Natural Resources Defense Coun v. Kenneth Salazar , 686 F.3d 1092 ( 2012 )


Menu:
  •                    FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    NATURAL RESOURCES DEFENSE                 
    COUNCIL; CALIFORNIA TROUT;
    BAYKEEPER & IT’S DELTAKEEPER
    CHAPTER; FRIENDS OF THE RIVER;
    THE BAY INSTITUTE, all non-profit
    organizations,
    Plaintiffs-Appellants,
    and
    METROPOLITAN WATER DISTRICT OF
    SOUTHERN CALIFORNIA, Plaintiff in
    Related Case,
    Plaintiff,
    v.                      
    KENNETH LEE SALAZAR, in his
    official capacity as Secretary of
    the Interior; SAM D. HAMILTON, in
    his official capacity as Director of
    the U.S. Fish and Wildlife
    Service; MICHAEL J. CONNOR, in
    his official capacity as
    Commissioner of the U.S. Bureau
    of Reclamation; ANDERSON-
    COTTONWOOD IRRIGATION DISTRICT;
    PACIFIC REALTY ASSOCIATES, LP;
    RECLAMATION DISTRICT 1004;
    
    8167
    8168                 NRDC v. SALAZAR
    BEVERLY F. ANDREOTTI; BANTA-         
    CARBONA IRRIGATION DISTRICT;
    PATTERSON IRRIGATION DISTRICT;
    WEST SIDE IRRIGATION DISTRICT;
    BYRON BETHANY IRRIGATION
    DISTRICT; CARTER MUTUAL WATER
    COMPANY; HOWALD FARMS, INC.;
    MAXWELL IRRIGATION DISTRICT;
    MERIDIAN FARMS WATER COMPANY;
    OJI BROTHERS FARM, INC.; HENRY
    D. RICHTER; SUTTER MUTUAL
    WATER CO.; TISDALE
    IRRIGATION AND DRAINAGE
    COMPANY; WINDSWEPT LAND AND
    LIVESTOCK COMPANY; CITY OF
    REDDING; COELHO FAMILY TRUST;        
    EAGLE FIELD WATER DISTRICT;
    MERCY SPRINGS WATER DISTRICT;
    ORO LOMA WATER DISTRICT;
    CONAWAY CONSERVANCY GROUP;
    DEL PUERTO WATER DISTRICT;
    WEST STANISLAUS IRRIGATION
    DISTRICT; FRESNO SLOUGH WATER
    DISTRICT; JAMES IRRIGATION
    DISTRICT; TRANQUILITY IRRIGATION
    DISTRICT; CHRISTO D. BARDIS;
    ABDUL RAUF; TAHMINA RAUF;
    SACRAMENTO RIVER RANCH, LLC;
    FRED TENHUNFELD; FAMILY FARM
    ALLIANCE,
    Defendants-Appellees,
    
    NRDC v. SALAZAR                       8169
    SAN LUIS & DELTA-MENDOTA                
    WATER AUTHORITY; WESTLANDS
    WATER DISTRICT; CALIFORNIA FARM
    BUREAU FEDERATION; STATE WATER
    CONTRACTORS; CALIFORNIA
    DEPARTMENT OF WATER RESOURCES;
    GLENN-COLUSA IRRIGATION                         No. 09-17661
    DISTRICT; NATOMAS CENTRAL
    D.C. No.
    MUTUAL WATER COMPANY; PELGER
    MUTUAL WATER COMPANY;                         1:05-cv-01207-
    OWW- GSA
    PLEASANT GROVE-VERONA MUTUAL
    WATER COMPANY; RECLAMATION                        OPINION
    DISTRICT 108; RIVER GARDEN
    FARMS; PRINCETON-CODORA-GLENN
    IRRIGATION DISTRICT; PROVIDENT
    IRRIGATION DISTRICT; KERN COUNTY
    WATER AGENCY,
    Defendant-intervenors-Appellees.
    
