Braintree Electric Light Department v. Federal Energy Regulatory Commission , 667 F.3d 1284 ( 2012 )


Menu:
  • United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued September 12, 2011          Decided February 7, 2012
    No. 09-1231
    BRAINTREE ELECTRIC LIGHT DEPARTMENT, ET AL.,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    ISO NEW ENGLAND INC., ET AL.,
    INTERVENORS
    Consolidated with No. 10-1395
    On Petitions for Review of Orders
    of the Federal Energy Regulatory Commission
    John P. Coyle argued the cause for petitioners. With him
    on the briefs were Scott H. Strauss and Jeffrey A. Schwarz.
    Carol J. Banta, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With her on the
    brief was Robert H. Solomon, Solicitor.
    2
    Carmen L. Gentile and Mary E. Gover were on the brief for
    intervenor NSTAR Electric Company in support of respondent.
    Before: TATEL, GARLAND, and BROWN, Circuit Judges.
    Opinion for the Court filed by Circuit Judge GARLAND.
    GARLAND, Circuit Judge: Braintree Electric Light
    Department and other municipally owned utilities in
    southeastern Massachusetts petition for review of four orders of
    the Federal Energy Regulatory Commission (FERC). The
    orders denied the petitioners’ claim that they were being
    unjustly charged in order to ensure system reliability on Cape
    Cod. The dispute was first addressed in a FERC-approved
    settlement agreement that reserved certain litigation rights to the
    petitioners. Because the Commission reasonably resolved the
    claims that were reserved, and reasonably construed the
    settlement agreement to foreclose the petitioners’ additional
    claims, we affirm the Commission’s orders and deny the
    petitions for review.
    I
    Two oil-powered generators, known as the Canal Units,
    have provided electricity to Cape Cod since the 1970s.
    Braintree Elec. Light Dep’t v. ISO New England Inc., 
    124 FERC ¶ 61,061
    , 61,360 & n.3 (2008) [hereinafter Complaint Order].
    In 2006, the rising price of oil made the Canal Units more
    expensive to run, and they became largely uneconomic. The
    Independent System Operator for New England (“ISO New
    England” or “ISO-NE”), however, determined that running the
    generators remained necessary to avoid blackouts on Cape Cod
    in the event that more than one transmission line providing
    power to the Cape were damaged in quick succession (a “second
    3
    contingency”).1 The ISO therefore designated the Canal Units
    as a “Local Second Contingency Protection Resource”
    (LSCPR). Under the ISO New England tariff, an effect of this
    designation was to spread the cost of running the Canal Units
    among all participants in the Southeastern Massachusetts
    (SEMA) Reliability Region, in proportion to their load
    obligations. ISO-NE Tariff § III.6.4.4 (Resp’t Br. A-12). The
    petitioners are load-serving entities that are within the region but
    do not serve Cape Cod.
    ISO New England’s designation of the Canal Units as
    LSCPRs prompted the petitioners, other utilities, ISO New
    England, and the transmission owners in the region to take part
    in a FERC-supervised mediation. After almost a year of
    negotiations, FERC approved the resulting Settlement
    Agreement in 2007. See J.A. 205-55. Under the settlement, the
    transmission owners agreed to reimburse the petitioners for
    some of the Canal Units’ 2006 charges. Settlement Agreement
    § 3.1. Section 4.1 of the agreement provided that the costs of
    operating the Canal Units after 2006 would be allocated on the
    same basis that costs for an LSCPR are allocated under the ISO
    New England tariff -- “[s]ubject to” the petitioners’ reserved
    litigation rights under Section 7 (and to provisions in certain
    other sections). Also subject to the petitioners’ reserved
    1
    An independent system operator is “an independent company
    that has operational control, but not ownership, of the transmission
    facilities owned by member utilities. ISOs ‘provide open access to the
    regional transmission system to all electricity generators at rates
    established in a single, unbundled, grid-wide tariff.’” NRG Power
    Mktg., LLC v. Me. Pub. Utils. Comm’n, 
    130 S. Ct. 693
    , 697 n.1 (2010)
    (quoting Midwest ISO Transmission Owners v. FERC, 
    373 F.3d 1361
    ,
    1364 (D.C. Cir. 2004)). Under its tariff, ISO-NE is obligated to assure
    that New England’s power supply “conforms to proper standards of
    reliability.” ISO-NE Tariff § I.1.3.
