Bayer Cropscience Ag v. Dow Agrosciences LLC , 680 F. App'x 985 ( 2017 )


Menu:
  •        NOTE: This disposition is nonprecedential.
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    BAYER CROPSCIENCE AG, BAYER
    CROPSCIENCE NV,
    Plaintiffs-Appellees
    v.
    DOW AGROSCIENCES LLC, MYCOGEN PLANT
    SCIENCE, INC., AGRIGENETICS, INC., DBA
    MYCOGEN SEEDS, LLC, PHYTOGEN SEED
    COMPANY, LLC,
    Defendants-Appellants
    ______________________
    2016-1530, 2016-1623
    ______________________
    Appeals from the United States District Court for the
    Eastern District of Virginia in No. 2:12-cv-00047-RAJ-
    RJK, Judge Raymond Alvin Jackson.
    ______________________
    Decided: March 1, 2017
    ______________________
    CHRISTOPHER JAMES GASPAR, Milbank, Tweed, Hadley
    & McCloy LLP, New York, NY, argued for plaintiffs-
    appellees. Also represented by RYAN HAGGLUND; ROBERT
    J. KOCH, MICHAEL D. NOLAN, STEPHANIE R. AMOROSO,
    EDWARD JOHN MAYLE, Washington, DC.
    2           BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    DAVID JASON LENDER, Weil, Gotshal & Manges LLP,
    New York, NY, argued for defendants-appellants. Also
    represented    by   ELIZABETH    WEISWASSER,     DAVID
    FITZMAURICE, ADAM BANKS; ALEX V. CHACHKES, PETER A.
    BICKS, ROBERT L. SILLS, JAMES STENGEL, Orrick, Herring-
    ton & Sutcliffe LLP, New York, NY; MARK S. DAVIES,
    KATHERINE M. KOPP, JEFFREY M. PROKOP, MELANIE L.
    BOSTWICK, Washington, DC; ELIZABETH MOULTON, Menlo
    Park, CA.
    LLOYD LEE DAVIS, III, Andrews Kurth Kenyon LLP,
    Houston, TX, for amicus curiae Jeff C. Dodd.
    ______________________
    Before MOORE, TARANTO, and CHEN, Circuit Judges.
    TARANTO, Circuit Judge.
    This case involves an international arbitration tribu-
    nal’s decision on a contract claim, under French law, and
    patent-infringement claims, under U.S. law, in a dispute
    between Bayer CropScience NV and Bayer CropScience
    AG (sometimes collectively, Bayer), on one side, and Dow
    Agrosciences LLC, Mycogen Plant Science, Inc., Agri-
    genetics, Inc., and Phytogen Seed Co. (collectively, Dow),
    on the other. Bayer initially sued Dow for patent in-
    fringement, but the district court stayed the action pend-
    ing arbitration. The arbitral tribunal awarded Bayer
    approximately $455 million, including damages for breach
    of contract and patent infringement, and set a rate for
    post-award interest. The district court, in the patent-
    infringement case, confirmed the arbitral award. The
    court rejected Dow’s arguments against the award and
    also denied Dow’s motion to clarify that interest from the
    date of the district court’s judgment would accrue at the
    statutory rate for post-judgment interest rather than the
    tribunal’s higher post-award rate. Dow appeals.
    BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC            3
    We conclude that the district court correctly con-
    firmed the award, but abused its discretion regarding
    post-judgment interest. We modify the judgment to state
    that interest from the date of the district court’s judgment
    accrues at the federal statutory rate. We affirm the
    judgment as modified.
    I
    A
    Bayer CropScience NV, a successor of Plant Genetic
    Systems NV, owns or co-owns the Leemans patent family,
    which includes U.S. Patent Nos. 5,561,236, 5,646,024,
    5,648,477, 7,112,665, and RE44,962. The patents describe
    and claim various technologies related to the pat gene,
    which confers resistance to the herbicide glufosinate. The
    Leemans patents issued from continuations of U.S. Patent
    Application No. 07/131,140 and have similar specifica-
    tions.
    Bayer CropScience AG, a successor of Hoechst AG,
    owns the Strauch patent family, including U.S. Patent
    Nos. 5,273,894 and 5,276,268 (Strauch ’268). Although
    not asserted by Bayer CropScience AG, the Strauch
    patents are indirectly at issue, as the basis for Dow’s
    double-patenting challenge to the Leemans patents.
    Bayer CropScience AG and Bayer CropScience NV are
    wholly owned subsidiaries of non-party Bayer AG.
    Dow AgroSciences LLC produces the Enlist E3, Enlist
    E3+IR, Enlist Soybean, Enlist Cotton, Widestrike, and
    Widestrike 3 products through its subsidiaries, Mycogen
    Plant Science, Inc., Agrigenetics, Inc., and Phytogen Seed
    Co. Each of those products contains the pat gene. The
    Enlist E3 products also contain a molecular stack of the
    aad-12 and dmmg genes. Like the pat gene, the aad-12
    and dmmg genes confer resistances to herbicides.
    In June 1992, Hoechst AG and Lubrizol Genetics, Inc.,
    Dow’s predecessor, agreed to cross-license certain technol-
    4           BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    ogies to which they had rights. That agreement (the 1992
    Agreement) granted Lubrizol licenses to certain patents,
    including the Strauch and the Leemans patents. At the
    time of the agreement, Hoechst owned the Strauch pa-
    tents and exclusively licensed the Leemans patents from
    Plant Genetic Systems NV.
    Article 4 of the 1992 Agreement restricts the parties’
    use of the licensed technology:
    No right or license is hereby granted, to     either
    party, either expressly or by implication,   to use
    any other proprietary technology owned        by or
    available to the other in connection with    the li-
    censes granted hereunder.
    Both parties are entitled to grant sublicences or
    distribution rights for their Transformants.
    Hoechst is furthermore entitled to grant subli-
    cences for gene promoter constructs containing a
    Promoter in conjunction with any gene of which
    Hoechst can dispose.
    J.A. 886, 4147. Article 12 states that the agreement is to
    be governed by and construed in accordance with French
    law and that all controversies or disputes are to be “decid-
    ed by arbitration in accordance with the Rules of Concilia-
    tion and Arbitration of the International Chamber of
    Commerce.” J.A. 889, 4150.
    Between 2007 and 2008, Dow and non-party MS
    Technologies, LLC entered into a series of agreements
    regarding the pat and dmmg genes. In September 2007,
    MS Tech granted Dow access to the dmmg gene, to which
    MS Tech had a license under a 2004 agreement with
    Bayer CropScience AG. In April 2008, Dow transferred
    soybean seed transformants containing the aad-12, pat,
    and dmmg genes to MS-Tech. Dow and MS Tech’s collab-
    oration resulted in the creation of the Enlist E3 products.
    BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC             5
    In November 2007, Bayer CropScience AG and MS
    Tech entered into a new agreement, which involved the
    dmmg gene and which transferred ownership of Event
    FG72 to MS Tech. The agreement required MS Tech to
    pay Bayer CropScience AG a percentage—in this case,
    determined to be 50%—of the net trait revenues associat-
    ed with Event FG72 until 2030.
    B
    In January 2012, Bayer CropScience AG terminated
    the 1992 Agreement after accusing Dow of materially
    breaching Article 4. The same month, Bayer CropScience
    AG and Bayer CropScience NV sued Dow in the Eastern
    District of Virginia for infringement of the ’236, ’024, ’477,
    and ’665 patents. Dow moved to dismiss or stay the
    action based on the agreement’s arbitration clause. The
    district court stayed the action. See 
    9 U.S.C. § 3
    .
    In September 2013, Bayer CropScience NV filed a re-
    issue application for the ’665 patent. See 
    35 U.S.C. § 251
    .
    In its application, Bayer CropScience NV stated that
    reissuance was appropriate in view of the Supreme
    Court’s decision in Association for Molecular Pathology v.
    Myriad Genetics, Inc., 
    133 S. Ct. 2107
     (2013). The ’665
    patent reissued as the RE’962 patent, which expires in
    2023. The other patents at issue expired no later than
    July 2014.
    Between November 2014 and August 2015, Dow filed
    six requests for inter partes reexamination of the ’236,
    ’024, ’447, and RE’962 patents. See Ex Parte Leemans,
    Control Nos. 90/013,394, 90/013,449, 90/013,452,
    90/013,453, 90/013,515, 90/013,563. Dow alleged that
    claims 8, 9, 12, 15, 18, and 19 of the ’236 patent; 1, 15,
    and 16 of the ’024 patent; 1, 2, 15–17, and 19 of the ’477
    patent; and 1 and 2 of the RE’962 patent were invalid for
    obviousness-type double patenting over Strauch ’268 and
    ’894 and 
    U.S. Patent No. 5,633,434
    . See Control Nos. -
    394, -449, -452, -453, -515. Dow also alleged that claim 2
    6           BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    of the RE’962 patent would have been obvious over cer-
    tain prior-art references. Control No. -563. At the exam-
    iner level, the Office has issued final rejections in four
    proceedings, Control Nos. -394, -449, -515, -563, and non-
    final rejections in the others, Control Nos. -452, -453.
    Those proceedings remain pending in the Office and do
    not alter our resolution of this appeal. See 
    35 U.S.C. § 294
    ; Fresenius USA, Inc. v. Baxter Int’l, Inc., 
    721 F.3d 1330
     (Fed. Cir. 2013).
    In October 2015, an arbitral tribunal entered an
    award, finding, in relevant part, that (1) Dow breached
    the 1992 Agreement by effectively sublicensing the pat
    gene to MS Tech; (2) Dow infringed various claims of the
    Leemans patents by its creation and other activities
    involving the identified Enlist and Widestrike product—
    specifically, claims 8, 9, 12, and 15 of the ’236 patent;
    claims 15 and 16 of the ’024 patent; claims 15, 16, and 19
    of the ’447 patent; and claim 1 of the RE’962 patent; (3)
    the asserted claims of the ’024, ’236, ’447, ’665, and
    RE’962 patents were not invalid for inadequate written
    description or lack of enablement; and (4) the ’236, ’024,
    ’447, and RE’962 patents were not invalid for obviousness-
    type double patenting over Strauch ’268. The tribunal
    awarded Bayer $455,459,187 in damages, including
    $374,731,000 in lost-opportunity damages under French
    law for breach of contract and $67,837,000 in reasonable-
    royalty damages under U.S. law for patent infringement.
    The tribunal also awarded Bayer pre-award interest
    using a rate of 8% and declared that the same rate would
    apply to “post-award interest.” J.A. 560, 563. Arbitrator
    George Berman dissented in part, disagreeing with the
    tribunal’s conclusion of no double patenting.
    Bayer moved the district court to confirm the arbitral
    award. See 
    9 U.S.C. § 207
    . Dow cross-moved to vacate
    the award. The court confirmed the award. The court
    also denied Dow’s motion to amend the judgment to
    clarify that any interest for a period after the district
    BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC             7
    court’s judgment would accrue at the rate specified by 
    28 U.S.C. § 1961
    (a), not at the tribunal’s 8% rate for “post-
    award interest.” Dow appeals. We conclude that we have
    jurisdiction, and we affirm the judgment as modified.
    II
    We have jurisdiction under 
    28 U.S.C. § 1295
    (a)(1),
    which gives us jurisdiction over any “appeal from a final
    decision of a district court . . . in any civil action arising
    under, or in any civil action in which a party has asserted
    a compulsory counterclaim arising under, any Act of
    Congress relating to patents.” An action arises under the
    patent laws if the complaint includes a claim asserting a
    cause of action created by federal patent law. Christian-
    son v. Colt Indus. Operating Corp., 
    486 U.S. 800
    , 808–09
    (1988). It also arises under the patent laws in certain
    circumstances where there is no federal cause of action.
    In Christianson, the Court stated that a state-law cause of
    action arises under federal patent law if “the plaintiff’s
    right to relief necessarily depends on resolution of a
    substantial question of federal patent law, in that patent
    law is a necessary element of one of the well-pleaded
    claims.” 
    Id.
     More recently, in Gunn v. Minton, 
    133 S. Ct. 1059
     (2013), which concerned patent-law issues involved
    in a state-law malpractice claim, the Court explained that
    “federal jurisdiction over a state law claim will lie if a
    federal issue is: (1) necessarily raised, (2) actually disput-
    ed, (3) substantial, and (4) capable of resolution in federal
    court without disrupting the federal-state balance ap-
    proved by Congress.” 
    Id. at 1065
    ; see also Grable & Sons
    Metal Prods., Inc. v. Darue Eng’g & Mfg., 
    545 U.S. 308
    ,
    314 (2005). In 2011, before the present suit was filed,
    Congress amended § 1295(a)(1) to extend our jurisdiction
    to actions that involve compulsory counterclaims arising
    under the patent laws. 
    28 U.S.C. § 1295
    (a)(1); Leahy-
    Smith America Invents Act, Pub. L. No. 112–29, § 19(b),
    
