Sandra Bahr v. Epa , 836 F.3d 1218 ( 2016 )


Menu:
  •                 FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    SANDRA L. BAHR; DAVID                     No. 14-72327
    MATUSOW,
    Petitioners,
    OPINION
    v.
    U.S. ENVIRONMENTAL PROTECTION
    AGENCY; GINA MCCARTHY,
    Administrator, United States
    Environmental Protection Agency;
    JARED BLUMENFELD, Regional
    Administrator, EPA Region IX,
    Respondents,
    STATE OF ARIZONA,
    Respondent-Intervenor.
    On Petition for Review of an Order of the
    Environmental Protection Agency
    Argued and Submitted June 17, 2016
    San Francisco, California
    Filed September 12, 2016
    2                        BAHR V. U.S. EPA
    Before: Richard R. Clifton and Sandra S. Ikuta, Circuit
    Judges, and William Q. Hayes,* District Judge.
    Opinion by Judge Ikuta;
    Partial Concurrence and Partial Dissent by Judge Clifton
    SUMMARY**
    Environmental Law
    The panel granted in part and denied in part a petition for
    review of an order of the United States Environmental
    Protection Agency approving Arizona’s Five Percent Plan for
    airborne particulate matter around Maricopa County,
    promulgated under the Clean Air Act.
    Arizona submitted a new State Implementation Plan
    revision on May 25, 2012 – the Five Percent Plan – to
    achieve a five percent annual reduction in PM-10, a harmful
    air pollutant.
    Petitioners alleged that the EPA acted contrary to law by
    failing to require that Arizona include an updated analysis of
    best available control measures and most stringent measures
    in the Five Percent Plan, excluding 135 exceedances from the
    monitoring data as “exceptional events,” and allowing
    *
    The Honorable William Q. Hayes, United States District Judge for
    the Southern District of California, sitting by designation.
    **
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    BAHR V. U.S. EPA                       3
    Arizona to satisfy the “contingency measures” requirement
    with previously implemented control measures.
    The panel held that it would apply Chevron U.S.A. Inc. v.
    Natural Resources Defense Council, Inc., 
    467 U.S. 837
    (1984), deference to the EPA’s interpretation of the Clean Air
    Act issued in connection with a State Implementation Plan
    approval.
    The panel upheld the EPA’s determination that the control
    measures in Arizona’s Five Percent Plan did not need to be
    updated, and that the 135 exceedances were exceptional
    events that were excluded from consideration under the
    EPA’s regulation and guidance documents.
    The panel did not defer to the EPA’s interpretation of the
    contingency measures requirement, however, because under
    the plain language of 42 U.S.C. § 7502(c)(9) contingency
    measures are measures that will be taken in the future, not
    measures that have already been implemented. The panel
    remanded to the EPA for further consideration of this portion
    of the State Implementation Plan, but otherwise denied the
    petition.
    Judge Clifton concurred in sections I-IV of the majority
    opinion, and dissented from the majority’s conclusion in
    section V that EPA’s approval of the contingency measures
    in Arizona’s State Implementation Plan was contrary to the
    clear language of the Clean Air Act. In his view, the scope of
    the Clean Air Act’s contingency measures requirement was
    ambiguous and EPA’s reasonable interpretation of that
    requirement was entitled to deference.
    4                   BAHR V. U.S. EPA
    COUNSEL
    Joy E. Herr-Cardillo (argued) and Timothy M. Hogan,
    Arizona Center for Law in the Public Interest, Tucson,
    Arizona, for Petitioners.
    Alan D. Greenberg (argued), Attorney; Sam Hirsch, Acting
    Assistant Attorney General; Environment & Natural
    Resources Division, United States Department of Justice,
    Denver, Colorado; Geoffrey Wilcox, Office of General
    Counsel; Kara Christenson, Office of Regional Counsel,
    Region 9; United States Environmental Protection Agency,
    San Francisco, California; for Respondents.
    Monique Coady, Assistant Attorney General, Office of the
    Attorney General, Phoenix, Arizona, for Respondent-
    Intervenor.
    OPINION
    IKUTA, Circuit Judge:
    Sandra Bahr and David Matusow petition for review of a
    final rule issued by the Environmental Protection Agency
    (EPA) approving Arizona’s Five Percent Plan for airborne
    particulate matter around Maricopa County. They argue that
    the EPA erred in approving this plan because it did not
    include best available control measures (BACM) and most
    stringent control measures (MSM) as of 2012. The
    petitioners also argue that the EPA failed to follow its own
    published guidance in approving Arizona’s claim that 135
    exceedances of the air emission standard could be excluded
    from consideration. See 42 U.S.C. § 7619(b)(1)(A). Finally,
    BAHR V. U.S. EPA                       5
    the petitioners argue that the EPA’s approval of the
    contingency measures included in Arizona’s Five Percent
    Plan was contrary to 42 U.S.C. § 7502(c)(9) because the
    measures had already been implemented. We uphold the
    EPA’s determination that the control measures in Arizona’s
    Five Percent Plan did not need to be updated, and that the 135
    exceedances were exceptional events that are excluded from
    consideration under the EPA’s regulation and guidance
    documents. We do not defer to the EPA’s interpretation of
    the contingency measures requirement, however, because
    under the plain language of § 7502(c)(9) contingency
    measures are measures that will be taken in the future, not
    measures that have already been implemented.
    I
    We begin by briefly describing the statutory framework.
    The Clean Air Act (CAA), 42 U.S.C. § 7401 et seq.,
    establishes “cooperative Federal, State, regional, and local
    programs to prevent and control air pollution,” 
    id. § 7401(a)(4).
    Under the CAA, the EPA is required to
    “publish . . . a list which includes each air pollutant . . .
    emissions of which, in [the EPA’s] judgment, cause or
    contribute to air pollution which may reasonably be
    anticipated to endanger public health or welfare.” 
    Id. § 7408(a)(1).
    The EPA is then required to “prescrib[e] a
    national primary ambient air quality standard” (NAAQS) for
    that pollutant. 
    Id. § 7409(a).
    One such harmful air pollutant is “PM-10,” defined as
    “particulate matter with an aerodynamic diameter less than or
    6                    BAHR V. U.S. EPA
    equal to a nominal ten micrometers.” 
    Id. § 7602(t).
    According to the EPA, “PM-10 causes adverse health
    effects by penetrating deep into the lungs, aggravating
    the cardiopulmonary system.” Approval and Promulgation
    of Implementation Plans—Maricopa County PM-10
    Nonattainment Area, 79 Fed. Reg. 7118, 7118 (Feb. 6, 2014).
    The EPA established a NAAQS for PM-10 of 150
    micrograms per cubic meter, averaged over a 24-hour period.
    40 C.F.R. § 50.6(a). This standard, which is sometimes
    referred to as the “24-hour PM-10 standard,” is “attained
    when the expected number of days per calendar year with a
    24-hour average concentration above 150 ìg/m³ . . . is equal
    to or less than one.” 
    Id. The CAA
    provides that “[e]ach State shall have the
    primary responsibility for assuring air quality” within the
    state “by submitting an implementation plan” explaining how
    the state will meet and maintain the NAAQS and other
    standards. 42 U.S.C. § 7407(a). An area within a state that
    does not meet a NAAQS is designated as a “nonattainment”
    area, 
    id. § 7407(d).
    Each state’s implementation plan (called
    a State Implementation Plan or SIP) must provide for the
    “implementation, maintenance, and enforcement” of the
    NAAQS. 
    Id. § 7410(a)(1).
    The CAA requires each SIP for
    a nonattainment area to contain specified information,
    including a requirement for reasonable further progress, 
    id. § 7502(c)(2),
    an emissions inventory, 
    id. § 7502(c)(3),
    and a
    list of “contingency measures” to “be undertaken if the area
    fails to make reasonable further progress, or to attain the
    BAHR V. U.S. EPA                            7
    national primary ambient air quality standard by the
    attainment date applicable under this part,” 
    id. § 7502(c)(9).1
    The CAA sets out a series of deadlines for states to meet
    the NAAQS for PM-10, with increasingly stringent
    requirements if a state misses a deadline. 
    Id. §§ 7513–7513b.
    The sequence is as follows:
    A nonattainment area is initially designated as a
    “moderate” area. 
    Id. § 7513(a).
    A SIP for a “moderate” PM-
    10 nonattainment area must explain how that area will meet
    the PM-10 NAAQS by the “attainment date,” which for
    nonattainment areas designated by Congress was no later than
    December 31, 1994. 
    Id. § 7513(c)(1).
    The SIP must “assure
    that reasonably available control measures for the control of
    PM-10” are implemented. 
    Id. § 7513a(a).
    If a moderate nonattainment area fails to meet the PM-10
    NAAQS by the attainment date, the EPA must reclassify it as
    a “Serious PM-10 nonattainment area.” 
    Id. § 7513(b).
    After
    redesignation, the state must submit a SIP that demonstrates
    how the area will meet the PM-10 NAAQS within 10 years of
    1
    42 U.S.C. § 7502(c)(9) states:
    (9) Contingency measures
    Such plan shall provide for the implementation of
    specific measures to be undertaken if the area fails to
    make reasonable further progress, or to attain the
    national primary ambient air quality standard by the
    attainment date applicable under this part. Such
    measures shall be included in the plan revision as
    contingency measures to take effect in any such case
    without further action by the State or the Administrator.
    8                          BAHR V. U.S. EPA
    the original nonattainment designation, or, for areas originally
    designated as nonattainment by Congress, no later than
    December 31, 2001. 
    Id. § 7513(c)(2).
    A SIP for a serious
    nonattainment area must also “assure that the best available
    control measures [BACM] for the control of PM-10 shall be
    implemented.” 
    Id. § 7513a(b).2
    If a state fails to meet the deadline for bringing a Serious
    Area into compliance, the EPA may grant the state a single
    five-year extension of the deadline to meet the NAAQS for
    PM-10, but only if the state submits a SIP that “includes the
    most stringent measures [MSM] that are included in the
    implementation plan of any State or are achieved in practice
    in any State, and can feasibly be implemented in the area.”
    
