Union Neighbors United, Inc. v. Sally Jewell , 831 F.3d 564 ( 2016 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued March 8, 2016                 Decided August 5, 2016
    No. 15-5147
    UNION NEIGHBORS UNITED, INC.,
    APPELLANT
    v.
    SALLY JEWELL, IN HER OFFICIAL CAPACITY AS SECRETARY OF
    THE UNITED STATES DEPARTMENT OF THE INTERIOR, ET AL.,
    APPELLEES
    Appeal from the United States District Court
    for the District of Columbia
    (No. 1:13-cv-01435)
    W. William Weeks argued the cause and filed the briefs
    for appellant.
    Robert P. Stockman, Attorney, U.S. Department of
    Justice, argued the cause for federal appellees. With him on
    the brief were John C. Cruden, Assistant Attorney General,
    and David C. Shilton, Attorney.
    Paul S. Weiland argued the cause for intervenor-appellee
    Buckeye Wind LLC. With him on the brief was Steven P.
    Quarles.
    2
    Before: SRINIVASAN, MILLETT and WILKINS, Circuit
    Judges.
    Opinion for the Court filed by Circuit Judge WILKINS.
    WILKINS, Circuit Judge: Buckeye Wind, LLC
    (“Buckeye”) wants to build a wind farm in Ohio. However,
    that wind farm may pose a danger to the Indiana bat, a
    federally listed endangered species. In order to comply with
    the Endangered Species Act (“ESA”), Buckeye applied for an
    incidental take permit with the United States Fish and
    Wildlife Service (“the Service”) and submitted a conservation
    plan. The conservation plan provided that Buckeye would
    site its turbines away from known Indiana bat habitats, adjust
    the turbines’ operating times and speeds, and protect
    additional habitat. The Service issued the permit.
    Union Neighbors United, Inc. (“Union Neighbors”)
    challenges the issue of the permit, claiming that the Service
    failed to comply with its obligations under the National
    Environmental Procedures Act (“NEPA”) and failed to make
    required findings under the ESA. As to the Service’s NEPA
    violations, Union Neighbors claims that it failed to consider a
    reasonable range of alternatives before issuing the permit.
    With regard to the ESA, Union Neighbors claims that the
    Service applied the incorrect standard in finding that Buckeye
    “to the maximum extent practicable, minimize[d] and
    mitigate[d] the impacts of such taking.”             16 U.S.C.
    § 1539(a)(2)(B)(ii). We conclude the Service failed to
    comply with its NEPA obligations when it failed to consider
    an economically feasible alternative that would take fewer
    bats than Buckeye’s proposal, and we reverse the District
    Court on that point. However, we also conclude that the
    Service’s interpretation of the ESA is entitled to deference. In
    light of its interpretation, the Service complied with its ESA
    3
    obligations, and we affirm the judgment of the District Court
    on Union Neighbors’ ESA claims accordingly.
    I.
    A.
    The Service’s decision to issue the permit to Buckeye
    implicates two statutory schemes: NEPA and the ESA.
    NEPA “requires federal agencies . . . to consider and
    report on the environmental effect of their proposed actions.”
    WildEarth Guardians v. Jewell, 
    738 F.3d 298
    , 302 (D.C. Cir.
    2013). “NEPA is an ‘essentially procedural’ statute intended
    to    ensure     ‘fully   informed     and    well-considered’
    decisionmaking . . . .” New York v. NRC, 
    681 F.3d 471
    , 476
    (D.C. Cir. 2012) (quoting Vt. Yankee Nuclear Power Corp. v.
    NRDC, 
    435 U.S. 519
    , 558 (1978)). “NEPA has twin aims.
    First, it places upon an agency the obligation to consider
    every significant aspect of the environmental impact of a
    proposed action. Second, it ensures that the agency will
    inform the public that it has indeed considered environmental
    concerns in its decisionmaking process.” Baltimore Gas &
    Elec. Co. v. NRDC, 
    462 U.S. 87
    , 97 (1983) (internal quotation
    marks and citations omitted). An agency meets these aims
    through the preparation of an Environmental Impact
    Statement (“EIS”) for agency action that will “significantly
    affect[] the quality of the human environment.” 42 U.S.C.
    § 4332(C).      The EIS must explore, inter alia, “the
    environmental impact of the proposed action,” 
    id. § 4332(C)(i);
    “any adverse environmental effects which
    cannot be avoided should the proposal be implemented,” 
    id. § 4332(C)(ii);
    and “alternatives to the proposed action,” 
    id. 4 §
    4332(C)(iii). 1   The discussion of alternatives must
    “[r]igorously explore and objectively evaluate all reasonable
    alternatives.” 40 C.F.R. § 1502.14.
    The Service’s decision to issue the permit also required
    compliance with the ESA. The ESA provides a means to
    conserve endangered or threatened species and their
    ecosystems. 16 U.S.C. § 1531(b). The Secretary of the
    Interior, who administers the ESA via the Service, lists
    endangered and threatened species and designates critical
    habitat for those species. 
    Id. § 1533(a)(2)(A);
    (a)(3)(A). An
    endangered species is “any species which is in danger of
    extinction throughout all or a significant portion of its range.”
    
