MacClarence v. Epa ( 2010 )


Menu:
  •                     FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    BILL MACCLARENCE,                          
    Petitioner,
    v.
    
    No. 07-72756
    UNITED STATES ENVIRONMENTAL                        OPINION
    PROTECTION AGENCY; STEPHEN L.
    JOHNSON,
    Respondents.
    
    On Petition for Review of an Order of the
    Environmental Protection Agency
    Argued and Submitted
    February 5, 2009—Portland, Oregon
    Filed March 4, 2010
    Before: Richard A. Paez and Johnnie B. Rawlinson,
    Circuit Judges, and Raner C. Collins,* District Judge.
    Opinion by Judge Paez
    *The Honorable Raner C. Collins, United States District Judge for the
    District of Arizona, sitting by designation.
    3409
    MACCLARENCE v. USEPA                3411
    COUNSEL
    Robert Ukeiley, Law Office of Robert Ukeiley, Berea, Ken-
    tucky, William M. Eddie, Field Jerger, LLP, Portland, Ore-
    gon, for the petitioner.
    3412               MACCLARENCE v. USEPA
    Ronald J. Tenpas, Assistant Attorney General, John C. Cru-
    den, Deputy Assistant Attorney General, Andrew J. Doyle,
    Attorney, Environment & Natural Resources Division,
    Department of Justice, Washington, DC, Kristi M. Smith,
    Office of General Counsel, Environmental Protection Agency,
    Washington, DC, Julie A. Vergeront, Office of Regional
    Counsel, Region 10, Environmental Protection Agency, Seat-
    tle, Washington, for respondents United States Environmental
    Protection Agency, and Stephen L. Johnson, Administrator,
    United States Environmental Protection Agency.
    OPINION
    PAEZ, Circuit Judge:
    Bill MacClarence petitions this court for review of an order
    by the Environmental Protection Agency Administrator (the
    “Administrator”) denying his request that the Environmental
    Protection Agency (“EPA”) object to the issuance of a Clean
    Air Act Title V permit for pollutant-emitting activities at
    Gathering Center #1 (“GC 1”), an oil and gas processing
    facility in Prudhoe Bay. The Alaska Department of Environ-
    mental Conservation’s (“ADEC”) granted the permit to
    British Petroleum Exploration (Alaska), Inc.’s (“BP”), which
    owns GC 1. We have jurisdiction to review MacClarence’s
    petition for review pursuant to 42 U.S.C. §§ 7661d(b)(2) and
    7607(b)(1). Because the Administrator’s denial of MacClar-
    ence’s request was not arbitrary or capricious, we deny the
    petition.
    I.    Background
    A.   The Prudhoe Bay Unit
    The Prudhoe Bay Unit (PBU) is located on the North Slope
    of Alaska and extends over 300 square miles. It consists of a
    MACCLARENCE v. USEPA                           3413
    series of oil and gas facilities, including thirty-eight drill sites
    or “well pads” and six production centers, as well as support
    facilities for PBU workers. GC 1 is one of the six production
    facilities at the PBU. BP owns approximately 26.35% to
    50.7% of the facilities at the PBU, including GC 1, and oper-
    ates all of the PBU facilities pursuant to an agreement with
    the other owners. Although the PBU oil field is composed of
    a number of different oil leases, those leases have been unit-
    ized or pooled by the State of Alaska so that the field may be
    exploited efficiently.
    The PBU facilities are engaged in a continuum of oil and
    gas refining activities, from drilling to sale.1 Well pads in the
    PBU pump “three-phase” crude oil from the tundra beneath
    the PBU facilities. This oil is transferred to the production
    centers, including GC 1, where it is separated into processed
    crude oil, water, and hydrocarbon gases. The processed crude
    oil is pumped from the production centers to the Trans-Alaska
    Pipeline for sale, while other facilities at the PBU dispose of
