Allegheny Defense Project v. FERC , 932 F.3d 940 ( 2019 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued December 7, 2018                Decided August 2, 2019
    No. 17-1098
    ALLEGHENY DEFENSE PROJECT, ET AL.,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    ANADARKO ENERGY SERVICES COMPANY, ET AL.,
    INTERVENORS
    Consolidated with 17-1128, 17-1263, 18-1030
    On Petitions for Review of Orders of the
    Federal Energy Regulatory Commission
    Elizabeth F. Benson argued the cause for petitioners
    Allegheny Defense Project, et al. Siobhan K. Cole argued the
    cause for petitioners Hilltop Hollow Limited Partnership, et al.
    With them on the joint briefs was Benjamin A. Luckett.
    Michael N. Onufrak and Derek O. Teaney entered appearances.
    Beth G. Pacella, Deputy Solicitor, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With her on the brief were James P. Danly, General Counsel,
    2
    and Robert H. Solomon, Solicitor.       Anand Viswanathan,
    Attorney, entered an appearance.
    John F. Stoviak argued the cause for intervenors. With
    him on the joint brief were Pamela S. Goodwin, Elizabeth U.
    Witmer, Patrick F. Nugent, Kevin M. Sweeney, Jesse Stuart
    Unkenholz, and Scott Borden Grover.
    Before: GARLAND, Chief Judge, and TATEL and MILLETT,
    Circuit Judges.
    Opinion for the court filed PER CURIAM.
    Concurring opinion filed by Circuit Judge MILLETT.
    PER CURIAM: In February 2017, the Federal Energy
    Regulatory Commission approved a natural gas pipeline
    expansion called the Atlantic Sunrise Project, which stretches
    from northern Pennsylvania, across the Carolinas, and into
    Alabama. Environmental Associations whose members live
    and work in the areas affected by the Project and individual
    Homeowners whose property was used for the Project seek
    review of the Commission’s orders permitting the
    Transcontinental Gas Pipe Line Company to move forward
    with the pipeline expansion. Because the challenges to the
    Commission’s decision cannot surmount the deferential
    standards of agency review and binding circuit precedent, we
    deny the petitions.
    I
    A
    Under the Natural Gas Act, 15 U.S.C. § 717 et seq., a
    company wishing to construct a natural gas pipeline must first
    3
    obtain a certificate of “public convenience and necessity” from
    the Federal Energy Regulatory Commission.                See 
    id. § 717f(c);
    Myersville Citizens for a Rural Community, Inc. v.
    FERC, 
    783 F.3d 1301
    , 1307 (D.C. Cir. 2015).                  The
    Commission “shall * * * issue[]” the certificate if it finds that
    the proposed project “is or will be required by the present or
    future public convenience and necessity.”            15 U.S.C.
    § 717f(e).
    When a pipeline company files a certificate application,
    the Commission reviews it under criteria set forth in its
    Certificate Policy Statement, 88 FERC ¶ 61,227 (1999),
    clarified, 90 FERC ¶ 61,128, further clarified, 92 FERC
    ¶ 61,094 (2000). The Certificate Policy Statement directs the
    Commission to consider whether the project meets a market
    need and whether the public benefits of the project outweigh
    the harms. See Sierra Club v. FERC, 
    867 F.3d 1357
    , 1379
    (D.C. Cir. 2017). If market need and public benefit are both
    established, the Commission will issue a certificate authorizing
    the pipeline’s construction. 
    Id. Once that
    certificate is
    granted, the Natural Gas Act empowers the private certificate
    holder to exercise eminent domain authority if it “cannot
    acquire by contract, or is unable to agree with the owner of
    property to the compensation to be paid for, the necessary
    right-of-way to construct, operate, and maintain a pipeline[.]”
    15 U.S.C. § 717f(h).
    A party wishing to challenge the Commission’s issuance
    of a certificate of public convenience and necessity must file a
    petition for rehearing with the Commission. 15 U.S.C.
    § 717r(a). Until the Commission disposes of that rehearing
    petition, the agency action is not final for purposes of judicial
    review. See 
    id. § 717r(a)–(b);
    Clifton Power Corp. v. FERC,
    
