AT&T, Inc. v. FCC , 886 F.3d 1236 ( 2018 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued October 26, 2017              Decided April 6, 2018
    No. 15-1038
    AT&T, INC.,
    PETITIONER
    v.
    FEDERAL COMMUNICATIONS COMMISSION AND UNITED
    STATES OF AMERICA,
    RESPONDENTS
    UNITED STATES TELECOM ASSOCIATION AND CENTURYLINK,
    INC.,
    INTERVENORS
    Consolidated with 16-1002, 16-1072
    On Petitions for Review of Orders of
    the Federal Communications Commission
    Benjamin S. Softness argued the cause for petitioners.
    With him on the briefs were Scott H. Angstreich, Robert A.
    Long Jr., Yaron Dori, Kevin King, Christopher Heimann, Gary
    L. Phillips, and David L. Lawson.
    Matthew J. Dunne, Counsel, Federal Communications
    Commission, argued the cause for respondents. With him on
    2
    the brief were Robert B. Nicholson and Robert J. Wiggers,
    Attorneys, U.S. Department of Justice, Howard J. Symons,
    General Counsel, Federal Communications Commission, and
    Richard K. Welch, Deputy Associate General Counsel. Jacob
    M. Lewis, Associate General Counsel, Maureen K. Flood,
    Counsel, and Sarah E. Citrin, Attorney, Federal
    Communications Commission, entered appearances.
    Before: GARLAND, Chief Judge, and PILLARD and
    WILKINS, Circuit Judges.
    Opinion for the Court filed by Circuit Judge PILLARD.
    PILLARD, Circuit Judge: The Federal Communications
    Commission has, since the agency’s inception, been charged to
    ensure that everyone in the United States has access to critical
    telecommunications services. This mandate is effected through
    a system of federal subsidies to certain designated carriers that
    are required to offer essential services to underserved
    consumers.       Recognizing the changing technological
    landscape, the Commission is currently in the process of
    expanding those services that must be universally accessible
    beyond landline telephone service to include broadband and
    cellular service. As the transition takes place, the agency has
    retained some preexisting obligations of a subset of landline-
    only providers to ensure that underserved populations in a
    small number of hard-to-reach areas do not lose access to basic
    telecommunications services during the transition, before the
    modernized program is fully in effect—July 24, 2018 in most
    areas.     Telecommunications carriers with such legacy
    obligations bring these petitions challenging the FCC’s
    decision to hold their obligations in place during this interim
    period.
    3
    I.   Introduction
    The telecommunications landscape—and the provision of
    essential services to hard-to-reach places and underserved
    individuals—has changed dramatically over the last two
    decades.        Regional monopolists initially provided
    telecommunications services, including to remote areas and
    low-income populations; then, in 1996, Congress introduced
    competition       into        telecommunications      markets.
    Telecommunications Act of 1996, Pub L. No. 104-104, 110
    Stat. 56 (codified at 47 U.S.C. § 151) (1996 Act); see Rural
    Cellular Ass’n v. FCC (Rural Cellular I), 
    588 F.3d 1095
    , 1098
    (D.C. Cir. 2009).        From 1996 to 2011, the Federal
    Communications Commission (FCC, Commission, or agency)
    ensured nationwide landline accessibility through the
    abovementioned system of service obligations and federal
    subsidies     for     certain     carriers,  called    Eligible
    Telecommunications Carriers (ETCs), that were well-
    positioned to reach the underserved. See 47 U.S.C. § 214(e)(2);
    Rural Cellular Ass’n v. FCC (Rural Cellular II), 
    685 F.3d 1083
    , 1086 (D.C. Cir. 2012).
    In 2011, the FCC recognized that its critical
    communications mandate was no longer meaningfully fulfilled
    by ensuring universal access to landlines alone. To bring the
    entire United States into the digital age, the Commission
    redefined these critical services to include broadband and
    cellular, and began to overhaul its regulatory framework
    accordingly. See In re Connect America Fund, 26 FCC Rcd.
    17,663, 17,667-72 (2011) (2011 Order). It sought to make the
    provider and subsidy system more technologically advanced
    and efficient. 
    Id. at 17,668-69.
    The Commission also
    recognized the need to, at a minimum, maintain existing
    coverage for marginalized populations and hard-to-reach areas
    while it renovated the federally supported network for
    4
    expanded services. The agency opted to retain certain elements
    of the landline-only ETC regime during the transition insofar
    as needed to prevent any customers from being cut off from
    key communications services. It determined that the landline
    carriers already providing those essential services were in the
    best position easily and efficiently to prevent coverage gaps.
    AT&T and CenturyLink, together with Intervenor industry
    group U.S. Telecom Association (USTelecom) (collectively
    Petitioners), are incumbent ETCs that currently retain a small
    fraction of their pre-2011 landline-only universal service
    obligations in certain areas—census blocks they once served
    that are denominated “high-cost” or “extremely high-cost”—
    until new ETCs can be competitively selected to provide
    expanded services there. 
    Id. at 17,709.
    For many census
    blocks, a new ETC will be selected via auction on July 24,
    2018. See Public Notice, Connect America Fund Phase II
    Auction Scheduled for July 24, 2018, FCC No. 18-6, at 3 (Feb.
    1, 2018), https://apps.fcc.gov/edocs_public/attachmatch/FCC-
    18-6A1.pdf (2018 Public Notice). In the interim, the
    Commission subsidizes the landline-only ETC services at
    frozen, preexisting funding levels. 2011 Order, 26 FCC Rcd.
    at 17,712-13, 17,715.
    Most census blocks where these incumbent carriers have
    ETC obligations have already transitioned to receiving federal
    subsidies based on the new funding model, which supports
    capital investment and operating costs for both voice and
    broadband. In re Petition of USTelecom for Forbearance, 31
    FCC Rcd. 6157, 6215 & n.365 (2015) (2015 Order). The only
    remaining disputed service obligations are those in the small
    number of census blocks where an incumbent ETC has been
    providing landline-only service and has declined, or is
    otherwise ineligible, to provide expanded services. See id.;
    2011 Order, 26 FCC Rcd. at 17,729. Petitioners asked the FCC
    5
    either to excuse their universal service obligations in those
    areas or, in the alternative, to reinterpret the statute to narrow
    ETC obligations in the same manner. Petitioners here
    challenge the FCC’s partial denials of their requests.
    First, in 2014, the FCC granted Petitioners’ request in part,
    relieving them of obligations in certain categories of census
    blocks where basic service was otherwise assured. In re
    Connect America Fund, 29 FCC Rcd. 15,644, 15,663-64
    (2014) (2014 Order). At the same time, the Commission left
    undecided the status of the remaining fraction—about six
    percent as of the 2015 Order—of high-cost and extremely high-
    cost census blocks where coverage was not otherwise assured.
    Id.; 2015 Order, 31 FCC Rcd. at 6215 n.365.
    Then, in 2015, the FCC denied Petitioners’ request with
    regard to those remaining census blocks, holding in place the
    incumbent ETCs’ residual service obligations pending
    completion of the transition. See 2015 Order, 31 FCC Rcd. at
    6211-12. The agency reasoned that Petitioners had not met
    their burden to demonstrate that underserved individuals and
    areas would retain access to essential services in the absence of
    incumbent ETC landline service. 
    Id. at 6216-17.
    Petitioners
    failed to marshal sufficiently fine-grained evidence that all
    vulnerable areas and individuals would continue to have
    access, and their aggregate data suggested that there would be
    service shortfalls. 
    Id. As a
    consequence, the FCC decided that
    available opportunities for Petitioners to seek case-by-case,
    area-specific forbearance or additional funding to compensate
    for shortfalls remained the best course. 
    Id. at 6224-25,
    6229 n.
    440. The agency did not want to devote significant resources
    to overhaul the preexisting system for a short, interim period
    when it is about to be replaced by the new regime. See 
    id. at 6223.
                                   6
    In the same 2015 Order, the Commission finalized the
    interim landline-only obligations for incumbent ETCs,
    declining Petitioners’ invitation to sunset their obligations by
    reinterpreting the statute to narrow ETCs’ duties. 
    Id. at 6226-
    27. The best reading of the statute, the agency maintained,
    authorized the interim system of obligations and frozen
    support. 
    Id. at 6228-29.
    As a result of the 2014 and 2015 Orders, the only
    remaining obligations, which Petitioners here dispute, are those
    not already excused in 2014 and not yet reassigned to a new
    ETC willing and able to provide modernized universal service.
    
