Mingo Logan Coal Co. v. United States Environmental Protection Agency , 714 F.3d 608 ( 2013 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued March 14, 2013                 Decided April 23, 2013
    No. 12-5150
    MINGO LOGAN COAL COMPANY,
    APPELLEE
    v.
    UNITED STATES ENVIRONMENTAL PROTECTION AGENCY,
    APPELLANT
    Appeal from the United States District Court
    for the District of Columbia
    (No. 1:10-cv-00541)
    Matthew Littleton, Attorney, United States Department of
    Justice, argued the cause for the appellant. Aaron P. Avila,
    Mark R. Haag, Cynthia J. Morris and Kenneth C. Amaditz,
    Attorneys, United States Department of Justice, and Stefania
    D. Shamet, Attorney, United States Environmental Protection
    Agency, were on brief.
    Emma C. Cheuse, Jennifer C. Chavez and Benjamin A.
    Luckett were on brief for amici curiae West Virginia
    Highland Conservancy et al. in support of the appellant.
    Robert M. Rolfe argued the cause for the appellee.
    George P. Sibley III, Virginia S. Albrecht and Deidre G.
    Duncan were on brief.
    2
    Kathryn Kusske Floyd and Jay C. Johnson were on brief
    for amici curiae Chamber of Commerce of the United States
    of America et al. in support of the appellee.
    Michael A. Carvin and Kevin P. Holewinski were on brief
    for amicus curiae United Company in support of the appellee.
    Benjamin L. Bailey and Michael B. Hissam were on brief
    for amicus curiae Randy Huffman in support of the appellee.
    Thanos Basdekis entered an appearance.
    Before: HENDERSON, GRIFFITH and KAVANAUGH, Circuit
    Judges.
    Opinion for the Court filed by Circuit Judge HENDERSON.
    KAREN LECRAFT HENDERSON, Circuit Judge: The Mingo
    Logan Coal Company (Mingo Logan) applied to the United
    States Army Corps of Engineers (Corps) for a permit under
    section 404 of the Clean Water Act (CWA), 33 U.S.C. § 1344,
    to discharge dredged or fill material from a mountain-top coal
    mine in West Virginia into three streams and their tributaries.
    The Corps—acting on behalf of the Secretary of the Army
    (Secretary) and without objection from the Administrator of
    the United States Environmental Protection Agency
    (Administrator, EPA), who has “veto” authority over
    discharge site selection under CWA subsection 404(c), 33
    U.S.C. § 1344(c)—issued the permit to Mingo Logan,
    approving the requested disposal sites for the discharged
    material. Four years later, EPA invoked its subsection 404(c)
    authority to “withdraw” the specifications of two of the
    streams as disposal sites, thereby prohibiting Mingo Logan
    from discharging into them. Mingo Logan filed this action
    challenging EPA’s withdrawal of the specified sites on the
    grounds that (1) EPA lacks statutory authority to withdraw
    site specification after a permit has issued and (2) EPA’s
    decision to do so was arbitrary and capricious in violation of
    the Administrative Procedure Act (APA), 5 U.S.C. §§ 701 et
    3
    seq. The district court granted summary judgment to Mingo
    Logan on the first ground without reaching the second. We
    reverse the district court concluding that EPA has post-permit
    withdrawal authority, and remand for further proceedings.
    I.
    The CWA provides that “the discharge of any pollutant by
    any person shall be unlawful” except as in compliance with
    specifically enumerated CWA provisions, including section
    404.1 33 U.S.C. § 1311(a). Subsection 404(a) authorizes the
    Secretary to issue permits allowing discharge of dredged or
    fill material “at specified disposal sites,” which are to be
    “specified for each such permit by the Secretary . . . through
    the application of guidelines developed by the Administrator,
    in conjunction with the Secretary.” Id. § 1344(a), (b). The
    Secretary’s authority to specify a disposal site is expressly
    made “[s]ubject to subsection (c) of [section 404].” Id.
