. The petition alleged insufficient process
    in approving the Certificate and requested that the proposed
    pipeline route bypass a number of master planned communi-
    ties. FERC denied the petition for rehearing, see 
    2008 WL 461054
     (F.E.R.C.) and, pursuant to the process outlined by
    the Natural Gas Act (NGA), several petitioners appealed the
    denial to the D.C. Circuit. See 15 U.S.C. § 717r. These
    appeals have since been dismissed during the pendency of this
    appeal. See Town of Buckeye v. F.E.R.C., No. 08-1126 (D.C.
    Cir. filed June 27, 2008); El Paso Natural Gas Co. v.
    F.E.R.C., No. 08-1161 (D.C. Cir. filed Aug. 25, 2008).2
    Because neither the rehearing nor the appeal automatically
    stayed the Certificate’s enforcement, see § 717r(c), Transwes-
    tern continued to pursue its construction objectives through-
    out this time. Transwestern was able to reach an agreement on
    an easement price with most of the 897 affected landowners.
    With regard to the remaining 129 parcels, Transwestern filed
    condemnation actions in the district court of Arizona. The
    NGA authorizes FERC Certificate holders to acquire neces-
    1
    The ramifications of a possible delay in completion are uncertain, how-
    ever, as 
    18 C.F.R. § 157.20
    (b) (1999), as cited in the Certificate, appears
    only to require that Transwestern notify FERC within ten days of expira-
    tion of the Certificate if it is unable to meet the imposed timetable to com-
    mence service. During the pendency of this appeal, Transwestern was, in
    fact, able to obtain an extension with FERC to complete the project by a
    revised deadline of April 15, 2009.
    2
    On August 25, 2008, the El Paso National Gas Company appeal was
    placed in abeyance, pending the completion of a proposed sale.
    16286 TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY
    sary land by the exercise of the right of eminent domain, after
    negotiations with affected landowners fail. § 717f(h).3
    After consolidating the actions, Transwestern sought a pre-
    liminary injunction to obtain immediate possession of the
    contested parcels. Transwestern claimed entitlement to relief
    under the court’s equitable powers and, specifically, Rule 65
    of the Federal Rules of Civil Procedure. Transwestern argued
    that the FERC certificate and NGA § 717f(h) guaranteed its
    success on the merits, and it would suffer irreparable harm if
    it could not take possession immediately, citing construction
    delays and resulting expenses, the necessity of complying
    with the timeline provided by the Certificate, its desire to
    meet contractual forecasts with suppliers and customers, and
    the public interest in getting the pipeline in service before fall
    2008. The landowners argued the Certificate was improperly
    granted and also contested the severity and nature of Trans-
    western’s harm. They argued primarily that any harm incurred
    by Transwestern was illusory and created by Transwestern’s
    own choice to prematurely enter contracts, and that Transwes-
    tern could easily obtain an extension of the FERC deadline.
    3
    15 U.S.C. § 717f(h) reads:
    When any holder of a certificate of public convenience and
    necessity cannot acquire by contract, or is unable to agree with
    the owner of property to the compensation to be paid for, the nec-
    essary right-of-way to construct, operate, and maintain a pipe line
    or pipe lines for the transportation of natural gas, and the neces-
    sary land or other property, in addition to right-of-way, for the
    location of compressor stations, pressure apparatus, or other sta-
    tions and equipment necessary to the proper operation of such
    pipe line or pipe lines, it may acquire the same by the exercise
    of the right of eminent domain in the district court of the United
    States for the district in which such property may be located, or
    in the State courts. The practice and proceeding in any action or
    proceeding for that purpose in the district court of the United
    States shall conform as nearly as may be with the practice and
    procedure in similar action or proceedings in the courts of the
    State where the property is situated. . . .
    TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY 16287
    Following a lengthy evidentiary hearing, the district court
    denied the preliminary injunction. Without reaching the par-
    ties’ factual contentions or balancing hardships, the district
    court held that it lacked authority to grant immediate posses-
    sion under the terms of the NGA, and doing so would effec-
    tively grant Transwestern a substantive quick-take power not
    authorized by the statute.
    During this appeal process, Tranwestern was able to settle
    with all but one affected landowner, Agua Fria Investments,
    LLC, the remaining appellee in this action.
    II.   Standard of Review
    “In general, we review the denial of a preliminary injunc-
    tion for abuse of discretion. The district court, however, nec-
    essarily abuses it discretion when it bases its decision on an
    erroneous legal standard or on clearly erroneous findings of
    fact. When the district court is alleged to have relied on an
    erroneous legal premise, we review the underlying issues of
    law de novo.” Earth Island Inst. v. U.S. Forest Serv., 
    351 F.3d 1291
    , 1298 (9th Cir. 2003) (citations omitted). Here, the dis-
    trict court found that it lacked authority to grant the prelimi-
    nary injunction. This appeal thus presents a legal question that
    we review de novo.
    III.   Discussion
    A.   Statutory Right to Possession Under NGA § 717f(h)
    [1] The usual process by which the government or another
    authorized party takes property for public use is through the
    straight condemnation proceeding. In straight condemnation
    actions, the government takes possession of the land follow-
    ing an order of condemnation and a trial determining just
    compensation. See 
    40 U.S.C. § 3113
    ; Kirby Forest Ind., Inc.
    v. United States, 
    467 U.S. 1
    , 3-4 (1984) (outlining different
    16288 TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY
    authority and procedures used by the government to condemn
    property).
    [2] Certain other statutes, chiefly the Declaration of Taking
    Act (DTA), provide an additional quick-take power, by which
    the government’s right of possession vests immediately upon
    filing a declaration of public use and assuring the court that
    the government will pay the full just compensation amount,
    once determined, by deposit, appropriation, or otherwise. See
    