    294 F.3d 108
    , 110–111 (D.C. Cir. 2002). The filing and
    disposition of such a rehearing petition is thus a mandatory
    4
    prerequisite to obtaining judicial review of the Commission’s
    action. See Delaware Riverkeeper Network v. FERC, 
    857 F.3d 388
    , 399 (D.C. Cir. 2017); Clifton Power 
    Corp., 294 F.3d at 110
    –111. Congress directed that petitions for rehearing
    may be “deemed to have been denied” if the Commission has
    not “act[ed] upon the application for rehearing within thirty
    days after it is filed[.]” 15 U.S.C. § 717r(a).
    The National Environmental Policy Act (“NEPA”), 42
    U.S.C. § 4321 et seq., “require[s] the Commission to consider
    and disclose the environmental effects of the actions it
    certifies.” Delaware Riverkeeper 
    Network, 857 F.3d at 394
    (internal quotation marks omitted). The Commission may
    fulfill this requirement by compiling an Environmental Impact
    Statement, which must consider, among other things, the
    proposed project’s “indirect” environmental effects. See 42
    U.S.C. § 4332(C); 40 C.F.R. §§ 1508.8, 1508.25(c).
    B
    In March 2015, the Transcontinental Gas Pipe Line
    Company (“Transco”) applied for a certificate of public
    convenience and necessity to build the Atlantic Sunrise Project.
    After notice and public comment, the Commission issued a
    final Environmental Impact Statement in December 2016. In
    that Statement, the Commission concluded that “neither
    construction nor operation of the Project would significantly
    contribute to [greenhouse-gas] cumulative effects or climate
    change.” J.A. 323.
    On February 3, 2017, the Commission granted Transco its
    requested certificate of public convenience and necessity. 158
    FERC ¶ 61,125 (2017) (“Certificate Order”). Environmental
    Associations and the private Homeowners whose land would
    become subject to an easement for the Project both filed
    5
    petitions for rehearing with the Commission, along with
    motions for a stay of construction pending disposition of their
    petitions. Before Congress’s 30-day deadline for action on the
    rehearing petitions expired, the Commission “granted”
    rehearing, but only “for the limited purpose of further
    consideration.” J.A. 600 (“Certificate Tolling Order”). The
    Commission took no action on the stay motions for more than
    five months, and then denied them.
    In late August, a Pennsylvania federal district court
    presiding over Transco’s eminent domain action entered an
    order that declared Transco’s “right to immediate possession of
    the properties in question,” based on the presumed validity of
    FERC’s Certificate Order. Transcontinental Gas Pipe Line
    Co. v. Permanent Easements for 2.14 Acres & Temp.
    Easements for 3.59 Acres in Conestoga Township, Lancaster
    County, Pa., Tax Parcel No. 1201606900000, 
    2017 WL 3624250
    , at *1, *3 (E.D. Pa. Aug. 23, 2017) (rejecting the
    Homeowners’ objections as “attacks on the FERC order itself,”
    which “can only be challenged in front of FERC, and then in
    the United States Court of Appeals for the District of Columbia
    Circuit”), aff’d, 
    907 F.3d 725
    (3d Cir. 2018).
    On September 15, 2017, while the Environmental
    Associations’ and Homeowners’ petitions for rehearing were
    still pending, the Commission issued an order authorizing
    Transco to begin construction of the Project. J.A. 616
    (“Construction Order”). Transco broke ground that same day.
    The Environmental Associations promptly moved for
    rehearing of the Construction Order and an order halting
    construction. As its 30-day statutory deadline for action on
    the Construction Order rehearing petition approached, the
    Commission again issued an order granting rehearing “for the
    6
    limited purpose of further consideration.”              J.A. 815
    (“Construction Tolling Order”).
    The Commission eventually denied the Homeowners’ and
    Environmental Associations’ petitions for rehearing in
    December 2017, more than nine months after rehearing was
    sought and three months after construction began. 161 FERC
    ¶ 61,250 (2017) (“Certificate Rehearing Order”). Three
    months after that—and nearly six months after construction
    commenced—the Commission denied rehearing of the
    Construction Order.         162 FERC ¶ 61,192 (2018)
    (“Construction Rehearing Order”).
    II
    This consolidated case arises out of four petitions for
    review collectively challenging the Certificate Order, the
    Certificate Tolling Order, the Construction Order, the
    Construction Tolling Order, and the Certificate Rehearing
    Order.      Because the Homeowners and Environmental
    Associations both properly sought rehearing of the Certificate
    Rehearing Order, which encompasses all of their claims for our
    review and is the final agency decision greenlighting the
    Project, this court has jurisdiction. See 15 U.S.C. § 717r. 1
    The Commission’s factual findings are conclusive so long
    as they are supported by substantial evidence. See 15 U.S.C.
    § 717(b). Where the Commission “has examined the relevant
    considerations and articulated a satisfactory explanation for its
    action, including a rational connection between the facts found
    and the choice made,” we must uphold its decision. FERC v.
    1
    We therefore deny as moot the motions to dismiss the
    petitions filed before the Certificate Rehearing Order issued, Nos.
    17-1098 and 17-1128.
    7
    Electric Power Supply Ass’n, 
    136 S. Ct. 760
    , 782 (2016)
    (formatting altered).
    The Homeowners and Environmental Associations argue
    that the Commission’s Certificate Order suffers from fatal
    substantive and procedural flaws. Specifically, they argue
    that the Commission improperly conducted its environmental