    125 Stat. 284
    , 331–32 (2011). That amendment became
    effective with respect to any civil action filed before Sep-
    8           BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    tember 16, 2011. Leahy-Smith America Invents Act
    § 19(e), 125 Stat. at 333; Wawrzynski v. H.J. Heinz Co.,
    
    728 F.3d 1374
    , 1378 (Fed. Cir. 2013).
    In this case, Bayer’s complaint arises under the pa-
    tent laws. The complaint expressly alleges multiple
    counts of patent infringement. The district court stayed
    adjudication of those claims pending arbitration, but did
    not dismiss the case or the patent claims. After the
    tribunal entered its award, the court resolved the parties’
    post-award motions in the same action. Bayer cites, and
    we are aware of, no authority establishing that the tribu-
    nal’s adjudication of the patent-infringement claims
    altered the court’s basis for jurisdiction.
    The conclusion would not change even if one looked
    beyond the original complaint to the post-arbitral-award
    proceedings in the district court. When Dow turned to the
    court to challenge the arbitral award by way of a motion
    to vacate, it asserted patent law as a necessary basis for
    certain challenges to parts of the tribunal’s award. See
    Gunn, 
    133 S. Ct. at 1065
    . In particular, Dow argued that
    the Convention on the Recognition and Enforcement of
    Foreign Arbitral Awards (New York Convention), June
    10, 1958, 21 U.S.T. 2517, 330 U.N.T.S. 38, required the
    court to decide, among other issues, whether enforcement
    of the award would violate a host of patent-law require-
    ments and policies. See New York Convention art.
    V(2)(b). Those questions were not only “necessarily
    raised,” but also “substantial” and “disputed.” Gunn, 
    133 S. Ct. at 1065
    . Moreover, because French law governed
    the contract claim, there was no basis for concern that the
    federal court’s determination of the patent-law issues,
    within the strict limits of arbitral-award review, would
    “disrupt[] the federal-state balance.” 
    Id.
     Thus, whether
    viewed as a new claim or as a compulsory counterclaim to
    Bayer’s claim for confirmation of the arbitral award,
    Dow’s challenge comes within the Gunn standard.
    BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC             9
    Precedent reinforces the conclusion that we have ju-
    risdiction over this appeal. In Flex-Foot, Inc. v. CRP, Inc.,
    
