NorthWestern Corporation v. FERC ( 2018 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued December 1, 2017               Decided March 16, 2018
    No. 16-1176
    NORTHWESTERN CORPORATION,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    MONTANA CONSUMER COUNSEL, ET AL.,
    INTERVENORS
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    John Lee Shepherd, Jr. argued the cause for petitioner.
    With him on the briefs were Clifford M. Naeve, James P.
    Danly, Heather H. Grahame, M. Andrew McLain, and Timothy
    T. Mastrogiacomo.
    Holly E. Cafer, Senior Attorney, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With her on the brief were David L. Morenoff, General
    Counsel, and Robert H. Solomon, Solicitor.
    Christina F. Gomez argued the cause for intervenors. With
    her on the brief were Kathleen L. Mazure, Thorvald A. Nelson,
    2
    and Michelle Brandt King. John P. Coyle, Natalie M. Karas,
    and Justin W. Kraske entered appearances.
    Before: KAVANAUGH and WILKINS, Circuit Judges, and
    RANDOLPH, Senior Circuit Judge.
    Opinion for the Court filed by Circuit Judge KAVANAUGH.
    KAVANAUGH, Circuit Judge:           The Federal Energy
    Regulatory Commission requires utilities that transmit
    electricity to supply extra power generation in order to balance
    moment-to-moment variations in demand for electricity.
    Utilities must add power to, or withdraw power from, the grid
    in real time as actual demand for electricity exceeds or falls
    short of projected demand. That extra power generation is
    known as regulation service.
    FERC allows utilities to recover costs associated with the
    provision of regulation service. Utilities may recover those
    costs by charging them to customers, as long as the utilities
    charge rates that are “just and reasonable.” 16 U.S.C.
    § 824d(a).
    NorthWestern is an electric utility that is subject to
    FERC’s regulation-service requirement.           Before 2011,
    NorthWestern lacked the generating capacity to provide its
    own regulation service, so it met the requirement by purchasing
    regulation service from other utilities. With FERC’s approval,
    NorthWestern then passed on the cost of that purchased
    regulation service to its wholesale and retail customers. But
    purchasing regulation service from other utilities eventually
    became too expensive, so NorthWestern built a new generating
    station dedicated to providing regulation service.
    NorthWestern then proposed to revise the rate that it charges
    3
    customers for regulation service in order to recover the costs of
    providing that service from the new station.
    FERC determined that NorthWestern’s proposed rate was
    not just and reasonable.          FERC therefore modified
    NorthWestern’s proposed rate and ordered NorthWestern to
    refund its customers the difference between the proposed rate
    and the modified rate. NorthWestern challenges FERC’s
    decision as arbitrary and capricious under the Administrative
    Procedure Act. The arbitrary and capricious standard requires
    that an agency’s decision be reasonable and reasonably
    explained. We conclude that FERC’s decision in this case was
    reasonable and reasonably explained, and we therefore deny
    the petition for review.
    I
    In 1996, FERC issued Order 888. 
    61 Fed. Reg. 21,540
    (May 10, 1996). Among other things, Order 888 requires
    electric utilities to provide their customers with certain
    ancillary services – services that supplement the basic service
    of transmitting electricity. 
    Id. at 21,579-80
    . One such ancillary
    service is “regulation service.” Regulation service is extra
    power generation that responds to “moment-to-moment
    variations” in demand for electricity in a given area. 
    Id. at 21,582
    . In other words, regulation service is “the injection or
    withdrawal of real power” into or from the electric grid in
    response to fluctuations in demand for electricity. Order No.
    755, 
    76 Fed. Reg. 67,260
    , 67,260-61 (Oct. 31, 2011).
    Regulation service helps to prevent blackouts and equipment
    damage by keeping the frequency of the electric current at close
    to 60 Hertz, the standard frequency in the United States. 
    Id.
     If
    a utility fails to maintain that frequency, FERC may impose
    civil penalties on the utility. See 16 U.S.C. § 825o-1.
    4
    A utility charges customers for regulation service under
    Schedule 3 of the utility’s Open Access Transmission Tariff,
    which is filed with FERC. FERC must examine the rate that a
    utility proposes to charge Schedule 3 customers in order to
    ensure that the rate is “just and reasonable.” 16 U.S.C.
