Columbia Riverkeeper v. U.S. Coast Guard , 761 F.3d 1084 ( 2014 )


Menu:
  •                FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    COLUMBIA RIVERKEEPER;                    No. 12-73385
    COLUMBIA-PACIFIC COMMONSENSE;
    WAHKIAKUM FRIENDS OF THE
    RIVER,
    Petitioners,         OPINION
    v.
    UNITED STATES COAST GUARD,
    Respondent,
    LNG DEVELOPMENT COMPANY,
    LLC, DBA Oregon LNG,
    Respondent-Intervenor.
    On Petition for Review of an Order of the
    United States Coast Guard
    Argued and Submitted
    May 12, 2014—Portland, Oregon
    Filed August 5, 2014
    Before: Arthur L. Alarcón, A. Wallace Tashima,
    and Sandra S. Ikuta, Circuit Judges.
    Opinion by Judge Ikuta
    2      COLUMBIA RIVERKEEPER V. U.S. COAST GUARD
    SUMMARY*
    Jurisdiction / U.S. Coast Guard
    The panel dismissed due to lack of jurisdiction a petition
    for review of the U.S. Coast Guard’s issuance of a letter of
    recommendation to the Federal Energy Regulatory
    Commission regarding the suitability of the Columbia River
    for vessel traffic associated with a proposed liquified gas
    facility and pipeline.
    The panel concluded that the court lacked jurisdiction
    because the Coast Guard’s letter of recommendation was not
    in practice a final agency action under 15 U.S.C. § 717r(d)(1)
    of the Natural Gas Act, which authorizes judicial review of
    final agency orders and actions that “issue, condition, or deny
    any permit, license, concurrence, or approval.”
    COUNSEL
    Thomas C. Buchele (argued) and Aubrey Baldwin, Earthrise
    Law Center, Portland, Oregon; Lauren Goldberg, Columbia
    Riverkeeper, Hood River, Oregon, for Petitioners.
    Brian C. Toth (argued) and Robert J. Lundman, Attorneys,
    Appellate Section; Robert G. Dreher, Acting Assistant
    Attorney General, United States Department of Justice,
    Environment & Natural Resources Division, Washington,
    D.C.; John T. Dewey, Curtis E. Borland, Frank G. Nolan, and
    *
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD              3
    Bronwyn Douglass, United States Coast Guard, Washington,
    D.C., for Respondent.
    Charles Scott, Fulbright & Jaworski, New York, New York,
    for Respondent-Intervenor.
    OPINION
    IKUTA, Circuit Judge:
    This appeal addresses one of the several administrative
    proceedings in which Columbia Riverkeeper, Columbia-
    Pacific Common Sense, and Wahkiakum Friends of the River
    (collectively Riverkeeper) have attempted to intervene in an
    effort to prevent LNG Development Company, LLC (doing
    business as Oregon LNG), from constructing a liquefied
    natural gas facility and pipeline along the Columbia River in
    Oregon. As part of the lengthy terminal siting process, the
    Coast Guard provided the Federal Energy Regulatory
    Commission (FERC) with a letter of recommendation
    (sometimes referred to as a LOR) regarding the suitability of
    the waterway for vessel traffic associated with the proposed
    facility. Riverkeeper petitions for review of the Coast
    Guard’s issuance of the letter of recommendation, contending
    that we have jurisdiction under 15 U.S.C. § 717r(d)(1), which
    authorizes judicial review of agency orders and actions that
    “issue, condition, or deny any permit, license, concurrence,
    or approval.” Because the letter of recommendation is not
    such an order or action, we conclude we lack jurisdiction and
    dismiss the petition for review.
    4     COLUMBIA RIVERKEEPER V. U.S. COAST GUARD
    I
    Liquefied natural gas (LNG) is natural gas that has been
    “supercooled into liquid form” and “reheated back into gas
    form at natural gas terminals” for transport to customers.
    Wash. Gas Light Co. v. FERC, 
    532 F.3d 928
    , 929 n.1 (D.C.
    Cir. 2008). Although the process for liquefying natural gas
    has been known since the 19th Century and used
    commercially since the 1950s, interest in transporting LNG
    for commercial use increased first in the 1970s due to
    declines in gas reserves, and again more recently. See Jacob
    Dweck, David Wochner, & Michael Brooks, Liquefied
    Natural Gas (LNG) Litigation After the Energy Policy Act of
    2005: State Powers in LNG Terminal Siting, 
    27 Energy L.J. 473
    , 473 (2006). The supercooling process reduces the
    volume of the natural gas to 1/600th of natural gas in vapor
    form, and, according to the Coast Guard, makes transporting
    liquefied natural gas “the most economical way to import
    natural gas from overseas.” Once natural gas has been
    liquefied, it can be transported in an LNG tanker to an LNG
    import terminal, which receives, stores and processes the
    LNG. These facilities are “typically sited in coastal areas
    with shipping access.” AES Sparrows Point LNG, LLC v.
    Smith, 
    527 F.3d 120
    , 124 (4th Cir. 2008). Because activities
    involving LNG have a potential for explosions, fires, and
    spills, federal, state, and local governments have taken steps
    to regulate the siting and operation of LNG terminal facilities.
    A
    To understand the role of the Coast Guard’s letter of
    recommendation in the regulatory process, it is necessary to
    review the historical development of the legal framework for
    siting LNG terminal facilities. Prior to 2005, different federal
    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD               5
    agencies allocated responsibility for regulating LNG terminal
    facilities amongst themselves by means of interagency
    agreements, with little guidance from Congress. The Natural
    Gas Act of 1938 (NGA) authorized FERC’s predecessor
    agency (the Federal Power Commission) to approve the
    import and export of natural gas, 15 U.S.C. § 717b (1938),
    and the extension and improvement of transportation
    facilities, 15 U.S.C. § 717f (1938), but did not reference LNG
    terminal facility siting responsibility. Beginning in 1968,
    Congress enacted a series of pipeline safety statutes that gave
    the Department of Transportation (DOT) authority to issue
    minimum safety standards for siting new liquefied natural gas
    pipeline facilities, 
    49 U.S.C. § 60103
    . DOT and FERC
    ultimately entered into an interagency agreement to allocate
    their respective responsibilities. See Memorandum of
    Understanding between the Department of Transportation and
    the Federal Energy Regulatory Commission regarding
    Liquefied Natural Gas Transportation Facilities (1985).
    In addition, the Coast Guard asserted authority over siting
    decisions affecting the safety and security of port areas and
    navigable waterways under the Ports and Waterways Safety
    Act, 
    33 U.S.C. §§ 1221
    –1236, the Magnuson Act of 1950,
    