    assessment under NEPA, failed to substantiate market need for
    the Project as required by the Natural Gas Act, and denied them
    due process by authorizing construction to commence before
    the issuance of the Certificate Order could be judicially
    reviewed. None of those arguments succeed.
    A
    The administrative record forecloses the Homeowners’
    and Environmental Associations’ three NEPA arguments.
    First, the Homeowners and Environmental Associations
    argue that the Commission did not factor downstream
    greenhouse-gas emissions into its evaluation of the Project’s
    environmental impacts.
    The Homeowners and Environmental Associations are
    correct that customers’ burning of the natural gas that the
    Project transports will produce greenhouse-gas emissions.
    See Sierra 
    Club, 867 F.3d at 1374
    . They are also correct that
    NEPA required the Commission to consider both the direct and
    indirect environmental effects of the Project, and that, despite
    what the Commission argues, the downstream greenhouse-gas
    emissions are just such an indirect effect. See id.; 40 C.F.R.
    § 1502.16(b).
    But that is as far as the argument gets them, because the
    Commission already took the steps the Homeowners and
    8
    Environmental Associations request.         The Commission
    addressed downstream emissions in the Environmental Impact
    Statement, the Certificate Order, and the Certificate Rehearing
    Order. In particular, the Commission estimated the amount of
    CO2 emissions resulting from the gas that the Project would
    transport and predicted that those emissions would be partially
    offset by reductions in higher carbon-emitting fuel that the
    Project’s natural gas would replace. Neither the Homeowners
    nor the Environmental Associations have identified what more
    the Commission should have said. That failure is fatal.
    Unsubstantiated objections are not enough to stop an agency’s
    action.
    Second, the Homeowners and Environmental Associations
    assert that the Commission impermissibly segmented its
    environmental review by failing to consider the synergistic
    effect of the Project on emissions associated with a different
    pipeline—the Southeast Market Pipeline.              Improper
    segmentation occurs when FERC creates separate
    Environmental Impact Statements for interconnected pipelines
    that should have been evaluated as a single project. See City
    of Boston Delegation v. FERC, 
    897 F.3d 241
    , 251–252 (D.C.
    Cir. 2018).
    But NEPA requires more to make out an improper
    segmentation claim than the Homeowners and Environmental
    Associations have offered. Specifically, the Commission has
    no duty to consider the environmental effects of a separate
    project if the project in question has “substantial independent
    utility.” City of Boston 
    Delegation, 897 F.3d at 252
    (internal
    quotation marks omitted); see also Coalition on Sensible
    Transp., Inc. v. Dole, 
    826 F.2d 60
    , 69 (D.C. Cir. 1987) (asking
    “whether one project will serve a significant purpose even if a
    second related project is not built”).
    9
    The record supports the Commission’s determination that
    the Southeast Market Pipeline and the Project are
    independently justified and that each has its own distinct utility.
    City of Boston 
    Delegation, 897 F.3d at 252
    . That is because,
    even if the Project were never built, the Southeast Market
    Pipeline still would be connected to enough natural gas supply
    to exceed its capacity. J.A. 843. On this record, that
    disproves any claim of improper segmentation.
    Third, the Homeowners and Environmental Associations
    contend that the Commission was deficient in its analysis of an
    alternative site for the Project called the Conestoga Route.
    Under NEPA, agencies must “identify the reasonable
    alternatives to the contemplated action,” Minisink Residents for
    Envtl. Pres. & Safety v. FERC, 
    762 F.3d 97
    , 102 (D.C. Cir.
    2014), and “discuss[] * * * the relevant issues and opposing
    viewpoints,” 
    Myersville, 783 F.3d at 1324
    –1325 (quoting
    Nevada v. Department of Energy, 
    457 F.3d 78
    , 93 (D.C. Cir.
    2006)). This requirement helps ensure that agency actions are
    “fully informed and well-considered.” 
    Id. at 1325
    (internal
    quotation marks omitted).
    The Commission’s consideration of the Conestoga Route
    passes NEPA muster. The Commission “look[ed] hard at the
    environmental effects of its decision” by comparing the
    proposed route with the Conestoga Route across highly
    detailed criteria. 
    Minisink, 762 F.3d at 102
    (formatting
    altered). 2 In doing so, the Commission openly grappled with
    the factors favoring the Conestoga Route and reasonably
    explained why the proposed route was nonetheless superior.
    2
    The “Waterbodies crossed” criterion, for example, quantifies
    waterbodies for “Trout Stocking,” “High Quality Cold Water
    Fishes,” “Cold Water Fishes,” “High Quality Warm Water Fishes,”
    and “Warm Water Fishes.” J.A. 318.
    10
    It acknowledged that the Conestoga Route was shorter and
    would follow existing rights-of-way for more of its length than
    the proposed route would, but it placed more weight on the
    proposed route’s virtues, including that it would cross fewer
    recreational areas and would avoid potentially dangerous
    elevation changes. That suffices for NEPA. See 
    Myersville, 783 F.3d at 1308
    ; 
    Minisink, 762 F.3d at 112
    .
    B
    The Homeowners and Environmental Associations
    separately claim that the Commission’s market-need
    determination violated the Natural Gas Act. A showing of
    market need is a precondition for the Commission to issue a
    certificate of public convenience and necessity. See Sierra
    
