Southern California Edison Co. v. Federal Energy Regulatory Commission , 162 F.3d 116 ( 1998 )


Menu:
  •                         United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued October 16, 1998   Decided December 11, 1998
    No. 97-1450
    Southern California Edison Company,
    Petitioner
    v.
    Federal Energy Regulatory Commission,
    Respondent
    Public Utilities Commission of the
    State of California, et al.,
    Intervenors
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    John G. Roberts, Jr. argued the cause for petitioner.  With
    him on the briefs were Kevin J. Lipson, Richard T. Saas,
    Catherine E. Stetson and Stephen E. Pickett.
    Larry D. Gasteiger, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent.  With him on
    the brief were Jay L. Witkin, Solicitor, and Susan J. Court,
    Special Counsel.
    Richard C. Green argued the cause for intervenors El Paso
    Natural Gas Company, et al.  With him on the brief were
    Judy A. Johnson, Kenneth M. Minesinger, James R. McCot-
    ter, David L. Huard, Patrick G. Golden, Joel L. Greene, John
    P. Gregg, Michael Hall, Kelly A. Daly, James H. McGrew,
    James F. Moriarty, Katherine B. Edwards, John C. Walley,
    Douglas M. Canter and Barbara S. Jost.  David W.
    Anderson and Kim M. Clark entered appearances.
    Before:  Edwards, Chief Judge, Williams and Ginsburg,
    Circuit Judges.
    Opinion for the Court filed by Circuit Judge Williams.
    Williams, Circuit Judge:  Petitioner Southern California
    Edison Company ("Edison") is an electric utility, and South-
    ern California Gas Company ("SoCal") is a gas distributor--a
    local distribution company or LDC.  To supply gas for the
    generation of electricity, Edison buys firm gas transportation
    service on the pipeline systems of both El Paso Natural Gas
    Company and SoCal.  In a curious way (described below),
    Edison is not only a direct customer of El Paso, but, through
    SoCal, a kind of indirect customer.  In 1995 El Paso filed new
    transportation rates with the Federal Energy Regulatory
    Commission under s 4 of the Natural Gas Act, 15 U.S.C.
    s 717c, and made an offer of settlement to which most of its
    customers agreed.  Edison objected, raising claims that in a
    disputed rate case would have entitled Edison to a hearing
    (according to the unreversed determination of the administra-
    tive law judge, El Paso Natural Gas Co., 78 FERC p 63,006
    at 65,131 (1997)).  The Commission approved the settlement
    as "uncontested," protecting Edison's interests as a direct
    customer by severing it and allowing it to pursue its objec-
    tions outside the settlement.  But the Commission denied
    Edison any right to either severance or litigation in its role as
    an indirect customer of El Paso.  See El Paso Natural Gas
    Co., 79 FERC p 61,028, reh'g denied, 80 FERC p 61,084
    (1997).  Finding the Commission order inconsistent with the
    settlement precedents of both the Commission and this court,
    we reverse.
    * * *
    Edison's role as an indirect customer of El Paso arises
    from gas industry restructuring.  SoCal formerly sold gas
    both to its "core" customers (largely residential as we under-
    stand it) and to non-core ones such as Edison.  As a result of
    restructuring, it now sells gas only to its "core" customers.
    SoCal still sells transportation services to the non-core cus-
    tomers.  Thus Edison buys gas and ships it via El Paso to
    California, and via SoCal to its generating stations.
    But because of SoCal's now abandoned sales service to non-
    core customers, it had reserved much more capacity on El
    Paso and other interstate pipeline systems than it now needs.
    To minimize its loss on this resource, SoCal sells the surplus
    capacity into the secondary market.  Because the available
    capacity far exceeds demand, however, the resulting revenues
    fall well below SoCal's cost.  See 79 FERC p 61,028 at 61,126.
    The California Public Utilities Commission ("CPUC") allows
    it to make up the loss by a charge to its non-core customers
    called the Interstate Transition Cost Surcharge ("ITCS").
    See 
    id. at 61,128-29
    n.21.
    The only issue before us is the propriety of FERC's refusal
    either to hold up the settlement pending resolution of Edi-
    son's merits claims as an indirect customer, or to sever
    Edison from the settlement in both its capacities.  Edison
    argues that the refusal was improper under both the Commis-
    sion's precedents and our own.  We examine the two sets of
    authorities in turn.
    * * *
    In United Gas Pipe Line Co., 55 FERC p 61,070 (1991),
    reh'g denied, 64 FERC p 61,014 (1993), the Commission al-
    lowed indirect customers of a pipeline to block a settlement.
    The Commission here attempted to distinguish United in two
    ways.  It first argued that, unlike the indirect customers in
    United, whose rates from direct customers were under
    FERC's jurisdiction, Edison "is concerned about SoCal's rate
    to its intrastate customers, ... which is a matter over which
    this Commission has no jurisdiction."  80 FERC p 61,084 at
    61,294.  This is blind to Edison's claim.  Edison challenges
    the validity of the settlement's allocation of costs to El Paso's
    customers--including SoCal--not the subsequent allocation of
    SoCal's share to Edison.  Equally blind is the Commission's
    suggestion that Edison's problems are of its own making, as it
    agreed before CPUC to bear a specified share of the ITSC.
    
