West Deptford Energy, LLC v. FERC , 766 F.3d 10 ( 2014 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued March 6, 2014               Decided August 26, 2014
    No. 12-1340
    WEST DEPTFORD ENERGY, LLC,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    FPL ENERGY MARCUS HOOK, L.P. AND PJM
    INTERCONNECTION, L.L.C.,
    INTERVENORS
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    Ashley C. Parrish argued the cause for petitioner. With
    him on the briefs were Karen F. Grohman, Neil L. Levy, and
    Stephanie S. Lim.
    Holly E. Cafer, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. On the brief
    were David L. Morenoff, Acting General Counsel, Robert H.
    Solomon, Solicitor, and Beth G. Pacella, Senior Attorney.
    2
    Paul M. Flynn argued the cause for intervenors. With
    him on the brief were Barry S. Spector, Jennifer H. Tribulski,
    and Stephen L. Huntoon.
    Before: GARLAND, Chief Judge, and SRINIVASAN and
    MILLETT, Circuit Judges.
    Opinion for the Court filed by Circuit Judge MILLETT.
    MILLETT, Circuit Judge: The Federal Power Act requires
    regulated utilities to file with the Federal Energy Regulatory
    Commission, as a matter of open and accessible public record,
    any rates and charges they intend to impose for sales of
    electrical energy that are subject to the Commission’s
    jurisdiction. See 16 U.S.C. § 824d(c). As a consequence,
    utilities are forbidden to charge any rate other than the one on
    file with the Commission, a prohibition that has become
    known as the “filed rate doctrine.” See NSTAR Elec. & Gas
    Corp. v. FERC, 
    481 F.3d 794
    , 800 (D.C. Cir. 2007); see also
    Arkansas La. Gas Co. v. Hall, 
    453 U.S. 571
    , 577 (1981)
    (describing filed rate doctrine under the Natural Gas Act).
    That requirement of transparent, public filing of rates ensures
    evenhandedness, fairness, stability, and predictability in the
    prices charged for electrical energy.
    The question in this case is, when a utility filed more than
    one rate with the Commission during the time it was
    negotiating an agreement with a prospective customer, which
    of the two filed rates governs: the rate at the time
    negotiations commenced or the rate at the time the agreement
    was completed? West Deptford argues that, as a matter of
    practice, the Commission has used the rate on file at the time
    the agreement was finalized. The Commission is of the view
    that it can pick and choose which rate applies on a case-by-
    case basis. See PJM Interconnection, L.L.C., 
    136 FERC
                    3
    ¶ 61,195 (2011) (“Order”); PJM Interconnection, L.L.C., 
    139 FERC ¶ 61,184
     (2012) (“Rehearing Order”). We vacate the
    Commission’s orders in part and remand because the
    Commission has provided no reasoned explanation for how its
    decision comports with statutory direction, prior agency
    practice, or the purposes of the filed rate doctrine.
    I
    STATUTORY AND REGULATORY FRAMEWORK
    The Federal Power Act, 16 U.S.C. §§ 791a et seq.,
    charges the Commission with regulating “the transmission of
    electric energy” and “the sale of electric energy at wholesale”
    in interstate commerce, id. § 824(b)(1). In exercising that
    authority, the Commission must ensure that “[a]ll rates and
    charges” for the “transmission or sale of electric energy
    subject to” its jurisdiction are “just and reasonable,” and that
    no public utility’s rates are unduly discriminatory or
    preferential. Id. § 824d(a) & (b); see NRG Power Marketing,
    LLC v. Maine Public Utils. Comm’n, 
    558 U.S. 165
    , 167
    (2010).
    To that end, the Act requires every public utility to “file
    with the Commission” and “keep open in convenient form
    and place for public inspection schedules showing all rates
    and charges for any transmission or sale subject to the
    jurisdiction of the Commission.” 16 U.S.C. § 824d(c). That
    obligation applies whether the rates and charges are set
    “unilaterally by tariff” or agreed upon in individual contracts
    between sellers and buyers. NRG Power Marketing, 
    558 U.S. at 171
    . When a public utility seeks to change its filed rate, it
    must “fil[e] with the Commission * * * new schedules stating
    plainly the change or changes * * * and the time when the
    change or changes will go into effect.” 16 U.S.C. § 824d(d).
    4
    The Federal Power Act’s express mandate of openness,
    transparency,    and consistency in           rates     prevents
    discrimination, promotes fair and equal access to the utilities’
    services, ensures the stability and predictability of rates, and
    reinforces the Commission’s jurisdictional authority. See
    Maislin Industries, U.S., Inc. v. Primary Steel, Inc., 
    497 U.S. 116
    , 130–131 (1990); Consolidated Edison Co. of New York
    v. FERC, 
    347 F.3d 964
    , 969 (D.C. Cir. 2003); Consolidated
    Edison Co. of New York v. FERC, 
    958 F.2d 429
    , 432 (D.C.
    Cir. 1992) (R.B. Ginsburg, J.).
    To foster competition in the wholesale energy market, the
    Commission drastically overhauled the regulatory scheme for
    public utilities in 1996.       As part of that effort, the
    Commission ordered regulated utilities to separate financially
    their wholesale power-generation and power-transmission
    services. See Order No. 888, FERC Stats. & Regs. ¶ 31,036
    (1996); see also New York v. FERC, 
    535 U.S. 1
    , 11 (2002)
    (describing Order No. 888). Accordingly, public utilities
    must now file tariffs with the Commission establishing
    separate rates for wholesale power generation service,
    transmission service, and any ancillary service. New York,
    
