Long Island Power Authority v. FERC ( 2022 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued May 13, 2021                   Decided March 4, 2022
    No. 20-1033
    LONG ISLAND POWER AUTHORITY AND LONG ISLAND
    LIGHTING COMPANY, D/B/A LIPA,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    AMERICAN ELECTRIC POWER SERVICE CORPORATION, ET AL.,
    INTERVENORS
    Consolidated with 20-1035, 20-1273
    On Petitions for Review of Orders
    of the Federal Energy Regulatory Commission
    Michael F. McBride argued the cause for petitioners Long
    Island Power Authority, et al. Eric J. Konopka argued the
    cause for petitioner Linden VFT, LLC. On the briefs were
    Richard P. Bress, David L. Schwartz, and Joseph B. Nelson.
    Anand R. Viswanathan, Attorney, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    2
    With him on the brief were Matthew R. Christiansen, General
    Counsel, and Robert H. Solomon, Solicitor.
    John Longstreth argued the cause for respondent-
    intervenors. With him on the brief were Gary E. Guy, Donald
    A. Kaplan, Cara J. Lewis, Richard P. Sparling, Bradley R.
    Miliauskas, Morgan E. Parke, Evan K. Dean, Pauline Foley,
    Paul M. Flynn, Miles H. Mitchell, Stacey Burbure, Robert
    Adkins, David Yost, Attorney General, Office of the Attorney
    General for the State of Ohio, Werner L. Margard, Assistant
    Attorney General, Steven D. Hughey and Spencer A. Sattler,
    Assistant Attorneys General, Office of the Attorney General
    for the State of Michigan, Daniel E. Frank, Allison E. Speaker,
    Kriss E. Brown, Aspassia V. Staevska, Christian A. McDewell,
    Gurbir S. Grewal, Attorney General, Office of the Attorney
    General for the State of New Jersey, Paul Youchak, Deputy
    Attorney General, Christopher R. Jones, Molly Suda, and
    Christopher J. Barr. William M. Keyser III, Steven M. Nadel,
    and Alex Moreau, Deputy Attorney General, Office of the
    Attorney General for the State of New Jersey, entered
    appearances.
    Before: HENDERSON, KATSAS, and WALKER, Circuit
    Judges.
    Opinion of the Court filed by Circuit Judge KATSAS.
    KATSAS, Circuit Judge: This case arises from a long-
    running dispute over how to allocate the costs of high-voltage
    facilities to transmit electricity within the mid-Atlantic
    planning region. The question is difficult because high-voltage
    projects afford two different kinds of benefits—local benefits
    that accrue primarily to utilities close to the project at issue,
    and regional benefits that accrue throughout the grid. The
    Seventh Circuit has twice set aside cost allocations that ignored
    3
    the local benefits, Illinois Commerce Comm’n v. FERC, 
    576 F.3d 470
     (7th Cir. 2009) (Illinois Commerce I); Illinois
    Commerce Comm’n v. FERC, 
    756 F.3d 556
     (7th Cir. 2014)
    (Illinois Commerce II), and we have set aside cost allocations
    that ignored the regional benefits, Old Dominion Elec. Coop.
    v. FERC, 
    898 F.3d 1254
     (D.C. Cir. 2018).
    This case involves a contested settlement covering high-
    voltage projects approved between 2007 and 2013. The
    settlement allocates their costs through hybrid formulas that
    account for both local and regional benefits. In that respect, it
    tracks the allocation formula for high-voltage projects
    approved after 2013, which is not challenged here.
    The Federal Energy Regulatory Commission approved the
    settlement over the objection of two utilities that transmit
    electricity from the mid-Atlantic region to New York. These
    utilities argue that the approval was inconsistent with the
    Seventh Circuit’s decisions, with FERC’s own precedent, and
    with an underlying cost-causation principle. One of the utilities
    also argues that FERC erroneously assigned it costs based on a
    flawed interpretation of the settlement. We agree with the
    second contention but not the first.
