Center for Biological Diversity v. Blm ( 2023 )


Menu:
  •                 FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    CENTER FOR BIOLOGICAL                 No. 22-55317
    DIVERSITY; DEFENDERS OF
    WILDLIFE; SIERRA CLUB,                   D.C. No.
    Plaintiffs-Appellees,            2:21-cv-02507-
    GW-AS
    v.
    BUREAU OF LAND                          OPINION
    MANAGEMENT; DEB HAALAND,
    Secretary of Interior; NADA
    CULVER, Senior Advisor to the
    Secretary of the Department of the
    Interior; KAREN MOURITSEN,
    California Director, Bureau of Land
    Mgmt.; ANDREW ARCHULETA,
    California Desert District Manager,
    Bureau of Land Mgmt.; MICHAEL
    AHRENS, Needles Field Office
    Manager, Bureau of Land Mgmt.,
    Defendants-Appellees,
    CADIZ, INC.; CADIZ REAL
    ESTATE LLC,
    Intervenor-Defendants-
    Appellees,
    v.
    2   CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.
    COMMUNITY BUILD, INC.;
    SOUTHERN CHRISTIAN
    LEADERSHIP CONFERENCE OF
    GREATER LOS ANGELES; LOS
    ANGELES METROPOLITAN
    CHURCHES; NEWSTART
    HOUSING CORPORATION; THE
    TWO HUNDRED FOR
    HOMEOWNERSHIP;
    FARMWORKERS INSTITUTE FOR
    EDUCATION & LEADERSHIP
    DEVELOPMENT; LEAGUE OF
    UNITED LATIN AMERICAN
    CITIZENS OF CALIFORNIA; LA
    COOPERATIVA CAMPESINA DE
    CALIFORNIA, Proposed Defendant-
    Intervenors,
    Movants-Appellants.
    Appeal from the United States District Court
    for the Central District of California
    George H. Wu, District Judge, Presiding
    Argued and Submitted January 12, 2023
    Pasadena, California
    Filed May 26, 2023
    Before: Paul J. Watford, Michelle T. Friedland, and Mark
    J. Bennett, Circuit Judges.
    Opinion by Judge Friedland;
    Concurrence by Judge Friedland
    CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.          3
    SUMMARY*
    Intervention
    The panel dismissed for lack of jurisdiction an appeal
    challenging the district court’s order denying several
    organizations’ motion to intervene as defendants in a lawsuit
    against the Bureau of Land Management (“BLM”)
    challenging the grant of two rights-of-way.
    While the appeal was pending, the district court held that
    the decision to grant the rights-of-way was arbitrary and
    capricious, vacated it, and remanded the matter to the
    agency. The panel held that the district court’s ruling
    mooted the intervention dispute.
    Generally, if the underlying litigation is complete, an
    appeal of a denial of intervention is moot and must be
    dismissed. The panel held that an intervention dispute
    would remain alive if this court could grant effectual relief,
    or if there were some other way for the proposed intervenors
    to obtain their desired relief.
    Here, the district court’s proceedings are complete. No
    party has filed an appeal of the district court’s merits order,
    and under Alsea Valley Alliance v. Department of
    Commerce, 
    358 F.3d 1181
     (9th Cir. 2004), this Court would
    not have jurisdiction over such an appeal brought by
    Appellants even if they were granted intervention.
    *
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    4   CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.
    Remands-without-vacatur are generally not considered
    final. However, Alsea held that when a district court
    declares an agency action invalid and orders remand-with-
    vacatur, the district court’s order is treated as a final,
    appealable judgment under 
    28 U.S.C. § 1291
     if: “(1) the
    district court conclusively resolves a separable legal issue,
    (2) the remand order forces the agency to apply a potentially
    erroneous rule which may result in a wasted proceeding, and
    (3) review would, as a practical matter, be foreclosed if an
    immediate appeal were unavailable.”
    In Pit River Tribe v. U.S. Forest Serv., 
    5615 F.3d 1069
    (9th Cir. 2010), this court relied on Alsea’s third prong to
    hold that it lacked appellate jurisdiction, reasoning that
    because the agencies could either extend or decline to extend
    two leases to develop geothermal power plants on remand,
    any decision by this court prior to the decision on remand
    could prove unnecessary, and thus the district court’s order
    was not final and appealable. The panel held that this case
    was indistinguishable from Pit River Tribe. BLM failed to
    conduct the relevant statutory reviews before granting the
    rights-of-way. The district court vacated the decision to
    grant the rights-of-way but explicitly noted that BLM might
    re-grant them on remand after performing the requisite
    analyses. From Appellants’ perspective, eventual appellate
    review about the rights-of-way is therefore not foreclosed,
    so Alsea’s third requirement is not satisfied.
    The panel also concluded that the “capable of repetition,
    yet evading review” exception to mootness did not apply
    because the intervention dispute is not inherently limited in
    duration such that it is always likely to become moot before
    federal court litigation is completed. There was no reason to
    think that if another lawsuit arose regarding similar rights-
    of-way and Appellants attempted to appeal a denial of
    CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.   5
    intervention, there would be another immediate remand that
    would moot any intervention appeal.
    Because the merits dispute has been remanded to the
    agency and this court could not afford Appellants any path
    to relief by granting intervention, Appellants’ appeal of the
    denial of intervention is moot.
    Judge Friedland, joined by Judge Bennett, concurred.
    Although precedent compelled the conclusion that the
    intervention dispute was moot, she wrote separately to urge
    the court to reconsider en banc Alsea’s holding—that orders
    invalidating and then remanding and vacating agency
    actions are nonfinal and not appealable unless three criteria
    are satisfied—when the right opportunity arises. She urged
    a more pragmatic approach to finality under which a
    remand-with-vacatur is considered a final order.
    COUNSEL
    Rafe Petersen (argued), Holland & Knight, LLP,
    Washington, D.C.; Jennifer L. Hernandez, Holland &
    Knight, LLP, Los Angeles, California.; David A. Robinson
    and Kevin J. Ashe, Holland & Knight, LLP, Irvine,
    California; for Movants-Appellants.
    Amelia G. Yowell (argued), Andrew C. Mergen, Daniel J.
    Halainen, and Luther L. Hajek, Attorneys; Todd Kim,
    Assistant Attorney General; Environment and Natural
    Resources Division, United States Department of Justice;
    Washington, D.C.; Laura L. Barhydt and Michael D. Smith,
    Attorney-Advisors; Office of the Solicitor, United States
    Department of Justice; Washington, D.C.; for Defendants-
    Appellees.
