Can Assn Petro v. FERC ( 2001 )


Menu:
  •                   United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued May 9, 2001       Decided July 13, 2001
    No. 96-1336
    Canadian Association of Petroleum Producers,
    Petitioner
    v.
    Federal Energy Regulatory Commission,
    Respondent
    Inland Pacific Energy Services Corporation, et al.,
    Intervenors
    Consolidated with
    97-1343
    ---------
    No. 99-1488
    Canadian Association of Petroleum Producers, et al.
    Petitioners
    v.
    Federal Energy Regulatory Commission,
    Respondent
    Northwest Pipeline Corporation, et al.,
    Intervenors
    Consolidated with
    00-1019, 00-1391, 00-1399
    On Petitions for Review of Orders of the
    Federal Energy Regulatory Commission
    James H. Holt argued the cause for petitioner Canadian
    Association of Petroleum Producers and supporting interve-
    nors Northwest Natural Gas Company, et al. in No. 96-1336.
    With him on the briefs were Jill M. Barker, Robert A.
    Nelson, Jr. and Paula E. Pyron. Sandra E. Rizzo and
    Edward A. Finklea entered appearances.
    Robert A. Nelson, Jr. argued the cause and filed the briefs
    for petitioner Northwest Natural Gas Company in No.
    97-1343.
    Judith A. Albert, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent in Nos. 96-1336
    and 97-1343.  With her on the brief were Jay L. Witkin,
    Solicitor at the time the brief was filed, and Susan J. Court,
    Special Counsel. Janet K. Jones, Attorney, entered an ap-
    pearance.
    Alex A. Goldberg argued the cause for intervenor North-
    west Pipeline Corporation in Nos. 96-1336 and 97-1343.
    With him on the brief was Steven W. Snarr.
    Robert A. Nelson Jr. argued the cause for petitioners in
    No. 99-1488 et al.  With him on the briefs were Edward A.
    Finklea and James H. Holt.
    Judith A. Albert, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent in No. 99-1488
    et al.  With her on the brief was Dennis Lane, Solicitor.
    Susan J. Court, Special Counsel, entered an appearance
    Alex A. Goldberg argued the cause for intervenor North-
    west Pipeline Corporation in No. 99-1488 et al.  With him on
    the brief were Steven W. Snarr and Timothy Muller.
    Before:  Williams, Ginsburg and Rogers, Circuit Judges.
    Williams, Circuit Judge:  On October 1, 1992 Northwest
    Pipeline Corporation ("Northwest") filed for a general rate
    increase under s 4 of the Natural Gas Act, 15 U.S.C. s 717c,
    to cover costs associated with a previously authorized expan-
    sion of its natural gas pipeline facilities.  The Federal Energy
    Regulatory Commission rejected certain proposed tariffs, ac-
    cepted and suspended other proposed tariffs subject to re-
    fund, and set an evidentiary hearing.  Almost a decade later,
    in two different consolidated cases, petitioners are seeking
    review of the relevant rate increase, which because of later
    filings by Northwest was in effect only from April 1, 1993
    through October 31, 1994.
    One of the cases involves issues that were resolved before
    we remanded to the Commission to consider the effect of a
    Commission policy change, the other involves issues resolved
    in the course of that remand.  The first, Nos. 96-1336 and
    97-1343 concerns five orders, the last of which issued in
    1997.1  The next year, in another proceeding, the Commis-
    __________
    1  The five are:  Opinion No. 396, 71 FERC p 61,253 (1995);
    Opinion No. 396-A, 76 FERC p 61,068 (1996);  78 FERC p 61,289
    (1997);  Opinion No. 396-B, 79 FERC p 61,309 (1997);  Opinion No.
    sion shifted positions on an important issue relating to the
    equity rate of return.  See Transcontinental Gas Pipe Line
    Corp., 84 FERC p 61,084 at 61,423 (1998), order on reh'g, 85
    FERC p 61,323 (1998), aff'd sub nom. North Carolina Utili-
    ties Comm'n v. FERC, 
    203 F.3d 53
     (D.C. Cir. 2000) (unpub-
    lished opinion).  Because of that shift, we remanded another
    case to the Commission for consideration of its possible effect.
    Williston Basin Interstate Pipeline Co. v. FERC, 
    165 F.3d 54
    , 62-63 (D.C. Cir. 1999).  The Commission then sought a
    remand in this case, which we granted.
    The later consolidated case, No. 99-1488 et al., involves the
    five orders issued after the remand.2  On July 14, 1999 the
    Commission promulgated the first such order, finding that
    Northwest was entitled to a re-weighting of the short- and
    long-term growth rates in the equity return calculation.  88
    FERC p 61,057 (1999) ("Initial Post Remand Order").  The
    Commission ordered Northwest to file a recalculation of its
    rates, a plan to impose surcharges to recover excess refunds
    under the previous rates, and pro forma tariff sheets that
    established the appropriate surcharges.  
    Id. at 61,146
    .  The
    Commission denied requests for rehearing.  88 FERC
    p 61,298 (1999) ("Initial Post Remand Order on Rehearing").
    Northwest filed its tariff sheets in August 1999, using for its
    rate of equity return the median rate of the proxy group.  On
    February 11, 2000 the Commission rejected Northwest's com-
    pliance filing because it used the wrong long-term growth
    rate, but approved its use of the median return on equity,
    stating that current Commission policy required the Commis-
    sion to select the median of the range of reasonable returns
    on equity instead of the midpoint that had been used earlier
    in the rate-making proceeding.  90 FERC p 61,146 at 61,468-
    __________
    396-C, 81 FERC p 61,036 (1997).  Unless stated otherwise, all
    FERC orders cited in this decision have the title "Northwest
    Pipeline Corporation."
    2  88 FERC p 61,057 (1999);  88 FERC p 61,298 (1999);  89
    FERC p 61,238 (1999);  90 FERC p 61,146 (2000);  92 FERC
    p 61,038 (2000).
    69 (2000) ("Median Rate Order").  The parties then agreed to
    a long-term growth rate.  The Commission denied rehearing
    on the median rate issue.  92 FERC p 61,038 (2000) ("Median
    Rate Order on Rehearing").
    Two parties, Northwest Natural Gas Company ("Northwest
    Natural"), a buyer of Northwest's gas, and the Canadian
    Association of Petroleum Producers ("CAPP"), a representa-
    tive of buyers, assert a variety of errors in the Commission's
    decisions.  We review the Commission's determinations under
    the Administrative Procedure Act's arbitrary and capricious
    standard.  See Missouri Public Service Comm'n v. FERC,
    