    I
    A
    The Federal Power Act requires utilities to charge “just
    and reasonable” rates for the transmission of electricity in
    interstate commerce. 16 U.S.C. § 824d(a). To be just and
    reasonable, rates must “reflect to some degree the costs actually
    caused by the customer who must pay for them.” Midwest ISO
    Transmission Owners v. FERC, 
    373 F.3d 1361
    , 1368 (D.C. Cir.
    2004) (cleaned up). This “cost causation principle” requires
    “comparing the costs assessed against a party to the burdens
    4
    imposed or benefits drawn by that party.” 
    Id.
     If FERC
    determines that a particular rate is unjust or unreasonable, it
    must “determine the just and reasonable rate.” 16 U.S.C.
    § 824e(a).
    B
    PJM Interconnection, LLC is the regional transmission
    organization (RTO) for an area encompassing much of the mid-
    Atlantic and part of the Midwest. PJM takes its name from
    Pennsylvania, New Jersey, and Maryland, the first three states
    in which it operated, but its territory now extends as far west as
    Illinois. As an RTO, PJM coordinates the movement of
    electricity across the region. It operates transmission facilities
    owned by member utilities, approves the construction of new
    facilities, and files tariffs allocating among its members the
    costs of the facilities.
    This case involves high-voltage transmission facilities
    within the PJM region. For over a decade, member utilities
    disputed how to allocate the cost of these projects, which
    provide both local and regional benefits. The facilities most
    obviously benefit nearby utilities that use them directly, but
    they also provide “backbone infrastructure” that improves
    reliability and reduces congestion regionwide.                PJM
    Interconnection, L.L.C., 
    119 FERC ¶ 61,063
    , P 80 (2007)
    (Opinion No. 494). A geographic asymmetry exacerbated the
    dispute: Given the location of generators, electricity must flow
    longer distances to reach consumers in the eastern part of PJM
    than to reach their western counterparts. And because high-
    voltage facilities work best to transmit electricity over long
    distances, they are more useful in the eastern part. See Ill. Com.
    II, 756 F.3d at 558; Ill. Com. I, 
    576 F.3d at 475
    .
    Initially, PJM allocated the cost of its high-voltage
    facilities based on what FERC calls the violation method (or,
    5
    less concisely, the violation-based distribution-factor method).
    This method assumes that new projects are approved in
    response to violations of reliability standards at overburdened
    facilities. And it allocates costs based on use of those facilities
    at the time of each violation. The violation method thus deems
    utilities using overburdened facilities to have “cause[d]” the
    relevant problem and to “benefit from” upgrades that eliminate
    it. See Opinion No. 494, 
    119 FERC ¶ 61,063
    , P 2 n.3.
    In 2007, FERC ordered PJM to replace its violation
    method with a “postage stamp” method. This method allocates
    the cost of a new facility in proportion to each utility’s sale of
    electricity, regardless of where the facility is located or how
    much each utility uses it. The Commission reasoned that the
    postage-stamp method accounts for the regional benefits of
    high-voltage facilities, incentivizes their development, and
    avoids the trouble of quantifying the specific benefits that each
    facility provides to each utility. Opinion No. 494, 
    119 FERC ¶ 61,063
    , PP 79–82.
    In Illinois Commerce I, the Seventh Circuit set aside
    FERC’s order. It reasoned that FERC had failed to make “even
    the roughest of ballpark estimates” of the regional benefits said
    to justify the postage-stamp method and had also failed to
    explain why quantifying the local benefits—as it continued to
    do for low-voltage projects—was now too difficult. 
    576 F.3d at
    475–78. Moreover, PJM’s geographic asymmetry made the
    distinction between local and regional benefits important:
    Because nearly all the high-voltage facilities were built in the
    eastern part of the grid, fully regionalizing their costs would
    substantially overcharge the western utilities. 
    Id.
     at 475–76.
    On remand, FERC again ordered the postage-stamp
    method. PJM Interconnection L.L.C., 
    138 FERC ¶ 61,230
    (2012) (Remand Order). It concluded that the violation method
    6
    was unjust and unreasonable because it ignores both regional
    benefits and the changing use of individual facilities over time.
    
    Id.
     PP 38–41. The Commission then concluded that the
    postage-stamp method was just and reasonable because it
    accounts for the significant, though difficult to quantify,
    “system-wide benefits” to the PJM grid. 