    40 U.S.C. § 3114
     (DTA); Kirby, 
    467 U.S. at 4-5
    ; Commercial
    Station Post Office v. United States, 
    48 F.2d 183
    , 184-186
    (8th Cir. 1931) (granting immediate possession to the govern-
    ment after the order of condemnation issued, but before just
    compensation was determined, because a congressional
    appropriation existed to acquire contested property). Congress
    has granted quick-take authority in only a limited number of
    statutes, including the Atomic Energy Act and the Second
    War Powers Act, and only for use by the federal government.
    See United States v. Parcel of Land, etc., 
    100 F. Supp. 498
    ,
    501, 503, n.8 (D.D.C. 1951). Furthermore, the Uniform Relo-
    cation Assistance and Real Property Acquisitions Policy Act
    of 1970 limits the use of quick-take power and requires “to
    the greatest extent practicable,” that the federal government
    use straight condemnation proceedings. 
    42 U.S.C. § 4651
    .
    [3] The “additional [quick-take] right conferred” by Con-
    gress is missing from § 717f(h) of the NGA. See Parcel of
    Land, 
    100 F. Supp. at 501
     (discussing the separate substantive
    right of the quick-take power, which must be expressly
    granted in a statute by Congress) (citing Catlin Trustees v.
    United States, 
    324 U.S. 229
    , 239 (1945)). All courts examin-
    ing the issue have agreed that the NGA does not authorize
    quick-take power, nor can it be implied, because eminent
    domain statutes are strictly construed to exclude those rights
    not expressly granted. See Humphries v. Williams Nat’l Gas
    Co., 
    48 F. Supp. 2d 1276
    , 1281 (D. Kan. 1999); see also
    Northern Border Pipeline Co. v. 86.72 Acres of Land, 
    144 F.3d 469
    , 471 (7th Cir. 1998) (Northern Border); Northwest
    TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY 16289
    Pipeline Corp. v. The 20″ x 1,430′ Pipeline Right of Way, 
    197 F. Supp. 2d 1241
    , 1243-1244 (E.D. Wash. 2002); Northern
    Border Pipeline Co. v. 127.79 Acres of land, more or less in
    Williams County, N.D., 
    520 F. Supp. 170
    , 173 (D.C.N.D.
    1981).
    [4] Transwestern concedes that the NGA itself does not
    authorize quick-take power, but cites numerous cases for the
    proposition that courts nonetheless have authority to grant
    immediate possession in condemnation actions under their
    equitable powers. See, e.g., City of Oakland v. United States,
    
