Kansas Corporation Commission v. FERC , 881 F.3d 924 ( 2018 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued November 20, 2017          Decided February 6, 2018
    No. 16-1093
    KANSAS CORPORATION COMMISSION,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    SOUTH CENTRAL MCN LLC, ET AL.,
    INTERVENORS
    Consolidated with 16-1164
    On Petitions for Review of Orders of the
    Federal Energy Regulatory Commission
    Jason T. Gray argued the cause for the petitioner.
    Kathleen L. Mazure was with him on brief.
    Anand R. Viswanathan, Attorney, Federal Energy
    Regulatory Commission, argued the cause for the respondent.
    Robert H. Solomon, Solicitor, and Susanna Y. Chu, Attorney,
    were with him on brief. Lona T. Perry, Attorney, entered an
    appearance.
    2
    Steven J. Ross argued the cause for the intervenors.
    Shaun M. Boedicker, Michael F. McBride, William L. Massey,
    Mark L. Perlis and Kevin F. King were with him on brief
    Before: HENDERSON and SRINIVASAN, Circuit Judges, and
    GINSBURG, Senior Circuit Judge.
    Opinion for the Court filed by Circuit Judge HENDERSON.
    KAREN LECRAFT HENDERSON, Circuit Judge: Petitioner
    Kansas Corporation Commission (KCC), a Kansas regulatory
    body that oversees Kansas public utilities, asserts that the
    Federal Energy Regulatory Commission (FERC) acted
    unlawfully by approving formula rates—which help determine
    the electric rates charged by public utilities to consumers in
    FERC jurisdictions—for future public utilities to use in
    operating electric transmission facilities. KCC argues that
    FERC cannot determine, as it must under the Federal Power
    Act, 16 U.S.C. §§ 792 et seq., that the formula rates for such
    not-yet-existing entities to implement at some point in the
    future are “just and reasonable,” 
    id. § 824d(a).
    By that same
    argument, however, KCC has not suffered an injury in fact
    sufficient to establish standing. A harm that will not occur
    unless a series of contingencies occurs at some unknown future
    time is not concrete, particularized, actual and imminent.
    Accordingly, we dismiss KCC’s petitions for review.
    I.   BACKGROUND
    FERC regulates the rates of public utilities engaged in the
    wholesale transmission of electric energy in interstate
    commerce. 16 U.S.C. § 824(a), (e). FERC must ensure, under
    section 205 of the Federal Power Act, that public utilities’ rates
    are “just and reasonable.” 
    Id. § 824d(a)
    (“All rates and charges
    made, demanded, or received by any public utility for or in
    connection with the transmission or sale of electric energy . . .
    3
    shall be just and reasonable, and any such rate or charge that is
    not just and reasonable is hereby declared to be unlawful.”). To
    do so, “every public utility shall file with” FERC, “[u]nder such
    rules and regulations as [FERC] may prescribe . . . and in such
    form as [FERC] may designate,” “schedules showing all rates
    and charges for any transmission or sale” of electricity. 
    Id. § 824d(c).
    Section 206 of the Federal Power Act allows
    FERC—on its own initiative or upon a third-party complaint—
    to adjust previously-approved rates if they are no longer just
    and reasonable. 
    Id. § 824e(a)
    (“Whenever [FERC], after a
    hearing held upon its own motion or upon complaint, shall find
    that any rate . . . is unjust, unreasonable, unduly discriminatory
    or preferential, [FERC] shall determine that just and reasonable
    rate . . . and shall fix the same by order.”).
    FERC encourages public utilities to participate in regional
    processes that allocate the costs of new energy transmission
    facilities on a region-wide basis. See S.C. Pub. Serv. Auth. v.
    FERC, 
    762 F.3d 41
    , 49–53 (D.C. Cir. 2014) (providing
    overview of electric industry). The Southwest Power Pool
    (SPP) is a FERC-regulated Regional Transmission
    Organization that currently provides electricity to parts of
    fourteen states 1 on behalf of member public utilities. The SPP
    uses a selection process by which incumbent and
    1
    Arkansas, Iowa, Kansas, Louisiana, Minnesota, Missouri,
    Montana, Nebraska, New Mexico, North Dakota, Oklahoma, South
    Dakota, Texas and Wyoming. Electric Power Markets: Southwest
    Power Pool—Overview, FEDERAL ENERGY REGULATORY
    COMMISSION, www.ferc.gov/market-oversight/mkt-electric/spp.asp
    (last visited Dec. 27, 2017). At the time of FERC’s orders, the SPP
    extended to eight states only (Arkansas, Kansas, Louisiana,
    Missouri, Nebraska, New Mexico, Oklahoma and Texas, see
    Southwest Power Pool, Inc., 144 FERC ¶ 61,059 at P 25 (2013)) but
    has since expanded to fourteen.