    § 824d(a), (e). A just and reasonable rate must be fair both to
    the utility and to its customers: It “should be based on the costs
    of providing service to the utility’s customers, plus a just and
    fair return on equity.” Alabama Electric Cooperative, Inc. v.
    FERC, 
    684 F.2d 20
    , 27 (D.C. Cir. 1982); see also FPC v. Hope
    Natural Gas Co., 
    320 U.S. 591
    , 603 (1944).
    This case concerns an attempt by petitioner NorthWestern
    to revise its Schedule 3 rate. NorthWestern is an electric utility
    subject to FERC’s regulation-service requirement. As relevant
    here, NorthWestern transmits electricity to wholesale and retail
    customers in Montana. 1 When NorthWestern first began
    operations in 2002, NorthWestern did not possess sufficient
    generating capacity to provide its own regulation service. So
    NorthWestern complied with Order 888 by purchasing
    regulation service from other utilities.          NorthWestern
    contracted with those other utilities for a set amount of
    regulation service and passed the cost of that regulation service
    on to customers under Schedule 3. From 2002 to 2010,
    NorthWestern purchased, and passed on the cost of, 60
    1
    The record is not clear about the precise makeup of
    NorthWestern’s customer base.               According to FERC,
    NorthWestern’s customers – presumably its wholesale customers –
    include generators and “load-serving entities.” Respondent’s Brief
    at 1. Load-serving entities are utilities that supply electricity to
    homes and businesses. NorthWestern’s retail customers appear to
    include industrial energy customers such as refining companies, see
    Intervenors’ Brief at ii, 1, but may also include commercial and
    residential customers. Regardless, the exact makeup of each
    customer class does not affect the resolution of this case.
    5
    megawatts of regulation service each year to its Schedule 3
    customers.
    But NorthWestern eventually decided that purchasing
    regulation service from other utilities was inefficient. So
    NorthWestern built the Dave Gates Generating Station, a
    station dedicated to providing regulation service to
    NorthWestern’s customers. The Gates Station has three
    generators, each with a maximum capacity of 50 megawatts,
    for a total nominal or “nameplate” capacity of 150 megawatts.
    The Gates Station began operating in January 2011.
    Whereas NorthWestern had previously passed on to its
    Schedule 3 customers the cost of purchasing regulation service
    from other utilities, NorthWestern now wanted to recover from
    its customers the cost of providing regulation service from the
    Gates Station. So NorthWestern filed a proposed revised
    Schedule 3 rate for FERC’s approval. NorthWestern filed its
    rate pursuant to Section 205 of the Federal Power Act, which
    places the burden on the utility to show that its proposed
    revised rate is just and reasonable. 16 U.S.C. § 824d(e).
    Here is how NorthWestern proposed to recover the cost of
    providing regulation service from the Gates Station. First,
    NorthWestern calculated the Gates Station’s revenue
    requirement – the station’s costs plus an allowed rate of return.
    NorthWestern then divided the Gates Station’s revenue
    requirement between two different groups of customers. The
    first group of customers included retail customers only. In
    Montana, retail customers pay for wind-generated electricity in
    addition to fuel-generated electricity. Retail customers pay for
    wind-generated electricity at state-approved rates; FERC does
    not enter into the picture, and utilities do not use Schedule 3 to
    recover the cost of regulation service associated with wind-
    generated electricity. Because NorthWestern calculated that
    6
    retail customers would need 45 megawatts of regulation service
    just to support wind-generated electricity, NorthWestern
    intended to charge retail customers alone for 45 megawatts of
    regulation service, and to do so at the state-approved rate –
    separate from Schedule 3.
    The second group of customers included both retail and
    wholesale customers. Both retail and wholesale customers pay
    for regulation service associated with fuel-generated electricity
    at FERC-approved rates under Schedule 3. NorthWestern
    determined that this second group of customers would need 60
    megawatts of regulation service – the amount that
    NorthWestern had historically purchased from other utilities.
    So NorthWestern proposed to recover the cost of 60 megawatts
    of regulation service from this second group of customers
    under Schedule 3.