    Id.
     P 49. On the
    record before it, FERC considered only the violation and
    postage-stamp methods, but it encouraged PJM stakeholders to
    develop “hybrid” or other allocation methods. 
    Id.
     P 2.
    The Seventh Circuit set aside the Remand Order in Illinois
    Commerce II. The court again faulted FERC for giving neither
    a cost-benefit analysis nor an explanation of why such an
    analysis was infeasible. 756 F.3d at 561. And it again
    concluded that the postage-stamp method was “guaranteed to
    overcharge the western utilities, as they will benefit much less
    than the eastern utilities from eastern projects that are designed
    to improve the electricity supply in the east.” Id.
    C
    While the Illinois Commerce litigation was ongoing,
    FERC promulgated a regulation known as Order No. 1000,
    which restructured arrangements for the coordinated
    transmission of electricity. Transmission Planning and Cost
    Allocation by Transmission Owning and Operating Public
    Utilities, 
    136 FERC ¶ 61,051
     (2011). Among other things,
    Order No. 1000 requires RTOs and their member utilities to
    establish tariff formulas allocating the costs of new
    transmission facilities in advance. 
    Id.
     P 558.
    In response, PJM and its utilities proposed a hybrid
    formula for new high-voltage facilities: allocate half the costs
    under the postage-stamp method and half under a new, flow-
    based method (also called a solution-based distribution-factor
    method). The flow-based method assigns costs based on how
    7
    much each utility uses the facility in question over time.
    Approving the hybrid formula, FERC concluded that it struck
    a “reasonable balance” between the “broad regional benefits
    and specifically identifiable benefits” of high-voltage facilities.
    PJM Interconnection, L.L.C., 
    142 FERC ¶ 61,214
    , P 417
    (2013) (Compliance Order). FERC also noted that the proposal
    reflected a “reasonable compromise” to resolve the “intensely
    practical difficulties” that had provoked extended discord
    within PJM. 
    Id.
     P 420 (cleaned up). All the member utilities
    supported the compromise, and no party challenged it in court.
    The new formula applied only to high-voltage projects that
    PJM approved on or after February 1, 2013. See 
    id.
     PP 1, 381,
    433. The Compliance Order thus narrowed the Illinois
    Commerce litigation to projects approved between FERC’s
    2007 postage-stamp order and January 31, 2013. The parties
    dub these 32 projects the “Vintage Projects.” Twenty-nine of
    them remain in service, and three have been cancelled. Their
    total cost was about $2.7 billion.
    D
    Following the Compliance Order and Illinois Commerce
    II, FERC encouraged interested parties to reach a settlement on
    how to allocate the costs of the Vintage Projects. PJM
    Interconnection, L.L.C., 
    149 FERC ¶ 61,233
    , P 10 (2014). In
    2016, several parties proposed a settlement that uses three
    formulas to assign the costs. Each of them, like the formula
    approved for post-2013 projects, has a hybrid structure
    including a postage-stamp component and a usage-based
    component. Which formula applies depends on when the costs
    were incurred and whether PJM had cancelled the project.
    First, for Vintage Project costs incurred in 2016 or later,
    the settlement uses the same formula that FERC had approved
    for new transmission projects—i.e., allocate half the costs
    8
    through the postage-stamp method and half through the flow-
    based method. For convenience, we refer to this approach as
    the “going-forward formula.”
    Second, the settlement makes a series of adjustments for
    Vintage Project costs incurred before 2016, which PJM
    previously had allocated under the postage-stamp method. The
    adjustments seek to bring the allocations in line with “what
    would have been credited or paid” had PJM adopted the going-
    forward formula from the start. J.A. 181. We refer to these
    adjustments as the “historical formula.”
    Third, for the cancelled projects, the settlement allocates
    half the costs through the postage-stamp method and half
    through the violation method. We refer to this approach as the
    “cancelled-projects formula.”
    This proposal received wide support from PJM
    stakeholders. All the Illinois Commerce petitioners joined it,
    as did many other transmission owners and state regulatory
    agencies. Together, the supporting or unopposed stakeholders
    account for virtually all the energy consumption within PJM.
