Ctr. for Biological Diversity v. David Bernhardt ( 2020 )


Menu:
  •                FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    CENTER FOR BIOLOGICAL DIVERSITY;         No. 18-73400
    DEFENDERS OF WILDLIFE; FRIENDS
    OF THE EARTH; GREENPEACE USA;
    PACIFIC ENVIRONMENT,                      OPINION
    Petitioners,
    v.
    DAVID BERNHARDT; BUREAU OF
    OCEAN ENERGY MANAGEMENT;
    UNITED STATES FISH AND WILDLIFE
    SERVICE,
    Respondents,
    HILCORP ALASKA LLC,
    Respondent-Intervenor.
    On Petition for Review of an Order of the
    Bureau of Land Management, Interior
    Argued and Submitted November 5, 2019
    Portland, Oregon
    Filed December 7, 2020
    2              CTR. FOR BIO. DIVERSITY V. ZINKE
    Before: Richard A. Paez and Johnnie B. Rawlinson,
    Circuit Judges, and Leslie E. Kobayashi, * District Judge.
    Opinion by Judge Paez
    SUMMARY **
    Appellate Jurisdiction / Environmental Law
    The panel granted in part, and denied in part, a petition
    for review brought by plaintiff conservation groups
    challenging the U.S. Department of Interior’s Bureau of
    Ocean Energy Management (“BOEM”)’s approval of the
    Liberty project – an offshore drilling and production facility
    along the coast of Alaska in the Beaufort Sea; vacated
    BOEM’s approval of the project; and remanded to the
    agency for further proceedings.
    The site of the Liberty project is governed by the Outer
    Continental Shelf Lands Act (“OCSLA”). Before Hillcorp
    Alaska, LLC could begin drilling, it had to obtain approval
    of the Liberty project from BOEM. Three environmental
    statutes and their concomitant regulations governed
    BOEM’s approval: the National Environmental Policy Act
    (“NEPA”); the Endangered Species Act (“ESA”); and the
    Marine Mammal Protection Act of 1973. Relying on a
    biological opinion prepared by the U.S. Fish and Wildlife
    *
    The Honorable Leslie E. Kobayashi, United States District Judge
    for the District of Hawaii, sitting by designation.
    **
    This summary constitutes no part of the opinion of the court. It
    has been prepared by court staff for the convenience of the reader.
    CTR. FOR BIO. DIVERSITY V. ZINKE               3
    Service and BOEM’s environmental impact statement
    (“EIS”), BOEM’s Regional Supervisor of Leasing and Plans
    signed a record of decision approving the Liberty project.
    The panel held that it had original jurisdiction over
    plaintiff’s challenge to BOEM’s approval of the Liberty
    project under the OCSLA’s 
    43 U.S.C. § 1349
    (c)(2), which
    included plaintiff’s challenge to the EIS prepared under
    NEPA and the biological opinion prepared under the ESA.
    The panel held that it also had jurisdiction over plaintiff’s
    claims that BOEM’s conditional approval of the Liberty
    project violated the ESA. The panel further held that the two
    statutes relevant to plaintiff’s Section 7 ESA claim – the
    OCSLA and the ESA - had conflicting jurisdictional
    provisions, and it would follow the more specific statute –
    the OCSLA. The OCSLA bifurcated jurisdiction between
    the courts of appeal and district courts. The panel concluded
    that under the OCSLA, it had jurisdiction to review whether
    BOEM’s approval violated the ESA.
    The panel concluded that BOEM acted arbitrarily and
    capriciously by failing to quantify the emissions resulting
    from foreign oil consumption in its EIS as required by the
    NEPA, or, at least, explaining thoroughly why it could not
    do so and summarizing the research upon which it relied.
    The panel also held that the Fish and Wildlife Service
    violated the ESA by (1) relying upon uncertain, nonbinding
    mitigation measures in reaching its no-adverse-effect
    conclusion in its biological opinion, and (2) failing to
    estimate the Liberty project’s amount of nonlethal take of
    polar bears. Because the panel concluded that Fish and
    Wildlife Service’s biological opinion was flawed and
    unlawful, the panel further concluded that BOEM’s reliance
    on the Fish and Wildlife Service’s opinion was arbitrary and
    4            CTR. FOR BIO. DIVERSITY V. ZINKE
    capricious. In all other respects, the panel denied the petition
    for review.
    COUNSEL
    Rebecca Noblin (argued) and Jeremy C. Lieb, Earthjustice,
    Anchorage, Alaska; Eric P. Jorgensen, Earthjustice, Juneau,
    Alaska; Kristen Monsell and Emily Jeffers, Center for
    Biological Diversity, Oakland, California; for Petitioners.
    James A. Maysonett (argued), Attorney, Appellate Section;
    Eric Grant, Deputy Assistant Attorney General; Jeffrey
    Bossert Clark, Assistant Attorney General; Environment &
    Natural Resources Division, United States Department of
    Justice, Washington, D.C.; for Respondents.
    Svend A. Brandt-Erichsen (argued) and Linda R. Larson,
    Nossaman LLP, Seattle, Washington, for Respondent-
    Intervenor.
    OPINION
    PAEZ, Circuit Judge:
    Hilcorp Alaska, LLC, is an energy management
    company seeking to produce crude oil from Foggy Island
    Bay, along the coast of Alaska in the Beaufort Sea. To
    extract the oil from under the Beaufort Sea, Hilcorp will
    need to construct an offshore drilling and production facility.
    The facility—referred to as “the Liberty project,” or “the
    Liberty prospect”—will be the first oil development project
    fully submerged in federal waters. Hilcorp estimates that the
    site contains about 120 million barrels of recoverable oil,
    CTR. FOR BIO. DIVERSITY V. ZINKE                      5
    which it hopes to extract over the course of fifteen to twenty
    years.
    The site of the Liberty project is within the outer
    Continental Shelf of the United States and thus governed by
    the Outer Continental Shelf Lands Act (“OCSLA”), 1
    
    43 U.S.C. § 1331
     et seq. OCSLA allows the Department of
    Interior—which houses the Bureau of Ocean Energy
    Management (“BOEM”)—to oversee the mineral
    exploration and development of the outer Continental Shelf. 2
    Administering the use of the Shelf under OCSLA may
    include leasing federal land for oil and gas production to
    entities like Hilcorp. See 
    43 U.S.C. §§ 1344
    ; 1331(c), (k)–
    (m). OCSLA requires BOEM to manage the outer Shelf in
    “a manner which considers [the] economic, social, and
    environmental values” of the Shelf’s natural resources.
    
    43 U.S.C. § 1344
    (a)(1).
    Before Hilcorp can begin drilling, it must obtain
    approval of the project from BOEM. Three environmental
    statutes and their concomitant regulations govern BOEM’s
    approval. First, approval of the Liberty project is considered
    a “major Federal action” under the National Environment
    Policy Act (“NEPA”), 
    42 U.S.C. § 4321
     et seq. See
    
    42 U.S.C. § 4332
    (C); 
    40 C.F.R. § 1508.18
    . NEPA requires
    BOEM to draft an “environmental impact statement”
    1
    We include a glossary of acronyms in an Appendix attached to this
    opinion.
    2
    The outer Continental Shelf includes “all submerged lands lying
    seaward of state coastal waters (3 miles offshore) which are under U.S.
    jurisdiction.” OCS Lands Act History, U.S. Department of the Interior,
    Bureau of Ocean Energy Management, http://www.boem.gov/oil-gas-
    energy/leasing/ocs-lands-act-history (last visited Aug. 19, 2020); see
    also 
    43 U.S.C. § 1331
    (a).
    6            CTR. FOR BIO. DIVERSITY V. ZINKE
    (“EIS”) evaluating the environmental consequences of the
    drilling and oil extraction. 
    42 U.S.C. § 4332
    (C). The EIS
    must contain, among other things, a statement of purpose, a
    description of the project, and a comparison of the Liberty
    project with other reasonable alternatives for extracting oil.
    Id.; 
    40 C.F.R. § 1502.12
    –1502.14. It must also include a “no
    action” alternative, in which BOEM evaluates the relative
    consequences of not approving any drilling in the Beaufort
    Sea. 
    40 C.F.R. § 1502.14
    (c). This comparative analysis is
    “the heart” of the EIS. 
    Id.
     § 1502.14.
    Second, the remarkable biodiversity of the drilling site
    implicates the Endangered Species Act of 1973 (“ESA”),
    
    16 U.S.C. § 1531
     et seq. The Liberty project requires the
    construction of an offshore gravel island, wells, a pipeline to
    transport the oil, gravel pads to support the intersections
    between pipes, ice pads, a hovercraft shelter, a small boat
    dock, a gravel mine, and additional ice roads and crossings.
    The gravel island’s proposed site is in the middle of “the
    Boulder Patch,” an isolated area of boulders and cobbles that
    supports the only high arctic kelp forest in the Alaskan
    Arctic and produces unusual species diversity and biomass.
    The Bay is home to a wealth of threatened and endangered
    marine mammals, including polar bears, six species of
    whales, three species of seals, sea lions, sea otters, and
    Pacific walruses. Seabirds, numerous species of fish, and
    larger mammals all frequent the shallow waters around the
    Bay.
    The ESA requires BOEM to ensure that its approval of
    the project does not jeopardize an endangered or threatened
    species or destroy or adversely modify the species’s habitat.
    