    6   CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.
    Lisa T. Belenky and Aruna M. Prabhala, Center for
    Biological Diversity, Oakland, California; Elizabeth Britta
    Forsyth and Gregory Cahill Loarie, Earthjustice, San
    Francisco, California; for Plaintiffs-Appellees.
    Diana C. De Felice, Brownstein Hyatt Farber Schreck LLP,
    Los Angeles, California; Christopher O. Murray,
    Brownstein Hyatt Farber Schreck LLP, Denver, Colorado;
    for Intervenor-Defendants-Appellees.
    OPINION
    FRIEDLAND, Circuit Judge:
    Several organizations sought to intervene as defendants
    in a lawsuit against the Bureau of Land Management
    challenging the grant of two rights-of-way. The district
    court denied intervention, and the proposed intervenors filed
    this appeal. While the appeal was pending, the district court
    held that the decision to grant the rights-of-way was arbitrary
    and capricious, vacated it, and remanded the matter to the
    agency. We hold that the district court’s ruling mooted the
    intervention dispute, and we accordingly dismiss this appeal.
    I.
    In 2020, Cadiz Real Estate LLC applied to the Bureau of
    Land Management (“BLM”) for two rights-of-way: one for
    the right to use an existing natural gas pipeline and the
    second to use that pipeline to transport water across federal
    lands in California. In its application, Cadiz represented that
    it would provide water for various municipal, agricultural,
    and industrial uses but identified no specific plans. Although
    CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.   7
    the potential impacts of the proposed rights-of-way could
    have triggered administrative review obligations under the
    National Historic Preservation Act (“NHPA”), the National
    Environmental Policy Act (“NEPA”), and the Federal Land
    Policy and Management Act (“FLPMA”), BLM did not
    conduct reviews under any of these statutes. It nonetheless
    approved the application, reassigning to Cadiz the existing
    gas pipeline and allowing its use for water transport.
    In early 2021, the Center for Biological Diversity and
    other environmental groups (collectively, “CBD”) filed the
    lawsuit that led to this appeal. CBD challenged BLM’s
    approval of the rights-of-way, arguing that BLM had
    violated NEPA and FLPMA. On the same day, the Native
    American Land Conservancy and the National Parks
    Conservation Association also sued BLM, asserting that
    approval of the rights-of-way had violated those same
    statutes, as well as NHPA. Cadiz moved to intervene as a
    defendant in both suits, which the district court permitted.
    Because a new presidential administration had just
    assumed office, both suits were stayed until late 2021 to
    allow the new administration to assess its position on the
    matter.        BLM then admitted error—conceding
    noncompliance with NEPA, failure to assess compliance
    with FLPMA, and failure to evaluate impacts under NHPA.
    In both suits, BLM moved for remand and vacatur of the
    grant of the rights-of-way.
    A coalition of civil rights, housing, and environmental
    justice organizations serving disadvantaged communities in
    Southern California (“Appellants”) subsequently moved to
    8   CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.
    intervene as defendants in this lawsuit.1 Appellants hoped
    Cadiz’s water pipeline would be used to expand access to
    clean, affordable water in their communities and sought to
    present social and environmental justice reasons for
    maintaining the grant of the rights-of-way to Cadiz. The
    district court denied both intervention as of right and
    permissive intervention, explaining that Appellants’
    interests would be adequately represented by Cadiz.
    Appellants appealed that decision to our court, and no one
    sought a stay of the district court proceedings pending that
    appeal.
    While the parties were still briefing the intervention
    dispute before our court, the district court granted BLM’s
    motion for remand and vacatur in a combined order that
    addressed both the suit brought by CBD and the suit brought
    by the Native American Land Conservancy. The court
    concluded that because BLM had not undertaken the
    analyses required by NEPA, NHPA, and FLPMA, the
    agency’s decision to grant the rights-of-way was arbitrary
    and capricious. The district court remanded to BLM to allow
    it to “reevaluate its decision” and vacated the grant of the
    rights-of-way, explaining that vacatur was appropriate
    because the “statutory processes were bypassed almost
    entirely” and the water transportation project was still in a
    preliminary phase. No one appealed that order.
    1
    Appellants did not move to intervene in the lawsuit brought by the
    Native American Land Conservancy.
    CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.          9
    Once the parties informed us of the remand-with-
    vacatur,2 we ordered supplemental briefing on whether this
    intervention appeal had become moot, which the parties
    submitted prior to oral argument. Appellants argue that their
    appeal is not moot and that, because Cadiz could not
    adequately represent their interests, the district court was
    wrong to deny intervention. BLM argues that the district
    court was correct to deny intervention but that we lack
    jurisdiction to review that decision because the intervention
    dispute was mooted by the district court’s order remanding
    and vacating the grant of the rights-of-way.
    II.
    The denial of a motion to intervene as of right is a final,
    appealable order, so we typically have jurisdiction over
    appeals of such denials. See 
    28 U.S.C. § 1291
    ; League of
    United Latin Am. Citizens v. Wilson, 
    131 F.3d 1297
    , 1302
    (9th Cir. 1997). But an appeal of a denial of intervention is
    moot if it is “impossible for the court to grant any effectual
    relief whatever to the putative intervenor even if [the court]
    were to determine that the district court erred in denying his
    intervention.” United States v. Sprint Commc’ns, Inc., 
    855 F.3d 985
    , 990 (9th Cir. 2017) (quotation marks and citation
    omitted). In other words, if reversing the district court’s
    denial of intervention could not help the prospective
    intervenors further their interests, the intervention dispute is
    moot.
    2
    In this opinion, we use “remand-with-vacatur” to mean only the kind
    of remand with vacatur that occurred here—one following a merits
    determination holding the rule invalid. We do not include the rare
    instances in which courts have impermissibly remanded and vacated
    rules without first holding them unlawful. See In re Clean Water Act
    Rulemaking, 
    60 F.4th 583
    , 593-94 (9th Cir. 2023).
