Bess Bair v. Cal. Dept of Transp. ( 2020 )


Menu:
  •                 FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    BESS BAIR; TRISHA LEE LOTUS;             No. 19-16478
    JEFFREY HEDIN; DAVID SPREEN;
    CENTER FOR BIOLOGICAL                       D.C. No.
    DIVERSITY; ENVIRONMENTAL                 3:17-cv-06419-
    PROTECTION INFORMATION CENTER;               WHA
    CALIFORNIANS FOR ALTERNATIVES
    TO TOXICS; FRIENDS OF DEL NORTE,
    Plaintiffs-Appellees,       OPINION
    v.
    CALIFORNIA DEPARTMENT OF
    TRANSPORTATION; TOKS
    OMISHAKIN, in his capacity as
    Director of the California
    Department of Transportation,
    Defendants-Appellants.
    Appeal from the United States District Court
    for the Northern District of California
    William Alsup, District Judge, Presiding
    Argued and Submitted October 13, 2020
    San Francisco, California
    Filed December 2, 2020
    2                BAIR V. CAL. DEP’T OF TRANSP.
    Before: Ferdinand F. Fernandez, Kim McLane Wardlaw,
    and Daniel P. Collins, Circuit Judges.
    Opinion by Judge Fernandez;
    Concurrence by Judge Wardlaw
    SUMMARY*
    Environmental Law
    Reversing the district court’s judgment in favor of
    plaintiffs, vacating an injunction, and remanding, the panel
    held that the California Department of Transportation
    complied with the National Environmental Policy Act in
    relying on an Environmental Assessment for a proposed
    highway improvement project within Richardson Grove State
    Park.
    Granting partial summary judgment in favor of plaintiffs,
    the district court concluded that Caltrans had failed
    adequately to consider certain issues and therefore had not
    taken the requisite “hard look” at the environmental impacts
    of the Project, and the 2010 Environmental Assessment (EA),
    as supplemented and revised, was inadequate. The district
    court concluded that substantial questions had been raised as
    to the effects of the Project, and it ordered Caltrans to prepare
    an environmental impact statement (EIS). The district court
    enjoined Caltrans from proceeding with the Project until the
    EIS was finalized.
    *
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    BAIR V. CAL. DEP’T OF TRANSP.                   3
    Reversing, the panel held that Caltrans based its 2017
    finding of no significant impact (FONSI) upon the analysis
    contained in the revised EA, which incorporated the analysis
    of the 2010 EA and the 2013 Revised Supplemental EA.
    Because Caltrans’ 2010 EA, as supplemented and revised,
    constituted the “hard look” at the Project’s effects required by
    NEPA, Caltrans’ issuance of the 2017 FONSI was
    reasonable. The panel held that none of the purported
    inadequacies identified by the district court rendered the
    revised EA arbitrary or capricious.
    Concurring, Judge Wardlaw wrote that she concurred in
    the majority opinion, and Caltrans did not violate NEPA
    because its reliance on the EA was not arbitrary and
    capricious. Judge Wardlaw wrote separately to emphasize
    that: (1) the administrative record was painful to review;
    (2) if significant new information is discovered during the
    proposed construction or substantial project changes are
    made, Caltrans may need to reevaluate its analysis; and
    (3) the Project seems likely to provide new data on the effects
    of construction on old-growth redwoods, which could prove
    important to future decisions surrounding these historic trees.
    COUNSEL
    Stacy Jayne Lau (argued), Michael A.G. Einhorn, and Angela
    Wuerth; Lucille Y. Baca, Assistant Chief Counsel;
    G. Michael Harrington, Deputy Chief Counsel; Erin E.
    Holbrook, Chief Counsel; State of California Department of
    Transportation – Legal Division, Oakland, California; for
    Defendants-Appellants.
    4               BAIR V. CAL. DEP’T OF TRANSP.
    Stuart G. Gross (Argued) and Timothy S. Kline, Gross &
    Klein LLP, San Francisco, California; Todd R. Gregorian and
    Garner F. Kropp, Fenwick & West LLP, San Francisco,
    California; for Plaintiffs-Appellees.
    OPINION
    FERNANDEZ, Circuit Judge:
    This environmental appeal arises from a highway
    improvement project proposed by the California Department
    of Transportation (collectively with its director, Toks
    Omishakin, Caltrans). Plaintiffs Bess Bair, Trisha Lee Lotus,
    Jeffrey Hedin, David Spreen, the Center for Biological
    Diversity, the Environmental Protection Information Center,
    Californians for Alternatives to Toxics, and Friends of del
    Norte (collectively, Bair1) challenged the project on a variety
    of grounds, including the failure to comply with the National
    Environmental Policy Act of 1969, Pub. L. No. 91–190, 
    83 Stat. 852
     (1970) (NEPA). The district court determined that
    Caltrans arbitrarily and capriciously relied upon the 2010
    Environmental Assessment (2010 EA), as supplemented and
    revised, because, it held, that document failed to sufficiently
    consider certain “significant issues.” Bair v. Cal. State Dep’t
    of Transp., 
    385 F. Supp. 3d 878
    , 886 (N.D. Cal. 2019). The
    district court also enjoined Caltrans from continuing the
    project until it finalized an appropriate environmental impact
    statement (EIS). It then entered a final judgment against
    Caltrans. We reverse and remand.
    1
    While the plaintiffs other than Bair have changed from time to time
    during the more than ten years of litigation that has ensued, unless
    otherwise noted, the plaintiffs will hereafter be referred to as Bair.
    BAIR V. CAL. DEP’T OF TRANSP.                      5
    I. BACKGROUND
    Richardson Grove State Park (the Grove) comprises
    approximately 2,000 acres within the redwood forests of
    southern Humboldt County, California, and is bisected by
    United States Highway 101. Within the Grove, Highway 101