    4
    nonincumbent utilities bid for the right to develop transmission
    projects within the SPP footprint.
    The SPP recovers transmission rates on behalf of utilities
    operating transmission facilities in the SPP’s region through its
    FERC-jurisdictional tariff. Part of the SPP’s tariff is the
    facility’s formula rate. A formula rate “specifies the cost
    components that form the basis of the rates a utility charges its
    customers” in a “fixed, predictable nature,” which allows
    utilities to recover costs that “fluctuate over time” and prevents
    them from using “excessive discretion in determining the
    ultimate amounts charged to customers.” Pub. Utils. Comm’n
    of Cal. v. FERC, 
    254 F.3d 250
    , 254 (D.C. Cir. 2001) (internal
    quotation omitted). KCC’s petitions involve two FERC orders
    approving formula rates for future utilities that may seek to
    develop transmission facilities in the SPP’s region.
    Transource Energy, LLC is a parent company that “serves
    as the holding company for transmission development-focused
    subsidiaries” nationwide. Joint Appendix (JA) 25. Transource
    Energy wanted to develop electric transmission facilities in the
    SPP’s regional footprint. Because of statutory and regulatory
    differences about “public utility governance and the issuance
    of securities” among the various states in the SPP, Transource
    Energy wanted to create state-specific subsidiaries which
    would then submit state-specific bids for SPP facilities. JA 17.
    Transource Energy formed Transource Kansas, a wholly
    owned subsidiary, to compete for Kansas-based transmission
    projects. Transource Energy also anticipates creating more
    state-specific subsidiaries in SPP states (e.g., Transource
    Arkansas) that will be “formally established as legal entities at
    the time Transource Energy submits its bid to develop a
    [transmission facility] within the corresponding state in the
    SPP footprint.” JA 25.
    5
    Transource Kansas wanted to get a formula rate approved
    before it bid for SPP transmission facilities. Without advance
    approval of the formula rate, it would be unable to
    competitively bid for two reasons. First, the SPP evaluates bids
    in part on a transmission facility’s charges, which are based in
    part on the formula rate; without an approved formula rate,
    Transource Kansas would be at a competitive disadvantage
    compared with other facilities that did have approved formula
    rates. Second, a utility has 180 days to bid for a transmission
    facility but cannot obtain FERC approval of a formula rate for
    up to one or two years, making it “impractical” to wait for
    FERC approval until the bidding window opens. JA 20.
    For the same reasons, Transource Energy also wanted to
    get formula rates approved for future state-specific subsidiaries
    (e.g., Transource Arkansas). Accordingly, when Transource
    Kansas submitted the requisite section 205 filings to secure
    formula rate approval, it also asked FERC to authorize future
    affiliates (e.g., Transource Arkansas) to replicate the formula
    rate approved for Transource Kansas if they won a bid.
    Transource Kansas explained that the data it submitted to show
    that its formula rate was just and reasonable would be used by
    the future affiliates that shared the same parent company.
    KCC, which is authorized to regulate rates for the sale of
    electricity to Kansas consumers, see KAN. STAT. ANN. § 66-
    101 (KCC has “full power, authority and jurisdiction to
    supervise and control the electric public utilities” in Kansas),
    objected. It argued that preapproving a formula rate for a future
    affiliate violated FERC’s section 205 mandate to ensure that
    charged rates are just and reasonable. FERC, however, granted
    Transource Kansas’s request. Order on Transmission Formula
    Rate Proposal and Incentives, 151 FERC ¶ 61,010 at P 81 (Apr.
    3, 2015). FERC instructed that “if and when” SPP awarded a
    bid to Transource Kansas, its section 205 filings should be
    6
    labeled as the pro forma templates “for use by any Transource
    [affiliates], which will obviate the need to make additional
    section 205 filings.” 
    Id. KCC requested
    a rehearing, which FERC denied. Order
    on Rehearing and Compliance, 154 FERC ¶ 61,011 (Jan. 8,
    2016). FERC reasoned that future Transource affiliates will be
    “similarly situated with respect to risk and capital
    requirements” to Transource Kansas so it made sense to allow
    both to use the same formula rate. 