    The petitioners here opposed the settlement. Linden VFT,
    LLC owns a merchant transmission facility that transmits
    power from PJM to New York. The Long Island Power
    Authority and its affiliate the Long Island Lighting Company
    (collectively, LIPA) hold long-term transmission rights over a
    similar facility. Under the settlement’s hybrid allocations,
    these parties would pay about $30 million more for the Vintage
    Projects than they would pay under a pure postage-stamp
    method. Linden and LIPA argued that the settlement was
    inconsistent with Illinois Commerce, with FERC’s Remand
    and Compliance Orders, and with the cost-causation principle.
    9
    FERC approved the settlement over these objections. PJM
    Interconnection, L.L.C., 
    163 FERC ¶ 61,168
     (2018)
    (Settlement Order). Incorporating the reasoning from its
    Compliance Order, FERC concluded that the going-forward
    formula allocates costs consistent with the regional and local
    benefits that each transmission owner receives from each
    individual facility. 
    Id.
     P 39. FERC approved the historical
    formula because it roughly recreates the cost allocations that
    would have occurred had PJM used the going-forward formula
    from the start of each project. 
    Id.
     P 40. And the Commission
    concluded that the cancelled-projects formula appropriately
    substitutes the violation method for the flow-based method
    because no ongoing usage data existed for cancelled projects.
    
    Id.
     P 45. Finally, FERC concluded that the settlement does not
    make the petitioners worse off relative to the expected outcome
    of further litigation, which would not likely have replaced the
    hybrid allocations with a pure postage-stamp method. 
    Id.
     PP
    41–43.
    LIPA and Linden moved for rehearing of the Settlement
    Order. Linden also asked FERC to clarify that it was not liable
    to pay adjustments under the historical formula. The
    Commission denied both motions. PJM Interconnection,
    L.L.C., 
    169 FERC ¶ 61,238
     (2019) (Rehearing Order).
    LIPA and Linden petitioned for judicial review. Several
    transmission owners and state regulatory commissions, as well
    as PJM, have intervened in support of FERC. We have
    jurisdiction to review the petitions under 16 U.S.C. § 825l(b).
    II
    The Administrative Procedure Act requires us to set aside
    FERC orders that are “arbitrary, capricious, an abuse of
    discretion, or otherwise not in accordance with law.” 
    5 U.S.C. § 706
    (2)(A). A decision is not arbitrary if the agency has
    10
    “examined the relevant considerations and articulated a
    satisfactory explanation for its action, including a rational
    connection between the facts found and the choice made.” Old
    Dominion, 898 F.3d at 1260 (cleaned up). Because ratemaking
    is imprecise and APA review is deferential, we do not require
    the Commission to allocate costs with “exacting precision.” Id.
    (cleaned up). But we do set aside cost allocations that are either
    unreasonable or inadequately explained. See id.
    Illinois Commerce and Old Dominion illustrate these
    principles in the context of high-voltage transmission projects.
    As explained above, the Seventh Circuit twice has set aside a
    pure postage-stamp allocation, on the ground that it
    unreasonably ignores the significant local benefits accruing to
    eastern PJM utilities but not to western ones. In Old Dominion,
    we confronted a PJM tariff amendment that would have
    required a pure flow-based allocation for certain high-voltage
    projects. 898 F.3d at 1257–59. We set it aside as unreasonably
    ignoring the significant regional benefits accruing throughout
    the PJM grid. Id. at 1261–63. Both courts described the
    contested cost allocations as “grossly disproportionate” to the
    benefits received by individual utilities. Id. at 1261 (quoting
    Ill. Com. II, 756 F.3d at 565).
    LIPA and Linden contend that the Settlement Order and
    its hybrid allocations are likewise arbitrary. We disagree.
    A
    FERC may approve a contested settlement “if the record
    contains substantial evidence upon which to base a reasoned
    decision or the Commission determines there is no genuine
    issue of material fact.” 