    16 U.S.C. § 1536
    (a)(2). BOEM must consult with either the
    U.S. Fish and Wildlife Service (“FWS”) or the National
    Marine Fisheries Service (“NMFS”), depending on the
    CTR. FOR BIO. DIVERSITY V. ZINKE                 7
    species at risk, and then either FWS or NMFS must prepare
    a biological opinion to determine whether the agency’s
    proposed action will jeopardize a species. 
    Id.
     § 1536(b)–(c).
    If BOEM concludes that the proposed action will not
    jeopardize a species or adversely modify its critical habitat—
    but that the project will result in the “incidental take” of the
    members of a species—FWS or NMFS must provide an
    “incidental take statement” authorizing such takings. A
    “take” occurs under the ESA when an animal is harassed,
    harmed, pursued, hunted, shot, wounded, killed, trapped,
    captured, or collected, or when anyone attempts to engage in
    such conduct. 
    16 U.S.C. § 1532
    (19).
    Third and finally, the proposed project must comply with
    the Marine Mammal Protection Act of 1972 (“MMPA”),
    
    16 U.S.C. § 1361
     et seq. The MMPA is narrower but more
    restrictive than the ESA. It broadly prohibits the take of any
    marine mammal. 
    16 U.S.C. § 1371
    (a). Under the MMPA,
    the Department of Interior may promulgate incidental take
    regulations that allow an agency to take marine mammals
    where such take is “in accord with sound principles of
    resource protection and conservation” as provided in the
    MMPA. 
    Id.
     § 1371(a)(3)(A).
    Relying on a biological opinion prepared by FWS and
    BOEM’s own EIS, BOEM’s Regional Supervisor of Leasing
    and Plans signed a record of decision approving the Liberty
    project. The Center for Biological Diversity and four other
    conservation organizations (collectively, “CBD”), dispute
    the legality of BOEM’s and FWS’s actions, arguing that the
    agencies failed to comply adequately with the procedural
    requirements imposed by NEPA, the ESA, and the MMPA.
    Specifically, CBD claims that (1) BOEM violated NEPA by
    arbitrarily and capriciously estimating the environmental
    consequences of the alternatives included in the EIS;
    8           CTR. FOR BIO. DIVERSITY V. ZINKE
    (2) FWS violated the ESA and MMPA by producing a
    legally inadequate biological opinion; and (3) BOEM
    violated the ESA by relying on FWS’s unlawful biological
    opinion to approve the Liberty project. Hilcorp intervened
    on behalf of BOEM. We agree in part with CBD and vacate
    BOEM’s approval of the project.
    I. Court of Appeals Review
    A. Jurisdiction
    We have original jurisdiction over CBD’s challenge to
    BOEM’s approval of the Liberty project under 
    43 U.S.C. § 1349
    (c)(2) (“Any action of the Secretary to approve . . .
    any development and production plan under this subchapter
    shall be subject to judicial review only in a United States
    court of appeals for a circuit in which an affected State is
    located.”). This includes CBD’s challenge to the EIS
    prepared under NEPA and the biological opinion prepared
    by FWS under the ESA. See 
    16 U.S.C. § 1531
    ; Am. Bird
    Conservancy v. F.C.C., 
    545 F.3d 1190
    , 1191 (9th Cir. 2008).
    We also have jurisdiction over CBD’s claims that
    BOEM’s conditional approval of the Liberty project violated
    the ESA. “[W]hen a Section 7 claim challenges an agency
    order issued pursuant to a substantive statute with a ‘more
    specific’ judicial review scheme than the ESA, courts must
    evaluate the plaintiff’s claims under the jurisdictional
    provisions of that substantive statute.” Ctr. for Bio.
    Diversity v. E.P.A., 
    847 F.3d 1075
    , 1089 (9th Cir. 2017)
    (quoting Am. Bird. Conservancy, 
    545 F.3d at 1194
    ). When
    two claims are “inextricably intertwined between two
    statutes,” “and those statutes contain conflicting
    jurisdictional provisions,” we follow the more specific
    statute. 
    Id.
    CTR. FOR BIO. DIVERSITY V. ZINKE                 9
    The two statutes relevant to CBD’s Section 7 ESA claim
    are OCSLA and the ESA, and they have conflicting
    jurisdictional provisions. OCSLA grants standing to “any
    person” to “compel compliance” with the Act. 
    43 U.S.C. § 1349
    (a)(1). A court of appeals has original jurisdiction
    under OCSLA to review the Secretary of the Interior’s action
    where that action is “to approve, require modification of, or
    disapprove . . . any development and production plan” under
    the Act. 
    Id.
     § 1349(c)(2). If the agency action does not
    “approve, require modification of, or disapprove” any plan,
    but still arises from (1) “any operation . . . which involves
    . . . development” or (2) “the cancellation, suspension, or
    termination of a lease or permit,” then federal district courts
    have jurisdiction to review the agency action.              Id.
    § 1349(b)(1).
    The ESA instead allows a citizen to “commence a civil
    suit on his own behalf . . . to enjoin any person, including the
    United States and any other governmental instrumentality or
    agency . . . , who is alleged to be in violation of any
    provision of this chapter or regulation issued under the
    authority thereof[.]” 
    16 U.S.C. § 1540
    (g)(1)(A). The ESA
    citizen-suit provision also provides, “The district courts shall
    have jurisdiction, without regard to the amount in
    controversy or the citizenship of the parties, to enforce any
    such provision or regulation, or to order the Secretary to
    perform such act or duty[.]” 
    Id.
     § 1540(g)(1).
    OCSLA is the more specific jurisdictional statute. It
    bifurcates jurisdiction between the courts of appeal and
    district courts, and it refers specifically to BOEM’s
    “approv[al]” of development plans, like the one at issue here.
    Additionally, OCSLA and the ESA are “inextricably
    intertwined”: BOEM’s lawful approval under OCSLA is
    contingent on whether it properly complies with the ESA.
    10           CTR. FOR BIO. DIVERSITY V. ZINKE
    Under OCSLA, then, we have jurisdiction to review whether
    BOEM’s approval of the Liberty project violated the ESA.
    
    43 U.S.C. § 1349
    (c)(2).
    B. Standard of Review
    NEPA, the ESA, and the MMPA all lack independent
    judicial review provisions. Claims arising under all three are
    therefore reviewed under the Administrative Procedure Act
    (“APA”), 
    5 U.S.C. § 551
     et seq., which authorizes courts to
    set aside agency actions, findings, and conclusions if they
    are “arbitrary, capricious, an abuse of discretion, or
    otherwise not in accordance with law,” 
    5 U.S.C. § 706
    (2)(A); see also Klamath-Siskiyou Wildlands Ctr. v.
    Bureau of Land Mgmt., 
    387 F.3d 989
    , 992 (9th Cir. 2004).
    In reviewing the adequacy of an EIS under NEPA, we
    employ “a rule of reason” analysis to determine whether the
    discussion of the environmental consequences included in
    the EIS is sufficiently thorough. Kern v. U.S. Bureau of
    Land Mgmt., 
    284 F.3d 1062
    , 1071 (9th Cir. 2002) (internal
    quotation marks omitted). The rule of reason analysis
    requires evaluating whether the agency took a sufficiently
    “hard look” at probable consequences; it is “essentially the
    same” as an abuse of discretion analysis. 
    Id.
     at 1071–72
    (internal quotation marks omitted).
    II. NEPA
    A. The EIS Process
    We begin with CBD’s challenge to BOEM’s NEPA
    compliance. NEPA “is our basic national charter for
    protection of the environment.” 
    40 C.F.R. § 1500.1
    (a). The
    statute provides environmental protection not by mandating
    “particular results,” but by prescribing the process that an
    CTR. FOR BIO. DIVERSITY V. ZINKE                     11
    agency must follow to evaluate and approve an action that
    will have environmental consequences. Robertson v.
    Methow Valley Citizens Council, 
    490 U.S. 332
    , 350 (1989).
    The EIS is the linchpin of NEPA’s procedural
    requirements. An EIS must be prepared for any and all
    “major Federal actions significantly affecting the quality of
    the human environment.” 3 
    42 U.S.C. § 4332
    (C); see also
    Ctr. for Bio. Diversity v. U.S. Dep’t of Interior, 
    623 F.3d 633
    , 642 (9th Cir. 2010).
    The purpose of the EIS is twofold: first and foremost, it
    is an action-forcing device, ensuring that the goals of NEPA
    are infused into the government’s actions. 
    40 C.F.R. § 1502.1
    . 4 NEPA’s requirements “are to be strictly
    interpreted ‘to the fullest extent possible’ in accord with the
    policies embodied in the Act.” State of Cal. v. Block,
    
    690 F.2d 753
    , 769 (9th Cir. 1982) (quoting 
    42 U.S.C. § 4332
    (1)). Second, the EIS provides important information
    3
    A “[m]ajor Federal action” includes an action with “effects that
    may be major” and is “potentially subject to Federal control and
    responsibility.” 
    40 C.F.R. § 1508.18
    . The “[a]pproval of specific
    projects, such as construction or management activities located in a
    defined geographic area,” may be major federal actions.             
    Id.
    § 1508.18(b)(4). “Projects” can “include actions approved by permit or
    other regulatory decision as well as federal and federally assisted
    activities.” Id.
    4
    We rely on two sets of NEPA regulations. The NEPA regulations
    promulgated by the Council on Environmental Quality (CEQ), codified
    at 
    40 C.F.R. §§ 1500.1
    –1508.28, provide NEPA guidance to all federal
    agencies. The Department of Interior, like many other agencies, has also
    promulgated its own NEPA regulations, codified at 
    43 C.F.R. §§ 46.10
    –
    46.450, to be used alongside the CEQ regulations.
    12           CTR. FOR BIO. DIVERSITY V. ZINKE
    to the public and any party interested in the proposed
    environmental action. See Robertson, 
    490 U.S. at 356
    .
    Agencies prepare EISs in two stages. See 
    40 C.F.R. § 1502.9
    (a). First, the agency creates a draft EIS. See
    
    40 C.F.R. § 1502.9
    (b). The draft examines the scope of the
    federal action, evaluates the consequences of the action, and
    includes viable alternatives for the project. Id.; see also
    
    42 U.S.C. § 4332
    (c). The agency has discretion to develop
    the alternatives it considers, see Citizens Against Burlington,
    Inc. v. Busey, 
    938 F.2d 190
    , 195 (D.C. Cir. 1991), but a “no
    action alternative”—in which the agency evaluates the
    consequences of taking no action—must be considered in
    every EIS, to provide a baseline against which every action
    alternative is evaluated, see 
    40 C.F.R. § 1502.14
    (d). The no-
    action alternative analysis should be “[i]nformed and
    meaningful,” Bob Marshall All. v. Hodel, 
    852 F.2d 1223
    ,
    1228 (9th Cir. 1988), and the agency must not minimize
    negative side effects, N. Alaska Envtl. Ctr. v. Kempthorne,
    
