New England Power Generators Ass'n v. Federal Energy Regulatory Commission , 757 F.3d 283 ( 2014 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued November 19, 2013              Decided July 8, 2014
    No. 12-1060
    NEW ENGLAND POWER GENERATORS ASSOCIATION, INC.,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    PSEG ENERGY RESOURCES & TRADE LLC, ET AL.,
    INTERVENORS
    Consolidated with 12-1074, 12-1085, 12-1149
    On Petitions for Review of Orders of the
    Federal Energy Regulatory Commission
    Stephen L. Teichler argued the cause for petitioners
    NSTAR Electric Company/Public Systems. With him on the
    briefs was Mary E. Grover.
    2
    Jeffrey A. Schwarz argued the cause for petitioners
    Massachusetts Municipal Wholesale Electric Company, et al.
    With him on the briefs were Scott H. Strauss and Peter J.
    Hopkins.
    Jeffrey A. Lamken argued the cause for petitioners New
    England Power Generators Association, Inc., et al. With him
    on the briefs were Martin V. Totara, Ashley C. Parrish, David
    G. Tewksbury, Stephanie S. Lim, Matthew S. Owen, and
    Abraham Silverman.
    John Lee Shepherd Jr. argued the cause for intervenors
    PSEG Energy Resources & Trade LLC, et al. With him on
    the brief was Jodi L. Moskowitz.
    John S. Wright and Michael C. Wertheimer, Assistant
    Attorneys General, Office of the Attorney General for the
    State of Connecticut, were on the brief for intervenor George
    Jepsen, Attorney General for the State of Connecticut, in
    support of petitioners.
    F. Anne Ross was on the brief for intervenor New
    England Conference of Public Utilities Commissioners, Inc.
    in support of petitioner.
    Robert M. Kennedy Jr., Attorney, and Beth G. Pacella,
    Senior Attorney, Federal Energy Regulatory Commission,
    argued the causes for respondent. With them on the brief
    were David L. Morenoff, Acting General Counsel, and Robert
    H. Solomon, Solicitor.
    Kimberly Frank argued the cause for intervenor
    Connecticut Public Utilities Regulatory Authority. With her
    on the brief were Randall L. Speck, Gregory S. Warner,
    3
    Robert A. Weishaar, Jr., F. Anne Ross, and Stephen L.
    Teichler.
    Ashley C. Parrish and David G. Tewksbury were on the
    brief for intervenor New England Power Generators
    Association, Inc. in support of respondent.
    Before: BROWN and GRIFFITH, Circuit Judges, and
    SENTELLE, Senior Circuit Judge.
    Opinion for the Court filed by Senior Circuit Judge
    SENTELLE.
    SENTELLE, Senior Circuit Judge: Multiple petitioners
    seek review of orders of the Federal Energy Regulatory
    Commission (“FERC” or “the Commission”) affecting the
    administration of the Independent System Operator-New
    England (“ISO-NE”) and specifically directed to curtailment
    of the exercise of market power in the New England energy
    market. While competing petitioners raise numerous and
    often opposite objections to FERC’s orders, upon review we
    conclude that none of the petitioners establishes that FERC
    has committed reversible error, and we therefore deny the
    petitions for review.
    I. BACKGROUND
    A. Statutory and Regulatory Framework
    The Commission is charged under the Federal Power Act
    (“FPA”) with regulating the sale and transmission of electric
    energy, primarily ensuring that energy is provided at a just
    and reasonable rate. 16 U.S.C. § 824d(a). The Commission
    has jurisdiction over such sale and transmission, but states
    retain the right to regulate the facilities responsible for the
    4
    generation of electric energy. 
    Id. § 824(b).
    In exercising its
    duty to oversee the wholesale electricity market, FERC has
    undertaken to regulate capacity markets, which dictate the
    amount of electricity available for production and
    transmission when needed. See Conn Dep’t of Pub. Util.
    Control v. FERC, 
    569 F.3d 477
    , 479 (D.C. Cir. 2009). At the
    foundation of FERC’s current regulatory scheme of the
    electric market stands Order No. 888. 1 In Order No. 888,
    FERC undertook to promote wholesale competition through
    open access and nondiscriminatory transmission services. As
    part of that undertaking, FERC “encouraged the formation of
    independent system operators (ISOs) to administer
    transmission services and new markets for wholesale
    electricity transactions.” Sithe/Independence Power Partners,
    LP v. FERC, 
    285 F.3d 1
    , 2 (D.C. Cir. 2002). The regulatory
    scheme contemplates that the ISOs will “adopt transmission
    (and ancillary services) pricing policies to promote the
    efficient use of, and investment in, generation, transmission,
    and consumption” of wholesale electric power in specific
    energy capacity systems. 
    Id. One such
    ISO is the
    Independent System Operator-New England, responsible for
    the electric energy capacity system in the New England
    region.
    1
    Promoting Wholesale Competition Through Open Access Non-
    Discriminatory Transmission Servs. By Pub. Utils.; Recovery of
    Stranded Costs by Pub. Utils. & Transmitting Utils., Order No.
    888, FERC Stats & Regs. ¶ 31,036 (1996), order on reh’g, Order
    No. 888-A, FERC Stats & Regs ¶ 31,048 (1997), order on reh’g,
    Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order
    No. 888-C, 82 FERC ¶ 61,046 (1998), affirmed in relevant part,
    remanded in part on other grounds sub nom. Transmission Access
    Policy Study Grp. v. FERC, 
    225 F.3d 667
    (D.C. Cir. 2000), aff’d
    sub nom. New York v. FERC, 
    535 U.S. 1
    (2002).
    5
    To ensure reliable electrical power, a system operator
    such as ISO-NE must implement a scheme that will incent
    resources to provide sufficient energy capacity, or energy
    available for later use. New England’s chosen scheme
    involves a Forward Capacity Market (“FCM”), which sets
    capacity price for the following three years via auction. After
    completing two auctions in 2008 under the most recent
    capacity market regime, New England market participants
    submitted on December 1, 2008 a filing to the Commission
    identifying certain parameters of the capacity market
    requiring further attention. Subsequently, after Auction 3,
    New England participants proposed revisions to the capacity
    market rules in a February 22, 2010 filing. FERC entered
    four orders regarding these and subsequent requests for
    modification that are before us.
