Continental Resources, Inc. v. Sally Jewell , 846 F.3d 1232 ( 2017 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued October 25, 2016             Decided January 31, 2017
    No. 15-5333
    CONTINENTAL RESOURCES, INC.,
    APPELLANT
    v.
    SALLY JEWELL, SECRETARY, UNITED STATES DEPARTMENT OF
    THE INTERIOR, ET AL.,
    APPELLEES
    Appeal from the United States District Court
    for the District of Columbia
    (No. 1:14-cv-00065)
    L. Poe Leggette argued the cause for Appellant. With him
    on the briefs were Rosario C. Doriott Domínguez and Alexander
    K. Obrecht.
    Tamara N. Rountree, Attorney, U.S. Department of Justice,
    argued the cause for Appellees. With her on the brief were John
    C. Cruden, Assistant Attorney General, and David Gunter,
    Attorney.
    Before: BROWN and SRINIVASAN, Circuit Judges, and
    RANDOLPH, Senior Circuit Judge.
    2
    Opinion for the Court filed by Senior Circuit Judge
    RANDOLPH.
    RANDOLPH, Senior Circuit Judge: The district court
    dismissed as untimely an action Continental Resources, Inc.
    brought for judicial review of a decision of the Department of
    the Interior. Cont’l Res., Inc. v. Jewell, 
    134 F. Supp. 3d 231
    ,
    237 (D.D.C. 2015). The question on appeal is whether, as the
    district court ruled, Continental filed its action more than 180
    days after its “receipt of notice” of Interior’s “final decision.”
    
    30 U.S.C. § 1724
    (j) & (h)(2)(B).
    Continental extracts gas from leased federal land and pays
    royalties to the Interior Department. On May 5, 2010, an agency
    within the Interior Department began an administrative
    proceeding against Continental by issuing an order demanding
    more than $1.7 million in additional royalties. Continental took
    an administrative appeal to the agency’s director. From the date
    of the agency’s order, the Secretary or a designee had thirty-
    three months to reach a final decision in this matter. See 
    30 U.S.C. § 1724
    (h)(1) & (2); Murphy Exploration and Production
    Co. v. U.S. Dep’t of Interior, 
    252 F.3d 473
    , 480-82 (D.C. Cir.
    2001). Under § 1724(h)(2)(B), if the Secretary fails to reach a
    final decision within that time, the Secretary “shall be deemed
    to have issued a final decision” against the lessee when the
    amount in controversy is $10,000 or more, as it was here. 
    30 U.S.C. § 1724
    (h)(2)(B).
    “The 33-month period may be extended by any period of
    time agreed upon in writing by the Secretary and the appellant.”
    
    Id.
     § 1724(h)(1). In July 2010, Continental and the Interior
    agency entered into such an extension agreement, placing
    Continental’s appeal “on hold from June 12, 2010 through
    December 13, 2010, pending completion of settlement
    discussions.” Joint Appendix 151. Extension agreements are
    3
    apparently common. See Agency’s Mot. for Recons. 7-10,
    Cont’l Res., Inc. v. Jewell, No. 1:14-cv-00065-RDM (D.D.C.
    Sept. 25, 2013), ECF No. 21-3. Continental’s written agreement
    also stated that the parties extended “for the same number of
    days the 33-month time frame for processing appeals as set out
    in 30 U.S.C. 1724(h)(1),” but that either party could terminate
    the agreement. Joint Appendix 151. Approximately three
    weeks later, on August 18, 2010, the Interior agency informed
    Continental that it had decided not to enter into settlement
    negotiations.
    In April 2013, Continental received an unfavorable decision
    from the agency’s director.           The company filed an
    administrative appeal to the Interior Board of Land Appeals.
    The Board, concerned about its jurisdiction, issued a show-cause
    order questioning whether the “deemed final” provision had
    already been triggered, thus ending all administrative
    proceedings with a final decision of the Secretary. In response,
    Continental argued that the August 2010 letter from the Interior
    agency terminated their extension agreement and that the
    deadline for the Secretary’s decision therefore passed on June
    15, 2013.1 Interior argued that the letter had not terminated the
    extension agreement and that the deadline would not be reached
    1
    The Board would find for Continental and hold that the deadline
    passed on June 17, 2013. That June 15, 2013, was a Saturday may
    explain this discrepancy. See FED. R. CIV. P. 6(a). But this
    discrepancy, like others in the parties’ proposed chronologies, does
    not affect the outcome of this appeal.
    4
    until August 12, 2013.2 In a five-page opinion, the Board ruled
    that the deadline passed on June 17, 2013, at which time the
    Secretary’s non-decision became “deemed final.”3 Cont’l Res.,
    Inc., 184 IBLA 59, 64 (2013). The Board issued its opinion on
    July 29, 2013.
    Under 
    30 U.S.C. § 1724
    (j), Continental had 180 days from
    “receipt of notice” of the final agency action to file its
    complaint. Continental filed the complaint in the district court
    on January 16, 2014. Interior moved to dismiss it, arguing that
    the complaint was untimely because more than 180 days had
    passed from the date of the Secretary’s “deemed final decision,”
    which Interior identified as June 17, 2013, the date given in the
    opinion of the Board of Land Appeals. The district court agreed
    and dismissed Continental’s complaint. Cont’l Res., 134 F.