    238 F.3d 1362
     (Fed. Cir. 2001), we exercised jurisdiction
    over a final district-court decision confirming an arbitral
    award for patent infringement. 
    Id. at 1364
    . Additionally,
    in Microchip Technology Inc. v. U.S. Philips Corp., 
    367 F.3d 1350
     (Fed. Cir. 2004), we held that we had jurisdic-
    tion under § 1292(a)(1) over interlocutory orders denying
    motions to compel arbitration. Id. at 1354–55. The Third
    and Eighth Circuits have reached the opposite conclusion
    regarding our jurisdiction over interlocutory appeals, but
    neither has questioned our jurisdiction over final appeals.
    Indus. Wire Prods., Inc. v. Costco Wholesale Corp., 
    576 F.3d 516
    , 518–20 (8th Cir. 2009); Medtronic AVE, Inc. v.
    Advanced Cardiovascular Sys., Inc., 
    247 F.3d 44
    , 51–53
    (3d Cir. 2001). To the contrary, the Third Circuit has
    concluded that we have jurisdiction in situations such as
    this. Medtronic AVE, 
    247 F.3d at 53
    .
    We are unaware of any instance in which the regional
    circuits have decided an appeal involving the confirmation
    or vacatur of an arbitral award for patent infringement.
    In DeRosa v. J.P. Walsh & J.L. Marmo Enterprises, Inc.,
    541 F. App’x 250 (4th Cir. 2013), and Rocket Jewelry Box,
    Inc. v. Noble Gift Packaging, Inc., 
    157 F.3d 174
     (2d Cir.
    1998), the parties excluded the patent-related issues from
    arbitration. DeRosa also involved only a counterclaim for
    patent infringement, which did not suffice to create
    jurisdiction in cases, like DeRosa, filed before September
    16, 2011. See Holmes Grp., Inc. v. Vornado Air Circula-
    tion Sys., Inc., 
    535 U.S. 826
     (2002); DeRosa v. J.P. Walsh
    & J.R. Marmo Enters., Inc., 471 F. App’x 902 (Fed. Cir.
    2012). Although Golden v. Lim, No. 2:15-cv-10795, 
    2016 WL 520302
     (E.D. Mich. Feb. 10, 2016), which is discussed
    in Bayer’s filings, might not have been distinguishable on
    the same grounds, the Sixth Circuit has since dismissed
    the appeal in that case. See Golden v. Lim, No. 16-1313
    (6th Cir. dismissed Apr. 14, 2016).
    10          BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    III
    On the merits, we follow the Supreme Court’s and rel-
    evant regional circuit’s law on issues not unique to patent
    law. Flex-Foot, Inc., 
    238 F.3d at
    1365–66. Nevertheless,
    we have been shown no reason to think that our conclu-
    sions would change under any other circuit’s law on
    matters not squarely controlled by Supreme Court prece-
    dent. We review the district court’s denial of the motion
    to vacate the arbitral award without deference and any
    underlying factual findings for clear error. Raymond
    James Fin. Servs., Inc. v. Bishop, 
    596 F.3d 183
    , 190 (4th
    Cir. 2010). We review the denial of the motion to amend
    the judgment for abuse of discretion. Wilkins v. Mont-
    gomery, 
    751 F.3d 214
    , 220 (4th Cir. 2014). A court neces-
    sarily abuses its discretion if it commits legal error.
    Highmark, Inc. v. Allcare Health Mgmt. Sys., Inc., 
    134 S. Ct. 1744
    , 1748 n.2 (2014). The award of post-judgment
    interest is a legal question, reviewed without deference.
    Hitachi Credit Am. Corp. v. Signet Bank, 
    166 F.3d 614
    ,
    632–33 (4th Cir. 1999). To the extent that the parties
    raise issues unique to patent law, we review those issues
    under our law. Flex-Foot, Inc., 
    238 F.3d at
    1365–66.
    A
    Judicial review of the arbitral award at issue here is
    very limited even if, as we assume for present purposes,
    the standards governing both international and domestic
    arbitration apply. In numerous ways, the relevant federal
    statutes and precedents make clear that ordinary legal or
    factual error is not a ground for disturbing an arbitral
    award like the one at issue here.
    The New York Convention and its enabling statute, 
    9 U.S.C. §§ 201
    –208, require that a district court confirm an
    award “unless it finds one of the grounds for refusal or
    deferral of recognition or enforcement of the award speci-
    fied in the said Convention.” 
    9 U.S.C. § 207
    . One ground
    invoked here requires a finding that “the award deals
    BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC             11
    with a difference [i.e., issue] not contemplated by or not
    falling within the terms of the submission to arbitration,
    or contains decisions on matters beyond the scope of the
    submission to arbitration.” New York Convention art.
    V(1)(c). Another requires a finding that “recognition or
    enforcement of the award would be contrary to the public
    policy” of “the country where recognition or enforcement is
    sought.” New York Convention art. V(2)(b).
    The Federal Arbitration Act likewise strictly limits
    the grounds for disturbing an arbitral award. See 
    9 U.S.C. §§ 10
    –11; Hall Street Assocs., L.L.C. v. Mattel, Inc.,
    
    552 U.S. 576
    , 584–89 (2008). For example, the Act per-
    mits vacatur “where the arbitrators exceeded their pow-
    ers.” 
    9 U.S.C. § 10
    (a)(4). But as the Supreme Court has
    explained, the Act authorizes only “the limited review
    needed to maintain arbitration’s essential virtue of resolv-
    ing disputes straightaway,” thus ensuring that arbitra-
    tion not become “merely a prelude to a more cumbersome
    and time-consuming judicial review process.” Hall Street
    Assocs., 
    552 U.S. at 588
     (quoting Kyocera Corp. v. Pruden-
    tial-Bache Trade Servs., Inc., 
    341 F.3d 987
    , 998 (9th Cir.
    2008)). The Court adhered to those principles in review-
    ing international arbitral awards under the Act. BG Grp.,
    PLC v. Republic of Argentina, 
    134 S. Ct. 1198
    , 1206
    (2014).
    The Fourth Circuit has stated that an award may be
    vacated if the arbitrators “manifestly disregarded” the
    applicable law. Wachovia Sec., LLC v. Brand, 
    671 F.3d 472
    , 480 (4th Cir. 2012). The court has explained that the
    manifest-disregard ground exists either “as an independ-
    ent ground for review or as a judicial gloss on the enu-
    merated grounds for vacatur set forth at 
    9 U.S.C. § 10
    .”
    