    or re-inject the by-products of the production process.
    B.    Title V of the Clean Air Act
    MacClarence petitioned the Administrator to object to a
    final permit issued for GC 1 pursuant to Title V of the Clean
    Air Act (the “CAA”), 42 U.S.C. §§ 7401 et seq. The CAA
    was enacted in 1963 to “protect and enhance the quality of the
    Nation’s air resources so as to promote the public health and
    welfare and the productive capacity of its population.”
    § 7401(b)(1). Built on a scheme of “cooperative federalism,”
    1
    The various functions and the interconnectedness of the PBU facilities
    are too complex to describe fully here. The brief description of the facili-
    ties and activities of the PBU is intended only to provide background and
    context for our opinion. For a more extensive discussion of the PBU oil
    and gas production and processing facilities, see generally Alaska Depart-
    ment of Environmental Conservation Air Quality Operating/Construction
    Permit, Permit No. 182TVP01 (Feb. 17, 2004) (“Revision 1”),
    http://www.dec.state.ak.us/air/ap/docs/182tvp01r1.pdf.
    3414               MACCLARENCE v. USEPA
    the CAA places the onus of enforcement on state and local
    governments, but “provides for ‘Federal financial assistance
    and leadership . . . for the development of cooperative, Fed-
    eral, State, regional, and local programs to prevent and control
    air pollution.’ ” N.Y. Pub. Interest Research Group v. Whit-
    man (NYPIRG I), 
    321 F.3d 316
    , 320 (2d Cir. 2003) (quoting
    42 U.S.C. § 7401(a)(3), (4); Connecticut v. EPA, 
    696 F.2d 147
    , 151 (2d Cir. 1982)).
    The Clean Air Act Amendments of 1990, Pub. L. No. 101-
    549, §§ 501-07, 104 Stat. 2399, 2635-48 (1990), enacted Title
    V of the CAA, which requires facilities that are “major
    sources” of pollutants to obtain operating permits from state-
    run permitting programs that have been approved by EPA.
    See 42 U.S.C. § 7661a. ADEC is Alaska’s EPA-approved
    Title V permitting authority. 66 Fed. Reg. 63,184, 63,184
    (Dec. 5, 2001). Each permit must “include enforceable emis-
    sion limitations and standards, a schedule of compliance, a
    requirement that the permittee submit to the permitting
    authority . . . the results of any required monitoring, and such
    other conditions as are necessary to assure compliance with
    applicable requirements of [the CAA].” 42 U.S.C. § 7661c(a).
    Title V, however, does not itself impose additional substan-
    tive clean air standards. 40 C.F.R. § 70.1(b).
    Title V further provides for both EPA and public review of
    permits. 42 U.S.C. § 7661d; 40 C.F.R. § 70.8(d). After a per-
    mitting authority receives an application for a Title V permit,
    it is required to submit a copy of the permit application and
    the “permit proposed to be issued and issued as a final per-
    mit” to EPA, 42 U.S.C. § 7661d(a)(1)(B), and to provide the
    public with notice and opportunity to comment on the draft
    permit, 40 C.F.R. § 70.7(h). If the permit “contains provisions
    that are determined by the Administrator as not in compliance
    with the applicable requirements of [the CAA],” the Adminis-
    trator, within forty-five days of receiving the proposed permit,
    “shall . . . object to its issuance.” 42 U.S.C. § 7661d(b)(1).
    MACCLARENCE v. USEPA                          3415
    If the EPA does not object to the permit within this time
    frame, however, “any person” may petition the Administrator
    to make an objection within sixty days after the expiration of
    EPA’s period of review. 
    Id. § 7661d(b)(2).
    The petition must
    be based on objections that were made “with reasonable spec-
    ificity during the public comment period” on the draft permit.
    