    Id. Edison's agreement
    before CPUC to bear a share of
    costs being determined by FERC cannot possibly have
    waived its rights to challenge the size of the cost it has
    agreed to share.
    A similar misunderstanding underlies the Commission's
    second proposed distinction.  In United, it said, "[t]he relief
    that the objectors sought would require a different allocation
    than the one provided in the settlement."  
    Id. Rejection of
    the settlement was proper because the indirect customers'
    objections went "to the very basis of the settlement."  
    Id. Here, by
    contrast, Edison "can litigate its rate with El Paso,
    without affecting the consenting parties' rate."  
    Id. This appears
    simply to change the subject.  Of course the Com-
    mission's order lets Edison pursue its objections as a direct
    customer;  but that does not enable it to pursue them as an
    indirect customer, even though, so far as appears, they go "to
    the very basis of the settlement" every bit as much as the
    objections in United.
    Although not raised by the Commission, another possible
    distinction suggests itself.  The Commission's order denying
    rehearing in United, after recognizing the general interest of
    indirect customers in the allocation of costs to their immedi-
    ate upstream suppliers, see 64 FERC p 61,014 at 61,097,
    noted the particular unfairness possible if that settlement
    were approved over the indirect customers' objection:  since
    the downstream cost-allocation proceedings had not yet oc-
    curred, the indirect customers could have challenged the
    direct customers' acceptance of the settlement there, which if
    the challenge were successful would have left these direct
    customers "trapped" with higher costs than they could pass
    on.  
    Id. at 61,097-98.
     But the current situation seems to
    present at least as compelling a scenario:  instead of the
    customer in the middle being stuck because of the upstream
    settlement, the indirect customer (Edison) will be stuck with
    the fait accompli of the costs SoCal has agreed to bear.
    While United might perhaps be distinguished here, the
    Commission has not done so.
    * * *
    This court has also found indirect customers entitled to
    contest Commission-approved settlements.  Tejas Power
    Corp. v. FERC, 
    908 F.2d 998
    (D.C. Cir. 1990), held that the
    Commission erred in approving a settlement, over the objec-
    tions of indirect customers, solely on the basis of the direct
    customers' approval.  We found that these indirect custom-
    ers' challenge "triggers the Commission's obligation, under
    s 7 of the NGA and s 385.602(h)(1)(i) of its rules, to examine
    the potential impact of the [settlement] upon [the indirect
    customers'] interests and to support its conclusions with
    substantial evidence."  
    Id. at 1003.
    Of course the Commission might satisfy that obligation
    either by deciding on the merits any genuine issue of material
    fact or, if it were possible, executing a severance that would
    fully protect the objecting party's interests.  But Tejas Power
    allowed an alternative, saying that "the Commission must, at
    a minimum, address the question of whether the [direct
    customers'] interests are sufficiently likely to be congruent
    with those of ultimate consumers that it may rely upon the
    [direct customers'] agreement as dispositive of the consumers'
    interests."  
    Id. at 1004.
    The Commission can point to no such congruence of inter-
    ests here.  It mentioned three sets of parties that agreed to
    the settlement:  CPUC and its Nevada regulatory counter-
    part, El Paso's customers generally, and SoCal.  FERC's
    emphasis on the state commissions' agreement seems to be
    based on a misreading of Tejas Power.  We did in fact direct
    the Commission to look to the role of the states, but only in
    their capacity as downstream rate-setters, and thus as possi-
    ble wielders of power to protect the ultimate consumers from
    being "saddled with unwarranted expenses that the LDC may
    have had little incentive to avoid."  See 
    id. at 1004.
     The
    probability of such protection here has certainly not been
    established.  Nor do we see, given the usual limits of agency
    staff resources, why CPUC's approval could be deemed to
    rest on any more penetrating scrutiny than that of FERC
    itself.
    The support for the settlement from the bulk of El Paso's
    customers, while entitled to "some weight" with the Commis-
    sion, Laclede Gas Co. v. FERC, 
    997 F.2d 936
    , 946 (D.C. Cir.
    1993), is itself not enough, and would not be even if unani-
    mous, id.;  see also Tejas 
    Power, 908 F.2d at 1003
    .
    As to SoCal, finally, the Commission attempted to make a
    showing that met the standard of Tejas Power for using a
    direct customer as a surrogate for indirect ones--i.e., a
    finding that it had interests so "likely to be congruent with
    those of ultimate consumers that [the Commission] may rely
    upon [its] agreement as dispositive of the consumers' inter-
    ests, notwithstanding the claim of some large and sophisticat-
    ed consumers to the 
    contrary." 908 F.2d at 1004
    .  Endeavor-
    ing to show such alignment, the Commission wrote:
    We believe there is merit in El Paso's contention that as
    a result of recent decisions by the CPUC and the Califor-
    nia legislature, electric energy sold in the future in
    California is likely to be subject to market competition.
    LDCs in California may no longer be able to assume that
    they will be able to automatically pass through genera-
    tion costs, including gas costs, that they have incurred,
    and any regulatory shield that those LDCs might have
    enjoyed in the past may be diminished.  Thus, LDCs, at
    least in California, have an incentive, as do end-users, to
    negotiate the most favorable interstate rate.
    79 FERC p 61,028 at 61,130 (footnotes omitted).  This seems
    to us too confused to pass muster.  First, when the Commis-
    sion (or its opinion-writing staff) writes of an LDC having
    "incurred" "generation costs," it leads one to suspect it has
    not decided what industry it is describing--gas distribution or
    electricity generation.  Second, competition at the electricity
    generation level is completely consistent with the gas distrib-
    utor's possessing a monopoly.  The Commission's murmur-
    ings here are not enough to show a substantial congruity of
    interests.
    * * *
    The Commission has neither adequately distinguished its
    own precedents nor fulfilled the minimum requirements of
    ours.  We accordingly grant the petition for review and
    remand the case.
    So ordered.
    

Document Info

Docket Number: 97-1450

Citation Numbers: 162 F.3d 116, 333 U.S. App. D.C. 226

Judges: Edwards, Ginsburg, Williams

Filed Date: 12/11/1998

Precedential Status: Precedential

Modified Date: 8/3/2023