    Id. at 483
     (quoting Stolt-Nielsen S.A. v. AnimalFeeds Int’l
    Corp., 
    559 U.S. 662
    , 672 n.3 (2010)). In one formulation,
    the ground applies only if the tribunal was “aware of the
    law, understood it correctly, found it applicable to the case
    before them, and yet chose to ignore it in propounding
    12          BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    their decision.” Three S Del., Inc. v. DataQuick Info. Sys.,
    Inc., 
    492 F.3d 520
    , 529 (4th Cir. 2007) (quoting Remmey v.
    PaineWebber, Inc., 
    32 F.3d 143
    , 149 (4th Cir. 1994)). In
    another, it applies only if “(1) the applicable legal princi-
    ple is clearly defined and not subject to reasonable debate;
    and (2) the arbitrator[s] refused to heed that legal princi-
    ple.” Long John Silver’s Rests., Inc. v. Cole, 
    514 F.3d 345
    ,
    349–50 (4th Cir. 2008) (quoting Merrill Lynch, Pierce,
    Fenner & Smith, Inc. v. Jaros, 
    70 F.3d 418
    , 421 (6th Cir.
    1995)); Wachovia, 671 F.3d at 483. That “carefully cir-
    cumscribed standard,” the Fourth Circuit has said, “is not
    an invitation to review the merits of the underlying
    arbitration.” Id. Instead, the standard has “for decades
    guaranteed that review for manifest disregard not grow
    into the kind of probing merits review that would under-
    mine the efficiency of arbitration.” Id.
    Additionally, although an award may be disturbed if
    it “fails to draw its essence” from the relevant contractual
    provisions, MCI Constructors, LLC v. City of Greensboro,
    
    610 F.3d 849
    , 857 (4th Cir. 2010) (quoting Patton v.
    Signator Ins. Agency, Inc., 
    441 F.3d 230
    , 234 (4th Cir.
    2006)), it does not fail to draw its essence from those
    provisions merely because the arbitrators misread them,
    see Oxford Health Plans LLC v. Sutter, 
    133 S. Ct. 2064
    ,
    2068 (2013); Stolt-Nielsen, 
    559 U.S. at 671
    ; United Pa-
    perworkers Int’l Union v. Misco, Inc., 
    484 U.S. 29
    , 38
    (1987); Choice Hotels Int’l, Inc. v. SM Prop. Mgmt., LLC,
    
    519 F.3d 200
    , 207 (4th Cir. 2008); Three S Del., 
    492 F.3d at
    527–28. Rather, “as long as the arbitrator is even
    arguably construing or applying the contract and acting
    within the scope of his authority, that a court is convinced
    he committed serious error does not suffice to overturn his
    decision.” United Paperworkers Int’l Union, 
    484 U.S. at 38
    ; Choice Hotels Int’l, 
    519 F.3d at 207
     (quoting U.S.
    Postal Serv. v. Am. Postal Workers Union, AFL-CIO, 
    204 F.3d 523
    , 527 (4th Cir. 2000)).
    BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC            13
    A challenger must meet related, and similarly high,
    standards to support a refusal to confirm an award as
    contrary to public policy.       In the domestic labor-
    arbitration context, the Supreme Court has said that, to
    justify non-enforcement, an asserted public policy “must
    be well defined and dominant, and is to be ascertained ‘by
    reference to the laws and legal precedents and not from
    general considerations of supposed public interests.’”
    W.R. Grace & Co. v. Local Union 759, Int’l Union of
    United Rubber, Cork, Linoleum & Plastic Workers, 
    461 U.S. 757
    , 766 (1983) (quoting Muschany v. United States,
    
    324 U.S. 49
    , 66 (1945)). Relatedly, the Court has recog-
    nized the strong policy considerations that favor allowing
    parties to enter into international arbitral agreements.
    See Vimar Seguros y Reaseguros, S.A. v. M/V Sky Reefer,
    
    515 U.S. 528
    , 537–39 (1995); Mitsubishi Motors Corp. v.
    Soler Chrysler-Plymouth, Inc., 
    473 U.S. 614
    , 631–40
    (1985); Scherk v. Alberto-Culver Co., 
    417 U.S. 506
    , 517–18
    (1974). Guided by those considerations, the Court has
    enforced an agreement to arbitrate, over a “public policy”
    objection that the arbitrators would not permit assertion
    of a U.S. statutory right, where it was not clear that such
    a “prospective waiver of a party’s right to pursue statuto-
    ry remedies” would occur. Vimar Seguros, 
    515 U.S. at 540
    ; see also Mitsubishi, 
    473 U.S. at
    637 & n.19.
    Courts of appeals have construed the New York Con-
    vention’s public-policy exception narrowly. In Parsons &
    Whittemore Overseas Co. v. Société Generale De
    L’Industrie du Papier (RAKTA), 
    508 F.2d 969
     (2d Cir.
    1974), the Second Circuit stated that, in accordance with
    general international choice-of-law principles, the excep-
    tion applies “only where enforcement would violate the
    forum state’s most basic notions of morality and justice.”
    
