Alliance for the Wild Rockies v. Carl Petrick ( 2023 )


Menu:
  •                 FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    ALLIANCE FOR THE WILD                    No. 21-35504
    ROCKIES,
    D.C. No.
    Plaintiff-Appellee,        2:19-cv-00332-
    REP
    v.
    CARL PETRICK, his official capacity        OPINION
    as Forest Supervisor for the Idaho
    Panhandle National Forests; UNITED
    STATES FOREST SERVICE, an
    agency of the U.S. Department of
    Agriculture; UNITED STATES FISH
    AND WILDLIFE SERVICE, an
    agency of the U.S. Department of
    Interior,
    Defendants-Appellants.
    Appeal from the United States District Court
    for the District of Idaho
    Ronald E. Bush, Magistrate Judge, Presiding
    2             ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    ALLIANCE FOR THE WILD                           No. 21-35785
    ROCKIES,
    D.C. No.
    Plaintiff-Appellee,          2:21-cv-00244-
    BLW
    v.
    UNITED STATES FOREST
    SERVICE, an agency of the U.S.
    Department of Agriculture; CARL
    PETRICK, in his official capacity as
    Forest Supervisor for the Idaho
    Panhandle National Forests,
    Defendants-Appellants.
    Appeal from the United States District Court
    for the District of Idaho
    B. Lynn Winmill, Chief District Judge, Presiding
    Argued and Submitted October 20, 2022
    Seattle, Washington
    Filed May 16, 2023
    Before: Ryan D. Nelson, Danielle J. Forrest, and Jennifer
    Sung, Circuit Judges.
    Opinion by Judge R. Nelson
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK               3
    SUMMARY*
    Environmental Law / Timber Projects
    The panel vacated the district court’s grant of summary
    judgment in Hanna Flats I, and vacated the district court’s
    preliminary injunction in Hanna Flats II, in two appeals
    involving an ongoing dispute over the Hanna Flats logging
    project in the Idaho panhandle (the “Project”).
    The United States Forest Service designated several
    thousand acres of national forest for various treatments,
    including commercial logging, to reduce the risk of wildfires
    and disease. The Forest Service invoked a categorical
    exclusion from National Environmental Policy Act (NEPA)
    review for projects in the wildland-urban interface. In
    Hanna Flats I, the district court granted summary judgment
    for Alliance for the Wild Rockies, based on reasoning that
    the record did not show that the Project fell within the
    statutory definition of wildland-urban interface, and ordered
    further analysis supporting the categorical exclusion on
    remand. Subsequently, the Forest Service issued a
    Supplement to the Decision Memo further justifying the
    categorical exclusion. In Hanna Flats II, the district court
    issued a preliminary injunction based on the reasoning that
    the Forest Service could not invoke the categorical
    exclusion.
    *
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    4          ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    The panel held that in Hanna Flats I, the district court
    erred in finding that Alliance’s public comments adequately
    put the Forest Service on notice of its eventual claim.
    The panel concluded that it had appellate jurisdiction.
    First, the panel held that the appeal was not moot. The
    parties did not intend to settle this matter; and the
    government’s compliance with the judgment of a lower
    court—even where compliance involved a new agency
    decision—did not necessarily moot the appeal, especially
    where some redress remained possible. Second, the Forest
    Service had standing to pursue this appeal. The Forest
    Service remains injured by the final judgment in Hanna
    Flats I, and this court can redress that injury with a favorable
    decision.
    The panel next evaluated whether the doctrine of
    administrative waiver barred Alliance’s challenge in Hanna
    Flats I because Alliance did not raise its arguments during
    the public-comment period. First, the panel held that the
    Forest Service sufficiently preserved its notice argument,
    even though it framed notice as an exhaustion requirement
    below and as a waiver issue on appeal. Second, the panel
    held that Alliance’s comments did not put the Forest Service
    on notice of the wildland-urban interface issue. Alliance’s
    vague and generalized statement that the district court cited,
    contained within more than a hundred pages of comments,
    did not provide sufficient notice to the government of
    Alliance’s current concerns. Alliance therefore never gave
    the Forest Service an opportunity to consider the issue
    presented by Alliance’s eventual claim in federal
    court. Alliance’s comment did not identify any violation of
    the Healthy Forests Restoration Act (“HFRA”), nor did it
    allege that the Project fell outside the wildland-urban
    interface. In addition, Alliance’s other comments were even
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK         5
    more removed from Alliance’s claim. The panel remanded
    for the district court to consider Alliance’s unaddressed
    argument that there was no administrative-objection
    requirement in this context.
    In Hanna Flats II, which Alliance brought after the
    Forest Service complied with the remand order and issued
    the Supplement, the district court enjoined the
    implementation of the Project because it found serious
    questions about whether the Forest Service validly applied
    HFRA’s categorical exclusion to the Project. First, the
    parties disagreed on the standard of review that should be
    applied to the Forest Service’s decision to rely on a
    categorical exclusion. Pursuant to the text of the
    Administrative Procedures Act (“APA”) and precedent, the
    panel reviewed the Forest Service’s reliance on HFRA’s
    categorical exclusion under the familiar arbitrary or
    capricious standard. Next, the panel considered the district
    court’s ruling that there were serious questions about the
    application of the categorical exclusion. The panel held that
    the district court did not, as the Forest Service contended,
    impermissibly create and impose new procedural duties on
    the Forest Service. It simply held the Forest Service to the
    strictures already required by the APA (and, by extension,
    HFRA). Turning to the district court’s analysis, the panel
    agreed with the district court that, under these facts, the
    Project’s location within the area designated as wildland-
    urban interface by the Bonner County community plan was
    not enough to establish the valid application of the
    categorical exclusion. However, the district court’s
    conclusion—that there were serious questions whether the
    categorical exclusion applied—was based on an erroneous
    interpretation of the HFRA. Because the preliminary
    injunction was based on faulty legal premises, the panel
    6         ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    vacated and remanded. Finally, the panel held that there was
    no reason to conclude that it should exercise its equitable
    discretion to leave an injunction in place that was wrongly
    granted, and where there was no clear likelihood of success
    on another claim.
    COUNSEL
    Joan M. Pepin (argued), Rachel E. Heron, John P. Tustin,
    and Emma L. Hamilton, Attorneys; Todd Kim, Assistant
    Attorney General; Environment and Natural Resources
    Division, United States Department of Justice; Washington,
    D.C.; Rickey D. Turner, Attorney; Environment and Natural
    Resources Division, United States Department of Justice;
    Denver, Colorado; Elise Foster, Attorney; United States
    Department of Agriculture, Office of the General Counsel;
    Washington, D.C.; for Defendants-Appellants.
    Rebecca K. Smith (argued), Public Interest Defense Center,
    Missoula, Montana, for Plaintiff-Appellee.
    OPINION
    R. NELSON, Circuit Judge:
    We address two appeals involving an ongoing dispute
    over the Hanna Flats logging project (the Project) in the
    Idaho panhandle. The United States Forest Service
    designated several thousand acres of national forest for
    various treatments, including commercial logging, to reduce
    the risk of wildfires and disease. The Forest Service invoked
    a categorical exclusion from National Environmental Policy
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK            7
    Act (NEPA) review for projects “in the wildland-urban
    interface.” 16 U.S.C. § 6591b(c)(2)(A).
    In the first case (Hanna Flats I), the district court granted
    summary judgment for Alliance for the Wild Rockies
    (Alliance), reasoning that the record did not show that the
    Project fell within the statutory definition of “wildland-
    urban interface,” and ordered further analysis supporting the
    categorical exclusion on remand.
    The Forest Service complied and issued a Supplement to
    the Decision Memo further justifying the categorical
    exclusion. But in a new action (Hanna Flats II), the district
    court issued a preliminary injunction, again reasoning that
    the Forest Service could not invoke the categorical
    exclusion.
    We find reversible error in both cases. In Hanna Flats I,
    we conclude that the district court erred in finding that
    Alliance’s comment adequately put the Forest Service on
    notice of its eventual claim. We remand to the district court
    to consider Alliance’s unaddressed argument that there is no
    administrative-objection requirement in this context.
    In Hanna Flats II, we agree with the district court that,
    under these facts, the Project’s location within the area
    designated as wildland-urban interface by the Bonner
    County community plan alone is not enough to establish the
    valid application of the categorical exclusion. But the
    district court’s conclusion that there were serious questions
    whether the categorical exclusion applied was based on an
    erroneous interpretation of the Healthy Forests Restoration
    Act (HFRA). Because the preliminary injunction was issued
    on faulty legal premises, we vacate it and remand.
    8          ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    I
    This case involves the interplay between two statutory
    regimes: NEPA and HFRA. “Congress enacted NEPA to
    establish a national policy for the environment.” Mountain
    Cmtys. for Fire Safety v. Elliott, 
    25 F.4th 667
    , 674 (9th Cir.
    2022). “NEPA imposes only procedural requirements on
    federal agencies with a particular focus on requiring
    agencies to undertake analyses of the environmental impact
    of their proposals and actions.” Dep’t of Transp. v. Pub.
    Citizen, 
    541 U.S. 752
    , 756–57 (2004). NEPA requires the
    preparation of an environmental impact statement (EIS) for
    “every recommendation or report on proposals for . . . major
    Federal actions significantly affecting the quality of the
    human environment.” Friends of Se.’s Future v. Morrison,
    