    535 U.S. at 11
    . In addition, they must “take transmission of
    [their] own wholesale sales and purchases under a single
    general tariff applicable equally to [themselves] and to
    others.” 
    Id.
    Problems soon arose, however, because every time a new
    generator of electricity asked to use a transmission network
    owned by another—to interconnect the two entities—disputes
    between the generator and the owner of the transmission grid
    would arise, delaying completion of the interconnection
    process. See Order No. 2003, FERC Stats. & Regs. ¶ 31,
    146 P 11
     (2003). The Commission waded into those disputes case
    by case, delaying entry into the market by new generators and
    5
    providing an unfair competitive advantage to utilities owning
    both transmission and generation facilities. 
    Id.
     at PP 10–11.
    To address those issues, the Commission, in 2003, issued
    Order No. 2003, FERC Stats. & Regs. ¶ 31,146 at PP 11–12.
    That order replaced the Commission’s case-by-case approach
    with a standardized process. The Order requires all regulated
    utilities that “own, control, or operate” transmission facilities
    to include standardized interconnection procedures and a form
    interconnection agreement in their filed tariffs. 
    Id.
     at P 2. By
    mandating that “standard set of procedures,” the Commission
    “minimize[d] opportunities for undue discrimination and
    expedit[ed] the development of new generation, while
    protecting reliability and ensuring that rates are just and
    reasonable.” 
    Id.
     at P 11.
    FACTUAL BACKGROUND
    1. PJM Interconnection, L.L.C., is a regional
    transmission organization, an independent entity that operates
    transmission facilities in thirteen states and the District of
    Columbia. See FPL Energy Marcus Hook, L.P. v. FERC, 
    430 F.3d 441
    , 442–443 (D.C. Cir. 2005). Under PJM’s Open
    Access Transmission Tariff, the interconnection process
    begins when a generator of electricity submits an
    interconnection request to PJM. PJM Tariff § 36.1.01, J.A.
    747–748. Each request is placed into a “first-come, first-
    served queue.” Marcus Hook, 
    430 F.3d at 443
    ; see PJM
    Tariff § 201, J.A. 752.
    The submission of an interconnection request triggers an
    often lengthy review by the utility and holds the requestor’s
    place in the interconnection queue until it concludes. During
    this process, PJM conducts “a series of studies to determine
    the impact of a generator interconnection request on the PJM
    transmission system,” including “the need for upgrades or
    6
    additions to those transmission facilities,” PJM Br. 6, and an
    estimate of the requestor’s cost responsibility for any needed
    upgrades, see Marcus Hook, 
    430 F.3d at 443
    . Those studies
    do “not set a rate for interconnection service,” however; they
    merely provide “a non-binding estimate of costs.” Dominion
    Res. Servs., Inc. v. PJM Interconnection, L.L.C, 
    123 FERC ¶ 61,025
     P 52 (2008). Customers are thus free to “terminate
    or withdraw their interconnection requests” at any time.
    Marcus Hook, 
    430 F.3d at 443
    . Once PJM finishes the
    studies, it provides the requestor with a proposed
    interconnection service agreement that “specifies the
    customer’s actual cost responsibility,” including the cost of
    any upgrades needed to PJM’s transmission network to
    sustain the increased demand. 
    Id.
    While a new service request might be what prompts a
    network upgrade, the “integrated transmission grid is a
    cohesive network,” Entergy Servs., Inc., 
    96 FERC ¶ 61,311
    ,
    62,202 (2001), and thus completed upgrades, whether they
    increase network capacity or simply improve stability,
    generally “benefit all transmission customers.” Order No.
    2003, FERC Stats. & Regs. ¶ 31,146 at P 21. For that reason,
    those generators who have to pay for upgrades under the PJM
    Tariff receive “incremental auction revenue rights” that give
    the generator the right to revenue from future sales of
    transmission services associated with the new or upgraded
    facility. See PJM Tariff § 231.1, J.A. 764; see also PJM
    Interconnection, L.L.C., 
    126 FERC ¶ 61,280
     P 3 (2009)
    (describing the function of auction revenue rights). That
    auction revenue, in turn, partially compensates the generator
    for the financial burden it bore in improving the transmission
    network for all users. See Order No. 2003, FERC Stats. &
    Regs. ¶ 31,146 at P 694.
    7
    2. In 1998, three generators submitted interconnection
    requests to PJM for the following projects: the Mantua Creek
    Project, the Liberty Electric Project, and the Marcus Hook
    Project. Rehearing Order at P 3; Marcus Hook, 
    430 F.3d at 444
    . PJM determined that the projects’ combined load would
    “push [its] system beyond the breaking point,” and thus
    advised a $13 million upgrade (“Upgrade”) to a transmission
    circuit. Marcus Hook, 
    430 F.3d at 444
    . Because that
    Upgrade was unnecessary at the time the first project, Mantua
    Creek, entered the queue, Mantua Creek was not assigned any
    cost responsibility for the Upgrade. Marcus Hook, 
    430 F.3d at 444
    . Marcus Hook and Liberty Electric bore it all, with
    90% of the Upgrade’s cost assigned to Marcus Hook. See id.;
    see also Rehearing Order at P 3. Both generators moved
    forward with the project, with Marcus Hook agreeing to pay
    “over $10 million of the upgrade’s total cost.” Marcus Hook,
    
    430 F.3d at 444
    .
    As the Upgrade neared completion, Mantua Creek
    unexpectedly cancelled its project and withdrew from the
    queue. See Rehearing Order at P 3. That decrease in the
    demand for power made the Upgrade unnecessary to support
    Marcus Hook’s and Liberty Electric’s projects. But PJM
    determined that completion of the almost-final Upgrade was
    the “least costly alternative,” and thus “trudged forward and
    completed the upgrade.” Marcus Hook, 
    430 F.3d at 444
    . The
    Upgrade was placed into service in June 2003.
    Marcus Hook felt differently about being required to
    continue financing the Upgrade. Having paid over $9 million
    to PJM for improvements that were no longer necessary,
    Marcus Hook filed a complaint with the Commission seeking
    a refund. Marcus Hook, 
    430 F.3d at
    444–445. The
    Commission rejected Marcus Hook’s complaint. See FPL
    Energy Marcus Hook, L.P. v. PJM Interconnection, L.L.C.,
    8
    