    Id.
     at 974 (citing 1 Restatement (Second) of the Conflict of
    Laws § 117 cmt. c, at 340 (Am. Law Inst. 1971)). Most
    circuits follow that approach. See Ministry of Def. &
    Support for the Armed Forces of the Islamic Republic of
    14          BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    Iran v. Cubic Def. Sys., Inc., 
    665 F.3d 1091
    , 1097 (9th Cir.
    2011); TermoRio S.A. E.S.P. v. Electranta S.P., 
    487 F.3d 928
    , 938 (D.C. Cir. 2007); Karaha Bodas Co. v. Perus-
    ahaan Pertambangan Minyak Dan Gas Bumi Negara, 
    364 F.3d 274
    , 306 (5th Cir. 2004); Slaney v. Int’l. Amateur
    Athletic Fed’n, 
    244 F.3d 580
    , 593 (7th Cir. 2001); M & C
    Corp. v. Erwin Behr GmbH & Co., KG, 
    87 F.3d 844
    , 851
    n.2 (6th Cir. 1996). The Eleventh Circuit has applied the
    Supreme Court’s labor-relations standard to the review of
    arbitral awards entered under the New York Convention,
    stressing the standard’s strictness. Indus. Risk Ins. v.
    M.A.N. Gutehoffnungshutte GmbH, 
    141 F.3d 1434
    , 1445
    (11th Cir. 1998). For the purposes of this appeal, any
    differences between the various approaches are immate-
    rial: under any approach, an asserted policy must be
    clearly established to justify non-enforcement of an arbi-
    tral award. See W.R. Grace & Co., 
    461 U.S. at 766
    ; Indus.
    Risk Ins., 141 F.3d at 1445; Parsons & Whittemore Over-
    seas Co., 
    508 F.2d at 974
    .
    B
    Dow’s first set of arguments attack parts of the arbi-
    tral award as counter to U.S. law or policies governing
    double patenting and post-patent-expiration royalties.
    We reject Dow’s arguments.
    1
    The tribunal’s rejection of Dow’s double-patenting de-
    fense to patent infringement does not justify non-
    enforcement of the award. Dow argued to the tribunal
    that the Leemans patents were invalid for obviousness-
    type double patenting in light of Strauch ’268, contending
    that the patents were commonly owned by Bayer AG, the
    parent company of Bayer CropScience AG (owner of the
    Strauch patents) and Bayer CropScience NV (owner or co-
    owner of the Leemans patents). The tribunal carefully
    scrutinized Dow’s argument, accepted the premise that
    the Leemans and Strauch patents did not claim patenta-
    BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC             15
    bly distinct inventions, but nevertheless rejected the
    challenge. It concluded that the patents were not com-
    monly owned because Bayer CropScience AG and Bayer
    CropScience NV were different entities and Dow had not
    provided sufficient evidence to pierce the corporate veil
    separating them. We cannot say that the tribunal’s
    conclusion is contrary to public policy or reflects a mani-
    fest disregard of the law under the strict standards gov-
    erning such challenges. 1
    It suffices to say that the tribunal’s conclusion did not
    contravene any well-defined, established law applicable to
    the situation presented here. Dow does not challenge the
    tribunal’s conclusion that, with no common inventors,
    common ownership of the patents was required for the
    double-patenting bar to apply. To support its position on
    common ownership, Dow relies on Manual of Patent
    Examining Practice (MPEP) § 706.02, which states that
    patents owned by wholly owned subsidiaries of the same
    parent company are commonly owned for purposes of
    deciding what qualifies as prior art under 
    35 U.S.C. § 103
    (c). See MPEP § 706.02(l)(2)(I), at 700-74. But the
    MPEP does not have the force of law. See Ethicon, Inc. v.
    Quigg, 
    849 F.2d 1422
    , 1425 (Fed. Cir. 1988). And in any
    event, the MPEP passage is not addressed to double-
    patenting doctrine.
    As we have explained, obviousness-type (or “non-
    statutory”) double patenting is a judicially-created corol-
    lary to “statutory” double patenting, which is itself a
    judicial gloss on § 101. See Geneva Pharm., Inc. v. Glax-
    oSmithKline PLC, 
    349 F.3d 1373
    , 1377–78 (Fed. Cir.
    2003). The authoritative source of law in this area is
    therefore judicial precedent. But while the courts may
    1  The tribunal separately found no common owner-
    ship on the ground that Biogen is a co-owner of the Lee-
    mans patents. We need not address that ground.
    16          BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    someday reach the present situation, they have not yet
    done so. 2 The Leemans and Strauch patents, having
    originated from separate inventors and unrelated compa-
    nies (Hoechst AG and Plant Genetic Systems), are now
    held by sibling companies. The tribunal concluded that
    Dow had not established that the corporate veil separat-
    ing the companies could be pierced. No precedent cited to
    the tribunal, or to us, considers and resolves in Dow’s
    favor the doctrinal questions presented by this situation,
    including those addressed to the policies that underlie the
    doctrine—the unjustified extension of exclusivity rights
    against the public and the potential for separate assignee
    suits enforcing the same rights. See 
    id. at 1378
    ; In re
    Hubbell, 
    709 F.3d 1140
    , 1145 (Fed. Cir. 2013). With the
    doctrinal question as unsettled as it is for the present
    circumstances, the tribunal’s rejection of Dow’s double-
    patenting challenge cannot be declared a manifest disre-
    gard of law or contrary to public policy.
    2
    We reach the same conclusion with respect to Dow’s
    argument that the tribunal’s contract-damages award is
    partially unenforceable because it violates U.S. patent-
    law limits on the recovery of post-expiration royalties for
    practicing a patent. In Brulotte v. Thys Co., 
    379 U.S. 29
    (1964), the Supreme Court held unenforceable a licensing
    agreement that required the licensee to pay royalties after
    the expiration of the patent. Recently, the Court declined
    to overrule that precedent. See Kimble v. Marvel Entm’t.,
    LLC, 
    135 S. Ct. 2401
     (2015). Under the standards for
    public-policy and manifest-disregard challenges, we
    2  A district-court decision concerning terminal-
    disclaimer law supports Bayer, not Dow, on this issue.
    Email Link Corp. v. Treasure Island, LLC, No. 2:11-cv-
    1433-ECR-GWF, 
    2012 WL 4482576
     (D. Nev. Sept. 25,
    2012).
    BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC          17
    conclude, Dow has not established that the contract
    award—more precisely, the portion of the award reaching
    past the 2023 expiration of the RE’962 reissue patent—
    must be vacated based on Brulotte.
    The tribunal awarded contract damages to compen-
    sate Bayer CropScience AG for certain revenues that it
    would have earned had Dow not breached the 1992
    Agreement’s restriction on sublicensing certain rights it
    obtained from Bayer. At the time of the breach, Dow and
    MS Tech were considering two alternatives, which the
    parties refer to as “Option B” and “Option C.” Although
    Dow and MS Tech chose Option C, which resulted in the
    Enlist E3 products, the tribunal found that, in the ab-
    sence of breach, Option C would have been unavailable,
    and Dow and MS Tech would have chosen Option B. That
    option would have required MS Tech to pay licensing
    revenues to Bayer CropScience AG under the 2007 Bayer-
    MS Tech agreement, which the tribunal determined to be
    50% of net trait revenues associated with Event FG72.
    The tribunal calculated contract damages based on the
    revenues that Bayer CropScience AG would have received
    under that agreement until it expired, in 2030. Although
    Dow argues that the tribunal misconstrued the amount
    that Bayer CropScience AG would have received under
    the 2007 Bayer-MS Tech agreement, see infra pp. 22–23,
    it does not dispute the tribunal’s conclusion that the
    agreement entitled Bayer CropScience AG to at least
    some revenues.
    No established law declares that result prohibited un-
    der the Brulotte rule. The 1992 Agreement established
    obligations entirely within the patent period: unless
    breached earlier, the agreement was to terminate upon
    expiration of the last covered patent—2023, as relevant
    here. The pertinent condition set by the Agreement on
    Dow’s use of the pat gene—namely, the restriction on
    sublicensing it to others—neither extends beyond the
    patent period nor violates any other identified law or
    18          BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    policy. If Dow’s predecessor had simply refused to accept