    Id. “[I]f the
    petitioner demonstrates to the Administrator that
    the permit is not in compliance with the requirements of [the
    CAA],” Title V provides that the Administrator “shall issue
    an objection . . . .” 
    Id. If EPA
    does object to a permit, “the
    permitting authority may not issue the permit unless it is
    revised” to meet the objection. 
    Id. §§ 7661d(b)(3),
    (c).
    C.    Aggregation
    Here, MacClarence petitioned for an objection pursuant to
    § 7661d(b)(2), arguing that the permit did not comply with
    the CAA because ADEC, in the final draft permit for GC 1,
    had not properly “aggregated” stationary sources of air pollu-
    tion in the PBU. Title V and other CAA provisions, such as
    the “prevention of significant deterioration” (PSD) require-
    ments, 42 U.S.C. §§ 7470-79, apply to certain “stationary
    sources” of air pollution. In some cases, several discrete sta-
    tionary sources may be required to be aggregated into one sin-
    gle stationary source for purposes of compliance with these
    provisions.2 For example, as noted above, Title V requires
    every “major source” of air pollution to obtain a permit. 42
    U.S.C. § 7661a(a). The Title V regulations, in turn, define
    “major source” as a “stationary source (or any group of sta-
    tionary sources that are located on one or more contiguous or
    adjacent properties, and are under common control of the
    same person (or persons under common control)) belonging
    to a single major industrial grouping . . . .” 40 C.F.R. § 70.2
    (emphasis added).
    2
    In making “stationary source” determinations, ADEC looks to the defi-
    nitions of “stationary source” outlined in the federal PSD and Title V reg-
    ulations. See Alaska Stat. § 46.14.990(26) (citing 40 C.F.R. 51.116(b)
    (PSD requirements) and 40 C.F.R. § 70.2 (Title V requirements)).
    3416                MACCLARENCE v. USEPA
    Similarly, the PSD requirements, which “ensure that the air
    quality in attainment areas or areas that are already ‘clean’
    will not degrade,” Alaska Dep’t of Envtl. Conservation v.
    EPA, 
    540 U.S. 461
    , 470 (2004) (quoting R. Belden, Clean Air
    Act 43 (2001)), may require the aggregation of stationary
    sources. Under the PSD requirements, “major stationary
    sources” may not be constructed or modified in a significant
    way “unless a permit prescribing emission limitations has
    been issued for the facility.” 
    Id. at 472
    (citing 42 U.S.C.
    §§ 7475(a)(1), 7479(2)(C)). A “major stationary source,” for
    PSD purposes, is a “stationary source” that emits or has the
    potential to emit a certain quantity of pollutants. 42 U.S.C.
    §§ 7479(1), 7602(j). In turn, a “stationary source” is “any
    building, structure, facility, or installation which emits or may
    emit a regulated . . . pollutant.” 40 C.F.R. § 51.166(b)(5). The
    regulations define “[b]uilding, structure, facility, or installa-
    tion” as “all of the pollutant-emitting activities which belong
    to the same industrial grouping, are located on one or more
    contiguous or adjacent properties, and are under the control of
    the same person . . . .” 
    Id. § 51.166(b)(6).
    As the record for this case reveals, the aggregation of
    pollutant-emitting activities for the purposes of designating a
    “major source” or “major stationary source” is not a clear-cut
    task. Under the governing regulations, however, determina-
    tions regarding “major sources” for purposes of issuing Title
    V permits and “major stationary sources” for purposes of
    meeting PSD requirements involve the same analysis; the
    aggregated sources must belong to the same industrial group-
    ing, be located on continuous or adjacent properties, and be
    under common control. See 40 C.F.R. §§ 51.166(b)(6), 70.2.
    Over the years, EPA has provided some guidance on the
    aggregation of pollutant-emitting activities and the designa-
    tion of “major sources” and “major stationary sources.” When
    EPA promulgated regulations for the PSD program in 1980,
    it noted that a “stationary source” should reflect “a common
    sense notion of ‘plant.’ ” 45 Fed. Reg. 52,676, 52,694-95
    (Aug. 7, 1980). EPA has also issued memoranda in order to
    MACCLARENCE v. USEPA                   3417
    provide regional EPA administrators and state permitting
    authorities with guidance in applying aggregation principles
    to designate stationary sources. See, e.g., Memorandum from
    Acting Assistant Administrator, EPA, to Regional EPA
    Administrators, Source Determinations for Oil and Gas Indus-
    tries (Jan. 12, 2007), EPA docket EPA-HQ-OAR-2007-0629-
    0001.pdf,       http://www.regulations.gov/search/Regs/content
    Streamer?objectId=0900006480269a33&disposition=
    attachment&contentType=pdf (withdrawn by Gina McCarthy,
    Assistant Administrator, EPA, to Regional EPA Administra-
    tors, Withdrawal of Source Determinations for Oil and Gas
    Industries (September 22, 2009), EPA docket EPA-HQ-OAR-
    2007-0629-0003.pdf,         http://www.regulations.gov/search/
