Backcountry Against Dumps v. Sally Jewell , 674 F. App'x 657 ( 2017 )


Menu:
  •                            NOT FOR PUBLICATION                             FILED
    UNITED STATES COURT OF APPEALS                          JAN 05 2017
    MOLLY C. DWYER, CLERK
    FOR THE NINTH CIRCUIT                        U.S. COURT OF APPEALS
    BACKCOUNTRY AGAINST DUMPS                        No.   13-57129
    and DONNA TISDALE,
    D.C. No.
    Plaintiffs-Appellants,             3:12-cv-02211-GPC-PCL
    v.
    MEMORANDUM*
    SALLY JEWELL, in her official capacity
    as Secretary of the United States
    Department of the Interior; et al.,
    Defendants-Appellees,
    OCOTILLO EXPRESS, LLC and
    PATTERN ENERGY GROUP, LP,
    Intervenor-Defendants-
    Appellees.
    Appeal from the United States District Court
    for the Southern District of California
    Gonzalo P. Curiel, District Judge, Presiding
    Argued and Submitted November 3, 2015
    Pasadena, California
    Before: FARRIS, BYBEE, and N.R. SMITH, Circuit Judges.
    *
    This disposition is not appropriate for publication and is not precedent
    except as provided by Ninth Circuit Rule 36-3.
    Backcountry Against Dumps and Donna Tisdale (“Appellants”) appeal the
    district court’s order granting summary judgment in favor of Appellees.
    Appellants maintain that the Bureau of Land Management (“BLM”) violated (1)
    the Federal Land Policy and Management Act (“FLPMA”) in failing to comply
    with the California Desert Conservation Area (“CDCA”) Plan, and (2) the National
    Environmental Policy Act (“NEPA”) when it granted Ocotillo Express, LLC
    (“Ocotillo”) a right of way to construct and operate the Ocotillo Wind Energy
    Facility (“OWEF Project” or “the Project”) near Ocotillo, California. We may
    affirm a district court’s grant of summary judgment “on any basis supported by the
    record.” Gordon v. Virtumundo, Inc., 
    575 F.3d 1040
    , 1047 (9th Cir. 2009).
    Because the parties are familiar with the facts and procedural history of this case,
    we will not recount them here.
    1. Appellants first contend the BLM violated the CDCA Plan by failing to
    determine whether the OWEF Project met the substantive requirements the Plan
    imposes on proposed uses of Class L land—the class of land upon which the
    OWEF Project is located. The CDCA Plan governs all land use activities within
    the CDCA. Because the OWEF Project is located on CDCA land, the BLM was
    required to ensure the Project complied with the Plan before granting the right-of-
    way. Significantly, the CDCA Plan includes a Plan amendment process that allows
    2
    the BLM to make changes to the CDCA Plan for a multitude of reasons, including
    accommodating a specific project that might not otherwise comply with the CDCA
    Plan. See BLM, California Desert Conservation Area Plan 1980, as amended, at
    119 (Mar. 1999) [hereinafter CDCAP].
    In the Record of Decision granting a right-of-way for the OWEF Project, the
    BLM adopted a Category 3 Plan amendment to accommodate the Project. See
    BLM, Record of Decision Ocotillo Wind Energy Facility and Amendment to the
    California Desert Conservation Area Plan, at 39 (May 2012). The BLM amended
    the CDCA Plan to designate the approximately 10,151 acres of public land where
    the Project was to be located as suitable for wind energy development. 
    Id. at 1.
    A Category 3 amendment “accommodate[s] a request for a specific use or
    activity [that] will require additional analysis” of its own. CDCAP, at 119. A
    Category 3 amendment, like a zoning variance, allows the BLM to carve out an
    exception to the CDCA Plan for a specific use or activity. 
    Id. Once the
    BLM
    determines that a specific project warrants a Category 3 amendment, that project is
    no longer required to comply with the substantive requirements of the class of land
    on which the project is sited. Rather, the project is governed by the Plan
    amendment.
    3
    When considering a Category 3 amendment, the District Manager begins by
    evaluating the “additional analysis” specific to the use or activity for which the
    amendment is requested. 