    215 F.3d 1
    , 3 (D.C. Cir. 2000);  5 U.S.C. s 706(2)(A).  We
    dismiss one claim for want of jurisdiction, we reverse and
    remand with respect to another claim, and we affirm on the
    remaining issues.  All of the petitioners' claims not addressed
    here have been considered and rejected.
    *  *  *
    The "just and reasonable" rates calculated by the Commis-
    sion under 15 U.S.C. s 717c(a) are typically based on a
    pipeline's costs.  Because several of the issues here revolve
    around one component, the cost of equity capital, we pause
    briefly to explain it.  Each year that a durable utility asset is
    in use imposes on the utility the annual cost of the capital
    used for its construction (net of amounts already recovered in
    depreciation charges).  In order to attract capital, a utility
    must offer a risk-adjusted expected rate of return sufficient
    to attract investors.  This return to investors is the cost to
    the utility of raising capital.  For the portion of capital
    acquired through bonds, the cost is comparatively easy to
    compute--the interest the company must pay its bondholders.
    Common equity is more complicated, for equity investors do
    not have a legally fixed return.  To calculate the rate of
    return necessary to attract them, the Commission measures
    the return enjoyed by the company's equity investors by the
    discounted cash flow ("DCF") model, which assumes that a
    stock's price is equal to the present value of the infinite
    stream of expected dividends discounted at a market rate
    commensurate with the stock's risk.  With simplifying as-
    sumptions, this can be summarized by the formula
    P = D/(r-g)
    where P is the price of the stock at the relevant time, D is the
    dividend to be paid at the end of the first year, r is the rate of
    return and g is the expected growth rate of the firm.  See
    Illinois Bell Telephone Co. v. FCC, 
    988 F.2d 1254
    , 1259 (D.C.
    Cir. 1993);  see also A. Lawrence Kolbe et al., The Cost of
    Capital:  Estimating the Rate of Return for Public Utilities
    53-55 (1984).  Since r is what the Commission is seeking, the
    equation is rearranged to the form
    r = D/P + g
    Illinois Bell, 
    988 F.2d at 1259
    .
    For a company that is not publicly traded, market-
    determined figures for P and D will be missing, and the
    Commission has recourse to calculating the implicit rate of
    return on companies that are comparable (or at least compa-
    nies whose business is predominately the operation of natural
    gas pipelines) and publicly traded.  These companies are
    called the "proxy group."  The Commission then makes ad-
    justments for specific characteristics of the company whose
    rates are in question.  Here, one of the issues involves a
    contention that Northwest's business risk was comparatively
    low (so that, petitioners argue, the Commission should have
    chosen a rate at the low end of those of the proxy group).
    Another issue involves calculation of the expected growth
    rates for the proxy group.  And a third, assuming that
    Northwest belongs in the middle of the proxy group, involves
    how to pick a number best representing the middle.
    *  *  *
    1.   Inclusion of Over-Run Costs in Rate Base
    In its expansion project Northwest added considerable
    mainline pipeline and compressor facilities and services.  Its
    original filing included $371.2 million in project costs but it
    ultimately persuaded the Commission to include about $61
    million more.  Because of decisions adverse to Northwest on
    other issues, the rates approved were lower than those for
    which it had originally filed.  See 71 FERC p 61,253 at
    61,992-95 (1995)("Opinion No. 396"), reversed in part and
    remanded, 76 FERC p 61,068 at 61,420-24 (1996) ("Opinion
    No. 396-A").
    Northwest Natural claims that Northwest should not be
    permitted to incorporate into its rate base costs that were not
    included in its original filing.  Its back-up position is that