    50 U.S.C. § 191
    , and Executive Order No. 10173, 
    15 Fed. Reg. 7005
     (Oct. 18, 1950). In early 1978, the Coast Guard
    and a DOT subagency (the Office of Pipeline Safety
    Operation of the Materials Transportation Bureau) entered
    into a memorandum of understanding regarding the division
    of regulatory responsibility over LNG terminals. Believing
    that the agreement gave it broad regulatory authority, the
    Coast Guard commenced a rulemaking proceeding and
    proposed regulations that would require any person siting an
    LNG facility to obtain a “use permit” from the Coast Guard.
    Liquefied Natural Gas Facilities, 
    43 Fed. Reg. 34362
    , 34365
    6    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD
    (Aug. 3, 1978) (proposed 
    33 C.F.R. § 126.2012
    ). After
    further congressional action suggested that the Coast Guard’s
    view of its regulatory authority was too broad, the Coast
    Guard reduced its ambition.         Pursuant to a revised
    memorandum of understanding with DOT, signed in 1986,
    the Coast Guard proposed revised regulations replacing its
    proposed “use permit” requirement with a requirement that a
    project proponent merely secure a letter of recommendation
    from the Coast Guard. Liquefied Natural Gas Waterfront
    Facilities, 
    53 Fed. Reg. 3370
    , 3377 (Feb. 5, 1988) (proposed
    
    33 C.F.R. § 127.009
    ).
    Beginning in the 1990s, there was a rapid increase in
    efforts to site LNG import terminals. In response to growing
    safety and environmental concerns, a number of states
    claimed authority to regulate LNG facilities under specific
    state LNG statutes or under general environmental, zoning, or
    construction laws. See Parfomake & Vann, Congressional
    Research Service, Liquefied Natural Gas (LNG) Import
    Terminals: Siting, Safety, and Regulation, at 16–17 (Dec. 14,
    2009); see also, e.g., Weaver’s Cove Energy, LLC v. R.I.
    Coastal Res. Mgmt. Council, 
    589 F.3d 458
    , 472–73 (1st Cir.
    2009); AES Sparrows Point LNG, 
    527 F.3d at 124
    . California
    also asserted exclusive authority to regulate LNG facilities
    that did not impact interstate commerce, claiming that FERC
    lacked authority under the NGA to regulate such sites. See,
    e.g., Re: Sound Energy Solutions, Notice of Intervention and
    Protest of the Public Utilities Commission of the State of
    California, at 7–9, FERC Docket No. CP04-58-000 (Feb. 23,
    2004).
    In 2004, FERC, the Coast Guard, and a DOT subagency
    (the Research and Special Programs Administration)
    responded to the terrorist events of September 11, 2001 by
    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD                           7
    entering into another interagency agreement to divide
    regulatory responsibility for the safety and security review of
    waterfront LNG facilities. This agreement confirmed that
    FERC had lead regulatory authority for the siting and
    construction of onshore LNG facilities. The agencies also
    agreed that FERC would be the lead agency for preparing an
    environmental impact statement (EIS) under the National
    Environmental Policy Act (NEPA), 1 
    42 U.S.C. §§ 4321
    –4370h.
    In 2005, consistent with this 2004 interagency agreement,
    the Coast Guard issued a “Navigation and Vessel Inspection
    Circular,” NVIC 05-05, providing guidance for persons
    “seeking a permit to build and operate a shore-side LNG
    terminal.” The circular confirmed that FERC was responsible
    for authorizing the siting and construction of onshore LNG
    facilities, and was the lead agency for the NEPA process.
    The circular stated that the Coast Guard would serve as a
    cooperating agency under NEPA, see 
    40 C.F.R. § 1501.6
    , and
    would provide FERC with a letter of recommendation (as
    required in the Coast Guard’s 1988 regulations) that set forth
    its formal evaluation of the suitability of the waterway for
    LNG marine traffic. According to the Coast Guard, issuing
    such a letter of recommendation was a “federal action which
    1
    For all “major Federal actions significantly affecting the quality of the
    human environment” the responsible official must conduct environmental
    analyses pursuant to NEPA. 
    42 U.S.C. § 4332
    (C). Such analysis must
    include a “full and fair discussion of [the action’s] significant
    environmental impacts and shall inform decisionmakers and the public of
    the reasonable alternatives which would avoid or minimize adverse
    impacts or enhance the quality of the human environment.” 
    40 C.F.R. § 1502.1
    . “Major federal actions” include “projects and programs entirely
    or partly financed, assisted, conducted, regulated, or approved by federal
    agencies.” 
    40 C.F.R. § 1508.18
    (a).
    8     COLUMBIA RIVERKEEPER V. U.S. COAST GUARD
    requires compliance with NEPA” to the same extent as
    FERC’s authorization for construction and operation of an
    LNG facility.
    Just a few months later, Congress enacted the Energy
    Policy Act (EPAct) of 2005, Pub. L. No. 109-58, 
    119 Stat. 594
    , which finally clarified Congress’s intent regarding the
    division of responsibility for siting and operating LNG
    terminal facilities. The EPAct resolved a number of
    important issues. First, the Act amended the applicable
    section of the Natural Gas Act to give FERC “the exclusive
    authority to approve or deny an application for the siting,
    construction, expansion, or operation of an LNG terminal,”
    