    153 F.3d 1059
    , 1062 (9th Cir. 1998) (quoting 
    42 U.S.C. § 4332
    (C)).
    To decide whether an EIS is needed, the agency can first
    prepare an environmental assessment (EA) “to determine
    whether a proposed federal action will have a significant
    impact.” Native Ecosystems Council v. U.S. Forest Serv.,
    
    428 F.3d 1233
    , 1238–39 (9th Cir. 2005) (citation omitted).
    “Some actions, however, are categorically excepted or
    excluded from NEPA’s procedural requirements.” Ctr. for
    Biological Diversity v. Ilano, 
    928 F.3d 774
    , 777 (9th Cir.
    2019). When a categorical exclusion applies, the agency
    need not prepare an EIS or EA. Mountain Cmtys. for Fire
    Safety, 25 F.4th at 675.
    HFRA creates one such statutory exclusion. HFRA
    “directs the Forest Service to take action to ‘reduce wildfire
    risk’ and ‘enhance efforts to protect watersheds and address
    threats to forest and rangeland health.’” WildWest Inst. v.
    Bull, 
    547 F.3d 1162
    , 1165 (9th Cir. 2008) (quoting 16 U.S.C.
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK                  9
    § 6501(1), (3)). “Specifically, the Forest Service is required
    ‘[a]s soon as practicable’ to implement an ‘authorized
    hazardous fuel reduction project[]’ on federal land” where
    certain imminent risks exist. Id. (alterations in original)
    (quoting 
    16 U.S.C. § 6512
    (a)(4)). HFRA also requires
    public notice of the decision-making process and public
    collaboration. Id. at 1166. And typically, projects under
    HFRA require NEPA compliance, meaning the preparation
    of an EA and potentially an EIS. See id. at 1165 (citing 
    16 U.S.C. § 6514
    (a)).
    But HFRA provides a statutory categorical exclusion to
    NEPA when the project is located “in the wildland-urban
    interface.” 16 U.S.C. § 6591b(c)(2)(A). Broadly speaking,
    a “wildland-urban interface” is an area where structures and
    other human development intermingle with undeveloped
    wild areas. Wildfires pose extraordinary risks to life and
    property in such areas. HFRA specifically defines a
    “wildland-urban interface” as “an area within or adjacent to
    an at-risk community that is identified in recommendations
    to the Secretary in a community wildfire protection plan.”
    Id. § 6511(16)(A) (emphases added).1             An “at-risk
    community” must satisfy multiple requirements; as relevant
    here, it “is comprised of . . . a group of homes and other
    structures with basic infrastructure and services . . . within
    or adjacent to Federal land.” Id. § 6511(1)(A)(ii).
    A
    In August 2017, the Forest Service issued a Scoping
    Notice announcing an agency project in the Idaho Panhandle
    1
    A separate definition applies “in the case of any area for which a
    community wildfire protection plan is not in effect.” Id. § 6511(16)(B).
    That definition is not applicable here because there is a community
    wildfire protection plan in place.
    10         ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    National Forests within Bonner County, Idaho. The Project
    involves several treatments, including commercial thinning,
    noncommercial thinning, and prescribed burning. The
    Forest Service, through the Project, seeks to remove forest
    fuel hazards to minimize wildfire risk and remove diseased
    trees spanning 6,814 acres, nearly 97% of which is public
    land.
    The Forest Service sought public comment. The
    Scoping Notice stated that the Project would likely be
    exempt from NEPA because of HFRA’s categorical
    exclusion, since “the entire project area is in the wildland-
    urban interface,” as defined by Bonner County’s
    Community Wildfire Protection Plan (the Bonner County
    community plan). Members of the public, including
    Alliance, provided extensive comments.
    The Forest Service issued a Decision Memo authorizing
    the Project. Like the Scoping Notice, the Decision Memo
    invoked HFRA’s categorical exclusion because the Project
    fell within the wildland-urban interface.
    B
    In Hanna Flats I, Alliance brought several claims
    seeking judicial review of the Forest Service’s Decision
    Memo approving the Project. All. for the Wild Rockies v.
    Higgins, 
    535 F. Supp. 3d 957
    , 962 (D. Idaho 2021). At issue
    on appeal is Alliance’s claim that the Project does not qualify
    for HFRA’s categorical exclusion because it is not within the
    “wildland urban interface.”
    The parties cross-moved for summary judgment, and the
    district court granted summary judgment for Alliance. 
    Id.
     at
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK             11
    975, 981.2 First, the district court ruled that Alliance had
    sufficiently exhausted its administrative remedies. 
    Id.
     at
    974–75. Then, the district court concluded that the record
    did not show that the Project qualified for the categorical
    exclusion. 
    Id.
     at 975–79. Though the Forest Service
    determined that the Project fell within the wildland-urban
    interface as identified in the Bonner County community
    plan, that plan defines wildland-urban interface differently
    than does the HFRA. Id. at 979. Thus, the community plan
    could not support use of the categorical exclusion. Id.
    Finally, the district court concluded that remand without
    vacatur was proper. Id. at 980. The district court directed
    the Forest Service to issue a supplemental Decision Memo
    to explain how the Project area falls within the wildland-
    urban interface under HFRA. Id. at 980–81.
    About a month later, the Forest Service issued a
    Supplement to the Decision Memo (the Supplement). The
    Forest Service explained that the Project fell within the
    wildland-urban interface—and thus qualified for the
    categorical exclusion—because it was “entirely within the
    Bonner County [wildland-urban interface] as it is defined in
    the County’s [community wildfire protection plan].” The
    Supplement provided a map of the Project, the surrounding
    area, and the Bonner County community plan’s wildland-
    urban interface. It also highlighted nearby locations
    Nordman and Lamb Creek as at-risk communities.
    In Hanna Flats II, Alliance sued the Forest Service again
    and sought a preliminary injunction against implementation
    of the Project. All. for the Wild Rockies v. Pierson, 
    550 F. 2
    Chief Magistrate Judge Bush decided Hanna Flats I with the parties’
    consent. See 
    28 U.S.C. § 636
    (c).
    12           ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    Supp. 3d 894, 895 (D. Idaho 2021). The district court
    granted the motion, noting “serious questions” about the
    valid application of the categorical exclusion to the Project.
    Id. at 898. The district court reasoned that the Bonner
    County community plan still could not justify use of the
    categorical exclusion because it departed from HFRA’s
    definition of wildland-urban interface. Id. at 899–900. The
    district court also rejected the Forest Service’s argument that
    the Supplement demonstrated that Nordman and Lamb
    Creek were “at-risk communities” under HFRA. Id. at 901–
    04. The Forest Service appealed both orders.
    II
    We begin with the Forest Service’s appeal of the district
    court’s grant of summary judgment in Hanna Flats I. We
    have jurisdiction under 
    28 U.S.C. § 1291
     and “review de
    novo a district court’s grant of summary judgment.” Ctr. for
    Biological Diversity v. U.S. Fish & Wildlife Serv., 
    33 F.4th 1202
    , 1216 (9th Cir. 2022) (citation omitted). When a “case
    involves review of a final agency determination under the
    Administrative Procedure Act,” our “review is limited to the
    administrative record.” Nw. Motorcycle Ass’n v. U.S. Dep’t
    of Agric., 
    18 F.3d 1468
    , 1472 (9th Cir. 1994).
    A
    We start with jurisdiction. Alliance argues that Hanna
    Flats I is moot because the Forest Service has completed its
    remand analysis and provided thirty days’ notice from the
    start of the Project, as ordered by the district court.3 Alliance
    3
    We denied the motion to dismiss for lack of jurisdiction without
    prejudice to renewing the arguments in the answering brief. Though the
    briefing on appeal raises a slightly different theory, we consider the full
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK                  13
    also argues that the Forest Service lacks standing because it
    has complied with the remand order. Alliance is incorrect,
    and we decline to dismiss the Hanna Flats I appeal.
    1
    To begin, the appeal is not moot. Article III “requires
    that an actual, ongoing controversy exist at all stages of
    federal court proceedings.” Bayer v. Neiman Marcus Grp.,
    Inc., 
    861 F.3d 853
    , 862 (9th Cir. 2017) (quoting Pitts v.
    Terrible Herbst, Inc., 
    653 F.3d 1081
    , 1086 (9th Cir. 2011)).
    “The basic question in determining mootness is whether
    there is a present controversy as to which effective relief can
    be granted.” 
    Id.
     (quoting Ruiz v. City of Santa Maria, 
    160 F.3d 543
    , 549 (9th Cir. 1998)).
    “Compliance with a judgment pending appeal presents
    distinctive mootness questions,” but “[t]he general rule is
    now well settled: the case is not moot unless the parties
    intended to settle, or unless it is not possible to take any
    effective action to undo the results of compliance.” 13B
    Charles Alan Wright & Arthur R. Miller, Federal Practice
    and Procedure § 3533.2.2 (3d ed.); see United States ex rel.
    Morgan & Son Earth Moving, Inc. v. Timberland Paving &
    Constr. Co., 
    745 F.2d 595
    , 598 (9th Cir. 1984) (“The usual
    rule in federal courts is that satisfaction of judgment does not
    foreclose appeal.”). Here, the parties did not intend to settle
    this matter. And a long line of Supreme Court authority
    instructs that the government’s compliance with the
    judgment of a lower court—even where compliance
    extent of the arguments to ensure our jurisdiction. Snell v. Cleveland,
    Inc., 
    316 F.3d 822
    , 826 (9th Cir. 2002) (“[A] court may raise the question
    of subject matter jurisdiction, sua sponte, at any time during the
    pendency of the action, even on appeal.”).
    14         ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    involves a new agency decision—does not necessarily moot
    an appeal, especially where some redress remains possible.
    For example, the issuance of provisional regulations by
    the Secretary of the Department of Health and Human
    Services did not moot controversy over the validity of the
    original regulations. Schweiker v. Gray Panthers, 
    453 U.S. 34
    , 42 n.12 (1981). “In issuing the provisional regulations,
    the Secretary simply was adhering to the lower court’s
    reasoning and mandate,” and the Secretary had represented
    “that the new regulations probably would be rescinded if the
    Court of Appeals’ decision were reversed.” 
    Id.
     Likewise,
    the adoption of a new regulation did not moot an appeal
    involving the previous regulation when the new regulation
    was “only for the purpose of interim compliance with the
    District Court’s judgment and order” and when the “appeal
    was taken and submitted on the theory that [the state] desires
    to reinstate the invalidated regulation.” Maher v. Roe, 
    432 U.S. 464
    , 468 n.4 (1977). And a revision to challenged
    regulations to comply with a court order did not moot the
    case when the government’s subsequent actions were
    “consistent with a desire to reinstate its prior regulations.”
    Cornelius v. NAACP Legal Def. & Educ. Fund, 
    473 U.S. 788
    , 791 n.1 (1985).
    So too here. The Forest Service’s compliance with the
    district court’s judgment does not moot this appeal. The
    Forest Service issued the Supplement “in response to the
    Idaho District Court’s order.” The Forest Service has
    consistently claimed it should be allowed to proceed based
    on the original Decision Memo alone and intends to rescind
    the Supplement if this court reverses the decision below.
    The agency rightly complied with the district court’s
    judgment. Still, the effect of that compliance can be undone
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK          15
    by withdrawal of the Supplement that the judgment
    mandated. Thus, the matter is not moot.
    2
    For similar reasons, the Forest Service has standing to
    pursue this appeal. The doctrine of standing, which also
    arises from Article III, “requires the litigant to prove that he
    has suffered a concrete and particularized injury that is fairly
    traceable to the challenged conduct, and is likely to be
    redressed by a favorable judicial decision.” Hollingsworth
    v. Perry, 
    570 U.S. 693
    , 704 (2013). This requirement
    persists “throughout all stages of litigation” and “must be
    met by persons seeking appellate review, just as it must be
    met by persons appearing in courts of first instance.” 
    Id. at 705
     (quoting Arizonans for Off. English v. Arizona, 
    520 U.S. 43
    , 64 (1997)).
    Alliance contends that the Forest Service lacks any
    redressable injury because this court can no longer provide
    any relief in Hanna Flats I given the Forest Service’s
    Supplement. According to Alliance, even a favorable
    decision from this court cannot remedy the Forest Service’s
    voluntary compliance with the district court’s remand order.
    Yet Alliance does not dispute that the district court’s
    judgment renders the Forest Service unable to withdraw the
    Supplement, as the Forest Service currently wishes to do.
    And although the remand order from Hanna Flats I has been
    fully complied with, we have the power to undo the effects
    of that compliance. Cf. DBSI/TRI IV Ltd. P’ship v. United
    States, 
    465 F.3d 1031
    , 1039 (9th Cir. 2006) (holding that
    appeal remained justiciable despite compliance with court-
    ordered sale because sale could “be undone”). The Forest
    Service remains injured by the final judgment in Hanna
    16         ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    Flats I, and this court can redress that injury with a favorable
    decision. Therefore, the Forest Service has standing.
    Alliance relies on Natural Resource Defense Council v.
    Gutierrez for the proposition that an agency has “no standing
    to challenge the district court’s legal rulings in the abstract.”
    
    457 F.3d 904
    , 906 (9th Cir. 2006) (per curiam). That case
    involved a unique set of facts where an agency did “not
    challenge” the only relief granted (a permanent injunction)
    and instead sought only to excise a portion of the district
    court’s ruling stating that the agency had violated a statute.
    
