Naec v. Usdoi ( 2020 )


Menu:
  •                  FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    NORTHERN ALASKA                          No. 19-35008
    ENVIRONMENTAL CENTER; ALASKA
    WILDERNESS LEAGUE; DEFENDERS                D.C. No.
    OF WILDLIFE; SIERRA CLUB; THE            3:18-cv-00030-
    WILDERNESS SOCIETY, INC.,                     SLG
    Plaintiffs-Appellants,
    v.                     ORDER AND
    AMENDED
    U.S. DEPARTMENT OF THE INTERIOR;           OPINION
    BUREAU OF LAND MANAGEMENT;
    DAVID L. BERNHARDT, in his official
    capacity as Secretary of the Interior;
    BRIAN STEED, in his official capacity
    as the official exercising the
    authority of the Director of the
    Bureau of Land Management,
    Defendants-Appellees,
    CONOCOPHILLIPS ALASKA, INC.,
    Intervenor-Defendant-
    Appellee.
    Appeal from the United States District Court
    for the District of Alaska
    Sharon L. Gleason, District Judge, Presiding
    Argued and Submitted February 7, 2020
    Seattle, Washington
    2                        NAEC V. USDOI
    Filed July 9, 2020
    Amended December 22, 2020
    Before: MILAN D. SMITH, JR. and N. RANDY SMITH,
    CIRCUIT JUDGES, and JOHN R. TUNHEIM, * District
    Judge.
    Order;
    Opinion by Judge Milan D. Smith, Jr.
    SUMMARY **
    Environmental Law
    The panel affirmed the district court’s summary
    judgment in favor of federal agencies and officials and
    intervenor ConocoPhillips Alaska, Inc. in a National
    Environmental Policy Act (“NEPA”) action brought by
    environmental groups challenging the Bureau of Land
    Management (“BLM”)’s 2017 offer and sale of oil and gas
    leases in the National Petroleum Reserve-Alaska (the
    Reserve).
    In 2012, BLM published a document styled as a
    combined Integrated Activity Plan (“IAP”) and
    Environmental Impact Statement (“EIS”), designed to
    determine the appropriate management of all BLM-managed
    *
    The Honorable John R. Tunheim, United States Chief District
    Judge for the District of Minnesota, sitting by designation.
    **
    This summary constitutes no part of the opinion of the court. It
    has been prepared by court staff for the convenience of the reader.
    NAEC V. USDOI                           3
    lands in the Reserve. In 2017, BLM issued a call for
    nominations and comments on all unleased tracts for the
    2017 lease sale.
    The panel first held that, to the extent plaintiffs argued
    that the 2017 lease sale was a distinct federal action requiring
    a tiered or standalone NEPA analysis, their claims were not
    barred by the Naval Petroleum Reserves Production Act 60-
    day limitations period applicable to the 2012 EIS.
    The panel agreed with the environmental groups that the
    2017 lease sale required some form of site-specific analysis,
    but found that the instant dispute was whether the required
    analysis had already been prepared. The panel held that the
    fact that the 2012 EIS provided a programmatic-level
    analysis for the IAP did not preclude the legal possibility that
    it also served as the necessary site-specific analysis for
    future lease sales. The panel also was not persuaded that the
    degree of site specificity required for the 2017 lease sale was
    so clearly greater than that reflected in the 2012 EIS that the
    2012 EIS could not have covered the 2017 lease sale.
    The panel declined to inquire whether the 2012 EIS
    adequately analyzed the impacts of the 2017 lease sale,
    finding that this approach would rob the statute of limitations
    of effect in situations where some steps of a previously
    studied action remain to occur after expiration of the
    limitations period. The panel also declined to inquire
    whether the 2017 lease sale was in conformity with the IAP,
    finding that this approach fails to account for whether
    members of the public have fair notice of when they should
    challenge the NEPA compliance of a particular action.
    Instead, the panel inquired whether the 2012 EIS
    purported to be the EIS for the 2017 lease sale, as reflected
    4                    NAEC V. USDOI
    in the 2012 EIS’ defined scope. The panel concluded that
    the expressly defined scope of the 2012 EIS was somewhat
    ambiguous as to this question, but that the language
    regarding future NEPA requirements provided reasonable
    notice that the intended scope encompassed actual future
    lease sales. The panel also found that construing the scope
    of the 2012 EIS as such was not unreasonable when
    considering the analysis performed therein and the
    applicable law. Thus, the panel deferred to BLM’s
    reasonable position that the 2012 EIS was the EIS for the
    2017 lease sale.
    The panel therefore held that BLM met the NEPA
    requirement for the 2017 lease sale of preparing at least an
    initial EIS, any challenge to the adequacy of which is now
    time barred. Although plaintiffs alleged significant new
    information and circumstances known to BLM before the
    2017 lease sale, the appropriate rubric for considering these
    allegations—given the existence of an initial EIS—was
    supplementation, and plaintiffs waived any supplementation
    claim.
    COUNSEL
    Suzanne Bostrom (argued), Brook Brisson, and Valerie
    Brown, Trustees for Alaska, Anchorage, Alaska, for
    Plaintiffs-Appellants.
    Thekla Hansen-Young (argued), John David Gunter II, and
    Romney S. Philpott, Attorneys; Eric Grant, Deputy Assistant
    Attorney General; Jeffrey Bossert Clark, Assistant Attorney
    General; Jonathan D. Brightbill, Principal Deputy Assistant
    Attorney General; Environment and Natural Resources
    Division, United States Department of Justice, Washington,
    NAEC V. USDOI                         5
    D.C.; Michael Gieryic, Attorney-Advisor, Office of the
    Solicitor, United States Department of the Interior,
    Washington, D.C.; for Defendants-Appellees.
    Ryan P. Steen (argued) and Jason T. Morgan, Stoel Rives
    LLP, Seattle, Washington, for Intervenor-Defendant-
    Appellee.
    ORDER
    The opinion filed on July 9, 2020, and reported at
    