    § 1344(b). Subsection 404(c) authorizes the Administrator,
    after consultation with the Corps, to veto the Corps’s disposal
    site specification—that is, the Administrator “is authorized to
    prohibit the specification (including the withdrawal of
    1
    Under the CWA, “discharge of a pollutant” means “any addition
    of any pollutant to navigable waters from any point source,” 33 U.S.C.
    § 1362(12); “pollutant,” in turn, “means dredged spoil, solid waste,
    incinerator residue, sewage, garbage, sewage sludge, munitions,
    chemical wastes, biological materials, radioactive materials, heat,
    wrecked or discarded equipment, rock, sand, cellar dirt and industrial,
    municipal, and agricultural waste discharged into water,” id.
    § 1362(6). CWA section 404 authorizes the Secretary, acting through
    the Corps, to issue permits for the discharge of dredged and fill
    material, while section 402 authorizes EPA to issue permits for the
    discharge of other pollutants. Nat’l Ass’n of Home Builders v. EPA,
    
    667 F.3d 6
    , 10 (D.C. Cir. 2011) (citing Nat’l Ass’n of Home Builders
    v. U.S. Army Corps of Eng’rs, 
    440 F.3d 459
    , 461 n.1 (D.C. Cir.
    2006)).
    4
    specification) of any defined area as a disposal site, and . . . to
    deny or restrict the use of any defined area for specification
    (including the withdrawal of specification) as a disposal
    site”—“whenever he determines” the discharge will have an
    “unacceptable adverse effect” on identified environmental
    resources. Id. § 1344(c).
    In June 1999, Hobet Mining, Inc., Mingo Logan’s
    predecessor, applied for a section 404 permit to discharge
    material from the Spruce No. 1 Mine into four West Virginia
    streams and their tributaries. In 2002, after the Corps
    prepared a draft Environmental Impact Statement, EPA
    expressed its concern that “even with the best practices,
    mountaintop mining yields significant and unavoidable
    environmental impacts that had not been adequately described
    in the document.” Letter from EPA, Region III to Corps,
    Huntington Dist., at 1 (June 16, 2006) (JA 617). In the end,
    however, EPA declined to pursue a subsection 404(c)
    objection. Email from EPA to Corps (Nov. 2, 2006) (JA 982)
    (“[W]e have no intention of taking our Spruce Mine concerns
    any further from a Section 404 standpoint . . . .”). On January
    22, 2007, the Corps issued Mingo Logan a section 404 permit,
    effective through December 31, 2031, which authorized
    Mingo Logan to dispose of material into three
    streams—Pigeonroost Branch, Oldhouse Branch and Seng
    Camp Creek—and certain tributaries thereto. Dep’t of the
    Army Permit No. 199800436-3 (JA 984) (Spruce Mine
    Permit). The permit expressly advised that the Corps “may
    reevaluate its decision on the permit at any time the
    circumstances warrant” and that “[s]uch a reevaluation may
    result in a determination that it is appropriate to use the
    suspension, modification, and revocation procedures
    contained in 33 CFR 325.7.” Id. at 3 (JA 986). The permit
    made no mention of any future EPA action.
    5
    On September 3, 2009, EPA wrote the Corps requesting it
    “use its discretionary authority provided by 33 CFR 325.7 to
    suspend, revoke or modify the permit issued authorizing
    Mingo Logan Coal Company to discharge dredged and/or fill
    material into waters of the United States in conjunction with
    the construction, operation, and reclamation of the Spruce
    Fork No. 1 Surface Mine,” based on “new information and
    circumstances . . . which justif[ied] reconsideration of the
    permit.” Letter from EPA, Region III to Corps, Huntington
    Dist., at 1 (Sept. 3, 2009) (JA 941). EPA noted in particular
    its “concern[] about the project’s potential to degrade
    downstream water quality.” Id. The Corps responded that
    there were “no factors that currently compell[ed it] to consider
    permit suspension, modification or revocation.” Letter from
    Corps, Huntington Dist. to EPA, Region III, at 2 (Sept. 30,
    2009) (JA 950). EPA wrote back: “We intend to issue a
    public notice of a proposed determination to restrict or
    prohibit the discharge of dredged and/or fill material at the
    Spruce No. 1 Mine project site consistent with our authority
    under Section 404(c) of the Clean Water Act and our
    regulations at 40 C.F.R. Part 231.” Letter from EPA, Region
    III to Corps, Huntingdon Dist., at 1 (October 16, 2009) (Supp.