    18 C.F.R. § 385.602
    (h)(1)(i). FERC
    reads this language to allow approval when the “overall result
    of the settlement is just and reasonable,” even if “individual
    aspects” of it “may be problematic.” Trailblazer Pipeline Co.,
    11
    
    85 FERC ¶ 61,345
    , 62,342 (1998). In that circumstance, FERC
    must further conclude that the challenger “would be in no
    worse position” under the settlement “than if the case were
    litigated.” Trailblazer Pipeline Co., 
    87 FERC ¶ 61,110
    , 61,439
    (1999). FERC found each of the three hybrid cost allocations
    here to be just and reasonable, but it also invoked the
    Trailblazer framework and found that LIPA and Linden would
    not have been better off litigating the merits. We uphold all
    these findings, which is more than enough to justify the overall
    settlement. 1
    FERC adequately justified its approval of each formula.
    Start with the going-forward formula, which allocates costs
    through a mix of the postage-stamp and flow-based methods.
    FERC approved the formula based on reasoning in its 2013
    Compliance Order, which had approved the same formula for
    future high-voltage transmission projects. Settlement Order,
    
    163 FERC ¶ 61,168
    , P 39; Rehearing Order, 
    169 FERC ¶ 61,238
    , PP 41–45. Doing so was not arbitrary. As FERC had
    earlier explained, the postage-stamp component takes account
    of “the full spectrum of benefits associated with high-voltage
    facilities, including difficult to quantify regional benefits” such
    as improved reliability, reduced congestion, and greater
    carrying capacity. Compliance Order, 
    142 FERC ¶ 61,214
    ,
    P 414. We too have recognized that high-voltage transmission
    systems provide “significant regional benefits” to the PJM
    network. Old Dominion, 898 F.3d at 1260. As for the flow-
    based component, FERC reasonably looked to usage data as a
    proxy for specific benefits—in other words, it looked to this
    data “to identify the subset of customers that benefit from a
    1
    We thus need not consider whether FERC may approve a
    settlement without addressing the merits of each contested rate, even
    though the Federal Power Act requires “[a]ll rates and charges made”
    to be just and reasonable, 16 U.S.C. § 824d(a).
    12
    facility simply through electrical proximity.” Compliance
    Order, 
    142 FERC ¶ 61,214
    , P 417. And FERC’s decision to
    approve a hybrid formula incorporating both measures was
    undoubtedly reasonable given the various benefits of high-
    voltage facilities. Indeed, it is compelled by precedents finding
    it arbitrary either to ignore local benefits by using a pure
    postage-stamp method (Illinois Commerce) or to ignore
    regional benefits by using a pure flow method (Old Dominion).
    As for the selection of a 50:50 ratio for the hybrid formula, the
    materials we have cited make clear that regional and local
    benefits are both substantial, thus requiring a significant weight
    for each component of the formula. And any debate over the
    choice between a 50:50 ratio and, say, a ratio of 60:40 one way
    or the other would “amount to a quibble about exacting
    precision,” rather than “a wholesale departure from the cost-
    causation principle.” Old Dominion, 898 F.3d at 1261 (cleaned
    up).
    The historical formula follows neatly from the going-
    forward formula. As FERC explained, the historical formula
    requires adjustments to approximate the cost allocations that
    would have occurred had PJM applied the going-forward
    formula from the start of each Vintage Project. Settlement
    Order, 
    163 FERC ¶ 61,168
    , P 40; Rehearing Order, 
    169 FERC ¶ 61,238
    , P 48. LIPA and Linden do not challenge this finding.
    And because the going-forward formula reasonably matches
    costs to benefits, so does the historical formula.
    Finally, FERC reasonably approved the cancelled-projects
    formula. For these projects, there was no ongoing usage data
    to support application of the flow-based method. Unable to
    measure changing usage over time, the parties substituted the
    violation method to measure which utilities caused the
    reliability violations that necessitated the projects. Settlement
    Order, 
    163 FERC ¶ 61,168
    , P 45; Rehearing Order, 
    169 FERC 13
    ¶ 61,238, P 52. Under the circumstances, that was a reasonable
    way to assess usage issues, for the cost-causation principle
    compares costs to “the burdens imposed or the benefits drawn”
    by individual utilities. Midwest ISO Transmission Owners,
    
    373 F.3d at 1368
    . And as explained above, the 50:50 weighing
    of local burdens and benefits (as measured by the violation
    method) and regional benefits (as measured by the postage-
    stamp method) was also reasonable.