    Id. § 1532(6).
    The ESA prohibits the “take” of an endangered
    species within the United States. 
    Id. § 1538(a)(1)(B).
    “Take”
    is a term of art that “means to harass, harm, pursue, hunt,
    shoot, wound, kill, trap, capture, or collect, or to attempt to
    engage in any such conduct.” 
    Id. § 1532(19).
    Although
    taking is prohibited, the Service may issue a permit to allow
    for an “incidental” taking, meaning the taking is “not the
    purpose of[] the carrying out of an otherwise lawful activity.”
    16 U.S.C. § 1539(a)(1)(B). In order to receive a permit, the
    applicant must submit a conservation plan that complies with
    certain specified requirements laid out at 16 U.S.C.
    § 1539(a)(2)(A).
    After receiving the application, the Service publishes a
    notice and receives comment on whether the permit should
    issue. See 
    id. § 1539(a)(2)(B);
    50 C.F.R. § 17.22 (endangered
    species), 17.32(b)(1)(ii) (threatened species). The Service
    “shall issue the permit” if it receives “assurances” that the
    1
    NEPA’s implementing regulations apply to all federal agencies.
    See 40 C.F.R. § 1500.3.
    5
    conservation plan will be implemented and if it makes the
    following five findings:
    (i) the taking will be incidental;
    (ii) the applicant will, to the maximum extent
    practicable, minimize and mitigate the impacts
    of such taking;
    (iii) the applicant will ensure that adequate
    funding for the plan will be provided;
    (iv) the taking will not appreciably reduce the
    likelihood of the survival and recovery of the
    species in the wild; and
    (v) the measures, if any, [otherwise required by
    the Secretary] will be met.
    16 U.S.C. § 1539(a)(2)(B).
    The ESA also requires federal agencies to insure that any
    action they “authorize[], fund[], or carr[y] out . . . is not likely
    to jeopardize the continued existence of any endangered
    species . . . or result in the destruction or adverse modification
    of habitat of such species.” 16 U.S.C. § 1536(a)(2). If
    agency action “may affect listed species or critical habitat,”
    the agency must consult with the Service. 50 C.F.R.
    § 402.14(a). Consultation ends with the issuance of a
    Biological Opinion, 50 C.F.R. § 402.14(l), which examines
    whether the action will jeopardize the listed species or destroy
    or adversely modify its habitat as well as “those reasonable
    and prudent measures . . . necessary or appropriate to
    minimize such impact,” 16 U.S.C. § 1536(b)(4).
    Although Union Neighbors brings challenges under
    NEPA and the ESA, the Service’s obligations are not identical
    under the two statutory schemes. NEPA’s “mandate to . . .
    agencies is essentially procedural,” Vt. 
    Yankee, 435 U.S. at 6
    558, in this case requiring the Service to consider reasonable
    alternatives to the proposed action, 42 U.S.C. § 4332(C)(iii);
    40 C.F.R. § 1502.14. The ESA provisions at issue required
    the Service to make substantive findings. See Gerber v.
    Norton, 
    294 F.3d 173
    , 184-85 (D.C. Cir. 2002); see also 16
    U.S.C. § 1539(a)(2)(B). Because the standards are not
    identical, a failure to comply with one statute does not
    necessarily result in a failure to comply with the other.
    B.
    The Indiana bat is a mouse-eared bat with habitats
    throughout the Eastern and Midwestern United States.
    During the winter, Indiana bats hibernate underground. 2
    Although the largest population of hibernating Indiana bats is
    present in Kentucky, Missouri, and Indiana, large colonies
    have been found in abandoned underground mines in Illinois,
    Ohio, New Jersey, and New York. During the spring, Indiana
    bats migrate to their summer habitats. For the Indiana bat, the
    “core . . . summer range includes southern Iowa, northern
    Missouri, northern Illinois, northern Indiana, southern
    Michigan, and western Ohio.” J.A. 254. Within Ohio, the
    Service has documented evidence of Indiana bat colonies in
    twenty-five counties. These summer ranges provide roosts
    for pregnant Indiana bats, which form colonies of 25 to 100
    bats, with each bat producing one pup. The bats generally
    migrate to winter sites in late August.
    Indiana bats were first listed as in danger of extinction in
    1967 under the Endangered Species Preservation Act of 1966,
    and were listed as endangered under the ESA in 1973
    following the law’s enactment. The Indiana bat recovery plan
    2
    The bats’ hibernating habitat is called “hibernacula.” Appellant
    Br. at 3; Fed. Appellees Br. at 6.
    7
    was first published in 1983 and later updated in 1999 and
    2007. Although the overall Indiana bat population declined
    from 1965 to 2001, the trend reversed from 2001 through
    2011, with the population increasing from 328,526 in 2001 to
    424,708 in 2011. The Midwest Recovery Unit, 3 which
    includes Ohio, contains a population of approximately
    305,297 Indiana bats. Despite these gains, several factors
    threaten the Indiana bat population, “including the loss and
    degradation of suitable hibernacula; human disturbance
    during hibernation; pesticides; . . . the loss, fragmentation, and
    degradation of forested habitat,” J.A. 248; and white nose
    syndrome, a lethal fungus, 
    id. at 249,
    641. Wind farms pose a
    potential threat to bats generally, either through collisions
    with the turbines or as a result of decompression sickness
    caused by pressure changes around rotating turbine blades.
    However, as of April 2013, only five known Indiana bat
    deaths have been associated with wind farms.
    C.
    Buckeye seeks to build and operate a commercial wind
    energy facility in Champaign County, Ohio. The proposed
    facility would include up to 100 wind turbines, each with a
    capacity of 1.6 to 2.5 Megawatts (“MW”), with a total
    3
    “Recovery Units are a tool developed to maintain the distribution
    of wide-ranging species that have multiple populations or varying
    ecological pressures in different paths of the range . . . . Recovery
    Units are geographically or otherwise identifiable . . . .” U.S. Fish
    and Wildlife Service, Indiana Bat (Myotis sodalis) Draft Recovery
    Plan: First Revision, at 116, April 2007 [hereinafter 2007 Recovery
    Plan],                          available                          at
    https://www.fws.gov/midwest/endangered/mammals/inba/pdf/inba_
    fnldrftrecpln_apr07.pdf. The Indiana Bat is grouped into four
    geographical Recovery Units: “Ozark-Central, Midwest,
    Appalachian Mountains, and Northeast.” 
    Id. at 8.
                                    8
    generating capacity of approximately 250 MW for the facility.
    Necessary construction and access infrastructure would be
    built as well. The site for the facility is a predominantly
    agricultural and rural area where Indiana bats maintain a
    presence during the summer maternity season and presumably
    traverse during spring and fall migrations to and from their
    hibernacula. 4
    In 2007, Buckeye began consulting with the Service and
    the Ohio Department of Natural Resources Division of
    Wildlife to determine the impact that its project would have
    on the local wildlife populations. After Buckeye consulted
    with the Service for several years and provided a number of
    pre-construction field studies, on January 29, 2010, the
    Service issued a notice of intent to initiate a scoping 5 period
    on the project and solicited public comments. Public scoping
    began on May 26, 2010, and the Service again solicited public
    comments regarding its intent to prepare a draft EIS and
    develop a Habitat Conservation Plan (“HCP” or
    “Conservation Plan”) addressing the impact of Buckeye’s
    proposed project. 75 Fed. Reg. 29575 (May 26, 2010); see
    also 40 C.F.R. § 1506.6(b) (requiring “public notice of
    NEPA-related hearings, public meetings, and the availability
    of environmental documents”). The Service worked with
    Buckeye to draft the HCP, and Buckeye submitted a
    completed application for its Incidental Take Permit (“ITP” or
    “Permit”) in February 2012.
    4
    The estimated number of Indiana bats traversing the area during
    summer ranged from 10.1 to 2,271.4, and the estimate during
    migration is approximately 5,800. J.A. 588.
    5
    Scoping is the “process for determining the scope of issues to be
    addressed and for identifying the significant issues related to a
    proposed action” to be addressed in an EIS. 40 C.F.R. § 1501.7.
    9
    On June 29, 2012, the Service issued a Draft EIS and
    Draft HCP for Buckeye’s proposal and solicited public
    comments. The Service issued a Final EIS and Final HCP on
    Friday, April 18, 2013, and solicited public comments before
    a final decision on the permit. In the Final EIS, the Service
    identified the issuance of the ITP as the proposed government
    action. The Service also explained that the five “purposes
    for” the ITP and Final EIS were to: (1) “[r]espond to Buckeye
    Wind’s application for an ITP for the . . . Indiana bat to
    related Project activities that have the potential to result in
    take . . .”; (2) “[p]rotect, conserve and enhance the Indiana bat
    and its habitat . . .”; (3) “[p]rovide a means and take steps to
    conserve the ecosystems depended on by the Indiana bat”;
    (4) “[e]nsure the long-term survival of the Indiana bat through
    protection and management of the species and its habitat”;
    and (5) “[e]nsure compliance with the ESA, NEPA, and other
    applicable Federal laws and regulations.” J.A. 175. Because
    of the potential for commercial wind facilities to take a high
    number of bats, the Service identified “a need to ensure that
    take of Indiana bats is avoided and minimized to the
    maximum extent practicable and to ensure that the impact of
    any remaining take is fully mitigated” and to “protect the
    habitat of Indiana bats.” J.A. 176. In furtherance of these
    objectives, the Service identified three options it could take
    under the ESA: 1) issue the ITP conditioned upon
    implementation of the HCP; 2) issue the ITP conditioned
    upon implementation of the HCP and other measures; or
    3) deny the application for the ITP. The Service proposed
    issuing the Permit subject to Buckeye’s Conservation Plan.
    Buckeye’s Conservation Plan proposes numerous steps to
    reduce impacts on the Indiana bat and its habitat, as well as
    impacts to other non-listed bats and birds. The HCP first
    attempts to minimize its impact on Indiana bats through the
    Action and Project Areas – those areas that could be affected
    10
    by the issuance of the Permit – and the locations of individual
    turbines. Specifically, the Conservation Plan moves the
    Action Area to a location 8 km (5 miles) away from a 2008
    discovery of Indiana bats. Additionally, turbines are sited in
    already-developed lands where turbines would pose a reduced
    risk to the bats, and no turbine is sited within 2.9 km of
    known maternity roost trees discovered in 2009. Finally, only
    10 of the 100 turbines are sited within habitat where the
    turbines would pose the greatest risk of impact to the Indiana
    bats.
    The Conservation Plan also includes operational
    restrictions. Buckeye commits to both “turbine feathering”
    and increased “cut-in speeds.” See J.A. 209-11, 757-60.