    is a two-lane highway “on a nonstandard alignment” with
    tight curves and narrow travel lanes and roadway shoulders.
    A number of trees, including old-growth redwood trees,2 abut
    the roadway as it meanders through the Grove. In light of
    antiquated roadway design, there are restrictions on the types
    of vehicles that may travel that portion of the highway.
    Sixty-five foot long “California Legal” trucks are permitted,
    but industry-standard Surface Transportation Assistance Act
    of 19823 (STAA) trucks generally are not. STAA trucks are
    longer than California Legal trucks and can carry larger cargo
    volumes, although both classes of trucks are subject to the
    same weight limitation. Because of their longer length,
    STAA trucks navigating the highway’s tight curves
    frequently “off-track” into the opposing traffic lane or onto
    the roadway shoulder.
    The STAA truck restriction at the Grove is the only
    remaining impediment to STAA trucks traveling into
    Humboldt County via Highway 101. Caltrans has long
    sought to remove that roadblock, but abandoned previous
    efforts because of the substantial projected expense, among
    other things. In 2007, Caltrans learned that the existing
    roadway could be strategically widened to render it accessible
    2
    Caltrans defined “old growth redwood[s]” as “trees over 30 inches
    in diameter at breast height (4.5 feet above ground level).”
    3
    Pub. L. No. 97–424, 
    96 Stat. 2097
     (1983).
    6              BAIR V. CAL. DEP’T OF TRANSP.
    to STAA trucks, and Caltrans developed the Richardson
    Grove Operational Improvement Project (the Project) to do
    just that. The Project involves slightly widening the roadway
    and straightening some curves in certain locations along a
    one-mile stretch of Highway 101, largely within the Grove.
    Its purposes are to accommodate STAA truck travel, improve
    the safety and operation of Highway 101, and improve the
    movement of goods into Humboldt County. The speed limit
    would remain unchanged at thirty five miles per hour.
    Caltrans assumed responsibility for obtaining environmental
    approval for the Project pursuant to NEPA. See 
    23 U.S.C. § 327
    (a)(2)(A), (B)(i).
    A. The Project as originally proposed in 2010
    The original 2010 EA included extensive analysis of the
    Project’s environmental effects and efforts to minimize those
    effects (developed in consultation with the California
    Department of Parks and Recreation (State Parks)). More
    than 100 pages of the 2010 EA were devoted to analyzing
    various environmental impacts, such as the effects on the
    nearby South Fork Eel River, the Grove and its recreation
    facilities, economic growth, traffic, water quality, noise, local
    plant and animal species (particularly old-growth redwood
    trees), and protected or threatened species.
    Caltrans ultimately determined that the impacts to the
    Grove would be minor, and would primarily consist of “tree
    removal resulting from cuts and fills that are necessary to
    accommodate the highway improvements,” as well as the
    BAIR V. CAL. DEP’T OF TRANSP.                             7
    effect on trees whose structural root zones4 were within the
    construction area. Although some trees would be removed,
    none of those would be old-growth redwoods. And while
    construction would occur in the structural root zones of fewer
    than 80 old-growth redwoods, plans were made to mitigate its
    effects. For example, Caltrans proposed to increase the
    height of the roadbed where possible to avoid severing tree
    roots, use a thinner roadbed material to allow greater
    permeability, conduct some construction (excavation) by
    hand, water trees during the summer, and remove some
    invasive plants. In light of those measures, both the Caltrans
    arborist (Darin Sullivan) and the arborist hired by Save the
    Redwoods League (Dennis Yniguez) determined that the
    Project as proposed in 2010 “would not significantly impact
    the root health of the old growth trees adjacent to the
    construction.” Caltrans issued the EA and Finding of No
    Significant Impact (FONSI) for the Project in May 2010.
    B. Past litigation
    Bair filed suit regarding the Project in both 20105 and
    2014,6 each time making similar claims. In the First
    Litigation, the district court granted partial summary
    judgment to the plaintiffs and ordered Caltrans to undertake
    4
    As defined in the 2010 EA, “the structural root zone is a circular
    area with the tree trunk at the center with a radius equal to three times the
    diameter of the tree trunk measured at 4.5 feet above ground level,” and
    “is where most of the [tree’s] nutrient and water absorption occurs.”
    5
    Bair v. Cal. Dep’t of Transp., No. 3:10-cv-04360-WHA (N.D. Cal.
    2010) (the First Litigation).
    6
    Bair v. Cal. Dep’t of Transp., No. 3:14-cv-03422-WHA (N.D. Cal.
    2014) (the Second Litigation).
    8               BAIR V. CAL. DEP’T OF TRANSP.
    additional studies, such as preparing new maps of each old-
    growth redwood tree, its root health zone, and the
    environmental impacts to each tree. Bair, 385 F. Supp. 3d
    at 883. Caltrans then revised its analysis accordingly. After
    commissioning a tree report from arborist Yniguez, it issued
    a 2013 Supplement to the 2010 EA. Caltrans then took public
    comments, responded to them, and finally issued a NEPA Re-
    validation for the Project in January 2014. It found that the
    2010 EA and FONSI remained valid.
    In the Second Litigation, Bair challenged the re-validated
    Project on many of the same grounds as in the First
    Litigation. See id. The Second Litigation was dismissed after
    Caltrans withdrew the FONSI7 in light of an adverse ruling in
    a parallel proceeding in the California Court of Appeal. See
    Bair, 385 F. Supp. 3d at 883–84; Lotus v. Dep’t of Transp.,
    