    JA 1).
    EPA’s Regional Director published the promised notice
    of proposed determination on April 2, 2010, requesting public
    comments “[p]ursuant to Section 404(c) . . . on its proposal to
    withdraw or restrict use of Seng Camp Creek, Pigeonroost
    Branch, Oldhouse Branch, and certain tributaries to those
    waters in Logan County, West Virginia to receive dredged
    and/or fill material in connection with construction of the
    Spruce No. 1 Surface Mine.” Proposed Determination, 75
    Fed. Reg. 16,788, 16,788 (Apr. 2, 2010). The Regional
    Director followed up with a Recommended Determination on
    September 24, 2010, limited to withdrawal of the
    specification of Pigeonroost Branch and Oldhouse Branch and
    6
    their tributaries. On January 13, 2011, EPA published its
    Final Determination, which, adopting the Regional Director’s
    recommendation, formally “withdraws the specification of
    Pigeonroost Branch, Oldhouse Branch, and their tributaries,
    as described in [the Spruce Mine Permit] . . . as a disposal site
    for the discharge of dredged or fill material for the purpose of
    construction, operation, and reclamation of the Spruce No. 1
    Surface Mine” and “prohibits the specification of the defined
    area . . . for use as a disposal site associated with future
    surface coal mining that would be expected to result in a
    nature and scale of adverse chemical, physical, and biological
    effects similar to the Spruce No. 1 mine.”                 Final
    Determination of the Assistant Administrator for Water
    Pursuant to Section 404(c) of the Clean Water Act
    Concerning the Spruce No. 1 Mine, Logan County, WV, 76
    Fed. Reg. 3126, 3128 (Jan. 19, 2011).
    Mingo Logan filed this action in district court
    immediately following the Proposed Determination,
    challenging EPA’s authority to “revoke” the three-year-old
    permit, Compl., ¶ 75, Mingo Logan Coal Co. v. U.S. EPA,
    C.A. No. 10-00541 (D.D.C. Apr. 2, 2010), and amended its
    complaint in February 2011 to challenge the Final
    Determination, asserting it is both ultra vires and arbitrary and
    capricious. Am. Compl., Mingo Logan Coal (Feb. 28, 2011).
    On cross-motions for summary judgment, the district
    court granted judgment to Mingo Logan on March 23, 2012.
    Mingo Logan Coal Co. v. U.S. EPA, 
    850 F. Supp. 2d 133
    (D.D.C. 2012). The court concluded EPA “exceeded its
    authority under section 404(c) of the Clean Water Act when it
    attempted to invalidate an existing permit by withdrawing the
    specification of certain areas as disposal sites after a permit
    had been issued by the Corps under section 404(a).” Id. at
    134. The United States filed a timely notice of appeal on
    7
    behalf of EPA. The Corps joined EPA on brief.                    See
    Appellant Br. & Reply Br.
    II.
    In granting summary judgment, the district court agreed
    with Mingo Logan’s interpretation of subsection 404 to
    preclude EPA from withdrawing a site specification once the
    Corps has issued a permit. “We review a grant of summary
    judgment de novo applying the same standards as those that
    govern the district court’s determination.” Troy Corp. v.
    Browner, 
    120 F.3d 277
    , 283 (D.C. Cir. 1997). “Moreover,
    insofar as the agency’s determination amounts to or involves
    its interpretation of . . . a statute entrusted to its administration,
    we review that interpretation under the deferential standard of
    Chevron U.S.A. Inc. v. Natural Resources Defense Council,
    Inc., 
    467 U.S. 837
     (1984).” Id. Under Chevron:
    We first ask “whether Congress has directly spoken
    to the precise question at issue,” in which case we
    “must give effect to the unambiguously expressed
    intent of Congress.” If the “statute is silent or
    ambiguous with respect to the specific issue,”
    however, we move to the second step and defer to the
    agency’s interpretation as long as it is “based on a
    permissible construction of the statute.”