    457 F.3d 969
    , 975 (9th Cir. 2006).
    The discussion of environmental consequences must be
    “reasonably thorough.” Kern, 
    284 F.3d at 1071
    . NEPA
    emphasizes the early presentation of relevant information to
    facilitate reaching fully informed decisions. See Blue
    Mountains Biodiversity Project v. Blackwood, 
    161 F.3d 1208
    , 1216 (9th Cir. 1998). Drafting an EIS “necessarily
    involves some degree of forecasting,” and the agency “must
    use its best efforts to find out all that it reasonably can” when
    predicting the environmental effects of the proposed action.
    City of Davis v. Coleman, 
    521 F.2d 661
    , 676 (9th Cir. 1975).
    After completing the draft, the agency must then “[m]ake
    diligent efforts to involve the public in preparing and
    implementing [its] NEPA procedures,” including soliciting
    public comments where appropriate. 
    40 C.F.R. § 1506.6
    (a);
    CTR. FOR BIO. DIVERSITY V. ZINKE               13
    see also 
    id.
     § 1506.6(b)–(f). The substantive comments
    received by the agency, and the agency’s responses to them,
    are attached to the final EIS. See Block, 
    690 F.2d at
    772–73
    (quoting 
    40 C.F.R. § 1500.10
    (a)).
    *     *    *
    CBD argues that BOEM’s EIS is arbitrary and capricious
    under the APA because BOEM improperly (1) relied on
    different methodologies in calculating the lifecycle
    greenhouse gas emissions produced by the no-action
    alternative and the other project alternatives, thus making the
    options incomparable, and (2) failed to include a key
    variable (foreign oil consumption) in its analysis of the no-
    action alternative. We consider each in turn.
    B. Comparison        of   the       Action   and   No-Action
    Alternatives
    CBD argues that BOEM unlawfully used different
    methodologies to calculate the greenhouse gas emissions
    resulting from the Liberty project and the no-action
    alternative. We disagree.
    CBD is correct that using different methodologies to
    capture the emissions resulting from each alternative would
    indeed prevent the agency from making an “informed and
    meaningful” choice, see Bob Marshall All., 
    852 F.2d at 1228
    , because the alternatives would be incomparable.
    But the record indicates that BOEM did not apply different
    methods in comparing the action and the no-action
    alternatives.
    In its final EIS, BOEM considered various alternatives:
    the Proposed Action (the Liberty project), other action
    alternatives (each of which propose different strategies,
    14           CTR. FOR BIO. DIVERSITY V. ZINKE
    locations, or other modifications of the Proposed Action),
    and the no-action alternative, in which BOEM analyzed the
    effects of not leasing the land at all. To calculate the
    emissions for each of the action alternatives, BOEM
    calculated both the “upstream” and the “downstream”
    emissions. Upstream emissions are those that result directly
    from the project itself (e.g., construction and operation), and
    downstream emissions are those that result from the
    consumption of the oil produced by the project (e.g., heating
    homes or fueling cars). BOEM then summed the two types
    of emissions, resulting in a “lifecycle greenhouse gas
    emissions” estimate for each alternative. To facilitate
    comparisons across the action alternatives, the total lifecycle
    emissions for each proposed plan were converted to metric
    tons of “carbon dioxide equivalents”—even though
    emissions would include methane, nitrous oxide, and other
    greenhouse gases.
    The lifecycle greenhouse gas emissions for the no-action
    alternative were not calculated by directly summing its
    upstream and downstream emissions.               The upstream
    emissions for the no-action alternative are, clearly, zero. The
    direct downstream emissions of the no-action alternative are
    zero, but—as BOEM recognized—its indirect downstream
    emissions may be much higher. Not drilling at the proposed
    site may cause global oil supply to fall, demand to rise, and,
    as a result, require drilling and oil extraction elsewhere. To
    capture these indirect downstream emissions, BOEM used a
    market-simulation model to predict the greenhouse gas
    emissions for energy sources that would substitute for the oil
    not produced at Liberty.
    CBD argues that the use of this model renders the
    choices incomparable. But, as the government notes, the
    Proposed Action and action alternatives implicitly take this
    CTR. FOR BIO. DIVERSITY V. ZINKE              15
    analysis into account: if the Liberty site is developed, none
    of the emissions in other parts of the United States estimated
    under the no-action alternative will result. In other words,
    BOEM could have instead used the market simulation model
    to offset the emissions calculated under each of the action
    alternatives and then compared it to zero, the lifecycle
    emissions produced by the no-action alternative. Summing
    all emissions from the proposed project assumes that, if
    Liberty is developed, there would be no need for the other
    sites to satisfy demand under the no-action alternative. The
    total numbers would be different, but the absolute
    differences between them would be the same. Both methods
    of calculation result in net—not gross—emissions. The
    analysis is ultimately a relative comparison, sufficient for
    making a “reasoned choice among alternatives.” 
    40 C.F.R. § 1502.22
    (a). We conclude BOEM did not arbitrarily and
    capriciously apply a different method of calculation in
    estimating the emissions from the action and no-action
    alternatives.
    C. Omission of Emissions Resulting from Foreign Oil
    Consumption
    But CBD’s second argument is persuasive. CBD argues
    that BOEM arbitrarily failed to include emissions estimates
    resulting from foreign oil consumption in its analysis of the
    no-action alternative. In its EIS, BOEM concluded that the
    Proposed Action and the action alternatives would each
    produce about 64,570,000 metric tons of carbon dioxide
    equivalents. It then estimated that the no-action alternative
    would produce—somewhat perplexingly—89,940,000
    metric tons of carbon dioxide equivalents, 25,370,000 more
    metric tons than if the land were leased under any scenario.
    The EIS explains that the no-action alternative will result in
    more emissions because the oil substituted for the oil not
    16           CTR. FOR BIO. DIVERSITY V. ZINKE
    produced at Liberty will come from places with
    “comparatively weaker environmental protection standards
    associated with exploration and development of the
    imported product and increased emissions from
    transportation.” CBD explains that BOEM reached this
    counterintuitive result by omitting a key variable in its
    analysis: foreign oil consumption.
    Understanding why foreign oil consumption is critical to
    BOEM’s alternatives analysis requires some basic
    economics principles. If oil is produced from Liberty, the
    total supply of oil in the world will rise. Increasing global
    supply will reduce prices. Once prices drop, foreign
    consumers will buy and consume more oil. The model used
    by BOEM assumes that foreign oil consumption will remain
    static, whether or not oil is produced at Liberty.
    This omission, according to CBD, makes BOEM’s
    analysis “misleading” because it fails to capture the
    emissions caused by increased global consumption in its
    estimate of Liberty’s downstream emissions. BOEM
    acknowledges that the no-action alternative will cause
    foreign oil consumption to decline; the EIS estimates that the
    no-action alternative will result in a reduction in oil
    consumption of one, four, or six billion barrels of oil,
    depending on the market price of oil. But the impacts on
    greenhouse gas resulting from such reductions in oil
    consumption “are not captured” in the EIS because BOEM
    determined it did not have sufficiently “reliable information
    on foreign emissions factors and consumption patterns.”
    CBD replies that BOEM was both required and able to
    estimate the variable and include its effect. We agree.
    NEPA requires agencies to evaluate the direct and
    indirect effects of the proposed action. 
    40 C.F.R. § 1502.16
    .
    Indirect and direct effects are both “caused by the action,”
    CTR. FOR BIO. DIVERSITY V. ZINKE                  17
    but direct effects occur “at the same time and place” as the
    proposed project, while indirect effects occur “later in time
    or [are] farther removed in distance.” 
    40 C.F.R. § 1508.8
    (a),
    (b). The agency need consider only indirect effects that are
    “reasonably foreseeable,” 
    id.
     § 1508.8(b); or those that “a
    person of ordinary prudence would take [] into account in
    reaching a decision.” EarthReports, Inc. v. F.E.R.C.,
    
    828 F.3d 949
    , 955 (D.C. Cir. 2016) (internal quotation marks
    omitted); see also 
    40 C.F.R. § 1502.22
    (b). An increased risk
    of an oil spill caused by an increase in crude oil tanker traffic,
    for example, is a reasonably foreseeable indirect effect of a
    proposed dock extension. See Ocean Advocates v. U.S.
    Army Corps. of Eng’rs, 
    402 F.3d 846
    , 867–70 (9th Cir.
    2005). “[G]rowth inducing effects” to a forest that result
    from a project that alters “pattern[s] of land use” are also
    indirect impacts that must be considered. 
    40 C.F.R. § 1508.8
    .
    An EIS that does not adequately consider the indirect
    effects of a proposed action violates NEPA. In Sierra Club
    v. Federal Energy Regulatory Comm’n, 
    867 F.3d 1357
     (D.C.
    Cir. 2017), for example, the D.C. Circuit concluded that the
    Federal Energy Regulatory Commission had unlawfully
    conducted its EIS for a natural gas pipeline project because
    it failed to quantify the indirect greenhouse gas emissions
    that would result from the burning of the natural gas
    transported by the pipelines. 
    Id. at 1374
    . The agency should
    have “either given a quantitative estimate of the downstream
    greenhouse emissions,” or “explained more specifically why
    it could not have done so.” 
    Id.
     Greenhouse gas emissions
    were an indirect, reasonably foreseeable consequence of the
    pipeline, and FERC’s justification for its omission—that
    “emission estimates would be largely influenced by
    assumptions rather than direct parameters about the
    project”—was unsatisfactory. 
    Id.
     The effects of the
    18               CTR. FOR BIO. DIVERSITY V. ZINKE
    agency’s assumptions on its estimates simply “can be
    checked” by disclosing the estimates so that readers could
    make informed decisions regarding the project and its
    consequences. Id.; see also WildEarth Guardians v. Zinke,
    