    167 Cal. Rptr. 3d 382
    , 393 (Ct. App. 2014). In response to
    the California court’s order, Caltrans slightly reduced the
    scope of the Project, and Yniguez prepared another tree
    report.
    C. 2017 Project proposal and current litigation
    Since the original issuance of the EA in 2010, Caltrans
    has modified the Project to reduce its impact, primarily by
    narrowing the proposed roadbed (roadway shoulders). The
    Project now requires the removal of 38 trees, none of which
    are old-growth redwoods, and construction will occur within
    the structural root zones of 78 old-growth redwood trees,
    72 of which are within the Grove. That construction activity
    largely consists of (1) excavation to a maximum depth of two
    7
    Notice of Rescission of Finding of No Significant Impact, 
    79 Fed. Reg. 70,612
    -01, 70,612 (Nov. 26, 2014).
    BAIR V. CAL. DEP’T OF TRANSP.                    9
    feet; (2) covering some of the root zone with impervious
    surface (roadbed); and (3) placing fill over tree roots. As
    noted, Caltrans retained arborist Yniguez to evaluate the
    effects of the Project on the redwoods and to produce two
    reports summarizing his conclusions. In general, he
    determined that the Project “would not have any substantial
    detrimental effect on individual old-growth redwoods . . . or
    the overall health of the stand of redwoods in Richardson
    Grove.” His reports were based on scientific literature
    regarding redwoods, his three decades of experience as an
    arborist, multiple site visits to the Grove (including a
    helicopter flight to evaluate tree crowns), and materials
    provided by Caltrans such as the EA, detailed schematic
    drawings of all trees with root zones within the Project area,
    and individual tree details for each. Yniguez assessed each
    tree individually to determine the likely effect on its health
    from the root zone disturbances created by the Project, both
    with and without mitigation measures, and assigned each tree
    a rating corresponding to the anticipated effects on its health,
    ranging from Level 0 to Level 6. He concluded that the
    Project would not jeopardize the lives of any old-growth
    redwood trees, and that the vast majority of such trees would
    sustain no decline in foliage density or health as a result of
    the Project. In the absence of mitigation measures, Yniguez
    decided that approximately eighteen old-growth redwood
    trees may manifest “a short-term visible reduction in foliage
    density that is still well within the adaptive capabilities of the
    tree” (Level 4 rating), while one such tree may undergo “a
    reduction in root health sufficient to cause lasting visible
    dieback of wood in the uppermost crown, although tree health
    and survival [would] not [be] threatened” (Level 5 rating).
    Including the Project’s mitigation measures substantially
    reduced those effects: Yniguez determined that only three
    old-growth redwood trees would remain in Level 4 and none
    10                 BAIR V. CAL. DEP’T OF TRANSP.
    in Level 5 if the proposed mitigation measures were
    implemented. Yniguez thus concluded that “[n]one of the
    proposed highway alterations is of sufficient magnitude to
    threaten the health or stability of any old-growth redwood”
    because “disturbances would be confined to a small
    percentage of the area occupied by roots and would be well
    within the adaptive capabilities of the tree[s].” Moreover,
    even without mitigation measures, Yniguez concluded that
    “the limited root disturbance would be inconsequential to the
    appearance, stability, and continued health of the old-growth
    redwoods in Richardson Grove.”
    Caltrans largely agreed with Yniguez’s analysis, but also
    considered other evidence, such as scientific literature about
    the resilience, health, and development of redwoods and their
    root systems generally, the condition of the particular old-
    growth redwood trees in the Project area, and the specific
    activities and mitigation measures comprising the Project.
    Caltrans thus concluded that “[i]n no case would root
    disturbance have a significant detrimental effect on the health
    or stability of old-growth redwoods.” In May 2017, Caltrans
    issued revisions to the EA and a new FONSI.
    Bair filed this litigation in 2017,8 again raising claims
    similar to those that had been made in the First Litigation and
    the Second Litigation, specifically: seven claims alleging
    various violations of NEPA, as well as claims for a violation
    of section 4(f) of the Department of Transportation Act,9 a
    8
    Bair v. Cal. Dep’t of Transp., No. 3:17-cv-06419-WHA (N.D. Cal.
    2017).
    9
    