    Id.
     We declined to “line-edit the district court’s ruling”
    because parties must seek “a reversal or a modification of
    the relief granted by the district court.” 
    Id.
     (citation
    omitted). Here, by contrast, the Forest Service seeks to
    reverse the relief granted by the district court by
    withdrawing the Supplement that it was ordered to create.
    Alliance also cites Crow Indian Tribe v. United States,
    
    965 F.3d 662
     (9th Cir. 2020). There, we rejected a challenge
    to our appellate jurisdiction, distinguishing Gutierrez
    because the Fish and Wildlife Service did “challenge what
    the district court ordered it to do on remand.” 
    Id. at 676
    . The
    Fish and Wildlife Service was therefore not “merely
    seek[ing] an advisory opinion.” 
    Id.
     Likewise here, the
    Forest Service challenges what the district court ordered it to
    do on remand. Though Crow Indian Tribe involved a
    challenge made before the agency complied with the
    remand, that does not alter its application because, as
    discussed, the Forest Service can still turn to this court to
    undo the order’s effects.
    We therefore conclude that the doctrines of mootness
    and standing do not deprive us of appellate jurisdiction and
    so turn to the merits of the appeal.
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK         17
    B
    We next evaluate whether the doctrine of administrative
    waiver bars Alliance’s challenge in Hanna Flats I because
    Alliance did not raise its arguments during the public-
    comment period.
    “[A]s a general rule . . . courts should not topple over
    administrative decisions unless the administrative body not
    only has erred but has erred against objection made at the
    time appropriate under its practice.” United States v. L. A.
    Tucker Truck Lines, Inc., 
    344 U.S. 33
    , 37 (1952); see Sisley
    v. DEA, 
    11 F.4th 1029
    , 1035 (9th Cir. 2021) (same). And
    absent exceptional circumstances, failure to raise arguments
    before an agency, such as in comments during a public-
    comment process, usually waives a litigant’s rights to make
    those arguments in court. See Exxon Mobil Corp. v. EPA
    
    217 F.3d 1246
    , 1249 (9th Cir. 2000) (“Petitioners have
    waived their right to judicial review of these final two
    arguments as they were not made before the administrative
    agency, in the comment to the proposed rule . . . .”). Thus,
    the question is whether Alliance adequately raised in its
    public comments that the Project was not within the
    wildland-urban interface or that the wildland-urban interface
    was not a basis for the exclusion.
    1
    At the start, we note the Forest Service has created some
    confusion about its precise argument. On appeal, the Forest
    Service frames the issue as one of administrative waiver.
    Yet below, the Forest Service framed the issue as one of
    administrative exhaustion. This change in the Forest
    Service’s framing of the issue matters because waiver and
    exhaustion are related but distinct doctrines: “the waiver rule
    only forecloses arguments that may be raised on judicial
    18         ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    review; it is not an exhaustion of remedies rule that
    forecloses judicial review.” Universal Health Servs., Inc. v.
    
    Thompson, 363
     F.3d 1013, 1020 (9th Cir. 2004). Further,
    the waiver and exhaustion doctrines do not apply under the
    same circumstances and do not have the same exceptions.
    See, e.g., Portland Gen. Elec. Co. v. Bonneville Power
    Admin., 
    501 F.3d 1009
    , 1023–24 (9th Cir. 2007) (discussing
    differences).
    For purposes of this appeal, we understand the Forest
    Service to be specifically invoking the doctrine of waiver.
    In fact, the Forest Service’s reply brief expressly disclaims
    reliance on the doctrine of exhaustion.
    There is no “bright line rule” when determining whether
    a matter has been properly raised below, but the usual
    standard requires simply “that the argument . . . be raised
    sufficiently for the trial court to rule on it.” Yamada v. Nobel
    Biocare Holding AG, 
    825 F.3d 536
    , 543 (9th Cir. 2016)
    (quoting Whittaker Corp. v. Execuair Corp., 
    953 F.2d 510
    ,
    515 (9th Cir. 1992)). The Forest Service’s labelling of its
    argument is not dispositive in this instance, as even this court
    has “phrased” waiver principles “in terms of standing or
    exhaustion.” Portland Gen. Elec. Co., 
    501 F.3d at 1023
    .
    Not that the doctrines are the same, or that any time the
    government raises exhaustion, it can change course and
    argue waiver on appeal. But the question of preservation
    should not elevate form over substance, particularly on an
    issue where labels have been used imprecisely in the past.
    The Forest Service sufficiently preserved its notice
    argument, even though it framed notice as an exhaustion
    requirement below and as a waiver issue on appeal. Looking
    to the essence of the Forest Service’s argument below, the
    parties focused on whether Alliance’s comments
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK          19
    “sufficiently alerted” the Forest Service “of its concern about
    how the wildland-urban interface was delineated for the
    Project.” Hanna Flats I, 535 F. Supp. 3d at 974. That
    inquiry, asking whether arguments had been “adequately
    raised before the agency” during a public-comment period,
    is an element of both exhaustion and waiver, but turns on a
    principle “best characterized as waiver.” Portland Gen.
    Elec. Co., 
    501 F.3d at 1023
    . The district court concluded
    that Alliance “put [the Forest Service] on notice of the
    issue,” 535 F. Supp. 3d at 974, which created a sufficient
    record for us to review the question of whether Alliance gave
    adequate notice on appeal, W. Watersheds Project v. U.S.
    Dep’t of Interior, 
    677 F.3d 922
    , 925 (9th Cir. 2012) (“There
    is no waiver if the issue was raised, the party took a position,
    and the district court ruled on it.”). We thus assess the Forest
    Service’s notice argument.
    2
    We conclude that Alliance’s comments did not put the
    Forest Service on notice of the wildland-urban interface
    issue. The district court relied on a single comment from
    Alliance to satisfy notice:
    The forest plan Glossary definition of
    [wildland-urban interface] under (A) has
    allowed entities other than the general public
    to set [wildland-urban interface] boundaries
    outside of NEPA . . . processes, and under (B)
    defines it so vaguely as to expand the
    delineation of the [wildland-urban interface]
    greatly – again outside . . . NEPA processes.
    20         ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    See Hanna Flats I, 535 F. Supp. 3d at 974. This sole
    statement bears little resemblance to Alliance’s arguments in
    court.
    The doctrine of administrative waiver “protects the
    agency’s prerogative to apply its expertise, to correct its own
    errors, and to create a record for our review.” Portland Gen.
    Elec. Co., 
    501 F.3d at 1024
    . “In general, we will not invoke
    the waiver rule in our review of a notice-and-comment
    proceeding if an agency has had an opportunity to consider
    the issue.” 
    Id.
     But challengers to government action cannot
    avoid waiver with “cryptic and obscure” objections or issues
    presented at a very high level of generality. See Vermont
    Yankee Nuclear Power Corp. v. Nat. Res. Def. Council, Inc.,
    
    435 U.S. 519
    , 553–54 (1978). Rather, they must present
    timely and “particular objections” that “alert[] the agency to
    the [parties’] position and contentions” and allow “the
    agency to give the issue meaningful consideration.” Pub.
    Citizen, 
    541 U.S. at 764
     (second alteration in original)
    (citation omitted); see Lands Council v. McNair, 
    629 F.3d 1070
    , 1076 (9th Cir. 2010).
    Here, Alliance’s vague and generalized statement that
    the district court cites, contained within more than a hundred
    pages of comments, did not provide sufficient notice to the
    government of Alliance’s current concerns. That comment
    complains only that the definition of “wildland-urban
    interface” is vague and allows “entities other than the
    general public to set [wildland-urban interface] boundaries.”
    This may reflect a broad concern about the size of the
    wildland-urban interface. And it may even be a criticism of
    HFRA. But it is not a claim that the Forest Service has
    violated HFRA—the claim raised in court.
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK          21
    Alliance therefore never gave the Forest Service “an
    opportunity to consider the issue,” Portland Gen. Elec. Co.,
    