    Appeal from the United States District Court
    for the Eastern District of California
    Oliver W. Wanger, Senior District Judge, Presiding
    Argued and Submitted
    May 9, 2011—San Francisco, California
    Filed July 17, 2012
    Before: Procter Hug, Jr. and Richard A. Paez,
    Circuit Judges, and Liam O’Grady, District Judge.*
    *The Honorable Liam O’Grady, District Judge for the U.S. District
    Court for Eastern Virginia, Alexandria, sitting by designation.
    8170     NRDC v. SALAZAR
    Opinion by Judge Hug;
    Dissent by Judge Paez
    NRDC v. SALAZAR                  8171
    COUNSEL
    Katherine Poole, Senior Attorney, Natural Resources Defense
    Council, San Francisco, California; Hamilton Candee and
    8172                      NRDC v. SALAZAR
    Barbara J. Chisholm, Altshuler Berzon LLP, for the plain-
    tiffs-appellants.
    Andrew C. Mergen and Robert H. Oakley, Attorneys, Envi-
    ronment & Natural Resources Division, Department of Jus-
    tice, Washington, D.C., for the defendants-appellees.
    Daniel J. O’Hanlon, Kronick Moskovitz Tiedemann & Girard,
    PC, Sacramento, California; Stuart L. Somach and Andrew
    M. Hitchings, Somach Simmons & Dunn, Sacramento, Cali-
    fornia; Steven P. Saxton, Downey Brand LLP, Sacramento,
    California, for the defendant-intervenors-appellees.
    OPINION
    HUG, Circuit Judge:
    In this appeal, we address whether the renewal of forty-one
    water supply contracts by the United States Bureau of Recla-
    mation violates § 7(a)(2) of the Endangered Species Act, 
    16 U.S.C. § 1536
    (a)(2) and illegally threatens the existence of
    the delta smelt. We conclude that it does not, and we affirm
    the judgment of the district court.
    I.    BACKGROUND
    A.        FACTUAL BACKGROUND
    The delta smelt is a small fish endemic to the San Joaquin
    and Sacramento Rivers Delta Estuary which was declared
    endangered by the United States Fish and Wildlife Service
    under the Endangered Species Act in 1993. Though previ-
    ously abundant, the population of the delta smelt has dimin-
    ished markedly in the last several decades. “The delta smelt
    presently has no commercial value, but it was commercially
    harvested as bait in the past.” San Luis & Delta-Mendota
    Water Auth. v. Salazar, 
    638 F.3d 1163
    , 1167 (9th Cir. 2011).
    NRDC v. SALAZAR                       8173
    Plaintiffs, several conservation groups, argue that in 2005
    the United States Bureau of Reclamation (“Bureau”) renewed
    forty-one water service contracts with various water users
    without conducting an adequate consultation under § 7(a)(2)
    of the Endangered Species Act and that the contracts jeopar-
    dize the existence of the delta smelt. The contracts at issue fall
    into two groups: (1) users who obtain water from the Delta-
    Mendota Canal (“DMC Contractors”); and (2) parties who
    claim to hold water rights senior to those held by the Bureau
    with regard to the Central Valley Project and who previously
    entered into settlement contracts with the Bureau (“Settlement
    Contractors”).
    Generally, the Bureau is a federal water management
    agency which operates the Central Valley Project (“CVP”).
    The CVP is a network of dams, reservoirs, and pumping facil-
    ities which regulates the flow of water in the San Joaquin and
    Sacramento Rivers. California’s State Water Project (“SWP”)
    operates the same watershed as the CVP and both offices con-
    vey water by pumping water from the two rivers. The SWP
    consists of dams, canals, and pumping plants and is “the state
    analogue to the Central Valley Project.” Sierra Club v.
    Andrus, 
    610 F.2d 581
    , 586 (9th Cir. 1979), rev’d on other
    grounds, California v. Sierra Club, 
    451 U.S. 287
    , 290-91
    (1981).
    The Bureau and SWP have coordinated management of
    CVP. The joint effort began in the 1930s when the Bureau
    assumed control of it because California could not finance the
    project. The Bureau had to obtain water rights under state law
    to operate CVP and a dispute arose regarding the priority of
    pre-project water rights. Under California law, a senior holder
    of water rights has the right “to fulfill his needs before a
    junior appropriator is entitled to use any water.” United States
    v. State Water Resources Control Bd., 
    182 Cal. App. 3d 82
    ,
    102 (Cal. Ct. App. 1986). The California Water Rights Board
    held hearings on the matter and issued a decision allowing the
    Bureau to use CVP water if it first addressed the issue of the
    8174                   NRDC v. SALAZAR
    holders asserting senior water rights. The Board recognized
    that senior water rights existed, though undefined, and
    required a settlement.
    In 1964, the Bureau and those asserting senior water rights
    entered into 145 settlement contracts for 40-year terms. The
    contracts did not resolve the seniority claims, but guaranteed
    Settlement Contractors a certain amount of “base water”
    annually without any fee and other “project water” for which
    they would pay a fee to receive. The “base water” could only
    be reduced by 25% in very dry years.
    The Bureau also contracted with a coalition of water ser-
    vice contractors who obtained water from the Delta-Mendota
    Canal, the DMC Contractors. These contracts provided for
    water delivery to the DMC Contractors annually which the
    contractors paid the Bureau to receive. Like the Settlement
    Contracts, these contracts were also long-term water supply
    contracts.
    B.   STATUTORY FRAMEWORK
    The Endangered Species Act (“ESA”) “has both substan-
    tive and procedural provisions designed to protect endangered
    species and their habitat.” American Rivers v. Nat’l Marine
    Fisheries Serv., 
    126 F.3d 1118
    , 1121 (9th Cir. 1997). Under
    § 7(a)(2) of the ESA, federal agencies are required to “insure
    that any action authorized, funded, or carried out by such
    agency . . . is not likely to jeopardize the continued existence
    of any endangered species or threatened species or result in
    the destruction or adverse modification of habitat of such spe-
    cies.” 
    16 U.S.C. § 1536
    (a)(2). An agency which proposes the
    action must determine whether its action may affect the listed
    species or critical habitat and present its conclusions in a bio-
    logical assessment. 
    16 U.S.C. § 1536
    (c)(1); 
    50 C.F.R. § 402.12
    . If the agency determines that its action will have no
    effect, consultation is not required. 
    50 C.F.R. § 402.14
    . If it
    finds its proposed action may affect a listed species or critical
    NRDC v. SALAZAR                       8175
    habitat, it must formally or informally consult with, in this
    case, the United States Fish and Wildlife Service (“Service”).
    American Rivers, 
    126 F.3d at 1122
    .
    If the acting agency or consulting agency determines that
    the proposed action is likely to adversely affect a listed spe-
    cies or critical habitat, it must engage in a formal consultation.
    