    107 FERC ¶ 61,069
     (2004) (Marcus Hook I), reh’g denied,
    
    108 FERC ¶ 61,171
     (2004) (Marcus Hook II). In 2005, this
    court upheld the Commission’s decision in relevant part.
    Marcus Hook, 
    430 F.3d at
    447–449.
    3. The next year, petitioner West Deptford submitted an
    interconnection request to PJM. Rehearing Order at P 4.
    Under Section 37.7 of the PJM Tariff that was in effect on the
    date that West Deptford submitted its request (July 31, 2006),
    PJM could seek reimbursement for a previously constructed
    network upgrade from a new applicant for interconnection
    like West Deptford if the new proposed project (i) used the
    added capacity created by the upgrade or would have required
    the upgrade itself, (ii) the cost of the upgrade was at least $10
    million, and (iii) the upgrade was “placed in service no more
    than five years prior to the affected Interconnection
    Customer’s Interconnection Queue Closing Date.” PJM
    Superseded Tariff § 37.7, J.A. 745.
    Based on Section 37.7, PJM’s first study of West
    Deptford’s project proposed imposing financial responsibility
    for the Upgrade on West Deptford. See Rehearing Order at
    PP 5, 9; PJM Feasibility Study 8 (Nov. 2006), J.A. 580. West
    Deptford does not dispute that, if the 2006 Tariff controls its
    interconnection agreement, it must reimburse Marcus Hook
    and Liberty Electric for the costs of the Upgrade. Order at
    P 28.
    Eighteen months later, while West Deptford’s
    interconnection request was still pending, PJM filed several
    proposed amendments to its tariff. Rehearing Order at P 11;
    see also Dominion, 
    123 FERC ¶ 61,025
     at PP 1–3 (settlement
    of administrative challenge to PJM Tariff resulted in proposed
    amendments).       One proposed amendment significantly
    changed Section 37.7’s assignment of financial responsibility
    9
    for prior upgrades. As relevant here, under Section 219 of the
    new 2008 tariff, PJM could seek reimbursement for
    previously constructed network upgrades only for a period of
    five years “from the execution date of the Interconnection
    Service Agreement for the project that initially necessitated
    the requirement for the Local Upgrade or Network Upgrade.”
    PJM Tariff § 219(a), J.A. 762. While the tariff was silent
    about the effective date of that change, a transmittal letter
    from PJM noted that the next interconnection queue would
    begin on August 1, 2008, and then “request[ed] an August 1,
    2008 effective date for these Tariff revisions.”          PJM
    Transmittal Letter 17, J.A. 711. Because Liberty Electric
    executed its interconnection agreement on May 14, 2001 and
    Marcus Hook executed its agreement on January 22, 2002,
    Rehearing Order at P 10, the Commission and PJM agree that,
    if the 2008 tariff controls, then that tariff’s five-year time
    limit insulates West Deptford from having to pay for the
    Upgrade, Order at P 34.
    Proceedings commenced before the Commission
    challenging aspects of the 2008 tariff, but West Deptford was
    not a party. In that proceeding, PJM received an inquiry
    asking whether the new cost-allocation provisions would
    “apply only to projects that enter the interconnection queue on
    or after the proposed effective date of August 1, 2008 or
    whether they will apply also to projects that have entered the
    queue before that date.” Request for Clarification of
    American Municipal Power – Ohio, Inc. at 1, Dominion Res.
    Servs., Inc. v. PJM Interconnection, L.L.C., Docket No.
    EL08-36-001 (FERC June 20, 2008). PJM responded that
    one revised provision of the tariff (known as Section 217.3a,
    J.A. 761, which governs upgrades costing less than $5 million
    and is not at issue here) “will become effective on August 1,
    2008, and will be initially applied to the U2-Queue (this
    queue will close on July 31, 2008).” Answer of PJM
    10
    Interconnection, L.L.C. to Request for Clarification of
    American Municipal Power – Ohio, Inc. at 4, Dominion Res.
    Servs., Inc. v. PJM Interconnection, L.L.C., Docket No.
    EL08-36-001 (FERC July 7, 2008), J.A. 555. With respect to
    Section 219(a), J.A. 762, the provision at issue here, PJM
    separately stated that “[t]hese modifications are intended to be
    effective as of August 1, 2008, and will be initially applied to
    the U2-Queue.” Id.
    On August 19, 2008, the Commission accepted PJM’s
    revised tariff, but referenced only PJM’s clarification of the
    effective date for the provision not relevant here, stating that
    Section 217.3a “will be applied to the U2-Queue effective
    August 1, 2008.” FERC Letter Order at 1, Dominion Res.
    Servs., Inc. v. PJM Interconnection, L.L.C., Docket No.
    EL08-36-001 (August 19, 2008), J.A. 742. The Commission
    did not mention PJM’s clarification of the effective date for
    the provision at issue in this case, Section 219(a). See id.
    Over the next three years, PJM conducted two more
    studies of West Deptford’s interconnection request. In both
    of them, PJM expressed its intention to charge West Deptford
    the full $10 million for the Upgrade, as had been permitted by
    the superseded tariff. PJM System Impact Study Report 4–5
    (September 2010), J.A. 594–595; PJM Facilities Study Report
    4, 10 (April 2011), J.A. 612, 618. West Deptford claims,
    Reply Br. 25, and no one disputes, that it repeatedly objected
    to this attempted cost allocation.
    PROCEDURAL HISTORY
    In 2011, PJM provided West Deptford a draft
    interconnection service agreement that imposed the full cost
    of the Upgrade on West Deptford. West Deptford Protest at
    9, J.A. 434. West Deptford objected, id., and PJM filed the
    unexecuted agreement with the Commission, seeking its
    11
    resolution of the dispute. Rehearing Order at P 6. West
    Deptford argued that imposing the superseded tariff’s terms
    for cost allocation violated both the filed rate doctrine and
    past Commission precedent enforcing the terms of tariffs that
    were in effect when an interconnection agreement was
    executed or filed, rather than when a prospective customer
    entered the queue. West Deptford Protest at 15, J.A. 440.
    West Deptford also argued, as relevant here, that even if it
    were required to reimburse Marcus Hook and Liberty Electric
    for the Upgrade, its cost should be offset by the value of the
    auction revenue rights that Marcus Hook and Liberty Electric
    had already received and exercised as a result of having
    previously paid for the Upgrade’s construction. Id. at 26–27,
    J.A. 451–452.
    The Commission rejected West Deptford’s protest.
    Acknowledging that West Deptford could not be liable for the
    Upgrade under the on-file tariff, the Commission nonetheless
    concluded that the cost-allocation provisions of the
    superseded tariff should govern “since, at the time when West
    Deptford entered the PJM interconnection queue, that
    provision was the one that established its financial
    responsibility.”     Order at P 35.         According to the
    Commission, that fact put West Deptford “on notice of the
    costs to which it potentially would be liable.” Id. at P 38.
    With respect to West Deptford’s separate claim for
    auction revenue rights, the Commission ruled that the issue
    was not ripe. Order at P 43. In so ruling, the Commission
    relied this time on the on-file 2008 Tariff, and noted that it
    provided that the surrender of auction revenue rights applies
    only once the “New Service Customer * * * executes * * * an
    Interconnection Service Agreement,” which West Deptford
    has not yet done.        Id. at P 43 (quoting PJM Tariff
    § 231.4(1)(b), J.A. 767; omissions in original).
    12
    West Deptford requested rehearing, which the
    Commission denied. The Commission said that PJM could
    enforce the superseded tariff’s cost-allocation rule because,
    during the tariff-revision proceedings to which West Deptford
    was not a party, PJM had clarified that the new tariff’s cost-
    allocation provision (Section 219) would only apply starting
    with projects in the “U2 Queue,” which closed in the Summer
    of 2008. Rehearing Order at P 31. The Commission also
    reasoned that each of PJM’s interconnection studies had
    provided West Deptford notice of PJM’s intent to enforce the
    superseded tariff’s cost-allocation provision. Id. at P 28.
    With respect to past Commission precedent, the Commission
    stated that its decisions did not bind it to “a single policy to
    address all of the myriad issues that may arise from a change
    to cost allocation in the interconnection process.” Id. at P 38.
    Finally, the Commission restated, without additional
    explanation, its conclusion that West Deptford’s auction-
    revenue-rights claim would be unripe until after it executed
    the interconnection agreement. Id. at P 59.
    West Deptford timely petitioned for review, and PJM and
    Marcus Hook intervened.
    II
    STANDARD OF REVIEW
    We have jurisdiction under 16 U.S.C. § 825l(b). We
    review Commission orders under the arbitrary and capricious
    standard, and will uphold the Commission’s factual findings
    if they are supported by substantial evidence. See 
    5 U.S.C. § 706
    (2); see also, e.g., Sacramento Municipal Util. Dist. v.
    FERC, 
    616 F.3d 520
    , 528 (D.C. Cir. 2010). Under that
    familiar standard, we must determine whether the
    Commission’s orders “examined the relevant data and
    articulated a rational connection between the facts found and
    13
    the choice made.” Alcoa Inc. v. FERC, 
    564 F.3d 1342
    , 1347
    (D.C. Cir. 2009) (internal punctuation and citation omitted).
    While we defer to the Commission’s interpretation of its own
    precedent, see NSTAR, 
    481 F.3d at 799
    , the Commission
    cannot depart from those rulings without “‘provid[ing] a
    reasoned analysis indicating that prior policies and standards
    are being deliberately changed, not casually ignored.’” Alcoa,
    