    501 F.3d at 1024
    , presented by Alliance’s eventual claim in
    federal court: “The Forest Service has failed to establish that
    this Project is in ‘wildland urban interface’ as defined under
    the HFRA.” Alliance’s comment does not identify any
    violation of HFRA; nor does it allege that the Project falls
    outside the wildland-urban interface. Even more, the
    wildland-urban interface definition complained about (found
    in the glossary of terms attached to the Idaho Panhandle
    National Forests Land Management Plan) is identical to
    HFRA’s definition of wildland-urban interface. This
    comment could not have reasonably alerted the Forest
    Service to Alliance’s eventual claim that the Project violated
    HFRA’s definition of wildland-urban interface, when the
    comment complained of the very definition used by HFRA.
    Alliance also points to other comments and portions of
    the record.      For example, Alliance cites comments
    requesting a map of the density of human residences within
    1.5 miles of the project unit boundaries, the exact criteria for
    a place to be designated as a “landscape-scale insect and
    disease area,” and a detailed map of condition classes and
    fire regimes. Alliance argues that, taken together, the record
    shows that the Forest Service was on notice that it lacked a
    basis to categorically exempt the Project from NEPA “based
    upon a claimed need for wildland-urban interface fuels
    reduction to protect structures or residences” in the Project.
    Yet these comments are even more removed from Alliance’s
    claim. The Forest Service may have been broadly aware that
    Alliance was concerned about the need for the Project or the
    potential lack of risk to local communities or structures
    because of wildfire. But Alliance did not mention before the
    agency that the Forest Service failed to establish that the
    22           ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    Project was in the wildland-urban interface as defined by
    HFRA. That is the claim that Alliance has raised in court.
    Alliance did not put the Forest Service on notice about
    the issue that would provide the basis for Alliance’s eventual
    claim in federal court. The district court erred in concluding
    otherwise.4
    ***
    The district court’s grant of summary judgment for
    Alliance was based on the incorrect conclusion that
    Alliance’s public comments sufficiently alerted the Forest
    Service of the concerns that undergird its current court
    challenge. We thus vacate the grant of summary judgment
    and remand for the district court to consider in the first
    instance whether any such comments were necessary to
    challenge a project exempted from NEPA analysis by a
    categorical exclusion.
    III
    We now address Hanna Flats II, which Alliance brought
    after the Forest Service complied with the remand order and
    4
    Alliance provides an alternative argument for affirmance on this issue:
    that challengers need not file an administrative objection for projects
    exempted from NEPA analysis with a categorical exclusion. The district
    court declined to resolve this issue below. Hanna Flats I, 535 F. Supp.
    3d at 974 n.14. “[W]e generally do not resolve issues that the district
    court did not first reach.” Munden v. Stewart Title Guar. Co., 
    8 F.4th 1040
    , 1049 (9th Cir. 2021). While we have discretion to resolve this
    question, Singleton v. Wulff, 
    428 U.S. 106
    , 120–21 (1976), the issue is
    better left for the district court in the first instance on remand. Alliance
    may raise other waiver-specific arguments that the district court
    concludes were reasonably not made previously given the Forest
    Service’s framing of the issue as one of exhaustion.
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK             23
    issued the Supplement.5 The district court enjoined the
    implementation of the Project because it found “serious
    questions” about whether the Forest Service validly applied
    HFRA’s categorical exclusion to the Project. Hanna Flats
    II, 550 F. Supp. 3d at 898. We have jurisdiction under 
    28 U.S.C. § 1292
    (a)(1) and vacate the preliminary injunction.
    A
    To obtain a preliminary injunction, a plaintiff must
    establish that (1) it is likely to prevail on the merits of its
    substantive claims, (2) it is likely to suffer imminent,
    irreparable harm absent an injunction, (3) the balance of
    equities favors an injunction, and (4) an injunction is in the
    public interest. Winter v. Nat. Res. Def. Council, Inc., 
    555 U.S. 7
    , 20, 22–23 (2008). This court has also instructed that
    “‘serious questions going to the merits’ and a hardship
    balance that tips sharply toward the plaintiff can support
    issuance of an injunction, assuming the other two elements
    of the Winter test are also met.” All. for the Wild Rockies v.
    Cottrell, 
    632 F.3d 1127
    , 1132 (9th Cir. 2011).
    We review a district court’s decision to grant a
    preliminary injunction for abuse of discretion. Sw. Voter
    Registration Educ. Project v. Shelley, 
    344 F.3d 914
    , 918 (9th
    Cir. 2003) (en banc). “An abuse of discretion will be found
    if the district court based its decision on an erroneous legal
    standard or clearly erroneous finding of fact.” Cottrell, 632
    F.3d at 1131 (internal quotation marks and citation omitted).
    We review conclusions of law de novo and findings of fact
    for clear error and “will not reverse the district court where
    it got the law right, even if we would have arrived at a
    5
    The Forest Service concedes that it did not raise an administrative
    waiver argument in Hanna Flats II.
    24         ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    different result, so long as the district court did not clearly
    err in its factual determinations.” Id. (internal quotation
    marks and citation omitted).
    B
    The parties disagree at the outset about the standard of
    review that we apply to the Forest Service’s decision to rely
    on a categorical exclusion. The Forest Service submits that
    we should apply the traditional “arbitrary or capricious”
    standard. But Alliance argues that a less deferential standard
    of “reasonableness” applies.
    Usually, where a statute fails to provide a private right of
    action, judicial review of an agency action proceeds under
    the Administrative Procedure Act (APA). See Lujan v. Nat’l
    Wildlife Fed’n, 
    497 U.S. 871
    , 882–83 (1990); 
    5 U.S.C. § 702
    (“A person suffering legal wrong because of agency action,
    or adversely affected or aggrieved by agency action within
    the meaning of a relevant statute, is entitled to judicial
    review thereof.”). Under the APA, an agency action may not
    be upheld if it is “arbitrary, capricious, an abuse of
    discretion, or otherwise not in accordance with law.” 
    5 U.S.C. § 706
    (2)(A). Here, “neither NEPA nor HFRA
    provide for a private right of action” for violating their
    provisions. Wild Watershed v. Hurlocker, 
    961 F.3d 1119
    ,
    1125 (10th Cir. 2020); accord Lujan, 
    497 U.S. at 882
    (addressing NEPA); Native Ecosystems Council v. Erickson,
    
    330 F. Supp. 3d 1218
    , 1228 (D. Mont. 2018) (addressing
    HFRA). Thus, the general rule suggests that we apply
    arbitrary or capricious review.
    To support its contention that a reasonableness standard
    should apply, Alliance invokes our instruction that “the less
    deferential standard of ‘reasonableness’ applies to threshold
    agency decisions that certain activities are not subject to
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK          25
    NEPA’s procedures.” Northcoast Env’t Cent. v. Glickman,
    