    Id. § 7513(e).3
    2
    42 U.S.C. § 7513a(b) provides:
    (b) Serious Areas
    (1) Plan provisions. In addition to the provisions
    submitted to meet the requirements of paragraph [1]
    (a)(1) (relating to Moderate Areas), each State in which
    all or part of a Serious Area is located shall submit an
    implementation plan for such area that includes each of
    the following: . . .
    (B) Provisions to assure that the best available control
    measures for the control of PM-10 shall be
    implemented no later than 4 years after the date the area
    is classified (or reclassified) as a Serious Area.
    3
    42 U.S.C. § 7513(e) provides in pertinent part:
    (e) Extension of attainment date for Serious Areas
    Upon application by any State, the Administrator may
    BAHR V. U.S. EPA                           9
    If a Serious Area fails to achieve compliance by the
    attainment date after receiving the one-time five-year
    extension under § 7513(e), the CAA requires the state to
    “submit within 12 months after the applicable attainment
    date, plan revisions which provide for attainment of the PM-
    10 air quality standard.” 
    Id. § 7513a(d).4
    The SIP revisions
    extend the attainment date for a Serious Area beyond
    the date specified under subsection (c) of this section,
    if attainment by the date established under subsection
    (c) of this section would be impracticable, the State has
    complied with all requirements and commitments
    pertaining to that area in the implementation plan, and
    the State demonstrates to the satisfaction of the
    Administrator that the plan for that area includes the
    most stringent measures that are included in the
    implementation plan of any State or are achieved in
    practice in any State, and can feasibly be implemented
    in the area. . . . The Administrator may not approve an
    extension until the State submits an attainment
    demonstration for the area. The Administrator may
    grant at most one such extension for an area, of no
    more than 5 years.
    4
    42 U.S.C. § 7513a(d) states:
    (d) Failure to attain
    In the case of a Serious PM-10 nonattainment area in
    which the PM-10 standard is not attained by the
    applicable attainment date, the State in which such area
    is located shall, after notice and opportunity for public
    comment, submit within 12 months after the applicable
    attainment date, plan revisions which provide for
    attainment of the PM-10 air quality standard and, from
    the date of such submission until attainment, for an
    annual reduction in PM-10 or PM-10 precursor
    emissions within the area of not less than 5 percent of
    10                     BAHR V. U.S. EPA
    must provide for an annual five percent reduction in PM-10
    within the Serious Area from the date the SIP revision was
    submitted to the EPA until the state attains the NAAQS in
    that area. 
    Id. States are
    required to conduct ambient air quality
    monitoring to determine whether a geographical region or
    area in the state is meeting the NAAQS for PM-10. 
    Id. § 7410(a)(2)(B)(i).
    State air quality monitoring systems must
    use the criteria and methodology established by the EPA. 
    Id. § 7619(a).
    Congress recognized that air quality monitoring
    data could be affected by exceptional events that could not
    reasonably be controlled by the states, and directed the EPA
    to promulgate regulations “governing the review and
    handling of air quality monitoring data influenced by
    exceptional events.” 
    Id. § 7619(b)(2)(A).
    The statute defines
    an “exceptional event” as an event that “(i) affects air quality;
    (ii) is not reasonably controllable or preventable; (iii) is an
    event caused by human activity that is unlikely to recur at a
    particular location or a natural event; and (iv) is determined
    by the Administrator through the process established in the
    regulations promulgated under paragraph (2) to be an
    exceptional event.” 
    Id. § 7619(b)(1)(A).
    Pursuant to this direction, the EPA promulgated the
    “Exceptional Events Rule,” 40 C.F.R. § 50.14. The rule
    repeats the statute’s definition of “exceptional event,” 
    id. the amount
    of such emissions as reported in the most
    recent inventory prepared for such area.
    BAHR V. U.S. EPA                            11
    § 50.1(j),5 and allows a state to “request EPA to exclude data
    showing exceedances or violations of the national ambient air
    quality standard that are directly due to an exceptional event,”
    