    Club, 867 F.3d at 1379
    ; 
    Myersville, 783 F.3d at 1309
    ; 90 FERC
    at ¶ 61,392; 88 FERC at ¶ 61,746. The certificate applicant
    can make its required showing of market need for the pipeline
    “by presenting evidence of ‘preconstruction contracts’ for gas
    transportation service.” Sierra 
    Club, 867 F.3d at 1379
    .
    The Commission held Transco to this obligation. Its
    finding of market need rested on the existence of contracts with
    shippers for 100% of the Project’s capacity. That alone is
    enough. See Sierra 
    Club, 867 F.3d at 1379
    ; 
    Myersville, 783 F.3d at 1311
    ; 
    Minisink, 762 F.3d at 111
    n.10. And the
    Commission did not stop there. It also relied on comments by
    two shippers and one end-user, as well as a study submitted by
    one of the Environmental Associations, all of which reinforced
    the demand for the natural gas shipments.
    11
    C
    Finally, the Environmental Associations and Homeowners
    argue that the Commission’s authorization for construction to
    go forward while their rehearing petitions were still pending—
    and thus before the Commission’s decision was final and
    judicially reviewable—denied them due process. Circuit
    precedent forecloses their claims.
    A due-process claim turns on two essential inquiries.
    First, is there a “liberty or property interest of which a person
    has been deprived”? Swarthout v. Cooke, 
    562 U.S. 216
    , 219
    (2011). Second, were the “procedures followed” by the
    government in encroaching on those interests “constitutionally
    sufficient”? 
    Id. The Environmental
    Associations run into trouble on the
    first prong of that test. They assert that liberty and property
    interests were bestowed upon them by the Pennsylvania
    Constitution’s Environmental Rights Amendment, Pa. Const.
    Art. 1, § 27, and the Natural Gas Act’s review procedures, 15
    U.S.C. §§ 717f(c)(1)(B), 717r(a)–(b). This court has already
    rejected those claims, and those decisions control here. See
    Delaware Riverkeeper Network v. FERC, 
    895 F.3d 102
    , 110
    (D.C. Cir. 2018) (Pennsylvania Constitution); Griffith v.
    Federal Labor Relations Auth., 
    842 F.2d 487
    , 495 (D.C. Cir.
    1988) (Natural Gas Act review procedures); see generally
    LaShawn A. v. Barry, 
    87 F.3d 1389
    , 1395 (D.C. Cir. 1996)
    (“One three-judge panel * * * does not have the authority to
    overrule another three-judge panel of the court.”).
    The Homeowners, for their part, lose on the second prong
    of the due-process analysis.           They argue that the
    Commission’s delay in acting on their rehearing petitions while
    authorizing construction to start “denied [them] the right to be
    12
    heard on whether Transco’s taking of their property actually
    satisfies the public use requirement of the Fifth Amendment.”
    Petitioners’ Opening Br. 47.
    But, again, circuit precedent says otherwise. We have
    held that, as long as FERC’s public-convenience-and-necessity
    determination is not legally deficient, it necessarily satisfies the
    Fifth Amendment’s public-use requirement. See Midcoast
    Interstate Transmission, Inc. v. FERC, 
    198 F.3d 960
    , 973 (D.C.
    Cir. 2000). The Homeowners make no claim that they were
    deprived of a meaningful opportunity to be heard as part of the
    Commission’s proceedings leading up to its issuance of the
    Certificate Order, and they make no effort to distinguish (or
    even acknowledge) our holding in Midcoast.
    * * *
    For the foregoing reasons, the petitions for review are
    denied.
    So ordered.
    MILLETT, Circuit Judge, concurring:            As for the
    Homeowners’ due-process claim, I recognize that circuit
    precedent ties my hands. But the Commission has twisted our
    precedent into a Kafkaesque regime.              Under it, the
    Commission can keep homeowners in seemingly endless
    administrative limbo while energy companies plow ahead
    seizing land and constructing the very pipeline that the
    procedurally handcuffed homeowners seek to stop. The
    Commission does so by casting aside the time limit on
    rehearing that Congress ordered—treating its decision as final-
    enough for the pipeline companies to go forward with their
    construction plans, but not final for the injured landowners to
    obtain judicial review. This case starkly illustrates why that is
    not right.
    I
    My concern is not one of outcomes. The law and
    administrative record dictate who should win in this case, as in
    all Commission cases. My concern is about fair process and,
    in particular, the ability of those who are directly injured—the
    individuals whose property is taken in whole or in part by
    Commission order—to have their day in court before it is too
    late.
    The Homeowners in this case are the Erb and Hoffman
    families. Their “much beloved properties,” J.A. 581, are
    located in Southeastern Pennsylvania, see Transcript of
    Evidentiary Hearing 9, 53, ECF No. 27 (E.D. Pa. July 20, 2017)
    (“Hearing Tr.”). That was where the Erbs built their “dream
    home” and planned for their three sons to settle one day. 
    Id. at 10–11.
    The Hoffmans’ house is tucked among “rolling
    hills” on their property—a home designed to be so private that
    it could not be seen from the road. 
    Id. at 52–53.
    They built
    their lives there, among “lots of wildlife,” including the scores
    of deer and turkeys they fed each day. 
    Id. at 54.
    Both
    2
    families cherished the quiet, secluded nature of the places
    where they chose to live.
    That was until the Commission allowed the
    Transcontinental Gas Pipeline Company (“Transco”) to move
    in. In October 2015, the Commission notified the Erbs and the
    Hoffmans that a pipeline under consideration might cut right
    through their land. That would mean “removing topsoil, trees,
    shrubs, brush, roots, and large rocks, and then removing or
    blasting additional soil and bedrock to create a trench for the
    pipeline,” and giving Transco a permanent right-of-way
    through their yards. J.A. 581. The Erbs were “deathly afraid
    of the pipeline” and did not “want to be anywhere near it.”
    Hearing Tr. 45. The Hoffmans found the idea “unacceptable”
    and “disturbing,” because Transco’s right-of-way in the middle
    of their property would “totally take[] [their] privacy away.”
    