    564 F.3d at 1347
     (quoting Entergy Servs., Inc. v. FERC, 
    319 F.3d 536
    , 541 (D.C. Cir. 2003)). Those same principles also
    govern our review of the Commission’s application of the
    filed rate doctrine. See NSTAR, 
    481 F.3d at 800
    . Our review
    of the Commission’s interpretation of filed tariffs is
    “Chevron-like in nature,” which means that we give
    “substantial deference” to the Commission’s interpretation
    unless “the tariff language is unambiguous.” Old Dominion
    Elec. Co-Op., Inc. v. FERC, 
    518 F.3d 43
    , 48 (D.C. Cir. 2008)
    (internal quotation marks omitted).
    III
    ANALYSIS
    As in many Federal Energy Regulatory Commission
    cases, aspects of this case seem complex. But the legal
    principles that dictate our decision are relatively
    straightforward. The Commission held that the amount of
    money West Deptford would have to pay to obtain
    transmission services would be dictated by a tariff provision
    that had been superseded more than three years before PJM
    even proposed a contract. To sustain that determination, the
    Commission was obligated to provide a reasoned explanation
    of how applying that charge comported with the text of the
    Federal Power Act and prior Commission precedent. The
    Commission’s decision did neither.           Nor did the
    Commission’s ripeness analysis adequately address West
    14
    Deptford’s claims concerning already-exercised auction
    revenue rights. We accordingly vacate the orders in part and
    remand the case to the Commission for further proceedings
    consistent with this decision.
    A. THE COMMISSION’S             APPLICATION OF THE
    SUPERSEDED TARIFF            WAS NOT ADEQUATELY
    REASONED
    1. The Commission’s decision, first and foremost, must
    conform to statutory direction. And the Federal Power Act is
    quite clear: “All rates and charges made, demanded, or
    received by any public utility for or in connection with the
    transmission or sale of electric energy” subject to the
    Commission’s jurisdiction must be “file[d] with the
    Commission,” “open in convenient form,” and available for
    “public inspection.” 16 U.S.C. § 824d(a) & (c) (emphasis
    added). Furthermore, if a utility makes any changes to a filed
    “rate, charge, classification, or service,” its public filing with
    the Commission must “stat[e] plainly” both the changes made
    to the tariff “then in force,” and “the time when the change or
    changes will go into effect.” Id. § 824d(d) (emphasis added).
    PJM’s 2008 tariff did not identify any effective date for
    its changed cost-allocation provision, let alone do so
    “plainly.” In particular, nothing in the tariff explained when
    the cost-allocation rules would transition from those
    previously in force (which would have obligated West
    Deptford to pay for the Upgrade) to those in the 2008 tariff
    (which would not charge West Deptford for the Upgrade).
    Right out of the box, then, the Commission’s application of
    the superseded tariff, rather than the new one, ran into
    statutory headwinds that the Commission needed to address.
    2. As the Commission noted, Order at P 37, a
    transmittal letter accompanying the new tariff did request an
    15
    “August 1, 2008 effective date for these Tariff revisions,” J.A.
    711. The Commission’s decision seems to assume, and West
    Deptford does not disagree, that the transmittal letter satisfied
    the Act’s legal requirements that the notice of the change’s
    effective date be “fil[ed] with the Commission” and be “open
    for public inspection,” 16 U.S.C. § 824d(d), and so we
    assume for purposes of decision that it does (although it
    would have been far better for the Commission to explain its
    thinking).
    The dispute in this case centers, instead, on whether the
    Commission’s application of the transmittal letter’s request
    for an August 1, 2008 effective date in this case “plainly”
    stated that the effective date would be August 1, 2008 only for
    those generators in the U2 queue, and not for those generators
    in earlier queues who signed interconnection agreements after
    the August 1st effective date. The Commission failed to
    adequately explain how it found the statutory requirements
    satisfied in this case.
    To start with, the letter, by its plain terms, does not
    contain the limitation on who gets the August 1, 2008
    effective date that the Commission enforced. At best, the
    request for “an August 1, 2008 effective date for these Tariff
    revisions,” J.A. 711, is silent about whether the date of the
    interconnection agreement or of entry into the queue had to
    fall on or after August 1st. And, at worst, given the Federal
    Power Act’s textual application of filed rates to “any
    transmission or sale,” 16 U.S.C. § 824d(c), the letter implies
    that, beginning August 1st, all charges for transmission and
    sales contracts, including interconnection service, would hew
    to the new tariff’s terms.
    PJM’s letter transmitting the new tariff to the
    Commission did introduce its proposed effective date by
    16
    noting that it requested August 1, 2008, “[b]ecause the next
    interconnection queue will begin on August 1, 2008.” J.A.
    711. But that introductory clause, which is crafted in
    explanatory rather than operative language, simply adds to the
    confusion about what must be in place by August 1st.
    Furthermore, the Commission never endorsed that
    prefatory language as part of the effective date when it
    accepted PJM’s tariff revisions, see J.A. 742, and it has failed
    to provide any explanation of whether and how the bare
    mention of the next queue date, without endorsement by the
    Commission at the time of acceptance, could have legally
    operative force for purposes of the filed rate doctrine. Indeed,
    the Commission has yet to explain, in this ruling or any other
    of which we are aware, what the legal status of information in
    a transmittal letter is—and what the impact of Commission
    endorsement is—for purposes of compliance with the Federal
    Power Act’s filed rate requirements.
    3. A further barrier to affirming the Commission’s
    decision is that it appears to contradict Commission precedent
    applying the tariff in effect on the date of execution of an
    interconnection agreement or the agreement’s filing with the
    Commission, and not the date a generator entered the queue.
    For example, in Midwest Independent Transmission System
    Operator, Inc. (MISO III), 
    125 FERC ¶ 61,277
     P 10 (2008),
    Midwest filed an amended tariff that took effect in August
    2008. When Midwest filed two interconnection agreements
    the next month, however, it sought—just as PJM does here—
    to apply the superseded tariff that was in effect when its
    customers entered the queue, rather than the updated tariff.
    