    In its orders, FERC imposed buyer- and supplier-side
    mitigation measures which, apparently, satisfied exactly none
    of its constituents. Petitioners NSTAR Electric Company
    (“NSTAR”), along with Massachusetts Municipal Wholesale
    Electric Company and New Hampshire Electric Cooperative,
    Inc. (together, “Public Systems”), challenge FERC’s buyer-
    side mitigation measures as going too far. Public Systems
    also assert that the Commission lacks jurisdiction under the
    Federal Power Act to impose these mitigation measures, an
    argument joined by Intervenors the Attorney General for the
    State of Connecticut (“Connecticut”) and the New England
    Conference of Public Utilities Commissioners (“New England
    Commissioners”).
    Petitioners New England Power Generators Association,
    Inc. (“NEPGA”) and several electricity generators, NRG
    Power Marketing LLC, Connecticut Jet Power LLC, Devon
    Power LLC, Middletown Power LLC, Montville Power LLC,
    Norwalk Power LLC, and Somerset Power LLC (together,
    6
    “Suppliers”), challenge the buyer-side mitigation measures as
    too lenient, while contending that the seller-side measures are
    too harsh.
    For the reasons explained below, we hold that the orders
    on review fall within FERC’s statutory rate-making authority
    conferred by the FPA.          Because FERC undertook its
    balancing responsibilities in the capacity market with
    appropriate consideration and based its decision on substantial
    evidence, we defer to the Commission’s sound judgment in
    crafting mitigation measures responsive to the needs of the
    New England Forward Capacity Market, and therefore deny
    each of the petitions before us.
    B. The Devon Power Settlement
    The New England market fashioned the particulars of its
    capacity market via a settlement including stakeholders of all
    stripes. FERC initially approved the Forward Capacity
    Market, Devon Power LLC, 115 FERC ¶ 61,340 (“Settlement
    Order”), order on reh’g, 117 FERC ¶ 61,133 (2006)
    (“Settlement Rehearing Order”), and all aspects of the
    Commission’s determination were eventually affirmed by this
    Court and/or the Supreme Court. See Me. Pub. Utils.
    Comm’n v. FERC, 
    520 F.3d 464
    , 467 (D.C. Cir. 2008), rev’d
    in part sub nom. NRG Power Mktg. v. Me. Pub. Utils.
    Comm’n, 
    558 U.S. 165
    (2010).
    The settlement contemplated use of auctions through
    which utilities can secure obligations to provide capacity.
    Before each auction, ISO-NE determines the amount of
    capacity that will be required for system reliability in three
    years—the Installed Capacity Requirement. Conn. 
    Dep’t, 569 F.3d at 480
    . Each energy provider is required to purchase
    enough capacity to meet its share of the Installed Capacity
    7
    Requirement. 
    Id. The auction
    is a “descending clock
    auction” in which the price gradually drops until the total
    amount of capacity offered by suppliers equals the Installed
    Capacity Requirement. The starting price for the auction is
    set at twice the estimated “Cost of New Entry.” 
    Id. Cost of
    New Entry is the price of capacity, expressed in $/kilowatt-
    month, that is needed to attract new capacity. Settlement
    Order ¶ 130. Theoretically, such a pricing scheme allows for
    the market to signal its need for additional electrical
    generation, while enabling generators to recover their costs.
    See TC Ravenswood, LLC v. FERC, 
    741 F.3d 112
    , 114 (D.C.
    Cir. 2013).
    The settlement provided several features designed to
    assure that the Forward Capacity Market did not suffer from
    the exercise of buyer-side market power, wherein the price of
    capacity drops too low to produce just and reasonable
    electricity rates. First, an Internal Market Monitor was to
    review the bids to ensure that they actually reflect a resource’s
    long-run costs. Settlement Order ¶ 109. Any bid below those
    costs would be deemed out-of-market (also known as “below-
    cost” or “uneconomic”). 
    Id. When such
    a bid is discovered,
    the capacity clearing price (i.e., the closing price of the
    auction) would be reset under the Alternative Price Rule to
    either (1) Cost of New Entry or (2) the price at which the last
    in-market resource withdrew from the auction via a de-list bid
    minus $0.01. 
    Id. Secondly, under
    the settlement, load-
    serving entities (“LSEs”), essentially electric utility
    companies, could designate some resources as self-supply:
    either utility-owned generation facilities or facilities with
    which the utility had contracted. 
    Id. ¶ 20.
    These self-
    supplied resources could be used to offset the utility’s
    required share of the Installed Capacity Requirement, even
    though they participate in the auction at prices below their
    long-run costs and are thus out-of-market. ISO New England,
    8
    Inc., 138 FERC ¶ 61,027, nn.99 & 103. Finally, the capacity
    market was to be subject to a clearing price floor in its first
    three auctions; the clearing price could not be set below 0.6
    times Cost of New Entry. Settlement Order ¶ 19.
    The settlement also included features designed to protect
    against supplier-side market power. While it allowed for
    several types of de-list bids, where suppliers of capacity
    resources could exit the market as the price dropped, certain
    of these de-list bid types were subject to review by the
    Internal Market Monitor. 
    Id. ¶ 28.
    A static de-list bid is one
    that allows a utility to exit the auction for a year, but must be
    submitted before the auction and must be reviewed by the
    Internal Market Monitor. ISO New England, Inc., 135 FERC
    ¶ 61,029 n.75. A dynamic de-list bid occurs when a capacity
    resource exits during the auction without Internal Market
    Monitor review. 
    Id. n.74; ISO
    New England, Inc., 119 FERC
    ¶ 61,045 P.35.
    C. Procedural History
    In 2008, ISO-NE held the first two auctions under the
    FCM regime outlined by the settlement and approved in the
    Settlement Order and Settlement Rehearing Order. On
    December 1, 2008, New England market participants
    submitted a filing proposing that modifications be made to the
    FCM and calling for stakeholder input. In June 2009, the
    Internal Market Monitor issued an initial assessment of the
    capacity market. The third auction took place in October
    2009. After a stakeholder process, several market participants
    submitted on February 22, 2010 proposed FCM changes that
    would go into effect on April 23, 2010, some three months
    before the scheduled August 2, 2010 fourth auction. This
    original proposal sought, among other things, to revise the
    Alternative Price Rule, extend the price floor beyond the third
    9
    auction, and revise the Cost of New Entry calculation. ISO
    New England, Inc., 131 FERC ¶ 61,065 P.6. The original
    proposal contemplated that other parameters would need yet
    additional stakeholder review and input.
    FERC issued four orders in connection with these and
    subsequent proposed changes to the New England capacity
    market. In the first order, FERC found certain parameters of
    the proposal to satisfy the “just and reasonable” standard and
    accepted them as proposed. ISO New England, Inc., 131
    FERC ¶ 61,065, Order on Forward Capacity Market
    Revisions and Related Complaints, April 23, 2010 (“First
    Order”) ¶ 16. FERC set other issues for paper hearing, but
    made the proposed changes effective as of the date of the
    order, April 23, 2010, to provide certainty heading into the
    fourth auction scheduled for August 2, 2010. 