    50 C.F.R. §§ 402.13
    , 402.14. In a formal consultation, the
    consulting agency (the Service) issues a biological opinion
    stating whether the action is likely to jeopardize such species
    or habitat. 
    16 U.S.C. § 1536
    (b); 
    50 C.F.R. § 402.14
    . If it finds
    jeopardy is likely, then the acting agency (the Bureau) may
    suggest reasonable and prudent alternatives to be employed in
    order to ensure that the listed species or critical habitat is not
    put in jeopardy. 
    16 U.S.C. § 1536
    (b). The requirements to
    engage in consultation only apply to agency actions “in which
    there is discretionary Federal involvement or control.” 
    50 C.F.R. § 402.03
    .
    C.   PROCEDURAL HISTORY
    In 2003, the Bureau prepared a biological assessment
    regarding the affect that the contract renewals would impose
    on the delta smelt and also requested a consultation with the
    Service. The Service prepared a biological opinion (“2004
    opinion”) addressing whether the contract renewals would
    likely adversely affect a listed species or critical habitat. The
    Service stated in its 2004 opinion that the Bureau’s proposed
    action was not likely to threaten the delta smelt. Shortly there-
    after, because of an intervening court decision, the Service
    issued a new biological opinion in 2005 (“2005 opinion”)
    which reached the same conclusion.
    As the Service’s opinions were issued, the contracts at issue
    in this case had expired or were nearing expiration. Because
    the Bureau and the Service determined that the contract
    renewals would not adversely affect the delta smelt, in 2004
    and 2005 the Bureau renewed 28 contracts with the Settle-
    8176                   NRDC v. SALAZAR
    ment Contractors not to exceed 40-years and 13 contracts
    with the DMC Contractors for 25-year terms.
    In 2005, plaintiffs in the instant case filed suit against the
    government alleging that it violated § 7 of the ESA based on
    the Service’s 2004 opinion. The Service then issued its new
    2005 opinion and plaintiffs filed another complaint referring
    to the 2005 opinion. In reviewing the 2005 opinion, the dis-
    trict court held that it was unlawful because it failed to ade-
    quately consider the impacts to the delta smelt’s critical
    habitat, did not rely on the best available scientific informa-
    tion, and did not include mandatory mitigation measures to
    protect the delta smelt. The district court remanded the 2005
    opinion without vacatur and ordered the Bureau and the Ser-
    vice to reconsult on the effects of the CVP and SWP opera-
    tion on the delta smelt. On December 14, 2007, interim
    measures were imposed by the court and were set to expire
    automatically on the issuance of a new biological opinion by
    the Service. A new opinion was filed by the Service in
    December 2008.
    Plaintiffs filed another complaint against the government
    arguing that the Bureau had violated its legal obligations
    under § 7(a)(2) of the ESA by renewing the DMC contracts
    and Settlement Contracts. Each party then moved for sum-
    mary judgment. The district court granted summary judgment
    for defendants, finding that plaintiffs lacked standing to chal-
    lenge the DMC contracts and that the plaintiffs’ claims
    against the Settlement Contractors failed because the con-
    tracts were not discretionary and were thus exempted from
    § 7(a)(2) compliance.
    In 2008, the Bureau completed a new biological assessment
    and the Service issued a new biological opinion (“2008 opin-
    ion”). In that opinion, the Service found that the CVP and
    SWP operations were likely to threaten the delta smelt and
    identified “reasonable and prudent alternatives” to avoid such
    jeopardy.
    NRDC v. SALAZAR                     8177
    II.   ANALYSIS
    A.   STANDARD OF REVIEW
    This court reviews a district court’s grant of summary judg-
    ment de novo. Butte Envtl. Council v. U.S. Army Corps of
    Engineers, 
    620 F.3d 936
    , 945 (9th Cir. 2010). “Mootness, a
    question of law, is reviewed de novo.” Tinoqui-Chalola
    Council of Kitanemuk and Yowlumne Tejon Indians v. U.S.
    Dep’t of Energy, 
    232 F.3d 1300
    , 1303 (9th Cir. 2000). Stand-
    ing to challenge renewal of the DMC contracts is a legal ques-
    tion also reviewed de novo. Salmon Spawning & Recovery
    Alliance v. Gutierrez, 
    545 F.3d 1220
    , 1224-25 (9th Cir. 2008).
    B.   MOOTNESS
    Federal defendants and DMC Contractors argue that the
    issuance of the 2008 opinion by the Service eliminates the
    “case or controversy” requirement for federal jurisdiction and
    makes this appeal moot. A federal court’s jurisdiction is lim-
    ited to cases or controversies. U.S. Const., Art. III, § 2; Pow-
    ell v. McCormack, 
    395 U.S. 486
    , 496 n.7 (1969). Federal
    courts do not have jurisdiction to review a case when no case
    or controversy exists. Foster v. Carson, 
    347 F.3d 742
    , 745
    (9th Cir. 2003). Issuance of a superceding biological opinion
    moots a legal challenge to a prior biological opinion. Forest
    Guardians v. U.S. Forest Serv., 
    329 F.3d 1089
    , 1096 (9th Cir.
    2003); American Rivers, 
    126 F.3d at 1123-24
    ; Idaho Dep’t of
    Fish & Game v. Nat’l Marine Fisheries Serv., 
    56 F.3d 1071
    ,
    1074 (9th Cir. 1995).
    [1] In this case, the issues before the court are not moot
    because although a new 2008 opinion was issued, parts of that
    2008 opinion have been held unlawful by the district court in
    San Luis & Delta-Mendota Water Authority v. Salazar, 
    760 F. Supp. 2d 855
     (E.D. Cal. 2010) (holding that the Service’s reli-
    ance on raw salvage numbers to set river flow limits violated
    ESA and that its conclusion that projects contributed to
    8178                   NRDC v. SALAZAR
    impacts on predation and microcystis on delta smelt was arbi-
    trary and capricious). Unlike previous cases that this court has
    addressed where a new superceding opinion clearly replaced
    the old opinion, in this case we have ongoing litigation
    regarding the validity of the 2008 opinion and a federal court
    which has held that parts of the 2008 opinion violate the ESA.
    Moreover, it is unclear whether the 2008 opinion specifically
    considered the impact of the forty-one contracts on CVP oper-
    ation. Because the 2008 opinion has been held, in part, unlaw-
    ful, and it is unclear if the contracts at issue were considered
    in that opinion, this case is not moot on appeal.
    C.   STANDING
    Plaintiffs argue that the district court erred in holding that
    they did not have standing to challenge the DMC contracts.
    To invoke the jurisdiction of the federal courts, a plaintiff
    must have Article III standing. Salmon Spawning & Recovery
    Alliance, 
    545 F.3d at 1224-25
    . To establish Article III stand-
    ing, a plaintiff must show that: “(1) he or she has suffered an
    injury in fact that is concrete and particularized, and actual or
    imminent; (2) the injury is fairly traceable to the challenged
    conduct; and (3) the injury is likely to be redressed by a favor-
    able court decision.” 
    Id. at 1225
    . If a plaintiff asserts a proce-
    dural injury, he must show that the procedures are designed
    to protect a concrete threatened interest and, once shown, his
    burden for showing causation and redressability is lessened.
    