    Feathering is a “reduc[tion in] the blade angle to the wind to
    slow or stop the turbine from spinning[] until a designated
    cut-in speed is reached.” J.A. 209. Cut-in speeds “are the
    wind speed at which rotors begin rotating and producing
    power.” J.A. 209. The HCP varies the cut-in speeds up to
    6.0 m/s based on the location of the turbine, the season, and
    the time of day.
    The HCP estimated the impact on Indiana bat mortality
    using a collision model that accounted for, among other
    factors, population size, flight height, temperature, wind
    speed, and movement within the turbine array. Without
    implementing any of the operational restrictions, an estimated
    6.9 to 25.4 bats would be killed per year. Using the
    operational restrictions, an estimated 5.2 bats would be taken
    per year, with no more than 26 Indiana bats in a 5 year period.
    The Service considered whether the estimated take of 5.2 bats
    per year would have significant consequences for the Indiana
    bat and determined that it would impact neither the Midwest
    Recovery Unit nor a local unit of a single maternity colony.
    11
    Finally, the HCP outlined additional mitigation measures
    related to habitat preservation and conservation funding.
    Buckeye intends to acquire and protect 217 acres of suitable
    habitat, 6 and to “restor[e] and/or enhance[]” suboptimal
    habitat, J.A. 768. Buckeye has also committed $200,000 to
    funding research and conservation efforts.
    During scoping, the Service identified and considered six
    alternatives to Buckeye’s proposal, three of which were
    analyzed in depth. 7       The alternatives “were primarily
    designed to address the potential for take of Indiana bats” and
    focused on the dates, times, and speed of turbine operation.
    J.A. 200. In addition to Buckeye’s proposal, the Service
    analyzed in depth what it called 1) a maximally restricted
    operations alternative (the “Max Alternative”); 2) a minimally
    restricted operations alternative (the “Minimal Alternative”);
    and 3) a No Action Alternative. J.A. 219-22. The Service
    considered the three alternatives and Buckeye’s proposal to
    determine the impacts on the Indiana bats and the outcome of
    the project. Under the No Action Alternative, the Service
    would not issue the ITP, no bats would be taken, and Buckeye
    would not construct the project. J.A. 220-21.
    6
    The habitat is located within seven miles of a Priority 2
    hibernaculum.      The Indiana bat Recovery Plan categorizes
    hibernacula by priority numbers that reflect bat population and the
    significance of the habitat to Indiana bat recovery. See 2007
    Recovery 
    Plan, supra, at 20
    . Priority 2 hibernacula “[c]ontribute[]
    to the recovery and long-term conservation” of the Indiana bat and
    “have a current or observed historic population of 1,000 or greater
    but fewer than 10,000 and an appropriate microclimate.” 
    Id. 7 The
    three alternatives the Service did not analyze in depth were:
    1) an ITP of shorter duration; 2) a reduced number of turbines; and
    3) an alternate location in Ohio. J.A. 195-96.
    12
    Buckeye’s plan would take 5.2 Indiana bats per year.
    This take would not reduce the long-term viability of a local
    colony while also protecting 217 acres of suitable habitat.
    Buckeye’s plan would generate 635,823 Megawatt-hours per
    year (“MWh/year”) with zero emissions, offsetting 486,000
    tons of carbon dioxide. J.A. 385. Buckeye’s proposal would
    result in a 2.5% reduction in clean energy production,
    $980,000 in lost annual revenues, and $24.5 million in lost
    revenues over the ITP term from feathering. J.A. 808.
    The Max Alternative would eliminate the take of any bats
    but would require shutting down all turbines from sunset to
    sunrise when Indiana bats are active. J.A. 220. Because no
    bats would be taken, no permit would need to issue. J.A. 219.
    However, no additional habitat would be preserved. J.A. 331-
    32. Only 491,587 MWh/year would be generated, and 22%
    fewer emissions would be reduced. J.A. 386. The maximally
    restrictive operations alternative would also result in a 22.7%
    reduction in clean energy, $8.65 million in lost annual
    revenues, and $216.5 million in lost revenues over the ITP
    term. J.A. 808.
    The Minimal Alternative would have feathered all
    turbines to a cut-in speed of 5.0 meters per second (“m/s”)
    during the fall migration period during the hours when the
    bats were most active. J.A. 220. This plan would have
    resulted in a take of 12 Indiana bats per year and over 300
    bats over the life of the project, requiring Buckeye to
    purchase additional habitat for mitigation. J.A. 220. The
    Minimal Alternative would generate 647,726 MWh/year,
    offsetting more emissions. J.A. 386.
    In public comments on the Final EIS, Union Neighbors
    asked the Service to consider a cut-in speed of 6.5 m/s as
    another alternative to Buckeye’s proposed plan. J.A. 1053-
    13
    55, 1061-84. In response, the Service “d[id] not disagree that
    higher cut-in speeds may result in less bat mortality,” but
    because of the “infinite combinations of cut-in speeds higher
    than the proposed action, or even higher than 6.5 m/s that
    could be applied to reduce bat mortality more,” it concluded
    the Max Alternative was “a reasonable alternative to consider
    in lieu of” Union Neighbors’ proposed speed. J.A. 1055. The
    Service reasoned that the difference between Buckeye’s
    proposal and the Max Alternative was “not significant,”
    making analysis of other variations with higher cut-in speeds
    “not necessary.” J.A. 1054.
    On July 18, 2013, the Service issued the ITP to Buckeye
    as well as its Record of Decision and Statement of Findings.
    J.A. 1033. The Service found that Buckeye’s HCP “meets the
    statutory criteria for issuance of a . . . Permit, meets
    [Buckeye’s] needs, and the []HCP provides an extensive set
    of conservation measures that minimizes and mitigates for the
    incidental take of the Indiana bat to the maximum extent
    practicable.” J.A. 1043. The Service also issued a Biological
    Opinion concluding that Buckeye’s proposal “is not likely to
    jeopardize the continued existence of the Indiana bat, and is
    not likely to destroy or adversely modify designated critical
    habitat.” J.A. 1001.
    The Service also issued a Statement of Findings under
    Section 10(a)(1)(B) of the Endangered Species Act, 16 U.S.C.
    § 1539(a)(1)(B). Specifically, the Service found that the
    taking was “incidental to and not the purpose” of Buckeye’s
    project, J.A. 1023; that Buckeye had sufficient funding for
    mitigation, J.A. 1026; and that the taking was “not likely to
    appreciably reduce the likelihood of survival and recovery” of
    the Indiana bat, J.A. 1027. The Service also found that the
    HCP
    14
    minimizes and mitigates the impacts of take of
    the [Indiana bat] to the maximum extent
    practicable . . . because: (1) the HCP’s
    minimization and mitigation measures
    effectively compensate for the impacts of take
    under the plan; [and] (2) the plan provides for
    adaptive management to adjust to changing
    conditions and adjusts mitigation costs over the
    life of the plan to fully fund its
    implementation.
    J.A. 1025.
    On September 20, 2013, Union Neighbors filed a
    complaint seeking declaratory and injunctive relief against the
    Secretary of the Department of the Interior, the Director of the
    Service, and the Regional Director for the Midwest region of
    the Service (collectively the “Federal Appellees”), alleging
    that the issuance of the ITP was arbitrary, capricious, an abuse
    of discretion, and otherwise not in accordance with law under
    NEPA and the ESA. Buckeye intervened. The parties cross-
    moved for summary judgment, and on March 18, 2015, the
    District Court denied Union Neighbors’ motion and granted
    the Federal Appellees’ and Buckeye’s motions. Union
    Neighbors United, Inc. v. Jewell, 
    83 F. Supp. 3d 280
    , 283
    (D.D.C. 2015). The District Court concluded that the Service
    satisfied the ESA’s permit issuance criteria and that the
    Service’s consideration of alternatives under NEPA was
    reasonable. 8 
    Id. at 286-89.
    Union Neighbors appeals.
    8
    The District Court also addressed whether Union Neighbors had
    standing. Although not raised by the parties, we conclude Union
    Neighbors has standing for the reasons stated by the District Court
    in its opinion. Union Neighbors 
    United, 83 F. Supp. 3d at 285-86
    .
    15
    II.
    We review the District Court’s grant of summary
    judgment de novo, “as if the agency’s decision ‘had been
    appealed to this court directly.’” 
    Gerber, 294 F.3d at 178
    (quoting Dr. Pepper/Seven-Up Cos. v. FTC, 
    991 F.2d 859
    ,
    862 (D.C. Cir. 1993)). Because NEPA does not provide a
    private right of action, we review the Service’s decision under
    the Administrative Procedure Act (“APA”), 5 U.S.C. § 501 et
    seq. Theodore Roosevelt Conservation P’ship v. Salazar, 
    661 F.3d 66
    , 72 (D.C. Cir. 2011). Likewise, we review the
    Service’s ESA findings under the APA. 
    Gerber, 294 F.3d at 178
    & n.4. Under the APA, “our task is to determine whether
    the agency’s decision was made ‘without observance of
    procedure required by law,’ 5 U.S.C. § 706(2)(D), or whether
    it was ‘arbitrary, capricious, an abuse of discretion, or
    otherwise not in accordance with law,’ 
    id. § 706(2)(A).”
    Id.
    “[A]n agency 
    acts arbitrarily or capriciously if it ‘has relied
    on factors which Congress has not intended it to consider,
    entirely failed to consider an important aspect of the problem,
    offered an explanation for its decision that runs counter to the
    evidence before the agency, or is so implausible that it could
    not be ascribed to a difference in view or the product of
    agency expertise.’” Am. Wildlands v. Kempthorne, 
    530 F.3d 991
    , 997-98 (D.C. Cir. 2008) (quoting Motor Vehicle Mfrs.
    Ass’n v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43
    (1983)).
    A.
    Union Neighbors argues that the Service did not satisfy
    NEPA’s requirement that it consider a reasonable range of
    alternatives because it failed to include among the alternatives
    an economically viable plan that would have taken fewer
    Indiana bats than Buckeye’s compliance with the HCP. The
    16
    Federal Appellees and Buckeye contend that the Service
    considered a reasonable range of alternatives.
    “Judicial review of agency actions under NEPA is
    available ‘to ensure that the agency has adequately considered
    and disclosed the environmental impact of its actions and that
    its decision is not arbitrary or capricious.’” Del. Riverkeeper
    Network v. FERC, 
    753 F.3d 1304
    , 1312-13 (D.C. Cir. 2014)
    (quoting Baltimore 
    Gas, 462 U.S. at 97-98
    ). “Where an issue
    ‘requires a high level of technical expertise,’ we ‘defer to the
    informed discretion of the [agency].’” 
    Id. at 1313
    (quoting
    Marsh v. Or. Nat. Res. Council, 
    490 U.S. 360
    , 377 (1989)).
    “Although the standard of review is deferential, we have
    made it clear that ‘[s]imple, conclusory statements of “no
    impact” are not enough to fulfill an agency’s duty under
    NEPA.’” 
    Id. (quoting Found.
    on Econ. Trends v. Heckler,
    