    Natural Res. Def. Council v. EPA, 
    706 F.3d 428
    , 431 (D.C.
    Cir. 2013) (quoting Chevron, 467 U.S. at 842–43). We
    construe subsection 404(c) under Chevron step 1 because we
    believe the language unambiguously expresses the intent of
    the Congress.
    As noted earlier, see supra p. 3, section 404 vests the
    Corps, rather than EPA, with the authority to issue permits to
    discharge fill and dredged material into navigable waters and
    to specify the disposal sites therefor. See 33 U.S.C. § 1344(a)-
    (b); see Senate Consideration of the Report of the Conference
    8
    Committee, 1 A Legislative History of the Water Pollution
    Control Act Amendments of 1972 (Legislative History) 161,
    177 (Jan. 1973) (Statement of Sen. Edmund Muskie, 118
    Cong. Rec. at 33,699 (Oct. 4, 1972)) (Senate Committee “had
    reported a bill which treated the disposal of dredged spoil like
    any other pollutant” but Conference Committee adopted
    provisions of House bill that “designated the Secretary of the
    Army rather than the Administrator of the Environmental
    Protection Agency as the permit issuing authority”).
    Nonetheless, the Congress granted EPA a broad environmental
    “backstop” authority over the Secretary’s discharge site
    selection in subsection 404(c), which provides in full:
    (c) Denial or restriction of use of defined areas as
    disposal sites
    The Administrator is authorized to prohibit the
    specification (including the withdrawal of
    specification) of any defined area as a disposal site,
    and he is authorized to deny or restrict the use of any
    defined area for specification (including the
    withdrawal of specification) as a disposal site,
    whenever he determines, after notice and opportunity
    for public hearings, that the discharge of such
    materials into such area will have an unacceptable
    adverse effect on municipal water supplies, shellfish
    beds and fishery areas (including spawning and
    breeding areas), wildlife, or recreational areas.
    Before making such determination, the Administrator
    shall consult with the Secretary. The Administrator
    shall set forth in writing and make public his findings
    and his reasons for making any determination under
    this subsection.
    33 U.S.C. § 1344(c); see Legislative History at 177 (“[T]he
    Conferees agreed that the Administrator . . . should have the
    veto over the selection of the site for dredged spoil disposal
    9
    and over any specific spoil to be disposed of in any selected
    site.”).2 Section 404 imposes no temporal limit on the
    Administrator’s authority to withdraw the Corps’s
    specification but instead expressly empowers him to prohibit,
    restrict or withdraw the specification “whenever” he makes a
    determination that the statutory “unacceptable adverse effect”
    will result. 33 U.S.C. § 1344(c) (emphasis added). Using the
    expansive conjunction “whenever,” the Congress made plain
    its intent to grant the Administrator authority to
    prohibit/deny/restrict/withdraw a specification at any time.
    2
    Thus, subsection 404(c) affords EPA two distinct (if
    overlapping) powers to veto the Corps’s specification: EPA may (1)
    “prohibit the specification (including the withdrawal of specification)
    of any defined area as a disposal site” or (2) “deny or restrict the use
    of any defined area for specification (including the withdrawal of
    specification).” In withdrawing the specifications here, EPA did not
    clearly distinguish between the two powers. See Final Determination,
    76 Fed. Reg. at 3127 (“EPA Region III published in the Federal
    Register a Proposed Determination to prohibit, restrict, or deny the
    specification or the use for specification (including withdrawal of
    specification) of certain waters at the project site as disposal sites for
    the discharge of dredged or fill material for the construction of the
    Spruce No. 1 Surface Mine.”). It appears, however, that EPA
    exercised the first authority—“to prohibit”/“withdraw[]”—given the
    post-permit timing. See id. at 3128 (“EPA’s Final Determination
    withdraws the specification of Pigeonroost Branch, Oldhouse Branch,
    and their tributaries, as described in DA Permit No. 199800436-3
    (Section 10: Coal River), as a disposal site for the discharge of
    dredged or fill material for the purpose of construction, operation, and
    reclamation of the Spruce No. 1 Surface Mine. This Final
    Determination also prohibits the specification of the defined area
    constituting Pigeonroost Branch, Oldhouse Branch, and their
    tributaries for use as a disposal site associated with future surface coal
    mining that would be expected to result in a nature and scale of
    adverse chemical, physical, and biological effects similar to the Spruce
    No. 1 mine.”).
