Dynegy Midwest Generation, Inc v. FERC ( 2011 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued December 3, 2010           Decided February 11, 2011
    No. 09-1306
    DYNEGY MIDWEST GENERATION, INC,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    FIRSTENERGY SOLUTIONS CORP., ET AL.,
    INTERVENORS
    Consolidated with 09-1308
    On Petitions for Review of Orders
    of the Federal Energy Regulatory Commission
    James K. Mitchell and Ashley C. Parrish argued the cause
    for petitioners. With them on the briefs was Neil L. Levy. A.
    Karen Hill and Michael J. Rustum entered appearances.
    Lona T. Perry, Senior Attorney, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With her on the brief were Thomas R. Sheets, General
    Counsel, and Robert H. Solomon, Solicitor.
    2
    Jeffrey G. DiSciullo, Wendy N. Reed, and David S.
    Berman were on the brief for intervenors Midwest ISO
    Transmission Owners in support of respondent.
    Before: SENTELLE, Chief Judge, BROWN, Circuit Judge,
    and WILLIAMS, Senior Circuit Judge.
    Opinion for the court filed by Senior Circuit Judge
    WILLIAMS.
    WILLIAMS, Senior Circuit Judge: The petitioners own
    and operate power generation facilities that are part of the
    Midwest Independent System Operator (“ISO”), a regional
    transmission organization. The generators supply two kinds
    of power: (1) “real power” of the sort we are all familiar with
    and use for running motors, lighting lamps, etc.; and (2)
    “reactive power,” a support service used to maintain adequate
    voltages to transmit real power, and to prevent damage such
    as overheating of generators and motors. See FERC STAFF
    REPORT, AD05-1-000, PRINCIPLES FOR EFFICIENT AND
    RELIABLE REACTIVE POWER SUPPLY AND CONSUMPTION 17-
    20               (2005),             available               at
    http://www.ferc.gov/eventcalendar/files/20050310144430-02-
    04-05-reactive-power.pdf. Inadequacies in reactive power can
    cause voltage collapse and blackouts. Id. at 20. Real power is
    sold to regular customers; reactive power is sold to the
    Midwest ISO and the cost passed on to transmission owners
    and operators. Midwest ISO Open Access Transmission and
    Energy Markets Tariff, Schedule 2, III. A & C.
    Before the orders in dispute here, generators within the
    Midwest ISO were compensated for all reactive power with
    cost-based rates, pursuant to Schedule 2 of the ISO’s tariff. In
    the challenged orders, FERC accepted a tariff amendment
    under which any transmission owner could elect an alternative
    rule of compensation, Schedule 2-A. Under that schedule, the
    3
    transmission owner would provide no compensation for
    reactive power produced within a specified range (the so-
    called “deadband” 1). (Transmission owners electing Schedule
    2-A would continue to pay for reactive power outside the
    deadband, though on a basis somewhat different from that of
    Schedule 2.) A transmission owner’s election between the
    two schedules would govern its compensation of all
    generators in its zone (and, in case of a multi-zone
    transmission owner, all its zones), affiliated and unaffiliated
    generators alike.
    The petitioners challenge the orders. Their primary
    contention is that allowance of the Schedule 2-A option was
    unduly discriminatory, as it would cause generators in
    different zones to be compensated differently, entirely at the
    untrammeled choice of each zone’s transmission owners, even
    though Midwest ISO generators compete with each other
    across zonal borders. Second, they contend that transmission
    owners were not authorized to file the new tariff under § 205
    of the Federal Power Act (“FPA”), 16 U.S.C. § 824d. We
    grant the petitions for review on the first objection but reject
    the second.
    * * *
    Historically, vertically integrated utilities could recover
    the costs for providing both real and reactive power through a
    single rate charged to customers. In 1996, FERC required
    utilities to functionally unbundle their generation and
    1
    The “deadband” is a range between a 0.95 “leading” power
    factor (reflecting the real/reactive ratio when the generator is
    consuming reactive power) and a 0.95 “lagging” power factor
    (reflecting the real/reactive ratio when the generator is supplying
    reactive power). Commission Br. 4-5.
    4
    transmission functions and to provide access to their
    transmission grid to customers on a non-discriminatory basis.
    See Promoting Wholesale Competition Through Open-Access
    Non-Discriminatory Transmission Services by Public
    Utilities, Order No. 888, 
    61 Fed. Reg. 21,540
     (May 10, 1996).