    136 F.3d 660
    , 667 (9th Cir. 1998). Glickman involved
    review of an agency’s determination that an EIS was not
    required because the project did not constitute a “major
    federal action.” 
    Id.
     We applied a more stringent standard
    since the dispute “involve[d] primarily legal issues . . . based
    upon undisputed historical facts.” Id.; see Alaska Wilderness
    Recreation & Tourism Ass’n v. Morrison, 
    67 F.3d 723
    , 727
    (9th Cir. 1995) (“We find that it makes sense to distinguish
    the strong level of deference we accord an agency in
    deciding factual or technical matters from that to be
    accorded in disputes involving predominantly legal
    questions.”).
    Yet Glickman did not involve the invocation of a
    categorical exclusion.        Alliance cites no authority
    establishing that a “reasonableness” standard applies in this
    context. Quite the contrary, we have consistently reviewed
    an agency’s reliance on a categorical exclusion under the
    arbitrary or capricious standard. See Alaska Ctr. for the
    Env’t v. U.S. Forest Serv., 
    189 F.3d 851
    , 858 n.5 (9th Cir.
    1999) (“The question of whether an action . . . fits within the
    categorical exclusion is a factual determination that
    implicates substantial agency expertise and is reviewed
    under the arbitrary and capricious standard.”); see also
    Mountain Cmtys. for Fire Safety, 25 F.4th at 680 (“Given the
    deferential standard of review, we cannot say that the Forest
    Service’s decision to apply [the categorical exclusion] was
    arbitrary and capricious.”); Alcoa, Inc. v. Bonneville Power
    Admin., 
    698 F.3d 774
    , 795 (9th Cir. 2012) (“We will uphold
    an agency’s reliance on a categorical exclusion if ‘the
    application of the exclusions to the facts of the particular
    action is not arbitrary and capricious.’”) (quoting Bicycle
    26         ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    Trails Council of Marin v. Babbitt, 
    82 F.3d 1445
    , 1456 &
    n.5 (9th Cir. 1996)).
    Following the text of the APA and our precedent, we
    review the Forest Service’s reliance on HFRA’s categorical
    exclusion under the familiar arbitrary or capricious standard.
    Applying that standard, we set aside an agency’s action
    if the agency has relied on factors which
    Congress has not intended it to consider,
    entirely failed to consider an important aspect
    of the problem, offered an explanation for its
    decision that runs counter to the evidence
    before the agency, or is so implausible that it
    could not be ascribed to a difference in view
    or the product of agency expertise.
    Motor Vehicle Mfrs. Ass’n of the U.S., Inc. v. State Farm
    Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983).
    C
    Turning to the merits, the district court ruled that there
    were “serious questions as to whether the [Forest Service]
    has adequately demonstrated that the Project area falls
    within HFRA’s statutory definition of the wildland-urban
    interface, and thus whether the [Forest Service’s] invoking
    of HFRA’s categorical exclusion is unlawful.” Hanna Flats
    II, 550 F. Supp. 3d at 899. The Forest Service challenges
    this ruling on multiple grounds, which we address in turn.
    1
    The Forest Service first contends that the district court
    violated the prohibition against “impos[ing] procedural
    requirements not explicitly enumerated in the pertinent
    statutes,” Lands Council v. McNair, 
    537 F.3d 981
    , 993 (9th
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK          27
    Cir. 2008) (en banc) (internal quotation marks and citation
    omitted), by creating a new duty to analyze and show the
    wildland-urban interface’s location before invoking the
    categorical exclusion.
    The Forest Service relies on Oregon Natural Desert
    Association v. U.S. Forest Service, where we rejected an
    argument under the APA and National Forest Management
    Act (NFMA) that the agency acted arbitrarily or capriciously
    when it failed to “analyze and show” that grazing
    authorizations were consistent with the governing forest
    plan. 
    957 F.3d 1024
    , 1033–35 (9th Cir. 2020). There, we
    distinguished caselaw about an agency’s obligations to
    produce NEPA-mandated documentation because NEPA did
    not govern. Id. at 1034. We emphasized that the particular
    duty invoked by plaintiff—mandating “a project’s
    consistency analysis to be memorialized at the time the
    project is authorized”—did not apply “in the absence of
    NEPA’s requirements.” Id. Nor did any “statute, regulation,
    or caselaw” impose the specific obligation “to memorialize
    each site-specific grazing authorization’s consistency with
    the forest plan.” Id. We declined to read that duty into the
    APA or NFMA and therefore concluded that “the absence of
    such a document [was] not in itself arbitrary and capricious.”
    Id.
    Oregon Natural Desert Association does not control.
    The district court did not craft any new procedural duties or
    graft duties from other statutory schemes. The district court
    concluded that there were serious questions about whether
    the Forest Service had “adequately demonstrated” that the
    Project fell within the wildland-urban interface, but it did not
    impose any duties beyond what the APA requires. Hanna
    Flats     II,     550      F.     Supp.     3d     at      899.
    “[T]he touchstone of ‘arbitrary and capricious’ review under
    28          ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    the APA is ‘reasoned decisionmaking.’” Altera Corp. &
    Subsidiaries v. Comm’r, 
    926 F.3d 1061
    , 1080 (9th Cir. 2019)
    (quoting Motor Vehicle Mfrs. Ass’n, 
    463 U.S. at 52
    ). That
    means an agency’s action can only survive arbitrary or
    capricious review where it has “articulate[d] a satisfactory
    explanation for its action including a ‘rational connection
    between the facts found and the choice made.’” 
    Id.
     (citation
    omitted); see Cal. Pub. Utils. Comm’n v. FERC, 
    29 F.4th 454
    , 463 (9th Cir. 2022).
    Tracking the duties already imposed by the APA, the
    district court concluded that the exclusive justification found
    in the record for applying the categorical exclusion—that the
    Project is within the Bonner County community plan’s
    definition of the wildland-urban interface—did not provide
    a satisfactory explanation for avoiding NEPA compliance.6
    Hanna Flats II, 550 F. Supp. 3d at 900. Though the district
    court also noted the Forest Service’s “failure to conduct an
    analysis” applying HFRA’s definition of wildland-urban
    interface, it only did so because it found the Forest Service’s
    “exclusive reliance” on the Bonner County community
    plan’s definition insufficient. Id. The district court did not
    purport to create a freestanding duty that the Forest Service
    conduct a type of independent analysis to be memorialized
    in every categorical-exclusion case.
    In sum, the district court did not, as the Forest Service
    contends, impermissibly create and impose new procedural
    6
    Moreover, Alliance’s claim is not limited to arguing that the Forest
    Service had a unique procedural duty to independently analyze the
    location of the wildland-urban interface. Alliance alleges more broadly
    that the Forest Service “violate[d] . . . HFRA” by relying on the Bonner
    County community plan which did not use “the definition of ‘at-risk
    community’ from the HFRA to define and map its wildland urban
    interface.”
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK        29
    duties on the Forest Service. It simply held the Forest
    Service to the strictures already required by the APA (and,
    by extension, HFRA). The question thus becomes whether
    the district court’s analysis was proper.
    2
    The Forest Service next contends that its Decision Memo
    and Supplement offered a sufficient explanation for use of
    the categorical exclusion simply by noting that the Project is
    within the wildland-urban interface identified by the Bonner
    County community plan.
    Under HFRA, the wildland-urban interface is “an area
    within or adjacent to an at-risk community that is identified
    . . . in a community wildfire protection plan.” 
    16 U.S.C. § 6511
    (16)(A). Here, Bonner County adopted such a plan, and
    the Project falls within the area defined by the plan as
    wildland-urban interface. The Forest Service emphasizes
    that the local community—not the Forest Service—
    identifies the wildland-urban interface in a community plan.
    And so the Forest Service argues that it can simply rely on
    the fact that the Project is within the Bonner County
    community plan’s identified wildland-urban interface;
    nothing else is required when invoking HFRA’s categorical
    exclusion.
    The district court rejected this argument, emphasizing
    that the Bonner County community plan “uses a definition
    that is inconsistent with HFRA’s definition of the wildland-
    urban interface.” Hanna Flats II, 550 F. Supp. 3d at 899
    (citing Hanna Flats I, 535 F. Supp. 3d at 978–79). Adopting
    analysis from the summary judgment order in Hanna Flats
    I, the district court explained:
    30         ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    Although a county’s wildfire protection plan
    can be relied upon in assessing the wildland-
    urban interface, where, as here, a wildfire
    protection plan defines the wildland-urban
    interface differently than HFRA, the wildfire
    protection plan definition cannot provide the
    justification for a categorical exclusion under
    HFRA.
    Id. (internal quotation marks omitted).
    We reject the Forest Service’s argument as well. What
    constitutes a wildland-urban interface is specifically defined
    by HFRA: in pertinent part, it is “an area within or adjacent
    to an at-risk community that is identified in
    recommendations to the Secretary in a community wildfire
    protection plan.” 
    16 U.S.C. § 6511
    (16)(A). HFRA further
    defines “at-risk community” as an area “that is comprised
    of” “an interface community” as defined by federal
    regulation, or “a group of homes and other structures with
    basic infrastructure and services . . . within or adjacent to
    Federal land.” 
    Id.
     § 6511(1)(A)(i), (ii). Thus, under HFRA,
    a wildland-urban interface’s boundaries are tethered to the
    location of at-risk communities, which are themselves
    defined with technical detail.
    The Bonner County community plan, by contrast, has a
    broader definition unmoored from the specifics of HFRA:
    “[A]n area where developed lands interact with undeveloped
    lands and includes the infrastructure and natural resources
    communities rely on for existence. Location: It is found in
    remote scattered development areas to highly developed
    urban areas and everywhere in between.” This definition is
    followed by a “[r]ationale for designating the wildland-
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK         31
    urban interface,” which discusses historical trends for fire
    events and best practices for reducing fire risk.
    Notably absent from the Bonner County community
    plan, however, is any discussion of the HFRA definition of
    wildland-urban interface or “at-risk communities.” Nor is
    there any discussion of interface communities or the relative
    location of federal lands—i.e., the metrics for determining
    at-risk communities under HFRA.           Untethered from
    HFRA’s more limited definitions, the Bonner County
    community plan’s broader definition may well sweep in
    more land than its HFRA counterpart.
    Put simply, the Forest Service seeks to justify invoking
    the categorical exclusion solely because the Project fell
    within the wildland-urban interface designated by the
    Bonner County community plan. But the community plan’s
