Myersville Citizens for a Rura v. FERC , 783 F.3d 1301 ( 2015 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued October 24, 2014               Decided April 24, 2015
    No. 13-1219
    MYERSVILLE CITIZENS FOR A RURAL COMMUNITY, INC., ET
    AL.,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    DOMINION TRANSMISSION, INC.,
    INTERVENOR
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    Carolyn Elefant argued the cause and filed the briefs for
    petitioners.
    Karin L. Larson, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With her on
    the brief were David L. Morenoff, Acting General Counsel,
    and Robert H. Solomon, Solicitor.
    Catherine E. Stetson argued the cause for intervenor. On
    the brief were J. Patrick Nevins, Christopher T. Handman,
    and Sean Marotta.
    2
    Before: TATEL, MILLETT, and PILLARD, Circuit Judges.
    Opinion for the Court filed by Circuit Judge PILLARD.
    PILLARD, Circuit Judge: Citizens of the small town of
    Myersville, in Frederick County, Maryland, oppose the
    construction of a natural gas facility called a compressor
    station in their town. The compressor station is a small part
    of a larger expansion of natural gas facilities in the
    northeastern United States proposed by Dominion
    Transmission, Inc., a regional natural gas company and
    Intervenor in this case. Dominion, which is in the business of
    storing and transporting natural gas, requested approval from
    the Federal Energy Regulatory Commission to move ahead
    with the project. The Commission, over the objections of the
    Myersville citizens, conditionally approved it in December
    2012. Dominion then fulfilled the Commission’s conditions,
    including obtaining a Clean Air Act permit from the
    Maryland Department of the Environment. Dominion built
    the station, and it has been operating for approximately six
    months.
    The Myersville citizens petition this court to vacate the
    Commission’s order approving the project. They attack the
    Commission’s decision on a number of fronts. They argue
    that the Commission lacked substantial evidence to conclude
    that there was a public need for the project Dominion
    proposed. They assert that the Commission unlawfully
    interfered with Maryland’s rights under the Clean Air Act.
    They challenge the Commission’s environmental review of
    the project, including its consideration of potential
    alternatives. And they claim the Commission unlawfully
    withheld hydraulic flow diagrams from them in violation of
    their due process rights. Because we conclude that each of
    3
    Petitioners’ challenges lacks merit, we deny the petition for
    review.
    I.
    Dominion runs underground natural gas storage and
    transportation facilities in six northeastern and mid-Atlantic
    states. Dominion operates over 947 billion cubic feet of
    storage capacity and approximately 11,000 miles of natural
    gas pipeline. Before it sought the Commission’s approval,
    Dominion conducted an “open season” in which it offered
    contracts for future supply of natural gas to potential
    customers. It entered contracts with two municipal utilities
    and a natural gas distribution company for firm transportation
    and storage services.1 Dominion’s proposed project, called
    the “Allegheny Storage Project,” called for new or expanded
    natural gas facilities in Maryland, Ohio, West Virginia, and
    Pennsylvania, thereby providing to Dominion’s customers an
    additional 115,000 dekatherms per day of firm transportation,
    7.5 billion cubic feet of storage capacity, and 125,000
    dekatherms per day of storage withdrawal at an estimated cost
    of over $112 million.2
    The Project required the building of two compressor
    stations—facilities along a pipeline that compress gas to move
    it through the system at high speeds—and additional pipeline
    to serve the compressors. One of those compressor stations is
    1
    “Firm” transportation service, as opposed to “interruptible”
    service, means the delivery of natural gas is guaranteed regardless
    of the proportion of the pipeline’s capacity that is in use. See
    United Distrib. Cos. v. FERC, 
    88 F.3d 1105
    , 1123 n.10 (D.C. Cir.
    1996).
    2
    A dekatherm is a unit of heat equal to one million British Thermal
    Units, or over one billion joules.
    4
    located on a twenty-one-acre plot in the town of Myersville.
    That compressor station is the subject of this appeal.
    Congress enacted the Natural Gas Act, ch. 556, 
    52 Stat. 821
     (1938) (codified as amended at 
    15 U.S.C. § 717
     et seq.),
    with the “principal purpose” of “encourag[ing] the orderly
    development of plentiful supplies of . . . natural gas at
    reasonable prices,” NAACP v. Fed. Power Comm’n, 
    425 U.S. 662
    , 669-70 (1976).         “[S]ubsidiary” purposes include
    respecting “conservation, environmental, and antitrust”
    limitations. 
    Id.
     at 670 & n.6. The Act vests the Commission
    with authority to regulate the transportation and sale of
    natural gas in interstate commerce, including authority to
    issue certificates permitting the construction or extension of
    natural gas transportation facilities, such as those Dominion
    operates. 15 U.S.C. § 717f(c).
    Before any applicant may construct or extend natural gas
    transportation facilities, it must obtain a “certificate of public
    convenience and necessity” from the Commission pursuant to
    Section 7(c) of the Act.            Id. § 717f(c)(1)(A).      The
    Commission may issue a certificate to “any qualified
    applicant” if it finds that “the applicant is able and willing
    properly to do the acts and to perform the service proposed
    . . . and that the proposed service” and “construction . . . is or
    will be required by the present or future public convenience
    and necessity.” Id. § 717f(e). As part of its certificate
    authority, the Commission has the “power to attach to the
    issuance of the certificate and to the exercise of the rights
    granted thereunder such reasonable terms and conditions as
    the public convenience and necessity may require.” Id.
    Petitioners in this case—Myersville Citizens for a Rural
    Community, Inc. and citizens of Myersville Franz Gerner,
    Ted Cady, and Tammy Mangan—protest the building of the
    5
    Myersville compressor station. During the public comment
    process before the Commission, they raised objections,
    several of which form the basis of the current petition.
    After preparing an Environmental Assessment of the
    Allegheny Storage Project, the Commission rejected the
    objections made by Petitioners and others and granted
    Dominion a conditional Section 7 certificate. Dominion
    Transmission, Inc., 
    141 FERC ¶ 61,240
     (Dec. 20, 2012)
    (“Certificate Order”). The Commission conditioned the
    certificate, in part, on Dominion’s ability to secure all
    necessary federal authorizations, including Clean Air Act
    permits. Certificate Order, App. B, Envtl. Condition 8. After
    considering renewed objections, the Commission denied
    rehearing. Dominion Transmission, Inc., 
    143 FERC ¶ 61,148
    (May 16, 2013) (“Rehearing Order”). The Myersville
    compressor station was placed into service on November 1,
    2014.       FERC, Docket No. CP12-72, Supplemental
    Information Filing Replacing Previous filed In Service
    Notification Request of Dominion Transmission, Inc. under
    CP12-72 (filed Nov. 10, 2014). Petitioners timely petitioned
    for review of the Commission’s orders.
    ***
    We have jurisdiction pursuant to 15 U.S.C. § 717r(b).
    Our review of the Commission’s decision is limited to
    determining whether the order was “arbitrary, capricious, an
    abuse of discretion, or otherwise not in accordance with law.”
    
    5 U.S.C. § 706
    (2)(A); see Minisink Residents for Envtl. Pres.
    & Safety v. FERC, 
    762 F.3d 97
    , 105-06 (D.C. Cir. 2014). “If
    supported by substantial evidence, the Commission’s findings
    of fact are conclusive.” B&J Oil & Gas v. FERC, 
    353 F.3d 71
    , 76 (D.C. Cir. 2004) (citing 15 U.S.C. § 717r(b)). We
    must assure ourselves that the Commission’s “decisionmaking
    6
    is reasoned, principled, and based upon the record.” Am. Gas
    Ass’n v. FERC, 
    593 F.3d 14
    , 19 (D.C. Cir. 2010) (internal
    quotation marks omitted). In so doing, we consider “whether
    the decision was based on a consideration of the relevant
    factors and whether there has been a clear error of judgment.”
    ExxonMobil Gas Mktg. Co. v. FERC, 
    297 F.3d 1071
    , 1083
    (D.C. Cir. 2002). Because the grant or denial of a Section 7
    certificate of public convenience and necessity is a matter
    “peculiarly within the discretion of the Commission,” Okla.
    Natural Gas Co. v. Fed. Power Comm’n, 
    257 F.2d 634
    , 639
    (D.C. Cir. 1958), this court does not “substitute its judgment
    for that of the Commission,” Nat’l Comm. for the New River
    v. FERC, 
    373 F.3d 1323
    , 1327 (D.C. Cir. 2004). Moreover,
    “[w]hen considering FERC’s evaluation of ‘scientific data
    within its technical expertise,’ we afford FERC ‘an extreme
    degree of deference.’” Washington Gas Light Co. v. FERC,
    