    even if consideration of those costs was proper, the Commis-
    sion should have reopened proceedings to consider its claim
    that about $48 million in costs was not actually paid within
    the "test period" (twelve consecutive months used, with ad-
    justments, in estimating a pipeline's costs) and should have
    been excluded.
    On the first claim, Northwest Natural argues that an
    earlier Commission decision, Natural Gas Pipeline Co. of
    America, 38 FPC 1136 (1967), governs how the Commission
    must deal with cost figures that differ from those of the initial
    filing.  It places special reliance on a phrase of that decision
    saying that the regulations "bind Natural to its case-in-chief
    as submitted."  Id. at 1148.  The phrase is indeed there, but
    the Commission went on to make clear that there was no flat
    rule against new data;  instead it performed a contextual
    analysis.  There (1) the evidence did not fit the very limited
    subject of the hearing;  (2) because of that disjuncture there
    was a risk that other parties would reasonably assume that
    the evidence would not be considered (and accordingly these
    parties would lack effective notice);  and (3) the new cost
    evidence in fact did not meet the Commission's requirement
    that changes in costs after the test period be "known and
    measurable."  Id. at 1148-50 (internal quotation omitted).
    None of these characteristics was present here.  The Com-
    mission found that because Northwest's revised costs were
    disclosed prior to the filing of direct testimony in the hearing
    before the Administrative Law Judge, that the parties had
    ample notice of the cost claims, and that such claims, though
    estimates, were known and measurable.  See Opinion No.
    396-A, 76 FERC at 61,423-24.
    In its second claim Northwest Natural argues that the
    Commission unlawfully refused to reopen proceedings to hear
    its claim that Northwest had not actually paid all of the
    expansion costs within the test period.  The claim has two
    strikes against it.  First, although Northwest Natural was
    aware of the change in plant costs well before direct testimo-
    ny was filed in the ALJ hearing, it failed to raise the issue
    there, and did not do so until the record closed.  Id. at 61,420.
    Northwest Natural's justification for the delay, if any, is
    obscure.  Second, Northwest Natural's position on the merits
    depends on its effort to transform the Commission's general
    practice of not including costs paid after the test period into
    an absolute bar.  But the Commission has discretion to
    consider costs outside of the test period.  See, e.g., Exxon
    Corp. v. FERC, 
    114 F.3d 1252
    , 1263 (D.C. Cir. 1997).  Here it
    is uncontested that Northwest placed the expansion facilities
    in service before the end of the test period, i.e., just before
    the start of the period for which the rates were charged.
    Payment in some cases occurred after the end of the test
    period, but only because some bills had not been paid by that
    day, some incurred costs had not been billed, and some sums
    were withheld by Northwest pending final completion of the
    work.  See Nos. 96-1336 and 97-1343, Joint Appendix
    ("J.A.") at 390.
    Northwest Natural also claims discriminatory treatment in
    the Commission's reopening refusal, as the Commission did
    reopen proceedings to consider the long-term growth projec-
    tions.  But it did so exclusively in light of its own intervening
    decision in Ozark Gas Transmission System, 68 FERC
    p 61,032 at 61,105 (1994), announcing a new policy to include
    such projections.  Such an effort by the Commission to
    assure that it applies similar principles in simultaneously
    pending cases may be obligatory.  See Williston Basin, 
    165 F.3d at 61-63
    .  It supplies, in any event, an ample basis for
    the Commission's different treatment of the two requests for
    reopening.  Cf. American Financial Services Ass'n v. FTC,
    