    Id. at 1226
    . In that case, plaintiffs “must show only that they
    have a procedural right that, if exercised, could protect their
    concrete interests.” 
    Id.
     (quoting Defenders of Wildlife v. U.S.
    E.P.A., 
    420 F.3d 946
    , 957 (9th Cir. 2005), overruled on other
    grounds by Nat’l Ass’n of Home Builders v. Defenders of
    Wildlife, 
    551 U.S. 644
     (2007)).
    [2] In this case, the district court properly held that plain-
    tiffs do not have standing to challenge the DMC contracts.
    Plaintiffs’ assertion that the DMC contracts are based on an
    improper biological opinion is an assertion of a procedural
    NRDC v. SALAZAR                       8179
    violation. See Defenders of Wildlife, 
    420 F.3d at 957
     (claim
    asserting an inadequate consultation between the Environ-
    mental Protection Agency and Fish and Wildlife Service
    asserts a procedural violation). Plaintiffs satisfy the injury-in-
    fact requirement by their assertion that they believe that the
    Bureau has overcommitted water under the contracts which
    will harm the delta smelt. See Salmon Spawning & Recovery
    Alliance, 
    545 F.3d at 1225-26
    . However, plaintiffs fail to
    establish a causal connection between the threatened injury
    and the Bureau’s action because the DMC contracts include
    a shortage provision. The shortage provision expressly allows
    the Bureau to take any action to meet its legal obligations,
    which includes not delivering water to DMC Contractors if it
    is necessary in order to comply with § 7(a)(2) of the ESA.
    The DMC contract terms, therefore, expressly require that
    water delivery be subject to the requirements of Federal law
    and that the Bureau may discontinue or reduce the quantity of
    water delivered to the DMC Contractors. The threatened
    injury, i.e., jeopardy to the delta smelt, would not be traceable
    to the contract renewals because such contracts expressly
    allow for § 7(a)(2) compliance. With no threatened injury
    there is nothing to redress. Even under a substantive claim
    analysis for standing, which imposes a higher burden than a
    procedural analysis, plaintiffs’ claim fails because they cannot
    show causation. See Warth v. Seldin, 
    422 U.S. 490
    , 506-08
    (1975) (facts asserted failed to show causation for Article III
    standing). Thus, the district court properly determined that
    plaintiffs lack standing to challenge the DMC contracts under
    both a procedural and a substantive claim analysis.
    D.   NON-DISCRETIONARY CONTRACTS
    [3] Plaintiffs argue that the district court erred in holding
    that their claims as to the Settlement Contracts fail because
    those contracts do not require compliance with § 7(a)(2) of
    the ESA. Section 7(a)(2) of the ESA only applies to federal
    agency action “in which there is discretionary Federal
    involvement or control.” Nat’l Ass’n of Home Builders v.
    8180                   NRDC v. SALAZAR
    Defenders of Wildlife, 
    551 U.S. 644
    , 666 (2007) (“Home
    Builders”) (quoting 
    50 C.F.R. § 402.03
    ). In Home Builders,
    the Supreme Court held § 7 did not apply to the Environmen-
    tal Protection Agency’s (“EPA”) approval of an application
    for Arizona to administer a program under the Clean Water
    Act because this was not a discretionary act of the agency. Id.
    at 666-67. The salient provisions of the Clean Water Act man-
    dated that the EPA approve the application once nine statu-
    tory criteria under 
    33 U.S.C. § 1342
    (b) were met. 
    Id.
     If the
    nine criteria were met, the EPA lacked discretion to deny the
    application, regardless of § 7(a)(2) requirements. Id. Because
    the EPA’s discretion was so limited in determining whether
    to approve the applications, it did not trigger the requirements
    under § 7(a)(2) of the ESA. Id. at 673. The Court stated that
    “[a]s the mandatory language of [50 C.F.R.] § 402(b) itself
    illustrates, not every action authorized, funded, or carried out
    by a federal agency is a product of that agency’s exercise of
    discretion.” Id. at 668.
    [4] In this case, the district court properly held that the
    Bureau’s renewal of the Settlement Contracts is not subject to
    § 7(a)(2) of the ESA because its action is not a “discretionary
    action.” Under § 8 of the Reclamation Act of 1902, the
    Bureau must operate the CVP in conformity with California
    water law on the “control, appropriation, use, or distribution
    of water used in irrigation, or any vested right acquired there-
    under.” 
    43 U.S.C. § 383
    ; California v. United States, 
    438 U.S. 645
    , 675-79 (1978) (holding that California may impose con-
    ditions on permits granted to the United States for CVP opera-
    tion). Section 8 includes the “full recognition” of any “vested
    right acquired” under California water law. 
    43 U.S.C. § 383
    ;
    United States v. Gerlach Live Stock Co., 
    339 U.S. 725
    , 734
    (1950). Under California law, senior appropriative water
    rights must be satisfied before junior water rights. Pasadena
    v. Alhambra, 
    33 Cal. 2d 908
    , 926 (1949). The Central Valley
    Project Improvement Act (“CVPIA”), Pub.L. 102-575, 
    106 Stat. 4714
     (1992), requires the Bureau to operate the CVP in
    compliance with “all decisions of the California Water
    NRDC v. SALAZAR                         8181
    Resources Control Board.” CVPIA § 3406(a). The California
    Water Resources Control Board issued Decision 990 in which
    it agreed to grant the Bureau rights to operate the CVP only
    if it addressed the issue of those claiming to hold senior water
    rights. Under the Settlement Contracts, negotiated at the
    behest of the California Water Resources Control Board, the
    Bureau is required to deliver base supply water for free and
    that the supply may only be reduced by 25% in critically dry
    years. The duty to deliver the base supply water is mandatory.
    Under the contracts, the contractors are entitled to 100% of
    their base water, which can only be reduced by 25% in very
    dry years. Under the CVPIA, the Bureau is required to renew
    these contracts upon request. See CVPIA § 3404(c).
    [5] Here, the Bureau’s discretion is limited with regard to
    the Settlement Contracts so that § 7(a)(2) of the ESA is not
    triggered. The Bureau’s hands are tied historically by those
    asserting senior water rights in the CVP. The Bureau was
    required to acknowledge such rights in order to operate the
    CVP, which it did by entering the Settlement Contracts. We
    agree with the district court, which held
    Plaintiffs’ claims fail as to the [Settlement Contracts]
    because [the Bureau’s] discretion is substantially
    constrained by prior contract. Therefore, following
    the Supreme Court’s decision in Home Builders,
    [
    551 U.S. 644
    ], Section 7(a)(2) of the ESA does not
    apply to the [Settlement] Contract renewal process.
    Specifically, Article 9(a) of the [Settlement] Con-
    tracts requires [the Bureau] to renew these contracts
    for the same quantity of water, the same allocation
    of water between base supply and project water, and
    the same place of use on specifically designated land
    as the original contracts. By executing the original
    [Settlement] Contracts, [the Bureau] surrendered its
    power to change these terms. Article 9(a) of the [Set-
    tlement] Contracts provides for the exact definition
    of water rights achieved in the original [Settlement]
    8182                  NRDC v. SALAZAR
    Contracts to be preserved upon renewal. This sub-
    stantially constrains [the Bureau’s] discretion to
    reduce diversions of Sacramento River System water
    for the benefit of the Delta smelt or any other reason,
    by fixing [Settlement] Contractor quantities, alloca-
    tions, and places of use upon renewal.
    Natural Res. Def. Council v. Kempthorne, No. 1:05-cv-1207,
    