    124 F.2d 959
    , 963 (9th Cir. 1942); Commercial Station, 
    48 F.2d at 184
    ; United States v. Fisk Bldg., 
    99 F. Supp. 592
    , 594-
    595 (S.D.N.Y. 1951); United States v. A Certain Tract or
    Parcel of Land in Chatham County, 
    44 F. Supp. 712
    , 716
    (S.D. Ga. 1942). These cases, however, do not address a pri-
    vate entity condemning property under the limited statutory
    authority of the NGA. Instead, these cases rely on other stat-
    utes, or on the inherent power of the United States govern-
    ment as sovereign, to condemn property. See, e.g.,
    Commercial Station, 
    48 F.2d at 185
     (relying on direct legisla-
    tive act and appropriation); Chatham County, 
    44 F. Supp. at 716
     (relying on inherent powers of United States government
    as sovereign). Additionally, in each case, the court was first
    assured of an adequate provision for payment. The govern-
    ment is able to proceed and condemn land, even where no
    appropriation has been made, because the Fifth Amendment
    ensures just compensation and serves as an implied promise
    to pay. See Commercial Station, 
    48 F.2d at 185
    . As a private
    entity, Transwestern has neither sovereign authority nor the
    backing of the U.S. Treasury to assure adequate provision of
    payment. The cited cases are inapplicable.4
    4
    In addition, each of these cases preceded the passage of the Uniform
    Relocation Assistance and Real Property Acquisitions Policy Act of 1970,
    mentioned above. 
    42 U.S.C. § 4651
    . We question whether the cases would
    have all reached the same result if the government had the additional bur-
    den of showing that straight condemnation proceedings were not at all
    practicable.
    16290 TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY
    B. Preliminary Injunction Authority Under Rule 71.1
    and 65 of the Federal Rules of Civil Procedure
    Transwestern correctly asserts that Federal Rule of Civil
    Procedure Rule 71.1 governs condemnation procedure in the
    district court. It argues that ordinary preliminary injunctions
    are permitted under Rule 65 because quick-take proceedings
    are not specifically addressed by Rule 71.1, and because 71.1(a)5
    specifically incorporates the other Rules.6 In support of this
    proposition, Transwestern cites both Ninth Circuit and
    Supreme Court cases holding that absent clear limiting lan-
    guage in a statute, the district court retains its equitable power
    to issue injunctions. See Califano v. Yamasaki, 
    442 U.S. 682
    ,
    705 (1979); United States v. Alisal Water Corp., 
    431 F.3d 643
    , 654 (9th Cir. 2005).
    This argument fails to recognize that procedural rules can-
    not provide the basis for new substantive rights.7 It also
    5
    Rule 71.1(a) Applicability of Other Rules
    These rules govern proceedings to condemn real and personal
    property by eminent domain, except as this rule provides other-
    wise.
    6
    In fact, Rule 71.1 may not apply at all to quick-take power as the origi-
    nal notes to the May 1948 draft of the Rules stated: “Rule 71A is not
    intended to and does not supercede the Act of February 26, 1931 [DTA],
    which is a supplementary condemnation statute, permissive in its nature
    and designed to permit the prompt acquisition of title by the United States,
    pending condemnation proceedings, upon a deposit in court . . . the same
    is true insofar as the following or any other statute authorize the acquisi-
    tion of title or the taking of immediate possession.” Parcel of Land, 
    100 F. Supp. at 503, n.8
    .
    7
    While Rule 71.1 cannot provide additional substantive rights under the
    NGA, it seems clear that it does supercede that part of the § 717f(h) which
    requires the district court to “conform as nearly as may be with the prac-
    tice and procedure in similar action or proceedings in the courts of the
    State where the property is situated.” The Supreme Court interpreted the
    precise language of the NGA in two other condemnation statutes and
    found it to be superceded by the Federal Rules of Civil Procedure. See
    TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY 16291
    ignores that preliminary injunctions, including those upheld in
    the cited cases, are primarily issued to preserve the status quo
    of the parties and as a means for the court to retain jurisdic-
    tion over the action. Here, Transwestern seeks not to preserve
    the status quo, but instead seeks a mandatory injunction,
    which is “particularly disfavored” in law. See Stanley v. Univ.
    of S. Cal., 
    13 F.3d 1313
    , 1320 (9th Cir. 1994) (holding that
    mandatory preliminary injunctions should be denied “unless
    the facts and law clearly favor the moving party”).
    [5] In Grupo Mexicano de Desarrollo S.A. v. Alliance Bond
    Fund, Inc., 
    527 U.S. 308
    , 323 (1999), the Supreme Court held
    that a district court lacks authority to grant a preliminary
    injunction under Rule 65 if the party does not have a substan-
    tive right to the injunction. There, even where the moving
    party creditor ultimately received final judgment and a perma-
    nent injunction, the creditor had no substantive right to freeze
    the debtor’s assets until the judgment issued. 
    Id.
     Only with the
    actual judgment did the creditor’s substantive right to the
    debtor’s assets accrue, “[n]otwithstanding the fusion of law
    and equity by the Rules of Civil Procedure . . . .” 
    Id.
     The
    Supreme Court’s analysis in that case helps to illustrate that
    “likelihood of success on the merits” does not subsume the
    entire preliminary injunction analysis and allow parties to
    obtain relief before bearing the burden of proof in their claim.
    [6] Here, Transwestern’s substantive right to condemn the
    Kirby Forest, 
    467 U.S. at 4, n.2
    ; United States v. 93.970 Acres of Land,
    