    definition of its wildland-urban interface—on its face—
    deviates from HFRA and likely results in a covered area
    beyond what Congress authorized. Thus, in this case, the
    Forest Service cannot properly rely on the Bonner County
    community plan—alone—to justify the categorical
    exclusion. This is not to say that the Forest Service can never
    rely on a community plan’s definition of the wildland-urban
    interface or that a community plan’s definition must simply
    parrot HFRA’s. Community plans may well inform the
    Forest Service’s analysis under HFRA. But reliance on a
    plainly overinclusive wildland-urban interface, without
    more, is the sort of “clear error of judgment” that arbitrary
    or capricious review is meant to prevent. Marsh v. Or. Nat.
    Res. Council, 
    490 U.S. 360
    , 378, 385 (1989); see Michigan
    v. EPA, 
    576 U.S. 743
    , 750 (2015) (“[A]gency action is
    lawful only if it rests on a consideration of the relevant
    factors.” (internal quotation marks and citation omitted)).
    32         ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    We thus conclude that the Project’s location within the
    Bonner County community plan’s asserted wildland-urban
    interface is not enough by itself to justify use of HFRA’s
    categorical exclusion.
    3
    The Forest Service also argues that new information
    provided in the Supplement shows that the Project is, in fact,
    within the wildland-urban interface as defined by HFRA. In
    particular, the Supplement contains a map showing the
    Project positioned near the Lamb Creek and Nordman
    communities. The Supplement also highlights that historical
    trends show communities in Bonner County are at the
    “greatest risk from wildfire.” Thus, the Forest Service
    argues that the record shows the Project falls within “an area
    within or adjacent to an at-risk community” and therefore,
    falls within HFRA’s definition of the wildland-urban
    interface. 
    16 U.S.C. § 6511
    (16)(A).
    The district court disagreed. It concluded that serious
    questions existed about whether Nordman and Lamb Creek
    qualified as an “at-risk community,” which is defined as “a
    group of homes and other structures with basic infrastructure
    and services (such as utilities and collectively maintained
    transportation routes) within or adjacent to Federal land.”
    Hanna Flats II, 550 F. Supp. 3d at 903 (quoting 
    16 U.S.C. § 6511
    (1)(A)(ii)).
    Drawing from § 6511(1)(A), the district court stated that
    “under the plain language of HFRA . . . the at-risk
    community must be ‘within or adjacent to,’ i.e., border or
    ‘abut,’ the Federal land at issue, i.e., the Project area.” Id.
    at 904 (emphasis added). There is no dispute that “neither
    Nordman nor Lamb Creek border the Project area.” Id. at
    903–04 (“[T]he communities identified in the Supplemental
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK            33
    Memo—Nordman and Lamb Creek—are three miles away
    and one mile away, respectively, from the Project area.”).
    Thus, the district court concluded that those communities did
    not qualify as “at-risk communities” under § 6511(1)(A) and
    therefore did not support the “determination that the Project
    area is entirely located within the wildland-urban interface.”
    Id. at 904.
    On appeal, the Forest Service contends that the district
    court’s reading of HFRA—which requires a community to
    border or abut the project area to qualify as an “at-risk
    community”—is incorrect. In particular, the Forest Service
    challenges the district court’s substitution of the words “the
    Project area” for the statutory text “Federal land.”
    a
    The district court erred in its interpretation. In fairness,
    HFRA is not a model of clarity and contains several
    interrelated provisions. But a careful reading of the
    unambiguous text shows that a project is subject to the
    categorical exclusion when it is “in the wildland-urban
    interface.” 16 U.S.C. § 6591b(c)(2)(A) (“A project under
    this section shall be limited to areas . . . in the wildland-urban
    interface . . . .”). An “area” qualifies as “wildland-urban
    interface” if it is “within or adjacent to an at-risk
    community.” Id. § 6511(16)(A). And a community is “at
    risk” if it is “within or adjacent to Federal land.” Id.
    § 6511(1)(A)(ii).
    In summary, the project must fall within an area (the
    wildland-urban interface) that is within or adjacent to an at-
    risk community. An at-risk community must be within or
    adjacent to federal land.           But the district court’s
    interpretation collapses these distinct provisions into a rule
    that the project itself must border the at-risk community. For
    34         ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    the district court, “Federal land” must be the federal land at
    issue in the case (which would be the Project land here).
    Under the district court’s interpretation, even if a project
    falls within a properly defined wildland-urban interface, the
    project is not valid unless it also directly borders or abuts an
    at-risk community. Yet nothing in the statutory language
    supports this limitation.
    The district court justified its “border or abut” rule by
    noting “the distinction made by HFRA between an area that
    has a community wildfire protection plan and an area that
    does not have a community wildfire protection plan.”
    Hanna Flats II, 550 F. Supp. 3d at 904. Where, as here, there
    is a community wildfire protection plan in place, the
    wildland-urban interface is defined as an area “within or
    adjacent to an at-risk community.”             
    16 U.S.C. § 6511
    (16)(A). By contrast, for an area where the community
    has not adopted such a plan, the wildland-urban interface is
    defined as an area either 0.5 miles or 1.5 miles from the
    boundary of an at-risk community, depending on geographic
    and other characteristics. See 
    id.
     § 6511(16)(B)(i), (ii).
    Thus, HFRA provides communities without plans a
    baseline level of protection but imposes a specific wildland-
    urban interface boundary of either 0.5 miles or 1.5 miles
    away, depending on various factors. Id. § 6511(16)(B). But
    HFRA also allows communities to adopt a community
    wildfire protection plan that “identifies and prioritizes areas
    for hazardous fuel reduction treatments.” Id. § 6511(3)(B).
    HFRA “gives priority” to projects “that implement
    community wildfire protection plans,” id. § 6513(a), and
    ensures that funding allocations “give priority to
    communities that have adopted a community wildfire
    protection plan,” id. § 6513(d)(2)(B). And for communities
    with such a plan, the wildland-urban interface is defined in
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK        35
    more flexible terms: “an area within or adjacent to an at-risk
    community that is identified . . . in a community wildfire
    protection plan.” Id. § 6511(16)(A).
    In sum, the statutory scheme creates a baseline
    protection of at least 0.5 or 1.5 miles around at-risk
    communities.        But the statutory scheme permits
    communities with plans to identify wildland-urban
    interfaces that extend beyond those strict limitations to meet
    their communities’ needs. Thus, while we agree with the
    district court that the statutory scheme treats communities
    with and without community plans differently, we conclude
    that the statutory scheme gives communities with plans
    more—not less—flexibility. This makes sense, because the
    increased flexibility gives communities an incentive to
    develop a community plan. The district court’s rule that a
    project must border or abut an at-risk community flips
    HFRA’s scheme on its head. Under that rule, communities
    that adopt plans would enjoy HFRA’s protections only for
    projects right next to the at-risk community, significantly
    limiting their choice to “identif[y]” wildland-urban
    interfaces in their community plans. Id. § 6511(16)(A).
    HFRA prioritizes communities with plans and allows them
    a more flexible standard for defining the wildland-urban
    interface. Therefore, the district court’s interpretation is
    belied by HFRA’s statutory language.
    b
    In issuing the injunction, the district court applied the
    less-stringent “serious questions” standard instead of the
    typical “likelihood of success of the merits” inquiry. Hanna
    Flats II, 550 F. Supp. 3d at 898. But that does not alter our
    analysis. In the context of injunctive relief, “serious
    questions” refer to “questions that ‘cannot be resolved one
    36         ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    way or the other at the hearing on the injunction’ because
    they require ‘more deliberative investigation.’” Manrique v.
    Kolc, --- F.4th ---, No. 22-15705, 
    2023 WL 3036993
    , at *3
    (9th Cir. 2023) (quoting Republic of the Philippines v.
    Marcos, 
    862 F.2d 1355
    , 1362 (9th Cir. 1988) (en banc)).
    Though this standard is less demanding, it does not erase the
    Supreme Court’s admonition that an injunction “may only
    be awarded upon a clear showing that the plaintiff is entitled
    to such relief.” Winter, 
    555 U.S. at 22
    . Accordingly, a
    “serious question” does not exist where the plaintiff’s claim
    is “merely plausible” or just because there are legal
    questions not directly answered by past precedent. Where
    Do We Go Berkeley v. Cal. Dep’t of Transp., 
    32 F.4th 852
    ,
    863 (9th Cir. 2022) (instructing that “the district court must
    analyze the merits” and cannot “forgo legal analysis just
    because it has not identified precedent that places the
    question beyond debate”).
    Here, the district court found a “serious question” about
    the validity of the categorical exclusion due to an incorrect
    interpretation of a statute—a pure error of law. But like
    many legal questions, the meaning of HFRA’s unambiguous
    provisions would not become clearer with “at least some
    discovery” or a “further hearing on the merits.” Cottrell, 632
    F.3d at 1131 (citation omitted). There is no need for more
    deliberative investigation or development of the record to
    resolve the plain meaning of HFRA.
    We therefore conclude that the district court relied on a
    misinterpretation of HFRA in concluding that serious
    questions existed going to the merits.7 Because a legal error
    7
    We do not decide whether Nordman or Lamb Creek (or anywhere else)
    qualify as “at-risk communities” for purposes of HFRA’s categorical
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK               37
    infected this “‘threshold inquiry,’ we need not consider the
    other factors” governing injunctive relief. See California v.
    Azar, 
    911 F.3d 558
    , 575 (9th Cir. 2018) (citation omitted).
    c
    Finally, Alliance argues that, even if the district court
    erred in issuing the preliminary injunction, we should leave
    it in place while the district court reconsiders whether there
    are sufficient serious questions on remand. The district court
    never addressed Alliance’s alternative theory for a
    preliminary injunction: that the Project violates limitations
    on roads in certain areas designated for bear protection
    called Bears Outside Recovery Zones (BORZ).
    It is counterintuitive to keep a preliminary injunction in
    place after concluding the district court abused its discretion
    in issuing it. Typically, a trial court’s decision about a
    preliminary injunction is properly “set aside when it is based
    on . . . improper legal premises.” Regents of Univ. of Cal.
    v. Am. Broad. Cos., 
    747 F.2d 511
    , 515 (9th Cir. 1984). After
    all, a preliminary injunction is an “extraordinary remedy
    never awarded as of right” or without a “clear showing” of
    entitlement; absent that, such relief should not issue. Winter,
    