    2009 WL 1575208
    , at *2 (E.D. Cal. June 3, 2009).
    III.   CONCLUSION
    [6] We hold that the district court properly granted sum-
    mary judgment for defendants, finding that plaintiffs lack
    standing with regard to the DMC contracts and that § 7(a)(2)
    of the ESA does not apply to the Settlement Contracts.
    AFFIRMED.
    PAEZ, Circuit Judge, dissenting:
    I respectfully dissent. I agree with the majority that this
    case is not moot. I disagree with the majority’s holdings that
    the plaintiffs lack standing to challenge the Bureau’s renewal
    of the Delta-Mendota Canal (“DMC”) contracts and that
    § 7(a)(2) of the Endangered Species Act (“ESA”), 
    16 U.S.C. § 1536
    (a)(2), does not apply to the United States Bureau of
    Reclamation’s (“Bureau”) renewals of the Sacramento River
    Settlement (“SRS”) contracts. Accordingly, I would reverse
    the district court’s grant of summary judgment to the defen-
    dants and remand for further proceedings.
    I
    I can not agree with the majority’s holding that the plain-
    tiffs lack standing to challenge the Bureau’s renewals of the
    NRDC v. SALAZAR                            8183
    DMC contracts. Because the plaintiffs allege a straightfor-
    ward procedural injury, they “must show only that they have
    a procedural right that, if exercised, could protect their con-
    crete interests.” Defenders of Wildlife v. EPA, 
    420 F.3d 946
    ,
    957 (9th Cir. 2005) (emphasis in original), overruled on other
    grounds by Nat’l Assoc. of Home Builders v. Defenders of
    Wildlife, 
    551 U.S. 644
     (2007). In my view, the plaintiffs have
    easily made such a showing.
    The plaintiffs argue that the Bureau violated the ESA when
    it renewed the 41 contracts at issue in this case—including the
    DMC contracts—without consulting with the United States
    Fish and Wildlife Service (the “Service”) on whether its
    actions were “likely to jeopardize the continued existence of”
    the delta smelt, a threatened species. See ESA § 7(a)(2), 
    16 U.S.C. § 1536
    (a)(2).1 I agree with the majority’s conclusion
    that the plaintiffs alleged a procedural injury. Our precedent
    makes clear, then, that the plaintiffs have standing if they can
    demonstrate that ESA compliance by the Bureau could
    advance their concrete interest in protecting the delta smelt
    and its habitat. See Salmon Spawning & Recovery Alliance v.
    Gutierrez, 
    545 F.3d 1220
    , 1226 (9th Cir. 2008); Defenders of
    Wildlife, 
    420 F.3d at 957
    .
    The plaintiffs have presented extensive evidence from
    which a reasonable factfinder could conclude that the
    Bureau’s ESA compliance would likely improve the condi-
    tions of the delta smelt and its habitat.2 For example, the
    1
    ESA § 7(a)(2) provides that, “[e]ach Federal agency shall, in consulta-
    tion with and with the assistance of the Secretary [of the Interior], insure
    that any action authorized, funded, or carried out by such agency . . . is
    not likely to jeopardize the continued existence of any endangered species
    or threatened species or result in the destruction or adverse modification
    of habitat of such species which is determined by the Secretary . . . to be
    critical.” 
    16 U.S.C. § 1536
    (a)(2).
    2
    Because we are reviewing a grant of summary judgment to the defen-
    dants, we must resolve all factual disputes in favor of the plaintiffs in
    determining whether they have standing. See Lujan v. Defenders of Wild-
    life, 
    504 U.S. 555
    , 561 (1992).
    8184                       NRDC v. SALAZAR
    plaintiffs allege that if the Bureau were to consult with the
    Service on the DMC contracts, it might choose to provide less
    water to the contractors, which would improve the conditions
    of the delta smelt and its habitat. The plaintiffs also allege that
    consultation by the Bureau might result in a pricing structure
    that is more protective of the delta smelt and its habitat.
    Finally, the plaintiffs allege that if the Bureau were to consult
    on the contracts, it might choose to alter the timing of water
    deliveries, which could inure to the benefit of the delta smelt
    and its habitat. The plaintiffs’ allegations and the record evi-
    dence to support them would allow a reasonable factfinder to
    conclude that the Bureau’s ESA compliance could further the
    plaintiffs’ concrete interest in protecting the delta smelt and
    its habitat. On this record, I would hold that the plaintiffs have
    standing to challenge the DMC contracts.
    The majority places unwarranted emphasis on the shortage
    provision of the DMC contracts. As the majority explains, this
    provision allows the Bureau to forsake water deliveries to the
    DMC contractors as necessary to comply with the ESA.3 The
    majority concludes that because the terms of the DMC con-
    tracts authorize the Bureau to comply with the ESA, the plain-
    tiffs do not have standing to assert a claim that the Bureau is
    violating the consultation requirement of ESA § 7(a)(2). This
    reasoning makes no sense. That the contracts allow the
    Bureau to comply with the ESA certainly does not ensure that
    the Bureau will do so. The plaintiffs contend that the Bureau
    violated the ESA; the fact that the DMC contracts contain a
    shortage provision tells us nothing about whether the plain-
    tiffs are right.4 Therefore, I dissent from the majority’s hold-
    3
    Specifically, as the district court noted, each DMC contract contains a
    provision that expressly allows the Bureau to take actions to protect Delta
    smelt, including not delivering any water to DMC contractors if required
    to comply with section 7(a)(2) . . . .” NRDC v. Kempthorne (NRDC I),
    