    Id. ¶¶ 17–19.
    The Commission later issued a second order clarifying certain
    portions of the First Order. 132 FERC ¶ 61,122, Order
    Granting in Part and Denying in Part Requests for
    Clarification and Rehearing and Denying Motion for
    Disclosure, August 12, 2010 (“Second Order”). On the paper
    hearing, ISO-NE presented a July 1, 2010 revised proposal
    outlining changes to the Forward Capacity Market, and
    various stakeholders responded to both the original and the
    revised proposal.
    FERC issued two orders responding to the revised
    proposal. 135 FERC ¶ 61,029, Order on Paper Hearing and
    Order on Rehearing, April 13, 2011 (“Third Order”); 138
    FERC ¶ 61,027, Order on Rehearing and Clarification and
    Order Accepting Compliance Filings, January 19, 2012
    (“Fourth Order”).       FERC identified “two major and
    interrelated issues . . . in this case: (1) whether the FCM
    design in New England will provide sufficient income to
    incent market entry when necessary without the assistance of
    10
    supplemental revenue streams from outside ISO-NE markets
    and (2) the proper design of market power mitigation regimes
    to protect against both buyer and seller market power.” Third
    Order ¶ 15. As a result, it found the majority of the proposal
    unjust and unreasonable, but accepted portions of ISO-NE’s
    July 1, 2010 revised proposal. 
    Id. ¶ 16.
    FERC found that the proposals did not adequately
    mitigate buyer-side power in that they failed to provide
    sufficient regulation of below-cost entry, but also found that a
    component of the revised proposal based on “benchmark
    pricing” could lead to a just and reasonable buyer-side
    mitigation measure. 
    Id. ¶¶ 17,
    165. Significantly, the
    Commission ordered ISO-NE to develop a minimum-offer
    price rule (“MOPR” or “offer-floor mitigation”) specific to
    resources’ asset class. FERC “require[d] ISO-NE to work
    with its stakeholders to develop a mitigation regime that relies
    on these benchmarks but does not procure more capacity than
    [the Installed Capacity Requirement], that is, to develop an
    offer-floor mitigation construct . . . .” 
    Id. ¶ 165.
    FERC found it inappropriate to adopt a categorical
    mitigation exemption for state-sponsored and self-supply
    entities, Third Order ¶¶ 170–71, but nothing in the order
    eliminated any right that entities might have to request
    mitigation exemptions, Fourth Order ¶ 91. The Commission
    extended the price floor through Auction 6, but did not further
    mitigate resources that had been deemed below-cost in the
    first five auctions once the MOPR construct was in place.
    Third Order ¶ 217.
    FERC found that the proposals also failed to adequately
    mitigate supplier-side power. The Commission lowered the
    dynamic de-list bid price to $1/kilowatt-month, requiring de-
    list bids over this price to be subject to review by the Internal
    11
    Market Monitor. Third Order ¶ 313; Fourth Order ¶¶ 121–
    28.
    D. Petitions for Review
    Before us, Petitioners NSTAR and Public Systems
    challenge the buyer-side mitigation measures as going too far.
    Public Systems first contends that FERC lacks jurisdiction
    under the FPA to impose mitigation requirements upon
    uneconomic entrants to the Forward Capacity Market. Both
    NSTAR and Public Systems go on to argue that, assuming
    jurisdiction, FERC’s orders imposing mitigation requirements
    in order to produce just and reasonable rates were not based
    on substantial evidence. Finally, NSTAR and Public Systems
    assert that the Commission acted arbitrarily and capriciously
    in declining to create a categorical mitigation exemption for
    self-supplied and state-sponsored resources.
    Conversely, petitioners NEPGA and Suppliers challenge
    the buyer-side mitigation measures as too lenient, while
    contending that the supplier-side mitigation measures are too
    harsh. On the buyer-side measures, they first argue that
    FERC acted arbitrarily and capriciously in declining to
    regulate uneconomic entrants from Auctions 1–5 in later
    auctions using the offer floor mitigation scheme. Secondly,
    they argue that the Commission erred in determining which
    resources constitute new import resources subject to offer-
    floor mitigation. Regarding the seller-side measures, they
    claim that it was arbitrary and capricious for FERC to lower
    the dynamic de-list price to $1/kilowatt-month.
    We consider each allegation in turn.
    12
    II. STANDARD OF REVIEW
    This Court reviews final orders issued by the
    Commission under the arbitrary and capricious standard of the
    Administrative Procedure Act, 5 U.S.C. § 706(2)(A). An
    agency action will be upheld if the agency “articulate[d] a
    satisfactory explanation for its action including a ‘rational
    connection between the facts found and the choice made.’”
    Motor Vehicle Mfrs. Ass’n of United States, Inc. v. State Farm
    Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983) (quoting
    Burlington Truck Lines, Inc. v. United States, 
    371 U.S. 156
    ,
    168 (1962)). The Commission’s factual findings will be
    upheld if supported by substantial evidence. 16 U.S.C.
    § 825l(b).
    The question of an agency’s interpretation of a statutory
    ambiguity that concerns the scope of the agency’s authority is
    reviewed under the Chevron standard. “[T]he question in
    every case is, simply, whether the statutory text forecloses the
    agency’s assertion of authority, or not.” City of Arlington,
    Tex. v. FCC, __ U.S. __, __, 
    133 S. Ct. 1863
    , 1871 (2013).
    III. DISCUSSION
    A. FERC’s Jurisdiction
    We begin by noting that the Settlement Order and
    Settlement Rehearing Order in this case entertained concerns
    over whether FERC had jurisdiction over the settlement.
    However, the Settlement Orders were devoted to considering
    the broad issue of FERC’s jurisdiction to regulate charges for
    capacity as opposed to wholesale energy. Settlement Order
    ¶ 201 (collecting cases in which “[c]ourts have confirmed that
    the Commission has jurisdiction under the FPA to regulate the
    charges for capacity in wholesale markets”). The Settlement
    13
    Orders did not consider the precise jurisdictional question
    before us.
    Our question is whether FERC has jurisdiction to
    regulate capacity where its regulation touches on which
    energy facilities may be used to fulfill capacity obligations.
    Public Systems argue that FERC exceeded its jurisdiction
    when it imposed buyer-side mitigation measures because the
    orders serve to dictate which resources a utility must use to
    satisfy its capacity obligations, in violation of the FPA.