    532 F.3d 928
    , 930 (D.C. Cir. 2008) (quoting Nat’l Comm. for
    the New River, Inc., 
    373 F.3d at 1327
    ).
    II.
    Petitioners challenge the Commission’s finding of public
    need for the Project as unsupported by substantial evidence.
    They fault the Commission for approving the Project without
    requiring Dominion to submit its revised agreements with the
    new natural gas customers that subscribed to the added
    capacity. They contend that the absence of current gas
    contracts in the record undermines the Commission’s finding
    that there is a public need for the Project adequate to ensure
    that pre-existing customers will not subsidize it. They also
    claim that the Project will result in an expansion of natural
    gas storage and transportation capacity beyond what
    Dominion disclosed to the Commission.
    7
    The Commission has outlined in a policy statement the
    criteria it considers in determining whether a proposed facility
    will receive a certificate of public convenience and necessity.
    Certification of New Interstate Natural Gas Pipeline
    Facilities, 
    88 FERC ¶ 61,227
     (Sept. 15, 1999), clarified, 
    90 FERC ¶ 61,128
     (Feb. 9, 2000), further clarified, 
    92 FERC ¶ 61,094
     (July 28, 2000). The “threshold” question the
    Commission considers is “whether the project can proceed
    without subsidies from [the applicant’s] existing customers.”
    88 FERC at 61,745. To ensure that a project will not be
    subsidized by existing customers, the applicant must show
    that there is market need for the project. The project must
    “stand on its own financially” through investment by the
    applicant and support from new customers subscribed to the
    expanded capacity through “preconstruction contracts.” Id. at
    61,746; see also 90 FERC at 61,392.
    Provided a project will not be subsidized by existing
    customers, the Commission then balances the “public benefits
    against the potential adverse consequences” of the proposal.
    88 FERC at 61,745. If no adverse effects would stem from
    the project, no balancing is required, and the Commission
    proceeds to environmental review.             Otherwise, the
    Commission balances the adverse effects with the public
    benefits of the project, as measured by an “economic test.”
    Id. Adverse effects may include increased rates for pre-
    existing customers, degradation in service, unfair competition,
    or negative impact on the environment or landowners’
    property. Id. at 61,747-48. Public benefits may include
    “meeting unserved demand, eliminating bottlenecks, access to
    new supplies, lower costs to consumers, providing new
    interconnects that improve the interstate grid, providing
    competitive alternatives, increasing electric reliability, or
    advancing clean air objectives.” Id. at 61,748.
    8
    Applying those criteria, the Commission found that the
    Project would not be subsidized by existing customers and
    that the “minimal” adverse effects were outweighed by the
    public benefits. Certificate Order ¶ 21. In finding a public
    need for the project, the Commission found that “[a]ll of the
    proposed capacity has been subscribed under long-term
    contracts, demonstrating the existence of a market for the
    project.” Id. The Commission concluded that the Project
    would ensure “the ability of two local distribution companies
    [Washington Gas Light Co. and Baltimore Gas & Electric] to
    meet the needs of their overall 1.5 million customers during
    periods of peak demand (i.e., the winter heating season),”
    providing “sufficient justification to authorize the
    construction and operation” of the Project. Id. ¶ 66.
    We review the Commission’s factual findings to ensure
    they are supported by “substantial evidence,” or “such
    relevant evidence as a reasonable mind might accept as
    adequate to support a conclusion.” Colo. Interstate Gas Co.
    v. FERC, 
    599 F.3d 698
    , 704 (D.C. Cir. 2010) (internal
    quotation marks omitted); see also 15 U.S.C. § 717r(b). The
    standard “‘requires more than a scintilla, but can be satisfied
    by something less than a preponderance of the evidence.’”
    Minisink, 762 F.3d at 108 (quoting FPL Energy Me. Hydro
    LLC v. FERC, 
    287 F.3d 1151
    , 1160 (D.C. Cir. 2002)).
    A.
    We first address the Commission’s finding that the
    Project was supported by market need.
    Dominion secured precedent agreements with three
    natural gas customers through the “open season” it conducted
    in the summer of 2007 for what was then called the “Storage
    Factory Project.” Certificate Order ¶ 10. A precedent
    agreement is a long-term contract subscribing to expanded
    9
    natural gas capacity. See, e.g., Process Gas Consumers Grp.
    v. FERC, 
    177 F.3d 995
    , 1000 (D.C. Cir. 1999). Technical
    issues led Dominion to abandon the Storage Factory Project
    in November 2008. Certificate Order ¶ 10 n.8. It revised and
    renamed the project the Allegheny Storage Project. 
    Id.
    Dominion stated in its application that its precedent
    agreements were revised to reflect the changes, and that the
    Allegheny Storage Project was designed “to meet the needs of
    the prospective Storage Factory Project customers.” 
    Id.
    Dominion did not submit those revised precedent agreements
    to the Commission. Instead, it provided a summary of
    relevant terms of the original agreements and the affidavit of
    Dominion’s Director of Gas Business Development stating
    that the Allegheny Storage Project customers had executed
    “binding precedent agreements representing 100% market
    commitment” for fifteen years for the expanded capacity.
    J.A. 96-98.
    Petitioners argue that the Commission’s finding of
    market need was unsupported by substantial evidence because
    Dominion did not submit the revised precedent agreements
    themselves for the record. To the extent that Petitioners argue
    the Commission is legally required to include in the record the
    most current version of precedent agreements in order to find
    that a project is supported by market need, that argument was
    not preserved for appeal. See 15 U.S.C. § 717r(b) (“No
    objection to the order of the Commission shall be considered
    by the court unless such objection shall have been urged
    before the Commission in the application for rehearing unless
    there is reasonable ground for failure so to do.”). Petitioners
    did not argue before the Commission that it lacks the
    authority to find public need unless the most current
    precedent agreements, as distinct from other evidence of
    demand, are in the administrative record. The closest they
    came was in a request for rehearing, where, in a footnote, they
    10
    stated: “It should be noted that there do[ ] not appear to be
    even sample or generic precedent agreements available in the
    public record.” J.A. 467 n.20. That did not adequately raise
    the issue, and, in any case, we need not consider arguments
    “tucked away in a footnote” in a request for rehearing. North
    Carolina v. FERC, 
    112 F.3d 1175
    , 1192 (D.C. Cir. 1997); see
    also Washington Legal Clinic for the Homeless v. Barry, 
    107 F.3d 32
    , 39 (D.C. Cir. 1997).
    Petitioners nonetheless preserved the more case-specific
    version of the argument: that the absence of the updated
    precedent agreements from this particular administrative
    record rendered the Commission’s factual finding that the
    Project was fully subscribed unsupported by substantial
    evidence. Petitioners argued on rehearing that the agreements
    were “out of date” and that they “relate to a completely
    different project so at best, they demonstrate only a need for
    the Storage Factory Project, not for the [Allegheny Storage
    Project].” J.A. 467. In denying rehearing, the Commission
    addressed and rejected that argument. See Rehearing Order
    ¶ 30 n.29. It was therefore preserved for review.
    Petitioners’ challenge to the Commission’s finding of
    market need fails on the record even in the absence of the
    updated precedent agreements. In addition to the sworn
    affidavit stating that the Project was fully subscribed, the
    Commission had before it motions to intervene filed by the
    two customers subscribed to the new natural gas
    transportation service and the bulk of the storage service. J.A.
    123, 571. Both customers restated the amount of added
    capacity expected from the Project and identified themselves
    as the customers of that added capacity. While they did not
    identify how it would be allocated between them, Dominion’s
    customers nevertheless made clear under oath that they had
    subscribed to the capacity Dominion proposed to add to its
    11
    natural gas infrastructure. Consistent with its Certificate
    Policy Statement, and based on the evidence before it, the
    Commission concluded that Dominion had adequately
    demonstrated market need. Applying our standard of review,
    in light of the facts taken together, we conclude that the
    Commission’s finding was supported by substantial evidence,
    despite the absence of more specifics on the revised precedent
    agreements.
    Contrary to Petitioners’ assertion, this case therefore does
    not resemble Bangor Hydro-Electric Co. v. FERC, 
    78 F.3d 659
    , 664 (D.C. Cir. 1996), where we held that the agency
    could not rely on a report outside the record in defending its
    factual findings, nor does it present a lack of evidence or
    reasoned findings such as was at issue in Atlantic Refining
    Co. v. Public Service Commission, 
    360 U.S. 378
     (1959). The
    Commission here does not attempt to rely on non-record
    evidence, nor did it lack sufficient evidence; instead, it argues
    that the affidavit and motions to intervene constituted
    substantial evidence to conclude that the Project was fully
    subscribed pursuant to precedent agreements. We agree.
    Even assuming the precedent agreements were executed
    and the Project is fully subscribed, Petitioners urge us to
    consider a market study showing declining demand for natural
    gas as evidence of insufficient market demand.           The
    Commission considered that same study, but found that it did
    not warrant a finding of lack of public need for two reasons.
    First, for a variety of reasons related to the nature of the
    market, “it is Commission policy to not look behind precedent
    or service agreements to make judgments about the needs of
    individual shippers.” Certificate Order ¶ 66. In keeping with
    its policy, the Commission concluded that the evidence that
    the Project was fully subscribed was adequate to support the
    finding of market need. Rehearing Order ¶ 30. It is the case
    12
    here, as it was in Minisink, that “Petitioners identify nothing
    in the policy statement or in any precedent construing it to
    suggest that it requires, rather than permits, the Commission
    to assess a project’s benefits by looking beyond the market
    need reflected by the applicant’s existing contracts with
    shippers.” 762 F.3d at 111 n.10.
    Second, even if the market study were relevant, the
    Commission found it unpersuasive because the study
    “provide[s] general overviews of demand by sector (that is,
    residential vs. industrial consumption), as well as general
    overviews of domestic inventories which are tied to weather
    extremes. The studies do not demonstrate that there is a
    decline in demand for natural gas in the markets which the
    Allegheny Storage Project is intended to serve.” Rehearing
    Order ¶ 31.       The petition does not respond to the
    Commission’s analysis. We therefore see no reason to disturb
    the Commission’s well reasoned finding.
    B.
    Petitioners also attack the Project as unsupported by
    market need because, in their view, there is evidence that
    Dominion designed the Project to add capacity to its natural
    gas infrastructure beyond the amount disclosed in its
    application—that is, that the Project would be “overbuilt.”
    Even assuming that the precedent agreements were executed
    by Dominion’s customers, Petitioners argue, the Project as
    proposed would produce excess capacity.
    To “[o]verbuild” an energy project means to “build
    capacity for which there is not a demonstrated market need.”
    90 FERC at 61,391. Petitioners have no clear evidence that
    the Project is overbuilt, but they believe there are grounds to
    infer that Dominion’s Myersville compressor station is larger
    and more powerful than it needs to be. In particular, they
    13
    argue that the 16,000 horsepower Myersville compressor
    station is more powerful than the 14,000 horsepower
    Middletown station originally proposed in connection with
    the Storage Factory Project—Dominion’s predecessor to the
    Allegheny Storage Project—and therefore is meant to provide
    more service than originally proposed. Petitioners provide no
    evidence beyond the difference in horsepower to substantiate
    that claim, and they do not explain how the size and power of
    a compressor station relates to the total capacity added to the
    natural gas network.
    As is evident from the structure of the natural gas system
    and the purpose of a compressor, a difference in horsepower
    does not necessarily mean a difference in storage and
    transportation capacity. A compressor station “‘boost[s] the
    system pressure’ along pipelines in order to ‘maintain
    required flow rates.’” Dominion Transmission, Inc. v.
    Summers, 
    723 F.3d 238
    , 241 (D.C. Cir. 2013) (alterations in
    original) (citing FERC, An Interstate Natural Gas Facility On
    My Land? What Do I Need To Know? 22 (2010)). Simply
    put, gas in a pipeline requires compression, or pressure, to
    keep it moving at desired rates. Given the capacity added by
    the Allegheny Storage Project to its pipeline network,
    Dominion identified a twelve-mile corridor between a
    compressor station in Chambersburg, Pennsylvania and
    another in Leesburg, Virginia where a new compressor station
    would have to be sited in order to maintain adequate natural
    gas pressure. J.A. 236. The Commission “independently
    analyzed the hydraulic corridor and [Dominion’s] associated
    assumptions and determined that they were accurate for the
    12-mile range.” 
    Id.
    Myersville falls along that twelve-mile corridor, as did
    several possible alternative sites the Commission considered
    in its Environmental Assessment, including some other sites
    14
    in Myersville. One of the alternatives was the site proposed
    in the Storage Factory Project for a compressor station in
    nearby Middletown, Maryland.             The Commission’s
    Environmental Assessment demonstrates the many
    differences between the two proposed sites, including that the
    Middletown station would need a 14,000 horsepower
    compressor to maintain adequate pressure, whereas the
    Myersville station would need a 16,000 horsepower
    compressor due to its different placement. J.A. 237.
    Petitioners seek to compare the two compressors in a
    vacuum, without regard to their different geographic
    placements and other changes necessitated by Dominion’s
    overall shift from the original Storage Factory Project. The
    Myersville station is one of several interconnected facilities in
    a larger network, as was the proposed Middletown station.
    Petitioners have only pointed to the horsepower difference
    without explanation. The change in horsepower does not,
    however, provide a basis for this court to conclude that the
    Commission’s finding that the station is not overbuilt was
    unsupported by substantial evidence. A change in one aspect
    of one facility as a result of the revision of the Project says
    nothing about the overall storage and transportation capacity
    the Project will add to Dominion’s pipeline network. We see
    no basis upon which to overturn the Commission’s finding.
    Similarly, Petitioners’ claim that “Dominion intends to
    use the facility for a purpose other than that stated in its
    application,” i.e. “to export gas through Dominion’s Cove
    Point liquefied natural gas (LNG) export facility in Calvert
    County, Maryland. Pet’rs’ Br. 29-30. Petitioners’ argument
    stems from their review of hydraulic flow diagrams filed
    confidentially with the Commission (and not in the record on
    appeal). They believe the flow diagrams demonstrate that
    natural gas that passes through Myersville will ultimately
    15
    make it to the Cove Point LNG Terminal. If that is the case,
    they claim, it undermines Dominion’s application for a
    Section 7 certificate, which sought to expand domestic natural
    gas capacity, not add to Dominion’s export capacity.
    The Commission has repeatedly rejected Petitioners’
    argument that the Project was built, at least in part, to export
    natural gas through Cove Point, concluding that the
    Allegheny Storage Project “is not associated in any way with
    the Cove Point LNG Terminal or potential export authority at
    the terminal.” Rehearing Order ¶ 33. First, in its Certificate
    Order, the Commission concluded that Petitioners’ reading of
    the flow diagrams “overlooks the fact that Washington Gas
    [one of the customers of the Allegheny Storage Project] has
    numerous delivery points off the Dominion Cove Point
    Pipeline,” which explains why the Cove Point Pipeline is
    associated with the Allegheny Storage Project. Certificate
    Order ¶ 161 n.109. It also noted that Petitioners’ reading was
    inaccurate because it sought to “compare design day
    (contractual obligation) flow with non-coincidental peak
    deliveries; such comparisons are not valid.” 
    Id.
     In denying
    rehearing, the Commission further explained that
    [a]lthough a pipeline is constructed to meet contracted
    peak demands during periods of 100 percent load
    conditions, customers are not required to, and rarely
    do, use 100 percent of their contracted capacity every
    day of the year. This means that on any given day
    there may well be unutilized capacity in a pipeline.
    However, such capacity can be used to satisfy
    additional demand on an interruptible and short term
    firm basis.
    Rehearing Order ¶ 32. Acknowledging that Dominion had
    recently filed an application to, “among other things,
    16
    construct, modify, own and operate certain facilities to enable
    the liquefaction of natural gas for export at its existing Cove
    Point LNG terminal,” the Commission added that “Dominion
    Cove Point LNG’s application does not indicate that the
    Myersville Compressor Station is needed to support the
    export of the liquefied natural gas.” 
    Id.
     ¶ 33 n.31.
    The Commission’s analysis is thorough and persuasive.
    In order to ensure adequate pressure during periods when all
    of the capacity required by the precedent agreements is being
    used, i.e., during periods of peak demand, a compressor
    station somewhere along the twelve-mile corridor that
    includes Myersville must be built. But, as Dominion
    explained at oral argument, natural gas molecules are not
    stamped with a destination when they enter an interstate
    pipeline. Oral Arg. Tr. 33. Nor can each molecule be traced
    from entry to exit. When the precedent agreement customers
    are not using their full capacity, and the compressor station is
    not working at full power, “there may well be unutilized
    capacity in a pipeline,” which could “satisfy additional
    demand on an interruptible and short term firm basis.”
    Rehearing Order ¶ 32. And because one of those customers,
    Washington Gas Light, has delivery points along a pipeline
    that ends at the Cove Point LNG terminal, when Washington
    Gas is not using full capacity, some gas that passes through
    Myersville may reach the Cove Point LNG Terminal. That
    does not imply that the compressor station is too large,
    because it says nothing about the horsepower needed to keep
    the system functioning when Dominion’s customers use all of
    their contractually guaranteed capacity. Those realities
    associated with fluctuating customer demand and the pooled
    character of gas within the pipeline system do not vitiate the
    public need for the Project. Petitioners provide no response to
    the Commission’s explanation of the flow diagrams, instead
    reiterating that the Commission has misread them.
    17
    Petitioners also point to what they perceive to be new
    evidence in support of their contention that the Project’s
    capacity exceeds market need. After briefing in this case was
    completed, the Commission issued an order granting
    Dominion’s separate Cove Point application. Dominion Cove
    Point LNG, LP, 
    148 FERC ¶ 61,244
    , 
    2014 WL 4854467
    (Sept. 29, 2014). Petitioners submitted the Cove Point
    certificate order as supplemental authority for their argument
    that the Myersville compressor station is designed to help
    provide excess capacity to Cove Point for export, and hence,
    overbuilt. We disagree with Petitioners’ inference from the
    Cove Point order because that order is entirely consistent with
    the two orders we review in this case.
    After completion of the Cove Point LNG export project,
    the expansion or modification of existing compressor stations
    in Virginia, “together with the use of capacity from a
    terminated contract,” will enable Dominion to transport up to
    860,000 dekatherms per day of natural gas on a firm basis to
    the Cove Point terminal for export to customers it has already
    secured. Id. at *3. Commenters in that proceeding raised the
    question whether the Allegheny Storage Project will result in
    added capacity exported through Cove Point.                The
    Commission reiterated the position it took in this case: The
    Allegheny Storage Project “significantly predated the Cove
    Point Liquefaction Project and is not in any way connected
    with it.” Id. at *56. It repeated that Washington Gas has
    delivery points located on the Cove Point Pipeline, that the
    Myersville compressor station is required for periods of peak
    demand, and that the Commission’s independent hydraulic
    analysis demonstrates that the two projects are separate and
    unrelated.     Id. at *56-60.        The Commission also
    acknowledged, as it did in this case, that during non-peak
    times, depending on a number of factors, Dominion “may be
    able to provide additional gas supplies, if nominated, to the
    18
    Dominion Cove Point Pipeline for liquefaction. This situation
    is no different than operating conditions on other Commission
    regulated pipeline facilities.” Id. at *58.
    In sum, Petitioners have not shown that the Commission
    was required to disapprove the Myersville compressor station
    on the ground that it would be overbuilt. Faced with
    Petitioners’ challenge, we need only assure ourselves that the
    Commission’s decision making is “reasoned, principled, and
    based upon the record.” Am. Gas Ass’n, 
    593 F.3d at 19
    (internal quotation marks omitted).          We review the
    Commission’s decision in light of its broad discretion in
    determining whether a particular project is supported by
    public convenience and necessity, see Okla. Natural Gas Co.,
    