    In other words, NorthWestern planned to use the Gates
    Station to supply a total amount of 105 megawatts of regulation
    service to all of its customers. Retail customers alone would
    pay for 45 megawatts of that total – 43% – at a state-approved
    rate, separate from Schedule 3. Retail and wholesale customers
    together would pay for the remaining 60 megawatts of that total
    – 57% – under Schedule 3. NorthWestern calculated its
    proposed Schedule 3 rate by multiplying the Gates Station’s
    revenue requirement by .57, which is the ratio of 60/105.
    Three other components of NorthWestern’s proposed
    Schedule 3 rate also matter here. First, NorthWestern planned
    to use Schedule 3 to recover fuel costs associated with
    operating the Gates Station, but also planned to credit
    customers for any revenue that the Gates Station might bring
    in from anything other than providing regulation service, such
    as from “off-system sales” – sales of energy to third parties.
    NorthWestern indicated, however, that it did not actually plan
    7
    to use the Gates Station for anything other than regulation
    service. Second, NorthWestern proposed to recover costs
    associated with a three-month outage of the Gates Station that
    occurred in 2012. During that outage, NorthWestern once
    again had to buy regulation service from other utilities.
    NorthWestern planned to pass the cost of that purchased
    regulation service on to its customers under Schedule 3. Third,
    NorthWestern also sought approval to pass on to customers the
    cost of any regulation service that NorthWestern might need to
    purchase in the future in the event of another Gates Station
    outage.
    In sum, NorthWestern asked FERC to approve a revised
    Schedule 3 rate that: (1) charged customers for regulation
    service by multiplying the Gates Station’s revenue requirement
    by the cost-calculation ratio of .57; (2) charged customers for
    fuel costs, but credited customers for any revenue the Gates
    Station might bring in from off-system sales and other non-
    regulation-service sales; (3) charged customers for the
    regulation service that NorthWestern purchased for three
    months during the 2012 outage; and (4) charged customers for
    any regulation service that NorthWestern might need to
    purchase during future outages.
    The administrative law judge assigned to NorthWestern’s
    case concluded that several aspects of the rate were not just and
    reasonable. The ALJ reduced NorthWestern’s proposed rate
    by: (1) multiplying the revenue requirement by a different cost-
    calculation ratio of .13, which is 19/150; (2) excluding fuel
    costs from the Schedule 3 rate altogether and rejecting
    NorthWestern’s crediting arrangement; (3) requiring
    NorthWestern to make a separate filing to recover costs
    associated with the 2012 outage; and (4) requiring
    NorthWestern to make separate filings before charging
    8
    customers for any regulation service that NorthWestern might
    need to purchase during future outages.
    FERC affirmed the ALJ’s decision in all respects. FERC
    ordered NorthWestern to refund its customers the difference
    between NorthWestern’s proposed rate and the lower rate that
    FERC ultimately approved as just and reasonable. FERC
    denied NorthWestern’s request for rehearing.
    NorthWestern timely petitioned for review in this Court.
    We review FERC’s order under the Administrative Procedure
    Act’s arbitrary and capricious standard. That standard requires
    that FERC’s decision be reasonable and reasonably explained.
    II
    NorthWestern raises four challenges to the revised rate
    that FERC approved.
    First, NorthWestern maintains that FERC unreasonably
    reduced the numerator of NorthWestern’s proposed cost-
    calculation ratio. The numerator reflects the number of
    megawatts needed to serve Schedule 3 customers. FERC
    reduced the proposed numerator from 60 to 19 megawatts after
    determining that only 19 megawatts were needed to serve
    Schedule 3 customers.
    Along with some other exclusions not at issue here, FERC
    excluded the megawatts associated with “regulation-down”
    capacity from the numerator. NorthWestern contends that it
    was unreasonable to exclude regulation-down capacity from
    the numerator. We disagree.
    “Regulation down,” a component of regulation service, is
    the capacity associated with operating a generator at a set point,
    9
    a steady point from which the utility can quickly ramp down if
    demand for electricity suddenly drops. The energy generated
    as a by-product of operating at a set point can potentially be
    used for non-regulation-service purposes – for example, it can
    be sold to third parties in “off-system sales.”