    368 F. Supp. 3d 41
    , 68 (D.D.C. 2019) (determining that an
    agency’s assertion that “quantifying [greenhouse gas]
    emissions . . .would be overly speculative” was “belied by
    an administrative record replete with information on oil and
    gas development and [greenhouse gas] emissions”).
    BOEM refers to the omission of foreign oil consumption
    in two separate pages of the final, 600-page EIS. The first is
    in Appendix B of the EIS, in response to public comments
    expressing concern over the omission of foreign oil
    consumption. BOEM responds only that “[c]ontext suggests
    that any change in foreign oil consumption resulting from
    the pending decision on the Liberty DPP would be very
    small,” 5 and because “Liberty DPP represents a very small
    fraction of the amount of oil comprising the global market,”
    it “could only have a negligible impact on worldwide oil
    prices and, as a result, only a negligible impact on foreign
    consumption and emissions levels.” It adds that “[e]ven if
    BOEM could reliably estimate these marginal differences
    (which it cannot, given the lack of reliable information on
    foreign emissions factors and consumption patterns), such
    estimates would not change the end results of BOEM’s
    analysis to a meaningful extent.” BOEM cites to no
    evidence in support of these conclusions and does not
    provide any further explanation for the omission.
    Appendix B then refers readers to a general report,
    incorporated by reference into the EIS, that describes the
    market-simulation model and its limitations. The relevant
    5
    “DPP” is shorthand for “development and production plan.”
    CTR. FOR BIO. DIVERSITY V. ZINKE               19
    portion of that report explains that “[e]xcluding the foreign
    oil and gas markets is reasonable” because “[o]il
    consumption in each country is different, and BOEM does
    not have information related to which countries would
    consume less oil.” Again, BOEM does not cite any materials
    in support of these statements nor describe the research it
    relied upon to reach these conclusions.
    This is insufficient to satisfy NEPA’s requirements.
    Emissions resulting from the foreign consumption of oil are
    surely a “reasonably foreseeable” indirect effect of drilling
    at Liberty, just as foreseeable as the emissions resulting from
    the consumption of oil produced at sites other than Liberty,
    which the market-simulation model already considers. Even
    if the extent of the emissions resulting from increased
    foreign consumption is not foreseeable, the nature of the
    effect is. Mid States Coal. for Progress v. Surface Transp.
    Bd., 
    345 F.3d 520
    , 549 (8th Cir. 2003). This is sufficient to
    require estimation or explanation under NEPA. 
    Id.
    The record belies BOEM’s contention that it could not
    have summarized or estimated foreign emissions with
    accurate or credible scientific evidence. See Seattle
    Audubon Soc. v. Espy, 
    998 F.2d 699
    , 704–05 (9th Cir. 1993).
    Various studies provided by CBD in the administrative
    record confirm the effect of increasing domestic oil supply
    on foreign consumption and the feasibility of its estimation.
    In one study, the Stockholm Environment Institute—noting
    that BOEM omitted the same calculation in its analysis of
    the effects of the Keystone Pipeline—demonstrates how an
    increase in foreign oil consumption translates into
    greenhouse gas emissions. See Peter Erickson, U.S. Again
    Overlooks Top CO2 Impact of Expanding Oil Supply, but
    That Might Change, Stockholm Environment Institute (Apr.
    30, 2016), http://www.sei.org/perspectives/us-co2-impact-
    20           CTR. FOR BIO. DIVERSITY V. ZINKE
    oil-supply. Using a “simple calculation,” relying on
    parameters publicly provided in BOEM’s report, the
    Institute calculates the expected resultant greenhouse gas
    emissions from increased foreign consumption of oil. It
    concludes that developing the Pipeline would cause an
    increase in global oil consumption ten times greater than the
    increase in domestic consumption forecasted by BOEM.
    Other studies in the record confirm the same: domestic
    consumption impacts foreign oil consumption, and increases
    in foreign oil consumption can be translated into estimates
    of greenhouse gas emissions. See Peter Erickson and
    Michael Lazarus, Impact of the Keystone XL Pipeline on
    Global Oil Markets and Greenhouse Gas Emissions, Nature
    Climate Change 778, 778–80 (2014) (modeling increased
    global oil consumption caused by the Keystone Pipeline and
    finding an increase in greenhouse gas emissions four times
    greater than that predicted by the model that did not account
    for global oil market effects). Jason Bordoff and Trevor
    Houser, Navigating the U.S. Oil Export Debate, Columbia
    SIPA Center on Global Energy Policy, Jan. 2015, at 57
    (assessing the net greenhouse gas impact of an increase in
    global crude oil demand under different scenarios).
    BOEM now explains that these studies rely on
    “simplistic assumptions that [fall] well short of the detailed
    model that BOEM used to analyze the U.S. energy market,”
    but it is unclear from the record why these assumptions are
    any more simplistic than those the market-simulation model
    incorporates. The model assumes, for example, near
    constant oil and gas demand over the next 40 to 70 years, an
    unrestricted supply of foreign oil for substitution, and that all
    oil and gas produced domestically is consumed
    domestically. BOEM’s conclusion for the higher emissions
    produced by the no-action alternative assumes that the
    petroleum products substituted for oil not produced at
    CTR. FOR BIO. DIVERSITY V. ZINKE               21
    Liberty will come from places with “comparatively weaker
    environmental protection standards.” It is unclear from the
    administrative record what justifies these assumptions and
    not those needed to estimate foreign oil consumption.
    Even if the nature of BOEM’s assumptions did not
    sufficiently demonstrate the need for further explanation, the
    result upon which the agency relied surely did. BOEM’s
    conclusion that not drilling will result in more carbon
    emissions than drilling is counterintuitive. An agency acts
    arbitrarily and capriciously when it reaches a decision that is
    “so implausible that it could not be ascribed to a difference
    in view or the product of agency expertise.” Motor Vehicle
    Mfrs. Ass’n of U.S., Inc. v. State Farm Mut. Auto. Ins. Co.,
    
    463 U.S. 29
    , 43 (1983). Without further explanation, we
    cannot ascribe the implausibility of the result to BOEM’s
    expertise or rational decision-making. We will uphold a
    decision “of less than ideal clarity if the agency’s path may
    be reasonably discerned,” but we cannot “supply a reasoned
    basis for the agency’s action that the agency itself has not
    given.” 
    Id. at 43, 57
     (internal quotation marks omitted).
    We “understand that in some cases quantification may
    not be feasible.” Sierra Club, 867 F.3d at 1374. But even if
    BOEM is unable to quantitatively evaluate the emissions
    generated by foreign countries in the absence of the Liberty
    project, it still must thoroughly explain why such an estimate
    is impossible. The Department of Interior has promulgated
    a regulation addressing such situations, where “incomplete
    or unavailable information” impedes the agency’s ability to
    evaluate a “reasonably foreseeable significant adverse
    effect[]” of the project. 
    40 C.F.R. § 1502.22
    . The regulation
    requires the agency to include a statement explaining that the
    information is lacking, its relevance, a summary of any
    existing credible evidence evaluating the foreseeable
    22           CTR. FOR BIO. DIVERSITY V. ZINKE
    adverse impacts, and the agency’s evaluation of the impacts
    based upon “theoretical approaches or research methods
    generally accepted in the scientific community.” 
    40 C.F.R. § 1502.22
    (b)(1). These requirements are read “in the
    context of the more general requirements for preparation of
    an EIS,” including the “rigorous evaluation” of the indirect,
    direct, and cumulative effects of the selected alternatives.
    National Environmental Policy Act Regulations, 50 FR
    32,234, 32,237 (Aug. 9, 1985); see also 
    40 C.F.R. §§ 1502.16
    (a)–(b), 1508.8(b).
    The EIS’s two-page explanation of BOEM’s decision to
    omit foreign oil emissions is insufficient to meet these
    requirements. BOEM did not summarize existing research
    addressing foreign oil emissions nor attempt to estimate the
    magnitude of such emissions. It cannot ignore basic
    economics principles and state—without citations or
    discussion—that the impact of the Liberty project on foreign
    oil consumption will be negligible.           See WildEarth
    Guardians v. Bureau of Land Mgmt., 
    870 F.3d 1222
    , 1237–
    38 (10th Cir. 2017); Mont. Envtl. Info. Ctr. v. U.S. Off. of
    Surface Mining, 
    274 F. Supp. 3d 1074
    , 1098 (D. Mont.
    2017). Nor can it ignore this foreseeable effect entirely. EIS
    estimates often involve some “[r]easonable forecasting and
    speculation.” Scientists’ Inst. For Pub. Info., Inc. v. Atomic
    Energy Comm’n, 
    481 F.2d 1079
    , 1092 (D.C. Cir. 1973).
    Some “educated assumptions are inevitable in the NEPA
    process,” and the “effects of assumptions on estimates can
    be checked by disclosing those assumptions so that readers
    can take the resulting estimates with the appropriate amount
    of salt.” Sierra Club, 867 F.3d at 1374.
    We note that we typically accord significant deference to
    an agency’s decisions that require a “high level of technical
    expertise.” Kleppe v. Sierra Club, 
    427 U.S. 390
    , 412 (1976).
    CTR. FOR BIO. DIVERSITY V. ZINKE              23
    But such deference applies only when the agency is making
    predictions “within its area of special expertise.” Baltimore
    Gas & Elec. Co. v. Nat. Res. Def. Council, Inc., 
    462 U.S. 87
    ,
    103 (1983). BOEM’s area of expertise is the management
    of “conventional (e.g., oil and gas) and renewable energy-
    related” functions, including “activities involving resource
    evaluation, planning, and leasing.” U.S. Dep’t of Interior,
    Sec. Order No. 3299A2, Establishment of the Bureau of
    Ocean Energy Management, the Bureau of Safety and
    Environmental Enforcement, and the Office of Natural
    Resources Revenue, § 2 (Aug. 29, 2011). The scope of its
    expertise does not include the economic analysis of
    greenhouse gas emissions. Therefore, we do not readily
    defer to its decision to exclude a discussion of foreign oil
    consumption, particularly in light of our conclusion that its
    decision to do so was unreasonable. See The Lands Council
    v. McNair, 
    537 F.3d 981
    , 993 (9th Cir. 2008), overruled in
    part on other grounds by Winter v. Nat. Res. Def. Council,
    Inc., 
    555 U.S. 7
     (2008).
    In short, the EIS “should have either given a quantitative
    estimate of the downstream greenhouse gas emissions” that
    will result from consuming oil abroad, or “explained more
    specifically why it could not have done so,” and provided a
    more thorough discussion of how foreign oil consumption
    might change the carbon dioxide equivalents analysis.
    Sierra Club, 867 F.3d at 1374. BOEM has the statutory
    authority to act on the emissions resulting from foreign oil
    consumption. If it later concludes that such emissions will
    be significant, it may well approve another alternative
    included in the EIS or deny the lease altogether. Cf. Dep’t
    of Transp. v. Public Citizen, 
    541 U.S. 752
    , 766–68, 770
    (2004). For these reasons, we agree with CBD that BOEM’s
    alternatives analysis in the EIS was arbitrary and capricious.
    24           CTR. FOR BIO. DIVERSITY V. ZINKE
    III. ESA
    A. Section 7 Consultation and Section 9 Take Regulation
    CBD next challenges FWS’s compliance with the ESA.
    In accordance with NEPA’s requirements, FWS prepared for
    BOEM a biological opinion that discusses the effects of the
    project on all threatened species and their habitats in the Bay.
    In the opinion, FWS concluded that polar bears—which are
    classified as threatened marine mammals—were present in
    the project area, but that the project was unlikely to
    jeopardize their continued existence or adversely modify
    their habitat. CBD argues that FWS violated the ESA
    because portions of its biological opinion and incidental take
    statement were arbitrary and capricious.
    The Department of the Interior and, by delegation, FWS,
    is responsible for implementing the ESA. See 
    16 U.S.C. § 1531
     et seq. Section 9 of the ESA regulates the “taking”
    of a threatened or endangered species. It prohibits “any
    person”—including an “instrumentality” of federal, state, or
    municipal government, see 
    id.
     § 1532(12), (13)—from,
    among other things, “taking” endangered wildlife, fish, or
    plants, id. § 1538(a). A “take” occurs under the ESA when
    an animal is harassed, harmed, pursued, hunted, shot,
    wounded, killed, trapped, captured, or collected, or when
    anyone attempts to engage in such conduct. Id. § 1532(19).
    FWS may issue a temporary permit approving conduct
    normally barred by Section 9 if the taking is incidental to an
    otherwise lawful activity. Id. § 1539(a)(1)(B). Before FWS
    may issue such a permit, it must find that (1) the applicant
    will minimize and mitigate the negative impacts of the
    taking; (2) the applicant will ensure adequate funding for the
    plan; and (3) the taking will not appreciably reduce the
    CTR. FOR BIO. DIVERSITY V. ZINKE               25
    likelihood of the survival and recovery of the species in the
    wild. Id. § 1539(a)(2)(B).
    Section 7 of the ESA describes the process for agency
    consultation. Unlike Section 9, it does not contain an
    outright prohibition on take; it requires only that an agency
    consult with FWS or NMFS before it takes any action that
    may affect a species listed as threatened or endangered under
    the ESA. See id. § 1536(a)(2), (4).
    “Section 7 consultation” begins with an assessment of
    the species affected by the action. If a threatened or
    endangered species “may be present” in the area of the
    proposed action, the agency must conduct a biological
    assessment to determine whether the species will be
    adversely affected by the project. Id. § 1536(c)(1); see also
    