    23 U.S.C. § 138
    (a); see also 
    23 C.F.R. § 774.1
    .
    BAIR V. CAL. DEP’T OF TRANSP.                       11
    violation of section 7 of the Wild and Scenic Rivers Act,10 a
    violation of the Administrative Procedure Act (APA),11 a
    declaration that Caltrans is responsible for Bair’s attorney’s
    fees and costs,12 and injunctive relief.13 The district court
    granted Bair partial summary judgment as to some of the
    NEPA claims. Bair, 385 F. Supp. 3d at 898.14 The district
    court identified certain issues that, in its view, Caltrans had
    not adequately considered: whether (1) redwoods would
    suffocate when more than half of their root zones were
    covered by pavement;15 (2) construction in a redwood’s
    structural root zone would cause root disease;16 (3) traffic
    noise would increase because of the larger size of the STAA
    trucks or because of additional numbers of trucks;17 and
    (4) redwoods would suffer more frequent and severe damage
    as a result of strikes by STAA trucks.18 Because of those
    deficiencies, the district court determined that Caltrans had
    not taken the requisite “hard look” at the environmental
    impacts of the Project, and that the EA was inadequate. Id.
    10
    
    16 U.S.C. § 1278
    (a).
    11
    
    5 U.S.C. § 706
    (2)(A), (D).
    12
    See 
    23 U.S.C. § 327
    (a)(2)(G); 
    Cal. Civ. Proc. Code § 1021.5
    .
    13
    Fed. R. Civ. P. 65(a).
    14
    The district court did not address Bair’s other claims. See 
    id.
    15
    
    Id. at 886, 888
    .
    16
    
    Id. at 891
    .
    17
    
    Id.
     at 892–93, 895.
    18
    
    Id. at 895
    .
    12            BAIR V. CAL. DEP’T OF TRANSP.
    at 890–91, 895, 898. In light of those supposed shortcomings
    in the EA, the district court concluded that substantial
    questions had been raised as to the effects of the Project, and
    it ordered Caltrans to prepare an EIS. The district court also
    enjoined Caltrans from proceeding with the Project until the
    EIS was finalized. Caltrans timely appealed. See Fed. R.
    App. P. 4(a)(1)(A).
    II. JURISDICTION
    The district court had jurisdiction pursuant to 
    28 U.S.C. § 1331
    . We have jurisdiction. 
    28 U.S.C. § 1291
    ; see
    HonoluluTraffic.com v. Fed. Transit Admin., 
    742 F.3d 1222
    ,
    1229 (9th Cir. 2014); Alsea Valley All. v. Dep’t of Com.,
    
    358 F.3d 1181
    , 1184 (9th Cir. 2004).
    III. STANDARDS OF REVIEW
    “We review de novo a district court’s grant of summary
    judgment.” Am. Wild Horse Campaign v. Bernhardt,
    
    963 F.3d 1001
    , 1007 (9th Cir. 2020). “[A]gency decisions
    that allegedly violate NEPA” are reviewed “under the
    Administrative Procedure Act, and we set aside those
    decisions only if they are ‘arbitrary, capricious, an abuse of
    discretion, or otherwise not in accordance with law.’” Id.; see
    also 
    5 U.S.C. § 706
    (2)(A). “Whether a plaintiff has
    exhausted required administrative remedies is a question of
    law reviewed de novo.” Great Basin Mine Watch v. Hankins,
    
    456 F.3d 955
    , 961 (9th Cir. 2006).
    IV. DISCUSSION
    NEPA generally “requires a federal agency . . . to prepare
    ‘a detailed statement on . . . the environmental impact’ of
    BAIR V. CAL. DEP’T OF TRANSP.                         13
    ‘major Federal actions significantly affecting the quality of
    the human environment,’”19 a document known as an EIS.20
    However, the regulations alternatively “allow an agency to
    prepare a more limited document, an Environmental
    Assessment (EA), if the agency’s proposed action . . . would
    [not] clearly require the production of an EIS.” Dep’t of
    Transp. v. Pub. Citizen, 
    541 U.S. 752
    , 757, 
    124 S. Ct. 2204
    ,
    2209–10, 
    159 L. Ed. 2d 60
     (2004); see also 
    40 C.F.R. § 1501.4
    (b)–(c). An EA is “a ‘concise public document’ that
    ‘[b]riefly provide[s] sufficient evidence and analysis for
    determining whether to prepare an [EIS].’” Dep’t of Transp.,
    