    965 F.3d 705
    , is amended by the Amended Opinion filed in
    its place concurrently with this order
    With these amendments, the full court has been advised
    of the petition for rehearing en banc and no judge has
    requested a vote on whether to rehear the matter en banc.
    Fed. R. App. P. 35.
    The petition for rehearing en banc is DENIED. No
    further petitions for panel rehearing or rehearing en banc
    may be filed.
    OPINION
    M. SMITH, Circuit Judge:
    Northern Alaska Environmental Center (NAEC), Alaska
    Wilderness League, Defenders Of Wildlife, Sierra Club, and
    The Wilderness Society, Inc. (collectively, Plaintiffs),
    appeal the district court’s grant of summary judgment for the
    U.S. Department of the Interior, the Bureau of Land
    6                        NAEC V. USDOI
    Management (BLM), Secretary of the Interior Ryan Zinke, 1
    and BLM Director Brian Steed (collectively, Federal
    Defendants),      as     well    as     Intervenor-Defendant
    ConocoPhillips Alaska, Inc. (collectively, Defendants).
    Plaintiffs assert claims under the National Environmental
    Policy Act (NEPA), 42 U.S.C. § 4321 et seq., and the
    Administrative Procedure Act (APA), 5 U.S.C. § 706(2), on
    the theory that BLM failed to prepare a required NEPA
    analysis for its 2017 offer and sale of oil and gas leases (the
    2017 lease sale) in the National Petroleum Reserve-Alaska
    (the Reserve). Defendants contend that BLM conducted the
    requisite NEPA analysis in an Environmental Impact
    Statement (EIS) prepared in 2012. Defendants also claim
    that, because any challenge to the adequacy of the 2012 EIS
    is subject to a 60-day statute of limitations pursuant to the
    Naval Petroleum Reserves Production Act (NPRPA),
    42 U.S.C. § 6506a(n)(1), Plaintiffs’ claims are time barred.
    Finding that the NPRPA statute of limitations does not
    bar our inquiry, we analyze the scope of the 2012 EIS and
    ultimately defer to BLM’s position that the scope of the 2012
    EIS encompassed future lease sales. We therefore find that
    BLM met the NEPA requirement for the 2017 lease sale of
    preparing at least an initial EIS, any challenge to the
    adequacy of which is now time barred. Although Plaintiffs
    allege significant new information and circumstances known
    to BLM before the 2017 lease sale, the appropriate rubric for
    considering these allegations—given the existence of an
    initial EIS—is supplementation, and Plaintiffs have waived
    any supplementation claim.
    1
    This appeal substitutes current Secretary of the Interior David L.
    Bernhardt.
    NAEC V. USDOI                          7
    Accordingly, we affirm the district court’s grant of
    summary judgment for Defendants on all counts.
    FACTUAL AND PROCEDURAL BACKGROUND
    The Reserve comprises over 23 million acres of land
    located along the north coast of Alaska, an area roughly the
    size of Indiana. This vast expanse of Arctic tundra provides
    habitat for polar bears, grizzly bears, gray wolves, moose,
    caribou, and dozens of species of migratory birds. It is home
    to numerous Native Alaskan communities that practice a
    subsistence way of life, relying on the biological resources
    of the Reserve. It is also a significant source of oil and gas.
    As of 2017, the U.S. Geological Survey (USGS) estimated
    that technically recoverable petroleum resources underlying
    the Reserve include 8.7 billion barrels of oil and 25 trillion
    cubic feet of natural gas.
    BLM manages 22.6 million acres of the Reserve
    pursuant to the NPRPA, 42 U.S.C. §§ 6501–07. The
    NPRPA directs BLM to lease Reserve land to private entities
    for oil and gas development, while taking such measures as
    BLM deems necessary or appropriate to mitigate adverse
    environmental impacts. 42 U.S.C. § 6506a. BLM’s actions
    taken pursuant to the authority of NPRPA are also subject to
    NEPA procedural requirements for the analysis of potential
    environmental impacts and reasonable alternatives. See
    42 U.S.C. § 4332(2)(C).
    I. The 2012 Environmental Impact Statement
    In 2012, BLM published a 2,600-page document styled
    as a combined Integrated Activity Plan (IAP) and EIS,
    designed to determine the appropriate management of all
    8                        NAEC V. USDOI
    BLM-managed lands in the Reserve. 2 The IAP/EIS
    analyzed five alternative proposals for a range of land
    allocations, including different options for the percentage of
    lands that would be made available for oil and gas leasing.
    The alternatives also included stipulations and required
    operating procedures or best management practices to
    mitigate environmental impacts. The IAP/EIS designated as
    its preferred alternative a proposal that would make
    approximately 52% of the federal lands in the Reserve
    available for oil and gas leasing.
    In order to analyze the environmental consequences of
    the various alternatives, BLM developed a set of
    hypothetical development scenarios based on assumptions it
    considered reasonable, seeking to minimize the chance that
    its analysis would underestimate potential impacts. BLM
    assumed that multiple annual lease sales would be held, each
    of which might offer all or only part of the lands made
    available for oil and gas leasing, and that the industry would
    need time to evaluate existing leases before actually leasing
    additional tracts. BLM assumed that full exploration and
    development of petroleum resources in the Reserve would
    take place over many decades. Based on the then-most
    recent USGS estimates, BLM assumed that the Reserve
    contained 896 million barrels of technically recoverable oil,
    604 million barrels of which were economically recoverable.
    The IAP/EIS predicted that it would fully satisfy
    NEPA’s requirements for the first oil and gas lease sale.
    With respect to anticipated subsequent lease sales, it stated
    2
    Hereinafter, we refer to this document generally as the IAP/EIS.
    However, when we reference this document specifically in its NEPA
    capacity, we refer to the 2012 EIS. When we reference this document
    specifically in its land management plan capacity, we refer to the IAP.
    NAEC V. USDOI                              9
    that BLM would prepare an administrative determination of
    NEPA adequacy (DNA) in connection with each proposed
    lease to determine whether the then-existing NEPA
    documentation was adequate. 3
    In 2013, BLM published a Record of Decision that
    finalized its decision to manage the Reserve under the
    preferred alternative. Each year thereafter, through 2016,
    BLM offered oil and gas leases on 1–2 million acres of the
    Reserve, but ultimately sold leases on only a small portion
    of the offered acreage. In conjunction with each offering,
    BLM prepared a four-page DNA documenting its conclusion
    that the 2012 EIS remained adequate to meet the
    requirements of NEPA, so no further NEPA documentation
    was required to support the offering or sale of the relevant
    leases.
    II. The 2017 Lease Sale
    In August 2017, BLM issued a call for nominations and
    comments on all unleased tracts for the 2017 lease sale.
    Several of the Plaintiffs submitted a joint comment letter
    arguing that BLM should not hold the proposed lease sale.
    Their letter contended that BLM was required either to
    prepare a new, “site-specific” NEPA analysis for the sale, or
    to retain the authority to prohibit future activities on the
    leased land.
    In September, BLM issued a DNA evaluating the NEPA
    adequacy of the 2012 EIS respecting a proposal to offer
    leases on all of the remaining tracts within the lands the IAP
    3
    A DNA is not itself a NEPA document; it is not subject to public
    comment or consultation with other federal agencies. S. Utah
    Wilderness All. v. Norton, 
    457 F. Supp. 2d 1253
    , 1255 (D. Utah 2006).
    10                    NAEC V. USDOI
    made available for leasing, a total of about 10.3 million
    acres. The DNA asserted that the current proposal was part
    of the preferred alternative analyzed in the 2012 EIS, and
    that no new information or circumstances substantially
    changed the analysis.
    BLM opened the bidding process in December 2017.
    Intervenor bid on seven of the 900 available tracts, covering
    roughly 80,000 acres. BLM received no other bids on any
    of the offered tracts. BLM accepted Intervenor’s bids in
    January 2018. During this same period, the USGS published
    an updated Assessment of Undiscovered Oil and Gas
    Resources in formations underlying the Reserve, raising the
    estimate of technically recoverable oil to 8.7 billion barrels.
    In early February, Plaintiffs filed a Complaint against
    Federal Defendants alleging that BLM had conducted the
    2017 lease sale without complying with NEPA. The
    Complaint asserted two alleged causes of action: first, that
    BLM failed to prepare a NEPA analysis, and second, that
    BLM failed to take a “hard look” at environmental impacts.
    See Baltimore Gas & Elec. Co. v. Nat. Res. Def. Council,
    Inc., 
    462 U.S. 87
    , 97 (1983) (“Congress in enacting NEPA
    . . . required only that the agency take a ‘hard look’ at the
    environmental consequences before taking a major action.”
    (quoting Kleppe v. Sierra Club, 
    427 U.S. 390
    , 410 n.21
    (1976))). The Complaint highlighted the updated USGS
    Assessment along with several other recent developments
    that it claimed BLM had failed to properly analyze.
    Later that month, BLM issued a nine-page Revised DNA
    that discussed several of those recent developments. The
    Revised DNA found the updated USGS Assessment
    unusable because it did not provide an estimate of
    economically recoverable resources, and because it included
    oil and gas underlying land and sea adjacent to the Reserve.
    NAEC V. USDOI                       11
    It also found several other developments insignificant
    because the 2012 EIS had “already erred on the conservative
    side and over analyzed likely potential impacts.” BLM’s
    Acting Alaska State Director approved the Revised DNA
    and executed the seven leases purchased by Intervenor on
    the same day.
    In May, Plaintiffs filed a First Amended Complaint that
    added a third cause of action, claiming that BLM had
    violated its own NPRPA regulations by issuing the Revised
    DNA “after it had already conducted the 2017 lease sale.”
    See 43 C.F.R. § 3131.2(b).
    III.   Proceedings in the District Court
    On cross-motions for summary judgment, the district
    court ruled in favor of Defendants. The court concluded that
    Plaintiffs were not asserting a time-barred claim that the
    2012 EIS failed to take a hard look at environmental
    consequences. Nevertheless, the court held that BLM was
    not required to prepare a new NEPA document for the 2017
    lease sale.
    The court concluded that its decision was controlled by
    Northern Alaska Environmental Center v. Kempthorne,
    