    50 C.F.R. § 402.14
    (a). If BOEM concludes that the species
    is likely to be adversely affected, it must initiate formal
    consultation with either FWS or NMFS (here, FWS). After
    formal consultation, FWS issues a written opinion (a
    “biological opinion,” or “BiOp”), concluding either that the
    project is unlikely to adversely affect the species or that the
    action will likely jeopardize the species or adversely modify
    its critical habitat. See 
    16 U.S.C. § 1536
    (b)(3)(A). If FWS
    determines that the proposed action is likely to jeopardize
    the species or modify its habitat, then it must suggest
    reasonable and prudent alternatives that could be taken by
    the agency. Id; see also 
    50 C.F.R. § 402.14
    (g).
    If, however, FWS determines that the proposed action
    will neither harm the species nor adversely modify its
    habitat, it may authorize the taking of a species incidental to
    the proposed project. 16 U.S.C § 1536(b)(4). To determine
    whether the action will ultimately jeopardize a listed species
    or adversely modify its habitat, the agency may rely on
    mitigation measures proposed by the project planners. See
    26            CTR. FOR BIO. DIVERSITY V. ZINKE
    Selkirk Conservation All. v. Forsgren, 
    336 F.3d 944
    , 955
    (9th Cir. 2003).
    When the agency authorizes the incidental taking of a
    species, it must also issue an “incidental take statement” with
    the biological opinion. 
    50 C.F.R. § 402.14
    (i); Ctr. for Bio.
    Diversity v. Salazar, 
    695 F.3d 893
    , 909 (9th Cir. 2012). The
    incidental take statement estimates the amount of the
    project’s incidental take of the listed species, includes any
    “reasonable and prudent measures” considered “necessary
    or appropriate to minimize such impact,” and—in the case
    of marine mammals like the polar bear—describes specific
    measures necessary to comply with the aforementioned
    provisions of the MMPA. 
    50 C.F.R. § 402.14
    (i)(1); see also
    Salazar, 695 F.3d at 909; 
    16 U.S.C. § 1536
    (b)(4). The
    statement also describes the terms that must be followed by
    BOEM or the applicant to implement any mitigation
    measures specified in the statement. 
    16 U.S.C. § 1536
    (b)(4).
    A taking that complies with the terms and conditions of a
    Section 7 incidental take statement is not prohibited by
    Section 9. Salazar, 695 F.3d at 909; 
    16 U.S.C. § 1536
    (o)(2);
    
    50 C.F.R. § 402.14
    (i)(5).
    B. Coordination between the ESA and the MMPA
    The MMPA prohibits the take or harassment of animals,
    but its scope is narrower and its procedures distinct from
    those of Sections 7 and 9 of the ESA. It entirely prohibits
    the take of marine mammals in U.S. waters. “Take” in the
    MMPA is similar to “take” under Section 9 of the ESA; the
    MMPA defines it as encompassing, among other things,
    “harassment,” “torment,” or “annoyance” which “has the
    potential to injure . . . or . . . disturb a marine mammal . . . in
    the wild by causing disruption of behavioral patterns,
    including, but not limited to, migration, breathing, nursing,
    CTR. FOR BIO. DIVERSITY V. ZINKE                27
    breeding, feeding, or sheltering.” 
    16 U.S.C. § 1362
    (13),
    (18)(A)(i)–(ii); see also 
    id.
     § 1371(a).
    As under the ESA, the MMPA allows FWS to permit the
    incidental take of “small numbers” of marine mammals
    pursuant to a specified activity for a limited period. The total
    incidental take must have a “negligible impact” on the
    species and cannot have an “unmitigable adverse impact” on
    the availability of the species for specified subsistence uses.
    
    16 U.S.C. § 1371
    (a)(5)(A); see also 
    50 C.F.R. § 18.27
    (b). If
    the incidental take meets these requirements, FWS may then
    prescribe regulations setting forth permissible methods of
    taking the species in question and describing methods of
    effecting the least adverse impact possible on the species and
    its habitat. See 
    50 C.F.R. § 18.27
    (b). The regulations are
    subject to public notice-and-comment.               
    16 U.S.C. § 1371
    (a)(5)(D)(iii). Once the regulations are finalized and
    promulgated, FWS issues individual letters of authorization
    to the agency, authorizing the project and the take. 
    Id.
    Both the ESA and the MMPA apply when, as here, an
    agency seeks approval for the incidental take of threatened
    and endangered marine mammals. The MMPA is more
    restrictive than the ESA; when the two statutes conflict, the
    relevant MMPA provision applies. 
    Id.
     § 1543. FWS cannot
    issue an incidental take statement authorizing the take of an
    endangered or threatened species under the ESA until the
    take has been authorized under the MMPA. See id.
    § 1536(b)(4)(C); see also Incidental Take of Endangered,
    Threatened, and Other Depleted Marine Mammals, 
    54 Fed. Reg. 40,338
    , 40,346 (Sept. 29, 1989), codified at 
    50 C.F.R. §§ 18.27
    , 228, 402.14. The incidental take statement must
    incorporate any mitigation measures required under the
    MMPA. 
    50 C.F.R. § 402.14
    (i)(1)(iii).
    28           CTR. FOR BIO. DIVERSITY V. ZINKE
    In consultation with BOEM, FWS issued a BiOp
    authorizing the Liberty project’s incidental take of polar
    bears. 
    16 U.S.C. § 1536
    (b)(4). The BiOp acknowledges that
    Liberty may “adversely affect polar bears through
    disturbance, an increase in polar bear-human interactions,
    and habitat loss,” and concludes that denning polar bear
    mothers and cubs are most likely to be affected, because they
    are the most sensitive to the disturbance caused by the
    project. The disturbance from the project is expected to
    include (1) construction, drilling, production operations,
    maintenance, and ancillary activities associated with the
    project; (2) noise and disturbance caused by aircraft, vessel,
    hovercraft, and vehicle traffic; and (3) drilling and
    production activities. The BiOp concludes that the proposed
    action is “not likely to jeopardize the continued existence of
    polar bears by reducing appreciably the likelihood of
    survival and recovery in the wild by reducing reproduction,
    numbers, or distribution of this species.”
    CBD argues that FWS violated the ESA by (1) relying
    on uncertain, insufficiently specific mitigation measures in
    reaching its no-jeopardy and no-adverse-modification
    conclusions, and (2) failing to specify the amount and extent
    of “take” in the incidental take statement included within the
    BiOp.
    C. Inadequacy of FWS’s Mitigation Measures
    Throughout the BiOp, FWS describes mitigation
    measures intended to alleviate the harm caused to polar bears
    by the Liberty project. CBD argues that the mitigation
    measures violate the ESA for two closely related reasons.
    First, the measures themselves are not sufficiently specific,
    binding, or certain to occur. Second, FWS relied on these
    non-binding mitigation measures to reach both its “no
    jeopardy and no adverse modification” conclusions for polar
    CTR. FOR BIO. DIVERSITY V. ZINKE                     29
    bears and their critical habitats, respectively.   The
    government responds that FWS did not rely on the
    mitigation measures and, even if it did, the mitigation
    methods are enforceable and sufficiently specific.
    1. Enforceability of the BiOp’s Mitigation Measures
    We first address whether the mitigation measures in
    FWS’s BiOp are sufficiently binding or certain to occur.
    Mitigation measures relied upon in a biological opinion must
    constitute a “clear, definite commitment of resources,” and
    be “under agency control or otherwise reasonably certain to
    occur.” Nat’l Wildlife Fed. v. Nat’l Marine Fisheries Serv.,
    