    The Commission ordered public utilities to offer ancillary
    services necessary for a reliable system (including reactive
    power supply), required transmission customers to purchase
    those services, 
    id. at 21
    ,580–82, and ordered that the rates
    paid to generators for reactive power be cost-based, 
    id. at 21,590
    .
    In two orders issued in 2003 and 2004, the Commission
    created the opportunity for transmission owners to select
    among alternative bases of compensation. First it found that,
    as a general matter, a generator should not be compensated for
    providing reactive power within a specified range, the
    deadband, “since it is only meeting its obligation [to do so].”
    See Standardization of Generator Interconnection Agreements
    and Procedures, Order No. 2003, 
    68 Fed. Reg. 49,846
     at
    49,891 (P 546) (Aug. 19, 2003) (“Order No. 2003”). But the
    Commission allowed ISOs and Regional Transmission
    Organizations to deviate from this principle. 
    Id. at 49,891
     (P
    548). On rehearing it made clear that if a transmission owner
    continued to pay its own or affiliated generators for reactive
    power service, the principle of “comparability” would require
    it to pay unaffiliated generators similarly.               See
    Standardization of Generator Interconnection Agreements
    and Procedures, Order No. 2003-A, 
    69 Fed. Reg. 15,932
     at
    15,964 (P 416) (Mar. 26, 2004) (“Order No. 2003-A”).
    The Midwest ISO is a regional transmission organization
    to which many of the public utilities in the Midwest
    transferred operational control over their transmission
    facilities.  Midwest Independent Transmission System
    Operator, Inc., 
    97 FERC ¶ 61,326
     (2001). It has designated
    5
    certain transmission pricing zones within its footprint which
    generally correspond to the boundaries of the transmission
    facilities of each participating transmission owner. Midwest
    ISO Transmission Owners, 
    122 FERC ¶ 61,305
    , P 1 & n.4
    (2008) (“Initial Order”). Transmission rates in different
    transmission zones may vary, but for a sale to any purchaser
    throughout the Midwest ISO, the transmission rate will be
    simply the price for the purchaser’s zone. Id.; Midwest ISO,
    
    84 FERC ¶ 61,231
     at 62,166 (1998) (explaining that the single
    rate is “based on the costs of the local service area where the
    point of delivery is located”).
    In October 2007, certain transmission owners in the
    Midwest ISO proposed a change in the ISO’s tariff that in
    effect exercised the option they believed had been created by
    Orders Nos. 2003 and 2003-A. Each transmission owner (or
    all transmission owners in a zone in the case of such multiple
    owners) could choose between Schedule 2 (cost-based
    compensation for all reactive power) and Schedule 2-A (no
    compensation for reactive power in the deadband, and
    somewhat different compensation for reactive power outside).
    Initial Order, P 1. FERC rejected a claim—raised only
    secondarily before us—that even if transmission owners in
    each zone compensated all the generators in their zone,
    affiliated and unaffiliated, on a comparable basis, granting
    transmission owners the right to choose would violate the
    comparability requirement developed in Orders Nos. 2003 and
    2003-A. Midwest ISO Transmission Owners, 
    129 FERC ¶ 61,041
    , P 78 (2009) (“Rehearing Order”). It paid virtually
    no attention to petitioners’ independent argument that its order
    allowed undue discrimination in violation of § 205(b) of the
    FPA, see, e.g., Request for Rehearing of Exelon Corporation
    at 5-12, treating it as merely a claim that some generators
    might be economically disadvantaged. See Rehearing Order,
    PP 91-97.
    6
    The petitioners object that comparability and absence of
    undue discrimination are not synonymous, and urge us to
    declare FERC’s orders to be in violation of § 205(b)’s anti-
    discrimination provision, as well as arbitrary and capricious
    and unsupported by substantial evidence.            
    5 U.S.C. § 706
    (2)(A), (E). They also argue that the filing of the tariff
    was (quite apart from FERC’s acceptance of it) without legal
    foundation.
    * * *
    Undue discrimination. Before reaching the merits of the
    petitioners’ discrimination claim, we must consider FERC’s
    objection that the petitioners’ challenge to Schedule 2-A was
    an impermissible collateral attack on the rule of comparability
    for reactive power tariffs as developed in Orders Nos. 2003
    and 2003-A—essentially an assertion that this court lacks
    jurisdiction to hear the discrimination claim. FPA § 313(b),
    16 U.S.C. § 825l(b) (giving this court jurisdiction only if an
    aggrieved party files a petition with the court within 60 days
    of the issuance of the order). FERC contends that petitioners
    failed to file a timely challenge to Orders Nos. 2003 and
    2003-A, which it now views as establishing the proposition
    that where “comparability” as defined in those orders is
    present, there can be no undue discrimination.