    767 F.2d 957
    , 964-65 n.5 (D.C. Cir. 1985) (noting Commission
    discretion to reject belated claims).
    2.   Assessment of Northwest's Business Risk
    As part of its process to determine Northwest's rate, the
    Commission assessed Northwest's costs of capital.  This esti-
    mation required, under the DCF method that the Commission
    used, calculating the implicit equity rate of return for a proxy
    group of supposedly similar corporations, and then determin-
    ing where Northwest belonged within that group, in large
    part on the basis of Northwest's business risk.  CAPP com-
    plains that the Commission didn't adequately consider evi-
    dence suggesting that Northwest's business risk was in fact
    lower than the average of the proxy group, so that it erred in
    assigning Northwest a rate based on the middle of the proxy
    group range.  CAPP's theory was that Northwest was more
    like the "pure" pipeline companies within the proxy group,
    which had lower rates of return, than like the companies with
    more diversified operations.  We do not review the merits of
    CAPP's petition because it is procedurally barred.
    Four of the Commission's orders prior to our remand are
    relevant.  We start with a very simple summary of each
    relevant order, what it did, and the nature of CAPP's petition
    for rehearing in the instances where it filed one.
    Opinion No. 396.  The Commission rejected CAPP's
    contention that Northwest's business risk was below the
    average of the proxy group.  71 FERC p 61,253 at 61,992
    (1995).  CAPP petitioned for rehearing, raising the issue
    of business risk.
    Opinion No. 396-A. The Commission remanded the
    matter to the ALJ for development of a record on long-
    term growth rates.  76 FERC p 61,068 at 61,419 (1996).
    It said nothing at all about the business-risk issue.
    CAPP did not seek rehearing, but petitioned for review
    in this court of both Opinion No. 396 and Opinion No.
    396-A.
    Opinion No. 396-B. Following the proceedings before
    the ALJ, the Commission identified a new range of rates
    for the proxy companies and selected the mid-point of
    that range as appropriate for Northwest.  79 FERC
    p 61,309 at 62,384-86 (1997).  Northwest sought rehear-
    ing in a petition that did not mention the business risk
    issue.
    Opinion No. 396-C. The Commission disposed of the
    petitions for rehearing.  81 FERC p 61,036 (1997).
    Northwest petitioned for review here.
    The Commission argues that neither of the first two opin-
    ions, No. 396 or No. 396-A, was final, which is a prerequisite
    to our review.  See Transwestern Pipeline Co. v. FERC, 
    59 F.3d 222
    , 226 (D.C. Cir. 1995).  That seems obvious for
    Opinion No. 396-A, as it remanded the matter to an ALJ.
    See 
    id.
     ("An order is considered final when it imposes an
    obligation, denies a right, or fixes some legal relationship,
    usually at the consummation of an administrative process.")
    (internal quotation omitted).  Opinion No. 396 was presum-
    ably a final decision when issued, but when CAPP sought
    rehearing under s 19(a) of the Natural Gas Act, 15 U.S.C.
    s 717r(a) (as it was required to do if it wished to preserve its
    right to appeal, see s 19(b), 15 U.S.C. s 717r(b)), its petition
    suspended the finality of Opinion No. 396 as applied to CAPP
    and precluded appeal until the Commission fully resolved the
    rehearing request by way of another final order.  See Ten-
    nessee Gas Pipeline Co. v. FERC, 
    9 F.3d 980
    , 980-81 (D.C.
    Cir. 1993).  Cf. Bellsouth Corp. v. FCC, 
    17 F.3d 1487
    , 1489-90
    (D.C. Cir. 1994). Because Opinion No. 396-A itself was non-
    final, CAPP's petition for review of both decisions was juris-
    dictionally defective.
    CAPP did, however, seek review of Opinion No. 396-C,
    thereby bringing up issues properly preserved from Opinion
    No. 396-B. But was the business risk issue, raised only on
    rehearing of Opinion No. 396, preserved?  Section 19(b)'s
    rehearing requirement itself applies "not to the issue in-
    volved, but to the order that comes before us for review."
    Kansas Cities v. FERC, 
    723 F.2d 82
    , 85 (D.C. Cir. 1983)
    (construing materially identical language in s 313(a) of the
    Federal Power Act);  see also Arkansas Louisiana Gas Co. v.
    Hall, 
    453 U.S. 571
    , 577 n.7 (1981) (discussing established
    practice of citing interchangeably provisions of the Natural
    Gas Act and the Federal Power Act that are substantially
    identical in all material respects).  As our review applies only
    to final orders, all appealable claims must generally be set
    forth in a petition for review of the final order itself.  Of
    course, a party that has petitioned for rehearing and seen its
    petition denied without significant modification to the order
    may then proceed directly to court without filing a new
    petition for rehearing of the denial;  imposing an additional
    rehearing requirement in this situation would lead to infinite
    regress and serve no useful end.  See Town of Norwood v.
    FERC, 
    906 F.2d 772
    , 775 (D.C. Cir. 1990);  Southern Natural