    524 F.3d 917
    , 936 & n.17 (9th Cir. 2008). A “sincere general
    commitment to future improvements”—without more
    specificity—is insufficient. 
    Id.
     at 935–36. The measures
    “must be subject to deadlines or otherwise-enforceable
    obligations; and most important, they must address the
    threats to the species in a way that satisfies the jeopardy and
    adverse modification standards.” Ctr. for Bio. Diversity v.
    Rumsfeld, 
    198 F. Supp. 2d 1139
    , 1152 (D. Ariz. 2002). 6
    Binding mitigation measures cannot refer only to
    generalized contingencies or gesture at hopeful plans; they
    must describe, in detail, the action agency’s plan to offset the
    environmental damage caused by the project.
    If an action agency fails to carry out the mitigation
    measures contained in a BiOp, it must re-initiate
    consultation with FWS. See Ctr. for Bio. Diversity v. U.S.
    Bureau of Land Mgmt., 
    698 F.3d 1101
    , 1115 (9th Cir. 2012)
    6
    District courts in this circuit follow the standard articulated by
    Rumsfeld. See, e.g., AquAlliance v. U.S. Bureau of Reclamation,
    
    287 F. Supp. 3d 969
    , 1071–72 (E.D. Cal. 2018) (“One district court
    persuasively provided further guidance [regarding when mitigation
    measures are sufficiently clear and definite].”) (citing to Rumsfeld).
    30           CTR. FOR BIO. DIVERSITY V. ZINKE
    (citing 
    50 C.F.R. § 402.16
    (c)). If the action agency does not
    re-initiate consultation, the BiOp is invalid and “any person”
    may bring suit and subject the action agency or the applicant
    to “substantial civil and criminal penalties.” 
    Id.
     (internal
    quotation marks omitted). An indefinite mitigation measure
    is less likely to trigger re-consultation because it will be
    difficult to know at which point or whether the action agency
    has failed to comply. For this reason, measures that are too
    vague, or do not commit resources, or are otherwise
    insufficiently integrated into the proposed action are
    generally unenforceable under the ESA, and thus cannot be
    properly relied upon. See 
    id.
     at 1113–14. The measures can
    be made enforceable in a variety of ways, including by
    incorporation into the terms and conditions of an incidental
    take statement. See 
    id.
     at 1114 n.9.
    CBD identifies four instances of planned mitigation in
    FWS’s biological opinion. The first two state:
    Available data indicate polar bears regularly
    den at low densities in the action area. . . .
    Den abandonment would be most likely to
    occur during new construction activities
    because ongoing activities during routine
    operations would allow more sensitive bears
    to select an alternative den site. However, the
    applicant has indicated they would conduct
    den detection surveys each winter in
    compliance with [guidance issued under
    MMPA incidental take regulations] and the
    project’s polar bear interaction plan. These
    surveys would be planned in cooperation
    with [FWS]. If dens are detected within
    1.6 km of the proposed locations of ice roads
    CTR. FOR BIO. DIVERSITY V. ZINKE                      31
    and pads, then [FWS] will be contacted for
    guidance.[ 7]
    ...
    As with denning polar bears, [FWS] expects
    potential adverse effects to non-denning
    polar bears would be reduced by the
    applicant’s compliance with existing and
    future authorizations issued under the
    MMPA . . . . Disturbance that disrupts
    behavioral patterns of polar bears is classified
    as take under the MMPA. The MMPA
    prohibits unpermitted incidental take of
    marine mammals. Under the MMPA,
    incidental take is only permitted provided the
    total of such taking will have no more than a
    negligible impact on the marine mammal
    species . . . , and does not have an
    unmitigable adverse impact on the
    availability of these species for subsistence
    uses. . .
    Both measures rely principally on yet unapproved and
    undefined mitigation measures under the MMPA. The
    government argues that the BiOp’s reliance on these
    measures is authorized under a 2013 Department of Interior
    rule governing the conservation and protection of polar
    bears. See Endangered and Threatened Wildlife and Plants;
    Special Rule for the Polar Bear Under Section 4(d) of the
    Endangered Species Act, 
    78 Fed. Reg. 11,766
     (Feb. 20,
    2013), codified at 
    50 C.F.R. § 17.40
    (q).        The rule
    7
    “Den detection surveys” are used to evaluate (with infrared radar,
    for example) where polar bear dens are located.
    32           CTR. FOR BIO. DIVERSITY V. ZINKE
    “synchronizes the management of the polar bear under the
    ESA with management provisions under the MMPA[.]” 
    Id. at 11,768
    .
    The rule does permit the agency to bypass Section 9
    compliance under the ESA once it has obtained a letter of
    authorization under the MMPA. It states that “if an activity
    is authorized or exempted under the MMPA,” “no additional
    authorization” under Section 9 of the ESA “for that activity
    will be required.” Id.; see also 
    50 C.F.R. § 17.40
    (q)(2)
    (“None of the prohibitions in § 17.31 of this part apply to
    any activity that is authorized or exempted under the Marine
    Mammal Protection Act (MMPA) . . . provided that the
    person carrying out the activity has complied with all terms
    and conditions that apply to that activity under the provisions
    of the MMPA . . . and [its] implementing regulations.”).
    MMPA protection is considered sufficient because the
    definition of “take” under the MMPA is “more protective”
    than take under the ESA. 78 Fed. Reg. at 11,770.
    Therefore, “managing take of polar bears under the
    MMPA adequately provides for the conservation of polar
    bears.” Id. Obviously, if incidental take of a threatened
    marine mammal is not authorized under the MMPA, “then
    the general [ESA take prohibitions] would apply, and [the
    Department of Interior] would require a permit for the
    activity as specified in [its] ESA regulations.” Id. at 11,766.
    But, as the rule repeatedly states, it “does not remove or alter
    in any way the consultation requirements under section 7 of
    the ESA.” Id. at 11,768. In other words, FWS’s BiOp
    remains unaffected by the polar-bear rule because it is part
    of the consultation process under Section 7 of the ESA.
    We have already rejected a similar interpretation of the
    rule, as applied to incidental take statements. Salazar,
    695 F.3d at 910–11. In Salazar, we held that an agency
    CTR. FOR BIO. DIVERSITY V. ZINKE                     33
    acted unlawfully by failing to issue an incidental take
    statement pursuant to Section 7 of the ESA, even though it
    separately complied with the MMPA prohibitions on marine
    mammal take. Id. at 910. The agency argued that the polar-
    bear rule preempted any need to publish an incidental take
    statement. Id. But, as we explained, Section 7 imposes a
    separate requirement for an incidental take statement and
    biological opinion in certain circumstances. Id. The rule
    itself states that “[n]othing in this special rule affects the
    issuance or contents of the biological opinions for polar
    bears[.]” 
    73 Fed. Reg. 76,249
    , 76,252 (Dec. 16, 2008)
    (emphasis added). In other words, compliance with
    
    50 C.F.R. § 17.40
    (q) satisfies the ESA’s Section 9 take
    requirement but does not fulfill the agency’s separate and
    independent Section 7 obligations. Salazar, 695 F.3d at
    910–11.
    So too here. FWS must comply with both Section 7 and
    Section 9 of the ESA, and approval of polar-bear take under
    the MMPA will meet the agency’s obligations only under
    Section 9. The rule does not preclude or preempt FWS’s
    responsibility to include the mitigation measures that it relies
    upon in a biological opinion under Section 7 of the ESA.
    The agency cannot refer to future, unstated authorizations
    under the MMPA to fulfill its obligations under Section 7. 8
    8
    FWS, NMFS, and two other federal agencies have also issued
    guidance suggesting they did not contemplate that MMPA compliance
    would automatically satisfy an action agency’s Section 7 obligations.
    The timelines between the MMPA and ESA differ substantially; the ESA
    process generally requires that Section 7 consultation be completed
    within 90 days, 
    16 U.S.C. § 1536
    (b)(1)(A), (B), but the MMPA approval
    process can take much longer because it requires public notice-and-
    comment. The agencies recommend that action agencies handle timing
    discrepancies in one of three ways. First, the action agency may
    “consider initiating the MMPA [] process in advance of the ESA section
    34             CTR. FOR BIO. DIVERSITY V. ZINKE
    Reliance on future MMPA measures is particularly
    inappropriate to satisfy the agency’s Section 7 obligations
    here, where the authorizations under the MMPA last for only
    five years, see 
    16 U.S.C. § 1371
    (a)(5)(A), and the Liberty
    project is expected to last fifteen to twenty years.
    7 process.” 54 Fed. Reg. at 40,346. The MMPA requirements can then
    “be incorporated into the ESA incidental take statement when the
    biological opinion is issued and subsequent revisions would not be
    necessary.” Id. Second, FWS and the action agency may together agree
    to extend the Section 7 consultation under the ESA “to accommodate
    completion” of the MMPA regulations. Id. Or, third, the action agency
    may begin “early consultation” with the ESA, and request a “preliminary
    biological opinion.” Id. Once the MMPA process is completed, the
    opinion “would be reviewed and the . . . incidental take statement
    amended or added, as appropriate.” Id.
    Whichever route the action agency chooses, the Department of
    Interior “is expected to proceed with issuance of the biological opinion
    and . . . incidental take statement in a timely manner” as Section 7
    consultation requires. 99th Cong. 32,185 (1986) (statement of Rep.
    Jones). The agency should “indicate that the findings and conditions
    applicable to affected marine mammals are subject to final completion
    of the MMPA” process and “that the statement would subsequently be
    revised to reflect the outcome of that review.” Id. “In this situation,” as
    the statute reflects, “incidental take of listed marine mammals would not
    be authorized under the ESA” until after “the MMPA and the section 7[]
    incidental take statement has been revised.” Id.; see also 
    16 U.S.C. § 1536
    (b)(4)(C).
    In other words, even if the action agency obtains MMPA approval,
    the take statement must be “subsequently revised” to reflect that
    approval, and authorization will not occur under after the statement has
    been revised. At no point does the guidance issued by FWS suggest that
    Section 7 approval occurs automatically, upon MMPA approval. Indeed,
    all three options suggested in the guidance recommend that the action
    agency complete the MMPA approval process before seeking final
    Section 7 consultation and approval.
    CTR. FOR BIO. DIVERSITY V. ZINKE              35
    The third proposed mitigation measure states:
    Additional     information     on     possible
    minimization measures that would reduce
    effects to polar bears from oil and gas
    industry activities can be found in the [2016
    generalized list on mitigation measures used
    in the Beaufort Sea].
    This measure references “possible” strategies, without
    selecting a mitigation measure from the incorporated list or
    committing BOEM or Hilcorp to carrying out any specific
    number of measures. These noncommittal assurances
    cannot shoulder the government’s burden to identify a
    “clear, definite commitment of resources.” Nat’l Wildlife
    Fed’n, 
    524 F.3d at 936
    ; see also Sierra Club v. Marsh,
    