    4
    litigation rights, the parties were barred from attempting to
    reclassify the Canal Units under the tariff and thereby from
    changing the method of cost allocation. Id. § 4.1; see also id.
    §§ 8(c), 10.1.
    Section 7 defined the reserved litigation rights of the
    petitioners, preserving future claims of two sorts. First, Section
    7.1 permitted the petitioners to seek
    relief from SEMA [reliability] Charges for LSCPR
    through litigation . . . over whether consistent with
    [applicable reliability criteria] such charges could be or
    should be reduced through implementation of [a
    Special Protection System] or Post-First Contingency
    Switching arrangement.
    In other words, the petitioners were permitted to litigate
    whether, consistent with maintaining system reliability, one of
    two identified alternatives to the Canal Units -- a specified type
    of protection system or switching arrangement -- could or
    should be implemented. Section 7.2 set forth the second
    reservation, which stated:
    The Parties, other than the Municipals [i.e. the
    petitioners], agree not to seek a change . . . in the ISO-
    NE definition of the SEMA Reliability Region . . . ;
    provided that the Municipals may seek such a change
    to become effective no earlier than January 1, 2008.
    That is, the petitioners were permitted to petition for a change in
    the definition of the SEMA reliability region to take effect on or
    after January 1, 2008.
    If successfully pursued, either reserved litigation right
    would permit the petitioners to reduce their share of Canal Unit
    5
    charges. If the petitioners could show that one of the identified
    alternatives could or should be implemented without degrading
    reliability, they would be entitled to financial relief. Likewise,
    if the SEMA reliability region were divided in a way that left the
    petitioners outside the subregion to which the costs of the Canal
    Units were allocated, they would be insulated from sharing those
    costs under ISO New England’s tariff.
    The petitioners filed a complaint with the Commission on
    March 28, 2008. They contended (1) “that ISO-NE should
    implement Post First Contingency Switching or a Special
    Protection System” as an alternative that would reduce LSCPR
    charges; and (2) that “costs that are incurred to protect Cape Cod
    should not be allocated to the entire SEMA region but that the
    region should be divided into two sub-regions, Upper and Lower
    SEMA, and the costs should be allocated only to Lower
    SEMA.” 124 FERC at 61,360, 61,361. In its Complaint Order,
    FERC denied the first request because it “would inappropriately
    degrade reliability.” Id. at 61,364. As to the second, it found
    that “whether or not the cost allocations resulting from the
    boundaries of the current SEMA region are just and reasonable
    raises issues of material fact” and, accordingly, it scheduled a
    hearing on the issue. Id. FERC held the hearing in abeyance,
    however, until ISO New England could consider the division of
    the SEMA region through its stakeholder process. Id. FERC
    ordered ISO New England to address “cost allocation issues” as
    part of that process and thereafter to submit a report to the
    Commission. Id. The petitioners filed a request for a rehearing,
    which was denied. Braintree Elec. Light Dep’t v. ISO New
    England Inc., 
    128 FERC ¶ 61,008
     (2009) [hereinafter 2009
    Rehearing Order].
    In compliance with the Complaint Order, ISO New England
    submitted a filing on June 17, 2009 that detailed the outcome of
    its stakeholder process. In the ISO’s view, “the SEMA regional
    6
    boundary resulted in just and reasonable cost allocations” and no
    change was warranted. Braintree Elec. Light Dep’t v. ISO New
    England Inc., 
    129 FERC ¶ 61,077
    , 61,351 (2009) [hereinafter
    Compliance Order]. Specifically, it reported that upgrades to
    the transmission system -- which effectively eliminated system
    reliance on out-of-merit dispatch of the Canal Units2 -- had
    obviated the need for prospective change to the SEMA
    boundary, and that no party continued to “advocate[] a
    permanent change to the boundary.” 