    Id.
     at P 5. The Commission flatly rejected that effort. 
    Id.
     at
    P 10. In sharp contrast to its decision in this case, the
    Commission ruled that Midwest could not apply the old tariff
    17
    to agreements executed after the amended tariff took effect.
    
    Id.
    The Commission reaffirmed that position two years later
    in another Midwest case. Describing its previous holding in
    MISO III, the Commission explained that, “because two
    generator interconnection agreements had been executed after
    the effective date of newly revised interconnection queue
    rules, the interconnection agreements [had to] be revised to
    conform with the new rules,” rather than the rules in place at
    the time the generators entered the queue. Midwest Indep.
    Transmission Sys. Operator, Inc. (MISO IV), 
    129 FERC ¶ 61,060
     P 62 n.120 (2009). The Commission then held that,
    as in MISO III, it had to apply the tariff “effective and on file
    on the date that the interconnection agreement is executed or
    filed unexecuted.” MISO IV, 
    129 FERC ¶ 61,060
     at P 62; see
    also Midwest Indep. Transmission Sys. Operator, Inc. (MISO
    I), 
    114 FERC ¶ 61,106
     P 70 (2006) (interconnection
    agreement would be governed by the presently effective tariff,
    rather than the tariff in effect when the agreement was being
    negotiated); Midwest Indep. Transmission Sys. Operator, Inc.
    (MISO V), 
    131 FERC ¶ 61,165
     P 32 (2010) (although cost-
    allocation methodology in tariff changed while
    interconnection agreement was being negotiated, “the cost
    allocation methodology that was effective and on file” on the
    date the agreement was executed or filed with the
    Commission controlled); Midwest Indep. Transmission Sys.
    Operator, Inc. (MISO VI), 
    138 FERC ¶ 61,199
     P 42 (2012)
    (declining to apply deadlines in an amended tariff because the
    interconnection agreement was governed by “the tariff
    effective and on file at the time the [agreement] was filed with
    the Commission and proposed to take effect”); MidAmerican
    Energy Co., 
    116 FERC ¶ 61,018
     P 13 (2006) (following
    practice of “review[ing] interconnection agreements based on
    18
    the terms and conditions in effect on the date when they are
    filed”).
    Indeed, until now, there appeared to be an unbroken
    Commission practice of holding that interconnection
    agreements filed after the designated effective date of an
    amended tariff are governed by the amended tariff, unless the
    amended tariff has a grandfathering provision. See Edison
    Mission Energy v. Midwest Indep. Transmission Sys.
    Operator, Inc., 
    136 FERC ¶ 61,035
     PP 38–40 (2011)
    (applying grandfathering provision in tariff that divided
    interconnection requests into four categories based on their
    status when tariff revisions took effect); Arizona Public Serv.
    Co., 
    137 FERC ¶ 61,099
     P 25 (2011) (accepting proposed
    tariff revision “grandfather[ing] existing interconnection
    requests for” customers that had reached a certain milestone
    in the interconnection process).
    It is textbook administrative law that an agency must
    “provide[] a reasoned explanation for departing from
    precedent or treating similar situations differently,” ANR
    Pipeline Co v. FERC, 
    71 F.3d 897
    , 901 (D.C. Cir. 1995), and
    Commission cases are no exception, see Colorado Interstate
    Gas Co. v. FERC, 
    146 F.3d 889
    , 893 (D.C. Cir. 1998)
    (“Because it has not adequately explained its decision to treat
    [entities] differently in a context where they appear similarly
    situated, we remand the case to the Commission for a fuller
    explanation.”). The Commission, however, failed to provide
    a reasoned explanation for why West Deptford’s
    interconnection agreement should be treated any differently
    than those in predecessor decisions.         Accordingly, the
    Commission’s deviation from that precedent is not “justified
    either as consistent with precedent or as a considered
    departure therefrom.” Williams Gas Processing-Gulf Coast
    Co. v. FERC, 
    475 F.3d 319
    , 327 (D.C. Cir. 2006).
    19
    4. With a paean to administrative flexibility, the
    Commission argues that it can employ a case-by-case
    approach to deciding whether entry into the queue or, instead,
    the execution or filing of an interconnection agreement is the
    relevant trigger for an effective date. Perhaps. But the
    Commission must first provide a reasoned decision
    explicating how such case-by-case variation, absent explicit
    tariff provisions publicly identifying different effective dates
    for customers, jibes with the Federal Power Act’s unqualified
    directive that “the time when the change or changes” in an
    amended tariff will displace the schedules “then in force” and
    “go into effect” must be “plainly” stated in an open,
    accessible, and convenient manner, 16 U.S.C. § 824d(d). In
    addition, the Commission would have to explain how such a
    case-by-case approach would protect against the
    discrimination and unpredictability in rates and charges that
    Section 824d proscribes. See NSTAR, 
    481 F.3d at 800
    .
    That is just the beginning. The Commission would also
    need to elucidate how such case-by-case variation would fit
    with the Federal Power Act’s purposes given that it has
    previously decided that those aims are best served by
    imposing increased uniformity in tariff terms in lieu of
    conducting case-by-case adjudications. See Order No. 2003,
    FERC Stats. & Regs. ¶ 31,146 at P 11. Generally, such
    standardization “ensures that interconnection customers * * *
    receive    non-discriminatory     service   and    that    all
    interconnection customers are treated on a consistent and fair
    basis.” MidAmerican Energy, 
    116 FERC ¶ 61,018
     at P 7.
    And finally, the Commission would have to provide a
    reasoned analysis, resting on articulated objective, non-
    discriminatory, and evenhanded criteria, that would justify
    treating West Deptford differently than the generators in all
    those other cases in which the Commission enforced the tariff
    20
    in effect at the time an agreement was filed or executed. See
    Muwekma Ohlone Tribe v. Salazar, 
    708 F.3d 209
    , 216 (D.C.
    Cir. 2013) (“Agency action is arbitrary and capricious if ‘the
    agency offers insufficient reasons for treating similar
    situations differently.’”) (quoting County of Los Angeles v.
    Shalala, 
    192 F.3d 1005
    , 1022 (D.C. Cir. 1999)). That is
    because identifying the relevant factors that would govern a
    case-by-case analysis is critical to ensuring that the Federal
    Power Act’s requirements of openness, equal treatment, and
    predictability in rates are enforced.
    The Commission’s decision in this case did none of those
    things. The Commission instead pointed to yet another
    Midwest decision as purportedly evidencing its case-by-case
    approach. See Rehearing Order at P 40 (citing Midwest
    Indep. Transmission Sys. Operator, Inc. (MISO II), 
    124 FERC ¶ 61,183
     P 90 (2008), order on reh’g, 
    127 FERC ¶ 61,294
    ).
    But MISO II makes things worse not better for the
    Commission’s position. In that case, the Commission
    permitted Midwest to apply interconnection procedures from
    its old tariff to certain customers already waiting in the queue.
    MISO II, 
    124 FERC ¶ 61,183
     at PP 1, 84–90. But the
    Commission did so because the text of the revised tariff itself
    provided for that differential treatment. See Proposed
    Revisions to Open Access Transmission and Energy Markets
    Tariff part 2, § 5.1.2, Midwest Indep. Sys. Operator, Inc.,
    Docket No. ER08-1169 (FERC June 26, 2008). In other
    words, all that MISO II establishes is that the Commission
    may approve a tariff the express terms of which differentiate
    when its terms will take effect and when they will not. That
    does nothing to justify what appears to be the Commission’s
    one-off decision in this case to deviate both from the filed
    tariff and from precedent consistently enforcing the tariff on
    file on the date an agreement is filed or executed, even though
    21
    the on-file tariff contained no grandfather clause or any other
    indication of its variable application.
    Compounding the problem for the Commission is its
    reliance on FPL Energy Marcus Hook, L.P. v. PJM
    Interconnection, L.L.C. (Marcus Hook III), 
    118 FERC ¶ 61,169
     (2008). Critically, that case involved not just the
    PJM system, but the very network upgrade for which cost
    allocation is at issue in this case. 
    Id.
     at P 2. The Commission
    in this case read Marcus Hook III as establishing that the time
    a generator enters the queue could be the relevant point at
    which costs are determined, given how long the
    interconnection process can take and the need to account for
    business risks at the outset. Order at P 36 & n.29; Rehearing
    Order at P 36. But in so stating, the Commission coyly cited
    a footnote in Marcus Hook III, and described it as applying
    the “tariff on file ‘when the interconnection was being
    considered.’” Order at P 36 n.29 (quoting Marcus Hook III,
    
