Western Watersheds Project v. Sally Jewell , 601 F. App'x 586 ( 2015 )


Menu:
  •                                                                               FILED
    NOT FOR PUBLICATION                                MAY 05 2015
    MOLLY C. DWYER, CLERK
    UNITED STATES COURT OF APPEALS                          U.S. COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    WESTERN WATERSHEDS PROJECT,                      No. 13-55027
    Plaintiff - Appellant,             D.C. No. 2:11-cv-00492-DMG-E
    v.
    MEMORANDUM*
    SALLY JEWELL**, in her official
    capacity as Secretary of the United States
    Department of the Interior, et al.,
    Defendants - Appellees,
    And
    BRIGHTSOURCE ENERGY, INC.,
    Intervenor-Defendant -
    Appellee.
    Appeal from the United States District Court
    for the Central District of California
    Dolly M. Gee, District Judge, Presiding
    *
    This disposition is not appropriate for publication and is not precedent
    except as provided by 9th Cir. R. 36-3.
    **
    Sally Jewell is substituted for her predecessor, Kenneth Lee Salazar,
    as Secretary of the United States Department of the Interior. Fed. R. App. P.
    43(c)(2).
    Argued and Submitted April 10, 2015
    Pasadena, California
    Before: KLEINFELD, BENAVIDES***, and CLIFTON, Circuit Judges.
    Western Watersheds Project appeals the district court’s summary judgment
    in favor of the Bureau of Land Management and Brightsource. We have
    jurisdiction under 28 U.S.C.§ 1291 and affirm.
    BLM took the requisite “hard look” at the impacts of the Ivanpah Solar
    Electric Generating System (“Solar Project”) on the desert tortoise. That BLM
    estimated tortoise populations based on surveys of only adult tortoises did not
    render its analysis arbitrary. Juvenile tortoises and their eggs were difficult to
    detect in population surveys, and the vast majority would die from causes unrelated
    to the Solar Project before reaching reproductive age. BLM’s consideration of
    impacts to the desert tortoise species, rather than individuals, was appropriate. See
    Envtl. Prot. Info. Ctr. v. U.S. Forest Serv., 
    451 F.3d 1005
    , 1010 (9th Cir. 2006).
    The district court did not abuse its discretion in excluding the extra-record
    declaration of Dr. Connor and concluding he was not qualified as a desert tortoise
    expert.
    ***
    The Honorable Fortunato P. Benavides, Senior Circuit Judge for the
    U.S. Court of Appeals for the Fifth Circuit, sitting by designation.
    2
    BLM also adequately discussed the Solar Project’s impacts to desert tortoise
    habitat fragmentation and connectivity. The final EIS qualitatively discussed both
    fragmentation and loss of connectivity and quantified expected habitat loss.
    Although not concentrated in a single subsection of the EIS, the analysis allowed
    for informed decisionmaking and public participation. Cf. Nat’l Parks &
    Conservation Ass’n v. Bureau of Land Mgmt., 
    606 F.3d 1058
    , 1073 (9th Cir.
    2010).
    BLM considered the cumulative impacts of the DesertXpress railway by
    assuming it would require a 40-mile long by 500-foot wide corridor. Because the
    DesertXpress route had not yet been identified when BLM analyzed its impacts,
    BLM could not have been required to assess the possible impacts to desert tortoise
    translocation from a plan that had not been sufficiently developed. See Envtl. Prot.
    Info. 
    Ctr., 451 F.3d at 1014
    (noting that an agency cannot be required to do the
    impractical where insufficient information is available).
    It was not arbitrary for BLM to determine that the revised estimates of
    tortoise population and anticipated mortality did not constitute significant new
    information and therefore did not require a supplemental EIS. BLM adequately
    explained its decision not to prepare a supplemental EIS in its Determination of
    NEPA Adequacy. That more tortoises would be affected did not require the
    3
    conclusion that the revised estimates significantly changed the impacts to the
    tortoise species or make the Solar Project’s impacts highly controversial.
    BLM also properly reviewed the Eldorado-Ivanpah Transmission Line as a
    cumulative rather than as a connected project. Because timing precluded BLM
    from combining the transmission line and the Solar Project in the same EIS, the
    final EIS adequately incorporated the transmission line by describing its impacts
    and referring the reader to the draft EIS for the transmission line. Cf. Northern
    Plains Resource Council, Inc. v. Surface Transp. Bd., 
    668 F.3d 1067
    , 1088 (9th
    Cir. 2011) (noting neither cumulative nor connected actions need be considered in
    the same EIS when the timing of the applications precludes it). The agency’s
    process did not reflect an effort to divide a project into multiple actions to hide
    significant impacts. See 
    id. at 1087.
    BLM’s justifications for eliminating the Ivanpah Dry Lake and private lands
    alternatives were sufficient. BLM explained the Ivanpah Dry Lake floods
    periodically, dikes that might prevent flooding would be economically prohibitive,
    and the site offers unique recreational opportunities. BLM also explained that
    obtaining the private lands would be challenging, risky, and time consuming. The
    only site that offered sufficient land was too expensive.
    4
    Finally, BLM took a hard look at the Solar Project’s impacts to birds. BLM
    identified potential impacts, discussed relevant scientific studies of similar bird
    mortalities, and noted limitations in existing data. BLM also explained why the
    McCrary study on bird mortality at a solar facility could not be translated into
    mortality estimates for the Solar Project.
    AFFIRMED.
    5