    Our determination that each formula in the settlement is
    just and reasonable is reason enough to uphold it, but we also
    note that FERC reasonably concluded LIPA and Linden would
    not have done better through litigation. The challengers do
    their best to obscure this point, but what they seek is application
    of a pure postage-stamp method—or at least a hybrid formula
    with a more heavily weighted postage-stamp component. The
    Seventh Circuit has twice set aside a pure postage-stamp
    formula for the Vintage Projects. We have little doubt that, if
    faced once again with a pure or almost pure postage-stamp
    formula, it would call strike three.
    B
    LIPA and Linden make several attacks on FERC’s
    reasoning, but none is persuasive.
    First, LIPA and Linden contend that the settlement
    violates Illinois Commerce II, which they say requires a cost-
    benefit analysis to quantify project benefits. It does not. The
    Seventh Circuit discussed cost-benefit analysis at length, but
    its holding was narrower. The court set aside the postage-
    stamp method because, in treating all benefits as regional, it
    was “guaranteed to overcharge the western utilities” and to
    produce a “grossly disproportionate” cost allocation. 756 F.3d
    at 561, 564–65. As we later explained, the Illinois Commerce
    decisions hold that a postage-stamp regime goes “too far” in
    14
    weighing regional benefits over local ones, but “nothing in
    those decisions casts doubt on” FERC’s view that high-voltage
    projects have substantial regionwide benefits. Old Dominion,
    898 F.3d at 1261. And given that view, FERC had at least “an
    articulable and plausible reason to believe” that a hybrid, 50:50
    formula would make project costs “at least roughly
    commensurate with” project benefits—which is good enough
    under Illinois Commerce II. See 756 F.3d at 562 (cleaned up).
    Second, LIPA and Linden contend that FERC could not
    approve the going-forward formula simply because it matches
    the one used for new high-voltage projects. Instead, they
    contend, the Commission had to separately consider the
    formula as applied to each Vintage Project. But while FERC
    may create different rules for different kinds of projects, see
    Pub. Serv. Elec. & Gas Co. v. FERC, 
    989 F.3d 10
    , 18 (D.C.
    Cir. 2021), “a regulator need not always carve out exceptions
    for arguably distinct subcategories of projects,” Old Dominion,
    898 F.3d at 1262. Nor must a regulator always consider cost-
    allocation rules on a project-by-project basis, which would
    unravel the framework of ex ante tariffs established by Order
    No. 1000 and approved by this Court. S.C. Pub. Serv. Auth. v.
    FERC, 
    762 F.3d 41
    , 82–83 (D.C. Cir. 2014). Instead, FERC
    must ensure only that there is “some resemblance” between
    costs and benefits. Pub. Serv. Elec. & Gas Co., 989 F.3d at 13–
    14. And without evidence that the Vintage Projects are
    different from other high-voltage transmission facilities within
    PJM, the Commission could reasonably extend to the Vintage
    Projects the previously approved, unchallenged formula that
    now generally governs newer projects. 2
    2
    Linden has filed a separate challenge to that formula as
    applied to two of the newer projects. Consol. Edison Co. v. FERC,
    No. 15-1183 (D.C. Cir. filed June 25, 2015). We express no view on
    the merits of that case.
    15
    Third, LIPA and Linden contend that the Settlement Order
    failed to explain what they characterize as a departure from the
    decision to make the Compliance Order purely prospective.
    The Compliance Order applied to projects approved after
    January 2013, and it stated that “administrative complications
    created by implementing the hybrid method should be limited,
    since this method will apply on a prospective basis only.” 
    142 FERC ¶ 61,214
    , P 433. But the order did not disfavor any
    further applications of the same formula. Instead, it stressed
    that the Order No. 1000 compliance process remained ongoing,
    and the governing formulas remained subject to change. 
    Id.