    Id. at 6215
    & n.365. Petitioners challenge the FCC’s decision
    to maintain those service obligations as arbitrary and capricious
    and contrary to various provisions of the amended
    Communications Act of 1934, 47 U.S.C. § 151 et seq.
    (Communications Act or Act).
    We deny the petitions for two primary reasons. First, we
    owe deference to the FCC’s decision to hold a preexisting
    regime in place for an interim period, so as to avoid
    commandeering agency resources and to respect the agency’s
    judgments about how to maintain baseline universal service in
    the context of uncertainties attending a major regulatory
    transition. Second, in response to Petitioners’ generalized
    allegations that vulnerable consumers do not need the disputed
    services and that the existing program leaves Petitioners with
    underfunded obligations, the FCC has made clear that it will
    grant case-by-case forbearance or supplemental funding in
    areas where providers can meet their burden to show that their
    services are not required or that they need additional financial
    help. Especially in the context of this systemic regulatory
    transition, no more is required.
    7
    II. Background
    A core mission of the FCC, dating from its establishment
    in 1934 by the Communications Act, is “to make available, so
    far as possible, to all the people of the United States . . . a rapid,
    efficient, Nation-wide, and world-wide . . . communication
    service with adequate facilities at reasonable charges.” Pub. L.
    No. 73-416, 48 Stat. 1064 (codified at 47 U.S.C. § 151). The
    FCC aims to achieve “universal service” by ensuring that
    critical communications technologies are made available
    throughout the United States. See 47 U.S.C. § 254. The Act
    makes clear that the universal service guarantee must be
    dynamic, so that the public has access to “an evolving level of
    telecommunications services”; as a result, the Commission
    must “periodically” redefine the “level of . . . services” that
    should be universally available to keep pace with technological
    advancements, need, use, and the public interest. 
    Id. § 254(c).
    Universal service has remained a consistent and
    fundamental goal for the FCC, even as the nature of that service
    and the regulatory means of achieving it have changed. See
    Rural Cellular 
    I, 588 F.3d at 1098
    .                  Historically,
    telecommunications providers formed natural monopolies, and
    the FCC achieved universal service by authorizing rates to
    monopoly providers sufficient to enable revenue from easy-to-
    reach customers, such as city dwellers, to implicitly subsidize
    service to those in areas that were hard to reach. In re Federal-
    State Joint Board on Universal Service, 12 FCC Rcd. 8776,
    8784 (1997) (First Universal Service Order); see Alenco
    Commc’ns, Inc. v. FCC, 
    201 F.3d 608
    , 616 (5th Cir. 2000).
    That approach no longer sufficed once the 1996 Act amended
    the Communications Act to create competition in local
    telephone markets, eliminating the monopolies. See Rural
    Cellular 
    I, 588 F.3d at 1098
    ; Alenco 
    Commc’ns, 201 F.3d at 616
    .
    8
    Beginning in 1996, the FCC therefore imposed obligations
    on certain well-positioned carriers—ETCs—to maintain
    landline services for high-cost, hard-to-reach rural areas, as
    well as indigent households and local institutions like schools,
    hospitals, and libraries. See 47 U.S.C. § 254(h); First
    Universal Service Order, 12 FCC Rcd. at 8790-97. A
    designated ETC generally served all the needy areas and
    individuals within a state. See In re Connect America Fund, 26
    FCC Rcd. 4554, 4669 & n.519 (2011). And Congress
    established the Universal Service Fund (Fund) to give each
    ETC financial support in providing those critical services. See
    Rural Cellular 
    I, 588 F.3d at 1098
    -99.
    In 2011, the FCC undertook the above-referenced
    redefinition of universal service and accompanying program
    overhaul. Recognizing significant changes to communications
    technology, the Commission, per its statutory mandate,
    redefined essential services that should be universally ensured
    to include broadband and cellular. See 2011 Order, 26 FCC
    Rcd. at 17,667-69. Given providers’ differing abilities to offer
    those expanded services, the agency needed to restructure its
    ETC system to include carriers capable of providing those
    newly essential technologies, and doing so most easily and
    cheaply. 
    Id. at 17,669.
    During the regulatory transition, to ensure that vulnerable
    regions and consumers were not completely cut off, the agency
    opted to hold in place certain preexisting landline-only
    obligations on incumbent ETCs already established under the
    pre-2011 system. 
    Id. at 17,712-13,
    17,715. Just how much
    support incumbent ETCs are due for providing critical landline
    services during this transition is the question at the heart of this
    litigation. In particular, the parties dispute whether the FCC
    has authority to hold these incumbent ETCs to preexisting
    obligations at frozen funding levels in a dwindling number of
    9
    census blocks pending these blocks’ reassignment to
    broadband universal service providers.
    A. The Communications Act
    Two provisions of the Communication Act, as amended by
    the 1996 Act, are at issue in this case. Section 254 establishes
    procedures for the FCC, together with the states, to review
    universal service requirements in light of the changing
    technological landscape and to propose new regulations
    governing the provision of universal service. 47 U.S.C. § 254.
    To guide in the “preservation and advancement of universal
    service,” Section 254 enumerates principles including service
    quality, reasonable rates, reasonably comparable access
    nationwide to “advanced telecommunications and information
    services,” “specific, predicable and sufficient” financial
    support for universal service providers, and generally equitable
    contributions to universal service by all telecommunications
    providers. 
    Id. § 254(b);
    see also 
    id. § 254(e)
    (requiring
    “explicit and sufficient” funding for universal service
    providers). That section also grants the Commission authority
    to identify, with state input, “other principles . . . necessary and
    appropriate for the protection of the public interest,
    convenience, and necessity.” 
    Id. § 254(b)(7).
    The FCC used
    that authority in 1997 to establish an additional principle of
    “competitive neutrality” among providers and technologies,
    requiring that specific universal support mechanisms “neither
    unfairly advantage nor disadvantage one provider over
    another.” First Universal Service Order, 12 FCC Rcd. at 8801.
    Section 214(e)(1), also enacted in 1996, spells out the
    competitive regime carriers’ eligibility and obligations with
    regard to effecting nationwide universal service coverage.
    Only a carrier “designated as an eligible telecommunications
    carrier” may receive universal-service support from the
    10
    Universal Service Fund. 47 U.S.C. § 214(e)(1). Any carrier
    that the FCC designates as eligible for support must,
    “throughout the service area for which the designation is
    received, . . . offer the services that are supported by Federal
    universal service support mechanisms.” 
    Id. As a
    mended in 1996, the Act also defines ETCs’ service
    areas. The Act provides that an ETC’s “service area” is the
    “area established . . . for the purpose of determining universal
    service obligations and support mechanisms.” 
    Id. § 214(e)(5).
    B. The Transition to Modernized Universal Service
    When the FCC in 2011 recognized that the
    communications landscape had fundamentally changed and
    sought to overhaul its universal service scheme to include
    nationwide broadband coverage, it called on ETCs going
    forward to “offer broadband service in their supported area.”
    2011 Order, 26 FCC Rcd. at 17,667-68, 17,695. The FCC also
    began to revise the support mechanisms for ETCs providing
    those services. See 
    id. at 17,673.
    Between 1996 and 2011,
    state boundaries defined the relevant “service areas” by default,
    so federal support for ETCs was calculated based on the cost
    of providing necessary services across the state. See 
    id. at 17,714.
    Under the new system, in contrast, ETCs would be
    designated on a census-block basis, and would receive federal
    subsidies based on a new cost-projection model; in some cases,
    the old landline-only ETCs signed up to continue to serve
    areas, but in others a new ETC would have to be selected via a
    competitive auction—for many census blocks in July 2018—
    to determine the most effective and efficient provider. 
    Id. at 17,725,
    17,727-29, 17,732-33; 2018 Public Notice at 3.
    In order to facilitate the rollout of universal broadband
    access without compromising existing universal landline
    service in high-need areas and to high-need individuals, the
    11
    FCC planned to stagger the phasing in of new requirements and
    the phasing out of old ones. See 2011 Order, 26 FCC Rcd. at
    17,727. The Commission decided that incumbent ETCs would
    retain preexisting obligations, at preexisting funding levels,
    until the FCC identified the replacement ETC provider that
    would bring a modernized universal service package to a
    specific area. See 
    id. Incumbent ETCs
    were in the best
    position to provide the basic landline service during the
    transition; after all, they were already doing it. See 2015 Order,
    31 FCC Rcd. at 6232.
    To explore ways that it might nevertheless minimize those
    interim obligations, the FCC included in its 2011 Order
    describing the ETC modernization a call for comment on
    whether there could or should be a “relaxation of . . . [ETC]
    voice service obligations” of incumbent providers pending
    completion of the transition. 2011 Order, 26 FCC Rcd. at
    18,063-64. The FCC wanted to identify areas where it might,
    without creating service gaps, excuse certain incumbent ETC
    landline obligations even before the regulatory transition was
    complete. 
    Id. at 18,064-65.
    (As noted above, the agency
    ultimately excused many such obligations, leaving landline-
    only ETCs with continued commitments in only a small
    fraction of the census blocks they once served.)
    In many states, incumbent ETCs—including Petitioners
    here—opted to renew their obligations, taking on new
    broadband requirements and concomitant funding awards
    newly calculated to support the modernized service. See Joint
    App’x (J.A.) 2129-30 (CenturyLink); 
    id. at 2131
    (AT&T). In
    those states, no incumbent ETC continues to bear any separate
    universal service obligation to maintain landline service. But
    in other states, the FCC has yet to select ETCs to provide
    modernized universal service. Hard-to-reach areas within
    12
    those states are where Petitioners retain the landline service
    obligations to which they object.
    C. The Challenged Orders
    Petitioners asked the Commission to be excused from their
    continued landline-only ETC obligations and funding by filing
    a request for blanket forbearance. See 2014 Order, 29 FCC
    Rcd. at 15,663. They also submitted comments urging the FCC
    to reinterpret parts of the Act to strictly limit ETC obligations
    so as to sunset those preexisting duties. 
    Id. Petitioners here
    challenge the FCC’s orders that only partially granted their
    forbearance request and kept their service obligations in certain
    census blocks where new ETCs have yet to be engaged. In
    those blocks, the FCC obligates incumbent ETCs to provide
    basic landline services pending upcoming auctions to select
    providers of modernized universal service.
    In the 2014 Order, the first of the two under review, the
    FCC granted USTelecom’s forbearance petition in part, halting
    enforcement of incumbent ETC obligations for three categories
    of census blocks: (1) low-cost blocks; (2) blocks served by an
    unsubsidized competitor that meets certain voice and
    broadband minima; and (3) blocks served by another ETC
    offering voice and broadband. See 
    id. at 15,663.
    The
    Commission reasoned that the services required under the
    modernized universal service obligation were already readily
    available in those categories of census blocks, so there was no
    reason to continue to subject incumbent ETCs to preexisting
    landline obligations there. 
    Id. at 15,665.
    As a consequence of the partial grant of forbearance,
    Petitioners have residual service obligations in only two
    categories of census blocks: high-cost and extremely high-cost
    census blocks where the incumbent ETC declined to (or could
    not) become the ETC for purposes of the modernization. See
    13
    