    10
    See 20 Oxford English Dictionary 210 (2d ed.1989) (defining
    “whenever,” used in “a qualifying (conditional) clause,” as:
    “At whatever time, no matter when.”). Thus, the unambiguous
    language of subsection 404(c) manifests the Congress’s intent
    to confer on EPA a broad veto power extending beyond the
    permit issuance.3 This construction is further buttressed by
    subsection 404(c)’s authorization of a “withdrawal” which, as
    EPA notes, is “a term of retrospective application.” Appellant
    Br. 27. EPA can withdraw a specification only after it has
    been made. See 20 Oxford English Dictionary 449 (2d
    ed.1989) (defining “withdraw” as “[t]o take back or away
    (something that has been given, granted, allowed, possessed,
    enjoyed, or experienced)”). Moreover, because the Corps
    often specifies final disposal sites in the permit itself—at least
    it did here, see Spruce Mine Permit at 1 (“You are authorized
    to perform work in accordance with the terms and conditions
    specified below . . . .”) (emphasis added) (JA 984)—EPA’s
    power to withdraw can only be exercised post-permit. Mingo
    Logan’s reading of the statute would eliminate EPA’s express
    statutory right to withdraw a specification and thereby render
    3
    Based on the plain meaning of the statutory language, EPA has
    consistently maintained this interpretation for over thirty years. See
    Section 404(c) Procedures, 44 Fed. Reg. 58,076, 58,077 (Oct. 9, 1979)
    (“The statute on its face clearly allows EPA to act after the Corps has
    issued a permit; it refers twice to the ‘withdrawal of specification,’
    which clearly refers to action by EPA after the Corps has specified a
    site (e.g. issued a permit or authorized its own work).”); Final
    Determination of the Administrator Concerning the North Miami
    Landfill Site Pursuant to Section 404(c) of the Clean Water Act at 1-2
    (Jan. 26, 1981) (JA 239-40) (exercising 404(c) authority “to restrict
    the use of [of the North Miami Landfill] for specification (including
    the withdrawal of specification) as a disposal site” almost five years
    after Corps issued permit therefor). The Corps has made clear by
    joining EPA in this litigation that it agrees with EPA’s interpretation.
    See supra p. 7.
    11
    subsection 404(c)’s parenthetical “withdrawal” language
    superfluous—a result to be avoided. See Corley v. United
    States, 
    556 U.S. 303
    , 314 (2009) (applying “one of the most
    basic interpretative canons, that a statute should be construed
    so that effect is given to all its provisions, so that no part will
    be inoperative or superfluous, void or insignificant”) (brackets
    and quotation marks omitted).
    Notwithstanding the unambiguous statutory language,
    Mingo Logan presses its own view of the language, the
    statutory structure and section 404’s legislative history to
    maintain that the Congress intended to preclude post-permit
    withdrawal. We find none of its arguments persuasive.
    First, Mingo Logan argues that the statutory language
    itself contemplates that specification occurs before (rather than
    when) the permit issues and therefore can (and must) be
    withdrawn pre-permit. We find no such intent in the statutory
    directive Mingo Logan quotes—that “each such disposal site
    shall be specified for each such permit by the Secretary . . .
    through the application of guidelines developed by the
    Administrator, in conjunction with the Secretary.” 33 U.S.C.