    756 F.2d 143
    , 154 (D.C. Cir. 1985)).
    The alternatives to the proposed action are “the heart of
    the [EIS].” 40 C.F.R. § 1502.14. “Reasonable alternatives
    . . . . include[] alternatives that are technically and
    economically practical or feasible and meet the purpose and
    need of the proposed action.” 43 C.F.R. § 46.420(b). We
    review the Service’s selection of alternatives under the “rule
    of reason.” Theodore Roosevelt Conservation 
    P’ship, 661 F.3d at 72
    . “[A]n agency need follow only a ‘rule of reason’
    in preparing an EIS, and . . . this rule of reason governs ‘both
    which alternatives the agency must discuss, and the extent to
    which it must discuss them.’” Citizens Against Burlington,
    Inc. v. Busey, 
    938 F.2d 190
    , 195 (D.C. Cir. 1991) (quoting
    Alaska v. Andrus, 
    580 F.2d 465
    , 475 (D.C. Cir. 1978))
    (citation omitted). Under the rule of reason, “as long as the
    agency ‘look[s] hard at the factors relevant to the definition of
    purpose,’ we generally defer to the agency’s reasonable
    definition of objectives.” Theodore Roosevelt Conservation
    17
    
    P’ship, 661 F.3d at 72
    (quoting Citizens Against 
    Burlington, 938 F.2d at 196
    ) (alteration in original). This is a deferential
    standard.     WildEarth 
    Guardians, 738 F.3d at 310
    .
    Furthermore, “where a federal agency is not the sponsor of a
    project, ‘the Federal government’s consideration of
    alternatives may accord substantial weight to the preferences
    of the applicant and/or sponsor in the siting and design of the
    project.’” City of Grapevine v. Dep’t of Transp., 
    17 F.3d 1502
    , 1506 (D.C. Cir. 1994) (quoting Citizens Against
    
    Burlington, 938 F.2d at 197
    )).
    Because “[t]he goals of an action delimit the universe of
    the action’s reasonable alternatives,” Citizens Against
    