    NorthWestern operates its Gates Station generators at a set
    point in order to reserve capacity for regulation down. But
    NorthWestern does not sell the energy thereby generated.
    NorthWestern nonetheless proposed to recover from its
    Schedule 3 customers the costs of reserving regulation-down
    capacity. The ALJ rejected NorthWestern’s proposal and
    subtracted the megawatts associated with regulation-down
    capacity from NorthWestern’s proposed numerator after
    determining that NorthWestern had neither produced adequate
    data to show how much regulation-down capacity the Gates
    Station would need to reserve, nor explained why
    NorthWestern could not recover its costs in some other way,
    such as by selling the energy.
    FERC affirmed the ALJ’s decision and added some further
    analysis, focusing primarily on NorthWestern’s failure to
    demonstrate that it could not recover its costs through means
    such as off-system sales. Drawing on other cases excluding
    regulation-down capacity from cost calculations, FERC
    applied the principle that animated those cases: Customers
    should not pay for what is essentially a backup service if the
    utility can recover its costs by using or selling the energy that
    it generates as a by-product. See NorthWestern Corp., 
    155 FERC ¶ 61,158
    , at ¶¶ 33-36 (2016); see also Kentucky Utilities
    Co., 
    85 FERC ¶ 61,274
     (1998); Allegheny Power Service
    Corp., 
    85 FERC ¶ 61,275
     (1998). NorthWestern, FERC
    acknowledged, might be in a different situation: It was
    possible, for example, that the location of the Gates Station
    might make off-system sales infeasible.             If so, then
    10
    NorthWestern might be able to show the justness and
    reasonableness of charging Schedule 3 customers for the costs
    of reserving regulation-down capacity. But FERC concluded
    that NorthWestern had failed to produce sufficient evidence to
    support such a showing. See NorthWestern Corp., 
    147 FERC ¶ 61,049
    , at ¶ 48 (2014). And because it was NorthWestern’s
    burden under Section 205 to show that its proposed rate was
    just and reasonable, that failure was fatal. FERC therefore
    reasonably excluded the megawatts associated with regulation-
    down capacity from the cost-calculation ratio.
    NorthWestern’s several rejoinders miss the mark.
    NorthWestern maintains that FERC lacked authority under
    Section 205 to reduce the numerator of NorthWestern’s
    proposed cost-calculation ratio.       Because NorthWestern
    previously passed on the cost of 60 megawatts of purchased
    regulation service with FERC’s approval, NorthWestern
    argues that the 60-megawatt amount was “embedded” in
    NorthWestern’s original rate. Petitioner’s Brief at 40. And
    because FERC (i) must act under Section 206 of the Federal
    Power Act in order to modify an existing rate component and
    (ii) may modify an existing rate component under Section 206
    only after showing that the existing rate component is not just
    and reasonable, NorthWestern contends that FERC made an
    “end-run” around Section 206 by (i) modifying an existing rate
    component in a Section 205 proceeding and (ii) placing the
    burden of proof on NorthWestern. 
    Id. at 41
    ; see 16 U.S.C.
    § 824e; Public Service Commission of New York v. FERC, 
    642 F.2d 1335
    , 1345 (D.C. Cir. 1980) (utility bears burden of proof
    on those parts of its proposed rate that depart from status quo,
    but not on those parts that are “constant elements” of the
    previous rate).
    NorthWestern is mistaken. The 60-megawatt amount was
    never “embedded” in any rate formula that FERC previously
    11
    approved because it was never a component of a traditional
    cost-of-service rate.      Rather, FERC previously allowed
    NorthWestern – as a temporary expedient – to pass on what it
    cost NorthWestern to procure a set amount (60 megawatts) of
    regulation service from third parties. NorthWestern’s proposed
    revised rate, which is structured as a traditional cost-of-service
    rate, departs from the previous status quo. NorthWestern
    therefore had to justify its entire revised and redesigned rate,
    including all of the rate’s components, as FERC explained.