    Intervenor Connecticut joins Public Systems’ jurisdictional
    argument, contending that FERC’s orders impermissibly
    determine the makeup of a state’s resource portfolio.
    Under 16 U.S.C. § 824(b)(1), “[t]he Commission shall
    have jurisdiction over all facilities for such [interstate]
    transmission or sale of electric energy, but shall not have
    jurisdiction . . . over facilities used for the generation of
    electric energy . . . .” Said another way, states regulate
    facilities, while FERC regulates sale and transmission. We
    have previously held that the Commission has jurisdiction to
    regulate certain parameters of the capacity market related to
    the price of capacity, even if those determinations touch on
    states’ authority. See, e.g., Conn. Dep’t of Pub. Util. Control
    v. FERC, 
    569 F.3d 477
    , 481–83 (D.C. Cir. 2009) (FERC may
    regulate Installed Capacity Requirement as it affects FERC
    jurisdictional rates, even if the requirement could result in the
    construction of facilities, a matter under state jurisdiction);
    Municipalities of Groton v. FERC, 
    587 F.2d 1296
    , 1300–03
    (D.C. Cir. 1978) (FERC approval of a capacity deficiency
    charge does not encroach on state jurisdiction, even though it
    14
    may “motivate [utilities] to develop sufficient capacity to
    meet their load requirements”). 2 We do so again here.
    Out-of-market resources—whether self-supplied, state-
    sponsored, or otherwise—directly impact the price at which
    the Forward Capacity Market auction clears. As the price of
    capacity is indisputably a matter within the Commission’s
    exclusive jurisdiction, FERC likewise has jurisdiction to
    mitigate buyer-side market power as to out-of-market
    entrants. We agree with the Commission’s finding that it has
    jurisdiction over mitigation matters “affecting or relating to
    wholesale rates” under FPA § 201 and 206. Third Order
    ¶ 220 (emphasis omitted) (citing Conn. Dep’t of Pub. Util.
    
    Control, 569 F.3d at 478
    , 481). We stress that FERC’s
    mitigation measures here do not entail direct regulation of
    facilities, a matter within the exclusive control of the states.
    See 16 U.S.C. § 824(b)(1). The Commission also found that
    uneconomic entry, regardless of resource and regardless of
    intent, “can produce unjust and unreasonable prices by
    artificially depressing capacity prices.” 
    Id. ¶ 170.
    As it is
    FERC’s statutory obligation to ensure that rates are
    appropriate, we must respect its decision to maintain just and
    reasonable rates through curbing or mitigating buyer-side
    market power. See Fourth Order ¶ 79 (“By regulating the
    mechanism that ultimately produces the capacity clearing
    price, the Commission is properly exercising its jurisdiction
    over rates, terms and conditions of service.”).
    Public Systems’ and Intervenor Connecticut’s arguments
    largely rest on the proposition that the Commission is
    2
    However, we have never held, and do not now hold, that
    regulation related to the price of capacity is within FERC’s
    authority if it entails direct regulation of generation facilities. Such
    matters are the province of the states. 16 U.S.C. § 824(b)(1).
    15
    improperly regulating “facilities used for the generation of
    electric energy.” 16 U.S.C. § 824(b)(1). However, their
    arguments fail: states remain free to subsidize the construction
    of new generators, and load serving entities to build or
    contract for any self-supply they believe is necessary; FERC’s
    orders simply regulate the “price constructs that result in
    offers into the capacity market from these resources that are
    not reflective of their actual costs.” Third Order ¶ 170.
    Moreover, this Court has already rejected in Connecticut
    Department of Public Utility Control the argument that the
    type of regulation at issue here constitutes “direct regulation
    of generation 
    facilities.” 569 F.3d at 481
    –82. There, we held
    that FERC had jurisdiction to regulate “a key input into the
    market-based mechanism.” 
    Id. at 478.
    Just so here. This
    mitigation parameter operates no differently.
    FERC’s rate-making authority confers broad power “to
    act in the public interest.” Miss. Indus. v. FERC, 
    808 F.2d 1525
    , 1549 (D.C. Cir. 1987) (internal quotations omitted),
    vacated and remanded in part on other grounds, 
    822 F.3d 1104
    (D.C. Cir. 1987). We hold that FERC has jurisdiction to
    regulate the parameters comprising the Forward Capacity
    Market, and that applying offer-floor mitigation fits within the
    Commission’s statutory rate-making power.
    B. Buyer-Side Mitigation
    As we have discussed, the orders on review address
    buyer-side market power by imposing a number of mitigation
    measures. Essentially, the arguments before us on each of the
    buyer-side mitigation measures are these: Petitioners NSTAR
    and Public Systems contend that FERC went too far in its
    measures designed to stop uneconomic entry. Petitioners
    NEPGA and Suppliers argue that FERC did not go far enough
    16
    in preventing this buyer-side market power. The Commission
    argues that it struck the appropriate balance.
    1. Necessity of Buyer-Side Mitigation Measures
    The Commission bears the statutory responsibility of
    ensuring that rates are just and reasonable. Therefore, our
    first consideration is whether FERC’s mitigation measures
    against buyer-side market power were undertaken in the
    establishment of just and reasonable rates. NSTAR argues
    that they were not. It contends that FERC erred in ignoring
    the settlement in place in this case, that its orders were not
    supported by substantial evidence, and that it acted arbitrarily
    and capriciously in imposing buyer-side mitigation.
    Similarly, Public Systems argue that FERC erred in its
    determination that self-supply artificially depresses capacity
    prices, causing the Commission’s mitigation measures to be
    unreasonable. We disagree with both sets of Petitioners and
    hold that FERC reasonably mitigated buyer-side market
    power.
    In its orders, the Commission determined that neither of
    ISO-NE’s proposals based on the Alternative Price Rule
    would result in just and reasonable rates, due to the exercise
    of buyer-side market power. Third Order ¶¶ 17–19, 59–61.
    The Alternative Price Rule is a mitigation tool intended to
    discourage buyers from suppressing market clearing capacity
    prices below a competitive level, and to ensure that the price
    of capacity is truly reflective of the cost of new entry into the
    market. By design, the Rule is to provide an upwards price
    adjustment for out-of-market resources. In practice, however,
    the Commission found that the Alternative Price Rule failed
    to adequately address the price suppressive effect of capacity
    that entered the market through below-cost auction bids, due
    to having too narrow a triggering mechanism. 