    10 CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.
    That is the case here. As we will explain, the district
    court’s remand-with-vacatur order terminated the
    proceeding in which Appellants sought to intervene, and we
    would not have jurisdiction over an attempted appeal of that
    order, so there is no relief available to Appellants even if
    they were to persuade us that the district court should have
    granted intervention. The appeal is therefore moot.
    A.
    Generally, if the underlying litigation is complete, an
    appeal of a denial of intervention is moot and must be
    dismissed. See W. Coast Seafood Processors Ass’n v. Nat.
    Res. Def. Council, Inc., 
    643 F.3d 701
    , 704 (9th Cir. 2011)
    (holding that because the underlying litigation had ended and
    no party had appealed, we could not grant any “effective
    relief” (quoting Outdoor Media Grp., Inc. v. City of
    Beaumont, 
    506 F.3d 895
    , 900 (9th Cir. 2007))); Akina v.
    Hawaii, 
    835 F.3d 1003
    , 1010 (9th Cir. 2016) (“[This court]
    has no jurisdiction over an appeal that has become moot.”).
    But if we could permit the proposed intervenors to
    participate in ongoing district court proceedings or in an
    appeal of a district court’s merits decision, that would
    amount to “effectual relief,” so the intervention dispute
    would remain alive.3 See, e.g., Allied Concrete & Supply
    Co. v. Baker, 
    904 F.3d 1053
    , 1066 (9th Cir. 2018).
    3
    Our caselaw has been arguably inconsistent about whether, in cases in
    which the district court reached a final judgment on the merits, the
    absence of an existing appeal by a current party renders moot any appeal
    of a denial of intervention. For example, in West Coast Seafood, we held
    that an appeal of a denial of intervention was moot because the district
    court had issued a final judgment on the merits “from which neither party
    ha[d] appealed,” suggesting that the intervention dispute remains live
    CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT. 11
    An intervention dispute may also remain alive if there is
    some other way for the proposed intervenors to obtain their
    desired relief. For instance, in Sprint Communications, the
    parties had settled, and the district court had granted
    voluntary dismissal of the suit before our court could rule on
    the proposed intervenor’s appeal of the denial of
    intervention. See 855 F.3d at 989-90. We held that because
    the proposed intervenor “might be able to object to the
    settlement or otherwise seek his share of the proceeds” from
    the liable party, the appeal was not moot. Id. at 990.
    only if an appeal has already been filed by existing parties. 
    643 F.3d at 704
    . By contrast, in DBSI/TRI IV Ltd. Partnership v. United States, 
    465 F.3d 1031
     (9th Cir. 2006), we suggested that the potential for a future
    merits appeal by the intervenors could keep the intervention dispute
    alive. See 
    id. at 1037
    . Even though DBSI and the government had
    stipulated to the district court’s judgment in the quiet title action there,
    see 
    id. at 1036
    , signaling that they would not appeal, we held that the
    proposed intervenors’ appeal of the denial of intervention was not moot
    because “if it were concluded on appeal that . . . [they were] indeed
    entitled to intervene . . . , then the [intervenors] would have standing to
    appeal the district court’s judgment.” 
    Id. at 1037
     (quoting Canatella v.
    California, 
    404 F.3d 1106
    , 1109 n.1 (9th Cir. 2005)).
    We need not resolve any inconsistency in these cases because, as we
    will explain, Appellants could not have appealed on the merits even if
    they had been granted intervention in the district court in the first place.
    Under our caselaw, the order remanding and vacating is not a final,
    appealable judgment. Further, because that order is not a final,
    appealable judgment, we need not consider whether any attempted
    appeal by Appellants would be barred on timeliness grounds at this point.
    See Evans v. Synopsys, Inc., 
    34 F.4th 762
    , 770 (9th Cir. 2022) (holding
    that the appeal deadline in 
    28 U.S.C. § 2107
     applies to appeals by
    intervenors).
    12 CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.
    B.
    Here, the district court’s proceedings are complete.
    Nothing remains pending before the district court: The court
    resolved all of the claims in its merits order and noted on the
    docket that “this matter is now closed.” The only potential
    path to relief for Appellants, then, would be through
    participation in an appeal of the merits order. But no party
    has filed such an appeal, and under Alsea Valley Alliance v.
    Department of Commerce, 
    358 F.3d 1181
     (9th Cir. 2004),
    we would not have jurisdiction over such an appeal brought
    by Appellants even if they were granted intervention.
    Remands-with-vacatur are generally not considered
    final. See 
    id. at 1184-86
    . Alsea held, however, that when a
    district court declares an agency action invalid and orders
    remand-with-vacatur, the district court’s order is treated as a
    final, appealable judgment under 
    28 U.S.C. § 1291
     if: “(1)
    the district court conclusively resolves a separable legal
    issue, (2) the remand order forces the agency to apply a
    potentially erroneous rule which may result in a wasted
    proceeding, and (3) review would, as a practical matter, be
    foreclosed if an immediate appeal were unavailable.” 
    Id. at 1184
     (quoting Collord v. U.S. Dep’t of Interior, 
    154 F.3d 933
    , 935 (9th Cir. 1998)). This framework applies to
    attempted appeals brought by both agency and non-agency
    litigants. See, e.g., Collord, 
    154 F.3d at 935
     (applying the
    inquiry to an appeal brought by an agency); Pit River Tribe
    v. U.S. Forest Serv., 
    615 F.3d 1069
    , 1072-77 (9th Cir. 2010)
    (applying the three-prong inquiry to an appeal brought by
    non-agency litigants).
    In Alsea, the third prong alone dictated that appellate
    jurisdiction was lacking. The district court there had
    declared unlawful and set aside the National Marine
    CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT. 13
    Fisheries Service’s final rule designating as “threatened”
    under the Endangered Species Act one type of salmon but
    not a related type. 
    358 F.3d at 1183
    . The district court had
    remanded to the agency for reconsideration of the salmon
    categorization, and several environmental organization
    intervenors appealed. See 
    id. at 1184
    . We evaluated
    whether future appellate review “would, as a practical
    matter, be foreclosed” from the perspective of the party
    attempting to appeal—the intervenors. 
    Id.
     (quoting Collord,
    