    Id. at 59.
    The Erbs and the Hoffmans fought hard before the
    Commission to preserve their land. After the Certificate
    Order issued, the Homeowners filed their request for rehearing
    as well as a motion to stay the Certificate Order pending the
    agency’s final rehearing decision. During the 30-day time
    period allotted by Congress for agency action on the
    Homeowners’ rehearing requests, the Commission ignored the
    application for a stay. And before the 30th day passed, the
    Commission issued a so-called “tolling order.” J.A. 600
    (“Certificate Tolling Order”).     Offering no explanation
    whatsoever for its delay, the Commission just declared that
    rehearing was “granted” for the sole purpose of buying the
    Commission more time.           
    Id. (“[R]ehearing of
    the
    Commission’s order is hereby granted for the limited purpose
    of further consideration[.]”).
    3
    The upshot of the Commission’s self-help was that its
    continued inaction on rehearing—the non-finality of the
    Certificate Order—jurisdictionally locked the Homeowners
    out of federal court. See Delaware Riverkeeper Network v.
    FERC, 
    857 F.3d 388
    , 393 (D.C. Cir. 2017); Clifton Power
    Corp. v. FERC, 
    294 F.3d 108
    , 110–111 (D.C. Cir. 2002).
    Indeed, when the Homeowners petitioned this court for review
    of both the Certificate Order and the Certificate Tolling Order,
    both the Commission and Transco were quick to seek dismissal
    of the petitions as “incurably premature” because the rehearing
    requests had not yet been resolved. See Motion of Movant-
    Intervenor Transcontinental Gas Pipe Line Company, LLC to
    Dismiss the Petitions for Review 15, No. 17-1128 (June 30,
    2017); see also Motion of Federal Energy Regulatory
    Commission to Apply Disposition of the Motion to Dismiss
    Filed in Docket No. 17-1098 to the Instant Petitions, No. 17-
    1128 (June 30, 2017); Motion to Dismiss for Lack of
    Jurisdiction 5–6, No. 17-1098 (April 28, 2017).
    While non-final for the Erbs and Hoffmans, the
    Commission’s order was still final enough for Transco to
    prevail in an eminent domain action in a Pennsylvania federal
    district court and to acquire the needed easements over the
    Erbs’ and Hoffmans’ land. Transco told the district court that,
    in deciding whether eminent domain is appropriate, it “must
    consider that the [Certificate Order] is final” and that its finding
    of public convenience and necessity controlled the question of
    whether the land was being taken for a public use. Hearing Tr.
    138–139 (emphasis added). On that basis, the district court
    granted Transco the “right to immediate possession of the
    properties[.]”     Transcontinental Gas Pipe Line Co. v.
    Permanent Easements for 2.14 Acres & Temp. Easements for
    3.59 Acres in Conestoga Township, Lancaster County, Pa., Tax
    Parcel No. 1201606900000, 
    2017 WL 3624250
    , at *1 (E.D. Pa.
    Aug. 23, 2017), aff’d, 
    907 F.3d 725
    (3d Cir. 2018); see also 
    id. 4 at
    *3–4 (rejecting the Homeowners’ claims as “attacks on the
    FERC order itself,” which the district court did not have
    jurisdiction to consider).
    On August 31, 2017—eight days after Transco prevailed
    in its eminent domain action and more than six months after the
    Homeowners asked the Commission for a stay of the
    Certificate Order—the Commission denied the Homeowners’
    request for a stay. The Commission reasoned that the
    Homeowners’ objections to Transco bulldozing and blasting its
    pipeline into their homesteads were nothing more than
    “generalized claims of environmental harm [that] do not
    constitute sufficient evidence of irreparable harm that would
    justify a stay.” 160 FERC ¶ 61,042, 
    2017 WL 3835932
    , at *2
    (Feb. 9, 2017).
    Two weeks later, apparently still too busy to act on the
    Homeowners’ rehearing petition, the Commission nonetheless
    found the time to issue a Construction Order authorizing
    Transco to start construction on the Homeowners’ land. J.A.
    616 (“Construction Order”). Which Transco promptly did.
    J.A. 616; Oral Arg. Tr. 19. And when the 30-day time limit
    for action on a request for rehearing of the Construction Order
    approached, guess what? The Commission once again issued
    an order that did nothing but give the Commission more time
    to decide. See J.A. 815. Meanwhile, Transco’s construction
    continued apace. And the Homeowners remained trapped
    before the agency.
    The Commission did not issue a final, appealable
    certificate decision until December 6, 2017, months after
    Transco had started construction.
    5
    II
    Circuit precedent gave the Commission the tools it has
    used to create this administrative quagmire for those who seek
    to challenge its decisions. In my view, we should put an end
    to it. A scheme that walls homeowners off from timely
    judicial review of the Commission’s public-use determination,
    while allowing eminent domain and functionally irreversible
    construction to go forward, is in substantial tension with
    statutory text and runs roughshod over basic principles of fair
    process.
    A
    1
    This much is clear: The Natural Gas Act makes the filing
    of a rehearing petition a jurisdictional precondition to obtaining
    judicial review of Commission decisions.               15 U.S.C.
    § 717r(a)–(b). The Act spells out what the Commission can
    do once an application for rehearing is filed. It “shall have
    power to grant or deny rehearing or to abrogate or modify its
    order[.]” 
    Id. § 717r(a).
    Unless the Commission so “acts
    upon the application for rehearing within thirty days,”
    rehearing “may be deemed to have been denied.” 
    Id. The most
    natural reading of that language is that Congress
    told the Commission to “act[] upon the application for
    rehearing” and to do so “within thirty days.” 15 U.S.C.
    § 717r(a).
    The Commission reasons that it has “acted” because it
    gave itself more time. But the Natural Gas Act requires the
    Commission not just to act, but to “act[] upon the application”
    itself. 15 U.S.C. § 717r(a). And Congress specified which
    6
    Commission actions count as “acts upon the application”: The
    Commission could “grant” rehearing, “deny” it, “modify” the
    underlying order, or “abrogate” it. 
    Id. Casting aside
    Congress’s time limit is not on that menu.
    The Natural Gas Act answers the question of what should
    happen if the Commission finds itself unable to act within the
    allotted 30 days. Rehearing “may be deemed denied” by the
    aggrieved party, who may then obtain judicial review. 15
    U.S.C. § 717r(a); see 
    id. § 717r(b);
    cf. 28 U.S.C. § 2675(a)
    (Under the Federal Tort Claims Act, “[t]he failure of
    an agency to make final disposition of a claim within six
    months after it is filed shall, at the option of the claimant any
    time thereafter, be deemed a final denial of the claim for
    purposes of this section.”); 42 U.S.C. § 2000e-16(c) (Under
    Title VII of the Civil Rights Act of 1964, agency inaction after
    a specified time period for agency decision permits the
    complainant to proceed to court.). There is no point to that
    statutory time limit if the Commission can ignore it for no
    reason at all and with no consequence at all.
    Congress, in other words, gave the Commission 30 days to
    fish or cut bait. Trapping an aggrieved party in administrative
    limbo while the Commission spends several months thinking
    about whether to go fishing is not an option.
    2
    But circuit precedent says otherwise. We have held that
    the Commission’s tolling orders qualify under the statute as an
    action upon the rehearing request. See Delaware Riverkeeper
    Network v. FERC, 
    895 F.3d 102
    , 113 (D.C. Cir. 2018); see also
    Moreau v. FERC, 
    982 F.2d 556
    , 564 (D.C. Cir. 1993) (FERC
    had “yet to rule on the merits” after forty-four days).
    7
    Delaware Riverkeeper and Moreau faithfully followed the
    fountainhead of circuit precedent upholding the Commission’s
    tolling orders:    California Company v. Federal Power
    Commission, 
    411 F.2d 720
    (D.C. Cir. 1969) (per curiam). But
    that decision long predates modern statutory construction
    jurisprudence, and did not claim to turn on the best reading of
    the statutory text. To the contrary, California Company
    described the Commission’s reading of Section 717r(a) as “far
    from self-evident.” 
    Id. at 722.
    Nonetheless, the court
    deferred to the Commission because its approach “avoids * * *
    administrative and judicial problems.” 
    Id. The court
    in Delaware Riverkeeper found itself bound by
    California Company, and thus yielded to concerns about the
    workability of a scheme that ties the Commission’s often
    complicated decisionmaking to a tight 30-day timeframe. 
    See 895 F.3d at 113
    . But, alas, “[i]f you give a mouse a cookie
    * * *.” 1 The Commission has taken this court’s patience and
    turned it into a license to routinely blow past Congress’s
    deadline, granting itself as much time as it desires to act on
    rehearing requests. One recent study showed that, between
    2009 and 2017, the Commission issued tolling orders in
    response to 99% of requests for rehearing of pipeline
    certification decisions. Petition for an Extraordinary Writ, In
    re Appalachian Voices, et al., No. 18-1006 at Exhibit G (Jan.
    8, 2018) (“Exhibit G”) (cataloguing tolling orders issued in 74
    out of 75 pipeline certifications between 2009 and 2017); see
    also Berkley v. Mountain Valley Pipeline, LLC, 
    896 F.3d 624
    ,
    631 n.4 (4th Cir. 2018) (noting that FERC does not dispute that
    it “regularly” issues tolling orders). FERC has issued a
    boilerplate tolling order in response to every motion for
    rehearing of a pipeline certification decision since 2017 too.
    1
    See LAURA NUMEROFF, IF YOU GIVE A MOUSE A COOKIE
    (1985).
    8
    It also bears noting that this court’s acceptance of tolling
    orders started in a case that involved disputes over money, not
    property. See California 
    Co., 411 F.2d at 720
    (rate dispute).
    The same is true of all of the other cases cited in Delaware
    Riverkeeper. 
    See 895 F.3d at 113
    (citing Kokajko v. FERC,
    