    Id. ¶¶ 17–19,
                                  17
    59. The Rule was only set to trigger when the Installed
    Capacity Requirement was higher than the amount of existing
    capacity, and thus there was a need for new capacity to make
    up the difference. First Order ¶ 70. However, new capacity
    may be needed in scenarios other than meeting the Installed
    Capacity Requirement, such as to replace existing capacity
    entering retirement. 
    Id. Further, the
    Commission found, the
    Alternative Price Rule did not account for out-of-market
    resources that affect prices even when no new capacity is
    needed, by displacing other price-setting resources. 
    Id. Indeed, the
    Rule was never triggered in the New England
    auctions despite the entrance of significant amounts of out-of-
    market capacity. Third Order ¶ 58. FERC specifically found
    that “[out-of-market] capacity suppresses prices regardless of
    intent,” 
    Id. ¶ 170,
    and necessitates action by the Commission
    to correct for unjust and unreasonable outcomes.
    Even in rejecting ISO-NE’s proposals, the Commission
    did find that one element of the revised proposal, the principle
    of benchmark pricing, “form[ed] the basis for a just and
    reasonable buyer-side mitigation measure.” 
    Id. ¶ 165.
    Under
    this approach, the Internal Market Monitor would establish
    resource-specific benchmark prices approximating the cost of
    new entry into the market. 
    Id. ¶¶ 165,
    169. Bids below a
    specified percentage of the relevant benchmark would be
    deemed uneconomic and would be subject to mitigation. The
    Commission therefore required ISO-NE “to work with its
    stakeholders to develop a mitigation regime that relies on
    these benchmarks but does not procure more capacity than
    [necessary], that is, to develop an offer-floor mitigation
    construct . . . .” 
    Id. ¶ 165.
    Under the offer-floor mitigation
    scheme, if the clearing price falls below the set benchmark,
    the new resource would not clear in the auction and would not
    obtain a capacity supply obligation. 
    Id. ¶¶ 165–69.
                                    18
    According to NSTAR, there is no evidence that the
    Alternative Price Rule is not working as designed to mitigate
    out-of-market entry. The Alternative Price Rule, NSTAR
    argues, should be aimed at preventing buyers from
    intentionally depressing capacity prices. It is true that the
    New England capacity market suffers from the exercise of
    buyer-side market power specifically at the hands of those
    interested in depressing capacity prices. However, NSTAR
    views too narrowly the circumstances in which the
    Alternative Price Rule is designed to operate.                 The
    Commission found that capacity offered into the market
    through below-cost bids can suppress prices even when no
    actor has the intent to do so. Third Order ¶ 170 (“[Out-of-
    market] capacity suppresses prices regardless of intent . . . .”);
    see also N.Y. Indep. Sys. Operator, Inc., 124 FERC ¶ 61,301
    P.29 (2008). The Alternative Price Rule “is a market power
    mitigation rule intended to discourage buyers who have the
    incentive and ability to suppress market clearing capacity
    prices below a competitive level from doing so,” not simply
    the intent to do so. First Order ¶ 69 (emphasis added). FERC
    stated that its objective is “to ensure that the prices in capacity
    markets reflect the market cost of new entry when new entry
    is needed.” 
    Id. However, the
    Commission “agree[d] with the
    [External Market Monitor] and the commenters that ISO-
    NE’s existing [Alternative Price Rule] does not fully meet this
    objective.” 
    Id. ¶ 70.
    Such a finding that the Rule is not working was based on
    substantial evidence. The External Market Monitor found
    that “[out-of-market] capacity can lead to a clearing price in
    the [auction] that is inefficiently low” and “can distort . . .
    prices by shifting the supply in the [auction] such that a bid
    with a substantially lower bid price . . . sets the clearing
    price.” External Market Monitor (Potomac Economics)
    Report at 4–6. In declining to accept the proposed
    19
    amendments to the Alternative Price Rule, the Commission
    relied also on the External Market Monitor’s finding that “the
    proposed [Alternative Price Rule] changes fail to trigger when
    new capacity is not needed or when the [out-of-market]
    quantity is less than the amount of new capacity needed, even
    though in both cases [out-of-market] capacity can
    substantially lower prices without an [Alternative Price Rule]
    adjustment.” First Order ¶ 50; External Market Monitor
    (Potomac Economics) Report at 14–15.
    In short, the Alternative Price Rule would not be
    triggered in all the scenarios necessary to produce just and
    reasonable rates. “[T]he existing [Alternative Price Rule]
    provides a price adjustment for [out-of-market] resources only
    when there is a need for new capacity as reflected by an
    [Installed Capacity Requirement] that exceeds all existing
    capacity.” First Order ¶ 70. The Rule would not be triggered
    when new capacity is needed because existing capacity is
    retiring, or when uneconomic capacity would displace “what
    would otherwise be the marginal, price-setting existing
    resource.” 
    Id. Moreover, even
    in those circumstances where
    the Rule would be triggered, it would not produce the same
    price that would have arisen had all the out-of-market entrants
    offered capacity truly reflective of their long-run costs. 
    Id. Upon evidence
    that the Alternative Price Rule failed to
    capture all of the instances of price-shifting out-of-market
    capacity, FERC acted within its authority to adjust parameters
    of the settlement and in fact “has a continuing obligation to
    ensure that . . . rates are just and reasonable.” OXY USA, Inc.
    v. FERC, 
    64 F.3d 679
    , 690 (D.C. Cir. 1995) (internal
    quotation marks omitted).
    Likewise, we defer to the Commission’s decision to
    mitigate buyer-side power because its determination was not
    arbitrary or capricious, but instead a proper exercise of its role
    20
    in balancing competing interests. FERC evaluated the
    relative importance of several parameters—allowing
    uneconomic resources to clear the market, preventing
    uneconomic resources from distorting the market clearing
    price, and limiting the purchased capacity to the Installed
    Capacity Requirement—and reasonably determined that it
    was more important to prevent price distortion and excess
    capacity purchase than it was to allow out-of-market
    resources to clear. Third Order ¶¶ 159–66; Fourth Order
    ¶¶ 28, 75. Such a juggling act would not benefit from our
    rearranging. See, e.g., Sacramento Mun. Util. Dist. v. FERC,
    
    616 F.3d 520
    , 541–42 (D.C. Cir. 2010) (the court “properly
    defers to policy determinations invoking the Commission’s
    expertise in evaluating complex market conditions,” where
    the Commission “reflected on the competing interests at stake
    to explain why it struck the balance it did”) (internal
    quotations omitted).