    257 F.2d at 639
    , and we must afford an “extreme degree of
    deference” to the Commission’s scientific analysis,
    Washington Gas Light, 
    532 F.3d at 930
     (internal quotation
    marks omitted). In light of the Commission’s well supported
    and thoroughly reasoned finding that the Myersville
    compressor station appropriately responds to market need and
    is not overbuilt, and Petitioners’ failure to adduce evidence
    convincingly contradicting that finding, we hold that the
    Commission’s decision to issue a Section 7 certificate of
    public convenience and necessity was supported by
    substantial evidence.
    III.
    The Natural Gas Act occupies the field of interstate
    natural gas transportation and sale, largely to the exclusion of
    state law. The Act confers on the Commission “exclusive
    jurisdiction” over transportation and sale, as well as over the
    rates and facilities of natural gas companies engaged in
    transportation and sale. See, e.g., Schneidewind v. ANR
    Pipeline Co., 
    485 U.S. 293
    , 306-08 (1988); N. Natural Gas
    19
    Co. v. Iowa Utils. Bd., 
    377 F.3d 817
    , 821 (8th Cir. 2004);
    Nat’l Fuel Gas Supply Corp. v. Pub. Serv. Comm’n, 
    894 F.2d 571
    , 576 (2d Cir. 1990). However, the Commission’s power
    to preempt state and local law is circumscribed by the Natural
    Gas Act’s savings clause, which saves from preemption the
    “rights of States” under the Clean Air Act and two other
    statutes.3 15 U.S.C. § 717b(d); see also 
    42 U.S.C. § 7401
     et
    seq. (Clean Air Act). Petitioners argue that the Commission’s
    issuance of a Section 7 certificate to Dominion conditioned on
    its subsequent receipt of an air quality permit under the Clean
    Air Act violated either provisions of the Natural Gas Act itself
    or provisions of the Clean Air Act that the Natural Gas Act’s
    savings clause preserved.
    The parties do not address the standard of review we
    should apply in evaluating the Commission’s authority to
    issue the challenged certificate of public convenience and
    necessity. We have previously reviewed the Commission’s
    interpretation of its authority to issue such a certificate by
    applying the two-step analytical framework of Chevron
    U.S.A. Inc. v. NRDC, 
    467 U.S. 837
     (1984). See Okla. Natural
    Gas Co. v. FERC, 
    28 F.3d 1281
    , 1283-84 (D.C. Cir. 1994); N.
    Natural Gas Co. v. FERC, 
    827 F.2d 779
    , 784 (D.C. Cir.
    1987). We find the Commission’s interpretation not only
    reasonable but persuasive and hold that its certificate order
    did not violate the savings clause or any of the other statutory
    provisions Petitioners identified.
    3
    The other two statutes are the Coastal Zone Management Act of
    1972, 
    16 U.S.C. § 1451
     et seq., and the Clean Water Act, 
    33 U.S.C. § 1251
     et seq.
    20
    A.
    Dominion, as an intervenor in this proceeding, asserts
    that Petitioners lack “prudential standing” to argue that the
    Commission violated the Natural Gas Act’s savings clause.
    Petitioners live in Myersville near the compressor station and
    claim they are affected by its construction and operation
    because of the effect it will have on their property values, its
    impact on the environment, the safety hazards they believe the
    facility poses, the noise it produces, and the aesthetic
    “eyesore” it presents. See Pet’rs’ Br. 21-22 & add. 47-54.
    Dominion argues that Petitioners cannot complain about the
    Commission’s encroachment on Maryland’s Clean Air Act
    rights because they are not within the “zone of interests” of
    the savings clause they seek to enforce. We disagree.
    The Supreme Court’s recent decision in Lexmark Int’l,
    Inc. v. Static Control Components, Inc., 
    134 S. Ct. 1377
    , 1387
    (2014), clarifies that “‘prudential standing is a misnomer’ as
    applied to the zone-of-interests analysis.” 
    Id.
     (quoting Ass’n
    of Battery Recyclers, Inc. v. EPA, 
    716 F.3d 667
    , 675-76 (D.C.
    Cir. 2013) (Silberman, J. concurring)). The zone of interests
    test simply “requires us to determine, using traditional tools of
    statutory interpretation, whether a legislatively conferred
    cause of action encompasses a particular plaintiff’s claim.”
    