    Burlington, 938 F.2d at 195
    , we evaluate the Service’s
    alternatives with its stated goals in mind. The Service
    explained that the five purposes of its action were:
    (1) responding to Buckeye’s application for an incidental take
    permit for the Indiana bat; (2) “[p]rotect[ing], conserv[ing]
    and enhanc[ing] the Indiana bat and its habitat”;
    (3) “[p]rovid[ing] a means and tak[ing] steps to conserve the
    ecosystems” upon which the Indiana bat depends;
    (4) “[e]nsur[ing] the long-term survival of the Indiana bat”;
    and (5) complying with all federal laws and regulations. J.A.
    175. At their core, these five purposes reflect “a need to
    ensure that take of Indiana bats is avoided and minimized to
    the maximum extent practicable and to ensure that the impact
    of any remaining take is fully mitigated” and “to protect the
    habitat of Indiana bats.” J.A. 176.
    The Federal Appellees recognize that the range of
    reasonable alternatives was designed to ensure preservation of
    the Indiana bat. Throughout their brief, the Federal Appellees
    reiterate the importance of an alternative that would reduce
    the take of bats while allowing the project to go forward. See
    Fed. Appellees Br. at 33 (“The [Max Alternative] reflects the
    18
    extent of operational restrictions necessary to ensure that the
    Project could still be built and operated, but without causing
    take.”); 
    id. at 33-34
    (explaining how the Max Alternative
    provided a “valuable point of comparison . . . to compare the
    proposed Project to an alternative which reduced likely
    impacts to the Indiana bat to zero but still built the project”
    (emphasis omitted)).
    The Service considered the following alternatives:
    Buckeye’s plan incorporating variable cut-in speeds of up to
    6.0 m/s at night from April to October; the No Action
    Alternative; the Minimal Alternative with a cut-in speed of
    5.0 m/s for the first six hours after sunset from August to
    October; and the Max Alternative, which would have turned
    off the turbines at night from April to October. Viewing the
    range of alternatives through the lens of its stated goals, the
    Service failed to consider a reasonable range of alternatives
    because it did not consider any reasonable alternative that
    would be economically feasible while taking fewer bats than
    Buckeye’s proposal. Buckeye’s proposal would take 5.2 bats
    per year. The only alternative the Service considered that
    would take fewer bats was the Max Alternative. According to
    the Federal Appellees, the value of the Max Alternative was
    in the fact that it “eliminat[ed] Indiana bat mortality.” Fed.
    Appellees Br. at 30. But the Federal Appellees concede that
    the Max Alternative is not an economically feasible
    alternative. See 
    id. at 33
    (noting higher costs and lower
    energy production with the Max Alternative). The Service
    knew, at a minimum, that Buckeye claimed a full nighttime
    option was not economically viable, and it was aware of
    other, more viable measures that would still take fewer bats
    than Buckeye’s proposal—Union Neighbors repeatedly
    suggested using a cut-in speed higher than 6.0 m/s. Yet the
    Service failed to consider any higher cut-in speed in either the
    Draft or Final EIS. Because the Service in that context failed
    19
    to consider any economically feasible alternative that would
    take fewer Indiana bats than Buckeye’s proposal, it failed to
    consider a reasonable range of alternatives.
    The unreasonableness of the Service’s failure to consider
    an economically viable alternative that would have taken
    fewer bats is evident after comparing the Draft EIS and Draft
    HCP with the Final EIS and the Final HCP. Attached to the
    Draft EIS was Buckeye’s Draft HCP. In its Draft HCP,
    Buckeye outlined the additional costs that the Max
    Alternative would impose. Proposed Habitat Conservation
    Plan & Incidental Take Permit for the Indiana Bat (Myotis
    sodalis) for the Buckeye Wind Power Project Champaign
    County, Ohio, Vol. 2, Appx. B, at 219 (June 2012),
    http://regulations.gov (search for “FWS-R3-ES-2012-0036-
    0005”). This analysis is identical to the financial analysis
    included in the Final HCP. See J.A. 808. The Federal
    Appellees describe this analysis as “explaining why the [Max
    Alternative] was not economically viable.” Fed. Appellees
    Br. at 33. Yet despite possessing this analysis at both the
    Draft and Final EIS stages, the Service considered only the
    same four alternatives in both the Draft EIS and Final EIS.
    Furthermore, the Service’s own responses to Union
    Neighbors’ comments reflect the potential for a higher cut-in
    speed to more effectively align with its stated goals.
    Following notice of the final EIS, Union Neighbors submitted
    a comment asking the Service to consider the impact of a cut-
    in speed of 6.5 m/s. Although the Service recognized that
    “higher cut-in speeds may result in less bat mortality,” it
    rejected analyzing a cut-in speed of 6.5 m/s because the
    difference between Buckeye’s proposal and the Max
    Alternative was “not significant,” making analysis of other
    variations with higher cut-in speeds “not necessary.” J.A.
    1054. Considering that one of the purposes behind the
    20
    issuance of the ITP was to “[p]rotect, conserve and enhance
    the Indiana bat and its habitat,” J.A. 175, an analysis of
    whether an increased cut-in speed would still allow the
    project to go forward while protecting more Indiana bats
    would be consistent with this purpose.
    The Federal Appellees argue that the Service did not need
    to consider another alternative because there “exists an
    infinite array of potential protective measures that could be
    varied depending on habitat, feathering, cut-in speed, and
    season, among many other factors.” Fed. Appellees Br. at 31.
    But the Service would not need to examine an “infinite
    array,” nor even examine Union Neighbors’ proposed 6.5 m/s
    speed. An analysis of a realistic mid-range alternative with a
    cut-in speed that would take materially fewer bats than
    Buckeye’s proposal while allowing the project to go forward
    would suffice. Although an agency “need not examine an
    infinite number of alternatives in infinite detail,” Allison v.
    Dep’t of Transp., 
    908 F.2d 1024
    , 1031 (D.C. Cir. 1990),
    examining a reasonable alternative that could potentially take
    fewer bats than Buckeye’s plan would “inform both the public
    and the decisionmaker,” Citizens Against 
    Burlington, 938 F.2d at 195
    , by “sharply defining the issues and providing a
    clear basis for choice among options,” 40 C.F.R. § 1502.14.
    Alternatively, the Federal Appellees argue that the
    Service already considered higher cut-in speeds separately by
    including the higher speeds in the literature supporting its
    analysis of the various alternatives. This argument would be
    compelling if only it were true. The Service’s response to
    Union Neighbors’ comment belies the Federal Appellees’
    argument here. When the Service rejected Union Neighbors’
    comment, it did not say that higher cut-in speeds were
    “effectively incorporated” or had been “previously
    considered” in its analysis. The Service stated simply that
    21
    considering a 6.5 m/s cut-in speed was “not necessary.” J.A.
    1054. Furthermore, although the adaptive management plan
    incorporates a speed of 6.5 m/s in certain scenarios, the
    Service’s analysis does not suggest that the impacts would be
    identical to a consistent permanent cut-in speed. If cut-in
    speeds could potentially reduce additional impacts on bats,
    see J.A. 1054, and the adaptive plan operates under 6.5 m/s
    under certain scenarios, see J.A. 209-11, certainly the impacts
    would be different with constant cut-in speeds. The Service’s
    failure to analyze a higher cut-in speed prevents us from
    accepting its conclusion.
    Accordingly, because the Service in these circumstances
    did not consider any other reasonable alternative that would
    have taken fewer Indiana bats than Buckeye’s plan, it failed to
    consider a reasonable range of alternatives and violated its
    obligations under NEPA. As a result, the Service’s issuance
    of the ITP was arbitrary and capricious, and we reverse the
    District Court on Union Neighbors’ NEPA claims.
    B.
    Union Neighbors also argues that the Service failed to
    comply with Section 10(a)(2)(B) of the ESA, 16 U.S.C.
    § 1539(a)(2)(B)(ii), which requires a finding that the applicant
    for an ITP “will, to the maximum extent practicable,
    minimize and mitigate the impacts of such taking.”
    Specifically, Union Neighbors argues that the Service failed
    to fulfill this requirement in three ways: 1) failing to ensure
    that Buckeye would, to the maximum extent practicable,
    minimize the number of individual Indiana bats that would be
    taken; 2) applying an inappropriate standard to determine
    what constitutes the “maximum extent practicable”; and
    3) failing to find that a reduced-impact alternative was
    22
    impracticable in contravention of Gerber v. Norton, 
    294 F.3d 173
    (D.C. Cir. 2002).
    1.
    The Service made an official finding that Buckeye
    minimized and mitigated the impact on the Indiana bat to the
    maximum extent practicable. The Service noted that the ESA
    required it “to examine and predict the efficacy of
    [Buckeye’s] proposed minimization and mitigation
    measures.” J.A. 1023. It explained the criterion as follows:
    “Impacts to the species . . . of the proposed taking that are not
    avoided or eliminated as a result of project and HCP planning
    must be minimized to the maximum extent practicable. Any
    remaining impacts must then be mitigated (e.g., ‘offset’ or
    ‘rectified’) to the maximum extent practicable.” 
    Id. The Service
    found “that Buckeye Wind will minimize
    and mitigate the impacts of take on the Indiana bat to the
    maximum extent practicable.” J.A. 1024. First, the Service
    reasoned that Buckeye’s approach “applies a biologically-
    based approach to minimizing take using avoidance
    measures” including “the use of feathering and cut-in speeds.”
    
    Id. Additionally, Buckeye
    minimized take through its siting
    strategies and its application of “the strictest operational
    protocols (cut-in speeds) to turbines in the highest quality
    habitat areas and during the seasonal periods of highest risk.”
    