    154 F.3d at 935
    ). Because the agency on remand could still
    issue a salmon-designation rule that satisfied the
    intervenors’ concerns and because, if the agency did not, the
    intervenors could “bring suit at that point to challenge the
    Service’s action,” a later appeal by the intervenors was not
    foreclosed, and “any decision by us could [have] prove[n]
    entirely unnecessary.” Id. at 1185.4 We therefore held that
    the remand-with-vacatur was not a final, appealable order
    under 
    28 U.S.C. § 1291
    . See id.5
    Alsea contrasted the situation there with one in which an
    agency appellant “compelled to refashion [its] own rules”
    could “face the unique prospect of being deprived of review
    4
    Alsea treated the part of the district court’s order that remanded the
    regulation as inseparable from the part of the order that vacated it. See
    
    358 F.3d at 1185-86
     (rejecting the intervenors’ efforts to “tr[y] to parse
    the district court’s order [by] arguing that setting aside the [rule] is a
    separately appealable district court decision, distinct from declaring the
    [rule] unlawful”).
    5
    In Alsea, we also rejected the argument that the order was appealable
    under 
    28 U.S.C. § 1292
    . See 
    358 F.3d at 1186
    . We observed that
    Section 1292(a)(1) gives us jurisdiction over appeals of interlocutory
    orders “granting . . . injunctions.” 
    Id.
     (quoting 
    28 U.S.C. § 1292
    (a)(1)).
    But we held that the remand-with-vacatur did not have the “practical
    effect” of granting an injunction. 
    Id. at 1186-87
    .
    14 CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.
    altogether” if an immediate appeal were unavailable. 
    Id. at 1184
    . For instance, in Collord, the district court had held
    that the Equal Access to Justice Act applied to the agency
    proceedings and remanded for the agency to consider the
    merits of an application for fees under that Act. See 
    154 F.3d at 935
    . The Secretary of the Interior appealed, and we
    explained that if immediate review of the applicability of the
    Act were not available, review of the Secretary’s position
    that the statute did not apply might be foreclosed altogether:
    The Secretary would not be able to appeal “his own agency’s
    decision” if it was favorable to the applicants on remand. 
    Id.
    The remand order was thus final for the purposes of the
    Secretary’s appeal. See 
    id.
    In Pit River Tribe, we held that the situation was more
    like that in Alsea than that in Collord and again relied on the
    third prong to hold that we lacked appellate jurisdiction.
    There, BLM had extended two leases to develop geothermal
    power plants without conducting the statutorily required
    environmental reviews. See 
    615 F.3d at 1073-74
    . The
    district court accordingly ordered vacatur of BLM’s actions
    and remanded with instructions for the agencies involved to
    perform the required analyses before ruling on the leases.
    See 
    id. at 1074
    . The plaintiffs who had challenged BLM’s
    actions appealed, disputing the scope of the district court’s
    vacatur. See 
    id. at 1072-74
    . We held that because the
    agencies could either extend or decline to extend the leases
    on remand, any decision by our court prior to the decision on
    remand could prove unnecessary and thus the district court’s
    CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT. 15
    order was not final and appealable under Alsea. See id at
    1074-77.6
    This case is indistinguishable from Pit River Tribe.
    BLM failed to conduct the relevant statutory reviews before
    granting the rights-of-way to Cadiz. The district court
    vacated the decision to grant the rights-of-way but explicitly
    noted that BLM might re-grant them on remand after
    performing the requisite analyses. If BLM reissues the
    rights-of-way on remand, Appellants will have gotten what
    they wanted. If BLM does not reissue the rights-of-way,
    Appellants will be able to challenge that decision then,
    including through an eventual appeal as needed. From
    Appellants’ perspective, eventual appellate review about the
    rights-of-way is therefore not foreclosed, so Alsea’s third
    requirement is not satisfied.7
    Appellants attempt to distinguish this case from Alsea by
    arguing that Alsea was about the validity of a regulation, not
    about rights granted to private parties. But Pit River Tribe
    concerned geothermal leases given to private parties—quite
    akin to the rights-of-way here. See 
    615 F.3d at 1073
    . And
    6
    In addition to determining that we lacked jurisdiction under 
    28 U.S.C. § 1291
     as interpreted in Alsea, Pit River Tribe also followed Alsea with
    respect to § 1292. Because the district court “did not compel the relevant
    agency to take or refrain from any action,” Pit River Tribe, 
    615 F.3d at 1078
    , but merely prohibited, as “a practical matter, the enforcement of
    the [agency’s] decision as is,” we held that “[i]t would be far too tenuous
    . . . to maintain that this is the practical equivalent of ‘enjoining’ the
    [agency],” 
    id.
     (quoting Alsea, 
    358 F.3d at 1186
    ).
    7
    Although from BLM’s perspective, future appellate review might be
    foreclosed, that makes no difference here. “[A]ppellant-intervenors ‘do
    not succeed to the agency’s right to appeal which is unique to itself.’”
    Alsea, 
    358 F.3d at 1185
     (quoting Smoke v. Norton, 
    252 F.3d 468
    , 472
    n.1 (D.C. Cir. 2001) (Henderson, J., concurring)).
    16 CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.
    our cases have in no way suggested that the type of agency
    action or whom it impacts should change our analysis under
    Alsea.
    C.
    Appellants also assert that, regardless of the availability
    of an appeal on the merits, the “capable of repetition, yet
    evading review” exception to mootness applies to the
    intervention question here.          To satisfy the second
    requirement of this exception (“evading review”), the
    controversy must be “inherently limited in duration such that
    it is likely always to become moot before federal court
    litigation is completed.” W. Coast Seafood, 
    643 F.3d at 705
    (quoting Ctr. for Biological Diversity v. Lohn, 
    511 F.3d 960
    ,
    965 (9th Cir. 2007)). As we recognized in West Coast
    Seafood, denials of intervention will not typically evade
    review because they usually do not become moot before
    appellate review is complete. See 
    id.
    Whether the controversy over a proposed intervenor’s
    right to intervene is moot “depends on the duration of the
    underlying litigation.” 
    Id.
     Where the underlying merits
    dispute about the validity of the agency’s action could
    continue for multiple years, the intervention dispute is not
    “inherently limited in duration.” 
    Id.
     (quoting Lohn, 
    511 F.3d at 965
    ). In both West Coast Seafood and here, the underlying
    case would have remained alive but for one of the party’s
    actions: There, the plaintiff voluntarily dismissed the appeal,
    see 
    id.,
     and here, BLM conceded error and requested
    remand. Such a quick resolution of the merits through a
    voluntary remand is not the norm. To the contrary, we
    frequently reverse denials of intervention while litigation is
    still pending before the district court. See, e.g., Citizens for
    Balanced Use v. Mont. Wilderness Ass’n, 
    647 F.3d 893
    , 895
    CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT. 17
    (9th Cir. 2011); California ex rel. Lockyer v. United States,
    