    118 FERC ¶ 61,169
     at P 11 n.9) (emphasis added); Rehearing
    Order at P 36 (quoting same footnote). So fortified, the
    Commission then assured that “[s]imilarly, the tariff we apply
    here is the one on file when West Deptford’s interconnection
    request was being considered.” Rehearing Order at P 36
    (emphasis added).
    The Commission would have done better to look above
    the footnote to what it actually ruled in Marcus Hook III,
    because there is nothing at all “similar[]” about the two
    outcomes. Quite the opposite, as counsel for the Commission
    conceded at oral argument, Oral Arg. Tr. 44:18-20, Marcus
    Hook III applied not the tariff in effect at the time the
    interconnection customer entered the queue, but “the PJM
    tariff in effect at the time the Interconnection Service
    Agreement was executed[.]” 
    118 FERC ¶ 61,169
     at P 10
    (emphasis added); see also FPL Energy Marcus Hook, L.P. v.
    22
    PJM Interconnection, L.L.C. (Marcus Hook IV), 
    123 FERC ¶ 61,289
     P 6 n.6 (2008) (reconfirming, on denial of rehearing,
    that PJM’s 2001 tariff, which was “in force at the time of
    execution of the [interconnection service agreement],”
    controlled); see also 
    id.
     at P 80 (tariff provision in effect “at
    the time that the [interconnection service agreement] was
    executed” “properly governs the relationship between the
    parties”).
    In other words, the last time the Commission addressed
    for this very same tariff the question of which event the
    effective date turned on—the queue entry date or the
    interconnection agreement date—the Commission gave the
    exact opposite answer.        That is the very essence of
    unreasoned and arbitrary decisionmaking: “[G]loss[ing] over
    or swerv[ing] from prior precedents without discussion * * *
    cross[es] the line from the tolerably terse to the intolerably
    mute.” Bush-Quayle ’92 Primary Committee, Inc. v. FEC,
    
    104 F.3d 448
    , 453 (D.C. Cir. 1997) (internal quotation marks
    omitted).
    5. The Commission also invoked the so-called notice
    exception to the filed rate doctrine. We have said that the
    “filed rate doctrine simply does not extend to cases in which
    buyers are on adequate notice that resolution of some specific
    issue may cause a later adjustment to the rate being collected
    at the time of service.” Natural Gas Clearinghouse v. FERC,
    