    Id. at 121.
    This additional analysis is generally an
    Environmental Impact Statement (“EIS”); therefore, a Category 3 amendment does
    not require its own EIS. 
    Id. at 119,
    121. If the District Manager approves, he or
    she recommends the amendment to the State Director. 
    Id. at 121.
    If the State
    Director agrees, the District Manager renders a decision and issues a public notice
    of the amendment decision that clearly explains how the CDCA Plan would be
    changed by the amendment. 
    Id. The BLM
    must then allow thirty days for the
    public to object to the amendment. 
    Id. After resolving
    the objections, the BLM
    may approve the amendment. 
    Id. The District
    Manager also has a series of six
    determinations and obligations that must be completed before the amendment can
    be approved. 
    Id. The BLM
    substantially complied with this process.
    Once the BLM adopted this Category 3 amendment to accommodate the
    OWEF Project, the Project was no longer required to comply with the multiple-use
    class designations, guidelines, or elements for Class L land. Therefore, even if we
    agree with Appellants that the BLM failed to determine whether the OWEF Project
    met the substantive requirements the Plan imposes on proposed uses of Class L
    land, we must nevertheless conclude that the Project did not violate the CDCA
    4
    Plan. The Project was governed by the Plan amendment rather than the Plan itself.
    Accordingly, we affirm the district court’s grant of summary judgment finding that
    the BLM did not violate the CDCA Plan.
    2. “NEPA requires agencies considering ‘major Federal actions significantly
    affecting the quality of the human environment’ to prepare and issue an
    environmental impact statement.” Oregon Nat. Res. Council Fund v. Brong, 
    492 F.3d 1120
    , 1132 (9th Cir. 2007) (quoting 
    42 U.S. C
    . § 4332(2)(C)). An EIS must
    “provide full and fair discussion of significant environmental impacts and shall
    inform decisionmakers and the public of the reasonable alternatives which would
    avoid or minimize adverse impacts or enhance the quality of the human
    environment.” 40 C.F.R. § 1502.1. We review an EIS “to ensure that the agency
    has taken a ‘hard look’ at the potential environmental consequences of [a]
    proposed action.” Klamath-Siskiyou Wildlands Ctr. v. Bureau of Land Mgmt., 
    387 F.3d 989
    , 993 (9th Cir. 2004).
    The BLM prepared and issued an EIS for the OWEF Project. Appellants
    contend that this EIS was inadequate, and thus violated NEPA, in four respects.
    First, Appellants argue that the BLM failed to take a “hard look” at the Project’s
    impacts on peninsular bighorn sheep because there were no available studies
    demonstrating how the sheep would respond to wind turbines, and the BLM failed
    5
    to conduct its own independent study. Although both assertions are true, the BLM
    did consider a formal Endangered Species Act Section 7 consultation of the
    Project’s impact on peninsular bighorn sheep, studies of bighorn sheep responses
    to other human activities, and a study of rocky mountain elk responses to wind
    turbine facilities. See BLM, Proposed Plan Amendment & Final Environmental
    Impact Statement/Final Environmental Impact Report for the Ocotillo Wind
    Energy Facility, at 1-15, 4.21-22, 4.21-43 (Feb. 2012) [hereinafter FEIS]. The EIS
    for the OWEF Project acknowledged that, although the Project would not directly
    affect the “critical habitat” of the peninsular bighorn sheep, the Project would
    temporarily impact 124.1 acres and permanently impact 43.1 acres of the of the
    “Essential Habitat” of the peninsular bighorn sheep. 
    Id. at 4.21-8.
    The EIS also
    identified possible indirect impacts of the Project’s construction and operation on
    the species. See 
    id. at 4.21-20
    to -22. The BLM sought to minimize and mitigate
    these impacts through the adoption of several different “Mitigation Measures,”
    which require, inter alia, the BLM to monitor and collect data on the Project’s
    impacts on the peninsular bighorn sheep, and to adjust its activities when
    appropriate and necessary. See 
    id. at 4.21-43
    to 4.21-51. Even though the actual
    effects the OWEF Project would have on the sheep were uncertain, we conclude
    the BLM took the requisite hard look, because it “considered extensively” the
    6
    potential impacts of the Project and the available mitigation measures. See
    Okanogan Highlands All. v. Williams, 
    236 F.3d 468
    , 477 (9th Cir. 2000).