    541 U.S. at 757
    , 
    124 S. Ct. at 2210
    ; see also Ctr. for
    Biological Diversity, 538 F.3d at 1185; 
    40 C.F.R. § 1508.9
    (a)–(b).
    If the “agency determines that an EIS is not required . . . ,
    it . . . issue[s] a ‘finding of no significant impact’ (FONSI),
    which briefly presents the reasons why the proposed agency
    action will not have a significant impact on the human
    environment.” Dep’t of Transp., 
    541 U.S. at
    757–58, 
    124 S. Ct. at 2210
    ; see also 
    40 C.F.R. §§ 1501.4
    (e), 1508.13. That
    decision “can be set aside only upon a showing that it was
    19
    Ctr. for Biological Diversity v. Nat’l Highway Traffic Safety
    Admin., 
    538 F.3d 1172
    , 1185 (9th Cir. 2008); see also 
    42 U.S.C. § 4332
    (C).
    20
    See 
    40 C.F.R. § 1501.4
    (a), (c). The Council on Environmental
    Quality has adopted new regulations that became effective on September
    14, 2020. Update to the Regulations Implementing the Procedural
    Provisions of the National Environmental Policy Act, 
    85 Fed. Reg. 43,304
    , 43,304 (July 16, 2020); see also 
    40 C.F.R. § 1506.13
     (2020).
    Because Caltrans applied the previous regulations to the Project, so do we.
    Unless otherwise indicated, the regulations cited herein are the versions
    in effect when the district court rendered its decision.
    14             BAIR V. CAL. DEP’T OF TRANSP.
    ‘arbitrary, capricious, an abuse of discretion, or otherwise not
    in accordance with law.’” Dep’t of Transp., 
    541 U.S. at 763
    ,
    
    124 S. Ct. at 2213
    ; see also 
    5 U.S.C. § 706
    (2)(A); Ocean
    Advocs. v. U.S. Army Corps of Eng’rs, 
    402 F.3d 846
    , 858 (9th
    Cir. 2005). Determining whether the agency’s decision not
    to prepare an EIS was arbitrary and capricious “requires us to
    determine whether the agency has taken a hard look at the
    consequences of its actions, based [its decision] on a
    consideration of the relevant factors, and provided a
    convincing statement of reasons to explain why a project’s
    impacts are insignificant.” Native Ecosystems Council v. U.S.
    Forest Serv. (Native Ecosystems I), 
    428 F.3d 1233
    , 1239 (9th
    Cir. 2005) (internal quotation marks omitted). Although our
    review “is ‘searching and careful,’” it is nevertheless
    narrowly circumscribed, “and we cannot substitute our own
    judgment for that of the [agency].” Ocean Advocs., 
    402 F.3d at 858
    . Instead, “[w]e ask ‘whether the [agency’s] decision
    was based on a consideration of the relevant factors and
    whether there has been a clear error of judgment.’” 
    Id. at 859
    ; see also In Def. of Animals v. U.S. Dep’t of the Interior,
    
    751 F.3d 1054
    , 1072 (9th Cir. 2014). But we must keep in
    mind that we are not “a panel of scientists that instructs the
    [agency] how to validate its hypotheses . . . , chooses among
    scientific studies . . . , [or] orders the agency to explain every
    possible scientific uncertainty.” Lands Council v. McNair,
    
    537 F.3d 981
    , 988 (9th Cir. 2008) (en banc), overruled in part
    on other grounds by Winter v. Nat. Res. Def. Council, Inc.,
    