    965 F.2d 1066
    , 1075 (D.C. Cir. 1992). Unfortunately, “[o]ur
    decisions on the necessary notice have not been altogether
    clear.” Transwestern Pipeline Co. v. FERC, 
    897 F.2d 570
    ,
    577 (D.C. Cir. 1990). For the most part, however, the notice
    exception has been confined to two scenarios.
    First, it permits the filing of tariffs that provide a formula
    for calculating rates, rather than a specific rate number. This
    23
    court had held that such a “formula itself is the filed rate that
    provides sufficient notice to ratepayers” to comport with the
    Federal Power Act’s open-filing requirements, and that the
    objectivity     of    formulae      ensures     evenhandedness,
    predictability and stability in rates. Public Utils. Comm’n v.
    FERC, 
    254 F.3d 250
    , 254 n.3 (D.C. Cir. 2001); see also
    Transwestern Pipeline, 
    897 F.2d at 578
     (“The Commission
    need not confine rates to specific, absolute numbers but may
    approve a tariff containing a rate ‘formula’ or a rate ‘rule’
    * * *; it may not, however, simply announce some formula
    and later reveal that the formula was to govern from the date
    of announcement[.]”); see also 
    id.
     (“[W]e think that where the
    Commission explicitly adopts a formula and indicates when it
    will take effect, courts may not * * * say that such a formula
    may never qualify as a ‘rate[.]’”) (emphasis added); NSTAR,
    
    481 F.3d at 801
     (confirming the “acceptability of tariffs with
    a rate formula” under the filed rate doctrine).
    Second, the notice exception has been applied when
    judicial invalidation of Commission decisions has resulted in
    retroactive changes in rates. Canadian Ass’n of Petroleum
    Producers v. FERC, 
    254 F.3d 289
    , 299–300 (D.C. Cir. 2001);
    Western Resources, Inc. v. FERC, 
    72 F.3d 147
    , 151 (D.C. Cir.
    1995); Public Utils. Comm’n v. FERC, 
    988 F.2d 154
    , 163–
    166 (D.C. Cir. 1993); Natural Gas Clearinghouse, 
    965 F.2d at
    1075–1077. The Commission has reasoned, and this court
    has agreed, that generators in those cases were aware in
    advance of the risk of litigation-induced change and, more
    importantly, “[w]ere the Commission not able to take
    remedial action to correct its errors, ‘[ratepayers] would be
    substantially and irreparably injured by Commission errors,
    and judicial review would be powerless to protect them from
    many of the losses so incurred.’” See Western Resources, 72
    24
    F.3d at 151 (quoting Natural Gas Clearinghouse, 
    965 F.2d at
    1074–1075) (internal brackets omitted). 1
    This case presented neither of those well-established
    situations. Instead, the Commission pointed (Order at P 26)
    to PJM’s statement in a pleading during the tariff-revision
    process that the revisions to the cost-allocation provision “are
    intended to be effective as of August 1, 2008, and will be
    initially applied to the U2-queue.”           J.A. 555.     The
    Commission’s decision, however, failed to provide any
    reasoned explanation of how such language in a non-binding
    pleading in litigation to which West Deptford was not even a
    party could provide the type of fair notice the Federal Power
    Act and precedent require.
    To begin with, as the Commission’s counsel
    acknowledged at oral argument, PJM’s supposedly clarifying
    statement was actually “confusing” as to the effective date.
    Oral Arg. Tr. 49:8. While the pleading said that amended
    Section 219(a) would “be effective as of August 1, 2008, and
    will be initially applied to the U2-Queue,” just a few
    sentences earlier PJM said that the “U2-Queue * * * will
    close on July 31, 2008.” Answer of PJM Interconnection,
    L.L.C. to Request for Clarification of American Municipal
    Power – Ohio, Inc. at 4, Dominion Res. Servs., Inc. v. PJM
    Interconnection, L.L.C., Docket No. EL08-36-001 (FERC
    July 7, 2008), J.A. 555. The first statement suggests
    prospectivity; the latter applies Section 219 backward to some
    unidentified date (apparently, sometime in May 2008) at
    which the U2 queue started. 2 Applying the new provision to
    1
    Parties may also mutually agree to give a new rate retroactive
    effect. See Consolidated Edison, 
    347 F.3d at 969
    .
    2
    See PJM INTERCONNECTION, L.L.C., Generation Queues: Active,
    http://www.pjm.com/planning/generation-interconnection/
    generation-queue-active.aspx (follow “U2” hyperlink) (last visited
    25
    customers who started the process in May ill fits the concept
    of an August effective date. More to the point, that
    contradiction undermines the Commission’s insistence that it
    accepted PJM’s tariff with only “prospective” effect,
    Rehearing Order at P 29, and “appl[ied] the tariff change at
    issue only to future queue participants,” 
    id.
     at P 42.
    Beyond that, charging customers with notice of every
    statement in every pleading submitted in proceedings to
    which they are not even parties is a far logical leap from the
    discrete categories to which the notice exception has generally
    been limited. The Commission cited no prior application of
    the notice exception that stretched this far. The Commission
    also failed to explain how that material expansion of the
    notice exception remains consistent with the express
    commands of the Federal Power Act and the filed rate
    doctrine, or how an exception so broadly construed could
    avoid consuming the rule that rates are supposed to identify
    new changes “plainly,” and do so in filed tariffs that are “open
    in convenient form and place for public inspection.” 16
    U.S.C. § 824d(c) & (d). Perhaps it can do that, but the
    decision on review provides no trace of a reasoned decision in
    that regard.
    Finally, the Commission indicated that the studies PJM
    undertook while West Deptford was in the queue provided
    ample notice because each assigned West Deptford financial
    responsibility for the Upgrade. The problem with that
    argument is threefold. First, it overlooks that West Deptford
    repeatedly objected throughout that time period to any such
    imposition of cost responsibility as impermissible.
    August 3, 2008) (listing projects entering the U2 queue from May
    16, 2008 through July 31, 2008).
    26
    Second, as with the pleading, the Commission provides
    no reasoned explanation for expanding the notice exception to
    encompass such one-way assertions, especially since
    generators have no apparent way to challenge any costs such
    studies purport to assign at that stage in the interconnection
    process.
    Third, the Commission’s position paid no heed to prior
    Commission precedent that treated such studies as just a
    “non-binding estimate of costs.” Dominion, 
    123 FERC ¶ 61,025
     at P 52.
    In sum, because the Commission failed, at multiple steps,
    to provide any reasoned explanation of how its decision
    conformed to the Federal Power Act and prior precedent, we
    must remand for the Commission “to explain why its decision
    in this case is not inconsistent with [past precedent] or,
    alternatively, to justify its apparent departures.” Brusco Tug
    & Barge Co. v. NLRB, 
    247 F.3d 273
    , 278 (D.C. Cir. 2001);
    see also Northeast Energy Associates v. FERC, 
    158 F.3d 150
    ,
    156 (D.C. Cir. 1998).
    B. The Commission Failed to Address the Impact of
    Already Exercised Auction Revenue Rights on West
    Deptford’s Cost
    Before the Commission, West Deptford made two
    distinct arguments regarding auction revenue rights should the
    2006 Tariff apply. First, West Deptford argued that PJM
    could not force West Deptford to pay for the Upgrade until
    Marcus Hook and Liberty Electric surrendered any
    unexercised auction revenue rights they still had. Second,
    West Deptford contended that its $10 million charge should
    be offset by the amount of compensation for building the
    Upgrade that Marcus Hook and Liberty Electric had already
    received from auction revenue rights they had previously
    27
    exercised. West Deptford Protest at 25–27, J.A. 450–452;
    West Deptford Request for Rehearing at 24–26, J.A. 665–667.
    Addressing only the first argument, the Commission
    construed the 2008 PJM Tariff to require transfer of
    unexercised auction rights only after West Deptford executed
    “‘an Interconnection Service Agreement.’” Order at P 43
    (quoting PJM Tariff § 231.4(1)). Because West Deptford
    “ha[d] not yet executed its” agreement, the Commission ruled
    that West Deptford’s claim was “not yet ripe.” Id.        In
    denying rehearing, the Commission reiterated that, once West
    Deptford executes the interconnection service agreement, its
    claim to auction revenue rights “will be perfected and PJM
    will be required to assign those [rights] as provided in its
    tariff.” Rehearing Order at P 59.
    While the Commission’s decision about the transfer of
    auction rights yet to be exercised was reasonable as far as it
    went, it did not go far enough. The ripeness rationale does
    not work for West Deptford’s separate argument that the $10
    million price tag should have been offset by the amount of the
    cost that Marcus Hook and Liberty Electric had already
    recovered through exercising auction revenue rights. Put
    differently, West Deptford asked the Commission for a price
    check on the Upgrade. There was nothing unripe about that.
    To the extent that Marcus Hook and Liberty Electric already
    recouped their payments from those auction revenue rights,
    they would have been paid a second time when West
    Deptford handed over its $10 million. Oral Arg. Tr. 38:19-20.
    West Deptford thus is presently out of pocket any such
    overpayment.
    The Commission’s counsel posited at oral argument that
    the issue remained unripe because, under the PJM Tariff,
    Marcus Hook or Liberty Electric could choose not to
    28
    relinquish any auction rights. Oral Arg. Tr. 68:13-21. But if
    that happened, it would appear to reduce West Deptford’s
    financial responsibility to zero, and disentitle Marcus Hook
    and Liberty Electric to their respective shares of the $10
    million already paid over by West Deptford. See PJM Tariff
    § 231.4(d)(2), J.A. 767. Why Marcus Hook and Liberty
    Electric are allowed to keep both the funds already received
    from exercised auction rights and the $10 million is left
    entirely unexplained by the Commission.
    In any event, we need not—and indeed cannot—consider
    “appellate counsel’s post hoc rationalizations” for
    Commission action. Maine Public Utils. Comm’n v. FERC,
    