    Id. Buckeye’s use
    of cut-in speeds based on habitat quality
    rather than population also ensured minimization over the 30-
    year life of the permit. See 
    id. Because “[t]he
    primary form
    of take of Indiana bats” was expected to be “mortality
    resulting from operation of the wind turbines,” Buckeye’s use
    of feathering and cut-in speeds would reduce the take by
    68.3%, with additional reductions possible. 
    Id. 23 The
    Service also considered Buckeye’s proposed
    mitigation measures. Buckeye’s “permanent protection of
    swarming habitat” would have two key effects: “enhanc[ing]
    reproductive success and increas[ing] the survival probability
    of Indiana bats that . . . overwintered in the hibernaculum.”
    J.A. 1025.       Moreover, because the “[t]he land will be
    protected in perpetuity,” the benefits to the Indiana bat would
    outlast the ITP’s duration. 
    Id. Considering both
    the
    minimization and mitigation measures, the Service concluded
    that Buckeye’s plan not only “fully compensates for impacts
    of the take to the” Indiana bat, but also “will assist in recovery
    of the species.” 
    Id. As a
    result, the Service found that
    Buckeye’s “HCP minimizes and mitigates the impact of take
    of the [Indiana bat] to the maximum extent practicable.” 
    Id. Furthermore, in
    response to substantive comments to the
    Final EIS, 9 the Service noted that its “analyses indicate that
    incidental take of individual bats associated with operation of
    the project is likely to have insignificant impacts on the
    subpopulations to which the taken individuals belong” and
    that Buckeye “has minimized the impact of the taking to the
    maximum extent practicable—to the extent that the impacts
    are insignificant.” J.A. 1052. The official statement of
    findings also describes how “none of the Expected Take or
    Worst-case Take scenarios resulted in appreciable reductions
    relative to the Baseline scenario in any of the metrics” and
    “appreciable reductions in the fitness of the local maternity
    colonies, migratory maternity colonies, and winter
    populations to which the taken individuals belong are
    unlikely.” J.A. 1021.
    9
    The Service’s official statement of findings also incorporated by
    reference its responses to comments on the Final EIS. See J.A.
    1022.
    24
    Finally, in response to comments on the Draft EIS, to the
    extent that Buckeye was required to show that the
    Conservation Plan represented “the extent practicable” to
    which it could take action, the Service considered Buckeye to
    have shown that the Conservation Plan was all that could be
    “reasonably required” because the “maximum extent
    practical” threshold is not “economic infeasibility.” J.A. 567-
    68. The Service explained that “the maximum extent
    practicable” standard “entails an analysis of the impact of the
    proposed taking on the species, as well as an analysis of how
    the mitigation proposal will offset those impacts.” J.A. 568.
    As a result, “[i]f the mitigation fully offsets the impact of the
    taking, the Applicant has met the ‘maximum extent
    practicable’ standard.” 
    Id. 2. Union
    Neighbors argues that the Service’s findings fail to
    comply with the statutory requirements under the ESA.
    Union Neighbors’ arguments – first, about what “impacts”
    must be minimized and mitigated, and, second, about the
    meaning of “the maximum extent practicable” – are questions
    of statutory interpretation. As a result, the Federal Appellees
    and Buckeye urge us to review the Service’s interpretation
    under the two-step standard articulated in Chevron U.S.A.,
    Inc. v. NRDC, 
    467 U.S. 837
    (1984).
    “When it enacted the ESA, Congress delegated broad
    administrative and interpretive power to the Secretary.”
    Babbitt v. Sweet Home Chapter of Cmtys. for a Great Or.,
    
    515 U.S. 687
    , 708 (1995). Accordingly, “[f]ashioning
    appropriate standards for issuing permits under § 10 for
    takings that would otherwise violate § 9 necessarily requires
    the exercise of broad discretion. . . . When Congress has
    entrusted the Secretary with broad discretion, we are
    25
    especially reluctant to substitute our views of wise policy for
    [the Secretary’s].”      
    Id. Generally, “[w]e
    review [the
    Service’s] interpretation of the statute under the familiar two-
    step framework from [Chevron].” Friends of Blackwater v.
    Salazar, 
    691 F.3d 428
    , 432 (D.C. Cir. 2012). Under that
    standard, “[a]t Step One, the court asks ‘if the statute
    unambiguously forecloses the agency’s interpretation,’” 
    id. (quoting Nat’l
    Cable & Telecomms. Ass’n v. FCC, 
    567 F.3d 659
    , 663 (D.C. Cir. 2009)), and “if it does not, then at Step
    Two ‘we defer to the administering agency’s interpretation as
    long as it reflects “a permissible construction of the statute,”’”
    
    id. (quoting Sherey
    v. Sebelius, 
    644 F.3d 388
    , 393 (D.C. Cir.
    2011)).
    The Service urges us to apply Chevron deference to
    interpretations outlined in the 1996 Habitat Conservation
    Planning and Incidental Take Permit Processing Handbook
    (the “Handbook”). See J.A. 1291. However, “not all
    statutory interpretations by agencies qualify for the level of
    deference afforded by that step.” Public Citizen, Inc. v. U.S.
    Dep’t of Health & Human Servs., 
    332 F.3d 654
    , 659 (D.C.
    Cir. 2003). “Chevron deference [is] appropriate only where
    Congress has ‘delegated authority to the agency generally to
    make rules carrying the force of law, and . . . the agency
    interpretation claiming deference was promulgated in the
    exercise of that authority.’” 
    Id. (quoting United
    States v.
    Mead Corp., 
    533 U.S. 218
    , 226-27 (2001)). The Handbook
    itself makes clear that it is only a guide, stating that it
    establishes “detailed but flexible guidelines” that are not
    “intended to supersede or alter any aspect of Federal law or
    regulations pertaining to the conservation of endangered
    species.” J.A. 1293. As a result, it is akin to “interpretations
    contained in policy statements, agency manuals, and
    enforcement guidelines, all of which lack the force of law
    [and] do not warrant Chevron-style deference.” Christensen
    26
    v. Harris Cnty., 
    529 U.S. 576
    , 587 (2000). However, where
    the deference we should accord an agency interpretation is
    unclear, “we need not reach the question of Chevron
    deference” if the Service’s interpretation “satisfies the
    requirements for Skidmore deference.” Brown v. United
    States, 
    327 F.3d 1198
    , 1205 (D.C. Cir. 2003) (citing Skidmore
    v. Swift & Co., 
    323 U.S. 134
    , 139 (1944)).
    “Under Skidmore, the court grants an agency’s
    interpretation only as much deference as its persuasiveness
    warrants.” 
    Id. Such interpretations
    reflect “a body of
    experience and informed judgment to which courts and
    litigants may properly resort for guidance.” 
    Skidmore, 323 U.S. at 140
    .        We accord deference to the agency’s
    interpretation in light of “the thoroughness evident in its
    consideration, the validity of its reasoning, its consistency
    with earlier and later pronouncements, and all those factors
    which give it power to persuade, if lacking power to control.”
    