    457 F.3d 969
    (9th Cir. 2006). The court interpreted
    Kempthorne to support Plaintiffs’ argument that BLM must
    prepare a NEPA document before issuing leases wherein
    BLM does not retain the authority to prohibit future on-the-
    ground activities. However, the court read Kempthorne as
    validating BLM’s position that the 2012 EIS was the
    required document.        The court further interpreted
    Kempthorne to hold that parcel-specific analysis was not
    required until BLM was reviewing actual exploration and
    development proposals. The court noted that Kempthorne
    differed from this case due to the passage of time between
    12                        NAEC V. USDOI
    the EIS and the lease sale, but concluded that this distinction
    was relevant only to whether supplementation might be
    required, which Plaintiffs did not allege. 4
    Plaintiffs timely appealed.
    JURISDICTION AND STANDARD OF REVIEW
    We have jurisdiction pursuant to 28 U.S.C. § 1291. We
    review de novo the district court’s grant of summary
    judgment upholding an agency decision. 
    Kempthorne, 457 F.3d at 975
    . Because NEPA does not contain its own
    provision for judicial review, we review BLM’s compliance
    with NEPA pursuant to the APA. Ka Makani ‘O Kohala
    Ohana Inc. v. Water Supply, 
    295 F.3d 955
    , 959 (9th Cir.
    2002). 5 Where an agency’s decision not to prepare an EIS
    turns on a threshold legal question regarding NEPA
    applicability, rather than a predominantly factual or
    technical decision, we review under a standard of
    “reasonableness.”
    Id. at 959
    & n.3 (citing Northcoast Envtl.
    Ctr. v. Glickman, 
    136 F.3d 660
    , 667 (9th Cir. 1998); see also
    4
    The court concluded in any event that “supplementation would
    likely have been unnecessary.”
    5
    Defendants do not renew on appeal the argument they made to the
    district court that the court lacked subject matter jurisdiction because the
    original complaint was filed before final agency action had occurred for
    purposes of the APA. See 5 U.S.C. § 704. While we offer no opinion
    on the validity of the prior complaint, because jurisdiction is something
    we must consider sua sponte, see Gonzalez v. Thaler, 
    565 U.S. 134
    , 141
    (2012), we nevertheless hold expressly that the district court correctly
    relied on Northstar Financial Advisors Inc. v. Schwab Investments,
    
    779 F.3d 1036
    (9th Cir. 2015), which allows us to rely on an amended
    complaint that satisfies the jurisdictional defects, if any, of an original
    complaint. See
    id. at 1043–48.
                             NAEC V. USDOI                               13
    High Sierra Hikers Ass’n v. Blackwell, 
    390 F.3d 630
    , 640
    (9th Cir. 2004). 6
    STATUTE OF LIMITATIONS
    We begin by rejecting Defendants’ threshold argument
    that Plaintiffs’ lawsuit is entirely time barred by the NPRPA.
    To the extent Plaintiffs argue that the 2017 lease sale was a
    distinct federal action requiring a tiered or stand-alone
    NEPA analysis, we find their challenge is justiciable.
    The NPRPA contains the following statute of
    limitations:
    Any action seeking judicial review of the
    adequacy of any program or site-specific
    environmental impact statement under
    section 102 of the National Environmental
    Policy Act of 1969 (42 U.S.C. 4332)
    concerning oil and gas leasing in the National
    Petroleum Reserve--Alaska shall be barred
    unless brought in the appropriate District
    Court within 60 days after notice of the
    6
    Where an agency’s decision not to prepare an EIS is based on
    preparing a NEPA “environmental assessment” (EA) and concluding
    therein that an action will have no significant impacts, we review under
    the familiar “arbitrary and capricious” standard. 
    Northcoast, 136 F.3d at 666
    –67 (citing Marsh v. Or. Nat. Res. Council, 
    490 U.S. 360
    , 376–77
    (1989)). This same standard applies where an agency’s decision not to
    supplement an EIS is based on its conclusion that new information or
    circumstances do not rise to the level of significance, such as the
    determinations BLM made in the DNA and Revised DNA. See
    id. As discussed below,
    this case gives us no occasion to review either such
    decision.
    14                       NAEC V. USDOI
    availability of such statement is published in
    the Federal Register.
    42 U.S.C. § 6506a(n)(1). Defendants argue that Plaintiffs
    “necessarily” challenge the adequacy of the 2012 EIS,
    regardless of how Plaintiffs attempt to characterize their
    complaint, and that the NPRPA statute of limitations
    therefore bars their claims. Cf. Turtle Island Restoration
    Network v. U.S. Dep’t of Commerce, 
    438 F.3d 937
    , 944–45
    (9th Cir. 2006) (in applying Magnuson Act statute of
    limitations for challenging regulations promulgated
    thereunder, “the decisive question is whether the regulations
    are being attacked, not whether the complaint specifically
    asserts a violation of the Magnuson Act”). Of Plaintiffs’
    three claims, we find that it is possible to resolve the first and
    third without an untimely adjudication of the adequacy of the
    2012 EIS. We find that Plaintiff’s second claim, however,
    is potentially barred by the statute of limitations, depending
    on how we resolve the first claim.
    Plaintiffs’ first and third claims allege that BLM violated
    NEPA and its own NPRPA regulations by failing to prepare
    an environmental assessment (EA) 7 or EIS for the 2017 lease
    sale. In order to adjudicate these claims, we must determine
    whether the 2012 EIS was the EIS for the 2017 lease sale, as
    BLM argues. Provided we are mindful that our inquiry not
    7
    If an agency is unsure whether a project may have significant
    environmental impacts and thus require an EIS, the agency can take the
    intermediate step of preparing an EA, which requires less detail and less
    formality of procedure than an EIS, and does not require the analysis of
    alternatives. 40 C.F.R. §§ 1501.4(b), 1508.9. The purpose of the EA is
    to determine whether the proposal may have significant impacts: If so,
    the agency must go on to prepare an EIS. See
    id. §§ 1501.4(c), 1502.14,
    1508.9(a)(1). If not, the agency certifies its conclusion with a Finding
    of No Significant Impact (FONSI).
    Id. § 1508.13. NAEC
    V. USDOI                               15
    amount to “judicial review of the adequacy of” the 2012 EIS,
    the statute of limitations does not prevent us from resolving
    this issue. If the 2012 EIS was the EIS for the 2017 lease
    sale, then BLM did not fail to prepare an EIS, and Plaintiffs’
    first and third claims fail on the merits. If the 2012 EIS was
    not an EIS for the 2017 lease sale—in other words, if the
    2017 lease sale required at least a tiered EA regardless of the
    adequacy of the 2012 EIS—then Plaintiffs’ first and third
    claims are not affected by the statute of limitations.
    Plaintiffs’ second claim is that BLM failed to take a hard
    look at the impacts of the 2017 lease sale. If the 2012 EIS
    was the EIS for the 2017 lease sale, then Defendants are
    correct that Plaintiffs’ second claim “necessarily” must
    challenge the adequacy of the 2012 EIS, and is barred by the
    statute of limitations. 8 If the 2012 EIS was not an EIS for
    the 2017 lease sale, then Plaintiffs’ second claim implicates
    only the DNA or Revised DNA, 9 and is not barred by the
    statute of limitations.
    ANALYSIS
    In light of the above, our task is to resolve not only
    whether the 2012 EIS was the EIS for the 2017 lease sale,
    but also how that determination should be made.
    Plaintiffs are correct that under a proper reading of our
    case law, the 2017 lease sale represented an irretrievable
    8
    To the extent Plaintiffs claim that BLM failed to take a hard look
    at information that became available after the 2012 EIS, the appropriate
    rubric would be supplementation, which Plaintiffs have waived.
    9
    We assume that without a properly tiered NEPA document
    incorporating analysis in the 2012 EIS by reference, BLM could not rely
    on any such analysis in defending a hard look challenge.
    16                   NAEC V. USDOI
    commitment of resources necessitating site-specific analysis
    in an EIS. However, we disagree with Plaintiffs’ suggestion
    that a programmatic EIS prepared for a broad-scale land use
    plan categorically cannot provide the site-specific analysis
    required for irretrievable commitments of resources. Thus,
    we reject the claim that the 2012 EIS was categorically a
    different type of EIS than what was required for the 2017
    lease sale. Furthermore, Plaintiffs fail to convince us that
    the required degree of site specificity was so clearly greater
    than that provided in the 2012 EIS that we cannot reasonably
    construe the 2012 EIS as covering future lease sales.
    Drawing from our precedents regarding the importance
    of accurately describing the action being taken, and from the
    NEPA regulations requiring agencies to properly define the
    scope of proposals which are the subject of an EIS, we
    conclude that the proper inquiry is whether the initial EIS
    defined its scope as including the subsequent action. To the
    extent the defined scope is ambiguous on this question, we
    find it appropriate to consider whether the defined scope of
    the initial EIS can be reasonably construed to include the
    subsequent action given the analysis performed therein, in
    light of applicable laws and regulations.
    Applying this framework to the facts in this case, we
    conclude that we can reasonably construe the defined scope
    of the 2012 EIS to include the 2017 lease sale. Thus, we
    defer to BLM’s position that the 2012 EIS was the EIS for
    the 2017 lease sale.
    I. Site-Specific Analysis
    We agree with Plaintiffs that the 2017 lease sale required
    some form of site-specific analysis. “The critical inquiry in
    considering the adequacy of an EIS prepared for a large
    scale, multi-step project is not whether the project’s site-
    NAEC V. USDOI                         17
    specific impact should be evaluated in detail, but when such
    detailed evaluation should occur.” California v. Block,
    