    id. at 15,664-65;
    2015 Order, 31 FCC Rcd. at 6211-12. In all
    of those census blocks, the FCC plans to select new ETCs but
    has yet to do so. See 2014 Order, 29 FCC Rcd. at 15,664-65.
    But the FCC deferred a final determination regarding continued
    landline-only ETC obligations for incumbents in those areas
    and asked for further comment. 
    Id. at 15,664-65,
    15,702.
    AT&T then petitioned this court for review of the 2014
    Order on the ground that the Commission had “adopted a rule”
    regarding the incumbent ETCs’ obligations in the residual
    areas. See Pet’rs’ Br., AT&T, Inc. v. FCC, No. 15-1038, Dkt.
    No. 15-57573 at 3 (June 15, 2015). The FCC moved for
    abeyance of that petition because the 2014 Order had adopted
    no such rule; indeed, it had not yet decided those issues and
    still had them under consideration. See FCC Motion to Hold
    Case in Abeyance, AT&T, Inc. v. FCC, No. 15-1038, Dkt. No.
    1560813 (July 2, 2015). In September 2015, this court granted
    the requested abeyance. See AT&T Inc. v. FCC, No. 15-1038,
    Dkt. No. 1571313 (D.C. Cir. Sept. 3, 2015) (per curiam order).
    In the wake of the FCC’s 2014 Order and our abeyance
    order, Petitioners submitted further comments to the
    Commission arguing that incumbent ETCs’ landline-only
    universal service obligations in remaining high-cost and
    extremely high-cost census blocks should be excused. See,
    e.g., J.A. 2132-38 (comments of AT&T). Particularly, they
    pointed to a subset of census blocks for which, based on the old
    formula, they did not receive much—or, in a rare case, perhaps
    any—high-cost support. See, e.g., J.A. 2136-37.
    In December 2015, the FCC issued another order, the
    second of the two now under review. That 2015 Order ruled
    on the remainder of USTelecom’s forbearance petition,
    denying the request for forbearance from incumbent ETCs’
    interim obligations in otherwise underserved high-cost and
    14
    extremely high-cost census blocks. 2015 Order, 31 FCC Rcd.
    at 6211-12. Recognizing, however, that there might be areas
    in which even maintaining existing landline service could be a
    hardship for incumbent ETCs, the FCC reiterated that it would
    entertain case-by-case forbearance petitions or applications for
    additional funding where providers could show a particularized
    need. 
    Id. at 6224,
    6229 n.440.
    In finalizing incumbent ETCs’ interim landline
    obligations, the FCC also declined to “reinterpret section
    214(e)(1) to require that [incumbent] carriers only provide
    voice services in areas where they are receiving support.” 
    Id. at 6227.
    Instead, the FCC cited prior orders interpreting the
    Act not to “require that all ETCs must receive support, but
    rather only that carriers meeting certain requirements be
    eligible for support.” 
    Id. (quoting In
    re High-Cost Universal
    Service Support, 23 FCC Rcd. 8834, 8847 (2008)); see 
    id. at 6227
    n.431. The agency discussed how “incumbent . . .
    carriers’ long history of providing service in the relevant
    service areas, coupled with the fact that they have already
    obtained the ETC designation necessary to receive universal
    service support to serve those areas, puts them in a unique
    position to maintain voice service as we transition fully” to the
    new system. 
    Id. at 6232.
    III. Discussion
    Petitioners challenge the 2014 and 2015 Orders as contrary
    to the Commission’s statutory authority. See 5 U.S.C.
    § 706(2)(C). If, as the FCC contends, the statutory provisions
    are “silent or ambiguous with respect to the specific issue,” this
    court defers to an agency’s interpretation that is “based on a
    permissible construction of the statute.” Chevron U.S.A., Inc.
    v. Nat. Res. Def. Council, 
    467 U.S. 837
    , 843 (1984). But “[i]f
    the intent of Congress is clear,” as Petitioners contend, the
    15
    reviewing court must “give effect to that unambiguously
    expressed intent.” 
    Id. at 842-43.
    Petitioners also challenge the FCC’s orders as “arbitrary,
    capricious, an abuse of discretion, or otherwise not in
    accordance with law.” 5 U.S.C. § 706(2)(A). While our
    review of such a claim is “highly deferential,” Nat’l Tel. Coop.
    Ass’n v. FCC, 
    563 F.3d 536
    , 541 (D.C. Cir. 2009), we require
    that the FCC at least “must examine” the relevant factors and
    data and articulate a “rational connection” between the record
    and the agency’s decision, Motor Vehicle Mfrs. Ass’n of U.S.,
    Inc. v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983)
    (second quotation from Burlington Truck Lines v. United
    States, 
    371 U.S. 156
    , 168 (1962)).
    We owe particular deference to interim regulatory
    programs involving some exigency, like the one at issue here.
    Rural Cellular 
    I, 588 F.3d at 1105-06
    ; MCI Telecomms. Corp.
    v. FCC, 
    750 F.2d 135
    , 141 (D.C. Cir. 1984). That added
    deference reflects the reality that, during a transition period, an
    agency must make “predictive judgments” and “certainty is
    impossible.” Rural Cellular 
    I, 588 F.3d at 1105
    ; see Melcher
    v. FCC, 
    134 F.3d 1143
    , 1151-52 (D.C. Cir. 1998). To that end,
    this court has been reluctant to interfere with an agency
    decision to freeze aspects of a preexisting regime for an interim
    period until a new program can be fully phased in—including
    in the context of the FCC’s comprehensive, high-cost universal
    service reform. Rural Cellular 
    I, 588 F.3d at 1099-1100
    , 1105
    (upholding an interim cap on existing subsidy payments to
    certain ETCs). Such interim measures must be accorded
    “[s]ubstantial deference” to permit the agency “to maintain the
    status quo so that the objectives of a pending rulemaking
    proceeding will not be frustrated.” MCI 
    Telecomms., 750 F.2d at 141
    ; see Rural Cellular 
    I, 588 F.3d at 1105-06
    . That
    substantial judicial deference also respects the agency’s
    16
    prerogative to dedicate its resources to “its top priority” of
    “ensuring that all regions of the nation have access to advanced
    telecommunications technology” without also “expending
    significant time and resources . . . updat[ing] the current cost
    model” that will soon be replaced. Vt. Pub. Serv. Bd. v. FCC,
    