    NorthWestern Corp., 
    155 FERC ¶ 61,158
    , at ¶¶ 27-29; see
    Kansas Gas & Electric Co. v. FERC, 
    758 F.2d 713
    , 719-20
    (D.C. Cir. 1985) (utility proposing rate clause that departs from
    previous status quo bears burden of proof). So FERC properly
    assigned NorthWestern the burden of proof in this Section 205
    proceeding.
    In another burden-shifting attempt, NorthWestern
    contends that FERC failed to identify other customers who
    might bear NorthWestern’s cost of reserving regulation-down
    capacity. But it was not FERC’s burden to identify alternative
    ways for NorthWestern to recover its costs (although FERC did
    suggest some ways). Instead, it was NorthWestern’s burden to
    show that its proposed rate was just and reasonable – here, for
    example, by showing that no other such customers could be
    identified.
    NorthWestern also objects that, in reducing the numerator,
    FERC failed to account for NorthWestern’s proposed crediting
    arrangement, which would have credited NorthWestern’s
    Schedule 3 customers the value of any off-system or other non-
    regulation-service energy sales that NorthWestern might
    manage to make. But FERC reasonably declined to discuss the
    crediting arrangement. The proposed crediting arrangement
    assumed the very point that NorthWestern needed to prove:
    12
    that Schedule 3 customers should bear the cost of reserving
    regulation-down capacity in the first place.
    In short, FERC reasonably modified NorthWestern’s
    proposed cost-calculation ratio by excluding the megawatts
    associated with “regulation down” from the numerator. We
    therefore reject NorthWestern’s first challenge.
    Second, NorthWestern contends that FERC arbitrarily
    increased the denominator of NorthWestern’s proposed cost-
    calculation ratio from 105 megawatts to 150 megawatts. We
    disagree.
    Recall that 105 megawatts is the total amount of regulation
    service that NorthWestern planned to provide from the Gates
    Station – 45 megawatts associated with wind-generated
    electricity, plus 60 megawatts associated with fuel-generated
    electricity. NorthWestern proposed to use that 105-megawatt
    figure as the denominator of the cost-calculation ratio in order
    to charge Schedule 3 customers for their portion of the total
    amount of regulation service that NorthWestern planned to
    provide from the Gates Station.
    Under FERC precedent, however, the denominator should
    reflect the nameplate capacity – here, meaning the number of
    megawatts that the Gates Station had the capacity to produce,
    not just the megawatts that NorthWestern planned to devote to
    regulation service. See Westar Energy, Inc., 
    130 FERC ¶ 61,215
    , at ¶ 40 (2010); NorthWestern Corp., 
    140 FERC ¶ 63,023
    , at ¶¶ 148-150 (2012). The record evidence
    established that each of the three generators at the Gates Station
    had a capacity of 50 megawatts, for a total of 150 megawatts.
    FERC therefore reasonably increased the denominator to 150
    megawatts.
    13
    NorthWestern retorts that, because FERC’s ratio uses “the
    nameplate capacity” as the denominator “despite using
    customer demand for regulation service as the numerator,” the
    ratio is somehow unreasonable. Petitioner’s Brief at 32-33.
    We disagree. The denominator measures the Gates Station’s
    total capacity, and the numerator measures the portion of that
    total capacity that is needed to provide regulation service to
    Schedule 3 customers.
    Because FERC acted reasonably in modifying the
    denominator, we reject NorthWestern’s second challenge to
    FERC’s decision.
    Third, NorthWestern maintains that FERC wrongly
    rejected NorthWestern’s proposal to recover fuel costs under
    Schedule 3. More particularly, NorthWestern argues that
    FERC inadequately explained its decision not to allow fuel
    costs, and failed to account for the fact that NorthWestern may
    not be able to recover fuel costs retroactively under Schedule
    4. FERC’s explanation, however, was adequate.
    FERC adopted the ALJ’s reasoning, which explained that
    FERC ordinarily requires utilities to recover fuel costs under
    Schedule 4, which governs “energy service,” rather than under
    Schedule 3, which governs “capacity service.” The two
    exceptional cases that NorthWestern identified both involved
    unusual circumstances, as the ALJ’s decision noted.