    id.,
     § 311, 119 Stat. at 686, codified at 15 U.S.C. § 717b(e)(1)
    (emphasis added), thereby precluding other federal or state
    agencies from asserting such authority.
    Second, in response to the states’ interest in having some
    control over LNG import terminals within their jurisdiction,
    Congress took a compromise position. Although Congress’s
    grant of “exclusive authority” to FERC in siting decisions
    precluded the states’ imposition of state law requirements, the
    EPAct preserved the states’ authority under several federal
    environmental laws to require project proponents to obtain a
    state compliance certification. Id., § 311, 119 Stat. at 686,
    codified at 15 U.S.C. § 717b(d). But to prevent states from
    using this authority to block LNG projects completely, see
    Dweck, Wochner, & Brooks, supra, at 483–85 (examining
    Connecticut’s successful efforts to block the Islander East
    pipeline project using its water quality certification authority
    under the CWA), the EPAct allowed for federal judicial
    review of an order or action of a “State administrative agency
    acting pursuant to Federal law to issue, condition, or deny any
    permit, license, concurrence, or approval,” Pub. L. No. 109-
    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD               9
    58, § 313, 119 Stat. at 689–90, codified at 15 U.S.C.
    § 717r(d)(1); see Islander E. Pipeline Co. v. Conn. Dep’t of
    Envtl. Prot., 
    482 F.3d 79
    , 85 (2d Cir. 2006) (stating that
    legislative history confirms that this provision was enacted to
    allow expedited federal judicial review of a state’s denial of
    a required federal permit); see also Dweck, Wochner, &
    Brooks, supra, at 482–83 (noting that the conflict between
    Islander East and Connecticut led Congress to enact
    § 717r(d)).
    Finally, the EPAct confirmed that FERC was the “lead
    agency for the purposes of coordinating all applicable Federal
    authorizations and for the purposes of complying with”
    NEPA. Pub. L. No. 109-58, § 313, 119 Stat. at 689, codified
    at 15 U.S.C. § 717n(b)(1). It required FERC to promulgate
    regulations for NEPA compliance that require a pre-filing of
    LNG import terminal siting applications. Id., § 311, 119 Stat.
    at 687, codified at 15 U.S.C. § 717b-1(a).
    Although the EPAct did not speak directly to the Coast
    Guard’s role in siting LNG facilities, after the EPAct’s
    enactment, the Coast Guard revisited its internal procedures,
    and issued a new “Navigation and Vessel Inspection
    Circular,” NVIC 05-08, on December 22, 2008. Now
    understanding that its letter of recommendation was not a
    final decision, but rather mere advice to FERC (the agency
    with exclusive authority to make all siting decisions under the
    EPAct), the Coast Guard determined its letter of
    recommendation did not “constitute a permitting action and
    must not impose requirements or conditions mandated by the
    Coast Guard.” Accordingly, the Coast Guard no longer
    deemed its letter of recommendation to require separate
    compliance with NEPA. In 2010, Congress confirmed this
    approach. In § 813 of the Coast Guard Authorization Act of
    10    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD
    2010, Congress required “the Secretary of the department in
    which the Coast Guard is operating” to “make a
    recommendation, after considering recommendations made
    by the States, to the Federal Energy Regulatory Commission
    as to whether the waterway to a proposed waterside liquefied
    natural gas facility is suitable or unsuitable for the marine
    traffic associated with such facility.” Pub. L. No. 111-281,
    § 813, 
    124 Stat. 2905
    , 2999. This language confirmed
    Congress’s intent to limit the Coast Guard’s role in licensing
    LNG facilities to issuing letters of recommendation.
    B
    Accordingly, by 2009 (the year the Coast Guard issued
    the letter of recommendation in this case), the regulatory
    framework for a party seeking to site an LNG facility was as
    follows. FERC was the exclusive siting authority and “lead
    agency” under NEPA. 15 U.S.C. § 717n(b)(1). FERC
    required an applicant to engage in a pre-filing procedure
    before filing an application. See 
    18 C.F.R. §§ 153.12
    , 157.21
    (2009). Among other pre-filing steps, the applicant had to
    file a letter of intent and waterway suitability assessment with
    the captain of the port2 of the zone in which the facility would
    be located, pursuant to 
    33 C.F.R. § 127.007
     (2009) and 
    18 C.F.R. § 157.21
     (2009). After reviewing the letter of intent
    and accompanying assessment, the captain of the port would
    issue a letter of recommendation regarding the proposed
    facility. 
    33 C.F.R. § 127.009
     (2009). Under Coast Guard
    regulations, a person “directly affected” by the letter of
    recommendation could “request reconsideration by the Coast
    Guard officer responsible,” 
    id.
     § 127.015(a) (2009), and
    2
    A “captain of the port” is the officer so designated by the
    Commandant of the Coast Guard. 
    14 U.S.C. § 634
    (a).
    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD                       11
    pursue two additional levels of administrative review, 
    id.
    § 127.015 (2009).3
    After the project proponent filed an application with
    FERC, FERC would undertake an extensive review and
    consultation process with various federal, state, and local
    agencies, as well as private parties, and also convene public
    hearings. See 15 U.S.C. §§ 717b(e)(2)(B), 717b-1. This
    process included the work necessary to comply with NEPA.
    Other state and federal cooperating agencies assist FERC in
    preparing an EIS. The project proponent was required to
    obtain all necessary permits and approvals from state and
    other federal bodies, and could challenge the denial of any
    permits or approvals required under federal law in a federal
    court of appeals. See id. § 717r(d)(1). Once this process was
    completed, FERC could issue a final decision approving or
    denying the application. See id. § 717b(e)(2). FERC could
    approve the application “in whole or part, with such
    modifications and upon such terms and conditions” as it
    found necessary and appropriate. Id. § 717b(e)(3).
    Upon FERC’s issuance of the order, any person could
    apply for rehearing within 30 days. Id. § 717r(a). Within 60
    days of FERC’s order on the application for rehearing, an
    aggrieved party could obtain review of the order in the court
    3
    In 2012, the Coast Guard amended its regulations to provide that the
    letter of recommendation is not appealable because it “is a
    recommendation from the [captain of the port] to the agency having
    jurisdiction” and “does not constitute agency action for the purpose of
    § 127.015 or the Administrative Procedure Act.” 
    33 C.F.R. § 127.009
    (b)
    (2012). That regulation does not apply retroactively. See 
    id.
     § 127.009(e)
    (2012).
    12      COLUMBIA RIVERKEEPER V. U.S. COAST GUARD
    of appeals “wherein the natural-gas company to which the
    order relates is located” by filing a written petition. Id.
    § 717r(b).
    II
    We now turn to the facts of this case. In 2007, Oregon
    LNG began the pre-filing process: It made an initial filing
    with FERC and filed a letter of intent and a preliminary
    waterway suitability assessment with the captain of the port
    for Portland for a proposed LNG terminal and pipeline. The
    letter stated that Oregon LNG intended to construct an LNG
    facility on the East Skipanon Peninsula, near the confluence
    of the Skipanon and the Columbia River in Warrenton,
    Oregon. In August 2007, FERC published a notice of intent
    to prepare an EIS for the East Skipanon LNG terminal. LNG
    Development Company, LLC and Oregon Pipeline Company;
    Notice of Intent, 
    72 Fed. Reg. 50356
     (Aug. 31, 2007).
    Oregon LNG filed its formal application for the East
    Skipanon LNG terminal with FERC in October 2008,
    prompting FERC to issue a notice of application. LNG
    Development Company, LLC (d/b/a Oregon LNG); Oregon
    Pipeline Company, LLC; Notice of Applications, 
    73 Fed. Reg. 65301
     (Nov. 3, 2008). Riverkeeper and other
    environmental organizations intervened in the FERC
    proceedings pursuant to 
    18 C.F.R. § 385.214
     on November
    17, 2008.4
    On April 24, 2009, the captain of the port issued the letter
    of recommendation at issue in this case, and the
    accompanying analysis for Oregon LNG’s East Skipanon
    4
    The FERC proceedings are ongoing.
    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD              13
    LNG terminal, pursuant to 
    33 C.F.R. § 127.009
    . The letter
    stated the captain’s determination “that the applicable
    portions of the Columbia River and its approaches are not
    currently suitable, but could be made suitable for the type and
    frequency of LNG marine traffic associated with this
    project.” The letter of recommendation included the
    following statement:
    While this letter has no enforcement status,
    the determinations, analysis, and ultimate
    recommendation as to the suitability of this
    waterway, as contained in this letter, would be
    referenced in concert with a Captain of the
    Port Order, should an LNG transit be
    attempted along this waterway without full
    implementation of the risk mitigation
    measures.
    The analysis accompanying the letter listed additional
    mitigation measures that were recommended “to responsibly
    manage the safety and security risks” of the project, while
    acknowledging that the specifics of each suggested mitigation
    measure would require “further development through the
    creation of an Emergency Response Plan as well as a Transit
    Management Plan.”
    On May 22, 2009, Riverkeeper and other intervenors
    requested reconsideration of the letter of recommendation
    under 
    33 C.F.R. § 127.015
    (a) (2009), on the ground that the
    Coast Guard had failed to comply with NEPA and the
    14     COLUMBIA RIVERKEEPER V. U.S. COAST GUARD
    Endangered Species Act (ESA),5 
    16 U.S.C. §§ 1531
    –44. The
    captain of the port denied the motion for reconsideration on
    July 9, 2009, and Riverkeeper filed an administrative appeal,
    see 
    33 C.F.R. § 127.015
    (b)(1) (2009), which was denied by
    a district commander on December 2, 2010.
    Thereafter, an assistant commandant denied
    Riverkeeper’s second administrative appeal, see 
    33 C.F.R. § 127.015
    (c), on August 25, 2012. In his August 25th
    decision letter, the assistant commandant stated that issuance
    of the letter of recommendation was not an agency action
    under the ESA or Administrative Procedure Act (APA), or a
    “major federal action” under NEPA, because its issuance
    “carries no legal significance in and of itself,” The letter of
    recommendation was “not a condition precedent for and does
    not bar FERC” from authorizing the East Skipanon LNG
    terminal without adopting the captain of the port’s
    recommendations or incorporating any of the mitigation
    measures. The letter does not “impose any legal requirement
    on any party to comply with” its recommendations; it is not
    legally binding on the Coast Guard, any other government
    agency, or Oregon LNG. Nor does the letter have an impact
    on vessel traffic, because “[t]he issuance of an LOR neither
    authorizes, nor prohibits, an LNG carrier from conducting a
    transit of the waterway” and vessels are not required to obtain
    Coast Guard transit permits. Rather, the issuance of a captain
    of the port letter “is separate and distinct from the
    5
    The ESA requires each federal agency to “insure that any action
    authorized, funded, or carried out by such agency . . . is not likely to
    jeopardize the continued existence of any endangered species or
    threatened species or result in the destruction or adverse modification of
    habitat of such species which is determined by the Secretary.” 
    16 U.S.C. § 1536
    (2).
    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD             15
    recommendations provided in an LOR, which are not
    enforceable, and the [captain of the port] is not bound by the
    recommendations contained in the LOR.”
    Riverkeeper then filed a petition for review here,
    challenging the letter of recommendation and the August 25,
    2012 decision pursuant to 15 U.S.C. § 717r(d)(1) of the
    Natural Gas Act. Oregon LNG intervened in the proceedings.
    III
    As a threshold matter, we must determine whether
    § 717r(d)(1) gives us jurisdiction to review Riverkeeper’s
    challenge to the letter of recommendation and the Coast
    Guard’s final denial of Riverkeeper’s administrative appeal.
    Riverkeeper contends that in enacting § 717r(d)(1), Congress
    intended to create an exception to the general rule that
    “review of agency action is typically located in the district
    courts under the APA absent a specific statutory provision to
    the contrary,” Cal. Energy Comm’n v. Dep’t of Energy,
    