    Id. at P
    17. FERC also
    reasoned that preapproving a formula rate for Transource
    Kansas, which did not operate any active transmission
    facilities, was “no different” from preapproving a formula rate
    for future Transource affiliates. 
    Id. Accordingly, FERC
    “s[aw]
    no reason at this time to litigate” separate formula rates for
    Transource Kansas and its future sibling affiliates of the same
    parent company. 
    Id. at P
    18.
    MPT Heartland Development, LLC is another parent
    company that, like Transource Energy, serves as a holding
    company for subsidiaries created to develop transmission
    facilities. MPT Heartland similarly formed Kanstar, a wholly
    owned subsidiary, to compete for Kansas-specific projects.
    MPT Heartland anticipates bidding on behalf of future state-
    specific subsidiaries for transmission facilities. The
    subsidiaries will be formally established as legal entities and
    will take control of the transmission facilities if MPT Heartland
    wins the bid. As with Transource Kansas, Kanstar submitted a
    filing to FERC under section 205 requesting a formula rate for
    its own use and approval for future Kanstar affiliates (e.g.,
    Arkstar) to replicate its formula rate. KCC protested the
    request. FERC accepted Kanstar’s proposal in relevant part and
    rejected KCC’s protest. Order on Transmission Formula Rate
    Proposal and Incentives, 152 FERC ¶ 61,209 at PP 83–84
    (Sept. 17, 2015). KCC filed a request for rehearing of the
    7
    Kanstar order. FERC denied rehearing “for the same reasons”
    that FERC denied rehearing of the Transource Kansas order.
    Order Denying Rehearing, 155 FERC ¶ 61,167 at P 9 (May 19,
    2016).
    KCC petitions for review of FERC’s April 3, 2015 and
    January 8, 2016 orders (Transource Kansas) as well as its
    September 17, 2015 and May 19, 2016 orders (Kanstar).
    II. ANALYSIS
    On the merits, KCC argues that FERC’s orders
    “contravene[]” the Federal Power Act. Pet’r’s Br. at 28. Under
    KCC’s reading, public utilities have an “obligation” to prove
    their electric rates are “just and reasonable” and FERC has a
    corresponding mandate to authorize only just and reasonable
    rates under section 205. Pet’r’s Br. at 34 (discussing 16 U.S.C.
    § 824d(a)). KCC asserts that the “principal error in the
    challenged orders” is that FERC has authorized future affiliates
    (e.g., Transource Arkansas and Arkstar) to replicate, “at some
    unknown time in the future,” the formula rates approved for
    use by Transource Kansas and Kanstar without the former, if
    formed, having to submit the requisite section 205 filings to
    establish the justness and reasonableness of those rates. Pet’r’s
    Br. at 27. FERC’s error, KCC asserts, shifted the burden to
    entities such as KCC to challenge the formula rates in a later
    section 206 proceeding, in which the challenger must prove the
    rates are in fact unjust or unreasonable. See 16 U.S.C. § 824e(a)
    (authorizing FERC to initiate, “upon [third-party] complaint,”
    proceeding to determine if rates are no longer just and
    reasonable and, if so, adjust them); Maine v. FERC, 
    854 F.3d 9
    , 21 (D.C. Cir. 2017) (in section 206 proceeding, “burden of
    demonstrating that the existing [rate] is unlawful is on . . . the
    complainant”).
    8
    But we cannot address the merits without ensuring KCC
    has the “irreducible constitutional minimum of standing.”
    Lujan v. Defenders of Wildlife, 
    504 U.S. 555
    , 560 (1992). As
    detailed below, we conclude that KCC does not have standing
    because it lacks the necessary injury in fact.
    To satisfy the constitutional requirements for standing, a
    party must have (1) an injury in fact, (2) fairly traceable to the
    challenged agency action, (3) that will likely be redressed by a
    favorable decision. 
    Id. at 560–61.
    An injury in fact is an
    “invasion of a legally protected interest which is (a) concrete
    and particularized, and (b) actual or imminent, not conjectural
    or hypothetical.” 
    Id. at 560
    (internal quotation omitted).
    Because KCC is not the “object of the [agency] action” it
    challenges, its injury is not “self-evident.” Sierra Club v. EPA,
    
    292 F.3d 895
    , 900 (D.C. Cir. 2002). Accordingly, it bears the
    burden to identify record evidence sufficient to support its
    standing to seek review. 
    Id. at 899.