    Second, Appellants argue the BLM violated NEPA by failing to consider the
    full visual impacts of the OWEF Project. Specifically, Appellants argue the BLM
    failed to analyze the visual impacts of the Project’s electrical substation, utility
    switchyard, operations and maintenance facility, observation tower, and parking
    lot. It is true that the EIS focused on the visual impacts of the wind turbines, not
    on the Project’s ancillary facilities. However, that analysis was permissible
    considering the visual impacts of the wind turbines would far exceed that of the
    ancillary facilities. See 40 C.F.R. § 1502.2(b) (“Impacts shall be discussed in
    proportion to their significance.”). The EIS did discuss the visual impact of all the
    Project’s facilities, from construction to operation to decommissioning, and
    discussed measures to mitigate these visual impacts. See FEIS, at 4.18. We
    conclude this discussion was sufficient under NEPA.
    Third, Appellants argue that the BLM violated NEPA, because it failed to
    consider the health effects of the low-frequence noise (“LFN”) and infrasound that
    would be produced by the wind turbines. In the EIS, the BLM acknowledged that
    experts are divided on the issue of whether exposure to LFN produced by wind
    turbines causes health problems. 
    Id. at 5-53.
    The BLM then discussed the validity
    7
    of several studies on both sides of the debate. See 
    id. at 4.11-13,
    5-53 to 5-55,
    App. N at 180. The BLM rejected several studies based on their lack of supporting
    documentation or experimental flaws. See 
    id. at 4.11-13,
    5-53 to 5-55. The BLM
    found persuasive several studies that concluded the LFN and infrasound levels,
    which would be produced by the OWEF Project, would not cause health problems
    for the nearby residents. For example, the BLM found reliable and relevant a 2011
    study that measured the LFN outside and inside homes near wind turbines, which
    were the same model as the turbines proposed for the OWEF Project. 
    Id. at 5-53.
    The authors of the study “concluded that no adverse public health effects from
    LFN or infrasound would be expected from the types of turbines studied at
    distances greater than 300 m[eters].” 
    Id. The BLM
    then concluded that the
    resulting LFN and infrasound that would be produced by the OWEF Project would
    be unlikely to cause health problems for the nearby residents because “the closest
    turbine is 804.67 m[eters] . . . from the nearest home.” 
    Id. We find
    the BLM conducted a full analysis of the potential consequences of
    LFN and infrasound that would be produced by the Project and, based on the
    studies it found reliable, the BLM determined that the health effects would be
    minimal. Thus, the BLM took the requisite “hard look” at LFN and infrasound,
    and we will defer to the agency’s position on this technical issue. See Nat’l Parks
    8
    & Conservation Ass’n v. U.S. Dep’t of Transp., 
    222 F.3d 677
    , 682 (9th Cir. 2000)
    (holding that when there are conflicting expert reports, an agency’s “determination
    is due deference—especially in areas of agency expertise”).
    Fourth, and finally, Appellants argue that the EIS did not adequately discuss
    the reasonable alternatives to the OWEF Project, in part because the BLM drafted
    the purpose and need statement too narrowly. An EIS must “[r]igorously explore
    and objectively evaluate all reasonable alternatives” to the proposed action. 40
    C.F.R. § 1502.14(a). An EIS must also state the “purpose and need” of a project.
    City of Carmel-By-The-Sea v. U.S. Dep’t of Transp., 
    123 F.3d 1142
    , 1155 (9th Cir.
    1997). The “purpose and need” section of an EIS “dictates the range of
    ‘reasonable’ alternatives” that the agency must consider. 
    Id. We “review
    purpose
    and need statements for reasonableness.” Alaska Survival v. Surface Transp. Bd.,
    
    705 F.3d 1073
    , 1084 (9th Cir. 2013). We give “agenc[ies] considerable discretion
    to define a project’s purpose and need.” 