    555 U.S. 7
    , 21–22, 
    129 S. Ct. 365
    , 375, 
    172 L. Ed. 2d 249
    (2008).
    Caltrans based its 2017 FONSI upon the analysis
    contained in the revised EA, which incorporated the analysis
    of the 2010 EA and the 2013 Revised Supplemental EA.
    Because Caltrans’ 2010 EA, as supplemented and revised,
    BAIR V. CAL. DEP’T OF TRANSP.                      15
    constituted the “hard look” at the Project’s effects required by
    NEPA, Caltrans’ issuance of the 2017 FONSI was
    reasonable. The district court erred in granting partial
    summary judgment to Bair. As we explain in the ensuing
    paragraphs, none of the purported inadequacies it identified
    rendered the revised EA arbitrary or capricious.
    First, as to redwood tree suffocation, Caltrans sufficiently
    considered the effect of paving over portions of tree root
    zones. The Project will use a special material to allow
    “‘greater porosity’” and to “‘promote air circulation’” under
    the asphalt,21 and Caltrans considered the aggregate amount
    of new roadbed material that would be placed over the
    structural root zones. Yniguez specifically relied in part upon
    Caltrans’ selection of permeable material, the minor and
    limited areas of new asphalt, and Caltrans’ decision to narrow
    the proposed roadway shoulders where possible in reaching
    his conclusion that the Project would not create extreme
    stress in the redwoods or overwhelm their natural resilience.22
    And, as more particularly described in Part I.C of this
    Opinion, Yniguez and Caltrans thoroughly assessed the
    amount of paving that would be placed over the root zone of
    each tree. Caltrans considered the possibility that paving
    could harm the trees, but simply (and reasonably) concluded
    that there was sufficient evidence to the contrary. See In Def.
    21
    Bair, 385 F. Supp. 3d at 888.
    22
    Caltrans reasonably relied upon Yniguez’s reports, and Bair does
    not argue otherwise. See Native Ecosystems Council v. Weldon (Native
    Ecosystems II), 
    697 F.3d 1043
    , 1051–52 (9th Cir. 2012). Caltrans’
    reliance on evidence specifically pertaining to redwoods (including
    Yniguez’s reports) was eminently reasonable, especially because the
    record reflects that redwood trees and their root systems are particularly
    (uniquely) resilient.
    16                BAIR V. CAL. DEP’T OF TRANSP.
    of Animals, 751 F.3d at 1072; Lands Council, 
    537 F.3d at 1003
    . That was not arbitrary or capricious. See In Def. of
    Animals, 751 F.3d at 1072–73.23 The district court erred in
    concluding that the EA failed to adequately consider the
    effects of paving over portions of the root zones of certain
    trees.
    Second, as to construction within root zones, Caltrans
    appropriately considered the extent and effect of the
    construction activity that would occur in the structural root
    zones of redwood trees, including construction guidelines in
    a State Parks handbook. The record plainly belies Bair’s
    contention that Caltrans failed to consider the effects of
    construction. On the contrary, as described in Part I of this
    Opinion, the record is replete with Caltrans’ comprehensive
    analyses of the extent and effects of construction activity in
    the root zones of individual trees. See Cold Mountain v.
    Garber, 
    375 F.3d 884
    , 893–94 (9th Cir. 2004).24 As to the
    23
    Moreover, there is no evidence supporting the district court’s
    assumption that 50% paving over root zones is some sort of “threshold”
    demarcating a “‘danger zone’” or “red zone” for redwood trees. Bair,
    385 F. Supp. 3d at 888–89. Rather, that is an unwarranted inference
    drawn from a misreading of evidence in the record. Indeed, no comments
    or evidence in the administrative record raised the 50% threshold issue.
    That suggests that the issue was not even administratively exhausted. See
    Barnes v. U.S. Dep’t of Transp., 
    655 F.3d 1124
    , 1132, 1135–36 (9th Cir.
    2011).
    24
    The district court erred in criticizing Caltrans for failing to consider
    whether root disease would arise from root injuries caused by
    construction. See Bair, 385 F. Supp. 3d at 891. Caltrans reasonably relied
    upon its expert’s opinion that redwoods have “no important . . . disease
    enemies”—evidence tailored to redwoods specifically, rather than trees in
    general. See In Def. of Animals, 751 F.3d at 1072; City of Carmel-By-The-
    Sea v. U.S. Dep’t of Transp., 
    123 F.3d 1142
    , 1151 (9th Cir. 1997).
    BAIR V. CAL. DEP’T OF TRANSP.                   17
    sentence in State Parks’ handbook that recommended that no
    construction should take place in the structural root zone “of
    a protected tree,” it is not clear that it applied to the affected
    redwoods or influenced State Parks’ opinion of the Project, or
    that Caltrans was obligated to defer to or adopt that opinion.
    See WildEarth Guardians v. Provencio, 
    923 F.3d 655
    , 672
    (9th Cir. 2019); see also Native Ecosystems I, 
    428 F.3d at 1242
    . NEPA anticipates that the administrative record may
    contain contradictory and conflicting opinions, expert and
    otherwise,25 and does not require an agency to follow all
    recommendations made by commentators, other agencies, or
    experts.26 Thus, to the extent that the recommendation in
    State Parks’ handbook is relevant here, Caltrans could (and
    did) reasonably refuse to follow it, especially when Caltrans
    relied upon evidence specifically pertaining to the effects of
    construction on redwoods in general and the redwoods in the
    Project area, in particular. In fine, the district court erred
    when it decided that Caltrans failed to sufficiently consider
    the State Parks handbook and the impact of construction in
    the structural root zones of old-growth redwoods.
    Third, as to traffic volume and noise, the district court
    erred when it decided that Caltrans failed to adequately
    consider how the visitor experience to the Grove would be
    affected by the presence of STAA trucks, particularly with
    regard to whether they would be more numerous or generate
    more noise. Bair, 385 F. Supp. 3d at 891–92, 895. Caltrans’
    EA concluded that truck traffic would not increase as a result
    of the Project, and it properly relied upon record evidence to
    25
    City of Carmel-By-The-Sea, 
    123 F.3d at 1151
    ; see also In Def. of
    Animals, 751 F.3d at 1072.
    26
    See WildEarth Guardians, 923 F.3d at 672.
    18                 BAIR V. CAL. DEP’T OF TRANSP.
    do so, including: a survey of regional business owners, traffic
    studies in nearby areas suggesting little latent demand for the
    route, the fact that highway capacity would be unchanged,
    and Caltrans’ opinion that STAA trucks currently using the
    straighter alignment and faster travel time of Interstate 5 to
    reach major coastal cities were unlikely to detour through the
    Grove. See In Def. of Animals, 751 F.3d at 1072. Caltrans
    reasonably concluded from that evidence that traffic would
    not increase as a result of the Project. Thus, Caltrans’
    conclusion that traffic would not increase is entitled to
    deference. See WildEarth Guardians, 923 F.3d at 672; Native
    Ecosystems II, 697 F.3d at 1052–53; cf. Ocean Advocs.,
    