    id. § 50.14(a)(1).
    In order to obtain EPA approval to exclude
    exceptional event data, a state must provide evidence that
    “[t]he event satisfies the criteria set forth in 40 C.F.R 50.1(j)”
    and meets other criteria. 
    Id. § 50.14(c)(3)(iv).
    If a state
    makes the required showing, the “EPA shall exclude [the
    exceptional event] data from use in determinations of
    exceedances and NAAQS violations.” 
    Id. § 50.14(b)(1).
    The EPA has recognized that PM-10 levels can be
    affected by natural events such as dust storms, see 
    id. § 50.1(j)–(k),
    and has therefore developed guidance for
    applying the Exceptional Events Rule to high wind events.
    See Treatment of Data Influenced by Exceptional Events,
    72 Fed. Reg. 13560 (Mar. 22, 2007) (Treatment of Data
    Guidance). The Treatment of Data Guidance states that
    increased particulate matter concentrations “raised by
    unusually high winds will be treated as due to uncontrollable
    natural events where (1) the dust originated from
    nonanthropogenic sources, or (2) the dust originated from
    5
    40 C.F.R. § 50.1(j) provides:
    (j) Exceptional event means an event that affects air
    quality, is not reasonably controllable or preventable, is
    an event caused by human activity that is unlikely to
    recur at a particular location or a natural event, and is
    determined by the Administrator in accordance with
    40 CFR 50.14 to be an exceptional event. It does not
    include stagnation of air masses or meteorological
    inversions, a meteorological event involving high
    temperatures or lack of precipitation, or air pollution
    relating to source noncompliance.
    12                       BAHR V. U.S. EPA
    anthropogenic sources within the State, that are determined
    to have been reasonably well-controlled at the time that the
    event occurred, or from anthropogenic sources outside the
    State.” 
    Id. at 13576
    (emphasis added).
    In May 2013, the EPA published additional “guidance
    and interpretation” explaining how the Exceptional Events
    Rule and the Treatment of Data Guidance applies to high
    wind events. See EPA, Interim Guidance on the Preparation
    of Demonstrations in Support of Requests to Exclude
    Ambient Air Quality Data Affected by High Winds Under the
    Exceptional Events Rule (May 2013) (Interim Guidance).6
    The Interim Guidance addresses when an anthropogenic
    source within the State is “reasonably well-controlled at the
    time that the event occurred,” 72 Fed. Reg. at 13576, as
    required by the Treatment of Data Guidance.
    II
    We now provide the background of this case. Congress
    designated Maricopa County, Arizona, as a “moderate” PM-
    10 nonattainment area in 1990. 42 U.S.C. § 7407(d)(4)(B);
    PM10 Group I and Group II Areas, 52 Fed. Reg. 29383,
    29384 (Aug. 7, 1987). The designated nonattainment area,
    termed the “Maricopa County PM-10 Nonattainment Area”
    (Maricopa Area), covers the eastern portion of Maricopa
    County, including the cities of Phoenix, Mesa, Scottsdale,
    6
    The Interim Guidance is available at: https://www.epa.gov/
    sites/production/files/2015-09/documents/exceptevents_highwinds_
    guide_130510.pdf; see also Draft Guidance To Implement Requirements
    for the Treatment of Air Quality Monitoring Data Influenced by
    Exceptional Events, 77 Fed. Reg. 39959, 39960 (July 6, 2012)
    (announcing the availability of a draft version of the Interim Guidance on
    the EPA’s website).
    BAHR V. U.S. EPA                      13
    Tempe, Chandler, and Glendale. 79 Fed. Reg. at 7118. It
    also covers unincorporated parts of Maricopa County and
    portions of Pinal County. 
    Id. Because the
    Maricopa Area was designated as a
    nonattainment area by Congress, Arizona’s first deadline for
    meeting the NAAQS for PM-10 was December 31, 1994.
    42 U.S.C. § 7513(c). The Maricopa Area was not in
    attainment by 1994, so the EPA reclassified the Maricopa
    Area as a Serious PM-10 nonattainment area. 42 U.S.C.
    § 7513(b)(2); Clean Air Act Reclassification; Arizona-
    Phoenix Nonattainment Area; PM-10, 61 Fed. Reg. 21372,
    21373 (May 10, 1996). This required Arizona to submit a
    SIP that would demonstrate how the Maricopa Area would
    meet the NAAQS for PM-10 by December 31, 2001, see
    42 U.S.C. § 7513(c)(2), and to explain how it would
    implement the best available control measures for PM-10, 
    id. § 7513a(b).
    The Maricopa Area did not meet the NAAQS for PM-10
    by the end of 2001. Rather, in 2000 Arizona preemptively
    applied for a five-year extension (until December 2006) under
    § 7513(e) and at the same time submitted a SIP for the
    Maricopa Area (the 2000 SIP). The 2000 SIP proposed to
    implement over 70 best available control measures for major
    dust sources, Approval and Promulgation of Implementation
    Plans; Arizona—Maricopa County PM-10 Nonattainment
    Area; Serious Area Plan for Attainment of the Annual PM-10
    Standard, 65 Fed. Reg. 19964, 19972–83 (Apr. 13, 2000), and
    stated that its measures were “the most stringent measures
    that are included in the implementation plan of any State, or
    are achieved in practice in any State,” 
    id. at 19984.
    In 2002,
    the EPA issued a final rule approving the 2000 SIP and
    granting the requested extension. Approval and Promulgation
    14                       BAHR V. U.S. EPA
    of Implementation Plans; Arizona–Maricopa County PM-10
    Nonattainment Area; Serious Area Plan for Attainment of the
    PM-10 Standards, 67 Fed. Reg. 48718, 48718–19 (July 25,
    2002) (the 2002 Final Rule). The 2002 Final Rule stated that
    the control measures in the 2000 SIP met the BACM and
    MSM standards. Id.7
    By December 2006, the Maricopa Area had still failed to
    meet the NAAQS for PM-10. See Findings of Failure To
    Attain; State of Arizona, Phoenix Nonattainment Area; State
    of California, Owens Valley Nonattainment Area; Particulate
    Matter of 10 Microns or Less, 72 Fed. Reg. 31183, 31184–85
    (June 6, 2007). At that point, the CAA gave Arizona 12
    months to submit revisions to the SIP that would achieve
    attainment of the NAAQS for PM-10, provide for an annual
    five percent reduction in PM-10 in the Maricopa Area,
    42 U.S.C. § 7513a(d), and contain appropriate contingency
    measures, 
    id. § 7502(c)(9).
    Arizona submitted revisions to the Maricopa Area SIP in
    December 2007 (the 2007 SIP). In addition to proposing 53
    control measures, the 2007 SIP proposed revising a
    previously approved agricultural control measure, namely an
    agricultural general permit specifying best management
    practices for reducing PM-10 from agricultural activities. See
    Approval and Promulgation of Implementation Plans—
    Maricopa County (Phoenix) PM-10 Nonattainment Area;
    7
    We considered a challenge to EPA’s 2002 Final Rule approving the
    2000 SIP and held that the EPA’s approval of Arizona’s rejection of a
    measure requiring the use of a reformulated diesel fuel as BACM was
    arbitrary and capricious. Vigil v. Leavitt, 
    381 F.3d 826
    , 841–46 (9th Cir.
    2004). We upheld the rest of the EPA’s approval, including its approval
    of Arizona’s general permit rule for agricultural emissions of PM-10 as
    BACM. 
    Id. at 836–38,
    847.
    BAHR V. U.S. EPA                       15
    Serious Area Plan for Attainment of the 24-Hour PM-10
    Standard; Clean Air Act Section 189(d), 75 Fed. Reg. 54806,
    54810, 54812–13 (Sept. 9, 2010) (the 2010 Proposed Rule).
    The 2010 Proposed Rule stated that the EPA would
    disapprove this revision to the agricultural general permit rule
    on the ground that other states and local agencies had
    “acquired additional expertise about how to control emissions
    from these sources,” and as a result the EPA no longer
    believed that the requirements in the agricultural general
    permit rule in the 2000 SIP were best available control
    measures. 
    Id. To avoid
    a partial disapproval, Arizona
    withdrew the plan in 2011. 79 Fed. Reg. at 7119. As a result
    of this withdrawal of the 2007 SIP, the EPA found that
    Arizona had failed to make a required SIP submittal. Finding
    of Failure To Submit State Implementation Plan Revisions for
    Particulate Matter, PM-10, Maricopa County (Phoenix) PM-
    10 Nonattainment Area, AZ, 76 Fed. Reg. 8300, 8300–01
    (Feb. 14, 2011). This finding required Arizona to submit
    another SIP by 2013. 
    Id. at 8301;
    42 U.S.C. § 7509(a).
    Arizona submitted a new SIP revision on May 25, 2012.
    See 79 Fed. Reg. at 7119. Because this SIP was prepared
    pursuant to § 7513a(d), which requires a state to achieve a
    five percent annual reduction in PM-10, we adopt the EPA’s
    term and refer to it as the “Five Percent Plan.” The Five
    Percent Plan proposed to achieve the five percent annual
    reduction required by § 7513a(d) by implementing many of
    the 53 control measures previously proposed in the 2007 SIP,
    as well as adopting a new emissions control measure, the
    “Dust Action General Permit.” Unlike the 2007 SIP, the Five
    Percent Plan did not propose any changes to the agricultural
    general permit.
    16                      BAHR V. U.S. EPA
    As required by § 7502(c)(9), the Five Percent Plan
    proposed a number of contingency measures. 79 Fed. Reg. at
    7124. Four of the five measures were permanent changes to
    infrastructure that had been completed in the years 2008
    through 2011, namely, paving existing dirt roads and alleys,
    paving and stabilizing unpaved shoulders, repaving or
    overlaying paved roads with rubberized asphalt, and lowering
    speed limits on dirt roads and alleys. 
    Id. The fifth
    contingency measure required the purchase of PM-10
    certified sweepers (which had already been accomplished by
    the end of 2009), and ongoing sweeping of ramps, freeways,
    and frontage roads. 
    Id. Arizona also
    acknowledged that there had been a number
    of exceedances of the 24-hour PM-10 standard during 2011
    and 2012, but claimed they should be deemed “exceptional
    events” and excluded from a determination of whether the
    Maricopa Area met the NAAQS for PM-10. In support of
    this claim, Arizona submitted documentation to the EPA to
    demonstrate that 137 exceedances of the NAAQS for PM-10
    on 27 days during the period from 2011 to 2012 were the
    result of “exceptional events,” namely high wind dust events.
    79 Fed. Reg. at 7122.8 The EPA wrote separate reports on
    each of Arizona’s submissions. The reports analyzed the data
    and concluded that the flagged exceedances met “the
    definition of an exceptional event: the exceedances affected
    air quality, were not reasonably controllable or preventable,
    and meet the definition of a natural event.”
    In February 2014, the EPA published its proposed
    decision regarding Arizona’s Five Percent Plan. 79 Fed. Reg.
    8
    Though the EPA’s proposed rulemaking mentioned 133
    exceedances, the parties agree that Arizona requested approval of 137.
    BAHR V. U.S. EPA                        17
    at 7118. The EPA noted that the monitoring data for the
    Maricopa Area showed 133 exceedances of the 24-hour PM-
    10 NAAQS during the 2011–2012 time period, but stated that
    131 of those exceedances “were caused by high wind
    exceptional events,” and “should not be used for regulatory
    purposes,” including for evaluation of the Five Percent Plan.
    