    Gas Co. v. FERC, 
    877 F.2d 1066
    , 1072-73 (D.C. Cir. 1989);
    see also Kansas Cities, 
    723 F.2d at 86
    .  Similarly, if a party
    properly seeks rehearing and secures modification of some
    parts of an order, it may go directly to court on the issues as
    to which there was no modification without seeking rehearing
    again on those issues;  only on matters where the rehearing
    order introduces a new source of complaint need the party
    file another rehearing petition.  Norwood, 
    906 F.2d at 775
    ;
    Tennessee Gas Pipeline Co. v. FERC, 
    871 F.2d 1099
    , 1109-10
    (D.C. Cir. 1989).  And we will assume without deciding that if
    a party does raise such new issues on rehearing it need not
    include its old complaints about the unmodified parts.
    In the present case, however, several stages of agency
    review and modification separate Opinion No. 396-B from
    CAPP's petition for rehearing of Opinion No. 396--proceed-
    ings before the ALJ on the long-term/short-term weighting
    issue, followed by Commission resolution of that issue and its
    selection of a new equity rate of return for Northwest.
    Enforcement of the rehearing requirement in this context
    serves not merely to inform the Commission of issues that
    may be appealed, but ensures certainty in the dispute pro-
    cess, apprising potentially settling parties of what issues
    remain contested.  See ASARCO, Inc. v. FERC, 
    777 F.2d 764
    , 773-74 (D.C. Cir. 1985).  We note, moreover, that CAPP
    does not argue, nor do we see any basis for finding, that its
    failure to preserve its right to appeal was justified under the
    "reasonable ground" exception to Section 19(b)'s rehearing
    requirement.  Accordingly, CAPP's petition is dismissed for
    lack of jurisdiction.
    3.   Weighting of Short- and Long-Term Growth Rates.
    On remand, the Commission changed the weighting of
    short- and long-term growth rates, now giving short-term
    rates twice the weight of long-term ones, rather than weight-
    ing them equally as before.  The petitioners claim that the
    Commission failed to explain its decision generally or to
    distinguish Ozark Gas Transmission System, 68 FERC
    p 61,032 (1994), where the Commission approved an equal
    weighting of all years of an 18-year period.  Id. at 61,107
    n.46.  To explain its decision, the Commission quoted its
    reasoning in Transcontinental Gas Pipe Line Corp., 84
    FERC p 61,084 at 61,423 (1998):
    [W]hile determining the cost of equity nevertheless re-
    quires that a long-term evaluation be taken into account,
    long-term projections are inherently more difficult to
    make, and thus less reliable, than short-term projections.
    Over a longer period, there is a greater likelihood for
    unanticipated developments to occur affecting the projec-
    tion.  Given the greater reliability of the short-term
    projection, we believe it is appropriate to give it greater
    weight.  However, continuing to give some effect to the
    long-term growth projection will aid in normalizing any
    distortions that might be reflected in short-term data
    limited to a narrow segment of the economy.
    Initial Post Remand Order, 88 FERC at 61,144;  see also
    Initial Post Remand Order on Rehearing, 88 FERC at 61,910.
    The Commission was obviously aware that the apparent
    relative reliability of short-term growth projections (due to
    temporal proximity) was to some degree offset by variability;
    it decided to use the long-term projections to "normaliz[e] any
    distortions" in the short-term expectations.  In an exercise so
    hard to limit by strict rules, it would likely be difficult to show
    that the Commission abused its discretion in the weighting
    choice.  Certainly petitioners offer no reason for us to find
    that it has done so here.  Its reason for giving extra weight
    to the short-term estimates implicitly justified its change
    from Ozark.
    4.   Choice of the Median Rate of Return on Equity.
    On remand the Commission also changed its method of
    selecting an equity rate of return from the array of rates of
    the proxy group.  Before the remand it had chosen the
    "midpoint" rate of the group--the average of the single
    lowest and single highest rates.  See Tennessee Gas Pipeline
    Co. v. FERC, 
    926 F.2d 1206
    , 1213 (D.C. Cir. 1991) (stating
    that the midpoint is a "starting place").  When Northwest
    submitted its pro forma tariff sheets as mandated by the
    Commission's July 14, 1999 order, however, it recalculated its
    rates using the median of the proxy group (the middle rate
    out of the five), which the Commission approved.  See Medi-
    an Rate Order, 90 FERC at 61,468.  When the short- and
    long-term growth rates had been equally weighted, the mid-
    point rate was higher than the median rate, leading to a
    higher overall pipeline rate.  With the change in weighting,
    the reverse was true.  See Median Rate Order on Rehearing,
    92 FERC at 61,095, 61,101.  Petitioners estimate that the
    difference between the midpoint (13.33%) and median
    (13.67%) spells $3.2 million in added charges.  They raise two