    Id. However, “an
    agency cannot define
    its objectives in unreasonably narrow terms.” Carmel-By-The 
    Sea, 123 F.3d at 1155
    . In drafting a purpose and need statement, “an agency must consider the
    statutory context of the proposed action,” any applicable “congressional
    directives,” and the “private applicant’s objectives.” Alaska 
    Survival, 705 F.3d at 1085
    .
    9
    The BLM’s framing of the purpose and need statement was reasonable. In
    the EIS, the BLM separately laid out its objectives and the distinct objectives of the
    Corps of Engineers, Ocotillo, and the State of California. FEIS, at 1-3 to 1-5.
    Within this discussion, the BLM noted relevant statutes, and congressional and
    executive directives. The BLM explained that the Proposed Project would assist it
    in addressing Executive Order 13212, the Energy Policy Act of 2005, Secretarial
    Order 3285A1, and the California Global Warming Solutions Act, all of which
    encourage, or mandate, the increased production of renewable energy. 
    Id. Although the
    focus of the purpose and need statement was responding to Ocotillo’s
    application, this was reasonable in light of the relevant statutes and directives and
    the wind resources available at the Proposed Project site.
    Based on the purpose and need statement, the BLM initially considered
    eighteen alternatives to Ocotillo’s Proposed Project, including other types of
    energy projects. 
    Id. at 5-50;
    see also 
    id. at 2-48
    to 2-50. The EIS briefly explains
    why the alternatives energy projects were eliminated from consideration. See 
    id. at 2-48
    to 2-50. For example, a solar power project was eliminated both because it
    did not meet the purpose of harnessing wind energy, but also because the
    installation of solar panels would cause more land disturbance, which could have
    had a greater effect on cultural and biological resources than the Proposed Project.
    10
    
    Id. at 2-49.
    The BLM also considered other locations for the Project. 
    Id. at 2-46.
    These alternative sites were eliminated from consideration for a variety of reasons.
    
    Id. Some of
    the sites had special designations that precluded them from use, such
    as wilderness areas, some of the sites were already in use or had already been
    proposed for other wind energy projects, and some of the sites had substantially
    lower wind resources. 
    Id. Ultimately, the
    BLM analyzed six alternatives in detail,
    including the required “no project” alternative. We find that the BLM explored
    and evaluated all reasonable alternatives to the Proposed Project based on a
    reasonably drafted purpose and need statement. Accordingly, we find the BLM did
    not violate NEPA.
    AFFIRMED.
    11
    FILED
    Backcountry v. Jewell, No. 13-57129 (Pasadena - November 3, 2015)             JAN 05 2017
    MOLLY C. DWYER, CLERK
    BYBEE, Circuit Judge, concurring in the judgment:                          U.S. COURT OF APPEALS
    I respectfully disagree with the majority’s decision to approve the Ocotillo
    Wind Energy Facility (“OWEF”) because the BLM amended its California Desert
    Conservation Area Plan (“CDCA Plan”). In my view the BLM approved the
    OWEF project because it conformed to the CDCA Plan, not as a way of short
    circuiting our review.
    Since 1980, the CDCA Plan has provided that wind energy generation
    facilities for this land classification “[m]ay be allowed after NEPA requirements
    are met.” Here, the BLM did exactly what it was supposed to do. It prepared an
    exhaustive environmental impact statement. It carefully considered the impact that
    the proposed project would have on cultural and natural resources in the area and,
    in response, it reduced the footprint of the project. The BLM also acknowledged
    that it could not satisfy all of the competing claims to the land and, in an exercise
    of its judgment, it decided to approve the OWEF. Only after it had satisfied itself
    that it had heard from all interested parties, considered their views, followed the
    processes set forth in the CDCA Plan, and determined that the project conformed
    with the Plan’s requirements, did the BLM amend the CDCA Plan. In my view,
    the BLM did not amend the CDCA Plan to avoid the Plan’s requirements and this
    court’s scrutiny under the APA; it amended the CDCA Plan to reflect that the
    OWEF project was consistent with the Plan and to add OWEF to a list of approved
    energy development sites in the CDCA. The BLM’s careful and considered
    decision was model and is not “arbitrary, capricious, an abuse of discretion, or
    otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A).
    I concur in the judgment.