    Regs/contentStreamer?objectId=0900006480a3309c&
    disposition=attachment&contentType=pdf);        Letter   from
    Director, Air Program, EPA, to Utah Division of Air Quality,
    Response to Request for Guidance in Defining Adjacent with
    Respect to Source Aggregation (May 21, 1998), http://
    www.epa.gov/region07/programs/artd/air/title5/t5memos/util-
    trl.pdf.
    D.   The Permitting Process for GC 1
    With this statutory and regulatory framework in mind, we
    turn to the permitting process for GC 1. In 1997, ARCO, then
    the owner of GC 1, applied to ADEC for a Title V permit.
    ADEC prepared a draft permit and submitted it for public
    comment on February 22, 2002. This initial draft permit did
    not aggregate GC 1 with any other potential pollutant-
    emitting sources in the PBU. The following month, MacClar-
    ence submitted comments on the draft permit, arguing that
    “[a]ll BP units within the Prudhoe Bay Facility” should be
    aggregated in such a way that the Title V permit applied to the
    PBU as a whole, rather than just GC 1. In April 2002, the
    Pacific Northwest Regional Office of the EPA (EPA Region
    10) also submitted “preliminary comments” to ADEC regard-
    ing the GC 1 draft permit. Echoing MacClarence’s concerns,
    EPA stated,
    3418               MACCLARENCE v. USEPA
    [A]bsent a contrary rationale, it is EPA’s position
    that the BP GC 1 facility is part of the larger source
    consisting of all BP units within the Prudhoe Bay
    . . . . [T]he BP facilities are interdependent, located
    on adjacent properties, and are owned or operated by
    the same person under common control.
    ADEC revised the draft permit and submitted a new draft
    permit for public comment in March 2003. ADEC again pro-
    posed to extend coverage of the operations permitted under
    Title V only to GC 1. Significantly, however, ADEC also pro-
    posed a condition that would require BP to aggregate all of
    the pollutant-emitting sources within the PBU “for the pur-
    pose of determining applicability with the modification
    requirements of [Alaska’s approved PSD program].” The
    revised permit’s Statement of Basis explained in detail why
    the PBU in its entirety should be considered a “major station-
    ary source,” referencing CAA provisions and EPA guidance
    on aggregation, and used diagrams to depict the interconnec-
    tedness of the various pollutant-emitting sources within the
    PBU. ADEC concluded by stating that “[t]he individual facili-
    ties at the Prudhoe Bay Unit act as a single integrated produc-
    tion facility for the purpose of delivering crude oil to the
    Trans Alaska Pipeline System . . . .”
    In response to the March 2003 draft permit, BP submitted
    comments requesting that aggregation conditions be com-
    pletely eliminated from the permit. Shortly thereafter, in July
    2003, ADEC reversed course and issued a proposed permit
    that, like the initial draft permit, did not aggregate GC 1 with
    any other PBU facilities. In August 2003, EPA responded to
    this proposed permit by requesting that ADEC
    postpone issuing draft, proposed and final Title V
    permits for those North Slope operations which raise
    aggregation issues until the agencies have come to a
    mutual understanding on an over-arching approach
    to the issue or until either agency has advised the
    MACCLARENCE v. USEPA                      3419
    other that it has decided to forego further attempts to
    reach a mutual understanding.
    BP was included in ADEC’s and EPA’s ensuing conversa-
    tions regarding aggregation of pollutant-emitting sources in
    the North Slope.
    In October 2003, after these discussions concluded, ADEC
    issued a new draft permit that employed a “hub-and-spoke”
    aggregation model. Under this model, ADEC aggregated GC
    1 with the well pads that supply it with three-phase crude oil
    for purposes of Title V and for the PSD requirements. The
    draft permit, however, did not aggregate GC 1 with the rest
    of the PBU facilities as had been requested by MacClarence
    in his March 2002 comments. In a Statement of Basis for “Re-
    vision 1,” discussed infra, ADEC explained that it rejected
    aggregation of the entire PBU facilities because, among other
    things (1) the PBU covers roughly 300 square miles and
    therefore aggregation “stretches the concept of proximity”
    that underlies aggregation determinations; (2) “[t]he complex-
    ity of administering . . . and operating . . . a stationary source
    as large as the PBU without clear corresponding environmen-
    tal benefit argues against” aggregation of the entire PBU; and
    (3) “there [was] no precedent for defining such a large station-
    ary source . . . .”
    When the EPA, in February 2004, did not object to this per-
    mit under 42 U.S.C. § 7661d(b), MacClarence petitioned the
    EPA Administrator to object to the permit. This petition, like
    MacClarence’s March 2002 comments, argued that the permit
    violated the CAA because it did not aggregate all of the