    555 U.S. at 22, 24
    . Yet on a handful of occasions, we have
    retained an injunction granted on improper legal bases,
    though under unique circumstances.
    For example, in Gerling Global Reinsurance Corp. of
    America v. Low, 
    240 F.3d 739
    , 754 (9th Cir. 2001), we held
    that the district court erred in finding that a statute violated
    the dormant Commerce Clause and the foreign affairs
    power, yet still left the preliminary injunction in place to
    exclusion. That question can be addressed on remand under proper legal
    and statutory standards.
    38         ALLIANCE FOR THE WILD ROCKIES V. PETRICK
    give the district court an opportunity to consider an
    unaddressed argument that the statute also violated the Due
    Process Clause. But the defendant “acknowledged at oral
    argument” that there was a “serious question” about the
    validity of a statute under that alternative ground, and there
    was no dispute that plaintiffs would suffer irreparable harm
    if the statute took effect. 
    Id.
     at 754 & n.11. And in United
    States v. Hovsepian, 
    359 F.3d 1144
    , 1157 (9th Cir. 2004) (en
    banc), we held that a district court erred in entering an
    injunction preventing the government from deporting
    someone. We also left the “the injunction in place . . . .
    pending the conclusion of all proceedings in this case, in aid
    of the court’s jurisdiction.” 
    Id.
    This is not a case, however, where Alliance’s alternative
    BORZ argument (which is discussed fairly briefly on appeal)
    clearly has merit. Unlike in Gerling, the Forest Service
    claims this alternative argument is meritless. And unlike in
    Hovsepian, nothing suggests that retaining the injunction is
    needed to protect our jurisdiction. Alliance makes no
    argument that irreparable harm or mootness issues will arise
    before it can renew its request for a preliminary injunction
    on these alternative grounds. Ultimately, whether to issue a
    preliminary injunction—or, in this case, retain one—“is an
    exercise of discretion and judgment.” Trump v. Int’l Refugee
    Assistance Project, 
    137 S. Ct. 2080
    , 2087 (2017). And here,
    there is no reason to conclude that we should exercise our
    equitable discretion to leave an injunction in place that was
    wrongly granted, and where no likelihood of success on
    another claim is clear.
    Because the preliminary injunction was based on a legal
    error, we vacate it.
    ALLIANCE FOR THE WILD ROCKIES V. PETRICK                      39
    VI
    For these reasons, the district court’s grant of summary
    judgment in Hanna Flats I is VACATED and the district
    court’s preliminary injunction in Hanna Flats II is
    VACATED. We REMAND both matters for proceedings
    consistent with this opinion.8
    8
    We DENY Alliance’s opposed request for judicial notice of a timber
    sale cancellation letter. Even assuming this letter is judicially noticeable,
    it is not “relevant to any issue on appeal.” Flick v. Liberty Mut. Fire Ins.
    Co., 
    205 F.3d 386
    , 393 n.7 (9th Cir. 2000). We also DENY Alliance’s
    request to strike portions of the Forest Service’s briefing that cite internet
    sources. We permit “undisputed facts offered only for general
    background” to be offered without a citation to the excerpts of record.
    9th Cir. R. 28-2.8.
    