     PP
    431–32. So there was no inconsistency when FERC, after five
    years of experience with the hybrid formula, allowed the
    parties to extend it to the Vintage Projects. See Settlement
    Order, 
    163 FERC ¶ 61,168
    , P 39. Nor was there any lack of
    explanation on this point. As FERC later noted, the
    Compliance Order’s “prospective application” did “not
    preclude the parties and the Commission from using a just and
    reasonable cost method in a settlement to resolve a remanded
    proceeding.” Rehearing Order, 
    169 FERC ¶ 61,238
    , P 46.
    Fourth, LIPA and Linden contend that the Settlement
    Order impermissibly departed from the 2012 Remand Order,
    which rejected the violation method “as the sole basis for
    allocating costs” of high-voltage projects. 
    138 FERC ¶ 61,230
    ,
    P 37. That decision reasoned that the violation method does
    not account for either (1) the specific benefits that utilities
    receive from using the facilities over time or (2) the facilities’
    regionwide benefits. 
    Id.
     PP 37–47. In approving the
    settlement, FERC reasonably addressed both points. As it
    explained, accounting for ongoing usage over time is
    impossible for cancelled projects, and the postage-stamp
    component of the hybrid formula adequately accounts for
    regionwide benefits. Settlement Order, 
    163 FERC ¶ 61,168
    , P
    45; Rehearing Order, 
    169 FERC ¶ 61,238
    , P 54.
    16
    Finally, LIPA and Linden contend that FERC prevented
    them from contesting the settlement in a live hearing. But
    FERC has discretion to resolve disputed issues on a written
    record. Minisink Residents for Envt’l Pres. & Safety v. FERC,
    
    762 F.3d 97
    , 114 (D.C. Cir. 2014). Here, the Commission
    relied on the extensive written records compiled in this
    proceeding and in the Order No. 1000 compliance proceeding.
    Moreover, LIPA and Linden had ample opportunity to object
    through written submissions, which they did in nearly 20
    filings including five expert affidavits. FERC did not abuse its
    discretion in approving the settlement on a written record.
    III
    Linden further contends that, under the settlement, it need
    not make any of the payments set forth in the historical
    formula. We agree.
    The historical formula imposes monthly Transmission
    Enhancement Charge adjustments (TEC adjustments)
    beginning in January 2016 and continuing through December
    2025. The “[e]ffective [d]ate” of these TEC adjustments is
    January 1, 2016. J.A. 100. For merchant transmission
    facilities, the TEC adjustments are based on “Firm
    Transmission Withdrawal Rights,” which are guaranteed rights
    to transmit electricity. PJM Tariff, sched. 12(b)(x)(B)(2).
    Linden surrendered its withdrawal rights on January 1, 2018,
    almost five months before FERC approved the settlement. The
    parties agree that Linden thus need not pay TEC adjustments
    for 2018 to 2025. They disagree over whether Linden must pay
    TEC adjustments for 2016 and 2017.
    Section 4(c) of schedule 12-C of the PJM tariff imposes
    the TEC adjustments. Section 4(c)(i)(2) provides the following
    “adjustment” to the adjustments:
    17
    If all Responsible Customers in a Zone or Merchant
    Transmission Facility are no longer subject to
    Transmission Enhancement Charges under the PJM
    Tariff during the period in which Transmission
    Enhancement Charge Adjustments are collected, then,
    during the portion of that period that such Responsible
    Customers are not subject to Transmission
    Enhancement Charges, the payments from or credits
    to such Responsible Customers shall cease .…
    J.A. 101–02. Linden is the only responsible customer in its
    merchant facility. According to Linden, the “period in which
    [TEC] Adjustments are collected” began when FERC approved
    the settlement, because PJM did not and could not collect any
    payments before then. Therefore, Linden reasons, it was “no
    longer subject to” TEC adjustments during any of that period,
    and so its “payments … shall cease.” FERC responds that TEC
    adjustments began to accrue—and thus were “collected”—as
    soon as the settlement became effective in January 2016. In
    resolving this dispute over tariff interpretation, we must
    enforce unambiguous tariff language, but defer to FERC’s
    reasonable interpretation of ambiguous text. Colo. Interstate
    Gas Co. v. FERC, 
    599 F.3d 698
    , 701 (D.C. Cir. 2010).