    Id.
     “[W]e presume that a statutory cause of action extends
    only to plaintiffs whose interests fall within the zone of
    interests protected by the law invoked.” Id. at 1388 (internal
    quotation marks omitted). The test is “lenient” and “not
    especially demanding.” Id. at 1389 (internal quotation marks
    omitted). In addition, “we generally presume that a statutory
    cause of action is limited to plaintiffs whose injuries are
    proximately caused by violations of the statute.” Id. at 1390.
    The petition before us easily fits within both of the
    presumptions Lexmark identifies, and, indeed, Dominion does
    21
    not dispute that Petitioners’ claimed injuries are proximately
    caused by the Commission’s approval of the Project.
    Relying on our statement in Grand Council of Crees v.
    FERC, 
    198 F.3d 950
    , 956 (D.C. Cir. 2000), that the zone of
    interests is to be determined “‘by reference to the particular
    provision of law upon which the plaintiff relies,’” 
    id.
     (quoting
    Bennett v. Spear, 
    520 U.S. 154
    , 175-76 (1997)), Dominion
    argues that Petitioners “rely” on the Natural Gas Act’s
    savings clause in arguing that the Commission acted
    unlawfully. Because Petitioners’ interests fall outside the
    “rights of States” protected by the savings clause, asserts
    Dominion, they fail the zone of interests test.
    Dominion, however, understates the interests “arguably
    within the zone of interests to be protected or regulated” by
    the relevant provisions of the Natural Gas Act and the Clean
    Air Act. Id. at 954 (internal quotation marks omitted). The
    zone of interests test is not demanding. See id. at 955. A
    would-be plaintiff is outside the statute’s “zone of interests”
    only if “the plaintiff’s ‘interests are so marginally related to or
    inconsistent with the purposes implicit in the statute that it
    cannot reasonably be assumed that Congress intended to
    permit the suit.’” Match-E-Be-Nash-She-Wish Band of
    Pottawatomi Indians v. Patchak, 
    132 S. Ct. 2199
    , 2210 (2012)
    (quoting Clarke v. Securities Indus. Ass’n, 
    479 U.S. 388
    , 399
    (1987)). Petitioners here rely on provisions focused primarily
    on the preservation of state and local authority in the fields of
    environmental and land use regulation, and it is precisely
    injuries in those domains that Petitioners assert. The statutory
    provision at issue, moreover, need not be intended to benefit
    Petitioners; it is sufficient that the interest asserted arguably
    falls within the provision’s scope. 
    Id.
     at 2210 & n.7. The
    environmental injuries asserted by Petitioners suffice to bring
    a claim under the provisions of the Natural Gas Act and the
    22
    Clean Air Act they cite. We are not empowered to decline for
    prudential reasons to hear their claim.
    Finally, we reject Dominion’s reliance on Delaware
    Department of Natural Resources & Environmental Control
    v. FERC, 
    558 F.3d 575
     (D.C. Cir. 2009), for the proposition
    that Plaintiffs lack Article III standing. There, we held that
    Delaware lacked Article III standing because it asserted only
    a “procedural injury” that was not accompanied by a
    “concrete substantive interest.” 
    Id. at 578-79
    . Importantly,
    Delaware identified no prejudice from the Commission’s
    having approved a project before Delaware had completed its
    regulatory process under the Coastal Zone Management Act
    and the Clean Air Act, other than the potential for “intense
    political pressure to acquiesce in the Commission’s
    conditional approval,” which we held was not a cognizable
    injury. 
    Id. at 578
    . In contrast to Delaware, Petitioners in this
    case have alleged various concrete injuries that they contend
    flow from the siting of the compressor station, including
    depressed property values, increased noise and air pollution,
    visual blight, and heightened safety risks. Their claims are
    not merely political or procedural. Petitioners have asserted a
    cognizable injury in fact stemming from the allegedly
    unlawful approval of the Project that is redressable through
    judicial review of the Commission’s order.
    B.
    Turning to the merits, we begin by reviewing the
    regulatory background and Dominion Transmission, Inc. v.
    Summers, our earlier decision relating to the project at issue
    here. See 723 F.3d at 238.
    The Clean Air Act “is an exercise in cooperative
    federalism.” Id. at 240. The Environmental Protection
    Agency promulgates air quality standards, and the states, if
    23
    they wish, adopt state implementation plans (SIPs)
    “‘providing for the implementation, maintenance, and
    enforcement of’” those air quality standards; “‘such plans are
    then submitted to EPA for approval.’” Id. (quoting Michigan
    v. EPA, 
    213 F.3d 663
    , 669 (D.C. Cir. 2000)); see also 
    42 U.S.C. § 7410
    (a). Maryland’s SIP, incorporated by reference
    in the Code of Federal Regulations, 
    40 C.F.R. § 52.1070
    ,
    includes Maryland Code Section 2-404, a provision of the
    state’s environmental law that governs permits to construct
    emissions sources such as the Myersville compressor station.
    Section 2-404(b)(1) prohibits the Maryland Department of the
    Environment (MDE) from accepting an application for an air
    quality permit unless the applicant submits documentation:
    (i) That demonstrates that the proposal has been
    approved by the local jurisdiction for all zoning and
    land use requirements; or
    (ii) That the source meets all applicable zoning and
    land use requirements.
    In the summer of 2012, pursuant to Section 2-404(b)(1),
    the MDE refused to process Dominion’s permit application
    because the compressor station had not “been approved by the
    local jurisdiction for all zoning and land use requirements”
    nor, in its view, had Dominion shown that the station “meets
    all applicable zoning and land use requirements.” Summers,
    723 F.3d at 241. Shortly thereafter, Myersville denied zoning
    approval for the proposed Myersville compressor station. Id.
    at 241-42. The Commission then issued its certificate order
    conditionally approving the Project. Id. at 242. “[W]ith
    FERC’s certificate in hand, Dominion applied to the [MDE]
    once again for an air quality permit. Its cover letter stated it
    now satisfied § 2-404(b)(1) because all local zoning and land
    use requirements had been preempted by FERC’s certificate
    24
    and were therefore not ‘applicable.’” Id. The MDE again
    refused to process the application. Id.
    Dominion then petitioned this Court to review
    Maryland’s refusal to issue an air quality permit for a facility
    conditionally approved by the Commission. In Summers, we
    agreed with Maryland that Section 2-404(b)(1) formed a part
    of Maryland’s SIP. Id. Consequently, by virtue of the
    Natural Gas Act’s savings clause, we held that the
    Commission’s certificate order approving the Allegheny
    Storage Project did not preempt Section 2-404(b)(1), and that
    the MDE was entitled to enforce it. Id. at 243-44.
    We also held, however, that the MDE failed to enforce
    Section 2-404(b)(1) according to its terms. The MDE argued
    that it could refuse to process Dominion’s permit application
    until Myersville granted the compressor station zoning
    approval. Id. at 244. We disagreed because the Natural Gas
    Act requires a state agency “to issue, condition, or deny”
    permits that federal law requires for subject facilities, and not
    merely to refuse to act on a permit application. 15 U.S.C.
    § 717r(d)(2). MDE contended that Dominion had not
    satisfied Maryland’s SIP because it had not shown that it had
    met all applicable zoning and land use requirements by
    merely submitting its own letter claiming compliance; a letter
    from the local authorities, it claimed, was necessary.
    Summers, 723 F.3d at 244. We held, however, that “the plain
    meaning of § 2-404(b) . . . expressly permits the applicant to
    avoid involvement by the local zoning authority altogether,”
    so requiring their written statement was contrary to law. Id. at
    244-45. We reasoned that the use of the phrase “meets all
    applicable zoning and land use requirements,” as an
    alternative to the subsection specifically referencing local
    approval, admitted the possibility that some such
    requirements might be satisfied other than by obtaining
    25
    affirmative approval from the local authorities. Id. at 245.
    Dominion’s documentation might, for example, show that it
    had in fact met all the local requirements. We also considered
    the possibility that Section 2-404(b)(1)(ii) might, despite the
    savings clause preserving the “rights of States” under the
    Clean Air Act, be designed to invite some amount of
    preemption of those rights by the Natural Gas Act, rendering
    any preempted rights no longer “applicable.” It thus struck us
    as at least plausible that, as a matter of Maryland law,
    Dominion might, without local approval in hand, “meet” all
    or some of whatever local requirements were “applicable.”
    Id. We held that the MDE could not refuse to process an
    application without first evaluating which local laws were
    “applicable,” and which were not. Id.
    Importantly, however, we declined to determine in the
    first instance the scope of any preemption that may have been
    effected by the Commission’s certificate order. In its order,
    the Commission had done the same thing, choosing to defer to
    Maryland to determine whether the Commission’s order had
    any effect on the applicability of Myersville’s local zoning
    laws. See Certificate Order ¶ 71. We thus remanded to the
    MDE to “either identify one or more ‘applicable’ (that is, not
    preempted) zoning or land use requirements with which
    Dominion has not demonstrated compliance, or . . . process
    Dominion’s application for an air quality permit.” Summers,
    723 F.3d at 245.
    On remand, the MDE concluded that the “only
    Myersville zoning or land use regulation that is applicable,
    i.e., not preempted by the Natural Gas Act, is a requirement
    for submission of a construction site plan to the Town.”
    Resp. to Comments for the Dominion Transmission, Inc.
    Natural Gas Compressor Station, Md. Dept. Env. Docket No.
    20-13, Permit Nos. 021-0707-5-0460 & -0461, at 3-4 (Jan. 16,
    26
    2014), available at http://www.mde.state.md.us/programs
    /Permits/AirManagementPermits/Documents/DTIResponseto
    Comments%20(1).pdf. Because Dominion had complied with
    the site plan requirement, the MDE processed Dominion’s air
    quality permit application; the MDE then approved the
    application and issued an air quality permit on June 10, 2014.4
    Dominion Rule 28(j) Letter, Ex. A (filed June 24, 2014).
    4
    The issuance of the air quality permit, after briefing in this case,
    rendered moot two arguments Petitioners made based on the Clean
    Air Act. First, they argued that the Commission could not approve
    a facility before an air quality permit issued because, if the state
    were to deny the requisite permit, the facility “may never be built.”
    Pet’rs’ Br. 32. Second, they argued that the Commission could not
    measure the compressor station’s potential to emit based on a 6000
    hour-per-year limitation that had not been incorporated into an
    enforceable air quality permit. Pet’rs’ Br. 36. The air quality
    permit that the MDE has now issued for the construction of the
    Myersville compressor station incorporated that 6000 hour-per-year
    limitation. Both of those arguments are now moot. See, e.g.,
    Schering Corp. v. Shalala, 
    995 F.2d 1103
    , 1105 (D.C. Cir. 1993)
    (citing Los Angeles Cnty. v. Davis, 
    440 U.S. 625
    , 631 (1979)). To
    the extent that Petitioners challenge the Commission’s assessment
    of the compressor station’s air quality impact more generally, the
    Commission’s Environmental Assessment reflects that the
    Commission reviewed modeling performed by Dominion and
    agreed that, for a range of pollutants, the Myersville compressor
    station would not have a significant air quality impact or would
    otherwise be below the National Ambient Air Quality Standards.
    See Certificate Order ¶ 111, J.A. 206-07. Other than the now moot
    objection to the 6000 hours-per-year cap, Petitioners do not
    meaningfully challenge that analysis.
    27
    C.
    Petitioners point to two statutory bases for their challenge
    to the Commission’s ability to issue a Section 7 certificate
    conditioned on an applicant’s subsequent receipt of the
    requisite air quality permit. Neither supports their argument.
    First, they note that, to issue a certificate of public
    convenience and necessity, the Commission must conclude
    that the applicant is “able and willing properly to do the acts
    and to perform the service proposed and to conform to the
    provisions of this chapter and the requirements, rules, and
    regulations of the Commission thereunder.” 15 U.S.C.
    § 717f(e). That provision requires nothing more than a
    finding that the applicant is “able and willing” to comply with
    the Natural Gas Act and the “requirements, rules, and
    regulations” promulgated thereunder. Petitioners have not
    identified any requirement under the Natural Gas Act that
    Dominion could not satisfy. As for the Clean Air Act permit
    specifically, it is clear that Dominion was “able and willing”
    to do so; indeed, it did.
    Second, Petitioners claim that the Commission’s
    certificate “undermines the Clean Air Act as well,” because
    the Clean Air Act “expressly preserves local authority.”
    Pet’rs’ Br. 34. But the provision on which they rely, 
    42 U.S.C. § 7431
    , states only that “[n]othing in [the Clean Air
    Act] constitutes an infringement on the existing authority of
    counties and cities to plan or control land use.” It does not
    purport to constrain the Commission beyond the constraints
    already provided by the Natural Gas Act and the Clean Air
    Act.5
    5
    An arguably relevant provision of the Clean Air Act, cited only by
    the Commission, is 
    42 U.S.C. § 7506
    (c)(1), which provides that
    28
    The lack of those claimed legal prohibitions against the
    Commission issuing a conditional certificate does not resolve
    what effect, if any, that certificate might have on Maryland’s
    decision whether and on what terms to issue an air quality
    permit. The Commission’s power to preempt state and local
    regulation by approving the construction of natural gas
    facilities is limited by the Natural Gas Act’s savings clause,
    which provides that the Natural Gas Act’s terms must not be
    construed to “affect[] the rights of States” under the Clean Air
    Act. 15 U.S.C. § 717b(d)(2). Invoking our decision in
    Summers, Petitioners assert that the Commission affected
    Maryland’s Clean Air Act rights because its certificate order
    preempted then-“applicable” zoning and land use
    requirements, removing them as obstacles to Dominion’s air
    quality permit. Had the Commission’s conditional certificate
    not issued unless and until Maryland granted the requisite
    Clean Air Act permit, Petitioners argue, Dominion could not
    have secured the permit. In thus “affect[ing] the rights of”
    Maryland under the Clean Air Act, contend Petitioners, the
    Commission violated the savings clause.
    “[n]o department, agency, or instrumentality of the Federal
    Government shall engage in, support in any way or provide
    financial assistance for, license or permit, or approve, any activity
    which does not conform to an implementation plan after it has been
    approved or promulgated under section 7410 of this title.” It
    appears the Commission decided that it was not required to perform
    a § 7506 general conformity determination.             J.A. 211-12.
    Petitioners have not challenged that decision, so we decline to
    address it and express no opinion on whether § 7506 affects the
    Commission’s authority to issue Section 7 certificates conditioned
    on the receipt of air quality permits. See 
    40 C.F.R. §§ 93.153
    (applicability of conformity determination requirement), 93.158
    (criteria for determining conformity).
    29
    We conclude that the effect Petitioners complain of is
    illusory, premised on a misunderstanding of our Summers
    decision, the statutory scheme, and the operation of
    preemption in this case. While Petitioners claim that the
    Commission’s Section 7 certificate had the effect of
    unlawfully influencing the MDE’s consideration of
    Dominion’s application for an air quality permit, their
    objections largely boil down to a challenge to the MDE’s
    decision regarding the preemptive interaction between the
    certificate and the relevant provisions of Maryland law, not to
    the Commission’s freestanding authority to issue a
    conditional certificate. The propriety of the MDE’s decision,
    however, is not properly before this court.
    Maryland’s rights under the Clean Air Act are those that
    it can exercise under its SIP.6 Cf. AES Sparrows Point LNG,
    LLC v. Smith, 
    527 F.3d 120
    , 126 (4th Cir. 2008) (holding
    “rights of States” under Coastal Zone Management Act are
    those rights that states can “exercise” under their Coastal
    Management Plans, analogues to Clean Air Act SIPs). While
    the Commission’s certificate order set forth the preemption
    standard as the Commission understands it, the Commission
    did not purport to preempt any local law, nor any portion of
    Maryland’s SIP. Indeed, it did not even identify whether any
    conflict with state or local law existed, as it explicitly
    declined to interpret “local, state and federal laws that are
    outside of the Commission’s jurisdiction.” Certificate Order
    ¶ 71 (“[T]he Maryland state and local agencies retain full
    authority to grant or deny air quality permits; if the State of
    6
    To the extent Petitioners’ claim rests on an assumption that the
    “rights of States” under the Clean Air Act extend beyond their
    power to enforce the provisions of their SIPs, no party has briefed
    the argument, and we decline to address it. See Ark Las Vegas Rest.
    Corp. v. NLRB, 
    334 F.3d 99
    , 108 n.4 (D.C. Cir. 2003).
    30
    Maryland rejects [Dominion’s] air quality permit application,
    or refuses to process it, then it is up to [Dominion] to
    determine how it wishes to proceed.”). In addition, the
    Commission conditioned the certificate on Dominion’s ability
    to secure all necessary federal authorizations, including the
    requisite federal Clean Air Act air quality permit obtainable
    from the MDE. Certificate Order, App. B, Env’l Condition 8.
    We, too, declined in Summers to determine the scope of
    any preemption that might have been effectuated by the
    Commission’s certificate order. We recognized that Section
    2-404(b)(1) is part of Maryland’s SIP, and therefore saved
    from preemption. We also decided, however, that the MDE
    was “better situated” to interpret the SIP and determine in the
    first instance the scope of the Natural Gas Act’s preemptive
    footprint and the extent to which local land use and zoning
    law is incorporated into Maryland’s SIP, and thereby shielded
    from preemption by the Natural Gas Act’s savings clause.
    723 F.3d at 245.
    In Summers, Dominion argued that Section 2-
    404(b)(1)(ii) does not incorporate any local land use laws in a
    way that would save them from preemption by the
    Commission. Rather, Dominion argued, the provision refers
    only to “applicable” laws because it anticipates the possibility
    that some laws will not be “applicable” by virtue of
    preemption. Petitioners read the word “applicable” as it
    appears in Section 2-404(b)(1)(ii) more broadly. Under
    Petitioners’ view, Maryland’s SIP incorporates Maryland’s
    zoning and land use requirements wholesale, saving them
    from preemption by the Commission. Advancing that view,
    Petitioners are participating in a challenge in Maryland state
    court to the MDE’s decision to process Dominion’s air quality
    permit application. See Oral Arg. Tr. 18.
    31
    We decline here, as we did in Summers, to address which
    interpretation of Section 2-404(b)(1)(ii) is correct, because it
    makes no difference in this case. The Commission’s
    certificate order has no bearing on what is and is not included
    in Maryland’s SIP, and therefore has no bearing on what are
    or are not Maryland’s “rights” saved by the Natural Gas Act’s
    clause preserving the “rights of States” under the Clean Air
    Act. The Commission did not “force[] MDE to accept an air
    quality permit application which would have otherwise been
    deemed deficient.” Pet’rs’ Br. 34. Nor did we.
    Regardless of how the scope of Section 2-404(b)(1) is
    accurately described, the Commission did not act unlawfully
    in granting a conditional certificate order.         Correctly
    understood, Petitioners’ complaint appears to be not with the
    certificate order as such, but with the MDE’s interpretation of
    its SIP in the wake of Summers and the certificate order. If
    Petitioners are right that the SIP’s reference to Section 2-
    404(b)(1)(ii) saves Myersville’s zoning and land use laws
    from preemption, it was the MDE, not the Commission, that
    erred by treating the Commission’s certificate order as
    preempting more than, by hypothesis, it lawfully could.
    Conversely, if the MDE correctly concluded that the SIP does
    not, under the circumstances here, require compliance with
    Myersville’s zoning laws, then, by the same token, the
    Commission did not exceed its statutory authority. In any
    event, the certificate order did not affect Maryland’s Clean
    Air Act rights. Under either interpretation, the certificate
    order has only whatever preemptive force it can lawfully
    exert, and no more. It did not purport to contravene the
    Natural Gas Act’s savings clause. Nor did it purport to
    compel the MDE’s interpretation of Maryland’s SIP.
    The precise scope of Maryland’s SIP and the preemptive
    effect of the Commission’s order is not before us. Petitioners
    32
    may continue to challenge the MDE’s conclusion on that
    score in the appropriate forum. We are called on to decide
    only whether it was lawful for the Commission to approve the
    Allegheny Storage Project subject to its compliance with
    Maryland’s Clean Air Act permitting process. Because no
    provision of the Natural Gas Act or the Clean Air Act
    identified by Petitioners barred the Commission from issuing
    a conditional Section 7 certificate under these circumstances,
    and the preemptive effect of that decision in light of the
    interaction of the two Acts and Maryland’s SIP is not properly
    before us, we hold that Petitioners’ challenges must be
    rejected.
    IV.
    Petitioners claim error in the Commission’s performance
    of its obligations under the National Environmental Policy
    Act of 1969 (NEPA), 
    83 Stat. 852
     (codified as amended at 
    42 U.S.C. § 4321
     et seq.), which requires federal agencies to
    “consider fully the environmental effects of their proposed
    actions.” Theodore Roosevelt Conservation P’ship v. Salazar,
    