    360 U.S. 328
    , 333 (1959). While there is no Supreme Court holding spe-
    cifically finding the condemnation provision of the NGA to be superceded
    by Rule 71.1, there appears to be no argument for distinguishing the
    NGA’s language. Indeed, other courts have already determined that Rule
    71.1 did supercede the state procedural provisions of the NGA. See Nat’l
    Fuel Gas Supply Corp. v. 138 Acres of Land, 
    84 F. Supp.2d 405
    , 415
    (W.D.N.Y. 2000); Guardian Pipeline, L.L.C. v. 950.80 Acres of Land, 
    210 F. Supp.2d 976
    , 979 (N.D. Ill. 2002) (citing Southern Nat’l Gas Co. v.
    Land, Cullman County, 
    197 F.3d 1368
    , 1373 (11th Cir. 1999)).
    16292 TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY
    affected parcels accrues only through the issuance of an order
    of condemnation by the district court. To obtain such an
    order, Transwestern must, at minimum, meet the requirements
    of § 717f(h), which include showing: “(1) that it holds a
    FERC certificate authorizing the relevant project, (2) that the
    land to be taken is necessary to the project; and (3) that the
    company and the landowners have failed to agree on a price
    for the taking . . . . In addition to showing an inability to agree
    on a price with the landowner, [Transwestern] must also
    establish that it engaged in good faith negotiations with the
    landowner.” Nat’l Fuel Gas Supply Corp. v. 138 Acres of
    Land, 
    84 F.Supp.2d 405
    , 416 (W.D.N.Y. 2000) (citations omit-
    ted).8
    [7] Most courts presented with the issue agree that a plain-
    tiff gas company must secure an order of condemnation
    before taking possession. In Northern Border, the Seventh
    Circuit held that the gas company could not obtain a prelimi-
    nary injunction without first showing a “substantive claim to
    immediate possession.” Norther Border Pipeline Co. v. 86.72
    Acres of Land, 
    144 F.3d 469
    , 472 (7th Cir. 1998). In East
    Tennessee Natural Gas Co. v. Sage, 
    361 F.3d 808
    , 825 (4th
    Cir. 2004), the Fourth Circuit found that the district court’s
    grant of immediate possession was appropriate only where an
    order of condemnation had first issued. In construing the
    holding of Northern Border, the Sage court agreed that with-
    out first accruing its substantive right of possession through
    an order of condemnation, the gas company could not invoke
    the court’s equitable powers. 
    Id. at 828
    . Sage also cited
    Northern Border Pipeline Co. v. 64.111 Acres of Land, 
    125 F. Supp.2d 299
    , 301 (N.D. Ill. 2000) and Guardian Pipeline,
    8
    Before satisfying the requirements to condemn under the NGA, Trans-
    western could likely obtain a preliminary injunction which sought only to
    maintain the jurisdiction of the court and the status quo of the parties. As
    contemplated, such an injunction could prevent the landowners from alter-
    ing their land in such a way that would make the property unsuitable for
    the gas company’s use or would prohibitively increase the cost of its use.
    Transwestern has not sought such relief.
    TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY 16293
    L.L.C. v. 950.80 Acres of Land, 
    210 F. Supp. 2d 976
    , 979
    (N.D. Ill. 2002), cases interpreting the Seventh Circuit’s
    Northern Border decision and which granted possession to
    gas companies only following judgments of condemnation.
    Transwestern relies upon Northwest Pipeline, because there
    the district court relied heavily on the court’s equitable pow-
    ers to grant a preliminary injunction under the NGA. North-
    west Pipeline Corp. v. The 20’ x 1,430’ Pipeline Right of
    Way, 
    197 F. Supp. 2d 1241
    , 1246 (E.D. Wash. 2002). Trans-
    western argues that the Northwest Pipeline decision cannot be
    reconciled with the district court’s decision in this case. But
    its reliance is misplaced. The court in Northwest Pipeline
    granted the gas company possession only after first deciding
    the gas company’s summary judgment motion, issuing an
    order of condemnation, and requiring the gas company to
    deposit the estimated fair market value of the condemnation.
    