    We are also unconvinced by Public Systems’ contentions
    concerning buyer-side mitigation in the context of self-
    supplied resources. They argue that lower prices are the
    natural result of the increased supply of capacity now
    available as states and other entities can produce or contract
    for their own capacity. For the reasons already discussed,
    FERC sufficiently explained how the Alternative Price Rule
    as contemplated in the settlement does not adequately adjust
    prices or prevent out-of-market resources from distorting
    prices irrespective of motivation. That conclusion does not
    change in consideration of the out-of-market resource’s status
    as self-supplied.
    2. Categorical Mitigation Exemption
    If there is to be mitigation of buyer-side market power,
    Petitioners contend, some resources—those which are self-
    21
    supplied and those which are state-sponsored—should be
    categorically exempt. We again defer to the Commission’s
    reasoned determination to the contrary.
    We first decide that the question of categorical mitigation
    exemptions is ripe for review. FERC contends that this issue
    is unripe because ongoing agency proceedings will consider
    mitigation exemptions for these resources. Respondent’s Br.
    at 4–8. However, states and LSEs are currently harmed by
    their inability to develop their portfolios for future years, as
    they are acting pursuant to orders declining to exempt them
    from mitigation. Moreover, since the completion of the
    briefing in this case, FERC has gone on to deny proposed
    tailored exemptions for both self-supplied and state-sponsored
    entities. See Public Systems’ Rule 28(j) letter at 2. In light of
    these factors, there is no reason to stay our consideration of
    the issue.
    Public Systems argue that allowing LSEs to choose
    which resources they will use to fulfill their capacity
    obligations is a cornerstone of the settlement in this case, and
    that the mitigation measures prevent them from electing to
    self-supply capacity because their bids will not clear the
    market. Intervenors New England Commissioners agree and
    argue that the Commission acted arbitrarily and capriciously
    when it failed to meaningfully consider the states’ request for
    a categorical exemption for state-sponsored resources, which
    are unlikely to be used for the purpose of suppressing capacity
    prices.
    It is true enough that, under the settlement, self-supplied
    and state-sponsored resources are available to fulfill capacity
    obligations, provided that they adhere to “the same
    performance obligations and qualification requirements as
    other resources participating in the [Forward Capacity
    22
    Market] and the [auctions.]” See Settlement Order ¶ 20.
    However, FERC did not act arbitrarily and capriciously in
    determining that new self-supplied resources should meet the
    additional burden of mitigation and should not be
    categorically exempt. Rather, it recognized the need for
    modification of the existing mitigation schemes in response to
    the failings of the Alternative Price Rule as applied to all
    uneconomic entry, including self-supplied and state-
    sponsored resources, and mitigated accordingly.
    The Commission found that designating a new resource
    as self-supply “has the same price effect as offering the . . .
    resource [into the auction] at a price of zero.” Fourth Order
    ¶ 60. This low price will serve to displace a higher-priced
    resource that otherwise would have set the clearing price; as a
    result, a lower offer will then set the clearing price. See 
    id. ¶ 72.
    This is definitional market distortion in favor of buyers.
    Further, it is the same market distortion that the Alternative
    Price Rule failed to correct, necessitating the introduction of
    the offer-floor mitigation scheme. Why then would identical
    distortions be treated differently?
    Simply, we uphold the Commission’s determination that
    because self-supply serves to depress capacity prices, a
    categorical exemption from mitigation is unwarranted. To
    categorically exempt new self-supplied resources “would
    allow the mitigation mechanism to be circumvented” and
    result in unjust and unreasonable rates. 
    Id. ¶ 60.
    FERC is
    within its jurisdiction to consider the economic, as well as the
    technical, attributes of a capacity resource.
    We note that, in any event, the mitigation measures do
    not apply to existing resources, 
    id. ¶ 74,
    leaving current self-
    supply purchasing decisions undisturbed and allowing state-
    sponsored projects already in the market to fulfill capacity
    23
    obligations, 
    id. ¶ 88.
    LSEs are free to shape their portfolios as
    they choose, including with new self-supplied resources,
    “provided these new resources clear the auction.” 
    Id. ¶ 74.
    Though the Commission has not yet approved any proposals,
    the orders also permit parties an opportunity to develop
    appropriately tailored exemptions for self-supplied and state-
    sponsored resources through the stakeholder process. See 
    id. ¶¶ 70,
    91. Finally, the Commission “reiterate[d] that state
    parties have the statutory right under [FPA] section 206 to file
    to . . . seek[ ] an exemption . . . .” 
    Id. ¶ 89.
    Public Systems attempt to persuade us that FERC could
    adopt a system wherein self-supply—often renewable energy
    technology—is prevented from affecting the Forward
    Capacity Market clearing price but is still allowed to displace
    other, less competitive resources. Perhaps so. However, the
    Commission reasonably determined that self-supply
    negatively affects prices, and reasonably acted to balance
    competing interests. In this instance, the Commission chose
    to value most strongly the concept of preventing price
    distortion; unfortunately for Public Systems, that decision
    came at the expense of their uneconomic resources’ ability to
    enter the market. FERC made the judgment that encouraging
    renewable energies was less important than allowing such
    out-of-market entrants to depress capacity prices. Such is
    FERC’s prerogative. That it is unfortunate does not make it
    arbitrary.
    FERC’s considered conclusion that certain resources, by
    definition, depress capacity prices falls within its duty of
    ensuring that rates are just and reasonable. Third Order ¶ 170.
    We defer to the Commission’s decision to decline a
    categorical mitigation exemption for self-supplied and state-
    sponsored resources.
    24
    3. Declining to Subject Auction 1–5 Uneconomic
    Entrants to the Further Mitigation
    We turn now to those issues in which a separate set of
    Petitioners asserts that the buyer-side mitigation measures did
    not go far enough to address uneconomic entry and the
    attendant capacity price distortion.
    While the proposals at issue in the case came under
    review by the Commission, the Forward Capacity Market
    marched on, holding three auctions, with Auctions 4 and 5
    soon to follow. During and after the first three auctions,
    FERC considered and rejected two ISO-NE proposals on
    buyer-side mitigation as unjust and unreasonable. Third
    Order ¶¶ 61–62 (rejecting original proposal); 
    id. ¶¶ 159–64
    (rejecting revised proposal). Having decided in the Third
    Order that the Alternative Price Rule was insufficient to curb
    buyer-side market power, the Commission directed
    development of the offer-floor mitigation scheme for future
    auctions. At that point in issuing the Third Order, FERC was
    left with a decision on whether to mitigate further those out-
    of-market entrants who had obtained capacity in Auctions 1–3
    and might well do so in Auctions 4 and 5. Ultimately, FERC
    extended the clearing price floor of 0.6 times Cost of New
    Entry that had been in place for the first three auctions,
    Settlement Order ¶ 19, through Auction 6, but declined to
    apply any other mitigation measures to uneconomic entrants
    in Auctions 1 through 5. Third Order ¶¶ 214–17, n.146;
    Fourth Order ¶¶ 38–46.         Of course, having just been
    conceived, the offer-floor mitigation construct was not yet in
    effect in any of Auctions 1–5, and thus was not a viable
    mitigation mechanism.