    Id. After considering
    the text, legislative history, and prior
    interpretations of the ESA, we find the Service’s
    interpretations of the statute persuasive under Skidmore.
    a.
    Where Union Neighbors and the Service first disagree is
    whether the “impacts” that must be “minimized” refer to the
    discrete number of Indiana bats taken or to effects on the
    population and subpopulations of Indiana bats as a whole.
    Union Neighbors submits that the language of the statute, as
    well as its legislative history, supports interpreting the ESA to
    require that the Service find that Buckeye minimized and
    mitigated the impact on individual Indiana bats, not their
    population or subpopulations as a whole.
    27
    Union Neighbors first argues that the Service has
    accepted its definition of impacts, or alternatively, that certain
    Service emails show that it incorrectly applied a jeopardy
    standard in evaluating impacts. The “jeopardy” standard
    governs actions by federal agencies, which are required to
    show that their activities are “not likely to jeopardize the
    continued existence of any endangered species.” 16 U.S.C.
    § 1536(a)(2). We can easily dispose of these arguments.
    Accepting that an individual bat death may be an impact does
    not mean that individual bat deaths are the sole impacts of
    such taking. Regarding the Service’s emails, even assuming
    that the emails reflect an official statement, the jeopardy
    interpretation was not offered in the Service’s findings and
    does not render those findings arbitrary or capricious. See
    Nat’l Ass’n of Home Builders v. Defs. of Wildlife, 
    551 U.S. 644
    , 658-59 (2007).
    Turning to the statute itself, although its language is
    unclear, it suggests that “impacts” refers to more than the
    discrete number of individual members of a listed species. As
    Union Neighbors concedes, the statute does not define what
    “the impacts of such taking” are.             See 16 U.S.C.
    § 1539(a)(2)(B)(ii); 
    id. § 1532.
    However, the natural reading
    of “the impacts of such taking” is that “impacts” and “taking”
    are distinct concepts where the impact is the consequence of
    the take. Under Union Neighbors’ reading, if the “take” is the
    death of 5 Indiana bats, the impacts of that take would be the
    death of 5 Indiana bats. Such a reading would render the
    word “impacts” superfluous. The more natural reading is that
    “impacts” refers to the effect of the taking on the species as a
    whole, which necessarily includes populations and
    subpopulations. See 16 U.S.C. § 1539(a)(2)(B)(iv) (requiring
    the Secretary to find that “the taking will not appreciably
    reduce the likelihood of the survival and recovery of the
    species in the wild”).
    28
    In an effort to make its preferred interpretation of
    “impacts” clear, Union Neighbors argues that the use of
    “impact” in ESA Section 7, 16 U.S.C. § 1536(b)(4), should
    inform the interpretation of Section 10 here. In Section 7, the
    ESA provides that the Secretary, after consultation for a
    Biological Opinion, should provide a written statement that
    “specifies the impact of such incidental taking on the species”
    and “specifies those reasonable and prudent measures that the
    Secretary considers necessary or appropriate to minimize such
    impact.” 16 U.S.C. § 1536(b)(4)(C)(i)-(ii). Turning to
    Section 7’s legislative history, Union Neighbors cites the
    1982 House report that “Section 7(b)(4) requires the Secretary
    to specify the impact o[f] such incidental taking on the
    species. The committee does not intend that the Secretary
    will, in every instance, interpret the word ‘impact’ to be a
    precise number. Where possible, the impact should be
    specified in terms of a numerical limitation on the . . .
    permittee . . . .” H.R. Rep. No. 97-567, at 27 (1982), as
    reprinted in 1982 U.S.C.C.A.N. 2807, 2827.
    To the extent that this legislative history is probative, it is
    inconclusive. After all, not “every instance” of impact is “a
    precise number.” 
    Id. The House
    report even later notes that
    federal action need not be suspended in the event “the
    specified impact on the species is exceeded . . . unless it was
    clear that the impact of the additional taking would cause an
    irreversible and adverse impact on the species.” 
    Id. Clearly, impact
    includes the effects of the taking on the species
    population, not just individual members of the species.
    Furthermore, another House report explains that the Section
    10 permitting provisions were designed with the “San Bruno
    Mountain Plan” in mind. See H.R. Rep. No. 97-835, at 31-32
    (1982) (Conf. Rep.), as reprinted in 1982 U.S.C.C.A.N. 2860,
    2872-73. Nowhere in the description of this plan does it
    mention minimizing the individual takings of two species of
    29
    endangered butterflies; rather, it notes that the plan “preserves
    sufficient habitat to allow for enhancement of the survival of
    the species.” 
    Id. at 32,
    as reprinted in 1982 U.S.C.C.A.N.
    2873 (emphasis added).
    Here, the Service submits that its interpretation in the
    Handbook is entitled to deference. Pursuant to the Handbook,
    the Service will find that an applicant will, to the maximum
    extent practicable, minimize and mitigate the impacts of such
    taking following consideration of two factors: “adequacy of
    the minimization and mitigation program, and whether it is
    the maximum that can be practically implemented by the
    applicant.” J.A. 1298. Additionally, “[t]o the extent
    maximum [sic] that the minimization and mitigation program
    can be demonstrated to provide substantial benefits to the
    species, less emphasis can be placed on the second factor.”
    
    Id. Presumably, the
    Service asks us to read the Handbook’s
    language describing whether the minimization and mitigation
    programs “provide substantial benefits to the species” as
    reflecting that it has interpreted “impacts” to refer to
    populations and subpopulations rather than individual bats.
    Although that interpretation may be less than clear, it is
    consistent with the interpretation offered in the Service’s
    responses to comments on the Final EIS that distinguish
    between individual bats and species-level impacts. The
    Service explained that “[t]he determination of whether or not
    a project has minimized the impacts of the taking to the
    maximum extent practicable is a biological standard that
    considers how the species is impacted by the taking and
    mitigation, and not just the quantity of take.” J.A. 1050
    (emphases added). The Service further noted that “[t]he
    impact of the taking . . . is dictated by the quantity of take and
    how it is distributed over time and population segments[,] . . .
    30
    how the populations to which the taken individuals belong
    respond to the loss of individuals, and how each
    subpopulation contributes to the population as a whole.” J.A.
    1050-51. In far more certain terms than it described in the
    Handbook, the Service stated: “the ‘impact of the taking’ is
    different than the quantity of taken individuals.” J.A. 1051.
    Considering the text of the statute, its legislative history,
    and the Service’s interpretation of the statue, we are
    persuaded that the term “impacts” refers to the populations or
    subpopulations of the species as a whole, rather than the
    discrete number of individual members of the species.
    Accordingly, we defer to the Service’s interpretation of the
    ESA under Skidmore, and its findings were not arbitrary or
    capricious.
    b.
    Union Neighbors’ second statutory argument concerns
    the interplay between the phrases “to the maximum extent
    practicable” and “minimize and mitigate such impacts.”
    According to Union Neighbors, the “maximum extent
    practicable” requirement operates independently on
    “minimize” and “mitigate.” Union Neighbors contends that
    to comply with the ESA, the Service must first find that the
    number of individual Indiana bats taken was minimized to the
    maximum extent practicable. Because “practicable” means
    “reasonably capable of being accomplished,” BLACK’S LAW
    DICTIONARY (10th ed. 2014), if Buckeye could further
    minimize the number of Indiana bats taken, it must. Only
    then could the Service determine whether Buckeye had
    mitigated that taking to the maximum extent practicable.
    Under Union Neighbors’ reading, this would make the
    Service’s finding, which accounted for minimization and
    31
    mitigation together before finding that such measures were to
    the “maximum extent practicable,” a violation of the statute.
    Union Neighbors’ reading of the statute is plausible, but
    the Service’s interpretation that the phrase “minimize and
    mitigate” creates a single duty is more persuasive and
    consistent with the statutory text. Specifically, the statute
    provides that the Secretary must find that “the applicant will,
    to the maximum extent practicable, minimize and mitigate the
    impacts of such taking.” 16 U.S.C. 1539(a)(2)(B)(ii). First,
    the statute uses the conjunctive “and” between “minimize”
    and “mitigate,” rather than “then,” suggesting that the terms
    should be read together, not as a sequence.            Further
    demonstrating that “minimize and mitigate” should be treated
    together is their shared object, “the impacts of such taking.”
    Additionally, the structure of the statute, which enumerates
    independent findings the Secretary must make, supports this
    reading. Minimize and mitigate are part of a single finding
    the Secretary must make. See 16 U.S.C. § 1539(a)(2)(B). If
    they had to be made independently, the duties could have
    been imposed as independent findings the Secretary would
    have to make. If the Secretary finds that the applicant can
    “minimize and mitigate the impacts,” the Secretary will have
    complied with its statutory duty. See Nat’l Wildlife Fed’n. v.
    Norton, 
    306 F. Supp. 2d 920
    , 927-28 (E.D. Cal. 2004)
    (discussing the relationship between minimize and mitigate).
    Accordingly, the text of the ESA supports reading “minimize
    and mitigate” jointly, and determining whether it has been
    done “to the maximum extent practicable.”
    Indeed, the Service’s prior interpretations of the statute
    are largely consistent with this interpretation. The Service
    points us to the Handbook, which, as discussed above, treats
    the ESA finding as a “consideration of two factors: adequacy
    of the minimization and mitigation program, and whether it is
    32
    the maximum that can be practically implemented by the
    applicant.” J.A. 1298. The Handbook also provides that “[t]o
    the extent maximum [sic] that the minimization and
    mitigation program can be demonstrated to provide
    substantial benefits to the species, less emphasis can be placed
    on the second factor.” 
    Id. According to
    the Service, this
    language demonstrates that it has interpreted the ESA to
    consider minimization and mitigation together, rather than
    sequentially.
    Union Neighbors argues that the Service has not been
    consistent in its interpretation of the statute. For example, in
    its October 2011 revision to its Indiana Bat Section 7 and
    Section 10 Guidance for Wind Energy Projects, the Service
    described “[w]hat . . . ‘minimize and mitigate to the
    maximum extent practicable’ mean[s].”                J.A. 1303.
    Specifically, the Service stated:
    We interpret this section to mean that the
    impacts of the proposed project, including the
    HCP, which were not eliminated through
    informal negotiation must be minimized to the
    maximum extent practicable and those
    remaining impacts that cannot be further
    minimized must be mitigated to the maximum
    extent practicable.
    