    Id. at 61,357
    . In its
    Compliance Order, the Commission “agree[d] with ISO’s
    proposal to retain the existing SEMA reliability region
    boundary,” and it rejected the petitioners’ request for “additional
    procedures.” 
    Id.
    The petitioners filed a request for rehearing, which the
    Commission denied. Braintree Elec. Light Dep’t v. ISO New
    England Inc., 
    132 FERC ¶ 61,248
     (2010) [hereinafter 2010
    Rehearing Order].       In its 2010 Rehearing Order, the
    Commission clarified its reading of the Settlement Agreement,
    holding that Section 7.2 reserved only the right to litigate for an
    actual change in the SEMA boundary. In FERC’s view, the
    settlement did not permit the petitioners to argue for a refund of
    Canal Unit charges based upon a hypothetical change in the
    SEMA region limited to an earlier period. Since the petitioners
    had abandoned their request for actual and prospective (from
    March 2008 forward) change, FERC viewed their remaining
    2
    In the New England Power Pool, generators are usually
    employed in order of “economic merit”; that is, units offering lower
    bids to supply power are employed first. NSTAR Elec. & Gas Corp.
    v. FERC, 
    481 F.3d 794
    , 797 (D.C. Cir. 2007). Sometimes, however,
    generators “whose bids exceed the market-clearing price are called
    into service to ensure system reliability.” 
    Id.
     This is referred to as
    “out-of-merit dispatch.”
    7
    argument for cost reallocation as barred by the settlement.
    These petitions for review followed.
    II
    We review FERC’s orders under the “arbitrary or
    capricious” standard of the Administrative Procedure Act,
    seeking to determine whether they are “arbitrary, capricious, an
    abuse of discretion, or otherwise not in accordance with law.”
    
    5 U.S.C. § 706
    (2)(A); see PSEG Energy Res. & Trade LLC v.
    FERC, No. 10-1103, 
    2011 WL 6450762
    , at *3 (D.C. Cir. Dec.
    23, 2011); TNA Merch. Projects, Inc. v. FERC, 
    616 F.3d 588
    ,
    591 (D.C. Cir. 2010). To survive this review, FERC “must
    ‘examine the relevant data and articulate a satisfactory
    explanation for its action including a rational connection
    between the facts found and the choice made.’” PPL
    Wallingford Energy LLC v. FERC, 
    419 F.3d 1194
    , 1198 (D.C.
    Cir. 2005) (quoting Motor Vehicle Mfrs. Ass’n v. State Farm
    Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983)). The Commission’s
    factual findings are conclusive if supported by substantial
    evidence. 16 U.S.C. § 825l(b).
    FERC’s interpretation of a settlement agreement within its
    jurisdiction is entitled to deference under the familiar two-step
    analysis of Chevron U.S.A. Inc. v. Natural Resources Defense
    Council, Inc., 
    467 U.S. 837
     (1984). See MarkWest Mich.
    Pipeline Co., LLC v. FERC, 
    646 F.3d 30
    , 34 (D.C. Cir. 2011).
    At step one, we “‘consider de novo whether the settlement
    agreement unambiguously addresses the matter at issue. If so,
    the language of the agreement controls . . . .’” 
    Id.
     (quoting
    Ameren Servs. Co. v. FERC, 
    330 F.3d 494
    , 498 (D.C. Cir.
    2003)). At step two, “[i]f the agreement is ambiguous or silent,
    . . . ‘we defer to the Commission’s construction of the provision
    at issue so long as that construction is reasonable.’” 
    Id.
     (quoting
    8
    Koch Gateway Pipeline Co. v. FERC, 
    136 F.3d 810
    , 814-15
    (D.C. Cir. 1998)).
    The petitioners contend that Chevron deference is
    unwarranted because the Commission did not expressly state
    that the settlement agreement it was interpreting was ambiguous.
    But the Chevron two-step is a dance for the court, not the
    Commission. To be sure, “[i]f the Commission’s decision turns
    on an erroneous assertion that the plain language of the relevant
    wording is unambiguous, . . . we must remand the matter to the
    Commission to require the agency to consider the question
    afresh in light of the ambiguity we see.” Ameren, 
    330 F.3d at 498-99
     (internal quotation marks omitted). But the Commission
    made no such erroneous assertion here, and no contrary
    assertion of ambiguity is required. As long as the text is
    ambiguous and the agency does not insist that it is clear, a
    reasonable interpretation will warrant our deference. There is no
    reason for us to assume that the Commission sees clarity where
    we do not.