    450 F.3d 436
    , 445 (9th Cir. 2006). We have also exercised
    jurisdiction over appeals of denials of intervention after
    district court proceedings have ended but while participation
    in an appeal is still possible. See, e.g., Canatella v.
    California, 
    404 F.3d 1106
    , 1109 n.1 (9th Cir. 2005); Wilson,
    131 F.3d at 1301 n.1. There is no reason to think that if
    another lawsuit arose regarding similar rights-of-way and
    Appellants attempted to appeal a denial of intervention, there
    would be another immediate voluntary remand that would
    moot any intervention appeal. The “capable of repetition,
    yet evading review” exception to mootness therefore does
    not apply.
    III.
    Because the merits dispute has been remanded to the
    agency and we could not afford Appellants any path to relief
    by granting intervention, Appellants’ appeal of the denial of
    intervention is moot. We therefore DISMISS for lack of
    jurisdiction.
    FRIEDLAND, Circuit Judge, with whom BENNETT,
    Circuit Judge, joins, concurring:
    Our precedent compels us to conclude that the
    intervention dispute here is moot, but I write separately to
    express my concern about that precedent. The holding in
    Alsea Valley Alliance v. Department of Commerce, 
    358 F.3d 1181
     (9th Cir. 2004)—that orders invalidating and then
    remanding and vacating agency actions are nonfinal and not
    appealable unless three criteria are satisfied—rests on
    flawed assumptions and risks serious injustice in high-stakes
    18 CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.
    disputes. At least in the context of formal regulations and
    other agency actions resembling the Bureau of Land
    Management’s grant of the rights-of-way here, vacatur1
    operates like a final judgment or an injunction such that we
    should have jurisdiction over appeals of remands-with-
    vacatur under 
    28 U.S.C. § 1291
    , § 1292, or both. I urge my
    colleagues to reconsider en banc Alsea’s rule when the right
    opportunity arises.2
    I.
    Alsea failed to recognize that, in a case challenging an
    agency action, vacatur of that agency action effectively ends
    the parties’ dispute and allows practical costs and benefits to
    immediately accrue, causing the vacatur to operate as a final
    judgment under 
    28 U.S.C. § 1291
    .
    In Alsea, we held that “remand orders generally are not
    ‘final decisions’ for purposes of section 1291” and that this
    remained true when the remand order included vacatur of a
    regulation.    
    358 F.3d at 1184-86
     (citation omitted).
    Assuming that “vacatur of an unlawful agency rule normally
    accompanies a remand,” we declined to separately evaluate
    a vacatur’s finality. 
    Id. at 1185-86
    . We recognized only a
    narrow exception to the rule of nonfinality that resembles the
    1
    When I refer herein to district court orders using the terms “vacatur” or
    “remand-with-vacatur,” I speak only of orders that occur after the district
    court has held the agency action to be invalid. I do not mean to include
    remand and/or vacatur orders that occur without a merits determination,
    such as the one reviewed in In re Clean Water Act Rulemaking, 
    60 F.4th 583
     (9th Cir. 2023). See 
    id. at 592-93
    .
    2
    For reasons related to a parallel lawsuit brought by the Native American
    Land Conservancy challenging the grant of the rights-of-way here, I do
    not think this particular case is a good vehicle for reconsidering Alsea en
    banc.
    CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT. 19
    three-prong test for a reviewable collateral order.3 We
    concluded, in other words, that a remand order—whether
    accompanied by vacatur of the challenged agency action or
    not—is by nature nonfinal, but may on rare occasion qualify
    as the kind of collateral order treated as final for purposes of
    appeal.
    Alsea was wrong to treat vacatur of a regulation as not
    adding anything significant to a remand and to treat the two
    together as presumptively nonfinal. Under general finality
    principles, an order that “ends the litigation on the merits”
    by resolving the “core dispute,” granting one party the
    desired relief, and “leav[ing] nothing for the court to do but
    execute the judgment” is final under 
    28 U.S.C. § 1291
    . In re
    Clean Water Act Rulemaking, 
    60 F.4th 583
    , 591-93 (9th Cir.
    2023) (first and third passages quoting Coopers & Lybrand
    v. Livesay, 
    437 U.S. 463
    , 467 (1978)). This inquiry is more
    pragmatic than technical. See Cohen v. Beneficial Indus.
    Loan Corp., 
    337 U.S. 541
    , 546 (1949).
    3
    Compare Alsea, 
    358 F.3d at 1184
     (“A remand order will be considered
    ‘final where (1) the district court conclusively resolves a separable legal
    issue, (2) the remand order forces the agency to apply a potentially
    erroneous rule which may result in a wasted proceeding, and (3) review
    would, as a practical matter, be foreclosed if an immediate appeal were
    unavailable.’” (quoting Collord v. U.S. Dep’t of Interior, 
    154 F.3d 933
    ,
    935 (9th Cir. 1998))), with United States v. Pace, 
    201 F.3d 1116
    , 1119
    (9th Cir. 2000) (“Under the collateral order doctrine, a small class of
    decisions are appealable under § 1291 even though they do not terminate
    the underlying action. We have jurisdiction to hear an appeal of a district
    court’s interlocutory order if the order (1) conclusively determines the
    disputed question; (2) resolves an important issue completely separate
    from the merits of the action; and (3) is effectively unreviewable on
    appeal from a final judgment.” (quotation marks omitted)).