    2008 WL 5054115
     at *15 (E.D. Cal. 2008).
    4
    In addition to a shortage provision, the DMC contracts also contain a
    liability-release provision that “relieves the Bureau of liability for any
    NRDC v. SALAZAR                             8185
    ing that the plaintiffs lack standing to challenge the Bureau’s
    renewals of the DMC contracts at issue in this case.
    II
    I also disagree with the majority’s holding that the require-
    ments of ESA § 7(a)(2) do not apply to the Bureau’s renewals
    of the SRS contracts. Pursuant to 
    50 C.F.R. § 402.03
    , the
    requirements of ESA § 7(a)(2) “apply to all actions in which
    there is discretionary Federal involvement or control.” The
    Supreme Court upheld this regulation in Nat’l Assoc. of Home
    Builders v. Defenders of Wildlife, stating, “§ 7(a)(2)’s no-
    jeopardy duty covers only discretionary agency actions and
    does not attach to actions . . . that an agency is required by
    statute to undertake once certain specified triggering events
    have occurred.” 
    551 U.S. 644
    , 669 (2007) (emphasis in origi-
    nal). I disagree with the majority’s conclusion that the
    Bureau’s renewals of the SRS contracts were not discretion-
    ary agency actions.
    A federal agency action is not discretionary when “consul-
    tation would be a meaningless exercise” and when “the
    agency simply does not possess the ability to implement mea-
    sures that inure to the benefit of the protected species.” Sierra
    Club v. Babbitt, 
    65 F.3d 1502
    , 1509 (9th Cir. 1995). For
    example, when an agency “cannot simultaneously obey the
    differing mandates set forth in [ESA] § 7(a)(2)” and another
    direct or indirect damage arising from reduced deliveries to DMC Con-
    tractors as a result of, among other things, actions taken by the Contracting
    Officer to meet legal obligations.” NRDC I, 
    2008 WL 5054115
     at *15
    (internal quotation marks omitted). I see one feature of the liability-release
    and shortage provisions that could inform our standing analysis, and it
    favors the plaintiffs’ redressibility argument. Because the liability-release
    and shortage provisions give the Bureau the ability to comply with the
    ESA without breaching the DMC contracts, these provisions guarantee
    that the DMC contracts are not a barrier to the Bureau’s ability to redress
    the plaintiffs’ alleged injuries.
    8186                   NRDC v. SALAZAR
    statutory provision, the agency need not follow § 7(a)(2). See
    Home Builders, 
    551 U.S. at 666
     (holding that EPA action was
    not discretionary where mandated by the Clean Air Act); see
    also Babbitt, 
    65 F.3d at 1509
    . On the other hand, “if the proj-
    ect’s implementation depend[s] on additional agency action,”
    then the agency “c[an] not avoid the procedural requirements
    of section 7(a)(2).” Babbit, 
    65 F.3d at 1509
    ; see also Karuk
    Tribe of California v. U.S. Forest Serv., ___ F.3d ___, 
    2012 WL 1959231
    , *17 (9th Cir. 2012) (en banc) (“Under our
    established case law, there is ‘agency action’ sufficient to trig-
    ger the ESA consultation duty whenever an agency makes an
    affirmative, discretionary decision about whether, or under
    what conditions, to allow private activity to proceed.”).
    The plaintiffs contend that the Bureau’s renewals of the
    SRS contracts were discretionary actions for two reasons: (a)
    because the Bureau could have chosen simply to not renew
    the SRS contracts; and (b) because the Bureau could have
    negotiated terms in the renewed SRS contracts that were pro-
    tective of the delta smelt and its habitat. I agree with the
    plaintiffs.
    A.     Discretion Not to Renew the SRS Contracts
    1.    Central Valley Project Improvement Act
    The majority holds that the Central Valley Project Improve-
    ment Act (“CVPIA”) § 3404(c) compels the Bureau to renew
    the SRS contracts. Op. at 8180-81. I disagree. CVPIA
    § 3404(c) provides, “the Secretary shall, upon request, renew
    any existing long-term repayment or water service contract
    for the delivery of water from the Central Valley Project for
    a period of twenty-five years and may renew such contracts
    for successive periods of up to 25 years each.” CVPIA
    § 3404(c), 
    106 Stat. 4600
    , 4707 (1992). By its terms, CVPIA
    § 3404(c) applies only to “long-term repayment [and] water
    service” contracts. There are several reasons to conclude that
    NRDC v. SALAZAR                            8187
    the SRS contracts are not “water service” contracts within the
    meaning of § 3404(c).5
    First, the CVPIA expressly distinguishes SRS contracts
    from “water service” contracts in another section, § 3405(a).6
    Section 3405(a) thus demonstrates that Congress considered
    “water service” contracts and settlement contracts to be two
    distinct categories of contracts. Accord Powerex Corp. v.
    Reliant Energy Servs., Inc., 
    551 U.S. 224
    , 232 (2007) (“A
    standard principle of statutory construction provides that iden-
    tical words and phrases within the same statute should nor-
    mally be given the same meaning.”).
    Second, § 3404(c) refers to contracts for “water from the
    Central Valley Project.” The CVPIA defines “Central Valley
    Project water” as “[a]ll water that is developed, diverted,
    stored or delivered by the Secretary in accordance with the
    statutes authorizing the Central Valley Project and in accor-
    dance with the terms and conditions of water rights acquired
    pursuant to California Law.” § 3403(f) (emphasis added). The
    SRS contractors persuasively argue that the water they use is
    not “Central Valley Project water” because it is not diverted
    by the federal government. Rather, the SRS contractors divert
    water directly from the Sacramento River. Because the SRS
    contracts do not involve “Central Valley Project water,”
    § 3404(c) seems inapplicable.
    Third, until this litigation, the Bureau had taken the posi-
    tion that the SRS contracts are not “water service” contracts
    within the meaning of § 3404(c).7 Of course, that the Bureau
    5
    It is undisputed that the SRS contracts are not “long-term repayment”
    contracts, as referenced in § 3404(c).
    6
    Section 3405(a) gives “all individuals or districts who receive Central
    Valley Project water under water service or repayment contracts, water
    rights settlement contracts, or exchange contracts” the right to transfer
    water. (emphasis added).
    7
    For example, in its 2004 EIS on the SRS contract renewals, the Bureau
    explained that “[t]he CVPIA expressly distinguishes Settlement Contracts
    8188                       NRDC v. SALAZAR
    has changed course is not fatal to its argument, but it is pow-
    erful evidence that Congress did not intend § 3404(c) to apply
    to the SRS contracts.8 Moreover, in 2004 Congress passed a
    rider to is appropriations bill that provided two additional
    years for the SRS contracts to be renewed, apparently contem-
    plating the possibility that the SRS contracts would otherwise
    expire. Energy Water Development Appropriation Act, Pub.
    L. No. 108-137, 
    117 Stat. 1827
     (2003). For these reasons, I
    would hold that CVPIA § 3404(c) does not require renewal of
    the SRS contracts.
    2.     State Water Resources Control Board Decision 990
    I disagree with the majority’s holding that a decision of
    California’s State Water Resources Control Board (SWRCB)
    requires the Bureau to renew the SRS contracts. Op. at 8181.
    In 1961, the SWRCB issued Decision 990 (“D-990”), which
    granted the Bureau state water permits to operate the CVP.
    Federal law requires the Bureau to comply with this decision.
    