    objections.  First, they claim that the Commission had no
    authority to reconsider how it selected a rate from the proxy
    group under the scope of our remand.  Second, they argue
    that the Commission's choice of the median was unreasonable.
    We remanded to the Commission to enable it "to reconsider
    its decisions in light of Williston Basin v. FERC, 
    165 F.3d 54
    (D.C. Cir. 1999)."  See Canadian Ass'n of Petroleum Produc-
    ers v. FERC, No. 96-1336 (D.C. Cir. Mar. 26, 1999) (order
    remanding case), Petitioners' Br. at Addendum B.  This
    prescribed affirmatively what the Commission was required
    to do--reconsider the weighting issue that was directly affect-
    ed by Williston.  But under our cases such a remand restores
    jurisdiction to the Commission and "discretion to reconsider
    the whole of its original decision."  Southeastern Michigan
    Gas Co. v. FERC, 
    133 F.3d 34
    , 38 (D.C. Cir. 1998).  Because
    the Commission was within its authority to reconsider which
    rate of return to use, we reach the question whether the
    Commission provided a reasoned explanation for choosing the
    median over the midpoint or alternatively the mean.
    The Commission's orders and brief speak only to the choice
    between median and midpoint.  Its orders pointed to the
    Transcontinental decision, where, besides changing the
    weighting of short- and long-term growth factors, it also
    selected the median instead of the midpoint.  But it supplied
    only the most limited reasoning there.  See Transcontinental
    Gas Pipe Line Corp., 84 FERC at 61,427-5.  The Commis-
    sion essentially reiterated its Transcontinental reasoning in
    this case:
    [U]se of the median gives consideration to more of the
    proxy company numbers.  The median is the point at
    which half of the numbers are higher and half are lower.
    The midpoint, on the other hand, merely represents an
    average of the highest and lowest of the numbers and
    completely disregards the middle three numbers.
    Median Rate Order on Rehearing, 92 FERC at 61,095.
    To a large extent this "explanation" merely describes the
    differences in calculating the median and the midpoint.  Inso-
    far as it seeks to justify on the basis of the number of
    numbers considered, it is not wholly accurate.  The midpoint
    doesn't "completely disregard[ ] the middle three numbers";
    the highest and lowest numbers achieve their status by
    reference to all five numbers.  But even if acceptable as an
    explanation for choosing the median over the midpoint, it fails
    as an explanation for rejecting petitioners' proposal that the
    Commission use the simple arithmetic mean (either of all five,
    or of the middle three companies of the proxy group).  See
    No. 99-1488 et al., J.A. at 105, 171, 192-93.  The mean of the
    five, after all, rather directly "uses" all the numbers and
    weights them all equally, as petitioners pointed out.  Id. at
    192-93.
    The Commission simply dismissed the alternative proposal
    in conclusory terms.  See Median Rate Order, 90 FERC at
    61,468;  Median Rate Order on Rehearing, 92 FERC at
    61,094.  Counsel for Northwest suggested at oral argument
    that there was Commission precedent for the view that the
    median is to be preferred to the average "as a [measure] of
    central tendency in cases in which the distribution is highly
    skewed."  See No. 99-1488 et al., Oral Arg. Tr. at 22.  But
    the Commission never offered such an explanation, and coun-
    sel did not offer an analysis of Commission precedents from
    which we could infer that the "skewing" here was such that
    choice of the median was foreordained.  See SEC v. Chenery
    Corp., 
    332 U.S. 194
    , 196 (1947);  cf. Health & Medicine Policy
    Research Group v. FCC, 
    807 F.2d 1038
    , 1045 (D.C. Cir. 1986).
    The Commission's failure to respond meaningfully to calls
    for using an average rate of all or of three of the proxy group
    companies renders its decision to use the median rate arbi-
    trary and capricious.  See City of Brookings Municipal
    Telephone Co. v. FCC, 
    822 F.2d 1153
    , 1169 (D.C. Cir. 1987).
    Unless the Commission answers objections that on their face
    seem legitimate, its decision can hardly be classified as rea-
    soned.  See International Harvester Co. v. Ruckelshaus, 
    478 F.2d 615
    , 648 (D.C. Cir. 1973);  see also Tesoro Alaska
    Petroleum Co. v. FERC, 
    234 F.3d 1286
    , 1294 (D.C. Cir. 2000).
    We thus reverse and remand the case to the Commission for
    reconsideration of its choice of the proxy group's median rate.
    5.   Imposition of Surcharges
    The Commission determined on remand that it had improp-
    erly reduced Northwest's rates in its first series of orders and
    consequently ordered Northwest to impose surcharges to
    recover those excess refunds from its shippers.  Petitioners
    claim that the surcharges violated the filed rate doctrine,
    "which forbids a regulated entity to charge rates for its
    services other than those properly filed with the appropriate
    federal regulatory authority," Arkansas Louisiana Gas Co.,
    