    690 F.2d 753
    , 761 (9th Cir. 1982) (emphasis added). “This
    threshold is reached when, as a practical matter, the agency
    proposes to make an ‘irreversible and irretrievable
    commitment of the availability of resources’ to a project at a
    particular site.”
    Id. (quoting Sierra Club
    v. Hathaway,
    
    579 F.2d 1162
    , 1168 (9th Cir. 1978)).
    Whether a lease is a critical decision requiring an EIS
    depends on whether the lease reserves the agency’s absolute
    right to preclude surface-disturbing activity. See Pit River
    Tribe v. U.S. Forest Serv., 
    469 F.3d 768
    , 782 (9th Cir. 2006).
    A lease that reserves an absolute right to prohibit surface-
    disturbing activities, sometimes called a “no surface
    occupancy” (NSO) lease, does not irreversibly and
    irretrievably commit any resources and therefore does not
    require a site-specific EIS.
    Id. (citing Friends of
    Southeast’s
    Future v. Morrison, 
    153 F.3d 1059
    , 1063–64 (9th Cir.
    1998)). A lease that does not retain an absolute right to
    prohibit surface-disturbing activities, even if it retains the
    right to impose mitigating conditions, constitutes an
    irreversible and irretrievable commitment of resources and
    therefore does require a site-specific EIS.
    Id. (citing Bob Marshall
    All. v. Hodel, 
    852 F.2d 1223
    , 1226–27 (9th Cir.
    1988); Conner v. Burford, 
    848 F.2d 1441
    , 1449–51 (9th Cir.
    1988)).
    For instance, in Conner, the Forest Service prepared EAs
    for the sale of oil and gas leases in the Flathead and Gallatin
    National Forests in 
    Montana. 848 F.2d at 1443
    . The EAs
    concluded that the mere sale of the leases would have no
    significant impact on the environment, largely because any
    proposed surface-disturbing activities would be subject to
    future NEPA analysis.
    Id. at 1443, 1446.
    We agreed with
    18                       NAEC V. USDOI
    the Forest Service with respect to the leases containing an
    NSO provision, but disagreed with regard to non-NSO
    leases.
    Id. at 1448, 1451.
    We explained that NSO leases
    really provide the leaseholder only a “right of first refusal,”
    that is, a priority with respect to other developers.
    Id. at 1448.
    Thus, an NSO lease “does not constitute an
    irretrievable commitment of resources.”
    Id. The opposite was
    true of the non-NSO leases.
    Id. at 1451
    (agreeing with
    Sierra Club v. Peterson, 
    717 F.2d 1409
    , 1412–15 (D.C. Cir.
    1983)).      We explained that the non-NSO leases
    “relinquish[ed] the ‘no action’ alternative,” consideration of
    which, among other “reasonable alternatives to the proposed
    action,” is the “heart” of the EIS.
    Id. NEPA did not
    allow
    the Forest Service to delay preparation of an EIS until a point
    at which the “no action” option was no longer available.
    Id. 10
    “There is no question” that NPRPA oil and gas leases
    constitute “an irretrievable commitment of resources,” and
    thus require “site specific analysis in [an] EIS.”
    
    Kempthorne, 457 F.3d at 975
    –76. However, the dispute here
    is not whether an EIS must be prepared for the leases, but
    whether an EIS has already been prepared for the leases.
    A. Programmatic EISs
    Plaintiffs appear to claim that a single document cannot
    be both a programmatic EIS for a broad-scale land
    10
    The Forest Service in Conner also argued that the non-NSO leases
    could not have a significant impact on the environment because they
    subjected future surface-disturbing activities to reasonable mitigation
    
    requirements. 848 F.2d at 1450
    . We noted that an EIS was required if
    there was even a chance that the mitigation measures would fail to reduce
    impacts to insignificance, which we thought highly likely given the
    typical scale of oil and gas activities.
    Id. NAEC V. USDOI
                             19
    management plan and also a site-specific EIS for an
    irretrievable commitment of resources. See Native Village
    of Point Hope v. Jewell, 
    740 F.3d 489
    , 497 (9th Cir. 2014)
    (distinguishing between the EIS analysis required for a
    programmatic plan that guides management of multiple-use
    resources, versus for a site-specific plan at the
    implementation stage). Plaintiffs are incorrect.
    In Block, we rejected a similar argument by the Forest
    Service that a programmatic EIS categorically “need not
    contain the type of detailed site-specific information
    normally contained in an EIS prepared for a more narrowly
    focused 
    project.” 690 F.2d at 761
    . Instead, we looked to the
    actual federal action being taken, which we concluded
    consisted of both a broad-scale management plan and a
    series of site-specific critical decisions that required site-
    specific analysis. See
    id. at 762–63.
    Though recognizing
    that a detailed site-specific analysis for a plan covering a
    very large area—in that case, a nationwide plan—would be
    difficult and involve significant uncertainty, we noted that
    “[t]he scope of the undertaking here, however, was the
    Forest Service’s choice and not the courts’.”
    Id. at 765.
    Block demonstrates that a single “federal action” for
    purposes of NEPA can be both broad-scale and site-specific,
    and can be evaluated at both of those levels in a single EIS.
    Friends of Yosemite Valley v. Norton is not to the
    contrary. 
    348 F.3d 789
    (9th Cir. 2003), clarified by 
    366 F.3d 731
    (9th Cir. 2004).         There, we concluded that a
    programmatic EIS prepared for the Merced River
    management plan did not need to include detailed site-
    specific analysis.
    Id. at 800–01.
    However, our conclusion
    regarding the required level of site specificity was tailored to
    our conclusion regarding the nature of the federal action that
    was the subject of the EIS. See
    id. Having concluded that
    20                        NAEC V. USDOI
    the management plan provided only broad guidelines and
    made no irreversible and irretrievable commitment of
    resources, we held that the EIS “contain[ed] sufficiently
    specific data and information for [its] purpose.”
    Id. at 801.
    Friends of Yosemite Valley does not dictate that any EIS
    labeled “programmatic” or covering a broad-scale
    management plan cannot also cover site-specific actions and
    the impacts thereof where appropriate.
    In Kempthorne, BLM had prepared a combined IAP and
    EIS to open parts of the Reserve within the Northwest
    Planning Area to oil and gas 
    leasing. 457 F.3d at 973
    –74;
    see NAEC v. Norton, 
    361 F. Supp. 2d 1069
    , 1072 (D. Alaska
    2005). The EIS conducted its analysis on a scale similar to
    that of the 2012 EIS here, using “hypothetical future
    projections of what might be undertaken in the exploration
    and development phases” to analyze impacts “on a resource
    by resource basis,” while “not attempt[ing] to examine the
    impact on specific 
    parcels.” 457 F.3d at 974
    . In evaluating
    the adequacy of that EIS, we treated it as equally covering
    “the leases” and “the leasing program.”
    Id. at 976.
    Plaintiffs
    had challenged the EIS specifically on the assumption that it
    covered both “planning decisions and site specific . . .
    resource commitments,” i.e., both the IAP and the individual
    