    pollutant-emitting sources in the PBU into one stationary
    source. MacClarence attached to the petition his 2002 com-
    ments, ADEC’s March 2003 Statement of Basis, and EPA’s
    August 2003 letter to ADEC requesting a postponement of
    ADEC’s issuance of any permits involving aggregation issues
    in the North Slope.
    3420                    MACCLARENCE v. USEPA
    After MacClarence submitted his petition, EPA notified
    him that ADEC had issued a revision to the final permit, “Re-
    vision 1.” Revision 1, among other things, “added to the per-
    mit itself the definition of the title V source, which was
    previously only in the statement of basis” and “made minor
    changes to the aggregation discussion in the statement of
    basis.” Pursuant to EPA’s request, MacClarence refiled his
    petition for an objection to the permit on April 14, 2004.3 He
    resubmitted his original petition with a cover letter stating that
    his petition remained unchanged as Revision 1 did not address
    his concerns and did not explain ADEC’s decision to reverse
    course from its March 2003 draft permit that required aggre-
    gation.
    The Administrator denied MacClarence’s request for an
    objection on April 20, 2007.4 MacClarence timely petitioned
    this court for review of EPA’s denial of his request for an
    objection.
    II.    Discussion
    In considering MacClarence’s petition for review, we do
    not decide whether MacClarence’s substantive argument—
    that the CAA requires all pollutant-emitting sources in the
    PBU to be aggregated for purposes of Title V and other sub-
    stantive CAA provisions—is correct. Rather, we consider
    3
    Revision 1 was the version of the final permit to which MacClarence
    responded in his petition to the EPA Administrator. Alaska Department of
    Environmental Conservation Air Quality Operating/Construction Permit,
    Permit No. 182TVP01 (Feb. 17, 2004) (“Revision 1”), http://
    www.dec.state.ak.us/air/ap/docs/182tvp01r1.pdf. ADEC, however, revised
    the permit yet again in August 2005, “Revision 2”. Because MacClarence
    petitioned for an objection prior to Revision 2, any future references to
    “the final permit,” or its Statement of Basis, are to the final permit as mod-
    ified by Revision 1.
    4
    MacClarence does not challenge EPA’s unexplained failure to respond
    to his petition within the sixty-day period required by statute. See 42
    U.S.C. § 7661d(b)(2).
    MACCLARENCE v. USEPA                     3421
    only whether the EPA Administrator erred in determining that
    MacClarence failed to demonstrate, pursuant to 42 U.S.C.
    § 7661d(b)(2), that the final Title V permit for GC 1 did not
    comply with the CAA.
    In denying MacClarence’s request, the Administrator rea-
    soned that MacClarence (1) “failed to provide adequate infor-
    mation to support his claim that the entire PBU should be
    aggregated,” and (2) “failed to demonstrate that the failure to
    aggregate all facilities within the PBU has led to a deficiency
    in the content of the permit.” Because we conclude that we
    may properly uphold the Administrator’s denial of MacClar-
    ence’s petition on the basis of the first ground, we need not
    reach the second.
    A.   Standard of Review
    Our review of the “the reasonableness of [the Administra-
    tor’s] decision-making processes” in denying MacClarence’s
    petition is governed by the Administrative Procedure Act
    (APA). CHW W. Bay v. Thompson, 
    246 F.3d 1218
    , 1226 (9th
    Cir. 2001) (citing Transitional Learning Comm. at Galveston,
    Inc. v. U.S. Office of Pers. Mgmt., 
    220 F.3d 427
    , 430 n.2 (5th
    Cir. 2000)); see Sierra Club v. EPA, 
    346 F.3d 955
    , 961 (9th
    Cir. 2003). Under the APA, we may only set aside an agency
    action if it is “arbitrary, capricious, an abuse of discretion, or
    otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A).
    We review the Administrator’s interpretation of 42 U.S.C.
    § 7661d(b)(2), as expressed in its order denying MacClar-
    ence’s petition, under the principles set forth in Chevron USA
    Inc. v. Natural Res. Def. Council, Inc., 
    467 U.S. 837
    (1984).
    De Jesus Ramirez-Zavala v. Ashcroft, 
    336 F.3d 872
    , 875 (9th
    Cir. 2003).
    B.   MacClarence’s Petition
    [1] This petition for review requires us, for the first time,
    to consider a petitioner’s burden under 42 U.S.C.
    3422                MACCLARENCE v. USEPA
    § 7661d(b)(2) to “demonstrate[ ] to the Administrator that [a
    Title V] permit is not in compliance with the requirements of
    [the CAA].” § 7661d(b)(2). Specifically, we must determine
    whether the Administrator’s interpretation of the word “dem-
    onstrate,” as expressed in his order denying MacClarence’s
    petition, was a permissible construction of § 7661d(b)(2), and
    whether the Administrator’s application of § 7661d(b)(2) to
    the petition was arbitrary and capricious.
    Chevron provides the guiding principles for according def-
    erence to an agency’s interpretation of a statute it administers.
    