    585 F.3d 1143
    , 1148 (9th Cir. 2009). We review questions
    regarding our jurisdiction de novo. Sandoval-Luna v.
    Mukasey, 
    526 F.3d 1243
    , 1245 (9th Cir. 2008) (per curiam).
    “It is to be presumed that a cause lies outside [of federal
    courts’] limited jurisdiction, and the burden of establishing
    the contrary rests upon the party asserting jurisdiction.”
    Kokkonen v. Guardian Life Ins. Co. of Am., 
    511 U.S. 375
    , 377
    (1994) (citations omitted).
    A
    We begin with the text of the jurisdictional statute, which
    provides in relevant part:
    16    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD
    The United States Court of Appeals for the
    circuit in which a facility subject to section
    717b of this title . . . is proposed to be
    constructed, expanded, or operated shall have
    original and exclusive jurisdiction over any
    civil action for the review of an order or
    action of a Federal agency (other than the
    Commission) or State administrative agency
    acting pursuant to Federal law to issue,
    condition, or deny any permit, license,
    concurrence, or approval (hereinafter
    collectively referred to as “permit”) required
    under Federal law . . . .
    15 U.S.C. § 717r(d)(1).
    The statute does not define the terms “order or action” or
    “permit, license, concurrence, or approval,” and so we
    interpret these words according to “their ordinary,
    contemporary, common meaning.” Transwestern Pipeline
    Co. v. 17.19 Acres of Prop. Located in Maricopa Cnty.,
    