    With this understanding of the scope of our review, we
    proceed to examine the petitioners’ contentions.
    A
    The petitioners’ first contention, which on its face appears
    to track their first reserved litigation right, is that ISO New
    England could have reduced the petitioners’ charges by using
    one of the alternatives identified in Section 7.1 -- a Special
    Protection System or a Post-First Contingency Switching
    arrangement -- instead of operating the Canal Units to maintain
    compliance with reliability criteria. FERC, however, disagreed.
    It found that either alternative “would expose Cape Cod to the
    risk of involuntary load shedding” if one of the transmission
    lines that provide power to the Cape were lost -- a result it
    9
    deemed unacceptable. Complaint Order, 124 FERC at 61,363.
    If “ISO-NE relied on a [Post First Contingency Switching] or a
    [Special Protection System],” FERC said, “then the next step
    after a first contingency would be the involuntary shedding of
    firm load.” 2009 Rehearing Order, 128 FERC at 61,032. Such
    a scenario “would inappropriately degrade reliability” by
    increasing the likelihood of forced outages. Id.; see Complaint
    Order, 124 FERC at 61,364 (finding that either alternative “has
    the potential to black out Cape Cod load for up to 24 hours”).
    We ordinarily defer to this kind of technical judgment, see B&J
    Oil & Gas v. FERC, 
    353 F.3d 71
    , 76 (D.C. Cir. 2004), and the
    petitioners proffer nothing that persuades us to take a different
    path here.
    The petitioners do point out that, in a report authored
    pursuant to the Settlement Agreement, ISO New England stated
    that a “switching alternative” could “technically be implemented
    under Applicable Criteria up to a New England load level of
    approximately 17,000 MW.” Short-Term Report of ISO New
    England, Inc. at 17 (July 17, 2007) (J.A. 164) (emphasis added).
    But the report ultimately recommended against a switching
    arrangement because “the need for load shedding” in the event
    of a second contingency “would occur at virtually all hours of
    the year.” 
    Id.
     As the petitioners concede, the New England load
    level is above the 17,000 MW specified in the report roughly
    70% of the time. Pet’rs Reply Br. 4. Moreover, under a
    switching arrangement, “system restoration” could “take 24
    hours” after a second contingency. Short-Term Report at 18
    (J.A. 165).      In these circumstances, FERC reasonably
    determined that implementation of a switching arrangement
    would not satisfy applicable reliability criteria.
    The petitioners respond that they did not mean to suggest
    that ISO New England should actually adopt either of the
    identified alternatives, and that FERC “addressed a strawman
    10
    argument about whether [a Post First Contingency Switching or
    Special Protection System] arrangement should be
    implemented.” Pet’rs Br. 39-40. Their true argument,
    petitioners maintain, was that the alternatives should serve as
    hypothetical arrangements under which their charges would be
    reduced. They further argue that, in light of the alternatives, the
    Canal Units were not “necessary” for adherence to applicable
    reliability standards and hence did not meet the definition of
    LSCPRs under the ISO New England tariff.3 Thus, the
    petitioners conclude, the units may be reclassified for billing
    purposes only, and because no physical change would actually
    be implemented, there would be no blackouts.
    But the so-called “strawman” argument that FERC
    addressed was the very argument the settlement had reserved for
    future litigation. In words that largely parallel the argument the
    petitioners now characterize as a strawman, Section 7 of the
    Settlement Agreement reserved for the petitioners the right to
    seek “relief from [reliability] Charges for LSCPR through
    litigation . . . over whether consistent with [applicable reliability
    criteria] such charges could be or should be reduced through
    implementation of [a Special Protection System] or Post-First
    Contingency Switching arrangement.” Settlement Agreement
    § 7.1. FERC can hardly be faulted for thinking that the
    petitioners were making the argument that Section 7 reserved for
    them.