    20 CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.
    Of course, a remand order does not necessarily operate
    as a final judgment. In a case in which a district court
    remands but does not vacate a challenged regulation, for
    example, the remand itself merely returns jurisdiction to the
    agency where the proceedings continue. In the meantime,
    the remand does not award practical relief to those
    challenging the regulation because the regulation remains
    enforceable throughout the agency’s review process.
    Appellate review in such a case may be premature: The
    dispute is ongoing, and the status quo is unchanged.
    But when the district court also vacates an agency rule,
    that order is fundamentally a final judgment. A remand with
    vacatur terminates the parties’ “core dispute” over whether
    the challenged agency action will remain in effect. In re
    Clean Water Act Rulemaking, 60 F.4th at 593. The remand-
    with-vacatur grants relief to the plaintiff and restores the
    state of the law to the status quo before the challenged
    agency action, ushering in real-world consequences—at
    least for the time that it takes for the agency to make a new
    decision and potentially indefinitely. See id. at 591 (holding
    that an order granting remand-with-vacatur that lacked a
    merits ruling was final because it “gave Plaintiffs everything
    they wanted”).
    In Alsea, we focused only on the potential for the
    agency’s original rule to eventually be reinstated (i.e., that
    the particular type of salmon could once again be protected
    as “threatened” under the Endangered Species Act) and
    ignored the impact of the vacatur in the interim. See 
    358 F.3d at 1185-86
    . The proposed intervenors had argued that
    “immediate harm” could befall the “salmon once stripped of
    the protections” of “threatened” status. 
    Id. at 1185
    . Indeed,
    in the time it could have taken for the agency to act, the
    relevant salmon population could have been seriously
    CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT. 21
    depleted or even gone extinct.              But Alsea entirely
    disregarded this aspect of remands-with-vacatur. In my
    view, it is critical to the finality analysis that an agency may
    take years to reevaluate its rule (and may not issue a new rule
    at all), causing vacatur of the agency action to have
    consequences in the meantime at least as severe and as final
    as other “final” judgments.
    Our jurisprudence has recognized and addressed this risk
    of practical harm during the pendency of remands by
    requiring district courts to weigh the severity of the
    “agency’s errors” against the “disruptive consequences” of
    vacatur before deciding whether to order vacatur. See Cal.
    Cmtys. Against Toxics v. U.S. E.P.A., 
    688 F.3d 989
    , 992
    (9th Cir. 2012). But our judicial system also recognizes that
    judges can make mistakes, and appellate review exists to
    provide an opportunity to fix such mistakes.4 After vacatur
    of an agency rule, however, justice is often denied under
    Alsea by delaying appellate review indefinitely until the
    agency issues a new decision. I urge a more pragmatic
    approach to finality under which a remand-with-vacatur is
    considered a final order.5
    4
    Although an appeal can also take time, parties can seek a stay pending
    appeal in a situation where we would have jurisdiction over the appeal.
    See, e.g., Lair v. Bullock, 
    697 F.3d 1200
    , 1203-04 (9th Cir. 2012).
    5
    Alternatively, a remand-with-vacatur should be appealable as a
    collateral order under the traditional collateral order doctrine, without the
    modifications to that test reflected in Alsea. See supra note 3. Vacatur
    is “conclusive” in the sense that it is a formal remedy that completes the
    district court litigation and carries immediate impact, as opposed to a
    provisional stance. See Cohen, 
    337 U.S. at 546
     (explaining that a matter
    is conclusive where it fully disposes of the issue rather than leaving it
    open or unfinished). It inherently resolves an important legal issue
    22 CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.
    II.
    For similar reasons, Alsea was also wrong to hold that an
    order vacating a regulation is not the functional equivalent
    of an injunction that could be appealed under 
    28 U.S.C. § 1292
    .
    Section 1292(a)(1) accords appellate jurisdiction over
    orders “granting . . . injunctions.” 
    28 U.S.C. § 1292
    (a)(1).
    To qualify under this provision, an order “must (1) have the
    practical effect of entering an injunction, (2) have serious,
    perhaps irreparable, consequences, and (3) be such that an
    immediate appeal is the only effective way to challenge it.”
    Calderon v. U.S. Dist. Ct., 
    137 F.3d 1420
    , 1422 n.2 (9th Cir.
    1998) (citing Carson v. Am. Brands, Inc., 
    450 U.S. 79
    , 84
    (1981)). We have previously applied this test to hold, for
    example, that escrow orders have the “practical effect” of an
    injunction because they coerce a particular party and accord
    substantive relief. See United States v. Cal-Almond Inc., 
    102 F.3d 999
    , 1002-03 (9th Cir. 1996). But lis pendens orders,
    which only serve as notice of an interest in a property
    without “absolutely forbid[ding]” any action, do not.
    Orange County v. Hongkong & Shanghai Banking Corp.
    Ltd., 
    52 F.3d 821
    , 825-27 (9th Cir. 1995).
    separate from the merits—that is, the equitable determination that the
    potentially disruptive consequences of vacating the rule are outweighed
    by the seriousness of the agency’s error. See Cal. Cmtys. Against Toxics,
    