    Id. at 7122.
    Excluding these exceedances, the EPA proposed
    to determine that the Maricopa Area had attained the NAAQS
    for 24-hour PM-10 by December 31, 2012. 
    Id. at 7125.
    The
    EPA also proposed to approve Arizona’s contingency
    measures. 
    Id. at 7124.
    In doing so, the EPA explained that
    it had previously “interpreted [42 U.S.C. § 7502(c)(9)] to
    allow states to implement contingency measures before they
    are triggered by a failure of . . . attainment as long as those
    measures are intended to achieve emission reductions over
    and beyond those relied on in the attainment and [reasonable
    further progress] demonstrations.” 79 Fed. Reg. at 7124.
    The EPA issued a final rule on June 10, 2014, approving
    the Five Percent Plan “as meeting all relevant statutory and
    regulatory requirements.” Approval and Promulgation of
    Implementation Plans—Maricopa County PM-10
    Nonattainment Area; Five Percent Plan for Attainment of the
    24-Hour PM-10 Standard, 79 Fed. Reg. 33107, 33107 (June
    10, 2014) (2014 Final Rule). The 2014 Final Rule stated that
    the EPA was excluding 135 exceedances9 from the
    monitoring data as exceptional events. 
    Id. at 33111.
    For each
    of the events that EPA determined was exceptional, “EPA
    found that the event was not reasonably controllable or
    preventable,” and that “reasonable controls” were in place for
    9
    The EPA’s final rule clarified that the number of approved
    exceedances was 135, which occurred on 25 days over the period of
    2010–12. 79 Fed. Reg. at 33110–11.
    18                   BAHR V. U.S. EPA
    anthropogenic sources of dust. 
    Id. The EPA
    reached its
    conclusion that “reasonable controls” were in place by relying
    on its 2002 Final Rule approving Arizona’s 2000 SIP as
    including best available control measures and most stringent
    control measures. 
    Id. at 33112.
    The EPA also determined
    that Arizona sufficiently demonstrated that dust sources
    outside the Maricopa Area were reasonably controlled. 
    Id. at 33113.
    The 2014 Final Rule included the EPA’s response to
    comments made by petitioners Sandra Bahr and David
    Matusow, two residents of Phoenix. First, the EPA addressed
    petitioners’ argument that the EPA should have required
    Arizona to update its control measures to ensure that they
    were BACM and MSM, rather than letting Arizona rely on
    the EPA’s approval of the 2000 SIP. 79 Fed. Reg. at
    33108–10. The EPA rejected this claim, explaining that “the
    requirement for BACM is triggered by a specific event: The
    reclassification of a moderate PM-10 nonattainment area to
    serious.” 
    Id. at 33108.
    Likewise, the EPA explained that
    § 7513(e) provides “that the requirement for MSM is
    triggered by a particular event: EPA’s granting of a state’s
    request for an extension of the attainment deadline for a
    serious nonattainment area.” 
    Id. The EPA
    then stated that
    § 7513(d) (the section requiring the submission of a five
    percent plan) “does not contain a specific requirement that the
    state update the previously approved requirements for BACM
    and MSM as a consequence of failing to reach attainment by
    the applicable deadline for serious PM-10 nonattainment
    areas.” 
    Id. at 33109.
    Because there was no statutory trigger
    requiring Arizona to update its demonstration that its control
    measures were best available and most stringent, the EPA
    explained, the Five Percent Plan could rely on the EPA’s
    approval of BACM and MSM in the 2000 SIP. 
    Id. The EPA
                         BAHR V. U.S. EPA                      19
    also disagreed with petitioner’s comment that the Five
    Percent Plan was inadequate because the agricultural control
    measures were not BACM, as indicated by the EPA’s 2010
    Proposed Rule disapproving of Arizona’s proposed revision
    to its agricultural general permit. In response to this
    comment, the EPA stated that the Five Percent Plan satisfied
    the requirements in § 7513a(d) “without relying on additional
    emissions reductions from agricultural sources.” 
    Id. at 33109.
    Second, the EPA addressed petitioners’ argument that its
    determination that the 135 exceedances constituted
    exceptional events was contrary to the Interim Guidance.
    Petitioners interpreted the Interim Guidance as preventing the
    EPA from concurring that best available control measures
    were in place unless the EPA had determined control
    measures for windblown dust to be BACM within the past
    three years. 79 Fed. Reg. at 33111–12. The EPA disagreed
    with this interpretation and concluded that Arizona’s controls
    were reasonable. 
    Id. at 33112.
    The EPA also rejected
    petitioners’ argument that Arizona had failed to provide an
    adequate description of upwind sources and control measures
    as required by the Interim Guidance. 
    Id. at 33113–14.
    Finally, the EPA dismissed petitioners’ comment that the
    EPA erred in accepting Arizona’s “contingency measures” in
    its Five Percent Plan because the measures had already been
    implemented. 
    Id. at 33114–15.
    The petitioners argued that
    because § 7502(c)(9) requires contingency measures that “are
    automatically and immediately implemented if a milestone
    for reasonable further progress or attainment is not met,” the
    previously implemented measures in the Five Percent Plan
    could not qualify. 
    Id. at 33114.
    In rejecting this comment,
    the EPA stated it interpreted § 7502(c)(9) as requiring only
    20                   BAHR V. U.S. EPA
    that “[c]ontingency measures must provide for additional
    emission reductions” that were not otherwise included “in the
    attainment demonstration,” and that “[n]othing in the statute
    precludes a state from implementing such measures before
    they are triggered,” relying on the Fifth Circuit decision in
    Louisiana Environmental Action Network v. EPA, 
    382 F.3d 575
    (5th Cir. 2004). 79 Fed. Reg. at 33114.
    The plaintiffs filed a petition for review of the 2014 Final
    Rule on July 29, 2014.
    III
    Under 42 U.S.C. § 7607(b)(1), we have jurisdiction over
    “[a] petition for review of the Administrator’s action in
    approving or promulgating any implementation plan.”
    In reviewing a challenge to the EPA’s approval of a SIP
    under § 7607(b)(1), we apply “the general standard of review
    for agency actions set forth in the Administrative Procedure
    Act (APA).” Latino Issues Forum v. EPA, 
    558 F.3d 936
    , 941
    (9th Cir. 2009); see also Vigil v. Leavitt, 
    381 F.3d 826
    , 833
    (9th Cir. 2004). Under the APA, we must uphold an agency
    action unless it is “arbitrary, capricious, an abuse of
    discretion, or otherwise not in accordance with law.”
    5 U.S.C. § 706(2)(A). This standard is “highly deferential,
    presuming the agency action to be valid and affirming the
    agency action if a reasonable basis exists for its decision.”
    Ranchers Cattlemen Action Legal Fund United Stockgrowers
    of Am. v. U.S. Dep’t of Agric., 
    499 F.3d 1108
    , 1115 (9th Cir.
    2007). Generally, “[a]n agency decision will be upheld as
    long as there is a rational connection between the facts found
    and the conclusions made.” Barnes v. U.S. Dep’t of Transp.,
    
    655 F.3d 1124
    , 1132 (9th Cir. 2011). We will deem an
    BAHR V. U.S. EPA                       21
    agency action to be arbitrary and capricious only “if the
    agency has relied on factors which Congress has not intended
    it to consider, entirely failed to consider an important aspect
    of the problem, offered an explanation for its decision that
    runs counter to the evidence before the agency, or is so
    implausible that it could not be ascribed to a difference in
    view or the product of agency expertise.” Motor Vehicle
    Mfrs. Ass’n of the U.S. v. State Farm Mut. Auto. Ins. Co.,
    
    463 U.S. 29
    , 43 (1983). Where the question presented for
    review is a factual dispute which implicates “a high level of
    technical expertise” we defer to “the informed discretion of
    the responsible federal agencies.” Kleppe v. Sierra Club,
    
    427 U.S. 390
    , 412 (1976). “Even when an agency explains its
    decision with ‘less than ideal clarity,’ a reviewing court will
    not upset the decision on that account ‘if the agency's path
    may reasonably be discerned.’” Alaska Dep’t of Envtl.
    Conservation v. EPA, 
    540 U.S. 461
    , 497 (2004) (quoting
    Bowman Transp., Inc. v. Ark.-Best Freight Sys., Inc.,
    
    419 U.S. 281
    , 286 (1974)).
    Where the petitioner challenges the agency’s action as
    inconsistent with the agency’s own policies, we examine
    whether the agency has actually departed from its policy and,
    if so, whether the agency has offered a reasoned explanation
    for such departure. See Encino Motorcars, LLC v. Navarro,
    
    136 S. Ct. 2117
    , 2125–26 (2016). Generally, “[a]gencies are
    free to change their existing policies as long as they provide
    a reasoned explanation for the change.” 
    Id. at 2125.
    In
    contrast, where the agency is not offering a policy
    explanation but is instead interpreting a binding regulation,
    the agency’s interpretation is “controlling” unless “plainly
    erroneous or inconsistent with the regulation.” Auer v.
    Robbins, 
    519 U.S. 452
    , 461 (1997).
    22                   BAHR V. U.S. EPA
    Where the agency’s action is an interpretation of a statute
    that the agency administers, “we follow the two-step
    approach set out in Chevron U.S.A. Inc. v. Natural Resources
    Defense Council, Inc., 
    467 U.S. 837
    (1984).” Latino Issues
    