    816 F.2d 1376
    , 1388 (9th Cir. 1987) (concluding that “one
    of several ‘reasonable and prudent alternatives’ that the FWS
    found necessary to minimize the project’s effects” was not
    reasonably certain to occur), abrogated on other grounds as
    recognized in Cottonwood Envtl. Law Ctr. v. U.S. Forest
    Serv., 
    789 F.3d 1075
    , 1088–91 (9th Cir. 2015).
    The fourth and final measure states:
    Mitigation measures applied to ensure least
    practicable impacts include requirement of
    site-specific plans of operation and site-
    specific polar bear interaction plans. In
    combination, these plans reduce attraction to
    bears (e.g., through garbage disposal
    procedures, snow management procedures)
    and provide training and other measures to
    eliminate the potential for injurious or lethal
    take of bears in defense of human life in the
    event that encounters occur. Other mitigation
    36           CTR. FOR BIO. DIVERSITY V. ZINKE
    measures may be required on a case-by-case
    basis, such as use of infra-red thermal
    technology or trained dogs to determine
    presence or absence of dens in suitable
    denning habitat; measures to protect pregnant
    polar bears during denning activities (den
    selection, birthing, and maturation of cubs);
    and limiting industrial activities near barrier
    islands . . . This incidental-take program and
    the associated mitigation measures have
    effectively limited human-bear interactions
    and disturbance to bears, ensuring that, at
    least to date, industry effects have had a
    negligible impact on bears.
    This contains the most concrete mitigation strategies found
    in the BiOp, but even these suggestions do not truly commit
    to the development of mitigation strategies. The few
    concrete strategies provided are offered only as examples of
    possible strategies that could be taken, “in the event that
    encounters occur.” It is unclear what will constitute a polar
    bear encounter or commit the action agency to carrying out
    any of the mitigation measures listed in the examples
    provided. It concludes that “[o]ther mitigation measures
    may be required on a case-by-case basis,” a statement which,
    alone, also does nothing to bind BOEM when the need for
    those measures apply. See, e.g., Rumsfeld, 
    198 F. Supp. 2d at 1153
     (explaining that a “laundry list of possible mitigation
    measures” is unenforceable). A mitigation strategy’s
    eventual MMPA approval does not change this analysis
    because, as we have held, MMPA authorization does not
    alter the agency’s obligations under Section 7 of the ESA.
    We agree with CBD that the mitigation measures
    proposed by FWS are too vague to enforce.    The
    CTR. FOR BIO. DIVERSITY V. ZINKE                37
    administrative record does reflect a “general desire” to
    impose mitigation strategies, but it does not reflect a definite
    commitment to those improvements. The generality of the
    mitigation measures makes it difficult to determine the point
    at which the action agency may renege on its promise to
    implement these measures.                “[S]incere general
    commitment[s] to future improvement” are insufficient
    under Section 7. Nat’l Marine Fisheries Serv., 
    524 F.3d. at
    935–36.
    2. Reliance on Mitigation Measures
    Our conclusion that the mitigation measures in the BiOp
    are insufficiently specific to enforce has no legal
    consequence unless we separately conclude that FWS relied
    on those measures. The government and Hilcorp argue that
    because the overall magnitude of the negative effect on polar
    bears is estimated to be low, FWS did not rely on any of its
    mitigation measures to reach its no-jeopardy and no-
    adverse-modification findings.
    Whether FWS relied on the proposed mitigation
    measures in reaching its conclusion depends on the language
    and structure of the BiOp. A BiOp that integrates mitigation
    measures into its decision-making is more likely to have
    relied upon those measures. Conversely, an opinion that
    relies upon indefinite “background cumulative effects” and
    uses those effects “as a basis for determining the likely
    effects” of the proposed project, for example, renders the
    agency’s reliance on that opinion arbitrary and capricious.
    See Ctr. for Bio. Diversity, 698 F.3d at 1113. To be
    enforceable, those effects “should properly have been part of
    the project itself.” Id.; see also Nat’l Wildlife Fed’n v. Nat’l
    Marine Fisheries Serv., 
    839 F. Supp. 2d 1117
    , 1125–26
    (D. Or. 2011) (holding that the agency improperly relied on
    habitat mitigation measures that “in some cases [were] not
    38           CTR. FOR BIO. DIVERSITY V. ZINKE
    even identified” and the agency had “assume[d] it w[ould]
    be able to identify and implement the additional projects that
    are necessary”); Ctr. for Bio. Diversity v. Salazar, 
    804 F. Supp. 2d 987
    , 1002 (D. Ariz. 2011) (concluding that a
    biological opinion that relied on water saving mitigation
    projects where the court could not ascertain the details of the
    planned projects or the estimated water savings was
    unlawful).
    The portion of the BiOp describing FWS’s no-jeopardy
    and no-adverse modification findings is brief. Its no-
    jeopardy conclusion states:
    A small number of polar bears may also be
    adversely affected through disturbance or
    polar bear-human interactions which may
    include intentional take. These adverse
    effects are expected to impact only small
    numbers of individuals . . . and therefore, we
    do not expect population-level impacts as a
    result of the proposed Liberty DPP. After
    reviewing the current status of the species,
    environmental baseline, effects of the action,
    and cumulative effects, [FWS] concludes the
    proposed action is not likely to jeopardize the
    continued existence of polar bears by
    reducing appreciably the likelihood of
    survival and recovery in the wild by reducing
    reproduction, numbers, or distribution of this
    species.
    FWS appears to conclude that the Liberty project, as a
    whole, will not significantly impact polar bears, with or
    without the mitigation measures. We conclude FWS did not
    CTR. FOR BIO. DIVERSITY V. ZINKE                 39
    rely on any of the aforementioned mitigation measures in its
    no-jeopardy determination.
    But in concluding that the bears’ critical habitat will not
    be adversely affected by the project, FWS relied on three
    stated factors, the second of which incorporates the
    mitigation measures. Specifically, the second basis for
    FWS’s no-adverse-modification finding is that the “terms
    and conditions associated with authorizations under the
    MMPA would minimize the level of persistent disturbance
    that may result from the Proposed Action[.]”
    As discussed, unauthorized, future mitigation measures
    under the MMPA cannot satisfy the FWS’s obligations
    under Section 7 of the ESA. The mitigation measures
    proposed in the BiOp are indefinite and do not constitute a
    “clear, definite commitment of resources,” and FWS’s
    reliance upon those measures to conclude that the polar
    bear’s critical habitat would not be adversely modified by
    the Liberty project was arbitrary and capricious. For these
    reasons, we hold that FWS’s BiOp violated the ESA. We
    further hold that FWS did not rely on its indefinite mitigation
    measures in finding that the polar bear’s continued existence
    would not be jeopardized by the project.
    D. Incidental Take
    We next evaluate whether FWS unlawfully failed to
    specify the amount and extent of “take” in its incidental take
    statement. The ESA requires an incidental take statement
    where FWS concludes, as here, that a project will not
    jeopardize a species or modify its critical habitat. The
    purpose of the incidental take statement is, at least in part, to
    specify the amount of take that may occur, and include
    triggers that indicate non-compliance with the statement and
    require re-consultation with FWS.            See 16 U.S.C.
    40           CTR. FOR BIO. DIVERSITY V. ZINKE
    § 1536(b)(4); 
    50 C.F.R. § 402.14
    (i)(l)(i). To “specify the
    impact” of any incidental take, the statement should either
    include a numerical cap on take or explain why it does not
    include the cap. Ctr. for Bio. Diversity, 698 F.3d at 1127.
    The numerical cap establishes a threshold that, when
    exceeded, results in an unacceptable level of take and
    requires parties to re-initiate Section 7 consultation. Ariz.
    Cattle Growers Ass’n v. U.S. Fish and Wildlife, 
    273 F.3d 1229
    , 1249 (9th Cir. 2001).
    The statement can use a proxy measure for take where
    “no number may be practically obtained.” Ctr. for Bio. Div,
    698 F.3d at 1126–27 (internal quotation marks omitted). For
    example, where an agency is unable to quantify the number
    of endangered or threatened fish that will be taken, it may
    instead estimate the project’s impact on the number of eggs
    laid by those fish. Id. (citing H.R. Rep. No. 97-567, at 27
    (1982)). Take can also be expressed as a change in habitat
    affecting the species (e.g., for “aquatic species, changes in
    water temperature or chemistry, flows, or sediment loads”),
    but “some detectable measures of effect should be
    provided.” Ariz. Cattle Growers, 
    273 F.3d at 1250
     (quoting
    Final ESA Section 7 Consultation Handbook, March 1998
    at 4-47–4-48). When it relies upon a proxy, the agency must
    explain why it cannot directly quantify the animal’s expected
    take. See Or. Nat. Resources Council v. Allen, 
    476 F.3d 1031
    , 1037–38 (9th Cir. 2007) (holding that FWS erred in
    quantifying the expected take of northern spotted owls in
    terms of habitat acreage without explaining why the agency
    was unable to numerically estimate take).
    CBD argues that FWS failed to quantify the amount of
    nonlethal take in its incidental take statement. The
    government argues that any nonlethal disturbance does not
    rise to the level of take, and so FWS did not need to quantify
    CTR. FOR BIO. DIVERSITY V. ZINKE               41
    any nonlethal take that may occur as a result of the project.
    We agree that FWS contemplated that nonlethal harassment
    of polar bears may rise to the level of “take” under the ESA
    and should have quantified the nonlethal take of the bears.
    In the BiOp, FWS does provide a numerical cap on the
    amount of take that constitutes injury or death to polar bears;
    injury or death to more than one polar bear triggers re-
    consultation:
    As provided in 50 C.F.R. 402.16, re-initiation
    of formal consultation is required where
    discretionary Federal agency involvement or
    control over the action has been retained (or
    is authorized by law), and re-initiation may
    be required if:
    1. The amount or extent of incidental
    take for listed species is exceeded
    over the life of the project;
    a. . . .
    b. If human-polar bear interactions
    result in injury and/or death of
    more than 1 polar bear over the
    life of the project.
    But FWS does not quantify the amount of other types of
    incidental take that the Liberty project may cause. Take
    under the ESA can occur via injury or death, as the BiOp
    recognizes, but it can also occur via nonlethal harassment.
    See 
    16 U.S.C. § 1532
    (19). FWS interprets “harassment” of
    an animal to have occurred under the ESA when an entity,
    either intentionally or negligently, “creates the likelihood of
    injury to wildlife by annoying it to such an extent as to
    42           CTR. FOR BIO. DIVERSITY V. ZINKE
    significantly disrupt normal behavioral patterns which
    include, but are not limited to, breeding, feeding, or
    sheltering.” 
    50 C.F.R. § 17.3
    (c). The MMPA includes an
    even broader view of “harassment” than the ESA—
    “harassment” includes actions which “ha[ve] the potential to
    disturb a marine mammal . . . by causing disruption of
    behavioral patterns, including, but not limited to, migration,
    breathing, nursing, breeding, feeding, or sheltering.”
    