    3
    ISO New England’s tariff defines an LSCPR as a resource
    “identified by the ISO on a daily basis as necessary for the provision
    of Operating Reserve Requirements and adherence to [North
    American Electric Reliability Council, Northeast Power Coordinating
    Council], and ISO reliability criteria over and above those Resources
    required to meet first contingency reliability criteria within a
    Reliability Region.” ISO-NE Tariff § III.6.1 (Resp’t Br. A-11).
    11
    Moreover, FERC made clear that the settlement did not
    reserve, but rather barred, the billing reclassification argument
    the petitioners press here. See 2009 Rehearing Order, 128
    FERC at 61,034-35 (“[T]he SEMA Settlement resolves the issue
    of classification of the Canal Unit out-of-merit dispatch costs as
    LSCPR.”). FERC explained that any argument that the Canal
    Units should merely be reclassified for financial purposes was
    barred by Section 4.1 of the agreement, which provides that no
    party shall seek a “‘reclassification of ISO-NE’s designation of
    Canal as an LSCPR’” -- “‘subject’” only to Section 7 (and other
    sections not relevant here). 2010 Rehearing Order, 132 FERC
    at 62,416 (quoting § 4.1).4 The suggestion that a special
    protection system or contingency switching arrangement should
    be considered on a hypothetical basis did not come within the
    Section 7 proviso, FERC said, because that section reserved
    only the possibility that “charges ‘could or should be reduced
    through implementation of’” those alternatives. 2010 Rehearing
    Order, 132 FERC at 62,416 (quoting § 7.1) (emphasis added);
    see 2009 Rehearing Order, 128 FERC at 61,034.5 This was
    certainly a reasonable construction, given that reclassification is
    4
    “Likewise,” the Commission noted, Section 8(c) provides that
    no party shall argue for amendments “‘that would provide for a
    different mechanism for allocation of NCPC charges for LSCPR, or
    shall seek or support reclassification of ISO-NE’s designation of Canal
    as a LSCPR[,] . . . other than as provided in Section[] . . . 7.’” 2010
    Rehearing Order, 132 FERC at 62,416 (quoting Settlement Agreement
    § 8(c)) (emphasis in the Rehearing Order).
    5
    This is not to say that FERC believed Section 7.1 applied only
    if one of the alternatives were actually implemented. In the
    Commission’s view, a refund was also possible if the ISO “could have
    implemented” it but had not done so. See 2010 Rehearing Order, 132
    FERC at 62,413. This would only apply, however, if the alternative
    could actually have been implemented consistent with applicable
    reliability criteria. See id. at 62,415.
    12
    not among the litigation rights reserved in the text of Section 7.
    See supra Part I (quoting Settlement Agreement § 7.1, 7.2).
    At oral argument, the petitioners maintained that we should
    infer the contents of the reserved rights not from the text of
    Section 7 but from the provisions that are “subject to” its
    reservations. Oral Arg. Recording at 44:10 - 45:15. They argue
    that, because Section 4’s bar on reclassification of the Canal
    Units is “subject to” the petitioners’ reserved litigation rights,
    reclassification is itself one of those rights. But Section 7 is
    quite explicit about what rights the settlement reserved, and it
    was not unreasonable for FERC to conclude that the content of
    the petitioners’ reserved litigation rights is defined by the
    language of the section that sets out those rights.
    B
    The petitioners’ second contention, as stated in their initial
    complaint to FERC, is that “the reliability costs that are incurred
    to protect Cape Cod should not be allocated to the entire SEMA
    region but [rather] the region should be divided into two
    sub-regions, Upper and Lower SEMA.” Complaint Order, 124
    FERC at 61,361. On its face, this contention again appears to
    fall within the litigation rights reserved for the petitioners in
    Section 7: specifically, the second reservation, as set out in
    Section 7.2, which permits the petitioners “to seek a change . . .
    in the ISO-NE definition of the SEMA Reliability Region to
    become effective . . . no earlier than January 1, 2008.”