    Forum, 558 F.3d at 941
    . First, “if Congress has ‘directly
    spoken to the precise question at issue,’ then the matter is
    capable of but one interpretation by which the court and the
    agency must abide.” 
    Vigil, 381 F.3d at 834
    (quoting
    
    Chevron, 467 U.S. at 842
    ).
    At the second step of Chevron, if we determine that
    Congress was silent on the issue, or the statute is subject to
    multiple interpretations, we must determine the degree of
    deference to give the agency’s interpretation of a statute.
    United States v. Mead Corp., 
    533 U.S. 218
    , 227–29 (2001).
    “Not all agency statutory interpretations are entitled to
    Chevron deference.” Sierra Club v. EPA, 
    671 F.3d 955
    , 962
    (9th Cir. 2012). “Rather, Chevron deference is appropriate
    where ‘the agency can demonstrate that it has the general
    power to make rules carrying the force of law and that the
    challenged action was taken in the exercise of that
    authority.’” 
    Id. (quoting Wilderness
    Soc’y v. U.S. Fish &
    Wildlife Serv., 
    353 F.3d 1051
    , 1067 (9th Cir. 2003) (en
    banc)). We generally deem Congress to have delegated such
    authority when it authorizes the agency to engage in notice-
    and-comment rulemaking. 
    Mead, 533 U.S. at 229
    –30. In
    such circumstances, a court should accept the agency’s
    interpretation “if Congress has not previously spoken to the
    point at issue and the agency’s interpretation is reasonable.”
    
    Id. at 229.
    Though we have previously applied Chevron deference to
    the EPA’s interpretation of the CAA issued in connection
    with a SIP approval, see Association of Irritated Residents v.
    BAHR V. U.S. EPA                      23
    EPA, 
    686 F.3d 668
    , 679–81 (9th Cir. 2011), we have never
    expressly held that such deference is appropriate, but rather
    have held the question open, see 
    Vigil, 381 F.3d at 835
    (declining to address “whether the EPA’s interpretation of the
    Act in the course of approving Arizona’s SIP is entitled to
    Chevron deference”). But because “[a] very good indicator
    of delegation meriting Chevron treatment [is] express
    congressional authorizations to engage in the rulemaking or
    adjudication process that produces the regulations or rulings
    for which deference is claimed,” Mead 
    Corp., 533 U.S. at 229
    , and because the EPA engages in such a rulemaking
    process in approving a SIP, we agree with the Fifth Circuit
    that “EPA’s final rules approving the [Arizona] SIP, to the
    extent they involve the reasonable resolution of ambiguities
    in the CAA, will be afforded Chevron deference,” BCCA
    Appeal Grp. v. EPA, 
    355 F.3d 817
    , 825 (5th Cir. 2003).
    IV
    On appeal, petitioners argue that the EPA acted contrary
    to law by failing to require that Arizona include an updated
    analysis of best available control measures and most stringent
    measures in the Five Percent Plan. They also argue that the
    EPA abused its discretion by excluding 135 exceedances
    from the monitoring data as “exceptional events.” Finally,
    they argue that the EPA violated the CAA by allowing
    Arizona to satisfy the “contingency measures” requirement
    with previously implemented control measures. We consider
    each argument in turn.
    A
    We first consider petitioners’ argument that the EPA’s
    approval of the Five Percent Plan constituted an abuse of
    24                   BAHR V. U.S. EPA
    discretion because the EPA did not require Arizona to
    demonstrate that the plan included best available control
    measures (BACM) or most stringent measures (MSM) for the
    control of PM-10. According to petitioners, the Five Percent
    Plan must demonstrate that Arizona’s control measures meet
    the BACM and MSM standards because Arizona has a
    continuing obligation to comply with § 7513a(b)(1)(B) and
    § 7513(e), which set the control requirements for serious
    nonattainment areas. Petitioners argue that had a BACM
    demonstration been required, the Five Percent Plan would
    have failed because the agricultural control measures in
    Arizona’s 2000 SIP are no longer BACM, as stated in EPA’s
    2010 Proposed Rule. Further, petitioners argue, the EPA’s
    statement in the 2010 Proposed Rule regarding Arizona’s
    failure to meet the BACM standard is evidence that the EPA
    generally requires an updated BACM demonstration in each
    SIP, meaning that the EPA acted inconsistently by not
    requiring such a demonstration in the Five Percent Plan.
    We disagree with these arguments. The EPA’s decision
    not to require an updated demonstration of BACM and MSM
    in the Five Percent Plan was not an abuse of discretion
    because it was not contrary to any language in the CAA.
    Section 7513a(d), which governs five percent plans such as
    the one before us here, provides only that if a state fails to
    achieve attainment after receiving the five-year extension, it
    must submit plan revisions providing for “attainment of the
    PM-10 air quality standard,” and an annual five percent
    reduction in PM-10 within the Serious Area. It does not
    mention BACM or MSM. The CAA sections that do require
    BACM and MSM demonstrations do not expressly apply to
    a five percent plan. Section § 7513a(b) provides that when
    the EPA reclassifies a Moderate Area as a Serious Area, the
    state must then submit a SIP that “assure[s] that the best
    BAHR V. U.S. EPA                       25
    available control measures for the control of PM-10 shall be
    implemented.” It does not require the state to update that
    assurance when submitting a five percent plan, nor does it
    require the EPA to review its previous BACM determination.
    Similarly, § 7513(e) provides that when the EPA grants a
    state a five-year extension of the deadline to meet the
    NAAQS for PM-10, the state must submit a SIP that
    “includes the most stringent measures” that are included in
    any SIP or achieved in any state. Again, this language does
    not require the state to include an updated demonstration of
    MSM when submitting a five percent plan.
    We also disagree with petitioners’ argument that the EPA
    acted inconsistently in failing to require an updated
    demonstration of BACM and MSM in the Five Percent Plan.
    Even though the EPA had previously reviewed and proposed
    to disapprove the agricultural control measure in Arizona’s
    2007 SIP as not meeting the BACM standard, the EPA
    provided a reasonable interpretation of its approach in the
    2014 Final Rule. According to the EPA, the CAA lays out a
    series of escalating control measures that are triggered by a
    finding of noncompliance with a series of statutory
    requirements. The EPA will assess compliance with the
    control measures that were triggered at each step, but will not
    reassess compliance with those measures at subsequent steps
    unless a state proposes changes to control measures that were
    previously approved. 79 Fed. Reg. at 33108–09. This
    approach is consistent with the CAA, which does not require
    the EPA to reassess a state’s controls in each SIP submission.
    Here, the EPA’s 2010 Proposed Rule reassessed Arizona’s
    agricultural control measures under the BACM standard
    because Arizona proposed to revise agricultural control
    measures that were previously approved as BACM in the
    2002 Final Rule. Arizona did not propose any revisions to its
    26                   BAHR V. U.S. EPA
    agricultural controls in the Five Percent Plan, however, so
    EPA did not have any occasion to reevaluate those measures.
    Given the EPA’s reasonable explanation for its approach, and
    the lack of any contrary statutory command in the CAA, we
    conclude that the EPA did not abuse its discretion or act
    contrary to law by declining to require an updated
    demonstration of BACM or MSM in the Five Percent Plan.
    Petitioners also argue that the EPA acted in an arbitrary
    and capricious manner in reviewing the Five Percent Plan
    because it evaluated Arizona’s compliance with CAA
    requirements regarding emission inventories, reasonable
    further progress, and contingency measures, but ignored
    BACM and MSM. We also reject this argument. The EPA
    reasonably explained that those particular CAA requirements
    are procedural or otherwise applicable to all SIP submissions,
    see 42 U.S.C. §§ 7410(a), 7502(c), 7506(c), 7513a(c)(1), and
    the EPA reviews such measures whenever it reviews a
    proposed SIP.       By contrast, the BACM and MSM
    requirements are not applicable to all SIP submissions, and so
    the EPA reviews them only when the state is required to
    demonstrate compliance with these requirements.
    B
    We next turn to the petitioners’ argument that the EPA
    acted contrary to law by excluding 135 exceedances in the
    Maricopa Area from Arizona’s air quality monitoring data.
    Petitioners raise several arguments as to why the EPA
    erred in concluding that the dust sources causing the 135
    exceedances were from anthropogenic sources that were
    “reasonably well-controlled,” and therefore were excludable
    as exceptional events. See 40 C.F.R. § 50.14(b)(1). The
    BAHR V. U.S. EPA                       27
    petitioners begin by pointing to the statement in the Interim
    Guidance that “[g]enerally, the EPA will consider windblown
    dust BACM to constitute reasonable controls if these
    measures have been reviewed and approved in the context of
    a SIP revision for the emission source area within the past
    three years.” Interim Guidance at 15. The EPA’s decision
    was inconsistent with this guidance, petitioners argue, for two
    reasons. First, Arizona’s dust control measures for the
    Maricopa Area had not been approved since 2002, well over
    three years before the 2014 Final Rule. Second, agricultural
    emissions are among the sources of windblown dust in the
    Maricopa Area, and the EPA’s 2010 Proposed Rule had
    proposed to disapprove of Arizona’s agricultural control
    measures because they were not BACM. Moreover,
    petitioners argue, the EPA failed to offer a reasonable
    explanation for its departure from its guidance.
    We disagree; the EPA’s 2014 Final Rule did not conflict
    with the Interim Guidance. First, nothing in the Interim
    Guidance indicates that EPA must find that control measures
    for windblown dust have been reviewed and approved as
    BACM within the past three years in order for the dust to be
    deemed reasonably well-controlled. Rather, the Interim
    Guidance gives the EPA flexibility to consider a wide range
    of issues, and emphasizes that a prior BACM determination
    “may be a reference point, but not the sole means, by which
    the EPA assess the reasonableness of controls.” Interim
    Guidance at 15. The EPA’s interpretation is therefore
    consistent with the Interim Guidance and is a reasonable
    interpretation of the Exceptional Events Rule, to which we
    owe deference. 
    Auer, 519 U.S. at 461
    .
    Second, the EPA provided a reasonable explanation as to
    why the Maricopa Area had reasonable controls for
    28                    BAHR V. U.S. EPA
    windblown dust even though the 2010 Proposed Rule had
    proposed to disapprove of Arizona’s agricultural control
    measures. The EPA’s 2002 Final Rule determined that the
    2000 SIP contained the best available control measures for
    the highest emitters of PM-10 (including unpaved roads and
    alleys, construction, paved road dust, and non-agricultural
    windblown dust). 79 Fed. Reg. at 33111–13. The 2014 Final
    Rule then explained that it was still appropriate to rely on that
    determination because neither the highest emitters of PM-10
    nor the techniques for controlling fugitive dust had changed
    significantly since 2002. 
    Id. at 33112.
    Moreover, Arizona
    made its dust control rules even more stringent in the years
    following its 2000 SIP, further bolstering the conclusion that
    the controls remained reasonable. 
    Id. Although the
    EPA had
    proposed to disapprove of the agricultural controls as not
    meeting the BACM standard in 2010, data showed that
    agricultural sources were only a minimal contributor to the
    Maricopa Area’s overall level of PM-10 emissions. 
    Id. Accordingly, the
    EPA’s judgment was that the control
    measures in the 2000 SIP ensured that anthropogenic
    windblown dust was reasonably controlled for purposes of the
    Exceptional Events Rule.
    “[W]e generally must be at [our] most deferential when
    reviewing scientific judgments and technical analyses within
    the agency’s expertise.” Lands Council v. McNair, 
    629 F.3d 1070
    , 1074 (9th Cir. 2010) (second alteration in original)
    (internal quotation marks omitted). Here, the EPA considered
    the relevant factors and articulated a rational connection
    between the facts found and the choice made. As a general
    rule, a determination that particular control measures are
    reasonable relies on technical considerations that are
    BAHR V. U.S. EPA                            29
    “properly left to the informed discretion of” the EPA.
    