    837 F.2d 524
    , 526 (1st Cir. 1988) (fees); General American Oil
    Co. of Tex. v. Federal Power Comm’n, 
    409 F.2d 597
    , 599 (5th
    Cir. 1969) (rates)). Because disputes over monetary payments
    can be fixed later, the consequences of Commission delay were
    temporary and remediable. One side or the other would have
    to bear the financial cost while administrative and judicial
    litigation went forward. The tolling order just assigned that
    burden to the party that lost before the agency.
    But allowing the Commission to take its time while private
    property is being destroyed is another thing altogether. Under
    the Natural Gas Act, “any holder of a certificate * * * may
    acquire the [property] by the exercise of the right of eminent
    domain.” 15 U.S.C. § 717f(h). On top of that, courts
    involved in eminent domain proceedings—including in this
    case—routinely treat the Commission’s non-final certificate
    order as final and conclusive evidence that the taking serves a
    public purpose. See Transcontinental Gas Pipe Line Co.,
    
    2017 WL 3624250
    , at *4 (collecting cases).
    Congress further directed that the filing of an application
    for rehearing “shall not, unless specifically ordered by the
    Commission, operate as a stay of the Commission’s
    [certificate] order.” 15 U.S.C. § 717r(c). Of course, in doing
    so, Congress presumably expected that rehearing decisions
    would be resolved within 30 days, as the statute says. See 
    id. § 717r(a).
    In other words, as Congress designed the rehearing
    system, eminent domain proceedings would likely not
    conclude before the Commission acted on rehearing and
    9
    afforded the applicant an opportunity for judicial review of the
    public-use determination.
    The Commission’s use of tolling orders upends that
    balanced framework. Now the Commission can, in effect,
    split the atom of finality knowing that its certificate orders will
    be treated as conclusive in eminent domain proceedings, while
    shielding those same orders from judicial scrutiny as non-final.
    This imbalance is what allowed Transco’s lawyer in this case
    to tell the Pennsylvania district court that, “as to this process,
    the eminent domain process, the [certificate] order is final,”
    Hearing Tr. 80, while it and the Commission told this court that
    the very same certificate order does not constitute final agency
    action for purposes of the Homeowners’ effort to obtain
    judicial review, see Motion of Movant-Intervenor at 15
    (arguing that the Homeowners’ petition for review of the
    Certificate Order must be dismissed as “‘incurably premature’
    because a Tolling Order was timely issued and the Commission
    has not yet ruled on the merits of the Requests for Rehearing”);
    see also Commission’s Br. 8 (asserting the same argument).
    Making that bad situation worse, the Commission that says
    it is too busy to act on rehearing applications nevertheless
    consistently manages to find the time to grant orders
    authorizing construction to go forward while rehearing is still
    pending. See Construction Order; Exhibit G (cataloguing
    cases where FERC authorized construction during the tolling
    period).
    The result is that the Commission can toll until the cows
    come home and thereby forestall judicial review while people’s
    homesteads are being destroyed. And the Commission knows
    exactly what it is doing with its repeated issuance of cookie-
    cutter tolling orders.      Commissioner Glick has openly
    acknowledged that the Commission’s use of tolling orders to
    10
    delay rehearing orders causes “landowners, communities, and
    the environment” to “suffer needless and avoidable harm”
    because, “while the parties await their opportunity to challenge
    the Commission’s certificate decision in court,” the developer
    goes ahead and “begin[s] construction on the new pipeline
    facility[.]” PennEast Pipeline Co., 163 FERC ¶ 61,159, 
    2018 WL 2453596
    , at *4 (May 30, 2018) (Glick, Comm’r,
    concurring).
    Of course, the Commission advises the companies that
    they proceed at the risk that the agency may have a change of
    heart on rehearing. Commission’s Br. 24. Perhaps such
    words work when the certificate orders just involve monetary
    payments for fees or rates. But they ring hollow in eminent
    domain and construction cases like this. Once the property is
    in the company’s possession, the land is cleared, trees are cut
    down, and the pipeline is cemented into a family’s backyard, it
    is difficult if not impossible to unshuffle the deck. The
    damage to property rights, property values, and the
    environment is done. That creates rather than “avoids * * *
    administrative and judicial problems.” California 
    Co., 411 F.2d at 722
    .
    In my view, the better course is to assume that Congress
    “says in a statute what it means and means in a statute what it
    says there.” Connecticut Nat’l Bank v. Germain, 
    503 U.S. 249
    , 254 (1992). So when Congress said that rehearing
    petitions may be deemed denied and agency action final after
    30 days, that is what it meant.
    III
    Circuit precedent has already rejected a due-process
    challenge to the Commission’s tolling orders. See Delaware
    