    627 F.3d 1268
    , 1270 (9th Cir. 2010) (internal quotation marks
    omitted). In making this interpretation, we give due
    consideration to the context of these words “with a view to
    their place in the overall statutory scheme.” Satterfield v.
    Simon & Schuster, Inc., 
    569 F.3d 946
    , 953 (9th Cir. 2009)
    (internal quotation marks omitted).
    Neither we nor our sister circuits have defined the phrase
    “order or action” in § 717r(d)(1). In interpreting statutes
    authorizing judicial review of agency decisions, however, the
    Supreme Court has held that “[t]he strong presumption is that
    judicial review will be available only when agency action
    becomes final.” Bell v. New Jersey, 
    461 U.S. 773
    , 778 (1983)
    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD              17
    (holding that a statute allowing judicial review of “any
    action” by the Secretary of Education gives federal courts
    jurisdiction only over orders or actions that are final); see
    also FPC v. Metro. Edison Co., 
    304 U.S. 375
    , 383–84 (1938)
    (holding that the word “order” in a section of the Federal
    Power Act substantially identical to § 717r(b) refers only to
    final orders). This long-standing rule of construction reflects
    the Supreme Court’s inference that Congress generally does
    not intend to “afford[] opportunity for constant delays in the
    course of the administrative proceeding,” such as would arise
    if courts could review every interim agency order or action.
    Metro. Edison, 
    304 U.S. at 383
    .
    Nothing in § 717r(d)(1) overcomes this “strong
    presumption.” Bell, 
    461 U.S. at 778
    . Congress’s intent to
    authorize judicial review over only final orders or actions is
    strongly supported by the language of § 717r(d)(1), which
    limits judicial review to those agency decisions that “issue,
    condition, or deny any permit, license, concurrence, or
    approval,” the sort of final decisions that occur at the
    conclusion of an administrative process. Further, reading
    § 717r(d)(1) as limiting judicial review to final agency
    decisions is consistent with the long-standing interpretation
    of § 717r(b), a related section of the same statute. Although
    § 717r(b) permits federal court review of “an order” issued by
    FERC, the Supreme Court (as well as our sister circuits and
    our own precedents) read this language as authorizing judicial
    review only over final orders. See Consol. Gas Supply Corp.
    v. FERC, 
    611 F.2d 951
    , 958 (4th Cir. 1979) (considering
    § 717r(b)); Atlanta Gas Light Co. v. FPC, 
    476 F.2d 142
    , 147
    (5th Cir. 1973) (same); cf. Metro. Edison Co., 
    304 U.S. at
    383–84 (considering language in the Federal Power Act,
    16 U.S.C. § 825l(b), which is substantially identical to
    § 717r(b)); The Steamboaters v. FERC, 
    759 F.2d 1382
    ,
    18       COLUMBIA RIVERKEEPER V. U.S. COAST GUARD
    1387–88 (9th Cir. 1985) (same); Papago Tribal Util. Auth. v.
    FERC, 
    628 F.2d 235
    , 238 (D.C. Cir. 1980) (same). In adding
    § 717r(d)(1) to § 717r when it enacted the EPAct, Congress
    did not give any sign it intended federal courts to exercise a
    broader scope of review over non-FERC decisions than over
    FERC decisions. Finally, the presumption that Congress
    intended to authorize judicial review over only final agency
    decisions is supported by the same considerations relied on
    by the Supreme Court in Metropolitan Edison Co.:
    construing § 717r(d)(1) as allowing judicial review of every
    interim action of a state or federal agency would “do violence
    to the manifest purpose of the provision,” 
    304 U.S. at 384
    ,
    which was to expedite siting decisions, see Islander E.
    Pipeline Co., 
    482 F.3d at 85
    . Accordingly, we conclude that
    § 717r(d) authorizes judicial review only over orders or
    actions that are “final.”6 An action or order is “final when it
    imposes an obligation, denies a right, or fixes some legal
    relationship.” City of Fremont, 336 F.3d at 914 (internal
    quotation marks omitted); see also Or. Natural Desert Ass’n
    v. U.S. Forest Serv., 
    465 F.3d 977
    , 986–87 (9th Cir. 2006)
    (same); Atlanta Gas, 
    476 F.2d at 147
     (noting an order
    reviewable under § 717r(b) must be “unambiguous in legal
    effect” and have “some substantial effect on the parties which
    cannot be altered by subsequent administrative action”).
    6
    In construing the language of the Federal Power Act, which is
    substantially identical to § 717r(b), Papago, 
    628 F.2d at 245
    , we imposed
    additional requirements for judicial review, holding that a FERC order is
    subject to judicial review under the Federal Power Act only if “(1) the
    order is final; (2) the order, if unreviewed, would inflict irreparable harm
    on the party seeking review; and (3) judicial review at this stage of the
    process would not invade the province reserved to the discretion of the
    agency,” City of Fremont v. FERC, 
    336 F.3d 910
    , 913–14 (9th Cir. 2003).
    We need not address here whether these requirements are also applicable
    in the § 717r context.
    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD                         19
    Section 717r(d)(1) limits our review not only to final
    actions and orders, but also to those that “issue, condition, or
    deny any permit, license, concurrence, or approval
    (hereinafter collectively referred to as ‘permit’) required
    under Federal law.” Although the statute does not define
    “permit, license, concurrence, or approval,” it collectively
    refers to these terms as “permit,” indicating that Congress
    intended to capture the type of agency determination that
    grants or denies permission to take some action. See United
    States v. Stevens, 
    559 U.S. 460
    , 474 (2010) (applying noscitur
    a sociis canon). The dictionary definition of permit is “a
    written warrant or license granted by one having authority,”
    Merriam-Webster’s Collegiate Dictionary 923 (11th ed.
    2003), which is similar to the definitions of the other statutory
    terms.7 Indeed, the terms are often defined by one another.
    See, e.g., Black’s Law Dictionary 1176 (8th ed. 2003)
    (defining “permit” as “a certificate evidencing permission; a
    license” (emphasis added)); id. at 938 (defining “license” as
    “[a] permission, usu. revocable, to commit some act”
    (emphasis added)).
    Accordingly, Congress contemplated that an order or
    action reviewable under § 717r(d)(1) would be (1) a final
    agency action or order (2) issuing, conditioning or denying
    (3) an agency determination (of a sort analogous to a permit)
    that has the legal effect of granting or denying permission to
    take some action.
    7
    See Merriam-Webster’s Collegiate Dictionary 717 (11th ed. 2003)
    (defining “license” as “a permission to act”; “a permission granted by
    competent authority to engage in . . . an activity otherwise unlawful”); id.
    at 259 (defining “concurrence” as “an agreement or union in action”); id.
    at 61 (defining “approval” as “an act or instance of approving” and
    defining “approve” as “to give formal or official sanction to”).
    20    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD
    B
    Applying this interpretation, the letter of recommendation
    for the East Skipanon LNG terminal is not a permitting action
    or order under § 19 of the Natural Gas Act.
    On its face, the Coast Guard’s letter of recommendation
    for this terminal is not an agency determination granting or
    denying permission to take some action. As early as 1986,
    the Coast Guard recognized that its siting authority was
    limited and retreated from its position that it was authorized
    to issue a “use permit” for LNG terminal facilities. Instead,
    it promulgated regulations allowing it to issue only a letter of
    recommendation. Congress’s express grant of exclusive
    siting authority to FERC, see 15 U.S.C. § 717b(e)(1), further
    clarified that the Coast Guard lacks authority over siting
    decisions. Congress is assumed to know existing law, and
    Congress did not require FERC to obtain or comply with the
    Coast Guard’s letter of recommendation, even though the
    Coast Guard had begun issuing such letters long before the
    EPAct was enacted. See Goodyear Atomic Corp. v. Miller,
    