    Kleppe, 427 U.S. at 412
    . We defer to its conclusion here.10
    C
    Petitioners also claim that the EPA’s approval of
    Arizona’s 135 exceedances as exceptional events violated the
    Interim Guidance because the EPA failed to adequately
    address the controls in upwind areas outside the Maricopa
    Area. To qualify as an exceptional event under the
    Exceptional Events Rule, an exceedance must be “caused by
    human activity that is unlikely to recur at a particular location
    or a natural event.” 40 C.F.R. §§ 50.1(j), 50.14. The
    Treatment of Data Guidance states that high wind events will
    be considered “natural” when “(1) the dust originated from
    nonanthropogenic sources, or (2) the dust originated from
    anthropogenic sources within the State, that are determined
    to have been reasonably well-controlled at the time that the
    event occurred, or from anthropogenic sources outside the
    State.” 72 Fed. Reg. at 13576. To assist the EPA in
    determining compliance with this requirement, the Interim
    Guidance requires a state to provide “a brief description” of
    “all contributing emission sources in upwind areas and
    provide evidence that those sources were reasonably
    controlled, whether anthropogenic or natural.” Interim
    Guidance at 42.
    Petitioners argue that Arizona’s submissions were
    inadequate because Arizona did not identify all contributing
    emission sources outside the Maricopa Area, failed to
    10
    Because we conclude that the EPA did not depart from its Interim
    Guidance, we do not reach the petitioners’ argument that the EPA failed
    to provide a reasoned explanation for departing from its guidance.
    30                   BAHR V. U.S. EPA
    distinguish between natural and anthropogenic sources, and
    failed to submit evidence that Pinal County had reasonable
    controls in place.
    We again disagree. Under the Treatment of Data
    Guidance, a high wind event may meet the criteria of the
    Exceptional Events Rule when the dust originated from
    nonanthropogenic sources, or from anthropogenic sources
    that are reasonably well-controlled at the time that the event
    occurred. 72 Fed. Reg. at 13576–77. Arizona explained that
    the high wind events causing the 135 exceedances stemmed
    from monsoonal dust storms. Because “outflow from
    thunderstorms can carry dust over vast distances
    encompassing many source areas,” Arizona could not clearly
    distinguish between nonanthropogenic and anthropogenic
    sources of dust. Nevertheless, Arizona adequately provided
    a “brief description” of contributing dust sources outside the
    Maricopa Area and demonstrated that reasonable controls
    were in place for any anthropogenic sources of dust. For
    instance, in describing exceedances that occurred during the
    August 11, 2012, event, Arizona provided a “conceptual
    model” identifying a nonanthropogenic source, the
    “undeveloped lands south of Maricopa County,” as being the
    primary contributing source areas in Pima and Pinal Counties.
    Arizona also provided evidence that any anthropogenic
    sources of dust in those areas were reasonably controlled,
    pointing to two Pinal County rules applicable to fugitive dust
    and construction sites. Arizona compiled similar submissions
    for each of its exceptional event submittals. Arizona’s
    submissions provided enough detail for the EPA to
    reasonably conclude that the dust originated either from
    “nonanthropogenic sources” or “anthropogenic sources” that
    were “reasonably well-controlled.” Interim Guidance at 42.
    Accordingly, the EPA’s conclusion that Arizona’s description
    BAHR V. U.S. EPA                       31
    of the upwind sources was adequate was not an abuse of
    discretion.
    Petitioners also argue that the EPA ignored the Interim
    Guidance and thus abused its discretion in concluding that the
    anthropogenic dust sources in the areas of Pinal County
    outside of the Maricopa Area were reasonably controlled.
    The Interim Guidance states that “[f]or the anthropogenic
    sources to be considered to be reasonably controlled, the EPA
    anticipates that it is reasonable for an air agency to have the
    controls required for an area’s attainment status.” Interim
    Guidance at 15. “[T]he EPA does not expect areas classified
    as attainment, unclassifiable, or maintenance for a NAAQS
    to have the same level of controls as areas that are
    nonattainment for the same NAAQS.” 
    Id. In other
    words, an
    area that is in attainment should have the control measures
    appropriate for an attainment area, while an area that has been
    designated a serious nonattainment area should have the
    control measures appropriate for that level of classification.
    