    661 F.3d 54
    , 64-65 (D.C. Cir. 2011) (internal quotation marks
    omitted).
    The FCC’s interpretations of “its own orders and
    regulations” are also owed deference because of the agency’s
    superior knowledge of its own regulations. Cellco P’ship v.
    FCC, 
    700 F.3d 534
    , 544 (D.C. Cir 2012) (quoting MCI
    Worldcom Network Servs., Inc. v. FCC, 
    274 F.3d 542
    , 548
    (D.C. Cir. 2001)); see Auer v. Robbins, 
    519 U.S. 452
    , 461
    (1997).
    We first address Petitioners’ threshold argument that the
    court should not consider the 2015 Order at all, on the ground
    that it impermissibly supplies ex post justifications for de facto
    rules adopted by the 2014 Order. Second, we evaluate the
    FCC’s statutory authority to act as it did. Finally, we turn to
    Petitioners’ argument that the challenged Orders are arbitrary
    and capricious.
    A. The Procedural Permissibility of the 2015 Order
    Petitioners contend that the 2015 Order impermissibly
    supplies ex post rationales for the 2014 Order, review of which
    should be confined to the reasons stated therein. A practical
    consequence of the 2014 Order’s partial grant of blanket
    forbearance was to leave in place some incumbent ETCs’
    landline-only obligations in a fraction of high-cost and
    extremely high-cost census blocks. Petitioners contend that the
    2014 Order thus established a de facto non-forbearance rule
    with respect to those remaining, unaddressed census blocks.
    As a result, they believe that we should look only to the reasons
    17
    supplied in the 2014 Order and disregard the 2015 Order’s
    reasons for retaining service obligations in those census blocks.
    The FCC says its 2014 Order did not purport to pass on the
    elements of the petition that the agency ultimately denied in the
    2015 Order. We are mindful that the agency’s reading “must
    be given controlling weight unless it is plainly erroneous or
    inconsistent.” Stinson v. United States, 
    508 U.S. 36
    , 45 (1993)
    (quoting Bowles v. Seminole Rock & Sand Co., 
    325 U.S. 410
    ,
    414 (1945)).
    The 2014 Order is limited to granting the forbearance
    petition “in part” and only “to the extent described”; it nowhere
    denied any part of the petition. See 2014 Order, 29 FCC Rcd.
    at 15,702 ¶ 167. The text of the 2014 Order acknowledged that
    the “result of [its] limited forbearance” was that incumbent
    carriers retained existing obligations in the remaining census
    blocks. 
    Id. at 15,664
    & n.117. At the same time, the possibility
    of additional “forbearance or other relief . . . where forbearance
    was not granted” by the 2014 Order “remain[ed] under active
    consideration before the agency.” Public Notice, Wireline
    Competition Bureau Releases List of Census Blocks Where
    Price Cap Carriers Still Have Federal High-Cost Voice
    Obligations, 30 FCC Rcd. 7417, 7419 ¶ 5 & n.12 (2015); FCC
    Motion for Leave to Seek to Hold Case in Abeyance, AT&T,
    Inc. v. FCC, No. 15-1038, Dkt. No. 1560810 at 2 (July 2,
    2015); see In re Lifeline and Link Up Reform and
    Modernization, 30 FCC Rcd. 7818, 7864 & n.261 (2015).
    The FCC’s position that the 2014 Order was not its last
    word on the forbearance petitions is buttressed by the agency’s
    statutory time window to respond to USTelecom’s forbearance
    petition, which remained open when the Commission issued its
    2014 Order. See AT&T Inc. v. FCC, No. 15-1038, Dkt. No.
    1571313 at 2 (D.C. Cir. Sept. 3, 2015) (per curiam order).
    18
    Under Section 10(c) of the Act, the agency has up to one year
    plus ninety days to respond to a petition for forbearance. 47
    U.S.C. § 160(c). The timing of the 2014 Order, only a few
    months after the petition’s filing, supports the agency’s
    characterization of its actions: The agency dealt with part of
    the petition when it still had ample time—until January 4,
    2016—to deal with the rest of it, all of which it would handle
    before the deadline.      See FCC Motion to Hold Case in
    Abeyance, AT&T, Inc. v. FCC, No. 15-1038, Dkt. No. 1560813
    at 2 (July 2, 2015).
    The FCC’s view of its own, multi-stage action is the
    natural way to understand the Commission’s actions. As a
    consequence, we consider the 2014 and 2015 Orders.
    B. The Statutory Permissibility of the Interim Regulatory
    Regime
    Petitioners challenge the interim regime as contrary to
    various provisions of the Communications Act that they argue
    compel certain sums of federal funding not offered during this
    transition period.
    1. Section 214(e)(1): “ETCs shall offer the
    services that are supported”
    Petitioners urge that the FCC’s interim regime violates
    Section 214(e)(1). That section provides that an ETC “shall be
    eligible to receive universal service support in accordance with
    section 254 . . . and shall, throughout the service area for which
    the designation is received . . . offer the services that are
    supported by Federal universal service support mechanisms
    under section 254(c).” 47 U.S.C. § 214(e). The interim regime
    runs afoul of that requirement, say Petitioners, by leaving in
    place service obligations that are not financially “supported”
    within the meaning of the statute.
    19
    Petitioners assert that the only permissible way to read “the
    services” that are “supported” is as requiring the FCC to dole
    out a satisfactory sum for each essential service that an ETC
    provides in a specific location. Under that reading, incumbent
    ETCs are not adequately funded under the interim scheme
    because funding levels are not determined by the cost to
    providers of supplying a particular high-cost service.
    The Commission, in contrast, reads “services that are
    supported” to refer more generally to “the types of services that
    ETCs must provide . . . rather than to instances of service for
    which a carrier receives support.” Resp’t Br. 38. That is, the
    agency interprets the provision “to refer broadly to the services
    that the Commission establishes as universal service, rather
    than only referring to services insofar as an ETC actually
    receives universal service support for its provision of them.”
    2015 Order, 31 FCC Rcd. at 6228. The FCC describes the
    relevant “type of service” as “voice telephony,” and takes it to
    include all universal service programs—whether high-cost
    landline support, or other programs that service schools,
    hospitals, and libraries, or indigent individuals. See Resp’t Br.
    38; 2015 Order, 31 FCC Rcd. at 6227-29. The FCC thus
    contends that incumbent ETCs must continue to provide “the
    services that are supported” under the interim regime because
    those ETCs are providing essential voice services and receive