    leases. 361 F. Supp. 2d at 1078
    . Plaintiffs argued that the
    EIS was inadequate because, while it did provide the
    programmatic analysis necessary for planning decisions, it
    did not provide the site-specific analysis required for
    resource commitments. 11
    Id. Although we did
    not consider
    the question directly, Kempthorne provides strong support
    for the conclusion that nothing legally precludes BLM from
    11
    Here, Plaintiffs take a different approach by arguing that the 2012
    EIS simply “was” a programmatic EIS for the IAP, and “was not” a site-
    specific EIS for a lease sale.
    NAEC V. USDOI                          21
    analyzing both an IAP and NPRPA lease sales in the same
    EIS.
    In sum, nothing in NEPA or our caselaw prevents
    agencies from using a single document to undertake both a
    programmatic-level analysis and a site-specific analysis at
    the level appropriate for any irretrievable commitments of
    resources. Thus, the fact that the 2012 EIS provided a
    programmatic-level analysis for the IAP does not preclude
    the legal possibility that it also served as the necessary site-
    specific analysis for future lease sales.
    B. Degree of Site Specificity
    Theoretically, one could argue that the 2012 EIS could
    not have been the NEPA analysis for the 2017 lease sale if
    NEPA clearly required a significantly greater degree of site
    specificity for the analysis of NPRPA lease sales than was
    provided in the 2012 EIS. However, we are not persuaded
    that NEPA so required.
    The question of whether any site-specific analysis is
    required, addressed above, is different from the question of
    what “degree of site specificity” is required. 
    Kempthorne, 457 F.3d at 976
    . “The detail that NEPA requires in an EIS
    depends upon the nature and scope of the proposed action.”
    
    Block, 690 F.2d at 761
    . “If it is reasonably possible to
    analyze the environmental consequences” of a particular
    type at a particular stage, “the agency is required to perform
    that analysis.” 
    Kern, 284 F.3d at 1072
    (requiring analysis of
    foreseeable impacts to particular species at the resource
    management plan stage, notwithstanding that those impacts
    could be analyzed more precisely at a later site-specific
    project stage). “We will defer to the agency’s judgment
    about the appropriate level of analysis so long as the EIS
    provides as much environmental analysis as is reasonably
    22                       NAEC V. USDOI
    possible under the circumstances, thereby ‘provid[ing]
    sufficient detail to foster informed decision-making’ at the
    stage in question.” Native Village of Point 
    Hope, 740 F.3d at 498
    (quoting Friends of Yosemite 
    Valley, 348 F.3d at 800
    ).
    Thus, when an oil and gas lease constitutes an
    “irretrievable commitment of resources,” the required
    degree of analytical site specificity depends on the
    specificity of the “reasonably foreseeable” environmental
    impacts in light of the factual context. New Mexico ex rel.
    Richardson v. BLM, 
    565 F.3d 683
    , 718 (10th Cir. 2009). For
    instance, in Richardson, the challenged lease pertained to a
    relatively small parcel (less than 2,000 acres);
    “[c]onsiderable exploration ha[d] already occurred on
    parcels adjacent to the [leased parcel]”; “a natural gas supply
    [was] known to exist beneath these parcels”; and the record
    contained sufficient information on which to predict the
    number of wells that the leaseholder would want to
    construct.
    Id. at 717–18.
    Given these facts, the Tenth
    Circuit concluded that “the impacts of this planned gas field
    were reasonably foreseeable before the . . . lease was
    issued.”
    Id. at 718.
    By contrast, in Kempthorne, we held that the plaintiffs’
    “particular challenge to site specificity lack[ed] merit”
    because “parcel by parcel” effects were “currently
    unidentifiable” given the facts at hand. 
    12 457 F.3d at 977
    .
    12
    We reasoned in part that “NEPA could never be satisfied” if BLM
    had to conduct “an analysis of the environmental effect with respect to
    each parcel involved in a possible lease for exploration and
    development,” because “until the lessees do exploratory work, the
    government cannot know what sites will be deemed most suitable for
    exploratory drilling, much less for 
    development.” 457 F.3d at 976
    .
    However, we did not address Conner’s admonition that the agency could
    avoid this difficulty by issuing non-NSO leases. 
    See 848 F.2d at 1451
    .
    NAEC V. USDOI                               23
    Though acknowledging that some degree of site-specific
    analysis was required, 13 we upheld BLM’s method of using
    “hypothetical situations that represented the spectrum of
    foreseeable results” as a way of analyzing oil and gas leasing
    in the Reserve’s Northwest Planning 
    Area. 457 F.3d at 976
    .
    We find the facts in this case bear a far greater
    resemblance to those in Kempthorne than those in
    Richardson. Accordingly, Kempthorne dictates that the type
    of analysis employed in the 2012 EIS may qualify as the site-
    specific analysis required of a critical decision given
    appropriate factual circumstances. As Plaintiffs urge,
    Nevertheless, Kempthorne is not inconsistent with Conner. We
    understand the “hypothetical situations” analysis in the Kempthorne 
    EIS, 457 F.3d at 976
    , to have satisfied Conner’s requirement to “estimate
    what [the] effects might 
    be,” 848 F.2d at 1450
    .
    13
    Native Village of Point Hope does not contradict this
    interpretation of Kempthorne. See Native Village of Point 
    Hope, 740 F.3d at 493
    –94 (“An agency is not required at the lease sale stage
    to analyze potential environmental effects on a site-specific level of
    detail.” (citing 
    Kempthorne, 457 F.3d at 975
    –76)). Native Village of
    Point Hope involved the Outer Continental Shelf Lands Act (OSCLA),
    43 U.S.C. §§ 1331–1356.
    Id. Under OSCLA, a
    lease conveys “no right
    to proceed with full exploration, development, or production . . . [but
    rather] only a priority in submitting plans to conduct these activities.”
    Tribal Village of Akutan v. Hodel, 
    869 F.2d 1185
    , 1187–88 (9th Cir.
    1988) (quoting Sec’y of the Interior v. California, 
    464 U.S. 312
    , 339
    (1984)). Thus, OSCLA leases are necessarily NSO leases, and unlike
    those at issue in this case. Accordingly, we had no occasion in Native
    Village of Point Hope to consider the nuance Plaintiffs assert regarding
    the difference between site-specific analysis, which Kempthorne
    acknowledged was required to some degree, and parcel-by-parcel
    analysis, which Kempthorne rejected as impossible at the NPRPA
    leasing stage. In any event, NPRPA leases were not before us in Native
    Village of Point Hope, so we could not have decided their requirements.
    Because OSCLA leases appear to be NSO leases by statute, our
    statement was accurate for the purposes at hand.
    24                    NAEC V. USDOI
    Kempthorne does not preclude the theoretical possibility that
    some greater degree of site specificity (even if not parcel-by-
    parcel) was “reasonably possible,” 
    Kern, 284 F.3d at 1072
    ,
    or that more site-specific impacts were “reasonably
    foreseeable,” 
    Richardson, 565 F.3d at 718
    , than that
    conducted or those analyzed in the 2012 EIS. However,
    because we ultimately conclude that the 2012 EIS covered
    future lease sales, the NPRPA statute of limitations makes it
    unnecessary for us to resolve whether BLM employed the
    precise degree of site specificity required. While we agree
    with Plaintiffs that some degree of site-specific EIS analysis
    is required for NPRPA leases, we are not persuaded that the
    degree required for the 2017 lease sale was so clearly greater
    than that reflected in the 2012 EIS that the 2012 EIS could
    not have covered the 2017 lease sale.
    II. Subsequent Actions
    We next consider other potential methods for
    determining NEPA’s requirements for an action that is
    separated from an EIS by the passage of time.
    As background, NEPA regulations provide two
    frameworks within which additional NEPA analysis may
    occur after an initial EIS is finalized: namely, tiering and
    supplementation. Tiering refers to the incorporation by
    reference in subsequent EISs or EAs, which concentrate on
    issues specific to the current proposal, of previous broader
    EISs that cover matters more general in nature. 40 C.F.R.
    § 1508.28. Supplementation refers to the process of
    updating a previous EIS in situations where the agency
    makes substantial changes to the proposed action, or there
    are significant new circumstances or information.
    Id. § 1502.9(c). The
    NEPA regulations do not provide any
    express guidance for determining whether to prepare a tiered
    NEPA analysis or a supplemental NEPA analysis in
    NAEC V. USDOI                               25
    borderline cases. See Daniel R. Mandelker et al., NEPA Law
    & Litig. § 9:12 (2d ed., Aug. 2019 update).
    A. NEPA Adequacy
    To support their respective contentions about what type
    of NEPA analysis was required for the 2017 lease sale,
    Plaintiffs and Defendants rely in part on cases which imply
    that the relevant inquiry is whether the previous EIS
    adequately analyzed the impacts of the subsequent action.
    We decline to take this approach.
    In Blue Mountains Biodiversity Project v. Blackwood,
    we concluded that the Forest Service’s previous
    programmatic forest plan EIS did not obviate the need for an
    EIS for several proposed timber salvage sales in an area
    burned by a large wildfire. 
    161 F.3d 1208
    , 1210, 1214 (9th
    Cir. 1998). The Forest Service argued that its EA for one of
    the salvage sales was sufficient given that it tiered to the
    forest plan EIS for additional analysis.
    Id. at 1214.
    We
    disagreed, finding that the forest plan EIS analysis was
    inadequate because it “d[id] not, and could not, evaluate the
    impacts of this catastrophic fire, or the additional
    environmental impacts that large scale logging of severely
    burned areas could bring.”
    Id. Plaintiffs here also
    allege
    significant developments that could not have been evaluated
    in the 2012 EIS because they did not take place until later.
    Our decision in Blue Mountains is of little utility to us in
    evaluating this case, however, because the fact that the
    proposed timber salvage sales constituted a new project was
    not in dispute. 14 Instead, the dispute focused on whether the
    14
    Furthermore, the timber salvage sales involved surface-disturbing
    activities, making them more analogous to oil and gas permits for
    exploration or development than to oil and gas leases.
    Id. at 1210. 26
                      NAEC V. USDOI
    EA for the new project contained sufficient analysis. Here,
    BLM did not prepare a contemporary NEPA analysis (such
    as an EA) for the 2017 lease sale. Rather, BLM argues that
    the 2012 EIS did contemplate the 2017 lease sale and already
    performed the necessary analysis.
    In Pit River Tribe, the plaintiffs challenged a 1998
    geothermal lease extension in the volcanic Medicine Lake
    Highlands in California. The agencies involved had
    prepared a nationwide programmatic EIS in 1973, which
    “d[id] not adequately address the potential impacts of
    