    661 F.3d 66
    , 68 (D.C. Cir. 2011) (internal quotation marks
    omitted). Any proposed “major Federal action[] significantly
    affecting the quality of the human environment” triggers in an
    agency the obligation to prepare an Environmental Impact
    Statement (EIS) discussing in detail the environmental impact
    of the proposed action, alternatives to the action, and other
    considerations. 
    42 U.S.C. § 4332
    (C). An agency may
    preliminarily prepare an Environmental Assessment (EA) to
    determine whether the more rigorous EIS is required. See 
    40 C.F.R. §§ 1501.4
    , 1508.9. An EIS is unnecessary if an
    agency makes a “finding of no significant impact” (FONSI)
    on the human environment; a FONSI discharges the agency’s
    NEPA documentation obligations. 
    40 C.F.R. §§ 1508.9
    (a)(1),
    1508.13; 
    18 C.F.R. § 380.2
    (g).          An agency’s NEPA
    33
    obligations are “essentially procedural.” Vt. Yankee Nuclear
    Power Corp. v. NRDC, 
    435 U.S. 519
    , 558 (1978). NEPA
    does not require any particular substantive result. Id.; see also
    Theodore Roosevelt Conservation P’ship, 
    661 F.3d at 68
    .
    Here, the Commission prepared an Environmental
    Assessment of the Allegheny Storage Project. Finding that
    the Project “would not constitute a major federal action
    significantly affecting the quality of the human environment,”
    the Commission prepared a FONSI and declined to prepare an
    EIS. J.A. 242. Petitioners challenge the Commission’s
    Environmental Assessment, arguing that it failed adequately
    to consider alternatives, that it failed fully to consider the
    impact on local residents’ property values, and that it
    unlawfully segmented its environmental review of the
    Allegheny Storage Project and Dominion’s Cove Point LNG
    export terminal, which Petitioners contend the Commission
    should have reviewed together as a single project.
    We overturn an agency decision under NEPA only if it is
    arbitrary and capricious, an abuse of discretion, or if the
    agency has failed to satisfy the procedural requirements of the
    statute. Theodore Roosevelt Conservation P’ship, 
    661 F.3d at 72
    . To issue a FONSI and decline to prepare an EIS, an
    agency must have concluded that “there would be no
    significant impact or have planned measures to mitigate such
    impacts.” Mich. Gambling Opposition v. Kempthorne, 
    525 F.3d 23
    , 29 (D.C. Cir. 2008). Our role in reviewing an
    agency’s decision not to prepare an EIS is a “‘limited’” one,
    “designed primarily to ensure ‘that no arguably significant
    consequences have been ignored.’” TOMAC v. Norton, 
    433 F.3d 852
    , 860 (D.C. Cir. 2006) (quoting Pub. Citizen v. Nat’l
    Highway Traffic Safety Admin., 
    848 F.2d 256
    , 267 (D.C. Cir.
    1988)). We ask “whether the agency ‘(1) has accurately
    identified the relevant environmental concern, (2) has taken a
    34
    hard look at the problem in preparing its EA, (3) is able to
    make a convincing case for its finding of no significant
    impact, and (4) has shown that even if there is an impact of
    true significance, an EIS is unnecessary because changes or
    safeguards in the project sufficiently reduce the impact to a
    minimum.’” Mich. Gambling, 
    525 F.3d at 29
     (quoting
    TOMAC, 
    433 F.3d at 861
    ). In both the EA and EIS contexts,
    this court applies a “rule of reason” to an agency’s NEPA
    analysis and has repeatedly refused to “flyspeck” the agency’s
    findings in search of “any deficiency no matter how minor.”
    Nevada v. Dep’t of Energy, 
    457 F.3d 78
    , 93 (D.C. Cir. 2006);
    see also Minisink, 762 F.3d at 112.
    A.
    An Environmental Assessment must include a “brief
    discussion[]”of reasonable alternatives to the proposed action.
    