    402 F.3d at
    865–66 (agency failed to consider possible traffic
    increase). Moreover, in light of its conclusion that truck
    traffic would not increase, Caltrans also reasonably concluded
    that traffic noise would not appreciably increase. Although
    the district court stated that it believed STAA trucks would be
    noisier than California Legal trucks because their tractor units
    “are bigger and heavier,”27 it cited no evidence for its
    assumptions about the size and weight of STAA tractor units,
    or its belief about their noise in comparison to California
    Legal trucks. Nor have we been pointed to any evidence of
    that in the record. A district court has no more license to act
    as “a panel of scientists” than we have. Lands Council,
    
    537 F.3d at 988
    . Caltrans adequately considered the Project’s
    effects on both traffic and traffic noise in the Grove, and
    reasonably concluded that the impacts would not be
    significant.
    Fourth, as to collisions with trees, the district court erred
    by determining that Caltrans should have analyzed whether
    the Project could cause trees to: suffer more frequent
    27
    Bair, 385 F. Supp. 3d at 894–95.
    BAIR V. CAL. DEP’T OF TRANSP.                         19
    collisions with trucks because STAA trucks are longer and
    more difficult to maneuver; and sustain more damage from
    collisions because STAA trucks are heavier and their engine
    compartments more protruding than California Legal trucks.
    Bair, 385 F. Supp. 3d at 895. Caltrans’ analysis was not
    arbitrary and capricious. See Lands Council, 
    537 F.3d at 993
    .
    As to collision frequency, the undisputed purpose of the
    Project is to widen the road in order to provide room for off-
    tracking STAA trucks, and Caltrans reasonably concluded
    that doing so would decrease the incidence of vehicles
    colliding with trees. Bair’s assumption that the collision risk
    will increase because the pavement will be closer to some
    trees ignores that the pavement is moving farther from other
    trees.28 Caltrans’ conclusions regarding the frequency of
    collisions were reasonable and entitled to deference,
    especially because they pertain to an “area[] of agency
    expertise.” Nat’l Parks & Conservation Ass’n v. U.S. Dep’t
    of Transp., 
    222 F.3d 677
    , 682 (9th Cir. 2000); see also Lands
    Council, 
    537 F.3d at 993
    .
    As to damage severity, we have not located any
    comments or documents in the administrative record which
    indicate that STAA trucks would cause more damage when
    they strike trees. Thus, it appears that issue was not
    administratively exhausted. See Barnes, 
    655 F.3d at 1132
    ,
    1135–36. And even if the issue had been exhausted, the
    district court’s speculation that trees would suffer more
    severe damage from collisions because of the weight or shape
    of STAA trucks is not supported by any evidence in the
    28
    It also ignores record evidence suggesting that the number of trucks
    traveling through the Grove may actually decrease because some of the
    California Legal trucks that would otherwise drive through the Grove may
    be replaced by fewer STAA trucks.
    20                  BAIR V. CAL. DEP’T OF TRANSP.
    record. It was reasonable for Caltrans’ EA not to anticipate
    that unfounded speculation. See Lands Council, 
    537 F.3d at 1002
    . We reject Bair’s argument that because Caltrans was
    responsible for drafting the EA, it was also required to amass
    evidence demonstrating the comparative damage caused to
    trees by collisions with STAA trucks and California Legal
    trucks. See 
    40 C.F.R. § 1508.9
    (a). While it is arbitrary and
    capricious for an agency to “‘entirely fail[] to consider an
    important aspect of the problem,’” that did not occur here.
    Lands Council, 
    537 F.3d at 993
    . As described above,
    Caltrans considered the effects of the Project with regard to
    traffic volume, noise, ease of navigation, and tree collisions.
    An agency is not required “to address in detail . . . every
    single comment . . . to prove that [it] ‘considered’ the relevant
    factors,”29 much less to anticipate conclusory supposition
    about speculative and tangential effects that are not supported
    by evidence in the record.30
    For those reasons, we are satisfied that Caltrans took a
    hard look at the consequences of the Project, and adequately
    considered the relevant factors. See Native Ecosystems I,
    