    16 U.S.C. § 1362
    (18)(A).
    Though it now argues otherwise, it appears that FWS
    contemplated these types of nonlethal take in its biological
    opinion. It noted that polar bears might face disturbance
    from “polar bear-human interactions,” and “ground-level
    activities within the action area,” including “construction of
    the LDPI, drilling activities, facility operations, pipeline
    construction and maintenance, mine site development, ice
    road construction and associated vehicle traffic, and air
    traffic.” “In addition to disturbance from ground-level
    activities within the action area, air traffic associated with
    the Liberty DPP could potentially disturb polar bears,
    affecting the success or likelihood of denning in the action
    area.” “Denning females may also be more likely to
    abandon their dens in the fall before cubs are born and
    relocate if disturbed. . . . Den abandonment would be most
    likely to occur during new construction activities because
    ongoing activities during routine operations would allow
    more sensitive bears to select an alternative den site.” These
    disturbances implicate disruptions in behavioral patterns
    contemplated in the ESA and MMPA, such as polar bears’
    breeding and sheltering.
    Two different portions of FWS’s biological opinion
    suggest that FWS contemplated that these expected
    disturbances rise to the level of nonlethal take. In its
    CTR. FOR BIO. DIVERSITY V. ZINKE              43
    discussion on the effects of these disturbances on polar
    bears, FWS noted that
    The potential that disturbance will indirectly
    reduce the value of polar bear critical habitat
    would be significantly reduced by other
    existing regulatory programs that directly
    address the disturbance of polar bears. As
    described previously, the MMPA allows for
    incidental, non-intentional take from
    harassment of small numbers of marine
    mammals during specific activities[.]
    The BiOp then lists the potential mitigating consequences of
    future measures authorized under the MMPA. This list
    suggests that FWS considered that such indirect harassment
    would rise to the level of “incidental, non-intentional take”
    under the MMPA, and that mitigation measures might
    alleviate the severity of such take.
    More pointedly, a later section of FWS’s BiOp states that
    re-initiation of formal consultation may be required if:
    New information reveals effects of the action
    that may affect listed species in a manner or
    to an extent not considered in this opinion
    (e.g., if observations in the Liberty DPP
    action area indicate levels of interaction with
    polar bears, especially the need for hazing, is
    increasing significantly over time, or is
    resulting in chronic or repeated interference
    with normal polar bear behavior).
    44            CTR. FOR BIO. DIVERSITY V. ZINKE
    FWS explains that the “levels of interaction with polar
    bears, especially the need for hazing” 9 is itself a trigger for
    further re-consultation: if interaction with the bears increases
    significantly or results in chronic, repeated interference with
    normal bear behavior, FWS requires re-consultation.
    Considering “levels of interaction” as a trigger suggests that
    this type of non-lethal harassment amounts to incidental take
    and requires FWS to provide an estimate for such take. See
    Ariz. Cattle Growers, 
    273 F.3d at 1249
    .
    This trigger is particularly important here, where FWS
    asserted that any take approved under the MMPA would take
    effect without further action by FWS. As the incidental take
    statement stands, there is no guarantee that these
    “harassment” take provisions—once they are made
    enforceable by authorization under the MMPA—will
    contain the numerical triggers required by the ESA.
    Because FWS contemplated that the harassment and
    disturbances polar bears will suffer could trigger re-
    consultation with FWS and did not quantify the nonlethal
    take that polar bears are expected to face (or explain why it
    could not do so), we hold that FWS’s incidental take
    statement violated the ESA. It was therefore arbitrary and
    capricious under the APA.
    9
    “Hazing” polar bears refers to actions taken to deter them from
    entering a worksite. “Polar bears may need to be hazed if they approach
    Liberty DPP infrastructure when humans are present (e.g., the work
    surface of the LDPI). Although the partial sheet pile wall may prevent
    some polar bears from accessing the LDPI, others may gain access to
    areas occupied by humans and require hazing.” Bears can be hazed by
    using loud noises (starting a car or revving an engine), or by using
    stronger mechanisms (such as chemical repellants, electric fences, or
    “firearm projectiles”).
    CTR. FOR BIO. DIVERSITY V. ZINKE                 45
    IV. BOEM’s Reliance on the Invalid BiOp
    Finally, we evaluate whether BOEM’s reliance on
    FWS’s biological opinion in its approval of the Liberty
    project was arbitrary and capricious. Section 7 of the ESA
    imposes a duty on BOEM to ensure that its actions are not
    likely to jeopardize the continued existence of the listed
    species or result in destruction or adverse modification of its
    critical habitat. Ctr. for Bio. Diversity, 698 F.3d at 1127–28.
    An agency cannot meet its Section 7 duties by relying on a
    legally flawed biological opinion or failing to discuss
    information that might undercut the opinion’s conclusions.
    See id. Because we conclude that FWS’s biological opinion
    is, at least in part, invalid, BOEM’s reliance on it is unlawful.
    V. Relief
    We vacate BOEM’s approval of the Liberty project. We
    conclude that BOEM acted arbitrarily and capriciously by
    failing to quantify the emissions resulting from foreign oil
    consumption in its EIS as required by NEPA, or, at least,
    explaining thoroughly why it cannot do so and summarizing
    the research upon which it relied. We also hold that FWS
    violated the ESA by (1) relying upon uncertain, nonbinding
    mitigation measures in reaching its no-adverse-effect
    conclusion in its biological opinion, and (2) failing to
    estimate the Liberty project’s amount of nonlethal take of
    polar bears. Because we conclude that FWS’s biological
    opinion is flawed and unlawful, we conclude that BOEM’s
    reliance on FWS’s opinion is arbitrary and capricious. In all
    other respects, we deny the petition for review.
    The petition for review is GRANTED in part and
    DENIED in part. BOEM’s approval of the Liberty project
    is VACATED and this action is REMANDED to the
    46          CTR. FOR BIO. DIVERSITY V. ZINKE
    agency for further proceedings consistent with this opinion.
    CBD shall recover its costs.
    CTR. FOR BIO. DIVERSITY V. ZINKE          47
    Appendix
    APA           Administrative Procedure Act
    BOEM          Bureau of Ocean Energy Management
    BiOp          Biological opinion
    CBD           Center for Biological Diversity
    EIS           Environmental Impact Statement
    ESA           Endangered Species Act
    FWS           U.S. Fish and Wildlife Service
    MMPA          Marine Mammal Protection Act
    NEPA          National Environmental Policy Act
    NMFS          National Marine Fisheries Service
    OCSLA         Outer Continental Shelf Lands Act
    

Document Info

Docket Number: 18-73400

Filed Date: 12/7/2020

Precedential Status: Precedential

Modified Date: 12/7/2020

Authorities (25)

Center for Biological Diversity v. Salazar , 804 F. Supp. 2d 987 ( 2011 )

Center for Biological Diversity v. Rumsfeld , 198 F. Supp. 2d 1139 ( 2002 )

selkirk-conservation-alliance-a-non-profit-public-interest-group-sierra , 336 F.3d 944 ( 2003 )

oregon-natural-resources-council-klamath-siskiyou-wildlands-center-cascadia , 476 F.3d 1031 ( 2007 )

klamath-siskiyou-wildlands-center-an-oregon-non-profit-organization-v , 387 F.3d 989 ( 2004 )

American Bird Conservancy v. FCC , 545 F.3d 1190 ( 2008 )

state-of-california-v-john-r-block-in-his-official-capacity-as , 690 F.2d 753 ( 1982 )

ocean-advocates-a-non-profit-organization-fuel-safe-washington-a , 402 F.3d 846 ( 2005 )

City of Davis, a Municipal Corporation v. William T. ... , 521 F.2d 661 ( 1975 )

arizona-cattle-growers-association-jeff-menges , 273 F.3d 1229 ( 2001 )

National Wildlife Federation v. National Marine Fisheries ... , 524 F.3d 917 ( 2008 )

sierra-club-a-california-non-profit-corporation-league-for-coastal , 816 F.2d 1376 ( 1987 )

bob-marshall-alliance-v-donald-p-hodel-secretary-of-the-interior-and , 852 F.2d 1223 ( 1988 )

The Lands Council v. McNair , 537 F.3d 981 ( 2008 )

citizens-against-burlington-inc-v-james-b-busey-iv-administrator , 938 F.2d 190 ( 1991 )

Scientists' Institute for Public Information, Inc. v. ... , 481 F.2d 1079 ( 1973 )

blue-mountains-biodiversity-project-blue-mountain-native-forest-alliance , 161 F.3d 1208 ( 1998 )

seattle-audubon-society-pilchuck-audubon-society-washington-environmental , 998 F.2d 699 ( 1993 )

hugh-r-kern-leigh-ann-lipscomb-oregon-natural-resources-council-v-united , 284 F.3d 1062 ( 2002 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... , 103 S. Ct. 2856 ( 1983 )

View All Authorities »