    40 C.F.R. § 1508.9
    (b). An alternative is “‘reasonable’ if it is
    objectively feasible as well as ‘reasonable in light of [the
    agency’s] objectives.’” Theodore Roosevelt Conservation
    P’ship, 
    661 F.3d at 72
     (alterations in original) (quoting City of
    Alexandria v. Slater, 
    198 F.3d 862
    , 867 (D.C. Cir. 1999)); see
    also 
    43 C.F.R. § 46.420
    (b) (defining “reasonable alternatives”
    in the context of an EIS as those alternatives “that are
    technically and economically practical or feasible and meet
    the purpose and need of the proposed action”). The
    Commission’s specification of the range of reasonable
    alternatives is entitled to deference.         Citizens Against
    Burlington, Inc. v. Busey, 
    938 F.2d 190
    , 196 (D.C. Cir. 1991).
    Although a consideration of alternatives is required regardless
    of whether the agency issues a FONSI, the relevant
    regulations provide that the consideration of alternatives in an
    Environmental Assessment need not be as rigorous as the
    consideration of alternatives in an EIS. Compare 
    40 C.F.R. § 1508.9
    (b) (requiring “brief discussion[]” of alternatives in
    35
    an EA) with 
    id.
     § 1502.14(a) (requiring agency to
    “[r]igorously explore and objectively evaluate all reasonable
    alternatives” when EIS required). See also Envtl. Prot. Info.
    Ctr. v. U.S. Forest Serv., 
    451 F.3d 1005
    , 1016 (9th Cir. 2006)
    (“[A]n agency’s obligation to consider alternatives under an
    EA is a lesser one than under an EIS”) (internal quotation
    marks omitted); La. Crawfish Producers Ass’n-W. v. Rowan,
    