    In the Complaint Order, FERC referred this issue for initial
    consideration to the ISO New England stakeholder process.6
    6
    The petitioners contend that the Commission “unreasonably
    deferred to the ISO-NE stakeholder process,” and that its adoption of
    ISO-New England’s recommendations was an “abdication of its
    13
    But by the time ISO New England supplied its analysis to
    FERC, it was plain to all parties that system upgrades that
    largely eliminated reliance on the Canal Units had made division
    of the SEMA region unnecessary, and the petitioners had
    dropped their request for a prospective division. Compliance
    Order, 129 FERC at 61,357 (“Both ISO-NE and Municipals
    agree that prospectively redrafting the SEMA boundary is
    unnecessary due to upgrades to the transmission system. The
    completion of these upgrades mitigates the need for out-of-merit
    dispatch of the Canal Units and the resulting LSCPR charges
    that are the subject of this dispute.”). Accordingly, the
    petitioners told FERC that they were “not seeking to ‘modif[y]’
    the SEMA zone during the refund effective period. Rather, they
    [were] seeking refunds of Canal LSCPR charges that were
    unjustly or unreasonably allocated to them because of the zonal
    boundaries during that period.” Protest and Request to Resume
    Hearing at 3 n.5, Braintree Elec. Light Dep’t v. ISO New
    England Inc., Docket No. EL08-48-002 (August 7, 2009) (J.A.
    681). At oral argument before this court, the petitioners again
    made clear that they were not seeking a permanent change in the
    boundaries of SEMA, but rather financial relief “as if” the
    regulatory responsibilities.” Pet’rs Br. 52, 53. We reject these
    contentions for two reasons. First, FERC merely referred the issue in
    order to obtain input from the interested parties; the Compliance Order
    provided FERC’s own independent assessment. See 129 FERC at
    61,357-58; see also 2009 Rehearing Order, 128 FERC at 61,038
    (“Because the Commission will ultimately review and act on any
    resulting proposal, there is no issue with respect to delegation of
    Commission authority.”). We have previously approved this kind of
    process. See Pub. Serv. Comm’n of Wis. v. FERC, 
    545 F.3d 1058
    ,
    1062-64 (D.C. Cir. 2008). Second, as we discuss below, FERC
    ultimately based its resolution of the petitioners’ argument about
    dividing the region on its construction of the Settlement Agreement,
    not on the stakeholder process.
    14
    boundaries had been retroactively changed for the “locked-in”
    2008-09 period. Oral Arg. Recording at 6:50 - 7:15.7
    The Commission, however, held that the Settlement
    Agreement precluded a claim for financial relief based on this
    kind of hypothetical, temporary, and retroactive change to the
    SEMA region that would apply only for the “locked-in” period.
    Section 4.1 of the settlement provides that “no Party shall seek
    or support a different allocation mechanism” for Canal Unit
    charges -- “[s]ubject to” Section 7 (and other sections not
    relevant here). Section 7.2, in turn, reserves for the petitioners
    the right “to seek a change . . . in the ISO-NE definition of the
    SEMA Reliability Region to become effective . . . no earlier
    than January 1, 2008.” Once the petitioners abandoned their
    claim for an actual, prospective change to the region’s boundary,
    FERC considered their remaining request for a hypothetical,
    retroactive bifurcation -- for cost-allocation purposes only -- to
    be barred by the settlement. “Contrary to Municipals’
    assertion,” FERC held, “neither Section 7.1 nor Section 7.2
    contains language to permit reallocation of Canal LSCPR costs
    because the SEMA boundary ‘should have been changed,’
    absent a change in the definition of the SEMA region.” 2010
    7
    The parties’ pleadings refer to a “locked-in” refund period that
    extends from March 28, 2008 through June 28, 2009. See, e.g., 2010
    Rehearing Order, 132 FERC at 62,423. Under Section 206 of the
    Federal Power Act, if FERC finds that any “rate, charge, or
    classification” is “unjust, unreasonable, unduly discriminatory or
    preferential,” the Commission is authorized to “order refunds of any
    amounts paid” for a fifteen-month period following the “refund
    effective date.” 16 U.S.C. § 824e(a), (b). In this case, FERC set
    March 28, 2008 -- the day the petitioners filed their complaint -- as the
    refund effective date. Complaint Order, 124 FERC at 61,360. As it
    happened, by the end of the fifteen-month statutory refund period,
    system upgrades had largely eliminated the disputed charges, making
    a division of SEMA no longer relevant. See Resp’t Br. 2.