    Id. Where “an
    area has been recently designated to
    nonattainment but has not yet been required to implement
    controls, the EPA will expect the level of controls that is
    appropriate for the planning stage.” 
    Id. Under the
    Interim Guidance, the EPA did not abuse its
    discretion in concluding that the anthropogenic dust sources
    in the areas of Pinal County outside of the Maricopa Area
    were reasonably well-controlled. The EPA provided a
    reasoned explanation as to why it deemed the Pinal County
    area to have the controls required for that area’s attainment
    status. The 135 exceedances approved by the EPA all
    occurred between 2010 and 2012. 79 Fed. Reg. at 33111.
    From January 2011 to June 2012, Pinal County (excluding the
    portion within the Maricopa Area) was an attainment area,
    32                   BAHR V. U.S. EPA
    and had adopted two rules addressing fugitive dust emissions
    that were appropriate for this status. Although Pinal County
    was redesignated a nonattainment area in July 2012, it was
    not required to submit a SIP until 18 months after
    redesignation, leaving it in the planning stage for the
    remainder of 2012. See Designation of Areas for Air Quality
    Planning Purposes; State of Arizona; Pinal County; PM10,
    77 Fed. Reg. 32024, 32030 (May 31, 2012). Because Pinal
    County had not yet been required to implement controls, the
    EPA reasonably concluded that Pinal County’s fugitive dust
    rules were appropriate for the planning stage.
    V
    Finally, we turn to petitioners’ argument that the EPA
    erred in approving the contingency measures in the Five
    Percent Plan because those measures had already been
    implemented. As noted above, four of five contingency
    measures in the Five Percent Plan were permanent changes to
    infrastructure that had been completed by 2012 (paving and
    stabilizing existing public dirt roads and alleys, paving and
    stabilizing unpaved shoulders, repaving or overlaying paved
    roads with rubberized asphalt, and lowering speed limits on
    dirt roads and alleys). The fifth contingency measure
    involved the purchase of PM-10 certified sweepers and
    sweeping of freeways, though the purchase occurred in 2009
    and Arizona had procured contracts for sweeping services by
    2010. The CAA provides that a nonattainment SIP:
    [S]hall provide for the implementation of
    specific measures to be undertaken if the area
    fails to make reasonable further progress, or
    to attain the national primary ambient air
    quality standard by the attainment date
    BAHR V. U.S. EPA                         33
    applicable under this part. Such measures
    shall be included in the plan revision as
    contingency measures to take effect in any
    such case without further action by the State
    or the Administrator.
    42 U.S.C. § 7502(c)(9). In its 2014 Final Rule, the EPA
    explained its interpretation of this requirement. While
    “[c]ontingency measures must provide for additional
    emission reductions that are not relied on for RFP [reasonable
    further progress] or attainment and that are not included in
    the attainment demonstration,” the EPA concluded that
    “[n]othing in the statute precludes a state from implementing
    such measures before they are triggered.” 79 Fed. Reg. at
    33114.
    Although we defer to the EPA’s interpretation of the
    CAA contained in a final rule approving a SIP if that
    interpretation involves the reasonable interpretation of
    ambiguous statutory terms, see supra at 22, we cannot defer
    to the EPA’s interpretation of § 7502(c)(9) here. Where
    Congress has “directly spoken to the precise question at issue
    . . . that is the end of the matter; for the court, as well as the
    agency, must give effect to the unambiguously expressed
    intent of Congress.” 
    Chevron, 467 U.S. at 842
    –43. The
    statutory language in § 7502(c)(9) is clear: it requires the SIP
    to provide for the implementation of measures “to be
    undertaken” in the future, triggered by the state’s failure “to
    make reasonable further progress” or to attain the NAAQS.
    These measures are included in the SIP as “contingency
    measures” and are “to take effect” automatically in the future.
    Although the statute does not define the word “contingency,”
    the meaning of the term is not ambiguous. According to the
    dictionary definition, it means “a possible future event or
    34                    BAHR V. U.S. EPA
    condition or an unforeseen occurrence that may necessitate
    special measures.” Webster’s Third New International
    Dictionary (2002). Because Congress was clear that
    “contingency measures” are control measures that will be
    implemented in the future, and the statutory language is not
    susceptible to multiple interpretations, we must give effect to
    its plain meaning. 
    Chevron, 467 U.S. at 842
    –43.
    In arguing that its interpretation of § 7502(c) is entitled to
    deference despite the clear language of the statute, the EPA
    relies on the Fifth Circuit’s decision in Louisiana Envtl.
    Action Network v. EPA, 
    382 F.3d 575
    , 580 (5th Cir. 2004).
    In Louisiana Envtl. Action Network, the petitioners
    challenged the EPA’s 2002 approval of Louisiana’s SIP
    because the contingency measure in the SIP (a compressor
    station’s permanent reduction of its emissions) had been
    implemented in 1998, and therefore was not a measure “to be
    undertaken” or “to take effect” in the future, as § 7502(c)(9)
    requires. 
    Id. at 582.
    The Fifth Circuit first acknowledged
    that “a plain reading of the terms ‘to take effect’ and ‘to be
    undertaken’ imply a prospective, forward looking
    orientation” that would “preclude the use of past reductions
    which have already failed to achieve attainment.” 
    Id. at 583.
    Nevertheless, the Fifth Circuit held that § 7502(c)(9) was
    ambiguous because it “neither affirms nor prohibits
    continuing emissions reductions—measures which originate
    prior to the SIP failing, but whose effects continue to
    manifest an effect after the plan fails—from being utilized as
    a contingency measure.” 
    Id. (emphasis omitted).
    Having
    found this “ambiguity,” it deferred to the EPA’s interpretation
    that “contingency measures” could include measures that had
    already been implemented by the state.
    BAHR V. U.S. EPA                        35
    We cannot agree with the Fifth Circuit’s interpretative
    approach. Having determined that the “plain reading of the
    terms” indicates a forward looking approach, the Fifth Circuit
    was bound by Chevron to give effect to the plain meaning of
    the statute. We disagree that the lack of any discussion in
    § 7502(c)(9) regarding treatment of continuing emissions
    reductions makes the statute ambiguous. Rather, unless such
    continuing emissions reductions are “to be undertaken” in the
    event of a contingency, they do not fit the definition of
    “contingency measures” provided in § 7502(c)(9). We also
    disagree with the dissent’s contention that previously
    implemented control measures that provide continuing
    emissions reductions “take effect” and are “undertaken” both
    “at the time they are first implemented but also thereafter.”
    Dissent at 38. This is a misreading of the statute, which
    defines contingency measures as measures “to be undertaken”
    or “to take effect” if a future event occurs, namely “if the area
    fails to make reasonable further progress, or to attain the
    [NAAQS].” 42 U.S.C. § 7502(c)(9) (emphases added).
    Control measures that have already been implemented are not
    measures “to be undertaken” or “to take effect” in the future,
    and the statute cannot reasonably be so interpreted.
    The EPA argues that its interpretation is consistent with
    the CAA’s policy goals, because permitting early
    implementation of contingency measures is consistent with
    the overall policy of the CAA to reduce particulate emissions
    and protect public health. La. Envtl. Action 
    Network, 382 F.3d at 583
    . The Fifth Circuit likewise relied on these
    policy considerations, stating that allowing states to
    implement measures before the contingency occurs was
    consistent with the CAA’s purpose of creating incentives for
    states to reach NAAQS compliance earlier and more
    efficiently. 
    Id. at 583–84.
    The dissent agrees, adopting the
    36                          BAHR V. U.S. EPA
    Fifth Circuit’s policy analysis.11 Dissent at 39–40. Even if
    we agreed that the EPA’s policy considerations are
    compelling, such considerations cannot override the plain
    language of the statute. We therefore cannot give them
    controlling weight here.
    Because the “contingency measures” in Arizona’s SIP
    were not “specific measures to be undertaken if the area fails
    to make reasonable further progress, or to attain the national
    primary ambient air quality standard by the attainment date
    applicable under this part,” the EPA’s approval of this part of
    the Five Percent Plan was contrary to the CAA. Accordingly,
    we remand to the EPA for further consideration of this
    portion of the SIP but otherwise deny the petition.12
    PETITION GRANTED IN PART AND DENIED IN
    PART.
    11
    In addition to relying on the Fifth Circuit’s policy arguments, the
    dissent argues that precluding the use of previously implemented controls
    as contingency measures “imposes an additional and unnecessary burden
    upon states where the failure to attain the NAAQS also triggers a bump up
    of an area’s classification under the Act” because states will not be able
    to “focus their efforts on implementing the newly imposed requirements.”
    Dissent at 40. This is incorrect: because contingency measures
    automatically take effect when the contingency occurs, “without further
    action by the State,” 42 U.S.C. § 7502(c)(9), the implementation of
    contingency measures cannot distract a state from meeting the other CAA
    requirements.
    12
    Each party is to bear its own costs on appeal.
    BAHR V. U.S. EPA                       37
    CLIFTON, Circuit Judge, concurring in part and dissenting
    in part:
    I fully concur in sections I–IV of the majority opinion. I
    disagree, however, with the majority’s conclusion in section
    V that EPA’s approval of the contingency measures in
    Arizona’s SIP is contrary to the clear language of the CAA.
    In my view, the scope of the CAA’s contingency measures
    requirement is ambiguous and EPA’s reasonable
    interpretation of that requirement is entitled to deference.
    Like the majority, I begin by analyzing the text of the
    relevant statutory provision, 42 U.S.C. § 7502(c)(9). That
    section of the CAA requires state nonattainment plans to
    include contingency measures “to be undertaken” and “to
    take effect” in the event that an area “fails to make reasonable
    further progress, or to attain” the NAAQS by the applicable
    attainment date. 
    Id. Although I
    agree with the majority that
    this language most often refers to measures that are to be
    implemented in the future, in the event that the other
    measures included in a state’s SIP are not sufficient to meet
    CAA requirements, I am not persuaded that the provision’s
    text forecloses the interpretation advanced by EPA and
    applied in this case.
    The language of the statute prohibits states from labeling
    as “contingency measures” the same proposed reductions
    relied upon to achieve NAAQS compliance. See La. Envtl.
    Action Network v. EPA, 
    382 F.3d 575
    , 583 (5th Cir. 2004)
    (“Such a prospective reading of the text would seemingly
    preclude the use of past reductions which have already failed
    to achieve attainment.”). It requires states to identify
    additional measures that must be put into effect without
    further action by the state or EPA if reasonable progress is
    38                    BAHR V. U.S. EPA
    not made or the air quality standard is not met by the
    attainment date. Those additional measures are what the
    statute describes as “contingency measures.”
    Arizona’s SIP identified additional measures that were
    not relied upon to obtain the anticipated compliance. The
    practical issue before us in this case is whether Arizona was
    prohibited from putting those additional measures into effect
    in advance. The majority opinion concludes that it was, that
    the state’s contingency measures must be left undone, sitting
    on the sidelines in reserve. I do not believe that the language
    or intent of the statute requires that conclusion.
    The early implementation of infrastructure improvements
    that are expected to result in additional and continuing
    emissions reductions is consistent with the language of
    § 7502(c)(9). These early-implemented contingency measures
    result in a net reduction in emissions following their
    implementation. They “take effect” and are “undertaken” not
    only at the time they are first implemented but also thereafter,
    including at the time they might formally be required due to
    nonattainment. So long as these reductions are not relied upon
    to meet other CAA requirements, they function as a backup
    plan, reducing the likelihood that the state will fail to attain
    the NAAQS even in the “contingency” that the measures
    explicitly included in the SIP for that purpose are not enough.
    The majority responds by asserting that the statute
    “defines contingency measures as measures ‘to be
    undertaken’ or ‘to take effect’ if a future event occurs,
    namely ‘if the area fails to make reasonable further progress,
    or to attain the [NAAQS].’” Majority opinion at 35 (emphasis
    in original). But this language fits just as well with EPA’s
    interpretation as it does with the view of the majority. In both
    BAHR V. U.S. EPA                       39
    scenarios, the contingency measures must be in effect at the
    time an area fails to achieve the goals outlined in the SIP.
    What is at issue here is whether states are prohibited from
    also implementing the measures before that “future event
    occurs.” The language quoted by the majority contains no
    such prohibition and it is not our role to read one into the
    statute.
    EPA’s interpretation also comports well with the purpose
    of the CAA. “In determining whether Congress has
    specifically addressed the question at issue, a reviewing court
    should not confine itself to examining a particular statutory
    provision in isolation. . . . It is a ‘fundamental canon of
    statutory construction that the words of a statute must be read
    in their context and with a view to their place in the overall
    statutory scheme.’” FDA v. Brown & Williamson Tobacco
    Corp., 
    529 U.S. 120
    , 132–33 (2000) (quoting Davis v. Mich.
    Dept. of Treasury, 
    489 U.S. 803
    , 809 (1989)).
    Allowing states to implement contingency measures
    before they are triggered makes sense in light of that same
    provision’s requirement that such measures “take effect . . .
    without further action by the State or the Administrator.” That
    requirement, read in context with the Act’s mandate that
    states implement emission-control measures “as expeditiously
    as practicable,” 
    id. § 7502(c)(1),
    evinces a clear congressional
    preference that contingency measures operate to reduce the
    emission of harmful pollutants in as efficient and timely a
    manner as possible. Taking this statutory purpose into
    account, “it seems illogical to penalize nonattainment areas
    that are taking extra steps, such as implementing contingency
    measures prior to a deadline” as a cushion to ensure NAAQS
    compliance and prevent the need for the contingency
    measures requirement to be triggered in the first place. La.
    40                        BAHR V. U.S. EPA
    Envtl. Action 
    Network, 382 F.3d at 584
    . It does not benefit
    ordinary citizens to read the CAA to incentivize states to hold
    off from purchasing new street sweepers or repaving their
    roads until the contingency measures requirement is
    triggered.
    The majority’s interpretation also imposes an additional
    and unnecessary burden upon states in circumstances where
    the failure to attain the NAAQS also triggers a bump up of an
    area’s classification under the Act. For example, the failure
    of a moderate nonattainment area to achieve NAAQS
    compliance by the applicable deadline triggers both
    § 7502(c)(9)’s contingency measures requirement and the
    additional requirements imposed upon serious nonattainment
    areas. 42 U.S.C. § 7513(b)(2). The early implementation of
    contingency measures allows states in this situation to focus
    their efforts on implementing the newly imposed
    requirements while the contingency measures continue to
    operate in the interim. See La. Envtl. Action 
    Network, 382 F.3d at 583
    .1
    1
    The majority argues that because contingency measures must take
    effect “without further action by the State” or EPA, 42 U.S.C.
    § 7502(c)(9), they “cannot distract a state from meeting the other CAA
    requirements.” Majority opinion at 36 n. 11. However, EPA has
    interpreted this language to require only “that no further rulemaking
    activities by the State or EPA would be needed to implement the
    contingency measures.” Greenbaum v. EPA, 
    370 F.3d 527
    , 541 (6th Cir.
    2004) (quoting State Implementation Plans; General Preamble for the
    Implementation of Title I of the Clean Air Act Amendments of 1990,
    57 Fed. Reg. 13498, 13512 (Apr. 16, 1992)). Thus, under the majority’s
    interpretation, states would still be required to perform the actual business
    of implementing the identified contingency measures at the same time
    they address other requirements imposed by a failure to attain the
    NAAQS.
    BAHR V. U.S. EPA                       41
    I recognize that what is lost by EPA’s interpretation of the
    statute is the advance identification of “still more” measures
    aimed at improving air quality that can be newly and
    additionally implemented in the event of nonattainment. If
    Arizona’s SIP does not reach its goal, then reliance upon
    contingency measures that have already been put into effect
    will not further reduce airborne particulate matter, and more
    will have to be done at that point. But EPA applied its
    expertise and exercised its judgment in concluding that the
    goal was likely to be reached by the measures proposed in the
    SIP, without regard to the additional contingency measures.
    By letting Arizona identify actions that have already been
    implemented as contingency measures, EPA has obtained a
    cushion. It is not an unreasonable judgment for EPA to
    conclude that implementing the cushion right away is more
    valuable than advance identification of what else might be
    done, if necessary.
    For these reasons, I would give Chevron deference to the
    EPA’s interpretation of § 7502(c)(9). I respectfully dissent
    from the majority’s conclusion to the contrary.
    