    leasing.” 469 F.3d at 783
    . Subsequently, the agencies
    prepared EAs in 1981 and 1984 which considered leases but
    did not consider the impacts of “actual geothermal
    development.”
    Id. at 784.
    The agencies then issued leases
    in 1988 which did not reserve an absolute right to prohibit
    development.
    Id. Because the statute
    of limitations had run,
    the plaintiffs challenged only the 1998 extensions of those
    leases, and not the original 1988 leases.
    Id. at 781.
    The
    agencies argued that they had completed the required NEPA
    analysis in 1973, 1981, and 1984.
    Id. We disagreed, and
    concluded that the agencies were required to prepare a new
    EIS for the 1998 lease extensions.
    Id. at 784.
    Pit River Tribe illustrates that the adequacy of analysis
    in previous NEPA documents for the present action may
    influence whether we construe those NEPA documents as
    covering the present action. Relatedly, Pit River Tribe
    shows that adequacy may remain relevant even after the
    statute of limitations has run. However, it appears that the
    agencies in Pit River Tribe conceded that the lease
    extensions constituted a new action, arguing rather that a
    new NEPA analysis was unnecessary because the leases only
    maintained the status quo. See
    id. We held that
    the
    extensions did not simply maintain the status quo because
    NAEC V. USDOI                         27
    they granted a new right to additional years of development
    which had not been granted previously.
    Id. In Mayo v.
    Reynolds, the D.C. Circuit considered a
    NEPA claim where the plaintiff alleged that the National
    Park Service “was required to issue a new EA or EIS” for
    each year’s proposed elk hunting authorization pursuant to a
    fifteen-year elk-reduction program in Grand Teton National
    Park. 
    875 F.3d 11
    , 14, 19 (D.C. Cir. 2017). The Park
    Service argued that it had prepared the required analysis in
    an initial EIS for the entire fifteen-year program, and the
    court agreed.
    Id. at 14–15.
    The court endorsed the Park
    Service’s assertion that although NEPA requires agencies to
    take a “hard look” at environmental impacts, NEPA “does
    not . . . require the agency to take a new look every time it
    takes a step that implements a previously-studied action, so
    long as the impacts of that step were contemplated and
    analyzed by the earlier analysis.”
    Id. The court concluded
    that the original EIS had already taken a hard look at all the
    potential impacts associated with each year’s hunt.
    Id. at 21.
    Our concern with relying on NEPA adequacy as the sole
    determinant of whether an action requires a “new look,” as
    Mayo puts it, is that this robs the statute of limitations of
    effect in certain situations. Specifically, the statute of
    limitations becomes meaningless where some steps of a
    previously studied action remain to occur after expiration of
    the limitations period. Such a result might discourage
    agencies from bothering to prepare EISs that contemplate the
    entirety of a multi-step, long-term project at all, contrary to
    NEPA’s goals that agencies analyze connected and
    cumulative actions as much as possible in one EIS. See
    40 C.F.R. § 1508.25(a). Nor are we satisfied with saying
    that, if the relevant inquiry is whether the initial EIS was
    adequate, the statute of limitations simply bars the inquiry.
    28                    NAEC V. USDOI
    B. Underlying Plan or Program
    Another approach is to look not at the initial NEPA
    analysis, but at the underlying plan or program. For
    instance, in Mayo, the D.C. Circuit relied in part on its
    conclusion that the plaintiff had not shown that the hunting
    authorizations deviated in any significant way from the
    fifteen-year 
    program. 875 F.3d at 21
    . While we agree that
    conformity with the initially analyzed plan or program is
    relevant to NEPA requirements, we do not think it sufficient
    to answer our question here. After all, the tiering regulations
    generally assume that the subsequent site-specific action is
    consistent with the previously studied broad-scale plan.
    “Nothing in the tiering regulations suggests that the
    existence of a programmatic EIS for a [regionwide
    management] plan obviates the need for any future project-
    specific EIS, without regard to the nature or magnitude of a
    project.” Blue 
    Mountains, 161 F.3d at 1214
    . Moreover, a
    focus on plan compliance fails to account for whether
    members of the public have fair notice of when they should
    challenge the NEPA compliance of a particular action.
    We also reject Plaintiffs’ argument that Norton v.
    Southern Utah Wilderness Alliance (SUWA) dictates that
    any action occurring after the adoption of a land use
    management plan is necessarily a new action subject to the
    tiering rubric. 
    542 U.S. 55
    (2004). In SUWA, the plaintiffs
    argued that BLM was required to supplement its previous
    NEPA analysis for land use plans governing off-road vehicle
    use on public lands in Southern Utah because there was new
    evidence available that such use had substantially increased.
    See
    id. at 61.
    The Supreme Court held that supplemental
    NEPA analysis can be required only where “there remains
    ‘major Federal actio[n]’ to occur.”
    Id. at 73
    (quoting Marsh
    v. Or. Nat. Res. Council, 
    490 U.S. 360
    , 374 (1989)). In the
    NAEC V. USDOI                        29
    circumstances of that case, the Court explained that the
    original EIS supported BLM’s adoption of a land use plan,
    and that “that action [was] completed when the plan [was]
    approved.”
    Id. There was thus
    “no ongoing ‘major Federal
    action’ that could require supplementation (though BLM is
    required to perform additional NEPA analyses if a plan is
    amended or revised).”
    Id. (citations omitted). Plaintiffs
    argue that SUWA dictates that the 2012 EIS
    covered only the adoption of the IAP, and that
    supplementation is not the appropriate framework for
    evaluating this case because Plaintiffs do not ask for an
    amendment to the IAP. But the circumstances here are
    different than in SUWA. In SUWA, BLM did not claim to be
    engaged in an ongoing action supported by the original
    NEPA analysis; what the plaintiffs challenged was BLM’s
    inaction. See
    id. at 61, 72–73.
    NEPA supplementation
    regulations did not require BLM to initiate a proposal for
    new action, such as amending the plans. See
    id. at 73.
    Here,
    BLM does argue that it is engaged in an ongoing action
    supported by the 2012 EIS, to which the NEPA
    supplementation regulations apply. Nothing in SUWA
    precludes BLM from structuring its activities in this way.
    C. Defined Scope
    In light of our concerns regarding the statute of
    limitations and the need for fair notice, we look instead to
    whether the initial EIS purported to be the EIS for the
    subsequent action.
    Our precedents support looking to the language of the
    EIS to help us form “an accurate description of the
    [agency’s] proposed action.” Friends of Yosemite 
    Valley, 348 F.3d at 801
    ; see also 
    Block, 690 F.2d at 761
    (“The
    starting point in our analysis is ‘to describe accurately the
    30                    NAEC V. USDOI
    “federal action” being taken.’” (quoting Aberdeen &
    Rockfish R.R. Co. v. Students Challenging Regulatory
    Agency Procedures (S.C.R.A.P.), 
    422 U.S. 289
    , 322
    (1975))). For instance, in NAEC v. Lujan, plaintiffs
    challenged the adequacy of the National Park Service’s EISs
    regarding mining in three national parks in Alaska, arguing
    that the EISs contained insufficiently site-specific analysis
    given the agency’s decision to authorize mining operations.
    See 
    961 F.2d 886
    , 887, 890 (9th Cir. 1992). We rejected
    plaintiffs’ characterization of the federal action, relying on
    the EISs’ own description that “[i]f, however, the National
    Park Service determines that the impacts of proposed mining
    operations would violate the decision standards for plan of
    operations approval, and the effects could not be sufficiently
    mitigated, the plan would be disapproved.”
    Id. at 890
    (citation omitted). We thus concluded that no irreversible
    and irretrievable commitment of resources had occurred.
    Id. Similarly, the D.C.
    Circuit in Mayo relied on the EIS’s
    statement that its “level of analysis [was] sufficient to allow
    several management actions to be carried out without having
    to complete additional environmental analyses (e.g.,
    environmental assessments) prior to 
    implementation.” 875 F.3d at 18
    . The court factored this EIS statement into
    its ultimate determination that the Park Service was not
    required to prepare “additional environmental analyses (e.g.,
    environmental assessments)” prior to each year’s elk hunt.
    See
    id. Furthermore, the NEPA
    regulations emphasize the need
    for EISs to carefully define the proposal(s) under
    consideration, and specify detailed criteria to be consulted in
    the process. For example, the regulations provide that:
    Agencies shall make sure the proposal which
    is the subject of an environmental impact
    NAEC V. USDOI                       31
    statement is properly defined. Agencies shall
    use the criteria for scope (§1508.25) to
    determine which proposal(s) shall be the
    subject of a particular statement. Proposals
    or parts of proposals which are related to each
    other closely enough to be, in effect, a single
    course of action shall be evaluated in a single
    impact statement.
    40 C.F.R. § 1502.4(a). The regulations further specify that
    the following types of actions “should” be included within
    the scope of a single EIS:
    (1) “Connected actions,” meaning actions
    that:
    (i)     “Automatically     trigger   other
    actions,”
    (ii)    “Cannot or will not proceed”
    without other actions, or
    (iii)   “Are interdependent parts of a
    larger action and depend on the
    larger      action  for    their
    justification”; and
    (2) “Cumulative actions,” meaning actions
    that have cumulatively significant
    impacts.
    Id. § 1508.25(a). A
    third category, “Similar actions,” “may”
    be included within the scope of a single EIS.