    § 1344(b). This language is at least as consistent with
    specification by the Corps at the time the permit issues as it is
    with pre-permit specification. Moreover, as noted earlier, see
    supra p. 10, the Corps expressly “specified” the final sites in
    the Spruce Mine Permit itself. Nor does the permitting
    process—including the “extensive coordination process during
    which EPA can review the Corps’s statement of
    findings/record of decision,” Appellee Br. 31—require that the
    specification be made before the permit issues. During the
    permitting process, the disposal sites are proposed,
    reviewed—perhaps even “specified,” as Mingo Logan
    contends—but the final specifications are included in the
    permit itself.
    12
    Second, Mingo Logan asserts EPA’s interpretation
    conflicts with section 404 “as a whole.” Id. at 35. Mingo
    Logan claims, for example, that “EPA’s reading obliterates the
    choice Congress made to give the permitting authority with all
    of its attributes to the Corps, not EPA.” Id. at 36. While it is
    true that subsections 404(a)-(b) unambiguously authorize the
    Secretary to issue a discharge permit—and to specify the
    disposal site(s) therefor—section 404(b) makes equally clear,
    as explained supra pp. 8-11, that the Administrator has, in
    effect, the final say on the specified disposal sites “whenever”
    he makes the statutorily required “unacceptable adverse
    effect” determination. Thus, insofar as site specification may
    be considered, as Mingo Logan asserts, an “attribute[]” of the
    permitting authority, the statute expressly vests final authority
    over this particular attribute in the Administrator.
    Mingo Logan also contends that EPA’s interpretation
    “tramples on provisions like sections 404(p) and 404(q) that
    are intended to give permits certainty and finality.” Appellee
    Br. 36. Subsection 404(p) provides: “Compliance with a
    permit issued pursuant to [section 404], including any activity
    carried out pursuant to a general permit issued under this
    section, shall be deemed compliance, for purposes of
    [enforcement actions brought under] sections 1319 and 1365
    of [title 33] . . . .” 33 U.S.C. § 1344(p).4 According to Mingo
    Logan, “absent . . . permit violations or public interest
    considerations, the permittee can rely on the permit shield of
    section 404(p).” Appellee Br. 37. But again, section 404(c)’s
    language is plain with regard to its enumerated “unacceptable
    adverse effects”: the Administrator retains authority to
    4
    Sections 1319 and 1365 of title 33 authorize an action by,
    respectively, (1) EPA against a violator of, inter alia, the terms of a
    section 404 permit; and (2) a citizen against a violator of a CWA
    effluent limitation or against EPA for failure to perform a non-
    discretionary “act or duty” under the CWA. 33 U.S.C. §§ 1319, 1365.
    13
    withdraw a specified disposal site “whenever” he determines
    such effects will result from discharges at the sites. And when
    he withdraws a disposal site specification, as he did here, the
    disposal site’s “terms and conditions specified” in the permit,
    see Spruce Mine Permit at 1 (JA 984), are in effect amended
    so that discharges at the previously specified disposal sites are
    no longer in “[c]ompliance with” the permit—although the
    permit itself remains otherwise in effect to the extent it is
    usable.5 Moreover, as EPA notes, subsection 404(c) was
    enacted in 1972 and its plain meaning did not change when
    404(p) was enacted five years later. Appellant Br. 33-34. As
    Mingo Logan acknowledges, if “the text of section 404(c)
    clearly and unambiguously gave EPA the power to act
    post-permit”—a reading it rejects—then section 404(p)
    “cannot be read to implicitly overturn section 404(c).”
    Appellee Br. 39 (citing Appellant Br. at 34 (citing Vill. of
    Barrington, Ill. v. STB, 
    636 F.3d 650
    , 662 (D.C. Cir. 2011))).
    As we have repeatedly stated throughout this opinion, the text
    of section 404(c) does indeed clearly and unambiguously give
    EPA the power to act post-permit. Thus, subsection 404(p)
    does not implicitly limit section 404(c)’s scope. Nor does
    EPA’s express statutory authority to act post-permit interfere
    with subsection 404(q)’s directive that the Secretary enter into
    5
    In this case for example, EPA left intact the specification as
    disposal site of “the Right Fork of Seng Camp Creek and its tributaries
    . . . in part because some of those discharges have already occurred
    and because the stream resources in Right Fork of Seng Camp Creek
    were subject to a higher level of historic and ongoing human
    disturbance than those found in Pigeonroost Branch or Oldhouse
    Branch.” Final Determination, 76 Fed. Reg. at 3127 n.1.