    KCC’s opening brief cursorily states that “FERC’s
    unfavorable rulings on the issues on appeal render KCC an
    aggrieved party.” Pet’r’s Br. at 32. FERC’s rejection of KCC’s
    challenges in the proceedings before it, however, does not
    establish constitutional standing. See N.Y. Reg’l Interconnect,
    Inc. v. FERC (NYRI), 
    634 F.3d 581
    , 586 (D.C. Cir. 2011) (party
    does not acquire requisite “direct stake in a litigation simply by
    participating in the antecedent administrative proceedings”
    (internal quotation omitted)). KCC must affirmatively
    demonstrate how it is adversely affected by FERC’s orders. See
    Sierra 
    Club, 292 F.3d at 899
    .
    KCC’s more thorough effort made in its reply brief fares
    no better. It asserts that FERC’s contravention of the Federal
    Power Act is sufficient to support its standing. See Reply Br. at
    6 (FERC orders “constitute[] concrete and particularized harm
    9
    to KCC and Kansas ratepayers because FERC determined, in
    advance, that [nonexistent] affiliates need not justify their rates
    at the future point in time when they propose to provide”
    electric service); 
    id. at 7
    (identifying “concrete harm” as
    “FERC’s predetermination that not-yet-formed affiliates’ rates
    are just and reasonable despite no such demonstration by those
    affiliates under FPA Section 205”); 
    id. at 9
    (“[The] harm to the
    KCC—undermining the FPA’s consumer-protection focus by
    pre-approving rates that have not been shown to be just and
    reasonable for the not-yet-formed affiliates authorized to
    charge those rates—has already occurred.”).
    United States Supreme Court precedent does not support
    KCC’s theory of harm. A party claiming “only harm to his . . .
    interest in [the] proper application of the . . . laws, and seeking
    relief that no more directly and tangibly benefits him than it
    does the public at large,” has no concrete and particularized
    injury. 
    Lujan, 504 U.S. at 573
    –74. KCC’s argument that it is
    harmed because FERC violated the Federal Power Act and
    determined legal rights is no more than a generalized interest
    in the proper application of the law. That is not enough. See
    Capital Legal Found. v. Commodity Credit Corp., 
    711 F.2d 253
    , 258 (D.C. Cir. 1983) (A “party who would complain that
    agency action has violated [a statute] must be adversely
    affected by that action”).
    At oral argument, KCC identified a more specific harm: its
    “future” burden of initiating a section 206 proceeding to
    challenge the formula rates as unjust or unreasonable. See Oral
    Argument at 3:50–3:55. As KCC’s theory goes, a public utility
    must demonstrate under section 205 that its rates are just and
    reasonable before commencing service. See 16 U.S.C.
    § 824d(a). FERC’s orders preapproving formula rates for
    future affiliates that have not yet made section 205 filings to
    establish the justness and reasonableness of the rates, KCC
    10
    argues, improperly invert the Federal Power Act’s allocation of
    burdens. KCC will have to challenge the same formula rates in
    a section 206 proceeding, when it will bear the burden to prove
    the rates are unjust or unreasonable.
    But that harm is not imminent, as demonstrated by KCC’s
    own arguments on the merits. It repeatedly argues that FERC
    could not determine the formula rates were just and reasonable
    because the formula rates will not be used until “some
    unknown time in the future.” Pet’r’s Br. at 10, 15, 17, 25, 27,
    33, 44, 51. A petitioner that asserts a harm that may occur
    “some day,” with no “specification of when the some day will
    be,” does not establish its standing. 
    Lujan, 504 U.S. at 564
    ; see
    Pub. Citizen v. NHTSA, 
    489 F.3d 1279
    , 1293–94 (D.C. Cir.
    2007) (no imminent harm to petitioner challenging rulemaking
    that allegedly increased risks of car accidents because “the time
    (if ever) when any such accident would occur is entirely
    uncertain”).
    Instead, any harm to KCC is “conjectural or hypothetical.”
    
    Lujan, 504 U.S. at 560
    . The particularized effect of FERC’s
    orders will not be felt by KCC unless an “attenuated chain of
    possibilities” occurs. Clapper v. Amnesty Int’l USA, 
    568 U.S. 398
    , 410 (2013). It will not be harmed until and unless (1) the
    parent company submits a bid for transmission facilities; (2)
    the SPP awards the bid to the parent company of the then-
    formed subsidiary, e.g., Transource Arkansas or Arkstar; (3)
    the subsidiary seeks to use the formula rates; and (4) KCC
    commences a section 206 proceeding.