    NEPGA and Suppliers argue that FERC should have
    applied mitigation, beyond merely extending the price floor,
    25
    to the uneconomic entrants in Auctions 1–5 until the
    minimum offer price rule went into effect. They claim that
    FERC’s finding that the Alternative Price Rule was
    inadequate is overwhelming evidence that additional
    mitigation was necessary. Due to the Commission’s failure to
    mitigate, the rates in future auctions will be affected and will
    therefore be unjust and unreasonable in violation of the FPA.
    However, our view is that FERC offered well-supported
    reasons in declining to further mitigate as to each of the
    auctions in question.
    As the Commission noted, the fundamental purpose of
    buyer-side mitigation is to prevent uneconomic entry, and
    further mitigation of out-of-market resources already in the
    market would not serve that end. Third Order ¶¶ 21, 214–15,
    n.151 (citing N.Y. Indep. Sys. Operator, 122 FERC ¶ 61,211
    PP.100–01, 118–19); Fourth Order ¶ 39. Instead, further
    mitigation would send inappropriate price signals, such that
    older, higher-cost resources would remain in the Forward
    Capacity Market during a time of capacity surplus. Fourth
    Order ¶ 39. For these two reasons, FERC declined to further
    mitigate uneconomic entrants from Auctions 1–3.
    FERC found that the same rationale—inability to prevent
    uneconomic entry through mitigation—applied equally to
    those resources deemed out-of-market in Auctions 4 and 5, as
    the newly-minted offer-floor mitigation construct would not
    go into effect until after those auctions had taken place.
    Fourth Order ¶¶ 45–46. In addition, there was a notice
    problem as to these interim uneconomic entrants: FERC had
    tentatively accepted the original mitigation proposal to
    provide certainty for Auction 4, but did not issue a final
    rejection of the original mitigation proposal until after the
    fourth auction and just before the fifth auction.          
    Id. Participants in
    these auctions, even with some awareness that
    26
    the Commission was considering stronger mitigation rules,
    could not adjust their offers effectively.
    NEPGA is correct when it tells us that FERC’s duty is to
    ensure that rates are just and reasonable, not ensure
    equitability between participants. Pet’rs Br. at 35–36.
    However, that the Commission also considered notice and
    fairness is hardly a reason to discredit its decision on the
    amount of mitigation to impose. The Commission reasonably
    determined that, in addition to inability to deter entry, fairness
    concerns militated in favor of declining further mitigation as
    against these interim out-of-market resources.                The
    Commission ruled that the entry and notice concerns were
    removed beginning with Auction 6 and thus, going forward,
    FERC did provide for mitigation of uneconomic entrants; the
    Commission found that uneconomic “resources entering in
    [Auction] 6 or any subsequent [auctions] prior to the
    implementation of the new rules will be carried forward under
    the existing rules and treated as new in the first auction in
    which offer floor mitigation is put into place.” Fourth Order
    ¶ 47.
    Intervenor PSEG argues that FERC should not have
    considered whether its mitigation measures would encourage
    older resources to stay in the market. However, this type of
    decision is precisely the sort of policy matter FERC is
    charged with considering. Again, we defer to FERC’s
    expertise, as the agency is best equipped to manage
    competing policy rationales.
    4. Subjecting only Certain Import Resources to the
    Offer-Floor Mitigation Construct
    Some resources did escape FERC’s mitigation measures.
    In the orders on review, FERC required buyer-side
    27
    mitigation—that is, application of the offer-floor construct—
    of capacity originating outside the New England market in
    limited circumstances. These so-called imports are subject to
    mitigation only when both of two conditions are met: (1) “a
    specific new external resource is identified as the sole support
    for the import;” and (2) “a significant investment (such as the
    construction of a new transmission line to import power from
    an adjacent control area) is made to provide capacity to New
    England.” Third Order ¶ 191.
    Petitioner NEPGA and others proposed an alternative
    standard that would have mitigated imports that satisfied
    either condition. NEPGA and Intervenor PSEG contend that
    FERC’s mitigation of only certain import resources was
    arbitrary and capricious.     According to them, FERC’s
    standard allows too many resources to avoid mitigation,
    resulting in the introduction of “unneeded capacity into the
    New England market,” Fourth Order ¶ 98, which “can
    produce unjust and unreasonable prices by artificially
    depressing capacity prices,” Third Order ¶ 170.
    The Commission determined that when imports involve
    “new resources that are devoted to the New England market
    over the long term,” they should “be treated like new internal
    resources for mitigation purposes.” 
    Id. ¶ 191.
    That is,
    imports committed to New England should be no different
    than new internal resources committed to New England; they
    should be mitigated because potential for buyer-side market
    power is high. However, FERC did not provide a blanket
    policy on mitigation of imports as is feasible between new
    and existing internal resources.        In response to the
    “significantly more complicated” task of categorizing new
    and existing import resources, Third Br. of ISO-NE before
    FERC at 44, FERC put into place a workable standard to
    identify those resources that actually support an import and
    28
    therefore should be treated as a new resource. Therefore, we
    defer to its standard.
    Further, the Commission responded to NEPGA’s
    alternative proposal to impose mitigation when only one of
    the two factors is met, and found it would be “contrary to the
    principles of open access and non-discrimination” among
    resources. Fourth Order ¶ 98. Such a system would unfairly
    differentiate between internal and external resources, as well
    as between service provided by new and existing transmission
    facilities. 
    Id. NEPGA disagrees
    with FERC’s open-access and
    discrimination rationales, but cannot demonstrate that they are
    arbitrary and capricious. FERC’s standard on mitigating
    imports was reasoned and supported by the record, namely
    ISO-NE’s undisputed submission that “the ‘new’ versus
    ‘existing’ distinction should be avoided for imports where
    possible, and should be based on more concrete distinctions
    when differentiation is necessary.” Third Br. of ISO-NE
    before FERC at 44 (responding to First Order and Second
    Order). FERC found that it should, in essence, err on the side
    of caution in mitigating import resources, and determined that
    most imports should be treated like existing, rather than new,
    resources. The Commission was aware of, and considered,
    the effect such a decision would have on capacity prices.
    Such a balancing function is precisely the role of expert
    agencies, and the record provides no basis on which FERC’s
    decision should be disturbed.