    486 U.S. 174
    , 184–85 (1988) (“We generally presume that
    Congress is knowledgeable about existing law pertinent to the
    legislation it enacts.”).
    Congress subsequently confirmed that the Coast Guard’s
    only obligation was to “make a recommendation” to FERC as
    to the suitability of the waterway. Pub. L. No. 111-281,
    § 813, 124 Stat. at 2999.8 Because “recommendation” is not
    8
    Congress passed the 2010 Coast Guard Authorization Act after the
    Coast Guard issued the letter of recommendation for the East Skipanon
    LNG terminal but before the final administrative appeal denial. The
    parties do not dispute that the 2010 statute applies here.
    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD                      21
    defined, we assume Congress adopted the common meaning
    of the term “recommendation,” which is a suggestion or
    advisement without decisive authority, see Merriam-
    Webster’s Collegiate Dictionary 1039 (11th ed. 2003)
    (defining “recommendation” as “the act of recommending”);
    id. (defining “recommend” as “to present as worthy of
    acceptance . . . . ; to endorse as fit worthy or competent . . . ;
    advise”). Because nothing in the EPAct or the Coast Guard
    Authorization Act suggests that the Coast Guard’s
    “recommendation” is anything more than expert advice which
    FERC will use to inform its decision of whether to approve
    the proposed facility, we conclude the Coast Guard’s letter of
    recommendation for the East Skipanon LNG terminal does
    not have any conclusive legal effect.9 Cf. Revision of LNG
    and LHG Waterfront Facility General Requirements, 
    75 Fed. Reg. 29420
    , 29423 (May 26, 2010) (“Recommendations
    expressed in the [letter of recommendation] represent the
    Coast Guard’s professional input and are provided in the
    context of the Federal, State, or local jurisdictional agency’s
    proceedings, which provide for participation and public
    comments.”). Because a letter is not a “permit, license,
    concurrence, or approval,” for purposes of § 717r(d)(1), it is
    therefore not subject to judicial review.
    9
    To the extent Riverkeeper argues that the final administrative appeal
    denial was a “final agency action” based on language in 
    33 C.F.R. § 127.015
    (d) (2009), we reject this argument, because nothing in the
    record indicates that the Coast Guard’s final decision had the effect of
    issuing, conditioning, or denying a permit, see 15 U.S.C. § 717r(d)(1).
    Because Riverkeeper did not appeal the action in district court asserting
    jurisdiction under the APA, which provides for judicial review of final
    agency actions, see 
    5 U.S.C. § 704
    , we need not address whether
    Riverkeeper could have asserted a claim for relief in that context.
    22    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD
    Riverkeeper raises several arguments against this
    interpretation. First, Riverkeeper suggests that if § 717r(d)(1)
    applies only to final actions relating to permits, and does not
    apply to the Coast Guard’s letter of recommendation, it will
    do no work in the statutory regime. Since we are to interpret
    statutes to avoid making any provision superfluous, Corley v.
    United States, 
    556 U.S. 303
    , 314 (2009), Riverkeeper argues
    that such an interpretation cannot be correct. We disagree.
    The main purpose of § 717r(d)(1) was to allow judicial
    review of state agencies’ denial of certifications required
    under federal environmental laws. See Islander E. Pipeline
    Co., 
    482 F.3d at
    85–88 (reviewing state order denying
    petitioner’s application for a Water Quality Certificate).
    Moreover, the NGA itself makes clear that certain federal
    agency actions are subject to judicial review under this
    section; for instance, FERC must “obtain the concurrence of
    the Secretary of Defense before authorizing the siting,
    construction, expansion, or operation of liquefied natural gas
    facilities affecting the training or activities of an active
    military installation.” 15 U.S.C. § 717b(f)(3) (emphasis
    added).
    Second, Riverkeeper argues that the term “letter of
    recommendation” is misleading, and as a practical matter,
    such a letter constitutes a final agency action or order under
    § 717r(d)(1). We agree that an agency’s characterization of
    its action as being provisional or advisory is not necessarily
    dispositive, and courts consider whether the practical effects
    of an agency’s decision make it a final agency action,
    regardless of how it is labeled. Under the APA, for instance,
    even if the agency does not label its decision or action as
    final, it may be reviewable if it “has the status of law or
    comparable legal force” or if “immediate compliance with its
    terms is expected.” Or. Natural Desert Ass’n, 465 F.3d at
    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD             23
    987. In Bennett v. Spear, 
    520 U.S. 154
     (1997), the Supreme
    Court concluded that a biological opinion issued by the Fish
    and Wildlife Service pursuant to the ESA was an appealable
    final agency action under the APA because it effectively
    authorized a federal agency to take endangered species if it
    complied with the prescribed conditions. 
    Id.
     at 177–78.
    While styled as an “opinion,” the biological opinion had
    “direct and appreciable legal consequences.” 
    Id. at 178
    .
    Likewise, a document styled as a “guidance document” may
    amount to a final agency action when it “reflect[s] a settled
    agency position which has legal consequences.” Appalachian
    Power Co. v. EPA, 
    208 F.3d 1015
    , 1023 (D.C. Cir. 2000). By
    contrast, an agency determination that certain property
    contains wetlands subject to the Clean Water Act is not a
    reviewable action under the APA, because that decision does
    not determine rights or obligations from which legal
    consequences will flow. Fairbanks N. Star Borough v. U.S.
    Army Corps of Eng’rs, 
    543 F.3d 586
    , 593–94 (9th Cir. 2008).
    We have followed the same approach in the NEPA and ESA
    contexts as well. See Ramsey v. Kantor, 
    96 F.3d 434
    , 444
    (9th Cir. 1996) (concluding an agency’s incidental take
    statement was the functional equivalent of a permit and
    therefore constituted a “major Federal action” triggering
    NEPA obligations); cf. Karuk Tribe of Cal. v. U.S. Forest
    Serv., 
    681 F.3d 1006
    , 1021–23 (9th Cir. 2012) (en banc)
    (concluding the Forest Service’s decision authorized rather
    than advised proposed mining activity and therefore triggers
    ESA requirements), cert. denied, 
    133 S. Ct. 1579
     (2013).
    Relying on these precedents, Riverkeeper maintains that
    the Coast Guard’s letter of recommendation for the East
    Skipanon LNG terminal is the functional equivalent of a
    permit because either (1) the letter of recommendation is in
    practice a necessary prerequisite for siting of a facility or
    24    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD
    (2) the letter of recommendation will effectively regulate
    vessel traffic along the waterway after the facility’s
    construction. We disagree with both assertions.
    First, the record does not establish that obtaining the
    Coast Guard’s approval of the proposed site for an LNG
    terminal is a necessary prerequisite for siting an LNG facility.
    Here, the Coast Guard has no enforcement authority over
    FERC’s siting decision, and its letter of recommendation does
    not produce legal consequences. In Bennett and Appalachian
    Power, by contrast, the agency action had a “virtually
    determinative effect” on the project proponent. Bennett, 
    520 U.S. at 169
    ; see also 
    id. at 178
     (stating that the Fish and
    Wildlife Service’s biological opinion “alter[ed] the legal
    regime” to which the federal agency was subject and had the
    power to preclude the federal agency’s ability to go forward
    with its water reclamation project); Appalachian Power,
    