    Riverkeeper, 895 F.3d at 112
    –113. Yet, in my view, the
    11
    authority our precedent affords the Commission to issue tolling
    orders while simultaneously allowing eminent domain
    proceedings and construction to proceed—all before the
    affected landowner can obtain judicial review of the
    Commission’s public-use determination—skates on thin
    constitutional ice. And courts must construe statutes to avoid,
    rather than to create, constitutional problems. Zadvydas v.
    Davis, 
    533 U.S. 678
    , 689 (2001) (describing this “cardinal
    principle” of statutory construction).
    A
    The Due Process Clause of the Fifth Amendment
    guarantees that “[n]o person shall * * * be deprived of life,
    liberty, or property, without due process of law[.]” U.S.
    Const. Amend. V. Due process “calls for such procedural
    protections as the particular situation demands” to
    meaningfully protect the constitutional right at stake.
    Morrissey v. Brewer, 
    408 U.S. 471
    , 481 (1972). At a
    minimum, due process requires an “opportunity to be heard.”
    Grannis v. Ordean, 
    234 U.S. 385
    , 394 (1914). And that
    opportunity “must be granted at a meaningful time and in a
    meaningful manner.” Armstrong v. Manzo, 
    380 U.S. 545
    , 552
    (1965). This requirement not only “ensure[s] abstract fair
    play to the individual.” Fuentes v. Shevin, 
    407 U.S. 67
    , 80–81
    (1972). It also “protect[s] his use and possession of property
    from arbitrary encroachment” by “minimiz[ing] substantively
    unfair or mistaken deprivations of property[.]” 
    Id. at 81.
    That “danger” is “especially great” when the government
    “seizes goods simply upon the application of and for the benefit
    of a private party” such as Transco. 
    Id. Landowners like
    the Erb and Hoffman families
    “[u]ndoubtedly * * * have a constitutionally protected property
    interest in their home.” Freeman v. F.D.I.C., 
    56 F.3d 1394
    ,
    12
    1403 (D.C. Cir. 1995).                Determining whether the
    Commission’s procedures for allowing private third parties to
    build on private land pass constitutional muster therefore
    requires weighing (i) “the private interest that will be affected
    by the official action”; (ii) “the risk of an erroneous deprivation
    of such interest through the procedures used”; and (iii) “the
    Government’s interest, including the function involved and the
    fiscal and administrative burdens that the additional or
    substitute procedural requirement would entail.” Mathews v.
    Eldridge, 
    424 U.S. 319
    , 335 (1976). That balance weighs
    against the Commission’s current process of saddling
    landowners with all the harm and risk of delay in its own
    decisionmaking. And it weighs heavily in favor of reading the
    statute’s 30-day time limit as the plain text prescribes to avoid
    this constitutional question.
    1
    The right of the Erb and Hoffman families “to maintain
    control over [their] home[s], and to be free from governmental
    interference, is a private interest of historic and continuing
    importance.” United States v. James Daniel Good Real
    Property, 
    510 U.S. 43
    , 53–54 (1993); 
    id. at 49
    (“The
    Government does not, and could not, dispute that the seizure of
    Good’s home and 4-acre parcel deprived him of property
    interests protected by the Due Process Clause.”).
    And the Commission’s decisions authorizing Transco’s
    “physical invasion” of the families’ homesteads, Loretto v.
    Teleprompter Manhattan CATV Corp., 
    458 U.S. 419
    , 426
    (1982), constitute a “government intrusion of an unusually
    serious character,” 
    id. at 433.
    Homeowners “suffer[] a special
    kind of injury when a stranger directly invades and occupies
    the owner’s property.” 
    Id. at 436
    (emphasis omitted); see also
    James Daniel Good Real 
    Property, 510 U.S. at 61
    (An
    13
    “essential principle” is that “[i]ndividual freedom finds
    tangible expression in property rights,” particularly where the
    “privacy of the home and those who take shelter within it” is at
    stake.); Hendler v. United States, 
    952 F.2d 1364
    , 1374 (Fed.
    Cir. 1991) (“In the bundle of rights we call property, one of the
    most valued is the right to sole and exclusive possession—the
    right to exclude strangers[.]”) (emphasis omitted); cf. United
    Church of the Med. Ctr. v. Medical Ctr. Comm’n, 
    689 F.2d 693
    ,
    701 (7th Cir. 1982) (“It is settled beyond the need for citation
    * * * that a given piece of property is considered to be unique,
    and its loss is always an irreparable injury.”).
    All the more so because building the pipeline would cause
    “permanent, irreparable environmental harm” to the Erb and
    Hoffman families’ lands. J.A. 581. “Environmental injury,
    by its nature, can seldom be adequately remedied by money
    damages and is often permanent or at least of long duration,
    i.e., irreparable.” Amoco Prod. Co. v. Village of Gambell, 
    480 U.S. 531
    , 545 (1987); see also National Wildlife Fed’n v.
    Burford, 
    835 F.2d 305
    , 323–325 (D.C. Cir. 1987)
    (“[D]estroying wildlife habitat, air and water quality, natural
    beauty, and other environmental and aesthetic values and
    interests” constitutes irreparable harm.).           After all,
    constructing a gas pipeline is not a tidy intrusion. It requires
    cutting down the families’ trees, digging up their soil, blasting
    their bedrock, displacing wildlife, and polluting the air.
    Once Commission-authorized construction starts, then
    “meaningful backward-looking relief to rectify an[]
    unconstitutional deprivation” is rarely a viable option.
    McKesson Corp. v. Division of Alcoholic Beverages &
    Tobacco, 
    496 U.S. 18
    , 31 (1990) (emphasis added); see also
    