    See 467 U.S. at 842
    . Here, it is undisputed that EPA is tasked
    with the administration of the CAA. Therefore, we first
    decide “whether Congress has directly spoken to the precise
    question at issue. If the intent of Congress is clear . . . the
    court, as well as the agency, must give effect to the unam-
    biguously expressed intent of Congress.” 
    Id. at 842-43.
    If,
    however, the statute is ambiguous, “Chevron deference
    applies, ‘when it appears that Congress delegated authority to
    the agency generally to make rules carrying the force of law,
    and that the agency interpretation claiming deference was pro-
    mulgated in the exercise of that authority.’ ” Nw. Ecosystem
    Alliance v. United States Fish & Wildlife Serv., 
    475 F.3d 1136
    , 1141 (9th Cir. 2007) (quoting United States v. Mead
    Corp., 
    533 U.S. 218
    , 226-27 (2001)). Under Chevron defer-
    ence, the agency’s interpretation is valid so long as it “is
    based on a permissible construction of the statute.” 
    Chevron, 467 U.S. at 843
    . When Chevron deference does not apply, we
    are guided by the principles of Skidmore v. Swift, 
    323 U.S. 134
    (1944); “[t]he ‘fair measure of deference’ may then range
    from ‘great respect’ to ‘near indifference,’ depending on ‘the
    degree of the agency’s care, its consistency, formality, and
    relative expertness, and . . . the persuasiveness of the agency’s
    position.’ ” Nw. Ecosystems 
    Alliance, 475 F.3d at 1141
    (quot-
    ing 
    Mead, 533 U.S. at 228
    ).
    [2] Several of our sister circuits have concluded that the
    word “demonstrate” in § 7661d(b)(2) is an ambiguous term.
    MACCLARENCE v. USEPA                    3423
    See Sierra Club v. EPA, 
    557 F.3d 401
    , 406 (6th Cir. 2009);
    Sierra Club v. Johnson (Sierra Club II), 
    541 F.3d 1257
    , 1266
    (11th Cir. 2008); Citizens Against Ruining the Environment v.
    EPA, 
    535 F.3d 670
    , 677-78 (7th Cir. 2008); N.Y. Pub. Interest
    Research Group v. Johnson (“NYPIRG II”), 
    427 F.3d 172
    ,
    179 (2d Cir. 2005). We agree. The word “demonstrate” may
    mean variously, to “point out;” “to manifest clearly, certainly,
    or unmistakably;” or “to make evident or reveal as true by
    reasoning processes, concrete facts and evidence, experimen-
    tation, operation, or repeated examples.” Webster’s Third New
    International Dictionary 600 (1993). As the Eleventh Circuit
    pointed out in Sierra Club II, the plain meaning of the term
    “demonstrate” in § 7661d(b)(2) “does not resolve important
    questions that are part and parcel of the Administrator’s duty
    to evaluate the sufficiency of a petition, for example, the type
    of evidence a petitioner may present and the burden of proof
    guiding the Administrator’s evaluation of when a sufficient
    demonstration has 
    occurred.” 541 F.3d at 1266
    . The ambigu-
    ity of this provision in the statute suggests that Congress has
    left the meaning of “demonstrate” open for EPA to supply a
    reasonable interpretation under Chevron. See NYPIRG 
    I, 321 F.3d at 333
    n.11 (“There clearly is some room for the exercise
    of agency expertise in [§ 7661d(b)(2)] . . . .”).
    [3] Whether we defer to the Administrator’s interpretation
    of “demonstrate” under Chevron’s reasonableness standard or
    Skidmore’s persuasiveness standard, nothing in the Adminis-
    trator’s order denying MacClarence’s petition qualifies as an
    impermissible interpretation of his burden under
    § 7661d(b)(2). The Administrator denied MacClarence’s peti-
    tion, in part, because MacClarence “failed to provide adequate
    information to support his claim that the entire PBU should
    be aggregated . . . .” Specifically, he noted that MacClarence
    “ma[d]e only generalized statements that all facilities in the
    PBU must be aggregated and d[id] not provide adequate refer-
    ences, legal analysis, or evidence in support of these general
    assertions.”
    3424               MACCLARENCE v. USEPA
    [4] This construction of MacClarence’s burden under
    § 7661d(b)(2) is both reasonable and persuasive, and is con-
    sistent with our common understanding of the word “demon-
    strate.” The Administrator’s expectation that MacClarence
    provide “references, legal analysis, or evidence” comports
    with Webster’s definition of “demonstrate”—“to make evi-
    dent or reveal as true by reasoning processes, concrete facts
    and evidence, experimentation, operation, or repeated exam-
    ples.” New International 
    Dictionary, supra, at 600
    . Further,
    the Administrator’s interpretation is consistent with
    § 7661d(b)(2) as a whole, which mandates that the Adminis-
    trator “shall issue an objection” to the permit with which the
    permitting authority must comply, should a petitioner satisfy
    his burden under the statute. See Sierra Club v. Johnson
    (Sierra Club I), 
    436 F.3d 1269
    , 1280 (11th Cir. 2006) (quot-
    ing 42 U.S.C. § 7661d(b)(2)) (holding that the Administra-
    tor’s duty to object to a permit once a petitioner demonstrates
    that it does not comply with the CAA is mandatory, not dis-
    cretionary); NYPIRG 
    I, 321 F.3d at 333
    (same). Because a
    petition that properly demonstrates that a permit is not in
    compliance with the CAA requires the Administrator and
    state permitting authority to take certain action, the Adminis-
    trator’s requirement that MacClarence support his allegations
    with legal reasoning, evidence, and references is reasonable
    and persuasive.
    [5] Thus, the Administrator’s conclusion that MacClarence
    “failed to provide adequate information to support his claim
    that the entire PBU should be aggregated” was not arbitrary
    or capricious. The success of MacClarence’s petition turned
    on his argument that aggregation of the entire PBU pollutant-
    emitting sources was necessary for the permit to comply with
    the CAA and that the final aggregation decision — the hub-
    and-spoke model — did not comply with the CAA. Rather
    than offering a reasoned analysis of why the entire PBU
    should be aggregated or of the deficiencies in the hub-and-