    the no-sublicensing condition, instead of accepting and
    then breaching it, Bayer’s predecessor could have refused
    to grant the patent license. In that scenario, according to
    the tribunal’s findings, Dow and MS Tech would have
    turned to Option B. If they had done so Bayer then would
    have earned the licensing revenues under the 2007 Bayer-
    MS Tech agreement that the tribunal awarded here as
    contract damages under French law. Dow does not allege
    that the 2007 Bayer-MS Tech agreement, to which Dow is
    not a party, violates Brulotte.
    Bayer has not shown why the facts of the present case
    are materially different from the foregoing scenario. More
    generally, it has not shown why the contract-damages
    award is prohibited by sufficiently established legal
    authority, whether Brulotte or its successors, to make the
    award contrary to public policy or manifestly in disregard
    of the law. We therefore reject the Brulotte-based chal-
    lenge without deciding whether the Brulotte rule involves
    the kind of public policy that would, where violated,
    undercut an arbitral award. 3
    C
    Dow presents a number of additional arguments for
    vacating the arbitral award. It argues that the tribunal
    exceeded its powers or manifestly disregarded applicable
    law (or committed some error that would justify vacatur)
    3  Dow’s invocation of the Constitution’s patent
    clause, U.S. Const. art. I, § 8, cl. 8, does not bolster its
    argument. If judicial precedent and statutory provisions
    do not forbid the contract-breach damages here under the
    limited standards of review of arbitral awards, neither
    does the Constitution’s “limited Times” language, which is
    no more self-defining, or fundamental, than the language
    limiting patents to “Inventors” and their “Discoveries.”
    BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC           19
    by (1) rejecting Dow’s written description and enablement
    defenses, (2) ruling on the RE’962 patent, (3) misconstru-
    ing the relevant contract provisions, and (4) imposing an
    8% rate for pre-award interest. We reject these conten-
    tions.
    1
    Dow challenges the tribunal’s rejection of its written-
    description defense, J.A. 379–95, but its arguments
    amount to no more than allegations of ordinary legal
    error. For example, Dow accuses the tribunal of conduct-
    ing its written-description analysis backwards, by first
    adopting a claim construction that, according to Dow,
    improperly narrowed the relevant genus based on the
    specification’s disclosures and then asking whether the
    narrowed genus was sufficiently disclosed. Similarly,
    Dow argues invalidity on the ground that the specification
    directly disclosed only two of the four members of the
    relevant genus. Dow’s assertions do not meet the de-
    manding standards for showing that arbitrators exceeded
    their powers or manifestly disregard the law. See Oxford
    Health Plans, 
    133 S. Ct. at 2068
    ; Stolt-Nielsen, 
    559 U.S. at 671
    ; Hall Street, 
    552 U.S. at
    584–85; Wachovia, 671
    F.3d at 481; Long John Silver’s Rests., 
    514 F.3d at
    349–
    50; Remmey, 
    32 F.3d at 149
    .
    The same is true of Dow’s challenge to the tribunal’s
    rejection of its enablement defense. J.A. 395–96. In its
    Phase II submissions, Dow argued to the tribunal that the
    asserted claims of the ’024 and ’447 patents were invalid
    because the specification did not enable monocots. The
    tribunal rejected that argument because it concluded that
    the claims did not cover monocots. In doing so, the tribu-
    nal properly considered Plant Genetic Systems, N.V. v.
    DeKalb Genetics Corp., 
    315 F.3d 1335
     (Fed. Cir. 2003), in
    which this court affirmed the district court’s conclusion
    that certain claims of the ’236 patent excluded monocots
    because they were limited to plants “susceptible to infec-
    20          BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    tion and transformation by Agrobacterium and capable of
    regeneration thereafter.” 
    Id. at 1345
    . After considering
    Plant Genetic Systems, the tribunal in the present matter
    concluded that the asserted claims were expressly or
    implicitly limited to Agrobacterium transformation. The
    tribunal’s analysis shows no manifest disregard of law or
    other error meeting the standards for rejection of arbitral
    determinations.
    2
    Dow’s argument that the tribunal exceeded the scope
    of its powers by including the RE’962 patent in the pro-
    ceeding, see J.A. 325–31, is similarly without merit. The
    RE’962 patent is a reissue of the ’665 patent, which Bayer
    asserted earlier in the arbitration. 4 In its opening Phase
    II Memorial—filed after the Office allowed the reissue
    application on April 25, 2014, but before the reissue
    patent issued on June 24, 2014—Bayer asserted claim 1
    of the RE’962 patent. In its Phase II Reply, Dow argued
    that Article 23(4) of the Rules of Arbitration of the Inter-
    national Chamber of Commerce prohibited parties from
    raising new claims outside the Terms of Reference with-
    out the tribunal’s authorization. The tribunal determined
    that Bayer’s RE’962 patent-infringement claim was not a
    “new claim” within the meaning of Article 23(4). J.A. 325,
    4   The ’665 and RE’962 patents recite only two
    claims: one specifying an amino-acid sequence; the other,
    a codon sequence. Where ’665 claim 1 states that amino
    acid X “is Met or Val,” RE’962 claim 1 limits X to Met and
    also requires the codon for X to be ATG. ’665 patent, col.
    51, lines 44–45; RE’962 patent, col. 51, lines 41–42.
    Where ’665 claim 2 allows ATG or GTG at a specified
    place in the codon sequence, RE’962 claim 2 limits that
    codon to ATG. ’665 patent, col. 52, line 45; RE’962 patent,
    col. 52, line 41.
    BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC             21
    330. We see no reason to vacate the arbitral award based
    on that determination.
    The tribunal concluded that whether Bayer’s RE’962
    patent-infringement claim was a “new claim” under
    Article 23(4) depended on considerations of “procedural
    integrity and fairness.” J.A. 330. Dow presents no mean-
    ingful argument against that aspect of the tribunal’s
    determination: although Dow suggests that the “new
    claim” standard must mirror U.S. patent law’s standard
    for whether a reissue claim supports intervening rights, it
    provides no persuasive reason that Article 23(4), a proce-
    dural provision governing international arbitration, must
    follow that standard. Given those considerations, the
    tribunal determined that Bayer’s RE’962 patent-
    infringement claim was not a new claim because: (1) claim
    1 of the RE’962 patent was “fully included in the asserted
    claim of the ’665 patent”; (2) the RE’962 patent “was fully
    briefed”; and (3) if the RE’962 patent were excluded, it
    would need “to be dealt with in another proceeding.” J.A.
    330.
    Dow has not presented any persuasive argument jus-
    tifying judicial reversal of the tribunal’s conclusion.
    Significantly, although Dow broadly asserted to the
    tribunal that including the RE’962 patent in the arbitra-
    tion would be fundamentally unfair, it did not present any
    evidence of concrete prejudice. As far as Dow has shown
    in this court, it did not identify to the tribunal any partic-
    ular argument or evidence that it needed greater oppor-
    tunity to develop and present or that it would have
    presented if it had known earlier that the RE’962 patent
    (rather than the ’665 patent) would be at issue. See J.A.
    3049–52. At a minimum, Dow did not identify such an
    argument in its opening brief in this court.              See
    SmithKline Beecham Corp. v. Apotex Corp., 
    439 F.3d 1312
    , 1319 (Fed. Cir. 2006) (“Our law is well established
    that arguments not raised in the opening brief are
    waived.”).
    22          BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    Dow suggests that we review the tribunal’s determi-
    nation regarding inclusion of the RE’962 patent without
    deference. But Dow provides no convincing basis for our
    departing from the established approach to judicial re-
    view of whether domestic arbitrators have exceeded their
    powers in construing the scope of arbitration agreements.
    In those circumstances, the Supreme Court has applied
    the same deferential standard that it applies to their
    determination of other issues. See Oxford Health Plans,
    