    208 F.3d at 1023
     (stating that “through the Guidance, EPA
    has given the States their ‘marching orders’”).
    Nor does the record support Riverkeeper’s argument that,
    as a practical matter, FERC always complies with the Coast
    Guard’s letter of recommendation, which effectively gives it
    the force of law. In making this claim, Riverkeeper relies
    primarily on the First Circuit’s decision in City of Fall River
    v. FERC, 
    507 F.3d 1
     (1st Cir. 2007). But Riverkeeper’s
    reliance on Fall River is misplaced because in that case FERC
    gave the person seeking to construct an LNG terminal facility
    a conditional approval that was subject to the Coast Guard’s
    approval of a vessel transportation plan. 
    Id.
     at 3–5. Under
    these circumstances, the Coast Guard’s approval did have
    binding effect, because FERC had the plenary authority to
    make a siting order subject to such a requirement. See
    15 U.S.C. § 717b(e). But nothing in Fall River suggests that
    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD              25
    FERC has a firm internal policy to condition its approval
    upon the Coast Guard’s decision, and there is no evidence in
    the record before us suggesting that FERC has such an
    entrenched policy generally or imposed such a condition here.
    Second, we reject Riverkeeper’s claim that the Coast
    Guard’s letter of recommendation will effectively regulate
    vessel traffic along the waterway after the facility’s
    construction. For this claim, Riverkeeper relies on the
    captain of the port’s statement in the letter of
    recommendation that “should an LNG transit be attempted
    along this waterway without full implementation of the risk
    mitigation measures” the Coast Guard would reference the
    letter of recommendation’s “determinations, analysis, and
    ultimate recommendation as to the suitability of this
    waterway” in a “Captain of the Port Order.” On its face, this
    language suggests that the Coast Guard intends to prevent the
    East Skipananon LNG facility from receiving vessels unless
    the project proponent complies with the letter’s requirements.
    But the record establishes that the Coast Guard has not taken
    this position. Most important, the Coast Guard’s final
    administrative decision, dated August 25, 2012, states that
    mitigation measures in the letter of recommendation are not
    binding on the captain of the port, and that as a practical
    matter, the Coast Guard does not and could not regulate the
    waterways by preventing vessel transit to LNG terminals that
    failed to obtain an approval letter. In considering the effect
    of the letter of recommendation, we are bound by the final
    determination at the higher level of the agency. Cf. Nat’l
    Ass’n of Home Builders v. Defenders of Wildlife, 
    551 U.S. 644
    , 659 (2007) (“[T]he fact that a preliminary determination
    by a local agency representative is later overruled at a higher
    level within the agency does not render the decisionmaking
    process arbitrary and capricious.”); Bechtel v. Admin. Review
    26     COLUMBIA RIVERKEEPER V. U.S. COAST GUARD
    Bd., U.S. Dep’t of Labor, 
    710 F.3d 443
    , 449 (2d Cir. 2013)
    (concluding ALJ’s error was “beside the point” where the
    Administrative Review Board recognized the error and
    explained that it did not affect the case’s outcome).10
    Accordingly, we conclude that the letter of recommendation
    is not in practice a final agency action.11
    C
    Although the record does not establish that the Coast
    Guard’s letter of recommendation is a final agency order or
    action “to issue, condition, or deny any permit, license,
    concurrence, or approval” required under Federal law,
    15 U.S.C. § 717r(d)(1), this does not mean that the Coast
    Guard’s recommendations are immune from judicial review.
    10
    The Coast Guard press release and public relations documents, which
    also state that Oregon LNG must implement the risk mitigation measures
    in the Coast Guard’s letter of recommendation, merely track the language
    of the letter, and so do not provide any additional support for
    Riverkeeper’s interpretation. The April 13, 2009 “Executive Brief”cited
    in Riverkeeper’s reply suffers from the same infirmity.
    11
    Riverkeeper points to two other documents to support its interpretation
    of the import of the letter of recommendation, but its arguments are
    meritless. First, Riverkeeper claims that language in the Bradwood
    project’s final environmental impact statement indicates that LNG tankers
    must comply with mitigation measures set forth in the Coast Guard’s letter
    of recommendation. Even if we interpreted the Bradwood environmental
    documents as Riverkeeper urges, the Coast Guard analyzed the Bradwood
    project under its pre-EPAct guidance document (NVIC 05-05), which is
    no longer applicable here. Riverkeeper’s reliance on a May 2009 letter
    from the Coast Guard to FERC is likewise misplaced; that letter merely
    explains that the Coast Guard, not FERC, has jurisdiction over design and
    equipment requirements on vessels. Nothing in the Coast Guard’s letter
    indicates that the advice contained in a letter of recommendation is
    binding.
    COLUMBIA RIVERKEEPER V. U.S. COAST GUARD               27
    Rather, any Coast Guard recommendation adopted by FERC
    in its final order, or any failure to adopt such a
    recommendation, would be reviewable under 15 U.S.C.
    § 717r(b). In addition, any final orders regarding vessel
    traffic issued by the Coast Guard pursuant to its own
    independent authority will be subject to judicial review as
    final agency action. See, e.g., Wong v. Bush, 
    542 F.3d 732
    ,
    735 (9th Cir. 2008) (considering challenges to rule
    establishing security zone); Wilmina Shipping AS v. U.S.
    Dep’t of Homeland Sec., 
    934 F. Supp. 2d 1
    , 4, 19 (D.D.C.
    2013) (considering challenge to a captain of the port’s order).
    But because Riverkeeper has not carried its burden of
    showing that the letter of recommendation for the East
    Skipanon LNG terminal is a final agency order or action to
    issue a permit we lack jurisdiction to consider it or the August
    25, 2012 decision affirming the letter.
    DISMISSED.
    