Document Info

Docket Number: 14-72327

Citation Numbers: 836 F.3d 1218

Filed Date: 9/12/2016

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (18)

BCCA Appeal Group v. United States Environmental Protection ... , 355 F.3d 817 ( 2003 )

LA Env Action Ntwrk v. EPA , 382 F.3d 575 ( 2004 )

Lands Council v. McNair , 629 F.3d 1070 ( 2010 )

Ranchers Cattlemen Action Legal Fund United Stock-Growers ... , 499 F.3d 1108 ( 2007 )

martha-vigil-andy-blackledge-and-robin-silver-v-michael-o-leavitt , 381 F.3d 826 ( 2004 )

robert-greenbaum-sierra-club-intervenor-v-united-states-environmental , 370 F.3d 527 ( 2004 )

United States v. Mead Corp. , 121 S. Ct. 2164 ( 2001 )

Latino Issues Forum v. United States Environmental ... , 558 F.3d 936 ( 2009 )

Sierra Club v. United States Environmental Protection Agency , 671 F.3d 955 ( 2012 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... , 103 S. Ct. 2856 ( 1983 )

The Wilderness Society Alaska Center for the Environment v. ... , 353 F.3d 1051 ( 2003 )

Barnes v. US Dept. of Transp. , 655 F.3d 1124 ( 2011 )

Kleppe v. Sierra Club , 96 S. Ct. 2718 ( 1976 )

Davis v. Michigan Department of the Treasury , 109 S. Ct. 1500 ( 1989 )

Auer v. Robbins , 117 S. Ct. 905 ( 1997 )

Food & Drug Administration v. Brown & Williamson Tobacco ... , 120 S. Ct. 1291 ( 2000 )

Alaska Department of Environmental Conservation v. ... , 124 S. Ct. 983 ( 2004 )

Chevron U. S. A. Inc. v. Natural Resources Defense Council, ... , 104 S. Ct. 2778 ( 1984 )

View All Authorities »