    133 S. Ct. at 2068
    ; Stolt-Nielsen, 
    559 U.S. at 671
    . In any
    event, for the reasons given above, we have been shown
    no error in the tribunal’s construction or application of the
    “new claim” standard of Article 23(4) to support inclusion
    of RE’962 in this arbitration.
    3
    Dow also contends that the tribunal, in calculating
    lost-opportunity contract damages, misconstrued relevant
    contract provisions. In particular, Dow challenges the
    tribunal’s reliance on the 50%-revenue provision of
    § 5.1.1(a)(i) of the 2007 Bayer-MS Tech Agreement in-
    stead of § 5.1.1(a)(x). See J.A. 448–68. But Dow forfeited
    this argument by not making it to the tribunal. In its
    Phase III submissions, Dow argued that Bayer’s evidence
    did not establish harm, causation, or foreseeability. Dow
    also objected to Bayer’s lost-profits theory on due-process
    grounds. Dow did not present the contract argument it
    now makes about Bayer’s prospective revenues under
    Option B. We see no basis for excusing Dow’s failure to
    raise this argument and now requiring the arbitral panel
    to redo its application of contract provisions clearly within
    its authority to interpret. 5 We conclude, therefore, that
    5  Dow’s new argument involves the interpretation
    of contract provisions clearly within the arbitral tribunal’s
    authority to interpret. In this respect, Dow’s challenge is
    quite different from the challenge at issue in Stolt-
    BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC           23
    Dow cannot raise the issue at this juncture. See Nat’l
    Wrecking Co. v. Int’l Bhd. of Teamsters, Local 731, 
    990 F.2d 957
    , 960 (7th Cir. 1993) (“Failure to present an issue
    before an arbitrator waives the issue in an enforcement
    proceeding.”); United Food & Commercial Workers Local
    100A, AFL-CIO v. John Hofmeister & Son, Inc., 
    950 F.2d 1340
    , 1343–45 (7th Cir. 1991).
    4
    For similar reasons, the tribunal did not manifestly
    disregard Indiana law governing pre-judgment interest.
    Based on the evidence submitted by the parties, the
    tribunal found it highly likely that Dow and MS Tech
    would have pursued Option B if they had not breached
    the 1992 Hoechst-Lubrizol Agreement. J.A. 464–68, 515–
    16. The tribunal calculated contract damages based on
    the amount that Bayer would have received under the
    2007 Bayer-MS Tech agreement and awarded pre-award
    interest based on that amount. The parties agree that
    Indiana law governs the pre-judgment interest award.
    Nielsen, in which the Supreme Court held that an arbi-
    trator exceeded his powers, i.e., acted without a contrac-
    tual basis, by concluding that the arbitration agreement
    authorized class arbitration when the parties had stipu-
    lated that the contract was silent on the issue. 
    559 U.S. at
    665–65; see Oxford Health Plans, 
    133 S. Ct. at 2069
    .
    This case likewise differs from Bankers Life & Casualty
    Insurance Co. v. CBRE, Inc., 
    830 F.3d 729
     (7th Cir. 2016),
    in which the Seventh Circuit disapproved the arbitration
    panel’s reliance on a disclaimer that was outside the scope
    of the agreement submitted to arbitration. 
    Id.
     at 730–33.
    See also Dewan v. Walia, 544 F. App’x 240, 245–48 (4th
    Cir. 2013) (arbitrator found release clause enforceable,
    but nevertheless refused to enforce it).
    24          BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    Dow argues that Indiana law allows pre-judgment in-
    terest to be awarded only when “the amount of the claim
    rests upon a simple calculation and the terms of the
    contract make such a claim ascertainable.” Kummerer v.
    Marshall, 
    971 N.E.2d 198
    , 201 (Ind. Ct. App. 2012) (quot-
    ing Olcott Int’l & Co. v. Micro Data Base Sys., Inc., 
    793 N.E.2d 1063
    , 1078 (Ind. Ct. App. 2003)). Indiana practice
    may not be as uniform as Dow suggests. See James P.
    Nehf, Contract Damages as Substitute for Full Perfor-
    mance, 
    32 Ind. L. Rev. 765
    , 783, (1999) (“In practice,
    however, Indiana courts have awarded prejudgment
    interest even when the terms of the contract did not make
    the amount of the claim readily ascertainable by mere
    computation.”). But the tribunal carefully considered and
    applied Indiana law in evaluating the parties’ arguments
    regarding pre-award interest. Dow’s challenge amounts
    to no more than an assertion that the tribunal misapplied
    the law, which is not enough. See Long John Silver’s
    Rests., 
    514 F.3d at
    349–50; Remmey, 
    32 F.3d at 149
    . We
    therefore decline to vacate the tribunal’s award of pre-
    award interest.
    D
    Although we affirm the district court’s decision to con-
    firm the arbitral award, we conclude that the court
    abused its discretion in denying Dow’s motion to amend
    the judgment to use the federal statutory rate for post-
    judgment interest for the period beginning with the entry
    of the district court’s judgment. 
    28 U.S.C. § 1961
    (a)
    provides that “interest shall be calculated from the date of
    the entry of the judgment, at a rate equal to the weekly
    average 1-year constant maturity Treasury yield, as
    published by the Board of Governors of the Federal Re-
    serve System, for the calendar week preceding the date of
    the judgment.” Dow argues that the court was obligated
    to replace the tribunal’s “post-award” interest rate with
    the statutory post-judgment rate for time after the district
    court’s judgment. We agree on the facts of this case.
    BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC             25
    Under the doctrine of merger, when “a valid and final
    judgment for the payment of money is rendered in favor of
    the plaintiff, the original claim of the plaintiff is extin-
    guished and a new cause of action on the judgment is
    substituted for it.” Restatement (Second) of Judgments
    § 47. Reflecting that notion, numerous circuits have
    concluded that once a federal court confirms an arbitral
    award, the award merges into the judgment and the
    federal rate for post-judgment interest presumptively
    applies. See Tricon Energy Ltd. v. Vinmar Int’l, Ltd., 
    718 F.3d 448
    , 456–460 (5th Cir. 2013); Newmont U.S.A. Ltd.
    v. Ins. Co. of N. Am., 
    615 F.3d 1268
    , 1275–77 (10th Cir.
    2010); Fid. Fed. Bank, FSB v. Durga Ma Corp., 
    387 F.3d 1021
    , 1023–24 (9th Cir. 2004); Carte Blanche (Sing.) Pte.,
    Ltd. v. Carte Blanche Int’l, Ltd., 
    888 F.2d 260
    , 268–70 (2d
    Cir. 1989); Parsons & Whittemore Ala. Mach. & Servs.
    Corp. v. Yeargin Constr. Co., 
    744 F.2d 1482
    , 1484 (11th
    Cir. 1984). To overcome this presumption, courts have
    required the parties or arbitrators to unambiguously
    express their intent to replace the federal rate for the
    post-judgment period. See Tricon Energy, 718 F.3d at
    456–60; Newmont U.S.A., 
    615 F.3d at
    1275–77; Fid. Fed.
    Bank, 
    387 F.3d at
    1023–24; Westinghouse Credit Corp. v.
    D’Urso, 
    371 F.3d 96
    , 101–02 (2d Cir. 2004).
    We think that the Fourth Circuit would follow the ap-
    proach taken by its sister circuits and apply the federal
    post-judgment interest rate in the absence of unambigu-
    ous evidence of the parties’ or arbitrators’ contrary intent.
    In a non-precedential opinion, the Fourth Circuit has
    applied the same rule to determine whether a contractual
    interest rate replaced the federal rate. See Kanawha-
    Gauley Coal & Coke Co. v. Pittston Minerals Grp., Inc.,
    501 F. App’x 247, 254–55 (4th Cir. 2012) (per curiam).
    Bayer does not identify any reason that the Fourth Cir-
    cuit would not apply the same rule to arbitral awards.
    We are also unaware of any instance in which a federal
    26          BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    court has allowed an interest rate specified in an award to
    replace the federal rate based on less than clear evidence.
    In this case, there is insufficiently clear evidence to
    displace the federal statutory rate. Here, the tribunal
    granted “post-award interest” “at the rate of 8% from the
    date of this Award until full payment.” J.A. 560, 563.
    And it is undisputed that the tribunal’s attention was not
    called to the distinction between the time from award to
    confirmation judgment and the time after confirmation
    judgment. We see no basis on which to distinguish these
    circumstances from other grants found to be insufficiently
    clear to displace the statutory post-judgment rate. See
    Tricon Energy, 718 F.3d at 456–60; Fid. Fed. Bank, 
    387 F.3d at
    1023–24; Westinghouse Credit, 
    371 F.3d at
    101–
    02.
    The Fifth Circuit’s decision in Tricon Energy is espe-
    cially instructive. There, arbitrators awarded Tricon
    contract damages and “post-award interest” “at the rate of
    8.5% per annum . . . [from] the date of th[e] award, until
    paid.” 718 F.3d at 459 (alterations in original). The
    district court awarded post-judgment interest at the
    statutory rate. Id. at 452. The Fifth Circuit affirmed,
    explaining that, because the “panel did not use the words
    ‘postjudgment interest,’ it is far from clear that it meant
    to award postjudgment interest.” Id. at 459. The court
    also rejected Tricon’s contention that because the panel
    awarded interest “until paid,” the arbitrators meant to
    replace the federal rate. Id. We do not see how this case,
    in which the tribunal awarded 8% interest “until full
    payment,” is materially different from the Tricon Energy
    arbitrators’ award of 8.5% interest “until paid.”
    Mobil Cerro Negro, Ltd. v. Bolivarian Republic of Ven-
    ezuela, No. 14 Civ. 8163 (PAE), 
    2015 WL 926011
    (S.D.N.Y. Mar. 4, 2015), is not to the contrary. There, the
    district court held that the federal post-judgment interest
    rate did not apply to post-judgment interest awarded
    BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC            27
    under the Convention on the Settlement of Investment
    Disputes Between States and Nationals of Other States
    (ICSID Convention), Mar. 18, 1965, 17 U.S.T. 1271, 575
    U.N.T.S. 159. 
    Id.
     at *1–3. In reaching that conclusion,
    however, the court relied on reasoning that applies to the
    ICSID Convention, but not the New York Convention.
    For example, the court noted that the Federal Arbitration
    Act’s enforcement provisions do not apply to the ICSID
    Convention. See 22 U.S.C. § 1650a. By contrast, the New
    York Convention’s enabling statute contains no such
    prohibition. See 
    9 U.S.C. § 208
    . The court also made
    specific factual findings regarding the language of the
    award.
    Under 
    28 U.S.C. § 2106
    , a federal appellate court
    “may affirm, modify, vacate, set aside or reverse any
    judgment, decree, or order of a court lawfully brought
    before it for review.” In exercising our discretion under
    that provision, we modify the district court’s judgment to
    include the relief requested by Dow’s motion to amend.
    See Bayer CropScience AG, No. 2:12-cv-47-RAJ-RJK (E.D.
    Va. Jan. 21, 2016), ECF Nos. 209–10. Specifically, we
    modify the district court’s judgment to provide that post-
    award interest, as set forth in the arbitral award, shall
    accrue through January 15, 2015, the date on which the
    court entered judgment, and post-judgment interest shall
    accrue thereafter at the rate established in § 1961. We
    affirm the judgment as modified. Like the Fourth Circuit,
    we believe that this approach is appropriate because the
    resolution of the parties’ dispute requires only the correc-
    tion of the relevant interest rates. See Martin v. Harris,
    