    43 U.S.C. § 383
    ; see also California v. United States, 
    438 U.S. 645
    , 653 (1978).
    The SRS contractors argue that Condition 23 of D-990
    compels the Bureau to renew the SRS contracts. Condition 23
    provides:
    The export of stored water under [the applicable per-
    from ‘CVP water service contracts’ or ‘repayment contracts.’ ” The
    Bureau even noted that “it is common for commentors to mistake CVPIA
    provisions relating to other types of contracts (i.e. water service contracts
    or repayment contracts, sometimes referred to as 9(e) contracts) as relating
    to all types of CVP water contracts. This is not the case. . . . [T]he provi-
    sion in Section 3404(c) limiting the term of repayment and water service
    contracts to a period not to exceed 25 years does not apply to the Settle-
    ment Contracts.” ER 1844-45.
    8
    The Bureau now characterizes the SRS contracts as “hybrid” contracts
    that are “both water service and settlement contracts.” The CVPIA, how-
    ever, does not refer to “hybrid” contracts.
    NRDC v. SALAZAR                          8189
    mits] outside the watershed of Sacramento River
    Basin or beyond the Sacramento-San Joaquin Delta
    shall be subject to the reasonable beneficial use of
    said stored water within said watershed and Delta,
    both present and prospective, provided, however,
    that agreements for the use of said stored water are
    entered into with the United States prior to March 1,
    1964, by parties currently diverting water from Sac-
    ramento River and/or Sacramento-San Joaquin
    Delta. . . .
    Like the district court, I read Condition 23 to have simply
    imposed a deadline—March 1, 1964—by which the parties
    were required to enter into the SRS contracts. It seems
    implausible that Condition 23 meant that the SRS contracts,
    entered for 40-year terms, were permanent. Therefore, I
    would reject the SRS contractors’ argument that D-990 com-
    pels renewal of the SRS contracts.
    Having concluded that the Bureau has discretion simply not
    to renew the SRS contracts, I would hold that the Bureau must
    comply with ESA § 7(a)(2). See, e.g., NRDC v. Houston, 
    146 F.3d 1118
    , 1126 (9th Cir. 1998); Turtle Island v. Nat’l Marine
    Fisheries Serv., 340. F3d 969, 977 (9th Cir. 2003).
    B.     Discretion to Negotiate the Terms of the SRS Renewal
    Contracts
    1.     Contract Language
    The majority holds that a provision contained in the origi-
    nal SRS contracts constrains the Bureau’s discretion to nego-
    tiate terms upon renewal that might inure to the benefit of the
    delta smelt.9 I disagree. Because I would conclude that the
    9
    As the district court noted, “[u]nder certain circumstances, a prior
    agreement, permit, or management decision that predates the listing of a
    species may constrain a federal agency’s ability to take action on behalf
    of that listed species, absolving the agency from the requirement of con-
    sultation.” NRDC II, 621 F.Supp.2d at 976 (E.D. Cal. 2009) (citing Bab-
    bitt, 
    65 F.3d at 1509
    ).
    8190                   NRDC v. SALAZAR
    original SRS contracts do not prevent the Bureau from renew-
    ing the SRS contracts on terms that might benefit the delta
    smelt and its habitat, I would hold that the Bureau must com-
    ply with the consultation requirements of ESA § 7(a)(2). See
    Houston, 
    146 F.3d at 1126
     (holding that “there was discretion
    available to the Bureau during the negotiation process” where,
    like here, the government was entitled to renew water con-
    tracts on “mutually agreeable” terms).
    The district court correctly noted that we must “look to
    general principles concerning the interpretation of contracts”
    in interpreting a contract to which the United States is a party.
    NRDC v. Kempthorne (NRDC II), 
    621 F.Supp.2d 954
    , 980
    (E.D. Cal. 2009). One of the bedrock principles of contract
    interpretation is that “[a] written contract must be read as a
    whole and every part interpreted with reference to the whole,
    with preference given to reasonable interpretations.” Klamath
    Water Users Protective Ass’n v. Patterson, 
    204 F.3d 1206
    ,
    1210 (9th Cir. 1999) (quoted in NRDC II, 
    621 F.Supp.2d at 980
    ). Moreover, we must interpret the SRS renewal contracts
    “so as to avoid internal conflict.” Trident Ctr. v. Conn. Gen.
    Life Ins. Co., 
    847 F.2d 564
    , 566 (9th Cir. 1988) (quoted in
    NRDC II, 
    621 F.Supp.2d at 980
    ).
    I disagree with the majority’s holding that Article 9(a) of
    the original SRS contracts prevents the Bureau from negotiat-
    ing the terms of the renewed SRS contracts. Article 9(a) of
    each original SRS contract provides:
    (a) During the term of this contract and any renewal
    thereof:
    (1) It shall constitute the full agreement as
    between the United States and the Contrac-
    tor as to the quantities of water and the allo-
    cation thereof between the base supply and
    Project Water which may be diverted by the
    Contractor from the Sacramento River for
    NRDC v. SALAZAR                       8191
    beneficial use . . . which said diversion, use,
    and allocation shall not be disturbed so long
    as the Contractor shall fulfill all its obliga-
    tions hereunder; and
    (2) The Contractor shall not claim any right
    against the United States in conflict with
    the provisions thereof.
    Like the district court, the majority interprets Article 9(a) to
    mean that the terms of the original SRS contracts constitute
    full agreement on all material terms, for all future renewals of
    the contracts. Op. at 8181-82. Read in isolation, Article 9(a)’s
    use of the phrase “full agreement” does seem to preclude the
    possibility of renegotiating the terms of the SRS contracts
    upon renewal. Read in context, however, the majority’s inter-
    pretation is unworkable because Article 2 of each SRS con-
    tract provides:
    This contract shall remain in effect until and includ-
    ing March 31, 2004: Provided, That under terms and
    conditions mutually agreeable to the parties hereto,
    renewals may be made for successive period not to
    exceed forty (40) years each. The terms and condi-
    tions of each renewal shall be agreed upon not later
    than one (1) year prior to the expiration of the then
    existing contract. . .
    (emphasis added). The language of Article 2 strongly suggests
    that the parties anticipated renegotiating the terms of the SRS
    contracts upon renewal.
    In light of Article 2 and the history of the SRS contracts,
    I interpret Article 9(a) to be a partial integration clause, which
    merely guarantees that each SRS contract (and renewal
    thereof) constitutes a “full agreement” between the parties
    with respect to water quantity and allocation. In other words,
    it appears that Article 9(a) was included in each SRS contract
    8192                      NRDC v. SALAZAR
    to avoid litigating the extent of the SRS contractors’ underly-
    ing water rights.10 The majority’s interpretation—that Article
    9(a) freezes in perpetuity the precise water quantity and allo-
    cation terms of each SRS contract—is illogical in light of
    Article 2, which expressly states that the terms and conditions
    of the renewal contracts must be “mutually agreeable.” Thus,
    I would hold that Articles 2 and 9(a) must be harmonized, and
    that the only sensible reading of Article 9(a) is that it is a par-
    tial integration clause.
    Moreover, even if Article 9(a) did constrain the Bureau’s
    discretion to renegotiate the water quantity and allocation
    terms of the SRS contracts upon renewal—which I do not
    think it does—the plaintiffs persuasively point out that Article
    9(a), by its terms, does not constrain the Bureau’s discretion
    to renegotiate non-quantity contract terms, such as the terms
    governing the pricing and timing of water deliveries. Because
    the Bureau has discretion to negotiate terms of the SRS
    renewal contracts that could inure to the benefit of the delta
    smelt, I would hold that it must comply with ESA § 7(a)(2).
    I therefore dissent from the majority’s holding that the Bureau
    was not required to comply with the consultation require-
    ments of § 7(a)(2) in renewing the SRS contracts.
    III
    For the foregoing reasons, I would reverse the district
    court’s grant of summary judgment to the defendants and
    remand this case to the district court for consideration in the
    first instance of the merits of the plaintiffs’ claims involving
    the DMC contracts and for further consideration of the plain-
    tiffs’ claims involving the SRS contracts.
    10
    The Bureau and the Sacramento River water users entered the SRS
    contracts in 1964 after the SWRCB instructed the parties to reach a settle-
    ment agreement rather than engage in a “lengthy and extremely costly
    adjudication of the waters of the Sacramento River and its tributaries.”
    