    463 F.3d 352
    , 357 (5th Cir. 2006) (“[T]he range of
    alternatives that the [agency] must consider decreases as the
    environmental impact of the proposed action becomes less
    and less substantial.”) (second alteration in original) (internal
    quotation marks omitted); Mt. Lookout-Mt. Nebo Prop. Prot.
    Ass’n v. FERC, 
    143 F.3d 165
    , 172 (4th Cir. 1998); Friends of
    Ompompanoosuc v. FERC, 
    968 F.2d 1549
    , 1558 (2d Cir.
    1992); Olmsted Citizens for a Better Cmty. v. United States,
    
    793 F.2d 201
    , 208 (8th Cir. 1986); River Rd. Alliance, Inc. v.
    Corps of Engineers of U.S. Army, 
    764 F.2d 445
    , 452 (7th Cir.
    1985).
    Petitioners claim that the Environmental Assessment
    lacks adequate consideration of two alternatives—an “existing
    pipeline” alternative and a “looping” alternative.7 On both
    counts, Petitioners mischaracterize the Environmental
    Assessment, which considered and rejected both alternatives,
    adequately discharging the Commission’s NEPA obligations.
    First, Petitioners argue that “there are numerous other
    pipeline systems in the region that could be used to meet” the
    needs of Dominion’s customers. Pet’rs’ Br. 40. The
    Commission’s Environmental Assessment rejected the
    7
    Although Petitioners also discuss the alternative of an electric
    compressor three times in passing, see Pet’rs’ Br. 6, 15, 20, they do
    not make any argument specific to that alternative, so we decline to
    address it.
    36
    proposition that there was existing, unused capacity that could
    satisfy the new demand. J.A. 233 (apart from alternatives
    considered in EA, the Commission “did not identify any other
    existing pipeline systems in the region that could provide the
    capacity of the Project.”). Petitioner Ted Cady, seeking
    rehearing, listed five pipeline systems that he believed had
    sufficient unused capacity. J.A. 416-17. His request for
    rehearing provided no explanation or technical analysis,
    however, relating to whether those pipelines are fully
    subscribed, for example, or whether they are located so as to
    be able to serve Dominion’s customers. Because the record is
    devoid of evidence that the Commission unreasonably
    concluded that the construction of new facilities was needed
    to meet demand, and that the use of existing pipelines was not
    feasible, we decline to second-guess the Commission. The
    Commission’s consideration of the “existing pipeline”
    alternative in its Environmental Assessment was adequate.
    Second, Petitioners argue that the Commission
    inadequately considered the “looping” alternative, which
    would have involved a thirty-mile loop of pipeline rather than
    a compressor station in Myersville. The Commission rejected
    the looping alternative because building it would disturb more
    land than would building the compressor station. See J.A.
    234. In the Commission’s view, a pipeline loop “would cause
    a greater environmental disturbance” than would the
    compressor station, so the loop was “not an environmentally
    preferable” alternative.      
    Id.
         Petitioners claim the
    Commission’s finding was flawed because the loop would
    cost only $2 million more than the compressor station, but
    would result in no emissions. NEPA, however, does not
    require a general focus “on the monetary costs and benefits of
    the respective proposals . . . particularly where only an
    environmental assessment, rather than an environment impact
    statement, is involved.” Minisink, 762 F.3d at 112; see
    37
    Webster v. USDA, 
    685 F.3d 411
    , 430 (4th Cir. 2012). And
    NEPA does not compel a particular result. Even if an agency
    has conceded that an alternative is environmentally superior,
    it nevertheless may be entitled under the circumstances not to
    choose that alternative. See Robertson v. Methow Valley
    Citizens Council, 
    490 U.S. 332
    , 350 (1989) (“If the adverse
    environmental effects of the proposed action are adequately
    identified and evaluated, the agency is not constrained by
    NEPA from deciding that other values outweigh the
    environmental costs.”).
    Petitioners also assert that the Commission overestimated
    the amount of land that would be disturbed by the looping
    option. The Commission estimated 527 acres for construction
    and operation; Petitioners estimated 102. See J.A. 500. That
    challenge falls under the category of “flyspecking,” and
    encroaches on the deference to which the Commission is
    entitled for its technical analysis. The Commission stands by
    its estimate, and, in any case, responds that Petitioners’ lower
    estimate would not have changed its analysis, since it far
    outstrips the 21-acre land disturbance required for
    construction and operation of the Myersville compressor
    station. See Resp.’s Br. 35. The looping option would
    require a significantly greater amount of land than the
    compressor station, and would adversely affect the
    environment in other significant ways discussed in the
    Environmental Assessment. The Commission adequately
    considered, and rejected, the looping option. That was
    sufficient to discharge its NEPA obligations.
    B.
    Petitioners also argue that the Environmental Assessment
    failed to take a “hard look” at “quantifying the impacts of the
    project on property values and lost development
    38
    opportunities” in Myersville. Pet’rs’ Br. 42. The definition
    of “hard look” may be “imprecise,” but we have explained
    that an agency has taken a “hard look” at the environmental
    impacts of a proposed action if “‘the statement contains
    sufficient discussion of the relevant issues and opposing
    viewpoints,’ and . . . the agency’s decision is ‘fully informed’
    and ‘well-considered.’” Nevada, 457 F.3d at 93 (quoting
    NRDC v. Hodel, 
    865 F.2d 288
    , 294 (D.C. Cir. 1988)).
    In response to community concern about the Myersville
    station’s potential impact on property values, the
    Environmental Assessment noted that each purchaser of
    property has different criteria and values, but that, generally
    speaking, a compressor station could depress property values,
    particularly those of adjacent and nearby land. J.A. 200.
    Nevertheless, the Commission concluded that the Myersville
    compressor station “would not significantly reduce property
    or resale values” in Myersville because of the Commission’s
    recommendations for noise and visual screening. 
    Id.
     Views
    of the compressor station would be significantly screened by
    natural vegetation both in summer and winter, and there
    would be “no perceptible operational noise from the
    compressor station at the nearest residences.” 
    Id.
     Indeed, the
    compressor station would contribute less noise and vibration
    to the local area than is already produced by the portion of I-
    70 running next to it. J.A. 218.
    The Commission also acknowledged the “lack of studies
    evaluating property values and aboveground natural gas
    facilities,” and that “the effects on property values are
    difficult to quantify.” J.A. 200. Seizing on that statement,
    Petitioners argue that the Commission should be required to
    do more to take into account the effects that safety concerns
    and pollution have on property values. But the Commission
    acknowledged three times, in the Environmental Assessment,
    39
    in its certificate order, and in its order denying rehearing, that
    property values could be negatively affected by the
    compressor station. It chose nevertheless to approve the
    project because the negative impact was not “sufficient to
    alter our determination that the Myersville Compressor
    Station is required by the public convenience and necessity.”
    Certificate Order ¶ 104.
    In Minisink, we recently turned away a challenge similar
    to this one. The Commission acknowledged the Minisink
    project’s adverse effects on property values but nevertheless
    approved it. Because the Environmental Assessment in
    Minisink “clearly addressed this issue,” and because the
    Commission concluded that some of those property-value
    effects could be mitigated through visual screening, we found
    the Environmental Assessment was adequate. 762 F.3d at
    112. The same is true here. “Though we can see how
    Petitioners may disagree with [the Commission’s] takeaway,
    their disagreement does not mean that the Commission failed
    to consider the issue altogether, as they suggest.” Id.
    Petitioners also argue that the Commission should be
    required to take into account the impact on property values
    stemming from “preemption.” Pet’rs’ Br. 42-43. According
    to Petitioners, “[a]s a result of preemption, the Town of
    Myersville and its residents suffered a loss because a site that
    would have once sustained uses that would benefit the
    community has now been taken off the market by Dominion.”
    Id. at 43. It is not clear what independent effects on
    Petitioners’ property value they argue would stem from
    “preemption” as opposed to the construction and operation of
    the compressor station, which the Environmental Assessment
    evaluated, and we decline to guess. The Commission’s
    consideration of this issue was reasonable as well. See
    Rehearing Order ¶ 64.
    40
    C.
    Finally, Petitioners reiterate their assertion that the
    “overbuilt” Allegheny Storage Project will produce excess
    natural gas capacity destined for export through Dominion’s
    Cove Point LNG terminal. By virtue of that alleged
    connection between the Project and Cove Point, Petitioners
    argue that the Commission should be required to review their
    environmental effects together.8
    Under applicable NEPA regulations, the Commission is
    required to include “connected actions,” “cumulative actions,”
    and “similar actions” in an Environmental Assessment. 
    40 C.F.R. § 1508.25
    (a)(1)-(3).      “An agency impermissibly
    ‘segments’ NEPA review when it divides connected,
    cumulative, or similar federal actions into separate projects
    and thereby fails to address the true scope and impact of the
    activities that should be under consideration.”           Del.
    Riverkeeper Network v. FERC, 
    753 F.3d 1304
    , 1313 (D.C.
    Cir. 2014) (internal quotation marks omitted). “The purpose
    of this requirement is to prevent agencies from dividing one
    project into multiple individual actions each of which
    individually has an insignificant environmental impact, but
    which collectively have a substantial impact.” Hodel, 
    865 F.2d at 297
     (internal quotation marks omitted). “Connected
    actions” include actions that are “interdependent parts of a
    8
    We conclude that Petitioners’ argument is adequately preserved
    because it was raised below, if briefly, and the Commission
    addressed the issue in denying rehearing. See Rehearing Order
    ¶ 33 n.31.
    41
    larger action and depend on the larger action for their
    justification.”9 
    40 C.F.R. § 1508.25
    (a)(1)(iii).
    Petitioners claim that the Cove Point LNG export project
    is a “connected action” that NEPA requires be considered
    together with the Allegheny Storage Project. In Delaware
    Riverkeeper, we held that the Commission unlawfully
    segmented its environmental review where four other pipeline
    projects were “certainly ‘connected actions’” that, taken
    together, would result in “a single pipeline,” that was “linear
    and physically interdependent,” and contained “no physical
    offshoots.” 753 F.3d at 1308, 1316. In addition, the other
    pipelines were under construction or pending review when the
    contested application was filed, the Commission’s review of
    the projects was overlapping, and their cumulative effects
    were visited on the same environmental resources. We
    premised our decision requiring joint NEPA consideration on
    the unquestionable connectedness of the projects, the fact that
    the projects all were under consideration by the Commission
    at the same time, and the fact that the projects were
    financially interdependent. Id. at 1318.
    The absence of all of those factors led us to reject an
    analogy to Delaware Riverkeeper in Minisink. There, as here,
    the petitioners argued that a project that the Commission
    found unrelated was nevertheless a “connected action.” We
    rejected that argument and distinguished the connectedness
    and timing of the projects at issue in Delaware Riverkeeper.
    Minisink, 762 F.3d at 113 n.11. The same distinctions apply
    9
    “Connected actions” also include actions that “(i) [a]utomatically
    trigger other actions which may require environmental impact
    statements,” and actions that “(ii) [c]annot or will not proceed
    unless other actions are taken previously or simultaneously.” 
    40 C.F.R. § 1508.25
    (a)(1)(i)-(ii).
    42
    here. Unlike in Delaware Riverkeeper, the Commission in
    this case made clear that the Allegheny Storage Project and
    the Cove Point LNG terminal are unrelated, and that neither
    depends on the other for its justification. See 
    40 C.F.R. § 1508.25
    (a)(1)(iii). This is therefore not a case in which
    “financially and functionally interdependent pipeline
    improvements were considered separately even though there
    was no apparent logic to where one project began and the
    other ended.” Del. Riverkeeper, 753 F.3d at 1318. The
    absence of evidence that would compel a finding of
    connectedness between the Allegheny Storage Project and the
    Cove Point LNG export terminal defeats Petitioners’
    challenge.
    V.
    Finally, Petitioners Cady and Gerner claim they suffered
    due process violations because the Commission failed to
    provide them with a meaningful opportunity to comment on
    the Environmental Assessment. Petitioners claim they were
    deprived of a “meaningful opportunity” to comment on
    Critical Energy Infrastructure Information (CEII) that they
    requested from the Commission—in particular, Dominion’s
    hydraulic flow diagrams.10
    10
    CEII is “specific engineering, vulnerability, or detailed design
    information about proposed or existing critical infrastructure that:
    (i) Relates details about the production, generation, transportation,
    transmission, or distribution of energy; (ii) Could be useful to a
    person in planning an attack on critical infrastructure; (iii) Is
    exempt from mandatory disclosure under the Freedom of
    Information Act, 5 U.S.C. 552; and (iv) Does not simply give the
    general location of the critical infrastructure.”         
    18 C.F.R. § 388.113
    (c)(1).
    43
    Due process challenges to agency action are subject to
    the general prejudicial error rule. See Air Canada v. Dep’t of
    Transp., 
    148 F.3d 1142
    , 1156-57 (D.C. Cir. 1998); 
    5 U.S.C. § 706
    . “Due process requires only a ‘meaningful opportunity’
    to challenge new evidence.” BNSF Ry. Co. v. Surface Transp.
    Bd., 
    453 F.3d 473
    , 486 (D.C. Cir. 2006) (quoting Mathews v.
    Eldridge, 
    424 U.S. 319
    , 349 (1976)); see also Blumenthal v.
    FERC, 
    613 F.3d 1142
    , 1145-46 (D.C. Cir. 2010). In BNSF
    Railway, we observed that, even where an opportunity to
    rebut evidence may be obstructed at one point in a
    proceeding, a rebuttal opportunity that arises before the
    issuance of a final order is sufficient for purposes of due
    process. See 
    453 F.3d at 486
    ; Opp Cotton Mills, Inc. v. Adm’r
    of Wage & Hour Div., 
    312 U.S. 126
    , 152-53 (1941) (“The
    demands of due process do not require a hearing, at the initial
    stage or at any particular point or at more than one point in an
    administrative proceeding so long as the requisite hearing is
    held before the final order becomes effective.”)).
    Consequently, we have held that a commenter before the
    Commission who has ample time to comment on evidence
    before the deadline for rehearing is not deprived of a
    meaningful opportunity to challenge the evidence. Minisink,
    762 F.3d at 115. Cady and Gerner argue that they received
    the CEII too late to comment at their preferred time in the
    proceeding, but neither contends that they lacked ample time
    to comment on the evidence before the deadline to seek
    rehearing. We conclude that Petitioners Cady and Gerner
    both had a “meaningful opportunity” to challenge the CEII
    before rehearing, and therefore suffered no prejudice from
    any alleged procedural deficiency in the way the CEII was
    produced to them.
    Moreover, Petitioners do not identify what they would
    have done differently with the CEII had the Commission
    44
    produced it earlier in the proceeding. “To show that error was
    prejudicial, a plaintiff must indicate with reasonable
    specificity what portions of the documents it objects to and
    how it might have responded if given the opportunity.”
    Gerber v. Norton, 
    294 F.3d 173
    , 182 (D.C. Cir. 2002)
    (internal quotation marks omitted). Petitioners have failed to
    satisfy that standard.
    ***
    Because each of Petitioners’ challenges to the
    Commission’s conditional approval of the Allegheny Storage
    Project falls short, the petition for review is denied.
    So ordered.
    