    Id. This passage
    suggests that minimization and mitigation
    must be done independently to the maximum extent
    practicable. Yet the Guidance later treats minimization and
    mitigation as a single factor: “If applicants provide
    biologically based minimization measures and mitigation
    measures that are fully commensurate with the level of
    impacts, they have minimized and mitigated to the maximum
    extent practicable.” 
    Id. This one
    instance of ambiguity is
    33
    not enough to deprive the Service’s interpretation of its
    persuasive power.
    Finally, the Service’s responses to comments provide the
    clearest picture about how the Service interprets the ESA’s
    requirement that it find minimization and mitigation to the
    maximum extent practicable. The Service described its
    findings, noting that the cut-in speeds and feathering led the
    Service to determine that Buckeye “has minimized the
    quantity of take.” J.A. 1051. Because the quantity of take
    would have “insignificant impacts on the subpopulations to
    which the taken individuals belong[ed],” the Service found
    that Buckeye “minimized the impact of the taking to the
    maximum extent practicable.” J.A. 1052. Furthermore,
    Buckeye’s mitigation measures would “contribute toward
    recovery of the species,” meaning Buckeye “mitigated the
    impact of the taking to the maximum extent practicable.” 
    Id. After quoting
    the Handbook, the Service explained that “an
    assessment of economic feasibility can be considered in part
    of the assessment of the ‘maximum that can be practically
    implemented by the Applicant,’ particularly if the mitigation
    does not fully offset the impact of the taking.” J.A. 1053. In
    this instance, “because the minimization and mitigation fully
    offset the impact of the taking,” the Service found “it [was]
    not necessary to determine if the plan [was] the ‘maximum
    that can be practically implemented by’” Buckeye. 
    Id. In other
    words, if combined minimization and mitigation fully
    offset the take, it does not matter whether Buckeye could do
    more; Buckeye has already satisfied what is required under
    the ESA. Accordingly, the Service’s ESA findings were not
    arbitrary or capricious.
    34
    3.
    Union Neighbors’ final salvo against the Service is
    Gerber v. Norton, 
    294 F.3d 173
    (D.C. Cir. 2002). Union
    Neighbors contends that Gerber requires the Service to make
    an independent finding that no reduced impact alternative is
    practicable in order to find that Buckeye minimized and
    mitigated to the maximum extent practicable. Assuming
    without deciding that Gerber imposes such a requirement, the
    Service made the necessary finding that no identified reduced
    impact alternative was practicable.
    In Gerber, we reviewed the issuance of a permit
    authorizing a taking of the endangered Delmarva fox 
    squirrel. 294 F.3d at 175
    . The Defenders of Wildlife challenged the
    issuance of the permit as a violation of Section 10 of the ESA
    because the Service failed to find independently that “no
    practical alternative” to the proposed development plan
    “would minimize the taking of fox squirrels.” 
    Id. at 185.
    Because the Service “found, both in its draft and final
    Environmental Assessment, that there was a ‘Reduced Impact
    Alternative’ that ‘would reduce the likelihood of take’ of fox
    squirrels,” “the agency could not have issued the permit
    consistent with section 10(a) without making a finding that
    the Reduced Impact Alternative was impracticable.” 
    Id. Although the
    developer found the Reduced Impact
    Alternative impracticable, the Service never did so. 
    Id. at 185.
    Because the Service never made an independent finding
    that the alternative was impracticable, it necessarily failed to
    find that take had been minimized to the maximum extent
    practicable, violating the ESA. 
    Id. at 186.
    Assuming that Gerber has implications for a situation in
    which the agency (as here) finds that minimization and
    mitigation fully offset the take, on the record before the Court,
    35
    the Service complied with any applicable obligations
    described in Gerber. Union Neighbors contends that the
    Service “failed to make any independent determination that
    known reduced-impact alternatives would be impracticable,”
    Appellant Br. at 55, which it defines as an alternative that
    would reduce individual bat mortality, id at 56. But Union
    Neighbors discounts the Service’s analysis and rejection of
    the Max Alternative. See Appellant Br. at 58. Although the
    Max Alternative would take no Indiana bats, the Service
    found that only 491,587 MWh/y would be generated and 22%
    fewer emissions would be reduced. The Max Alternative
    would also result in a 22.7% reduction in clean energy; $8.65
    million in lost annual revenues; and $216.5 million in lost
    revenues over the Permit term. J.A. 808. In the Service’s
    Record of Decision for issuing the permit, it specifically
    found that it “would likely result in the Project not being
    built.” J.A. 1043. These findings are sufficient to reject the
    practicability of the Max Alternative under Section 10.
    Accordingly, at least with respect to the one reduced
    impact alternative identified by the agency and accepting its
    assumption that there were no other reduced impact
    alternatives, the Service complied with its purported
    obligations under Gerber. Union Neighbors submits that the
    Service failed to reject another known reduced impact
    alternative when it did not find a 6.5 m/s cut-in speed
    impracticable. But at this time we express no opinion
    whether, after analyzing another reasonable alternative under
    NEPA on remand, the Service has obligations under the ESA
    to make additional independent findings as to whether any
    such alternative is impracticable.
    36
    ***
    For the foregoing reasons, we reverse in part and affirm
    in part the judgment of the District Court.
    So ordered.
    

Document Info

Docket Number: 15-5147

Citation Numbers: 831 F.3d 564

Filed Date: 8/5/2016

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (23)

Gerber, John E. v. Norton, Gale A. , 294 F.3d 173 ( 2002 )

American Wildlands v. Kempthorne , 530 F.3d 991 ( 2008 )

Theodore Roosevelt Conservation Partnership v. Salazar , 661 F.3d 66 ( 2011 )

citizens-against-burlington-inc-v-james-b-busey-iv-administrator , 938 F.2d 190 ( 1991 )

City of Grapevine, Texas v. Department of Transportation, ... , 17 F.3d 1502 ( 1994 )

foundation-on-economic-trends-v-margaret-m-heckler-secretary-of-the , 756 F.2d 143 ( 1985 )

Skidmore v. Swift & Co. , 65 S. Ct. 161 ( 1944 )

Dr Pepper/seven-Up Companies, Inc. v. Federal Trade ... , 991 F.2d 859 ( 1993 )

State of Alaska v. Cecil D. Andrus , 580 F.2d 465 ( 1978 )

Pub Ctzn Inc v. HHS , 332 F.3d 654 ( 2003 )

Sherley v. Sebelius , 644 F.3d 388 ( 2011 )

John W. Allison, Jr. v. Department of Transportation, City ... , 908 F.2d 1024 ( 1990 )

National Cable & Telecommunications Ass'n v. Federal ... , 567 F.3d 659 ( 2009 )

National Wildlife Federation v. Norton , 306 F. Supp. 2d 920 ( 2004 )

United States v. Mead Corp. , 121 S. Ct. 2164 ( 2001 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... , 103 S. Ct. 2856 ( 1983 )

Vermont Yankee Nuclear Power Corp. v. Natural Resources ... , 98 S. Ct. 1197 ( 1978 )

Marsh v. Oregon Natural Resources Council , 109 S. Ct. 1851 ( 1989 )

Babbitt v. Sweet Home Chapter, Communities for Great Ore. , 115 S. Ct. 2407 ( 1995 )

Christensen v. Harris County , 120 S. Ct. 1655 ( 2000 )

View All Authorities »