Document Info

Docket Number: 09-17661

Citation Numbers: 686 F.3d 1092

Judges: Hug, Liam, O'Grady, Paez, Procter, Richard

Filed Date: 7/17/2012

Precedential Status: Precedential

Modified Date: 8/5/2023

Authorities (22)

forest-guardians-a-nonprofit-corporation-white-mountain-conservation , 329 F.3d 1089 ( 2003 )

Butte Environmental Council v. US ARMY CORPS , 620 F.3d 936 ( 2010 )

tinoqui-chalola-council-of-kitanemuk-and-yowlumne-tejon-indians-and , 232 F.3d 1300 ( 2000 )

Trident Center v. Connecticut General Life Insurance Company , 847 F.2d 564 ( 1988 )

SAN LUIS WATER AUTHORITY v. Salazar , 638 F.3d 1163 ( 2011 )

sierra-club-headwaters-inc-forest-conservation-council-and-oregon-natural , 65 F.3d 1502 ( 1995 )

City of Pasadena v. City of Alhambra , 33 Cal. 2d 908 ( 1949 )

natural-resources-defense-council-trout-unlimited-of-california-bay , 146 F.3d 1118 ( 1998 )

sarah-curtis-foster-kim-jean-fey-anthony-wohllaib-and-metropolitan-public , 347 F.3d 742 ( 2003 )

defenders-of-wildlife-center-for-biological-diversity-craig-miller-v , 420 F.3d 946 ( 2005 )

97-cal-daily-op-serv-7390-97-daily-journal-dar-11916-american , 126 F.3d 1118 ( 1997 )

San Luis & Delta-Mendota Water Auth. v. Salazar , 760 F. Supp. 2d 855 ( 2010 )

Natural Resources Defense Council v. Kempthorne , 621 F. Supp. 2d 954 ( 2009 )

Salmon Spawning & Recovery Alliance v. Gutierrez , 545 F.3d 1220 ( 2008 )

California v. United States , 98 S. Ct. 2985 ( 1978 )

Warth v. Seldin , 95 S. Ct. 2197 ( 1975 )

United States v. Gerlach Live Stock Co. , 70 S. Ct. 955 ( 1950 )

California v. Sierra Club , 101 S. Ct. 1775 ( 1981 )

Powell v. McCormack , 89 S. Ct. 1944 ( 1969 )

Lujan v. Defenders of Wildlife , 112 S. Ct. 2130 ( 1992 )