    Under § 313(b) the 60-day clock starts running only when
    “the agency has decided a question in a manner that
    reasonably puts aggrieved parties on notice of the rule’s
    content.” Southern Company Services, Inc. v. FERC, 
    416 F.3d 39
    , 44–45 (D.C. Cir. 2005) (citing RCA Global
    Communications, Inc. v. FCC, 
    758 F.2d 722
    , 730 (D.C. Cir.
    1985)). A petition is a “collateral attack only if a reasonable
    firm in [petitioners’] position would have perceived a very
    7
    substantial risk that the [order] meant what the Commission
    now says it meant.” Id. at 45 (internal quotations omitted).
    Those criteria are not satisfied here. In its Rehearing
    Order, FERC acknowledged that,
    prior to this case, the Commission has never evaluated a
    proposed tariff provision that allows all generators within
    a particular zone in an RTO—affiliated and
    unaffiliated—to collect reactive power compensation on
    one basis, while all generators in a different zone in the
    same RTO collect reactive power compensation on a
    different basis.
    Rehearing Order, P 71.
    Moreover, if Orders Nos. 2003 and 2003-A made it clear
    that satisfaction of the comparability requirement within each
    zone inherently and automatically meant satisfaction of the
    FPA’s anti-discrimination provisions, one would have
    expected the Commission to offer us some snippet from the
    orders advancing that idea. It offers no such thing.
    When FERC itself has acknowledged that the issue it was
    considering was new, and can point to no words expressing
    the supposedly governing principle, we cannot conclude that a
    reasonable petitioner would have perceived a “very substantial
    risk” that Orders Nos. 2003 and 2003-A meant what FERC
    now says they mean. Southern Company Services, Inc., 
    416 F.3d at 45
    . Thus petitioners are not mounting a collateral
    attack on Orders Nos. 2003 and 2003-A, and, equivalently,
    § 313(b) is no bar to our jurisdiction.
    We now turn to the merits of the discrimination claim. Its
    gist is that a compensation regime that allows transmission
    owners to choose whether or not to compensate generators for
    providing reactive power within the deadband will create
    8
    arbitrary differences in the competitive position of generators
    in different zones, and is thus unduly discriminatory under
    § 205(b) of the FPA.
    It is not altogether clear that the Commission understood
    petitioners’ discrimination complaint. It insisted that so long
    as the proposed Schedule 2-A requires transmission owners to
    treat affiliated and unaffiliated generators comparably, as
    required by Orders Nos. 2003 and 2003-A, resulting zonal
    variations in compensation would not be unduly
    discriminatory.       It analogized zonal reactive power
    compensation to zonal transmission rates and concluded that
    there was no discrimination because “customers are obligated
    to pay only one zonal rate.” Rehearing Order, P 81.
    This completely disregards the core of petitioners’ theory.
    Generators in the Midwest ISO compete across zonal
    boundaries. If transmission owners in one zone offer cost-
    based compensation for reactive power under Schedule 2,
    while transmission owners in another zone invoke Schedule 2-
    A and therefore withhold compensation for reactive power
    within the deadband, generators in the latter zone appear to be
    competitively disadvantaged.
    The Commission brushed this off, saying that
    independent power producers can “recover” the
    uncompensated reactive power cost “in their market-based
    power sales rates.” Rehearing Order, P 97.
    This appears to be a complete non-answer (or is based on
    a misconception of rudimentary economics). It is true, of
    course, that if generators did not compete across zonal lines,
    then all generators in each zone governed by Schedule 2-A
    would incur an uncompensated reactive power cost and none
    would be competitively disadvantaged in the relevant market.
    But the Commission acknowledged in oral argument that
    9
    generators can and do sell real power outside their own zones.
    Oral Arg. Recording 17:30-19:00. Generators that follow the
    Commission’s advice to raise their power sales rates would
    suffer an increased risk of being undersold by generators from
    zones where reactive power costs are compensated. The
    Commission has revealed no basis for its contention that
    generators in different zones are not “similarly situated” for
    purposes of receiving reactive power compensation. Initial
    Order, PP 49, 55; Rehearing Order, PP 59-60.