    625 F.3d 754
    , 759 (D.C. Cir. 2010) (internal quotation marks
    omitted). The Commission’s failure to explain why the
    retrospective offsets could not be calculated, and our inability
    to “discern a reasoned path” to that conclusion, Marcus Hook,
    
    430 F.3d at 449
    , require us to remand for further explanation.
    IV
    CONCLUSION
    Because the Commission failed to provide an adequate
    explanation either for its decision to apply the superseded
    tariff to an interconnection agreement filed after the new
    tariff’s effective date, or for its refusal to address the auction
    revenue rights offset, we grant West Deptford’s petition for
    review, vacate the Commission’s orders in relevant part, and
    remand to the Commission for additional explanation
    consistent with the decision of this court.
    So ordered.
    

Document Info

Docket Number: 12-1340

Citation Numbers: 412 U.S. App. D.C. 295, 766 F.3d 10

Filed Date: 8/26/2014

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (26)

public-utilities-commission-of-the-state-of-california-v-federal-energy , 988 F.2d 154 ( 1993 )

Consolidated Edison Co. of New York, Inc. v. Federal Energy ... , 347 F.3d 964 ( 2003 )

Brusco Tug & Barge Co. v. National Labor Relations Board , 247 F.3d 273 ( 2001 )

Bush-Quayle '92 Primary Committee, Inc. v. Federal Election ... , 104 F.3d 448 ( 1997 )

FPL Energy Marcus Hook, L.P. v. Federal Energy Regulatory ... , 430 F.3d 441 ( 2005 )

NSTAR Electric & Gas Corp. v. Federal Energy Regulatory ... , 481 F.3d 794 ( 2007 )

canadian-association-of-petroleum-producers-v-federal-energy-regulatory , 254 F.3d 289 ( 2001 )

Williams Gas Processing-Gulf Coast Co. v. Federal Energy ... , 475 F.3d 319 ( 2006 )

Alcoa Inc. v. Federal Energy Regulatory Commission , 564 F.3d 1342 ( 2009 )

Sacramento Municipal Utility District v. Federal Energy ... , 616 F.3d 520 ( 2010 )

transwestern-pipeline-company-v-federal-energy-regulatory-commission-the , 897 F.2d 570 ( 1990 )

natural-gas-clearinghouse-v-federal-energy-regulatory-commission-anadarko , 965 F.2d 1066 ( 1992 )

Colorado Interstate Gas Co. v. Federal Energy Regulatory ... , 146 F.3d 889 ( 1998 )

Old Dominion Electric Cooperative, Inc. v. Federal Energy ... , 518 F.3d 43 ( 2008 )

NE Engy Assoc v. FERC , 158 F.3d 150 ( 1998 )

Pub Util Cmsn St CA v. FERC , 254 F.3d 250 ( 2001 )

Entergy Services, Inc. v. Federal Energy Regulatory ... , 319 F.3d 536 ( 2003 )

Western Resources, Inc. v. Federal Energy Regulatory ... , 72 F.3d 147 ( 1995 )

county-of-los-angeles-a-political-subdivision-of-the-state-of-california , 192 F.3d 1005 ( 1999 )

consolidated-edison-company-of-new-york-inc-v-federal-energy-regulatory , 958 F.2d 429 ( 1992 )

View All Authorities »