    453 U.S. at 577
    , and are thus unauthorized.  Petitioners make
    no claim that the ultimately effective rate (net of refunds and
    surcharges) exceeded that of Northwest's original filing.
    Petitioners rely on Natural Gas Clearinghouse v. FERC,
    
    965 F.2d 1066
     (D.C. Cir. 1992), to argue that Northwest could
    not collect surcharges unless it had explicitly reserved its
    right to impose surcharges under the tariffs that produced
    the refunds.  But petitioners read too much into Clearing-
    house.  Although the pipeline in that case had specifically
    reserved the right to impose surcharges when it was ordered
    to file a new, lower tariff, we did not hold that such a
    reservation was necessary.  So long as the parties had ade-
    quate notice that surcharges might be imposed in the future,
    imposition of surcharges does not violate the filed rate doc-
    trine.  "The filed rate doctrine simply does not extend to
    cases in which buyers are on adequate notice that resolution
    of some specific issue may cause a later adjustment to the
    rate being collected at the time of service."  
    Id. at 1075
    .  (It
    is not even clear that the refunds were paid during the period
    service was actually being provided under the "locked-in" rate
    at issue here.  But petitioners lose whether they were or
    were not.)  The Commission reasonably concluded that
    Northwest's initial rate filing--combined with the ongoing
    litigation and absence of a final, non-appealable order--pro-
    vided the necessary notice to the shippers that they might
    have to pay rates up to the level originally filed.  See Western
    Resources, Inc. v. FERC, 
    72 F.3d 147
    , 151 (D.C. Cir. 1995).
    *  *  *
    CAPP's petition for review is dismissed for want of juris-
    diction on the business-risk issue.  The case is reversed and
    remanded to the Commission for further consideration of the
    selection of the median rate of return on equity from the
    proxy group.  Otherwise, the petitions are denied.
    So ordered.
    