Document Info

Docket Number: 12-73385

Citation Numbers: 761 F.3d 1084

Filed Date: 8/5/2014

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (24)

City of Fall River v. Federal Energy Regulatory Commission , 507 F.3d 1 ( 2007 )

Islander East Pipeline Company, LLC v. State of Connecticut ... , 482 F.3d 79 ( 2006 )

the-steamboaters-an-oregon-non-profit-corporation-v-federal-energy , 759 F.2d 1382 ( 1985 )

Satterfield v. Simon & Schuster, Inc. , 569 F.3d 946 ( 2009 )

consolidated-gas-supply-corporation-v-federal-energy-regulatory , 611 F.2d 951 ( 1979 )

atlanta-gas-light-company-v-federal-power-commission-atlanta-gas-light , 476 F.2d 142 ( 1973 )

city-of-fremont-v-federal-energy-regulatory-commission-pacific-gas-and , 336 F.3d 910 ( 2003 )

Sandoval-Luna v. Mukasey , 526 F.3d 1243 ( 2008 )

Appalachian Power Co. v. Environmental Protection Agency , 208 F.3d 1015 ( 2000 )

Fairbanks North Star Borough v. U.S. Army Corps of Engineers , 543 F.3d 586 ( 2008 )

California Energy Commission v. Department of Energy , 585 F.3d 1143 ( 2009 )

Transwestern Pipeline Co. v. 17.19 Acres of Property ... , 627 F.3d 1268 ( 2010 )

james-a-ramsey-elf-atochem-north-america-aluminum-company-of-america , 96 F.3d 434 ( 1996 )

Wong v. Bush , 542 F.3d 732 ( 2008 )

Washington Gas Light Co. v. Federal Energy Regulatory ... , 532 F.3d 928 ( 2008 )

Papago Tribal Utility Authority v. Federal Energy ... , 628 F.2d 235 ( 1980 )

Goodyear Atomic Corp. v. Miller , 108 S. Ct. 1704 ( 1988 )

Kokkonen v. Guardian Life Insurance Co. of America , 114 S. Ct. 1673 ( 1994 )

Bennett v. Spear , 117 S. Ct. 1154 ( 1997 )

National Ass'n of Home Builders v. Defenders of Wildlife , 127 S. Ct. 2518 ( 2007 )

View All Authorities »