    funding for those services generally, even if a particular high-
    cost service is not guaranteed to be a breakeven proposition for
    providers in each and every census block. 2015 Order, 31 FCC
    Rcd. at 6228-29.
    The FCC’s reading does not conflict with Section
    214(e)(1)’s general command that ETCs offer “services that are
    supported.” In fact, it is supported by the statute’s text. A
    cross-reference in Section 214(e)(1) tethers its definition of
    “the services that are supported” as it appears in Section
    20
    214(e)(1) to Section 254(c), which uses the same phrase to
    identify, as a general matter, the types of services required to
    be universally provided (as determined by the Commission)—
    those that have, like voice telephony, for example, “been
    subscribed to by a substantial majority of residential
    customers.” See 47 U.S.C. § 254(c)(1). The legislative history
    provides further support for the FCC’s reading by glossing
    ETC obligations to include all of “the services included in the
    definition of universal service,” S. Rep. No. 104-230, at 141
    (1996) (Conf. Rep.), while making clear that, from a funding
    perspective under Section 214(e)(1), an ETC need only “be
    eligible to receive support payments, if any, established by the
    Commission or a State to preserve and advance universal
    service,” 
    id. at 129
    (emphases added). The text and history of
    Section 214(e) thus suggest that “the services that are
    supported” can, consistent with the FCC’s reading, refer to the
    whole package of voice services and broadly require eligibility,
    not services as priced and paid for à la carte for each distinct
    area.
    Considering the 2011 Order setting out the FCC’s planned
    overhaul of its universal service program, the Tenth Circuit has
    held that that this same phrase is, at a minimum, open to the
    FCC’s interpretation. See In re FCC 11-161, 
    753 F.3d 1015
    ,
    1088 (10th Cir. 2014); see also Tex. Office of Pub. Util.
    Counsel v. FCC, 
    183 F.3d 393
    , 412 (5th Cir. 1999) (approving
    the agency’s reading of the statute, requiring that ETCs be
    “eligible” for funding, not that they receive “support . . . equal
    [to] the actual costs incurred”). We, too, find the FCC’s
    interpretation to be reasonable.
    The interim measure, then, satisfies Section 214(e)(1)
    because incumbent ETCs receive and remain eligible for
    federal funding.    Incumbent ETCs continue to receive
    considerable high-cost support, both in the form of frozen
    21
    funding for interim landline ETC service and subsidies
    calculated by the new model for broadband-inclusive service.
    2015 Order, 31 FCC Rcd. at 6229. In addition, incumbent
    ETCs can receive various forms of supplemental funding from
    the FCC or states based on a particularized showing of need
    arising from the provision of high-cost landline service during
    the regulatory transformation. See 
    id. at 6229
    & n.440, 6231-
    32; In re FCC 
    11-161, 753 F.3d at 1088
    . Therefore, under the
    Commission’s reasonable reading, Petitioners are eligible for
    funding, as Section 214(e) requires.
    2. Section 214(e)(5): “service areas”
    Petitioners also challenge the interim scheme as contrary
    to the Act’s definition of “service area.” Under the Act, a
    “service area” is “a geographic area established . . . for the
    purpose of determining universal service obligations and
    support mechanisms.” 47 U.S.C. § 214(e)(5). Petitioners
    argue that, “[b]ecause [old] statewide service areas no longer
    serve ‘the purpose of determining . . . support mechanisms,’”
    the FCC cannot maintain incumbent ETC service obligations
    on a statewide basis. Pet’rs’ Reply Br. 10 (quoting 47 U.S.C.
    § 214(e)(5)) (ellipsis in original).
    But the old “service areas” remain the touchstone for
    incumbent ETCs’ frozen funding for interim landline-only
    service. The FCC calculates the frozen sum with reference to
    statewide service areas because funding remains a product of
    the old formula, based on service across the state. Other ETC
    funding, too, is available on a statewide basis, such as targeted
    service for low-income individuals. 2015 Order, 31 FCC Rcd.
    at 6214, 6225. As a result, statewide service areas remain a
    reference point for “determining . . . support mechanisms” and
    obligations, in keeping with the statute.
    22
    C.    The Interim Regime’s Reasonableness & The FCC’s
    Reasons
    Petitioners further argue that, in retaining preexisting
    obligations, the FCC failed to adequately balance the several
    universal service principles set forth in Section 254(b). Those
    principles are: (1) quality and “affordab[ility]” of services; (2)
    nationwide access to “advanced telecommunications”; (3)
    nationwide access at “reasonably comparable” rates in high-
    cost areas; (4) “equitable and nondiscriminatory
    contribution[s]” by carriers; (5) “sufficient” funding for
    carriers; (6) access for public services like “schools . . . , health
    care providers, and libraries”; and (7) “other principles,” which
    the FCC has specified to include “competitive neutrality.” 47
    U.S.C. § 254(b); First Universal Service Order, 12 FCC Rcd.
    at 8801. Petitioners frame the FCC’s failure as, first, an
    unexplained vindication and impermissible prioritization of
    “universal access,” second, neglect of the principle of
    “competitive neutrality,” and, third, misreading and so failing
    to fulfill the requirement of “sufficient” funding. We address
    each argument in turn.
    1. Universal Access
    Petitioners criticize the FCC’s chosen means of preserving
    “universal access” under Section 254(b) in two respects.
    Petitioners contend that the FCC did not explain how
    continuing their obligations helped to fulfill the Act’s
    universal-access objective. And they assert that the FCC
    designed its scheme in violation of Section 254(b) because it
    pursued universal access at the expense of the other factors
    Section 254(b) lists.
    Petitioners contend that retaining ETC designations and
    obligations is unnecessary to protect service to consumers. But
    the agency found that, for now, some consumers need residual
    23
    universal landline service. See 2015 Order, 31 FCC Rcd. at
    6221-23, 6231. Before deciding to keep in place some of the
    incumbent ETCs’ obligations, the Commission analyzed
    Petitioners’ blanket forbearance proposal with reference to “the
    consumer protection goals identified in” the statute. 
    Id. at 6216.
    The FCC was particularly concerned whether, if ETC
    interim obligations were dropped, “consumer[s] living in high-
    cost or extremely high cost census blocks . . . will continue to
    have access to voice service at reasonably comparable rates.”
    