    560 F.3d 210
    , 219–22 (4th Cir. 2009); First Fed. Sav. &
    Loan Ass’n of S.C. v. Chrysler Credit Corp., 
    981 F.2d 127
    ,
    135–36 (4th Cir. 1992). Remand for further proceedings
    would cause the parties to suffer additional delay and
    expense with no change in outcome.
    28          BAYER CROPSCIENCE AG   v. DOW AGROSCIENCES LLC
    IV
    For the foregoing reasons, we affirm the district
    court’s decision to confirm the arbitral award. We vacate
    the court’s decision denying Dow’s motion to amend the
    judgment. We modify the court’s judgment to provide
    that post-award interest accrued at the tribunal-set rate
    through January 15, 2015, and thereafter post-judgment
    interest shall accrue at the rate established in 
    28 U.S.C. § 1961
    . We affirm the judgment as modified.
    Costs awarded to Bayer.
    AFFIRMED AS MODIFIED
    

Document Info

Docket Number: 16-1530

Citation Numbers: 680 F. App'x 985

Filed Date: 3/1/2017

Precedential Status: Non-Precedential

Modified Date: 1/13/2023

Authorities (50)

Newmont U.S.A. Ltd. v. Insurance Co. of North America , 615 F.3d 1268 ( 2010 )

parsons-whittemore-alabama-machinery-and-services-corporation-and-parsons , 744 F.2d 1482 ( 1984 )

Rocket Jewelry Box, Inc. v. Noble Gift Packaging, Inc., ... , 157 F.3d 174 ( 1998 )

westinghouse-credit-corporation-nka-cbs-corporation-westinghouse , 371 F.3d 96 ( 2004 )

parsons-whittemore-overseas-co-inc-plaintiff-appellant-appellee-v , 508 F.2d 969 ( 1974 )

in-the-matter-of-the-arbitration-of-certain-controversies-between-carte , 888 F.2d 260 ( 1989 )

hitachi-credit-america-corporation-v-signet-bank-formerly-known-as-signet , 166 F.3d 614 ( 1999 )

Martin v. Harris , 560 F.3d 210 ( 2009 )

Medtronic Ave, Inc. v. Advanced Cardiovascular Systems, Inc. , 247 F.3d 44 ( 2001 )

Ralph F. Patten, Jr. v. Signator Insurance Agency, ... , 441 F.3d 230 ( 2006 )

Three S Delaware, Inc. v. DataQuick Information Systems, ... , 492 F.3d 520 ( 2007 )

Long John Silver's Restaurants, Inc. v. Cole , 514 F.3d 345 ( 2008 )

MCI CONSTRUCTORS, LLC v. City of Greensboro , 610 F.3d 849 ( 2010 )

Raymond James Financial Services, Inc. v. Bishop , 596 F.3d 183 ( 2010 )

Fed. Sec. L. Rep. P 98,943 Merrill Lynch, Pierce, Fenner & ... , 70 F.3d 418 ( 1995 )

M & C Corporation, a Michigan Corporation, D/B/A Connelly ... , 87 F.3d 844 ( 1996 )

United Food & Commercial Workers Local 100a, Afl-Cio & Clc ... , 950 F.2d 1340 ( 1991 )

Karaha Bodas Co. v. Perusahaan Pertambangan Minyak Dan Gas ... , 364 F.3d 274 ( 2004 )

United States Postal Service v. American Postal Workers ... , 204 F.3d 523 ( 2000 )

fed-sec-l-rep-p-98366-kathryn-thompson-remmey-for-the-estate-of , 32 F.3d 143 ( 1994 )

View All Authorities »