    In its Rehearing Order the Commission observed that it
    had “previously noted” that “the incremental cost to the
    generator of reactive power within the deadband is minimal.”
    Rehearing Order, P 96 (citing Bonneville Power Admin., 
    120 FERC ¶ 61,211
    , at P 21 (2007)). There is, however, no
    finding to that effect in this case, and no evidence in the case
    that would support such a finding. Indeed, the record contains
    one transmission owner’s estimate that shifting to Schedule 2-
    A would reduce its reactive power costs from over $11
    million to about $228,000. Affidavit of Greg M. Gudeman,
    October 1, 2007, at 9-10. Thus, if the Commission’s glancing
    remark expresses an intent to rely on a de minimis theory,
    which seems doubtful, there is no evidence, much less
    substantial evidence, to support it.
    A reader may wonder whether there may be less
    substance in all this than meets the eye. A generator’s
    competitive position would seem to depend on the sum of two
    costs: (1) its own generating and related costs, and (2) its costs
    in transmitting power. Uncompensated reactive power costs
    would fit in (1); if compensated by the transmission owner,
    they would seemingly justify an increase in transmission rates,
    and thus fit in (2). If the generating firm’s transmission costs
    were the charges for its zone, then generators who were paid
    by the local transmission company for reactive power would
    find the reactive power cost burdening them in their out-of-
    10
    zone sales just as much as it would with reactive power
    uncompensated. But as we explained above, all transmissions
    to any given customer are priced at the rate for that customer’s
    zone, so that in fact equal treatment of generators’ costs of
    supplying reactive power is critical to giving meaning to the
    zonal rate system’s apparent intent to assure competitive
    equality between generators.
    Accordingly, we grant the petitions for review as to their
    claim that the Commission’s orders violate § 205(b) of the
    FPA.
    Authority to file. The petitioners complain that FERC
    should not have accepted the filing of Schedule 2-A as a valid
    tariff filing under § 205 of the FPA. Transmission owners’
    rights to file tariff changes under § 205 have been modified by
    the Settlement Agreement Between Transmission Owners and
    Midwest ISO On Filing Rights (the “Filing Rights
    Settlement”). Its § 3.9 governs tariff filings for ancillary
    services:
    3.9 Ancillary Services Other Than Schedule 1—Both
    Transmission Owners that own or control generation or
    other resources capable of providing ancillary services
    (offered to customers pursuant to the [Open Access
    Transmission Tariff]) and the Midwest ISO shall have the
    right to submit filings under FPA section 205 to govern
    the rates, terms, and conditions applicable for the
    provision of ancillary services. . . . [A]ny ancillary
    service proposal with regional impacts shall be subject to
    the governance and coordination provisions of Sections 4
    and 5 of this Settlement Agreement [requiring
    transmission owners to decide by a majority vote to make
    a joint section 205 filing and to provide at least 30 day
    notice].
    11
    Filing Rights Settlement, § 3.9 (emphasis added).
    As § 3.9 gives filing rights to the Midwest ISO and to
    “Transmission Owners that own or control generation or other
    resources capable of providing ancillary services [including
    reactive power],” the petitioners argue that transmission
    owners may file reactive power tariffs only for services they
    provide.
    The Commission found § 3.9 ambiguous and noted that it
    appeared to draw no distinction between the filing rights of
    “Transmission Owners that own or control generation or other
    resources capable of providing ancillary services” and of the
    Midwest ISO itself. Petitioners’ proposed limitation would
    render the ISO’s filing rights meaningless, as it provides no
    “ancillary services.” Initial Order, P 24; Rehearing Order, PP
    6-7. The Commission also noted—persuasively, in our
    opinion—that the reference in § 3.9 to filings with “regional
    impacts” would be redundant if, as the petitioners say, the
    Filing Rights Settlement authorized transmission owners to
    make only those § 205 filings that pertain to their individual
    rates for reactive power. Id. at P 8.
    We find FERC’s conclusion that the Filing Rights
    Settlement gave transmission owners the right to file Schedule
    2-A to be reasonable.
    * * *
    In sum, though we uphold the Commission’s decision as
    to the transmission owners’ right to file the tariff amendment
    creating Schedule 2-A, the Commission’s approval of that
    change violated § 205(b)’s ban on undue discrimination and
    must be vacated.
    So ordered.
    

Document Info

Docket Number: 09-1306

Filed Date: 2/11/2011

Precedential Status: Precedential

Modified Date: 10/15/2015