    Id. at 6217.
    “[N]o other proposals” for interim regulation, the
    FCC concluded, “would provide assurance that [those]
    consumers will continue to have access to voice service at
    reasonably comparable rates” during the transition. 
    Id. at 6233.
    And data that Petitioners submitted to the agency suggested
    that nearly “one-quarter of U.S. households rely on traditional
    switched service,” 
    id. at 6162,
    such that in the absence of
    interim landline ETC obligations, a significant number of
    otherwise       underserved     individuals      might      lose
    telecommunications service altogether.            The agency
    determined, then, that retaining incumbent ETCs’ residual
    obligations in high-cost census blocks would “serve the public
    interest and advance universal service.” 
    Id. at 6231.
    The agency also invoked the admittedly imprecise
    predictive task of projecting how best to “protect consumers”
    and ensure “just and reasonable” market rates during the
    uncertainty of a complex regulatory transition. 
    Id. at 6218,
    6221-22. This court has “repeatedly held” that difficulties of
    predicting the results of a regulatory shift are a “standard and
    accepted” justification for such a “temporary rule.” Rural
    Cellular 
    I, 588 F.3d at 1105-06
    (citing Competitive Telcomms.
    Ass’n v. FCC, 
    309 F.3d 8
    , 14 (D.C. Cir. 2002)). The FCC was
    not confident that it could “reasonably predict that customers
    will continue to be served with voice service at reasonably
    comparable rates if the [incumbent ETC] carrier no longer has
    24
    this obligation.” 2015 Order, 31 FCC Rcd. 6221. As such, the
    agency’s decision to hold those obligations in place
    temporarily is reasonable and adequately reasoned.
    Petitioners further assert that, even if the FCC found a
    demonstrated need to retain the obligations, the way the
    Commission designed its interim regime fails to account for
    Section 254(b) factors other than universal access. The FCC
    did, however, address the other factors. For example, as
    discussed below, it addressed both “competitive neutrality” and
    “sufficient” funding before it determined “on balance” how to
    advance the statute’s aims. 
    Id. at 6231-33.
    The record
    therefore does not support Petitioners’ claim that the FCC’s
    consideration began and ended with the universal-service
    objective.
    2. Competitive Neutrality
    Petitioners further argue that the 2015 Order ignores and
    therefore violates the principle of “competitive neutrality” in
    its differential treatment of the responsibilities and funding of
    incumbent ETCs and newcomers. Petitioners give too little
    credit to the FCC’s reasoning and balancing.
    “Competitive neutrality” stands for the idea that “universal
    support mechanisms and rules neither unfairly advantage nor
    disadvantage one provider over another, and neither unfairly
    favor nor disfavor one technology over another.” See First
    Universal Service Order, 12 FCC Rcd. at 8801. We have held
    that competitive neutrality “only prohibits the Commission
    from treating competitors differently in ‘unfair’ ways,” and not
    from according different treatment to competitors whose
    circumstances are materially distinct. Rural Cellular 
    I, 588 F.3d at 1104
    . Of particular relevance here, “competitive
    neutrality” does not require the “same levels of support to all
    ETCs.” 
    Id. at 1105.
    In Rural Cellular I, we rejected a
    25
    challenge to a cap on federal funding for only one category of
    ETCs, recognizing that “targeting only [one type of ETC] was
    hardly unfair” in view of the agency’s findings that those ETCs
    had disproportionately drawn on federal resources. 
    Id. at 1104.
    The 2014 and 2015 Orders holding constant certain service
    obligations and funding mechanisms similarly rest on the
    FCC’s findings that incumbent ETCs remained in the best
    position, given existing practice and infrastructure, to maintain
    existing services, at existing funding levels. See 2015 Order,
    31 FCC Rcd. at 6232-34. In concluding that these carriers are
    in “a unique position to maintain voice service as we transition
    fully,” the agency relied on their “long history of providing
    service in the relevant service areas, coupled with the fact that
    they have already obtained the ETC designation necessary to
    receive universal service support to serve those areas.” 
    Id. at 6232.
    The FCC thus took account of how “new ETCs are
    differently situated than incumbent ETCs,” 
    id. at 6234,
    particularly with respect to incumbent ETCs’ “history” and
    their ability to continue to “serv[e] customers with voice
    services.” 
    Id. at 6233.
    The agency then reasonably concluded
    that, for a small subset of census blocks during a limited,
    transitional period, “the benefits of maintaining voice service”
    in terms of consumer access “outweigh . . . concerns” about
    competitive neutrality. 
    Id. at 6232.
    The Commission also offered additional funding for
    incumbent ETCs as needed. In Rural Cellular I, we noted the
    availability of such additional funding as a mechanism to
    ameliorate on a case-by-case basis any potentially “unfair”
    effects. Rural Cellular 
    I, 588 F.3d at 1105
    (“[T]o the extent a
    [carrier affected by the cap] believes it should be entitled to
    greater per-line high-cost support than the amount disbursed
    under the cap, the Order permits [it] to obtain an exception
    upon ‘fil[ing] cost data.’”) (alteration in original). Here, the
    26
    FCC has provided for additional funding on a case-by-case
    basis for any ETCs that find they require more support. 2015
    Order at 6229 n.440. That safety valve provides additional
    assurance that the scheme will not, in practice, be “unfair” to
    incumbents. The FCC thus identified adequate grounds for
    distinguishing between incumbent ETCs and new ones and, by
    providing for additional funding, ensured that incumbents
    would not be left with an “unfair” burden in any service area.
    In advancing its policy priorities to serve the public
    interest, convenience, and necessity, the FCC may, so long as
    it explains itself, determine how to account for the various
    guiding principles in Section 254(b). See Fresno Mobile
    Radio, Inc. v. FCC, 
    165 F.3d 965
    , 971 (D.C. Cir. 1999). The
    FCC here met its obligation to consider competitive neutrality
    as one among several principles.
    3. “Sufficient” Funding
    Finally, Petitioners assert that the FCC failed to ensure
    “sufficient” funding for incumbent ETCs, or at least that its
    reasoning on this point was inadequate.
    We start from the premise that the FCC is entitled to
    deference about what constitutes “sufficient” funding. Under
    Section 254(b)(5), the Commission is responsible for
    developing “specific, predictable and sufficient . . .
    mechanisms to preserve and advance universal service.” 47
    U.S.C. § 254(b)(5). This obligation overlaps with Section
    254(e)’s requirement that the Commission establish “explicit
    and sufficient” funding for ETCs. 
    Id. § 254(e).
    “Since the
    principles outlined use ‘vague, general language,’ courts have
    analyzed language in § 254(b) under Chevron step two.” Rural
    Cellular 
    I, 588 F.3d at 1101-02
    (citing 
    Chevron, 467 U.S. at 843
    ); see also In re FCC 
    11-161, 753 F.3d at 1055
    ; Tex. Office
    of Pub. Util. 
    Counsel, 183 F.3d at 425-26
    . So, too, for Section
    27
    254(e). See Tex. Office of Pub. Util. 
    Counsel, 183 F.3d at 425
    -
    26. Our role is to consider whether the agency’s interpretation
    is “a permissible construction” and to uphold it so long as it is
    reasonable, even in the face of “‘other reasonable, or even more
    reasonable, views.’” Rural Cellular 
    I, 588 F.3d at 1102
    (quoting AT&T Corp. v. FCC, 
    220 F.3d 607
    , 621 (D.C. Cir.
    2000)).
    Examined with appropriate deference, the FCC’s
    interpretation defeats Petitioners’ claim that the statute
    mandates federal funding at a level that would ensure an
    attractive business case for providers in each and every census
    block. To the contrary, Section 254 does not compel any
    particular level of funding to count as “sufficient” under the
    Act. Rural Cellular 
    I, 588 F.3d at 1103
    .
    In fact, we have held—contrary to Petitioners’ position—
    that “sufficient” funding under Section 254(b)(5) is not merely
    a means to sweeten the pot for providers. Rather, it “seeks to
    strike an appropriate balance between the interests of”
    consumers and industry. 
    Id. at 1102.
    Too-ample funding or
    compensation of carriers may even “itself violate the
    sufficiency requirements of the Act” by so “detracting from
    universal service by causing rates unnecessarily to rise, thereby
    pricing some consumers out of the market.” 
    Id. at 1103
    (quoting 
    Alenco, 201 F.3d at 620
    (alteration omitted)); see
    Qwest Commc’ns Int’l Inc. v. FCC, 
    398 F.3d 1222
    , 1234 (10th
    Cir. 2005).
    The FCC’s mandate to balance carrier compensation and
    consumer access is reflected in the statutory structure of the
    “sufficient” funding requirement under Section 254(b)(5): The
    sufficiency of funding is but one of several enumerated
    principles that the FCC must consider in devising universal
    service mechanisms. See 47 U.S.C. § 254(b). It makes good
    28
    sense that the FCC has considered funding’s sufficiency “in
    light of the other statutory directives.” In re FCC 
    11-161, 753 F.3d at 1060
    . And here the Commission has, in keeping with
    our guidance in Rural Cellular 
    I, 588 F.3d at 1103
    , set
    “sufficient funding” levels that also take account of consumer
    access and affordability. 2015 Order, 31 FCC Rcd. at 6217,
    6233. As a consequence, the FCC’s conclusion that funding
    may fall short of full compensation in particular areas and still
    be “sufficient” is faithful to Section 254(b)(5) of the Act.
    Petitioners do not identify any salient difference between
    “specific” and “sufficient” funding for the purposes of Section
    254(b)(5) and Section 254(e)’s parallel mandate that ETC
    funding be “explicit and sufficient.” As a consequence, we
    conclude that the existing subsidies also satisfy Section 254(e)
    of the Act.
    Petitioners further contend that, even accepting the FCC’s
    interpretation of funding “sufficiency” under Section 254, the
    Commission failed to justify the particular funding levels held
    in place here. However, it weighs substantially in our thinking
    that the agency is not writing “on a blank slate, but rather
    against the backdrop of a decades-old regulatory system.”
    2011 Order, 26 FCC Rcd. at 17,727. The FCC is keeping this
    existing program in place during a temporary period of
    regulatory transition. See Rural Cellular 
    I, 588 F.3d at 1105
    ;
    