    In addition, EPA has made clear that a permittee may not be
    penalized for discharges that occurred in compliance with the permit
    before the effective date of the withdrawal of the specification.
    14
    agreements with other agency heads “to minimize, to the
    maximum extent practicable, duplication, needless paperwork,
    and delays in the issuance of permits under this section” and
    “to assure that, to the maximum extent practicable, a decision
    with respect to an application for a permit under subsection
    (a) of this section will be made not later than the ninetieth day
    after the date the notice for such application is published under
    subsection (a) of this section.” 33 U.S.C. § 1344(q) (emphases
    added). The enumerated obligations apply only pre-permit
    and are therefore unaffected by EPA’s post-permit actions.
    Finally, Mingo Logan argues that the legislative history
    “confirms that Congress intended EPA to act under section
    404(c), if at all, prior to permit issuance.” Appellee Br. 42. In
    particular, it relies on the statement of then-Senator Edmund
    Muskie that
    prior to the issuance of any permit to dispose of spoil,
    the Administrator must determine that the material to
    be disposed of will not adversely affect municipal
    water supplies, shellfish beds, and fishery areas
    (including spawning and breeding areas), wildlife or
    recreational areas in the specified site. Should the
    Administrator so determine, no permit may issue.
    118 Cong. Rec. at 33,699, reprinted in Legislative History at
    177 (emphasis added). “Assuming legislative history could
    override the plain, unambiguous directive” of section 404(c)
    and “putting to one side the fact that this was the statement of
    a single member of Congress,” the quoted language is “not
    necessarily inconsistent with” EPA’s interpretation. See
    Natural Res. Def. Council v. EPA, 
    706 F.3d 428
    , 437 (D.C.
    Cir. 2013) (quotation marks and brackets omitted); see also
    Mims v. Arrow Fin. Servs., LLC, 
    132 S. Ct. 740
    , 752 (2012)
    (“[T]he views of a single legislator, even a bill’s sponsor, are
    not controlling.”). That EPA should review the preliminary
    specifications pre-permit to determine whether discharges will
    15
    have the required “unacceptable adverse effect”—as EPA in
    fact did here—does not mean it is foreclosed from doing so
    post-permit as well—as it also did here.6 “Thus, ‘this case
    does not present the very rare situation where the legislative
    history of a statute is more probative of congressional intent
    than the plain text.’ ” Va. Dep’t of Med. Assistance Servs. v.
    U.S. Dep’t of Health & Human Servs., 
    678 F.3d 918
    , 923
    (D.C. Cir. 2012) (quoting Consumer Elecs. Ass’n v. FCC, 
    347 F.3d 291
    , 298 (D.C. Cir. 2003)) (brackets omitted).
    For the foregoing reasons, we reverse the district court
    insofar as it held that EPA lacks statutory authority under
    CWA section 404(c) to withdraw a disposal site specification
    post-permit. Because the district court did not address the
    merits of Mingo Logan’s APA challenge to the Final
    Determination and resolution of the issue is not clear on the
    present record, we follow our ususal practice and remand the
    issue to the district court to address in the first instance. See
    Friends of Blackwater v. Salazar, 
    691 F.3d 428
    , 434 n.* (D.C.
    Cir. 2012) (citing Piersall v. Winter, 
    435 F.3d 319
    , 325 (D.C.
    Cir. 2006)).
    So ordered.
    6
    Similarly, post-permit withdrawal is not precluded by 33 C.F.R.
    § 323.6(b) (“The Corps will not issue a permit where the regional
    administrator of EPA has notified the district engineer and applicant
    in writing pursuant to 40 CFR 231.3(a)(1) that he intends to issue a
    public notice of a proposed determination to prohibit or withdraw the
    specification, or to deny, restrict or withdraw the use for specification,
    of any defined area as a disposal site in accordance with section 404(c)
    of the Clean Water Act.”).