Document Info

Docket Number: 13-1219

Citation Numbers: 414 U.S. App. D.C. 438, 783 F.3d 1301

Filed Date: 4/24/2015

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (50)

Friends of the Ompompanoosuc, State of Vermont v. Federal ... , 968 F.2d 1549 ( 1992 )

national-fuel-gas-supply-corporation-v-public-service-commission-of-the , 894 F.2d 571 ( 1990 )

northern-natural-gas-co-northern-border-pipeline-company-v-iowa , 377 F.3d 817 ( 2004 )

LA Crawfish Prodcr v. Rowan , 463 F.3d 352 ( 2006 )

River Road Alliance, Inc. v. Corps of Engineers of United ... , 764 F.2d 445 ( 1985 )

mt-lookout-mt-nebo-property-protection-association-an-unincorporated , 143 F.3d 165 ( 1998 )

Michigan Gambling Opposition v. Kempthorne , 525 F.3d 23 ( 2008 )

Natl Com New Riv Inc v. FERC , 373 F.3d 1323 ( 2004 )

TOMAC v. Norton, Gale A. , 433 F.3d 852 ( 2006 )

environmental-protection-information-center-a-california-nonprofit , 451 F.3d 1005 ( 2006 )

Colorado Interstate Gas Co. v. FERC , 599 F.3d 698 ( 2010 )

Gerber, John E. v. Norton, Gale A. , 294 F.3d 173 ( 2002 )

Theodore Roosevelt Conservation Partnership v. Salazar , 661 F.3d 66 ( 2011 )

olmsted-citizens-for-a-better-community-a-nonprofit-minnesota-corporation , 793 F.2d 201 ( 1986 )

B&J Oil & Gas v. Federal Energy Regulatory Commission , 353 F.3d 71 ( 2004 )

Ark Las Vegas Restaurant Corp. v. National Labor Relations ... , 334 F.3d 99 ( 2003 )

Blumenthal v. Federal Energy Regulatory Commission , 613 F.3d 1142 ( 2010 )

northern-natural-gas-company-division-of-internorth-inc-v-federal , 827 F.2d 779 ( 1987 )

state-of-michigan-michigan-department-of-environmental-quality-and-state , 213 F.3d 663 ( 2000 )

public-citizen-v-national-highway-traffic-safety-administration-ford , 848 F.2d 256 ( 1988 )

View All Authorities »