    Id. Agencies must use
    a public “scoping” process to decide the scope of
    “actions, alternatives, and impacts to be considered in an
    environmental impact statement.”
    Id. §§ 1501.7, 1508.25.
    32                        NAEC V. USDOI
    Thus, in deciding whether a previous EIS is the EIS for
    a subsequent action, we find it appropriate to rely on an
    EIS’s defined scope. If the defined scope of the initial EIS
    included the subsequent action, NEPA requirements for the
    subsequent action would fall under the supplementation
    rubric. If the defined scope of the initial EIS did not include
    the subsequent action (but presumably the analysis in the
    initial EIS is to some extent relevant), NEPA requirements
    for the subsequent action would fall under the tiering
    rubric. 15 Of course, we recognize that the defined scope of
    the initial EIS may be ambiguous with regard to whether it
    does or does not include the precise subsequent action at
    issue. Applying our standard of review, we must determine
    whether the agency’s interpretation of the scope is
    reasonable. Ka 
    Makani, 295 F.3d at 959
    & n.3.
    Although the adequacy of the initial EIS for purposes of
    the subsequent action may be relevant in an extreme case,
    where the inadequacy of analysis is so clear as to
    demonstrate that the scope of the initial EIS cannot
    reasonably be construed as including the subsequent action,
    we do not think our scope inquiry constitutes “judicial
    review of the adequacy” of the initial EIS within the meaning
    of the NPRPA statute of limitations.               42 U.S.C.
    § 6506a(n)(1). It cannot reach the adequacy of the initial EIS
    for those actions actually within its scope.
    15
    These two frameworks are not mutually exclusive. If an agency
    wishes to tier a new NEPA analysis to a previous NEPA analysis, the
    agency may have to take into account whether the previous NEPA
    analysis requires supplementation. Also, we are not aware of anything
    that would prevent an agency from performing the analysis required by
    the tiering regulations in a document styled as a supplement to a previous
    NEPA analysis.
    NAEC V. USDOI                              33
    III.    Application
    We next undertake to determine how the 2012 EIS
    defined its own scope. The 2012 EIS abstract identifies the
    “Proposed Action” as the “National Petroleum Reserve-
    Alaska Integrated Activity Plan/Environmental Impact
    Statement,” which it states “is designed to determine the
    appropriate management of all BLM-managed lands in the
    [Reserve].” Under the heading, “What is BLM proposing to
    do in this plan?” the Executive Summary similarly states that
    BLM completed the combined IAP and EIS “to determine
    the appropriate management of the BLM-administered lands
    (public lands) in the nearly 23-million-acre Petroleum
    Reserve.” It further highlights that “[a]mong the most
    important decisions the BLM will make through this plan is
    what lands should be made available for oil and gas leasing
    and with what protections for surface resources and uses.”
    The section of the Introduction entitled “Scoping and Issues”
    does not clearly articulate the “range of actions . . . to be
    considered.” 40 C.F.R. § 1508.25. As relevant here, it says
    only that “[t]he plan will examine a range of alternatives for
    oil and gas leasing and development.” We find all these
    high-level summaries are ambiguous as to whether the
    “proposal which is the subject of” the EIS is merely to
    designate certain lands as available for leasing, with actual
    lease sale decisions to be proposed and analyzed at a later
    point, or if the subject proposals include the actual offerings
    and sales of the leases. 16 40 C.F.R. § 1502.4(a).
    16
    Similarly, Chapter 2 of the 2012 EIS, which describes the
    Alternatives under consideration, explains that under “[a]ll of the
    alternatives,” “BLM has discretion to offer for lease in any given lease
    sale all or only some of the unleased lands that, based on the existing
    IAP decision document, are available for leasing.” This language too is
    34                       NAEC V. USDOI
    However, a section of the Introduction regarding
    “Requirements for Further Analysis” provides somewhat
    greater guidance. This section states that “BLM anticipates
    that this IAP/EIS will fulfill the NEPA requirements for the
    first oil and gas lease sale.” As to future lease sales, it states
    that “[p]rior to conducting each additional sale, the agency
    would conduct a determination of the existing NEPA
    documentation’s adequacy. If the BLM finds its existing
    analysis to be adequate for a second or subsequent sale, the
    NEPA analysis for such sales may require only an
    administrative determination of NEPA adequacy.” It then
    contrasts future “actions,” such as a “proposed exploratory
    drilling plan,” which “would require further NEPA analysis”
    based on the specifics of the proposal.
    By stating that future lease sales might require only an
    “administrative determination of NEPA adequacy,” as
    opposed to “further NEPA analysis,” this section implies
    that future leases are within the scope of the 2012 EIS. A
    DNA could suffice only if the relevant question was whether
    the lease sale required a supplemental EIS. See Idaho
    Sporting Congress Inc. v. Alexander, 
    222 F.3d 562
    , 566 (9th
    Cir. 2000) (recognizing a “limited role” for non-NEPA
    evaluation procedures “for the purpose of determining
    whether new information or changed circumstances require
    the preparation of a supplemental EA or EIS”). If the
    relevant question was whether the lease sale required its own
    EIS, we assume BLM would have to prepare at least a tiered
    EA to make this determination. Likewise, the fact that this
    section does not describe future lease sales as future
    “actions” implies that future lease sales are components of
    ambiguous as to whether those discretionary lease sale offerings are an
    aspect of the alternative proposals under consideration, or whether they
    are distinct future actions subject to independent NEPA requirements.
    NAEC V. USDOI                          35
    the action that is the subject of the 2012 EIS. Finally, the
    fact that this section claims that the 2012 EIS will entirely
    fulfill the NEPA requirements for the first lease sale suggests
    that all lease sales are within the scope of the subject action,
    with the only potential trigger for additional NEPA analysis
    being new information or circumstances arising before
    subsequent sales—i.e., factors potentially requiring
    supplementation. See 40 C.F.R. § 1502.9(c).
    As Plaintiffs point out, the 2012 EIS does not analyze the
    impacts of any proposal for when to offer which particular
    tracts of land for leasing, let alone alternative proposals that
    vary by location, amount, or timing. However, we think this
    is a criticism better directed at whether BLM considered
    adequate alternatives in 2012 EIS, than at whether BLM
    considered future lease sales at all. We see nothing in NEPA
    that would in principle prevent BLM from analyzing a
    proposed authorization of multiple, entirely discretionary
    lease sales. Cf. 
    Mayo, 875 F.3d at 20
    –22 (rejecting
    plaintiffs’ argument that EIS for fifteen-year plan could not
    satisfy EIS requirement for each year’s elk hunt because it
    did not analyze the “timing, location, restrictions, and . . .
    potential alternatives” for each hunt). Had Plaintiffs brought
    a timely challenge against the 2012 EIS, they could have
    argued that NEPA required consideration of a reasonable
    alternative authorization of multiple lease sales that
    employed particular criteria regarding how many and which
    tracts to offer when. See 
    Kempthorne, 457 F.3d at 978
    .
    Furthermore, to the extent the minimal degree of site
    specificity in the 2012 EIS might suggest that lease sales
    were not within its scope, we have already rejected that
    argument. Even if Kempthorne does not foreclose the
    possibility that proper analysis of non-NSO NPRPA leases
    requires some greater degree of site specificity than that
    provided in the 2012 EIS, we are not persuaded that the
    36                    NAEC V. USDOI
    difference (if any) is so great as to make it unreasonable to
    construe the scope of the 2012 EIS to include such leases.
    Although the expressly defined scope of the 2012 EIS is
    somewhat ambiguous as to the question before us, we find
    that the language regarding future NEPA requirements
    provides reasonable notice that the intended scope
    encompassed the actual lease sales. Furthermore, we do not
    find it unreasonable to construe the scope of the 2012 EIS as
    such when considering the analysis performed therein and
    the law applicable to non-NSO NPRPA leases. Thus, we
    defer to BLM’s reasonable position that the 2012 EIS was
    the EIS for the 2017 lease sale. See Ka 
    Makani, 295 F.3d at 959
    & n.3.
    Accordingly, Plaintiffs’ first and third claims fail on the
    merits. BLM did not violate NEPA or its own NPRPA
    regulations by failing to prepare a NEPA analysis for the
    2017 lease sale before the 2017 lease sale took place,
    because BLM prepared the required NEPA analysis in 2012.
    The 2017 lease sale offering did not require a new tiered or
    stand-alone NEPA analysis.
    Furthermore, because we conclude that the 2012 EIS was
    the EIS for the 2017 lease sale, Plaintiffs’ second claim,
    alleging that BLM failed to take a hard look at the impacts
    of the 2017 lease sale, is time barred in part and waived in
    the remainder. The NPRPA statute of limitations prevents
    us from inquiring whether the 2012 EIS took a sufficiently
    hard look at the impacts of the 2017 lease sale. Following
    the 2012 EIS, BLM’s only remaining hard look obligation
    with respect to the 2017 lease sale was to analyze new
    circumstances and new information under the
    supplementation rubric. See 40 C.F.R. § 1502.9(c). Because
    Plaintiffs have disavowed a supplementation claim, we
    consider this issue waived.
    NAEC V. USDOI                       37
    CONCLUSION
    For the foregoing reasons, we affirm the district court’s
    grant of summary judgment in favor of Defendants.
    AFFIRMED.
    