    spoke model, MacClarence merely stated in his petition:
    MACCLARENCE v. USEPA                          3425
    As reinforced by ADEC’s original analysis, shown at
    Attachment 2, the March 7, 2003 version of this per-
    mit complies with all federal requirements for source
    aggregation. ADEC’s rationale for requiring aggre-
    gation is based on EPA directives. By contrast, the
    permit decisions referenced in the final permit are at
    variance with your agency’s own guidance.
    Although MacClarence’s March 2002 comments and
    ADEC’s March 2003 Statement of Basis, which were
    attached to the petition, provided an explanation of why
    aggregation of the entire PBU pollutant-emitting sources was
    necessary to comply with the CAA, he merely alleged that the
    final aggregation decision, the hub-and-spoke model, was “at
    variance with [EPA’s] own guidance.”5 Neither MacClar-
    ence’s petition nor the documents attached to the petition
    address EPA guidance memoranda or directives with which
    the hub-and-spoke model conflicted or explained how the
    hub-and-spoke model contravened such guidance or the CAA.6
    At the end of his petition, MacClarence did challenge
    ADEC’s reliance on permit decisions by other states to sup-
    port its final aggregation decision. His brief discussion of
    these references, however, noted only that the facilities at
    issue in those other permit decisions were dissimilar to the
    PBU, and at best, showed that those permit decisions did not
    support ADEC’s decision to adopt a hub-and-spoke aggrega-
    tion model. MacClarence made no attempt to show that the
    5
    MacClarence argues that the Administrator did not consider the docu-
    ments he attached to his petition in evaluating his arguments and thus pro-
    hibited him from “incorporating by reference” arguments and other
    information. In light of the Administrator’s statement that he considered
    “available information, including . . . information provided by the Peti-
    tioner in his petition,” we are not persuaded by this argument.
    6
    MacClarence’s attempt to challenge the merits of the hub-and-spoke
    aggregation model before this court are unavailing. Our review is limited
    to the record before the Administrator. Asarco, Inc. v. EPA, 
    616 F.2d 1153
    , 1158-60 (9th Cir. 1980).
    3426                MACCLARENCE v. USEPA
    hub-and-spoke model was at “variance” with the CAA or any
    other EPA guidance.
    MacClarence also argues that the Administrator improperly
    faulted him for failing to challenge the reasonableness of
    ADEC’s Statement of Basis for the final permit. In denying
    MacClarence’s petition, the Administrator stated that Mac-
    Clarence “does not provide any argument as to why ADEC’s
    decision not to aggregate [the entire PBU], which is described
    in great detail in the Statement of Basis for the final Revision
    1 permit, is unreasonable.” MacClarence argues that this
    statement reflects an improper interpretation of his burden
    under § 7661d(b)(2) by requiring him to show the “unreason-
    ableness” of ADEC’s rationale for employing the hub-and-
    spoke model in the final permit, rather than the final permit’s
    noncompliance with the CAA.
    [6] We reject this argument. The Administrator’s order
    denying MacClarence’s petition properly sets forth MacClar-
    ence’s burden under § 7661d(b)(2), stating that “[t]o justify
    exercise of an objection by EPA to a title V permit pursuant
    to [§ 7661d(b)(2)], a petitioner must demonstrate that the per-
    mit is not in compliance with the requirements of the CAA”
    and later concluding that “the general allegations of the Peti-
    tioner in the April 2004 Petition . . . fail to demonstrate a basis
    for Petitioner’s claim that Revision 1 to the GC 1 Permit vio-
    lates the CAA . . . .” In light of the Administrator’s proper
    recitation of MacClarence’s burden, we view the Administra-
    tor’s statement that MacClarence should have shown that
    ADEC’s explanation for its aggregation decision was unrea-
    sonable, as requiring MacClarence to challenge the basis or
    reasons for ADEC’s final decision and to demonstrate that the
    permit did not comply with the CAA. We see nothing wrong
    with the Administrator’s expectation that MacClarence
    needed to challenge this reasoning. MacClarence’s petition
    relied on ADEC’s March 2003 Statement of Basis. ADEC,
    however, rejected the aggregation decisions reflected in that
    Statement of Basis and explained why it did so in the new
    MACCLARENCE v. USEPA                     3427
    Statement of Basis for the final permit. The Administrator
    reasonably expected MacClarence to challenge that explana-
    tion.
    [7] Further, the Administrator’s conclusion that MacClar-
    ence did not challenge ADEC’s reasoning for the final permit
    was not arbitrary or capricious. ADEC’s final Statement of
    Basis explained how the hub-and-spoke aggregation model
    complied with the CAA, why complete aggregation of the
    facilities in the PBU was impractical and unprecedented, and
    why the hub-and-spoke model was a better alternative than
    complete aggregation. Although MacClarence asserted in his
    petition that the out-of-state permit decisions cited by ADEC
    did not support its final aggregation decision, his petition
    failed to demonstrate that the hub-and-spoke aggregation
    model did not comply with the CAA. More importantly, Mac-
    Clarence failed to challenge ADEC’s reasoning that “[t]he
    complexity of administering . . . and operating . . . a stationary
    source as large as the PBU without clear corresponding envi-
    ronmental benefit argues against [the aggregation of the entire
    PBU].”
    Therefore, we conclude that the Administrator’s determina-
    tion that MacClarence did not demonstrate that the entire
    PBU should be aggregated did not constitute an impermissible
    interpretation of MacClarence’s burden under 42 U.S.C.
    § 7661d(b)(2), to “demonstrate” that ADEC’s final Title V
    permit for BP’s GC 1 did not comply with the CAA, nor was
    it arbitrary or capricious.
    PETITION DENIED.
    