    Supp. 3d at 237.
    2
    This proposed deadline created another discrepancy in the
    record. Interior argued for the August 12 deadline by adding 154 days
    to the 33-month period, but it later conceded that under its own theory
    of the case, the extension was for 184 days. See Agency’s Mot. for
    Recons. 5 n.3, Cont’l Res., Inc. v. Jewell, No. 1:14-cv-00065-RDM
    (D.D.C. Sept. 25, 2013), ECF No. 21-3.
    3
    As the Board recognized, the thirty-three months plus extension
    should have been calculated from the time Interior issued its order
    requiring Continental to pay up (May 5, 2010), rather than from the
    time Continental took an appeal from that order (June 10 or 11, 2010).
    Cont’l Res., Inc., 184 IBLA 59, 62 n.3 (2013). See also 
    30 U.S.C. § 1702
    (18); Murphy Exploration, 252 F.3d at 480-82. This error does
    not affect the outcome of the appeal.
    5
    Did the 180-day period begin on June 17, 2013, as Interior
    argued and the district court decided, or on July 29, 2013, the
    date of the Board’s decision, as Continental argued? If June 17,
    Continental’s complaint is time-barred;4 if July 29, the
    complaint is timely.
    In answering this question we understand that the 180-day
    period for seeking judicial review did not run from the date of
    final agency action. The 180-day period ran instead from the
    date Continental received notice of that action. Section 1724(j)
    is quite clear about this. The provision states that “a judicial
    proceeding challenging the final agency action” is “timely so
    long as such judicial proceeding is commenced within 180 days
    from receipt of notice by the lessee or its designee of the final
    agency action.” 
    30 U.S.C. § 1724
    (j).
    So when did Continental receive notice of the Secretary’s
    “deemed final” decision? The date of notice could not possibly
    have been earlier than the ruling of the Board of Land Appeals
    on July 29, 2013. Until then neither Continental nor Interior
    could know what date the Board would designate as the date of
    the Secretary’s final decision. Both sides had presented
    colorable arguments to the Board. Needless to say, one cannot
    be on notice of final agency action while the date of that action
    has not yet been determined. Only when the Board ruled on July
    29, 2013, did Continental learn that § 1724(h) had converted
    4
    The district court treated this as a matter of “subject-matter
    jurisdiction.” Cont’l Res., 134 F. Supp. 3d at 233. United States v.
    Kwai Fun Wong, 
    135 S. Ct. 1625
     (2015), decided five months before
    the district court decision, makes it doubtful that the 180-day period
    is jurisdictional, but nothing in our opinion turns on the point.
    6
    Interior’s inaction into a “final decision in favor of the
    Secretary” on June 17, 2013. The Board’s ruling, and
    Continental’s “receipt of notice” of that ruling, triggered the
    running of the 180-day period under § 1724(j). It follows that
    Continental commenced this action within the 180-day period.
    The company filed its complaint on January 16, 2014, 171 days
    after the Board’s ruling of July 29, 2013.
    The district court decided that the 180-day period ran from
    June 17, 2013, the date of the Secretary’s deemed-final decision.
    But as we have pointed out, § 1724(j) provides that the 180-day
    period runs not from the date of the final decision, but from the
    lessee’s “receipt of notice” of the final decision. To explain the
    discrepancy, the district court stated that “although the plaintiff
    did not receive notice of final agency action until July 29, 2013,
    the plaintiff received notice by operation of law that the
    Secretary had not issued a decision within the 33 month period.”
    Cont’l Res., 134 F. Supp. 3d at 237. “Operation of law”?5 What
    “law”? The “law” here is § 1724(h)’s 33-month provision and
    § 1724(j), pursuant to which the 180-day period runs “from
    receipt of notice.” If the district court believed that § 1724(h)
    5
    When courts have interpreted “receipt of notice” in other
    contexts, the discussion has often focused on a question not presented
    here – namely, who must receive the mailed notice. We have held that
    in some instances the litigant must personally receive the notice, Bell
    v. Brown, 
    557 F.2d 849
    , 857 (D.C. Cir. 1977), while receipt by the
    litigant’s attorney sufficed in others, Rao v. Baker, 
    898 F.2d 191
    , 198
    (D.C. Cir. 1990). See also Irwin v. Dep’t of Veterans Affairs, 
    498 U.S. 89
    , 91-93 (1990); Christmas v. Spellings, 
    404 F. Supp. 2d 239
    , 240-41
    (D.D.C. 2005) (collecting cases). We have never held that a party
    received notice by “operation of law” and we are not aware of any
    decision to that effect in the other courts of appeals.
    7
    somehow triggered § 1724(j), it offered no basis for that belief.
    It instead relied on the “operation of law,” and thereby read
    § 1724(j)’s “receipt of notice” requirement out of the statute.
    We do not decide what level of notice is required in other
    situations. This case does not involve, for instance, the
    § 1724(h) conversion deadline passing without dispute or the
    Secretary issuing a timely decision on the merits. We hold only
    that because Continental could not have known the date of final
    agency action until July 29, 2013, receipt of notice could not
    have occurred before then. Continental’s complaint was
    therefore timely. The judgment of the district court is reversed
    and the case is remanded for further proceedings.
    So ordered.