Document Info

Docket Number: 19-35008

Filed Date: 12/22/2020

Precedential Status: Precedential

Modified Date: 12/22/2020

Authorities (25)

Northern Alaska Environmental Center v. Norton , 361 F. Supp. 2d 1069 ( 2005 )

New Mexico Ex Rel. Richardson v. BLM , 565 F.3d 683 ( 2009 )

pit-river-tribe-native-coalition-for-medicine-lake-highlands-defense-mount , 469 F.3d 768 ( 2006 )

turtle-island-restoration-network-ka-iwa-kua-lele-center-for-biological , 438 F.3d 937 ( 2006 )

High Sierra Hikers Association v. Blackwell , 390 F.3d 630 ( 2004 )

state-of-california-v-john-r-block-in-his-official-capacity-as , 690 F.2d 753 ( 1982 )

The Sierra Club v. Stanley K. Hathaway , 579 F.2d 1162 ( 1978 )

friends-of-southeasts-future-sitka-conservation-society-and-southeast , 153 F.3d 1059 ( 1998 )

friends-of-yosemite-valley-a-non-profit-corporation-mariposans-for , 366 F.3d 731 ( 2004 )

james-r-conner-v-robert-burford-director-bureau-of-land-management , 848 F.2d 1441 ( 1988 )

blue-mountains-biodiversity-project-blue-mountain-native-forest-alliance , 161 F.3d 1208 ( 1998 )

bob-marshall-alliance-v-donald-p-hodel-secretary-of-the-interior-and , 852 F.2d 1223 ( 1988 )

idaho-sporting-congress-inc-the-ecology-center-v-david-alexander , 222 F.3d 562 ( 2000 )

ka-makani-o-kohala-ohana-inc-a-hawaii-nonprofit-corporation-v-water , 295 F.3d 955 ( 2002 )

Sierra Club v. R. Max Peterson, in His Official Capacity as ... , 717 F.2d 1409 ( 1983 )

northern-alaska-environmental-center-sierra-club-inc-denali-citizens , 961 F.2d 886 ( 1992 )

northcoast-environmental-center-klamath-forest-alliance-siskiyou-regional , 136 F.3d 660 ( 1998 )

Aberdeen & Rockfish R. Co. v. Students Challenging ... , 95 S. Ct. 2336 ( 1975 )

Kleppe v. Sierra Club , 96 S. Ct. 2718 ( 1976 )

Marsh v. Oregon Natural Resources Council , 109 S. Ct. 1851 ( 1989 )

View All Authorities »