    C. Supplier-Side Mitigation
    Finally, we turn to the claim by NEPGA and Suppliers
    that FERC improperly constricted the ability of suppliers to
    withdraw from the Forward Capacity Market. FERC, of
    29
    course, contends that its supplier-side mitigation measure—
    lowering the dynamic de-list bid threshold—was also striking
    a balance between interests. We agree.
    We briefly review the dynamic de-list concept. A
    dynamic de-list bid is one allowing a resource to exit an
    auction as the capacity price drops, and is not subject to
    review by the Internal Market Monitor. In the proposals put
    forth here, ISO-NE proposed to lower the threshold price at
    which de-list bids are reviewed by the Internal Market
    Monitor, so that more bids would be reviewed and the
    potential for supplier-side market power would be lessened.
    In its proposal, ISO-NE explained that the existing dynamic
    de-list bid threshold of 0.8 times Cost of New Entry was not
    representative of a resource’s costs. Third Order ¶ 305 (“ISO-
    NE notes that the current threshold of 0.8 [times the Cost of
    New Entry] bears no particular relationship to a resource’s
    opportunity or going forward costs and is a reasonable
    threshold only under the former approach to determining
    zones . . . .”). Without review by the Internal Market
    Monitor, a de-list bid at 0.8 times Cost of New Entry could
    not be assured to be competitive and allowed to set zonal
    prices in an auction.
    To ensure that the Forward Capacity Market is
    competitive, review of bids by the Internal Market Monitor is
    required; thus, suppliers should only be permitted to exit via
    dynamic de-list bids, and escape Internal Market Monitor
    review, at amounts low enough that the exercise of supplier-
    side market power is unlikely. ISO-NE proposed that the
    threshold be set at $1/kilowatt-month instead. It arrived at
    this number using the lowest clearing price of three capacity
    reconfiguration auctions in the New England Market. In a
    reconfiguration auction, resources seeking to reduce their
    capacity supply obligations trade with resources willing to
    30
    take on those obligations. Because reconfiguration auctions,
    unlike the garden-variety capacity auctions thus far discussed,
    have no floor price, a reconfiguration auction’s clearing price
    represents a competitive market price.               Therefore,
    reconfiguration auctions serve as a reasonable proxy for a
    capacity price.
    NEPGA and Suppliers argue that FERC was arbitrary
    and capricious in lowering the de-list threshold: it mitigated
    seller-side market power that it never found existed,
    inappropriately decoupled the de-list threshold from Cost of
    New Entry, and borrowed its structure from a reconfiguration
    auction rather than a capacity auction. FERC’s careful
    consideration of the de-list process survives all these
    complaints.
    The impetus for the Commission’s decision to accept
    ISO-NE’s proposal to lower the de-list bid amount was the
    New England market’s move to a zonal modeling system in
    its capacity market pursuant to the settlement. In this system,
    the market responds to the amount of capacity needed in each
    of New England’s eight load zones.              Internal Market
    Monitoring Unit Review of the Forward Capacity Market
    Auction Results and Design Elements, ISO New England Inc.
    Market Monitoring Unit (June 5, 2009) at 13, 17, available at
    http://iso-
    ne.com/markets/mktmonmit/rpts/other/fcm_report_final.pdf.
    If a zone’s projected capacity is below its requirements, that
    zone is “modeled” as a separate zone and allowed to have a
    higher clearing price in the auction than the rest of the market.
    First Order ¶ 131. As a result, high de-list bids are in the
    position to set clearing prices, but were not reviewed by the
    Internal Market Monitor.
    31
    In undertaking to ensure that rates are just and
    reasonable, the Commission properly lowered the de-list
    threshold. That ISO-NE and the Internal Market Monitor
    agree with this decision underscores its reasonableness. All
    of these parties determined that increased review of de-listing
    is necessary given the move to a zonal modeling system,
    because suppliers are incented to withhold their capacity to
    create a separately modeled zone with a higher clearing price.
    Fourth Order ¶ 123. It is irrelevant that de-list bids were not
    previously wielded as market power because the zoning
    system dramatically changes the Forward Capacity Market.
    The orders’ de-list price of $1/kilowatt-month was also
    reasonable; the threshold reflects one at which supplier-side
    market power is unlikely to be exercised and thus Internal
    Market Monitor review is not necessary, as reflected in the
    reconfiguration auction results.
    In setting this price, FERC agreed with ISO-NE that the
    previous level of 0.8 times Cost of New Entry did not
    represent a competitive de-list bid in the zonal modeling
    version of the Forward Capacity Market, and thus the
    dynamic de-list threshold could be decoupled from the Cost
    of New Entry. Third Order ¶ 315. It responded to parties
    who disagreed and offered its acceptable rationale:
    A resource’s de-list bid is not intended to serve as a
    price stabilizer; it is intended to represent the offer a
    competitive supplier would accept voluntarily to
    commit its resource as a capacity resource. . . . No
    assurance for cost recovery is made for participating in
    competitive markets, only an opportunity to do so.
    
    Id. 32 Finally,
    FERC carefully considered the options for
    auctions to use as a proxy in setting the de-list price. The
    Commission found that a reconfiguration auction was a
    reasonable proxy because it accomplished the goal of finding
    the offer at which “a competitive supplier would accept
    voluntarily to commit its resource as a capacity resource.” 
    Id. ¶¶ 313–15.
    See also Fourth Order ¶ 122.
    The dynamic de-list bid is but one option in a
    constellation of strategies available to a supplier in making
    cost-effective capacity determinations. We note, as did the
    Commission, that Suppliers can still submit de-list bids above
    the threshold, so long as the de-list bids are static and thus
    presented in advance. Third Order ¶ 313. Further, we take
    the Commission at its word that the threshold will be updated
    to account for new information. 
    Id. ¶ 314.
    We hold that FERC’s determination of the dynamic de-
    list threshold, set in agreement with ISO-NE and the Internal
    Market Monitor, was neither arbitrary nor capricious. FERC
    reasonably determined that the zonal modeling system would
    have such an effect on the Forward Capacity Market, and act
    to incent suppliers to exercise market power, that
    preemptively providing for Internal Market Monitor review of
    most bids was the prudent course of action. FERC adequately
    explained why Cost of New Entry has become irrelevant to
    de-list bids, why the reconfiguration auction served as an
    appropriate proxy, and why the de-list price chosen was likely
    to prevent the exercise of supplier-side market power.
    Therefore, the Commission did not err.
    33
    IV. CONCLUSION
    For the foregoing reasons, we deny the petitions for
    review.
    So ordered.