    KCC points to nothing in the record to meet its burden to
    show a “substantial probability” that all of these steps will
    occur and, if so, when. Am. Petroleum Inst. v. EPA, 
    216 F.3d 50
    , 63 (D.C. Cir. 2000) (internal quotation omitted). It does not
    assert that any bid by the parent company is pending. Even if a
    11
    bid had been placed, KCC’s feared result depends on the
    SPP—an independent third party—accepting the bid. KCC
    provides no supporting evidence that the SPP is more likely to
    select the bids of Transource Kansas or Kanstar affiliates’
    parent company than bids of other companies. We are
    “usual[ly] reluctan[t] to endorse standing theories that rest on
    speculation about the decisions of independent actors,”
    
    Clapper, 568 U.S. at 414
    , and we will not break with that
    general rule here. Finally, even if the SPP does select bids made
    by the parent companies on behalf of future Transource Kansas
    or Kanstar affiliates, it is uncertain that KCC will initiate a
    section 206 proceeding. The formula rates may not, in the end,
    turn out to be unjust or unreasonable at the time they are
    imposed. If that is so, KCC would have no reason to bring a
    section 206 proceeding and there would be no harm. See Oral
    Argument at 5:20–5:30 (KCC counsel acknowledging that “it
    may turn out that there is no issue” because formula rates may
    be just and reasonable). In sum, then, KCC’s alleged harm
    “stacks speculation upon hypothetical upon speculation, which
    does not establish an actual or imminent injury.” 
    NYRI, 634 F.3d at 587
    (internal quotation omitted).
    Further, KCC’s reliance on ANR Pipeline Co. v. FERC,
    
    771 F.2d 507
    (D.C. Cir. 1985), is unavailing. In that case, the
    petitioner had standing because FERC’s approval of a pipeline
    company’s rate increase was necessarily adverse to the
    petitioner because it automatically took effect as soon as the
    pipeline company filed to implement the new rate, which filing
    the Court found “unavoidable.” 
    Id. at 516.
    In contrast, if the
    preapproved formula rates here are ever put into effect, KCC
    may not necessarily challenge them because, as pointed 
    out supra
    , KCC may view the formula rates as just and reasonable
    when imposed. Moreover, the SPP may never select
    Transource Kansas or Kanstar affiliates to operate transmission
    facilities within the SPP’s footprint. Thus, KCC’s alleged harm
    12
    is not “unavoidable.” See 
    NYRI, 634 F.3d at 587
    (denying
    corporation’s standing to challenge FERC orders because
    alleged harm “rests upon a hypothetical chain of events, none
    of which is certain to occur”); see also Whitmore v. Arkansas,
    
    495 U.S. 149
    , 155 (1990) (injuries must be “concrete” in
    “temporal sense”).
    One final bit of housekeeping. KCC stated that it needs
    judicial review now because FERC, in any proceeding initiated
    by a future affiliate to use the preauthorized formula rates, will
    be bound by the orders at issue here. Although in its reply brief
    KCC expressly disclaimed that it relied on this theory to
    establish standing, Reply Br. at 11 (denying that it “relies on
    any precedential effect of the rulings below to establish
    standing”), we address the issue because KCC nonetheless
    expressed its concern, see Reply Br. at 6 (“These petitions
    present the only opportunity to challenge [FERC’s] findings
    without facing claims of collateral attack.”); Oral Argument at
    2:30–2:45 (“At any future proceeding, the Kansas Commission
    would not have the opportunity to challenge [FERC’s]
    determinations. This appeal is the only opportunity.”). Whether
    or not KCC is correct in its assertions, its now-or-never
    argument cannot establish standing. We have repeatedly
    rejected similar arguments. See New England Power
    Generators Ass’n, Inc. v. FERC, 
    707 F.3d 364
    , 369 (D.C. Cir.
    2013) (“[N]either a FERC decision’s legal reasoning nor the
    precedential effect of such reasoning confers standing unless
    the substance of the decision itself gives rise to an injury in
    fact.”); Exxon Mobil Corp. v. FERC, 
    571 F.3d 1208
    , 1219
    (D.C. Cir. 2009) (“[A] mere interest in FERC’s legal reasoning
    and the possibility of a ‘collateral estoppel effect’ are
    insufficient to confer a cognizable injury in fact.”).
    13
    For the foregoing reasons, we dismiss KCC’s petitions for
    lack of standing.
    So ordered.