    688 F.3d at 992
    . And this equitable determination is effectively
    unreviewable if an immediate appeal is unavailable. Once the agency
    makes a new decision, any new challenge in court will not concern the
    propriety of the vacatur; that question will be moot, and the practical
    impacts will have already occurred, potentially irreparably.
    CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT. 23
    Alsea rejected the argument that an order remanding and
    vacating an agency rule has the “practical effect” of granting
    an injunction, stating:
    The order does not compel the Service to
    remove Oregon coast coho salmon from the
    threatened species list or take any other
    actions. Indeed, the only aspect of the
    summary judgment that remotely resembles
    injunctive relief is that it prohibits, as a
    practical matter, the enforcement of the
    Service’s listing decision as is. It would be
    far too tenuous, however, to maintain that this
    is the practical equivalent of “enjoining” the
    Service.
    
    358 F.3d at 1186
    . We warned that, if we took the conclusion
    that this had “the practical equivalent of ‘enjoining’ the
    Service . . . to its logical end, such reasoning would classify
    as ‘injunctive’ all declaratory relief that deems an agency
    rule unlawful.” 
    Id.
    Contrary to this reasoning, vacatur operates just like a
    preliminary injunction. Indeed, by setting aside and thus
    forbidding the enforcement of the salmon listing in Alsea,
    the district court’s vacatur did specifically compel the
    agency to remove the particular type of salmon from the
    threatened list—at least while the agency’s new decision on
    remand was pending. See 
    id. at 1185-86
    . Likewise, in this
    litigation, the vacatur of the grants of the rights-of-way
    accorded substantive relief to the plaintiffs by forcing the
    agency to prohibit Cadiz from developing the pipeline at
    least while the agency reconsiders whether to re-grant Cadiz
    24 CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.
    the rights-of-way. There is nothing “tenuous” about the
    analogy to an injunction.
    In fact, in scenarios virtually indistinguishable from
    Alsea or this litigation, district courts have sometimes
    chosen to enjoin agency enforcement of a rule—rather than
    vacate it—pending further analysis. For instance, in High
    Sierra Hikers Association v. Blackwell, 
    390 F.3d 630
    (9th Cir. 2004), the district court ordered the agency to
    complete the required National Environmental Policy Act
    (“NEPA”) analysis and enjoined enforcement of its prior
    policy until the analysis was complete. See 
    id. at 638
    , 642-
    43. The impact of the vacatur here is the same: The agency
    is forbidden from taking a certain action (i.e., granting and
    enforcing the rights-of-way) until the statutorily required
    analyses are complete.
    Given the functional equivalence of an order enjoining
    enforcement of an unlawful rule and an order vacating one,
    our current practice of reviewing the former but not the latter
    makes no sense and is inconsistent with the § 1292(a)(1)
    “practical effect” inquiry. Compare, e.g., Env’t Def. Ctr. v.
    Bureau of Ocean Energy Mgmt., 
    36 F.4th 850
    , 866-71
    (9th Cir. 2022), petition for cert. filed, No. 22-703 (Jan. 27,
    2023) (exercising jurisdiction over an appeal of the district
    court’s injunction ordering agencies to stop approving
    permits for well stimulation until the statutorily required
    environmental review was complete); Bair v. Cal. Dep’t of
    Transp., 
    982 F.3d 569
    , 576-77 (9th Cir. 2020) (exercising
    jurisdiction over an appeal of the district court’s injunction
    halting a transportation development project until the
    environmental impact statement was finalized); and High
    Sierra Hikers Ass’n, 
    390 F.3d at 638-39
     (exercising
    jurisdiction over an appeal of a district court’s order
    modifying agency activity pending the required NEPA
    CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT. 25
    analysis), with Alsea, 
    358 F.3d at 1187
     (dismissing for lack
    of jurisdiction an appeal of a district court’s remand-with-
    vacatur that prohibited the agency from enforcing the
    existing salmon listing). Although district courts have
    discretion to determine the appropriate remedy, they should
    not be able to insulate their orders from review by selecting
    between forms of relief that differ only nominally. As the
    Supreme Court has held, “[t]he ‘practical effect’ inquiry
    prevents such manipulation.” Abbott v. Perez, 
    138 S. Ct. 2305
    , 2320 (2018). It should “not allow[] district courts to
    ‘shield their orders from appellate review’ by avoiding the
    label ‘injunction.’” 
    Id.
     (quoting Sampson v. Murray, 
    415 U.S. 61
    , 87 (1974)). Yet Alsea encourages district courts to
    do just that.
    Further, concluding that remand-with-vacatur of an
    invalid agency action is practically equivalent to an
    injunction would not, as Alsea feared, result in us
    “classify[ing] as ‘injunctive’ all declaratory relief that deems
    an agency rule unlawful.” Alsea, 
    358 F.3d at 1186
    . First,
    Alsea wrongly assumed that vacatur always accompanies
    remand. See Nat’l Wildlife Fed’n v. Espy, 
    45 F.3d 1337
    ,
    1343 (9th Cir. 1995) (holding, nearly a decade before Alsea
    was decided, that “[a]lthough [a] district court has [the]
    power to do so, it is not required to set aside every unlawful
    agency action”); see also Cal. Cmtys. Against Toxics, 
    688 F.3d at 992
     (adopting the holding in Allied-Signal, Inc. v.
    U.S. Nuclear Regul. Comm’n, 
    988 F.2d 146
    , 150-51
    (D.C. Cir. 1993), that a court should evaluate the severity of
    the agency’s errors and “the disruptive consequences of an
    interim change that may itself be changed” to determine if
    vacatur is appropriate). To the contrary, a court could
    declare a rule unlawful and remand it but refuse to set it aside
    due to equitable considerations; such declaratory relief
    26 CTR. FOR BIOLOGICAL DIVERSITY V. BUREAU OF LAND MGMT.
    would then not be injunctive. Second, the other two prongs
    of the § 1292(a)(1) inquiry limit when we would classify
    vacatur as injunctive, at least for purposes of appellate
    review. The consequences would need to be “serious,
    perhaps irreparable,” and an immediate appeal would need
    to be the only way to address them. See Calderon, 
    137 F.3d at
    1422 n.2 (citation omitted). But where these two criteria
    are satisfied, a specious distinction between the effects of
    vacatur and the effects of injunctive relief should not
    preclude us from exercising jurisdiction under § 1292.
    ***
    Agency actions take many forms, and a one-size-fits-all
    approach to the finality of remands-with-vacatur may not
    necessarily be appropriate. But at least for agency actions
    similar to the one here, remand-with-vacatur operates as a
    final judgment. A remand-with-vacatur resolves the parties’
    core dispute; compels the agency to take or refrain from
    taking a certain action; and can inflict serious, sometimes
    irreparable consequences, even if agency policy is subject to
    future change. Sections 1291 and 1292 thus grant us
    appellate jurisdiction to review remands-with-vacatur.
    Alsea’s holding to the contrary should be reconsidered.
    