    428 F.3d at 1239
    . That Bair or the district court may disagree
    with Caltrans’ conclusions “does not constitute a NEPA
    violation.” Native Ecosystems II, 697 F.3d at 1053; see also
    WildEarth Guardians, 923 F.3d at 672. Thus, the district
    court erred in finding Caltrans’ EA arbitrary and capricious
    and in setting aside the 2017 FONSI.
    29
    In Def. of Animals, 751 F.3d at 1072.
    30
    See WildEarth Guardians, 923 F.3d at 672; Native Ecosystems II,
    697 F.3d at 1053, 1055; see also Am. Wild Horse Campaign, 963 F.3d
    at 1008–10.
    BAIR V. CAL. DEP’T OF TRANSP.                           21
    In light of our conclusion, we reverse the district court’s
    judgment requiring Caltrans to produce an EIS and enjoining
    it from continuing the Project until it has done so. An agency
    must prepare an EIS “[i]f there is a substantial question
    whether an action ‘may have a significant effect’ on the
    environment.” Ctr. for Biological Diversity, 
    538 F.3d at 1185
    ; see also 
    42 U.S.C. § 4332
    (C); 
    40 C.F.R. §§ 1502.1
    ,
    1508.18, 1508.27. The district court’s rationale for requiring
    an EIS was predicated on its erroneous conclusions about the
    Project’s effects on redwood tree health and possible
    increases in truck traffic and noise. Because we have
    determined that the EA’s analysis was adequate in those
    respects, the district court necessarily erred in setting aside
    the 2017 FONSI and ordering Caltrans to prepare an EIS if it
    desired to proceed. See Dep’t of Transp., 
    541 U.S. at
    762–64,
    
    124 S. Ct. at
    2212–13.31
    V. CONCLUSION
    The parties have engaged in contentious litigation over
    the (relatively limited) Project for more than ten years.
    However, Caltrans’ environmental analyses regarding the
    redwoods and traffic satisfied NEPA’s requirements.
    Therefore, we reverse the district court’s judgment, and we
    vacate the injunction.
    While we have now resolved those aspects of the parties’
    dispute, Bair’s other claims regarding defects in Caltrans’
    31
    Caltrans invites us to exercise our discretion to resolve Bair’s other
    claims, which the district court did not reach when it entered final
    judgment against Caltrans. See Bair, 385 F. Supp. 3d at 898. We decline
    the invitation. See Davis v. Nordstrom, Inc., 
    755 F.3d 1089
    , 1094–95 (9th
    Cir. 2014).
    22            BAIR V. CAL. DEP’T OF TRANSP.
    consideration of other issues remain unresolved because the
    district court’s order that Caltrans must prepare an EIS made
    it unnecessary to do so. We expect that the district court will
    now expeditiously consider and dispose of those remaining
    claims on remand.
    REVERSED and REMANDED for further
    proceedings not inconsistent with this Opinion.
    WARDLAW, Circuit Judge, concurring
    “Although the environmental assessment did not always
    make [Caltrans’s] reasoning explicit” and is “a decision of
    less than ideal clarity,” “the agency’s path may reasonably be
    discerned.” Am. Wild Horse Campaign v. Bernhardt,
    
    963 F.3d 1001
    , 1009 (9th Cir. 2020). Therefore, in light of
    the administrative record in this case, I concur in the majority
    opinion. Caltrans did not violate NEPA because its reliance
    on the EA was not arbitrary and capricious. I write separately
    to emphasize three points.
    First, reviewing the “nightmarish ‘administrative record’
    in this case was a painful exercise. Bair v. Cal. State Dep’t
    of Transp., No. C 17-06419 WHA, 
    2019 WL 2644074
    , at *5
    (N.D. Cal. June 27, 2019). When resolving the remaining
    claims on remand, the district court’s suggestion that Caltrans
    provide a “fresh administrative record . . . with no
    incorporations by reference” seems sensible. Id. at *5.
    Second, and as Caltrans’s counsel acknowledged at oral
    argument, if “significant new information is discovered”
    during the proposed construction or if “substantial project
    BAIR V. CAL. DEP’T OF TRANSP.                     23
    changes are made,” Recording of October 13, 2020 Oral
    Argument at 17:10–17:42,1 Caltrans may well need to
    reevaluate its analysis and potentially prepare an additional
    revised EA or even an EIS. See 
    23 C.F.R. §§ 771.129
    ,
    771.130; see also Idaho Sporting Congress Inc. v. Alexander,
    
    222 F.3d 562
    , 566 n.2 (9th Cir. 2000) (“NEPA imposes on
    federal agencies a continuing duty to supplement existing
    EAs and EISs in response to significant new circumstances or
    information relevant to environmental concerns and bearing
    on the proposed action or its impacts.” (internal quotation
    marks and citation omitted)); Price Road Neighborhood
    Ass’n, Inc. v. U.S. Dep’t of Transp., 
    113 F.3d 1505
    , 1510 (9th
    Cir. 1997) (examining the FHWA NEPA framework and the
    continuing duty to supplement).
    Third and relatedly, the road or highway construction that
    Caltrans has proposed here seems likely to provide new data
    on the effects of construction on old-growth redwoods.
    Given that much of the scientific evidence in the record is
    non-quantitative and dated, I would expect that such data
    would prove important to future decisions surrounding these
    historic trees, and—if that data becomes available during the
    project—to any decision concerning the preparation of a
    supplemental EA or EIS.
    So therefore, I respectfully concur, with slight
    reservations in these tumultuous times.
    1
    https://tinyurl.com/y39s2g6o (last visited Nov. 24, 2020).