Document Info

Docket Number: 96-1336

Filed Date: 7/13/2001

Precedential Status: Precedential

Modified Date: 12/21/2014

Authorities (22)

Tennessee Gas Pipeline Company v. Federal Energy Regulatory ... , 9 F.3d 980 ( 1993 )

MO Pub Svc Cmsn v. FERC , 215 F.3d 1 ( 2000 )

Exxon Corporation v. Federal Energy Regulatory Commission, ... , 114 F.3d 1252 ( 1997 )

Kansas Cities v. Federal Energy Regulatory Commission, ... , 723 F.2d 82 ( 1983 )

Tesoro Alaska Petroleum Co. v. Federal Energy Regulatory ... , 234 F.3d 1286 ( 2000 )

bellsouth-corporation-bellsouth-enterprises-inc-and-mobile , 17 F.3d 1487 ( 1994 )

tennessee-gas-pipeline-company-v-federal-energy-regulatory-commission , 926 F.2d 1206 ( 1991 )

southern-natural-gas-company-v-federal-energy-regulatory-commission-texas , 877 F.2d 1066 ( 1989 )

city-of-brookings-municipal-telephone-company-v-federal-communications , 822 F.2d 1153 ( 1987 )

american-financial-services-association-v-federal-trade-commission-silas , 767 F.2d 957 ( 1985 )

international-harvester-company-v-william-d-ruckelshaus-administrator , 478 F.2d 615 ( 1973 )

natural-gas-clearinghouse-v-federal-energy-regulatory-commission-anadarko , 965 F.2d 1066 ( 1992 )

tennessee-gas-pipeline-company-v-federal-energy-regulatory-commission , 871 F.2d 1099 ( 1989 )

asarco-inc-inspiration-consolidated-copper-company-and-kennecott , 777 F.2d 764 ( 1985 )

Town of Norwood, Massachusetts v. Federal Energy Regulatory ... , 906 F.2d 772 ( 1990 )

Transwestern Pipeline Company v. Federal Energy Regulatory ... , 59 F.3d 222 ( 1995 )

Western Resources, Inc. v. Federal Energy Regulatory ... , 72 F.3d 147 ( 1995 )

Williston Basin Interstate Pipeline Co. v. Federal Energy ... , 165 F.3d 54 ( 1999 )

Midland Cogn Vntrs v. FERC , 133 F.3d 34 ( 1998 )

illinois-bell-telephone-company-indiana-bell-telephone-company , 988 F.2d 1254 ( 1993 )

View All Authorities »