    Amoco, 480 U.S. at 545
    ; RoDa Drilling Co. v. Siegal, 
    552 F.3d 1203
    , 1210 (10th Cir. 2009) (“[C]ourts have held that, when
    interests involving real property are at stake, preliminary
    14
    injunctive relief can be particularly appropriate because of the
    unique nature of the property interest.”) (formatting altered)
    (collecting additional cases).
    2
    The Commission’s process leaves landowners like the
    Erbs and the Hoffmans to bear a material “risk of an erroneous
    deprivation.” See 
    Mathews, 424 U.S. at 335
    . Every time a
    court reverses, vacates, or remands a Commission pipeline
    certification decision—or when the Commission grants a
    landowner’s rehearing motion on the merits—it means that the
    people who had owned and organized their lives on the
    pipeline-occupied land were subject to an erroneous
    deprivation by the initial decision. See, e.g., Sierra Club v.
    FERC, 
    867 F.3d 1357
    , 1379 (D.C. Cir. 2017); Delaware
    Riverkeeper Network v. FERC, 
    753 F.3d 1304
    , 1320 (D.C. Cir.
    2014).
    The Commission’s prolonged tolling while construction
    proceeds apace compounds the problem. The Supreme Court
    has recently recognized that a “property owner has suffered a
    violation of his Fifth Amendment rights when the government
    takes his property without just compensation,” regardless of
    whether damages might later ensue. Knick v. Township of
    Scott, Pa., 
    139 S. Ct. 2162
    , 2168 (2019) (Takings Clause case
    involving regulation by state government); see also 
    id. at 2170.
    Prompt access to federal court review of the lawfulness of the
    taking, including the public use determination, is part of the
    protection the Fifth Amendment affords. That access is
    necessary to avoid “hand[ing] authority over federal takings
    claims to state courts[,]” 
    id., or—as here—to
    the same federal
    agency that authorized eminent domain in the first place, see
    City of Cincinnati v. Vester, 
    281 U.S. 439
    , 446 (1930) (“[T]he
    question what is a public use is a judicial one.”).
    15
    Unsurprisingly, Transco supports the current state of
    affairs.   It reasons that homeowners can always seek
    mandamus relief under the All Writs Act, 28 U.S.C. § 1651,
    while the pipeline company’s bulldozers keep bulldozing. We
    agreed in Delaware 
    Riverkeeper, 895 F.3d at 113
    , and I
    recognize that decision binds this panel.
    But the due-process question is whether the Commission’s
    process protects against erroneous deprivations. Mandamus
    only protects against the most extreme outlier—the clearest,
    most obvious, and wholly irreparable agency errors, and even
    then only if a court chooses to use its discretion to grant that
    extraordinary remedy. See Cheney v. United States Dist.
    Court for D.C., 
    542 U.S. 367
    , 380–381 (2004) (Mandamus
    requires a showing of “exceptional circumstances,” the absence
    of “other adequate means” to obtain relief, and a “clear and
    indisputable” right to the writ, and even still “the issuing court,
    in the exercise of its discretion, must be satisfied that the writ
    is appropriate under the circumstances.”) (formatting altered).
    The proof is in the pudding. The Commission routinely
    fends off mandamus actions while its tolling orders remain in
    effect. See, e.g., In re Appalachian Voices, No. 18-1006 (D.C.
    Cir. Feb. 2, 2018) (denying property owners’ petition for a stay
    of pipeline construction under the All Writs Act); In re
    Appalachian Voices, No. 18-1271 (4th Cir. March 21, 2018)
    (same); Coalition to Reroute Nexus v. FERC, No. 17-4302 (6th
    Cir. March 15, 2018) (same). Neither the Commission nor
    Transco has cited a single instance in which a petitioner
    opposing pipeline construction has succeeded by invoking the
    All Writs Act.
    The question then becomes “whether ‘the risk of an
    erroneous deprivation’ would be reduced” by “procedural
    16
    safeguards” that would prevent pipeline construction from
    beginning until the Commission acts on the merits of rehearing
    requests. UDC Chairs Chapter, American Ass’n of Univ.
    Professors v. Board of Trustees, 
    56 F.3d 1469
    , 1474 (D.C. Cir.
    1995) (quoting 
    Mathews, 424 U.S. at 335
    ).
    The answer is plain as day. Requiring the Commission to
    act in a timely manner on applications for rehearing would
    allow landowners to obtain both final agency and federal court
    review before construction starts. Or the Commission could
    achieve the same result just by declining to issue construction
    orders until it resolves certificate rehearing requests on the
    merits.
    3
    The Commission has no legitimate interest that outweighs
    the unfairness and risk of harm imposed by the current regime,
    especially given how easy it would be for the Commission to
    fix the problem.
    The Commission insists that tolling orders are necessary
    because it takes more than 30 days to resolve the issues raised
    in applications for rehearing. Oral Arg. Tr. 33. The short
    answer is that the Commission should raise that argument with
    Congress, which prescribed the 30-day timeframe for decision.
    An equally short answer is that the Commission could try
    working with rehearing applicants to obtain more time by, for
    example, agreeing to hold its hand on construction orders or
    staying initial certificate orders to forestall eminent domain
    proceedings before it takes final action.
    If that is too administratively burdensome, then the
    Commission could try the easiest path of all: take absolutely
    no action on the rehearing application. That would have the
    17
    effect of denying the request as a matter of law. See 15 U.S.C.
    § 717r(a). And that approach would have opened the
    courthouse doors to the Homeowners four months before the
    eminent domain decision and five months before construction
    started. See 
    id. § 717r(b).
    Lastly, the Commission appeals to the “public need” for
    the pipeline itself. Oral Arg. Tr. 35. That is pure question-
    begging. The public need for the Atlantic Sunrise Project—
    whether the Commission’s finding of public convenience and
    necessity was lawful—is precisely the question for which the
    Erb and Hoffman families seek judicial review.
    Anyhow, it is well-settled that “the right to procedural due
    process is ‘absolute’ in the sense that it does not depend upon
    the merits of a claimant’s substantive assertions[.]” Carey v.
    Piphus, 
    435 U.S. 247
    , 266 (1978); see also 
    Fuentes, 407 U.S. at 87
    (“The right to be heard does not depend upon an advance
    showing that one will surely prevail at the hearing.”). In other
    words, “[t]o one who protests against the taking of his property
    without due process of law, it is no answer to say that in his
    particular case due process of law would have led to the same
    result[.]” Coe v. Armour Fertilizer Works, 
    237 U.S. 413
    , 424
    (1915). The question is not whether the Erbs and Hoffmans
    will win; it is only whether they have a right to be fairly and
    timely heard before their “federal claim dies aborning” in the
    Commission’s process. 
    Knick, 139 S. Ct. at 2167
    .
    * * * * *
    In cases involving private property rights, the Commission
    has transformed this court’s decisions upholding its tolling
    orders into a bureaucratic purgatory that only Dante could love.
    While I acknowledge that circuit precedent currently forecloses
    the Homeowners’ constitutional challenge to the tolling orders,
    18
    this case starkly illustrates why a second look by us or by the
    Commission is overdue.
    

Document Info

Docket Number: 17-1098

Citation Numbers: 932 F.3d 940

Filed Date: 8/2/2019

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (31)

John Kokajko, D/B/A Voyageurs v. Federal Energy Regulatory ... , 837 F.2d 524 ( 1988 )

RoDa Drilling Co. v. Siegal , 552 F.3d 1203 ( 2009 )

Clyde C. Freeman and Nancy F. Freeman v. Federal Deposit ... , 56 F.3d 1394 ( 1995 )

Jacqueline A. Tommas Griffith v. Federal Labor Relations ... , 842 F.2d 487 ( 1988 )

united-church-of-the-medical-center-a-religious-corporation-v-medical , 689 F.2d 693 ( 1982 )

general-american-oil-company-of-texas-v-federal-power-commission-humble , 409 F.2d 597 ( 1969 )

Clifton Power Corp. v. Federal Energy Regulatory Commission , 294 F.3d 108 ( 2002 )

Midcoast Interstate Transmission, Inc. v. Federal Energy ... , 198 F.3d 960 ( 2000 )

Udc Chairs Chapter, American Association of University ... , 56 F.3d 1469 ( 1995 )

judith-b-moreau-n-robert-moreau-clara-lawrence-and-walter-lawrence-v , 982 F.2d 556 ( 1993 )

National Wildlife Federation v. Robert F. Burford, Mountain ... , 835 F.2d 305 ( 1987 )

Coalition on Sensible Transportation, Inc. v. Elizabeth Dole , 826 F.2d 60 ( 1987 )

the-california-company-v-federal-power-commission-union-texas-petroleum , 411 F.2d 720 ( 1969 )

Lashawn A. v. Marion S. Barry, Jr. , 87 F.3d 1389 ( 1996 )

Amoco Production Co. v. Village of Gambell , 107 S. Ct. 1396 ( 1987 )

Grannis v. Ordean , 34 S. Ct. 779 ( 1914 )

Cincinnati v. Vester , 281 U.S. 439 ( 1930 )

Coe v. Armour Fertilizer Works , 35 S. Ct. 625 ( 1915 )

Morrissey v. Brewer , 92 S. Ct. 2593 ( 1972 )

Mathews v. Eldridge , 96 S. Ct. 893 ( 1976 )

View All Authorities »