    15
    Rehearing Order, 132 FERC at 62,416; see also id. at 62,415
    (“[We] determin[e] that the SEMA Settlement permits
    Municipals to seek a change in the SEMA boundary, but not
    reallocation in the absence of such a change . . . .”).
    We defer to this construction of the Settlement Agreement
    under Chevron principles. The agreement provides that the
    petitioners may seek “a change” in the definition of the SEMA
    Region “to become effective no earlier than January 1, 2008.”
    Settlement Agreement § 7.2. It is (at best) unclear from the text
    whether “a change” encompasses the hypothetical and
    temporary bifurcation the petitioners seek, or only an actual and
    prospective change. The phrase “to become effective” suggests
    the latter. Moreover, other provisions of the agreement indicate
    an overarching intent to have the settlement resolve all cost
    allocation issues among the parties, see id. §§ 4.1, 8(c), and
    therefore counsel against construing Section 7 to permit what
    are essentially cost-reallocation claims in the guise of a litigation
    reservation. FERC’s reading of the ambiguous Settlement
    Agreement is reasonable and entitled to deference.
    C
    Finally, the petitioners contend that FERC’s orders should
    be overturned because they violate the “cost causation”
    principle. Pet’rs Br. 44. “We have described this principle as
    ‘requir[ing] that all approved rates reflect to some degree the
    costs actually caused by the customer who must pay them.’”
    Midwest ISO Transmission Owners v. FERC, 
    373 F.3d 1361
    ,
    1368 (D.C. Cir. 2004) (quoting KN Energy, Inc. v. FERC, 
    968 F.2d 1295
    , 1300 (D.C. Cir. 1992)). The petitioners maintain that
    the costs they were charged were far out of proportion to the
    reliability benefits they obtained from the operation of the Canal
    Units.
    16
    The short answer to the petitioners’ cost causation
    argument, and the only one we need consider, is that it is beyond
    the scope of the litigation rights reserved in the Settlement
    Agreement. As we have discussed, FERC construed the
    settlement to reserve two types of claims: whether an alternative
    to the Canal Units could or should be implemented, and whether
    the SEMA region should be divided. 2010 Rehearing Order,
    132 FERC at 62,418-19. The petitioners’ cost causation claim
    comes within neither of these categories. As the Commission
    explained in the 2010 Rehearing Order, “[c]ontrary to
    Municipals’ assertion, the Commission did not [in the
    Compliance Order] improperly avoid consideration of Canal
    Unit out-of-merit dispatch costs and resulting benefits.” Id. at
    62,419. Rather, “the Commission did not review such issues
    because we found that the SEMA Settlement, to which
    Municipals are a party, barred reallocation and, in the
    compliance phase, no party continued to advocate a change in
    the definition of the SEMA boundary as permitted by the SEMA
    Settlement, section 7.2.” Id. We affirm FERC’s reasonable
    determination that the Settlement Agreement bars the
    petitioners’ cost causation argument.8
    8
    In the 2010 Rehearing Order, FERC went on to consider and
    reject the petitioners’ cost causation argument on the merits. See 2010
    Rehearing Order, 132 FERC at 62,419-21. It also considered and
    rejected the merits of the petitioners’ proposal to “divide SEMA for
    the interim period.” Id. at 62,424; see supra Part II.B. We need not
    address those determinations here. “When an agency offers multiple
    grounds for a decision, we will affirm the agency so long as any one
    of the grounds is valid, unless it is demonstrated that the agency would
    not have acted on that basis if the alternative grounds were
    unavailable.” BDPCS, Inc. v. FCC, 
    351 F.3d 1177
    , 1183 (D.C. Cir.
    2003) (citing, inter alia, SEC v. Chenery Corp., 
    318 U.S. 80
    , 88
    (1943)). The 2010 Rehearing Order makes it clear that the settlement
    bar constituted an independent rationale for the Commission’s
    decision. See 2010 Rehearing Order, 132 FERC at 62,415.
    17
    III
    For the foregoing reasons, the petitions for review are
    denied.