Document Info

Docket Number: 22-55317

Filed Date: 5/26/2023

Precedential Status: Precedential

Modified Date: 5/26/2023

Authorities (23)

Akina v. Hawaii , 835 F.3d 1003 ( 2016 )

Center for Biological Diversity v. Lohn , 511 F.3d 960 ( 2007 )

High Sierra Hikers Association v. Blackwell , 390 F.3d 630 ( 2004 )

United States v. Cal-Almond Inc. , 102 F.3d 999 ( 1996 )

Alsea Valley Alliance v. Department of Commerce , 358 F.3d 1181 ( 2004 )

California Communities Against Toxics v. United States ... , 688 F.3d 989 ( 2012 )

Pit River Tribe v. United States Forest Service , 615 F.3d 1069 ( 2010 )

Outdoor Media Group, Inc. v. City of Beaumont , 506 F.3d 895 ( 2007 )

James Collord Marjorie Collord v. United States Department ... , 154 F.3d 933 ( 1998 )

98-cal-daily-op-serv-1704-98-daily-journal-dar-2393-arthur-calderon , 137 F.3d 1420 ( 1998 )

United States v. Don H. Pace, Opinion , 201 F.3d 1116 ( 2000 )

Citizens for Balanced Use v. Montana Wilderness Ass'n , 647 F.3d 893 ( 2011 )

State of California v. United States , 450 F.3d 436 ( 2006 )

Goldammer v. United States , 465 F.3d 1031 ( 2006 )

Ransom, Alma v. Norton, Gale A. , 252 F.3d 468 ( 2001 )

Doug Lair v. Steve Bullock , 697 F.3d 1200 ( 2012 )

West Coast Seafood Processors Ass'n v. Natural Resources ... , 643 F.3d 701 ( 2011 )

Orange County, California Airport Hotel Associates, a ... , 52 F.3d 821 ( 1995 )

Abbott v. Perez , 201 L. Ed. 2d 714 ( 2018 )

Coopers & Lybrand v. Livesay , 98 S. Ct. 2454 ( 1978 )

View All Authorities »