    Melcher, 134 F.3d at 1151-52
    ; MCI 
    Telecomms., 750 F.2d at 141
    . The agency’s obligation to reiterate the basis of the
    scheme being phased out is therefore somewhat relaxed,
    especially in light of the agency’s prerogative not to “expend[]
    significant time and resources”—so as to potentially “impede”
    its ability to fulfill its statutory directives—on a program that
    will soon be replaced. Vt. Pub. Serv. 
    Bd., 661 F.3d at 64-65
    ;
    see MCI 
    Telecomms., 750 F.2d at 141
    . The Commission
    provided in the 2015 Order for continued “eligib[ility] to
    29
    receive high-cost support” that it believed would suffice. See
    2015 Order, 31 FCC Rcd. at 6233. It also noted that incumbent
    “carriers have not provided enough information beyond
    generalized assertions . . . that the support they receive . . . is
    insufficient.” Id.; see also 
    id. at 6222-23.
    Under the agency’s
    modest obligation to re-justify its existing subsidy program, its
    rationale suffices.
    If Petitioners’ mandate in some census blocks proves, at
    the end of the day, to be unnecessary, or underfunded and
    therefore untenable, the FCC has expressly taken the potential
    for such hardships into account. As discussed above, the
    interim regime keeps in place mechanisms for relief that
    together can ensure “sufficient” funding, including “case-by-
    case” forbearance by the FCC (or the state), 2015 Order, 31
    FCC Rcd. at 6224; see also 2011 Order, 26 FCC Rcd. at
    18,064-65, and case-by-case additional funding from the FCC
    (or the state), 2015 Order, 31 FCC Rcd. at 6229 n. 440. We
    therefore affirm the agency’s reasoned conclusion that its
    general but limited forbearance, plus the continued availability
    of continued case-by-case supplemental funding or
    forbearance answered industry concerns.
    IV. Conclusion
    The FCC is shepherding the nation’s communications
    infrastructure into the Twenty-First Century, even as it seeks to
    ensure that hard-to-serve areas and individuals retain access at
    least to basic landline service. The Commission is owed
    deference as it temporarily holds in place preexisting
    requirements until the new systems are up and running. And
    the FCC has provided for sufficient case-by-case relief if and
    when Petitioners establish a need for it. There is no defect in
    the FCC’s challenged Orders. We therefore deny the petitions.
    So ordered.
    