    The plain meaning of “collected” unambiguously supports
    Linden.      Section 4(c)(i)(2) concerns the collection of
    “adjustments”—i.e., financial liabilities for which payment can
    be obtained. In that context, “collect” means “[t]o call for and
    obtain payment of.” Collect, American Heritage Dictionary
    (5th ed. 2018); accord Collect, Oxford English Dictionary (2d
    ed. 1989) (“[t]o gather (contributions of money, or money due,
    as taxes, etc.) from a number of people”). FERC has not
    identified a single example, in a dictionary or otherwise, where
    “collect” means to accrue liability. Nor have we found any.
    18
    This strongly suggests that “collect” simply cannot bear that
    meaning. See DHS v. MacLean, 
    574 U.S. 383
    , 394 (2015).
    Context confirms that “collect” here means collect. As
    FERC notes, schedule 12-C imposes liability for TEC
    adjustments beginning on its “[e]ffective [d]ate” of January 1,
    2016. PJM Tariff, sched. 12-C §§ 2–3. But schedule 12-C also
    plainly distinguishes the concepts of accrual and collection.
    For although it imposes liability beginning on the effective
    date, it permits collection only after an “implementation date”
    defined as “the date of a FERC order … authorizing PJM to
    begin collecting” TEC adjustments. Id. § 3 (emphasis added).
    Schedule 12-C’s procedures underscore this distinction.
    During the interim period between the effective and
    implementation dates, PJM had to “track and accumulate the
    differences between” what it was collecting under the existing
    rate and what the settlement would require if FERC approved
    it. PJM Tariff, sched. 12-C § 3. After the implementation date,
    PJM would issue “credits or charges” that equaled “the
    aggregate of such differences.” Id. Schedule 12-C thus
    recognizes that utilities began accruing liability as of the
    settlement’s effective date, but that PJM would not “begin
    collecting” until FERC approved the settlement.
    FERC contends that the settlement agreement, which
    states that “PJM shall collect” adjustments “[e]ffective as of
    January 1, 2016,” J.A. 86–88, shows that collection began as
    of then. But this language was not incorporated into PJM’s
    tariff, and it is flatly inconsistent with the tariff provisions
    expressly linking collection to the implementation date rather
    than the effective date. Because the tariff is unambiguous on
    this point, it is controlling. See Colo. Interstate, 
    599 F.3d at 701
    .
    19
    IV
    Linden asks us to vacate FERC’s order holding it liable for
    TEC adjustments. Vacatur is the normal remedy under the
    APA, which provides that a reviewing court “shall … set aside”
    unlawful agency action. 
    5 U.S.C. § 706
    (2). Nonetheless, we
    have held that remand without vacatur is sometimes
    appropriate, depending on the seriousness of the agency error
    and the disruptive consequences of vacatur. See Allied-Signal,
    Inc. v. NRC, 
    988 F.2d 146
    , 150–51 (D.C. Cir. 1993).
    For the legal error identified above, vacatur is clearly
    warranted. The “seriousness” of agency error turns in large
    part on “how likely it is the agency will be able to justify its
    decision on remand.” Heartland Reg’l Med. Ctr. v. Sebelius,
    
    566 F.3d 193
    , 197 (D.C. Cir. 2009) (cleaned up). And
    disruptive consequences matter “only insofar as the agency
    may be able to rehabilitate its rationale.” Comcast Corp. v.
    FCC, 
    579 F.3d 1
    , 9 (D.C. Cir. 2009). Here, because the
    controlling tariff provision is unambiguous, FERC cannot
    rehabilitate its preferred interpretation on remand.
    The intervenors contend that a remand without vacatur
    would have been warranted had we set aside the entire
    settlement on the ground that FERC’s approval was
    inadequately reasoned. Having upheld the settlement, we need
    not consider that argument. We note only that the concerns
    raised by the intervenors, positing a highly disruptive judicial
    intervention based on a likely curable agency error, have no
    application to the narrow legal error that we have identified.
    V
    For these reasons, we set aside FERC’s ruling that Linden
    must pay TEC adjustments, and we remand for any further
    20
    proceedings that may be necessary to implement this ruling. In
    all other respects, we deny the petitions for review.
    So ordered.