    Id.
     Using the court’s equitable powers after issuing an order
    of condemnation and ensuring the preliminary injunction
    standard is met was proper. The Northwest Pipeline decision
    is also consistent with the district court’s actions here, as
    Transwestern did not file any summary judgment motion
    before seeking immediate possession.
    [8] Given the limited statutory authority afforded by the
    NGA, an order of condemnation must be issued before the
    substantive right of taking accrues. This approach strikes the
    correct balance of requiring the gas company to satisfy all ele-
    ments of the statute, but does not require it to wait for the full
    determination of just compensation for each parcel before the
    district court uses its equitable powers to grant possession.
    Rather, once the order is issued, the district court can require
    Transwestern to deposit the full estimated amount of the tak-
    ing and engage in the standard preliminary injunction analy-
    sis, as it did in Northwest Pipeline.
    Requiring an order of condemnation also protects the due
    process rights of landowners by affording them the opportu-
    16294 TRANSWESTERN PIPELINE v. 17.19 ACRES OF PROPERTY
    nity to show that the gas company is exceeding the authoriza-
    tion under the Certificate, or that the gas company did not
    negotiate in good faith, before losing possession of their prop-
    erties. This protection is particularly necessary when, as here,
    the landowners have challenged the validity of the FERC cer-
    tificate itself in a separate proceeding.9
    IV.     Conclusion
    [9] We hold that the substantive right to condemn under
    § 717f(h) of the NGA ripens only upon the issuance of an
    order of condemnation. At that point, the district court may
    use its equitable powers to grant possession to the holder of
    a FERC certificate if the gas company is able to meet the stan-
    dard for issuing a preliminary injunction.
    AFFIRMED.
    9
    The NGA does not allow landowners to collaterally attack the FERC
    certificate in the district court, it only allows enforcement of its provisions.
    See Williams Nat’l Gas Co. v. City of Oklahoma City, 
    890 F.2d 255
    , 264
    (10th Cir. 1989). As noted above, during the pendency of this appeal,
    FERC denied the petition for rehearing and the appeals to the D.C. Circuit
    have been dismissed.
    

Document Info

Docket Number: 08-15991

Filed Date: 12/11/2008

Precedential Status: Precedential

Modified Date: 10/14/2015

Authorities (22)

williams-natural-gas-company-a-utah-corporation-smith-cogeneration-inc , 890 F.2d 255 ( 1989 )

Southern Natural Gas Co. v. Land, Cullman County , 197 F.3d 1368 ( 1999 )

No. 93-56185 , 13 F.3d 1313 ( 1994 )

Util. L. Rep. P 14,202 Northern Border Pipeline Company v. ... , 144 F.3d 469 ( 1998 )

united-states-v-alisal-water-corporation-toro-water-service-inc-north , 431 F.3d 643 ( 2005 )

Commercial Station Post Office, Inc. v. United States , 48 F.2d 183 ( 1931 )

City of Oakland v. United States , 124 F.2d 959 ( 1942 )

earth-island-institute-sierra-pacific-industries-intervenor-appellee-v , 351 F.3d 1291 ( 2003 )

Guardian Pipeline, L.L.C. v. 950.80 Acres of Land , 210 F. Supp. 2d 976 ( 2002 )

United States v. Parcel of Land With Improvements Thereon ... , 100 F. Supp. 498 ( 1951 )

Northern Border Pipeline Co. v. 127.79 Acres of Land , 520 F. Supp. 170 ( 1981 )

United States v. a Certain Tract or Parcel of Land in ... , 44 F. Supp. 712 ( 1942 )

Humphries v. Williams Natural Gas Co. , 48 F. Supp. 2d 1276 ( 1999 )

Northern Border Pipeline Co. v. 64.111 Acres of Land , 125 F. Supp. 2d 299 ( 2000 )

Catlin v. United States , 65 S. Ct. 631 ( 1945 )

Califano v. Yamasaki , 99 S. Ct. 2545 ( 1979 )

United States v. 93.970 Acres of Land , 79 S. Ct. 1193 ( 1959 )

Grupo Mexicano De Desarrollo, S. A. v. Alliance Bond Fund, ... , 119 S. Ct. 1961 ( 1999 )

United States v. Fisk Building , 99 F. Supp. 592 ( 1951 )

National Fuel Gas Supply Corp. v. 138 Acres of Land in the ... , 84 F. Supp. 2d 405 ( 2000 )

View All Authorities »