Document Info

Docket Number: 21-35504

Filed Date: 5/16/2023

Precedential Status: Precedential

Modified Date: 5/16/2023

Authorities (37)

Wildwest Institute v. Bull , 547 F.3d 1162 ( 2008 )

Natural Resources Defense Council v. Gutierrez , 457 F.3d 904 ( 2006 )

Southwest Voter Registration Education Project v. Shelley , 344 F.3d 914 ( 2003 )

Lands Council v. McNair , 629 F.3d 1070 ( 2010 )

United States v. Hovsepian , 359 F.3d 1144 ( 2004 )

Friends of Southeast's Future v. Morrison , 153 F.3d 1059 ( 1998 )

Alaska Center for the Environment Alaska Wildlife Alliance ... , 189 F.3d 851 ( 1999 )

Whittaker Corporation Whittaker Controls, Inc. v. Execuair ... , 953 F.2d 510 ( 1992 )

Pitts v. Terrible Herbst, Inc. , 653 F.3d 1081 ( 2011 )

Donald L. Snell v. Cleveland, Inc., and Patricia Faber John ... , 316 F.3d 822 ( 2002 )

Alcoa, Inc. v. Bonneville Power Administration , 698 F.3d 774 ( 2012 )

Western Watersheds Project v. United States Department of ... , 677 F.3d 922 ( 2012 )

Goldammer v. United States , 465 F.3d 1031 ( 2006 )

The Lands Council v. McNair , 537 F.3d 981 ( 2008 )

Ruiz v. City of Santa Maria , 160 F.3d 543 ( 1998 )

Gerling Global Reinsurance Corp. of America v. Low , 240 F.3d 739 ( 2001 )

United States ex rel. Morgan & Son Earth Moving, Inc. v. ... , 745 F.2d 595 ( 1984 )

Jason Yamada v. Nobel Biocare Holding Ag , 825 F.3d 536 ( 2016 )

The Republic of the Philippines v. Ferdinand E. Marcos , 862 F.2d 1355 ( 1988 )

Portland General Electric Co. v. Bonneville Power ... , 501 F.3d 1009 ( 2007 )

View All Authorities »