Document Info

Docket Number: 07-72756

Filed Date: 3/4/2010

Precedential Status: Precedential

Modified Date: 10/14/2015

Authorities (17)

The Sierra Club v. Stephen L. Johnson , 436 F.3d 1269 ( 2006 )

Sierra Club v. Johnson , 541 F.3d 1257 ( 2008 )

New York Public Interest Research Group, Inc. v. Stephen L. ... , 427 F.3d 172 ( 2005 )

state-of-connecticut-v-environmental-protection-agency-anne-m-gorsuch , 696 F.2d 147 ( 1982 )

Transitional Learnin v. US OPM , 220 F.3d 427 ( 2000 )

new-york-public-interest-research-group-v-christine-todd-whitman-in-her , 321 F.3d 316 ( 2003 )

northwest-ecosystem-alliance-center-for-biological-diversity-tahoma-audubon , 475 F.3d 1136 ( 2007 )

Asarco, Inc. v. U. S. Environmental Protection Agency , 616 F.2d 1153 ( 1980 )

Skidmore v. Swift & Co. , 65 S. Ct. 161 ( 1944 )

Sierra Club, Imperial County Air Pollution Control District,... , 346 F.3d 955 ( 2003 )

Maria De Jesus Ramirez-Zavala v. John Ashcroft, Attorney ... , 336 F.3d 872 ( 2003 )

Citizens Against Ruining the Environment v. Environmental ... , 535 F.3d 670 ( 2008 )

Chw West Bay, Dba Seton Medical Center v. Tommy g.thompson, ... , 246 F.3d 1218 ( 2001 )

Sierra Club v. United States Environmental Protection Agency , 557 F.3d 401 ( 2009 )

United States v. Mead Corp. , 121 S. Ct. 2164 ( 2001 )

Alaska Department of Environmental Conservation v. ... , 124 S. Ct. 983 ( 2004 )

Chevron U. S. A. Inc. v. Natural Resources Defense Council, ... , 104 S. Ct. 2778 ( 1984 )

View All Authorities »