    NorthWestern Corp., 
    140 FERC ¶ 63,023
    , at ¶ 181. In addition,
    FERC was not persuaded by NorthWestern’s argument about
    the potential difficulty of recovering past fuel costs under
    Schedule 4, because NorthWestern “admittedly never
    attempted” to recover those costs under Schedule 4.
    NorthWestern Corp., 
    155 FERC ¶ 61,158
    , at ¶ 43. FERC’s
    decision on fuel costs was reasonable and reasonably
    explained.
    14
    Fourth, NorthWestern argues that FERC acted arbitrarily
    by (1) requiring NorthWestern to make a separate Section 205
    filing to recover costs associated with the 2012 Gates Station
    outage, and (2) requiring NorthWestern to make separate
    Section 205 filings before charging customers for any
    regulation service that NorthWestern might need to purchase
    during future outages. NorthWestern again maintains that
    FERC inadequately explained its decision and failed to
    consider the possibility that NorthWestern might not be able to
    recover costs associated with the 2012 outage retroactively.
    But FERC again adopted the ALJ’s reasoning, which justified
    the separate proceedings on reasonable grounds – the need for
    more data related to the 2012 outage, and the need for case-by-
    case analysis of any future contracts. FERC acted reasonably
    here as well.
    In sum, we find that FERC’s decision on NorthWestern’s
    proposed rate was reasonable and reasonably explained.
    III
    NorthWestern also challenges FERC’s decision to order a
    refund of the difference between the higher rate that
    NorthWestern proposed and the lower rate that FERC
    approved.    NorthWestern contends that FERC’s refund
    decision resulted from faulty reasoning and an inadequate
    assessment of equitable factors. We are not persuaded.
    The parties agree that FERC ordinarily does not order
    refunds in cases where a utility collects the appropriate total
    amount of revenue but improperly allocates it among different
    customer groups. The parties also agree that FERC ordinarily
    does order refunds in cases where a utility instead overcharges
    a given customer group. See, e.g., Black Oak Energy, LLC, 139
    
    15 FERC ¶ 61,111
    , at ¶ 11 & nn. 17-18 (2012). But the parties
    disagree about how to classify this case.
    FERC concluded that NorthWestern over-collected from
    its Schedule 3 customers, making this the kind of case in which
    FERC ordinarily orders refunds. That determination was
    reasonable. As FERC explained, the purpose of the Section
    205 proceeding was to decide whether the revised rate that
    NorthWestern proposed to charge its Schedule 3 customers was
    just and reasonable. The object of the proceeding was not to
    decide how to divvy up the Gates Station’s revenue
    requirement among different customer groups. NorthWestern
    Corp., 
    155 FERC ¶ 61,158
    , at ¶¶ 55-56. Because FERC
    concluded that NorthWestern’s proposed Schedule 3 rate was
    too high, FERC naturally also concluded that NorthWestern
    had overcharged, and therefore over-collected from, its
    Schedule 3 customers.
    NorthWestern objects that the parties’ frequent use of the
    word “allocate” throughout the proceeding demonstrates that
    this case was really about cost allocation. True, the parties
    tossed that term around somewhat loosely. But to make the
    classification of this case turn on the parties’ imprecise use of
    the term “allocate” would be to ignore the substantive
    distinction that FERC’s precedent attempts to draw between
    “cost-allocation” and “over-collection” cases. NorthWestern’s
    other objections take too narrow a view of FERC’s relevant
    precedents and rely on comparisons to dissimilar cases. Put
    simply, FERC reasonably determined that NorthWestern over-
    collected from its Schedule 3 customers in this case.
    Even so, NorthWestern contends that FERC did not
    adequately assess the relevant equitable factors before
    imposing the refund order. But FERC considered the argument
    that NorthWestern acted in good faith, and found it irrelevant
    16
    to the question whether FERC should depart from its general
    policy of ordering refunds in over-collection cases. FERC also
    considered the fact that NorthWestern was on notice about a
    potential refund order from the start of the proceeding, when
    FERC accepted and suspended NorthWestern’s proposed rate
    subject to refund. After considering those factors, FERC
    decided to treat this case like an ordinary over-collection case
    and order a refund. That decision was reasonable and
    reasonably explained.
    ***
    We deny the petition for review.
    So ordered.