Document Info

Docket Number: 15-1038

Citation Numbers: 886 F.3d 1236

Filed Date: 4/6/2018

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (18)

qwest-communications-international-inc-v-federal-communications , 398 F.3d 1222 ( 2005 )

Texas Office of Public Utility Counsel v. Federal ... , 183 F.3d 393 ( 1999 )

Compet Telecom Assn v. FCC , 309 F.3d 8 ( 2002 )

At&T Corp. v. Federal Communications Commission , 220 F.3d 607 ( 2000 )

Melcher v. Federal Communications Commission , 134 F.3d 1143 ( 1998 )

Alenco Comm v. FCC , 201 F.3d 608 ( 2000 )

Rural Cellular Ass'n v. Federal Communications Commission , 588 F.3d 1095 ( 2009 )

National Telephone Cooperative Ass'n v. Federal ... , 563 F.3d 536 ( 2009 )

Vermont Public Service Board v. Federal Communications ... , 661 F.3d 54 ( 2011 )

Fresno Mobile Radio, Inc. v. Federal Communications ... , 165 F.3d 965 ( 1999 )

MCI WrldCom Ntwrk v. FCC , 274 F.3d 542 ( 2001 )

Bowles v. Seminole Rock & Sand Co. , 65 S. Ct. 1215 ( 1945 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... , 103 S. Ct. 2856 ( 1983 )

mci-telecommunications-corporation-v-federal-communications-commission-and , 750 F.2d 135 ( 1984 )

Burlington Truck Lines, Inc. v. United States , 83 S. Ct. 239 ( 1962 )

Stinson v. United States , 113 S. Ct. 1913 ( 1993 )

Auer v. Robbins , 117 S. Ct. 905 ( 1997 )

Chevron U. S. A. Inc. v. Natural Resources Defense Council, ... , 104 S. Ct. 2778 ( 1984 )

View All Authorities »