Western Organization v. Ryan Zinke , 892 F.3d 1234 ( 2018 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued March 23, 2018                 Decided June 19, 2018
    No. 15-5294
    WESTERN ORGANIZATION OF RESOURCE COUNCILS AND
    FRIENDS OF THE EARTH,
    APPELLANTS
    v.
    RYAN ZINKE, IN HIS CAPACITY AS SECRETARY OF THE
    INTERIOR, ET AL.,
    APPELLEES
    Appeal from the United States District Court
    for the District of Columbia
    (No. 1:14-cv-01993)
    Eric F. Citron argued the cause for appellants. With him
    on the briefs were Thomas C. Goldstein and Richard E. Ayres.
    Sarah E. Harrington entered an appearance.
    Michael T. Gray, Attorney, U.S. Department of Justice,
    argued the cause for appellees. With him on the brief were
    Jeffrey H. Wood, Acting Assistant Attorney General, and Eric
    Grant, Deputy Assistant Attorney General.
    James Kaste, Deputy Attorney General, Office of the
    Attorney General for the State of Wyoming, Erik E. Petersen,
    Supervisory Attorney General, and Michael M. Robinson,
    2
    Senior Assistant Attorney General, were on the joint brief of
    intervenors the State of Wyoming, et al. in support of appellees.
    Margaret I. Olson, Assistant Attorney General, Office of the
    Attorney General for the State of North Dakota, and Andrew C.
    Emrich entered appearances.
    James M. Auslander and Peter J. Schaumberg were on the
    brief for amicus curiae National Mining Association in support
    of defendants-appellees and intervenors-appellees for
    affirmance of the District Court.
    Before: HENDERSON and SRINIVASAN, Circuit Judges, and
    EDWARDS, Senior Circuit Judge.
    Opinion for the Court by Senior Circuit Judge EDWARDS.
    Concurring opinion filed by Circuit Judge HENDERSON.
    Concurring opinion filed by Senior Circuit Judge
    EDWARDS.
    EDWARDS, Senior Circuit Judge: The Mineral Leasing
    Act, 30 U.S.C. § 181 et seq. (2012), and the Federal Land
    Policy and Management Act of 1976, 43 U.S.C. § 1701 et seq.,
    authorize the Secretary of the Department of the Interior
    (“Secretary” or “Department”) to lease rights to mine coal on
    public lands. In 1979, acting through the Bureau of Land
    Management (“BLM”), the Secretary published a
    programmatic environmental impact statement (“PEIS”) for a
    Federal Coal Management Program (“Program”). The PEIS
    was issued pursuant to the requirements of the National
    Environmental Policy Act (“NEPA”), 42 U.S.C. § 4332(2)(C),
    and it reflected the Secretary’s proposed approach for
    exercising his statutory authority. In July of that year, the
    Department issued a Record of Decision adopting the Program.
    3
    BLM then promulgated regulations establishing the Program’s
    procedures. It amended those regulations in 1982, and last
    issued a supplement to the Program’s PEIS in 1985.
    In 2014, Appellants Western Organization of Resource
    Councils and Friends of the Earth brought suit in the District
    Court, seeking an order compelling the Secretary to update the
    Program’s environmental impact statement. The District Court
    granted the Secretary’s motion to dismiss. In so doing the court
    held that the Secretary had “no duty to supplement the 1979
    programmatic EIS for the federal coal management program
    because there is no remaining or ongoing major federal action
    that confers upon them a duty to do so.” W. Org. of Res.
    Councils v. Jewell, 
    124 F. Supp. 3d 7
    , 13 (D.D.C. 2015).
    Appellants timely appealed to this court.
    Appellants claim that the Secretary’s failure to supplement
    the Program’s PEIS violates both NEPA and the
    Administrative Procedure Act (“APA”). Appellants note that
    when the Department issued amended regulations in 1982, “it
    reaffirmed that it retained an obligation under NEPA to revise
    or update the 1979 Program EIS when its assumptions,
    analyses and conclusions [were] no longer valid.” Appellants’
    Br. 2. Appellants point out that, since 1979, “tens of thousands
    of peer-reviewed scientific studies have identified the causes
    and consequences of continued atmospheric warming and
    showed that coal combustion is the single greatest contributor
    to the growing concentration of greenhouse gases in the
    atmosphere.” 
    Id. at 3.
    Given that these studies were not
    available when the Secretary issued the 1979 PEIS or the 1985
    supplement, Appellants contend that the Secretary is required
    to supplement its programmatic environmental analysis.
    The federal action establishing the Federal Coal
    Management Program was completed in 1979. And the
    4
    Secretary has not proposed to take any new action respecting
    the Program. In these circumstances, neither NEPA nor the
    APA requires the Secretary to update the PEIS for the Federal
    Coal Management Program. We therefore lack authority to
    compel the Secretary to do so. Accordingly, the judgment of
    the District Court is affirmed.
    I.      BACKGROUND
    A. Statutory and Regulatory Background
    1. The National Environmental Policy Act
    NEPA requires all federal agencies to prepare and include
    an environmental impact statement (“EIS”) in “every
    recommendation or report on proposals for . . . major Federal
    actions significantly affecting the quality of the human
    environment.” 42 U.S.C. § 4332(2)(C). As part of this process,
    agencies must “take a ‘hard look’ at their proposed actions’
    environmental consequences in advance of deciding whether
    and how to proceed.” Sierra Club v. U.S. Army Corps of
    Eng’rs, 
    803 F.3d 31
    , 37 (D.C. Cir. 2015). This ensures that
    agencies “consider every significant aspect of the
    environmental impact of a proposed action,” and “inform the
    public” of their analysis. Balt. Gas & Elec. Co. v. Nat. Res. Def.
    Council, Inc., 
    462 U.S. 87
    , 97 (1983).
    The Council on Environmental Quality (“CEQ”),
    established by NEPA, has authority to interpret the statute and
    has promulgated regulations to guide federal agencies in
    complying with its mandate. Dep’t of Transp. v. Pub. Citizen,
    
    541 U.S. 752
    , 757 (2004). The CEQ regulations articulate two
    principles that govern the dispute in this case.
    5
    First, the regulations require an environmental analysis to
    account for the cumulative impacts of an action “when added
    to other past, present, and reasonably foreseeable future
    actions.” 40 C.F.R. § 1508.7 (2017); see also 
    id. § 1508.25(a)(2).
    One way agencies can satisfy this requirement
    is by “tiering” their analyses. Tiering allows an agency to meet
    its NEPA obligations in steps: First, the agency publishes a
    PEIS assessing the entire scope of a coordinated federal
    program. See Nevada v. Dep’t of Energy, 
    457 F.3d 78
    , 91 (D.C.
    Cir. 2006). The PEIS ensures that the agency assesses “the
    broad environmental consequences attendant upon a wide-
    ranging federal program.” 
    Id. at 92.
    The agency later
    supplements that programmatic analysis with narrower EISs
    analyzing the incremental impacts of each specific action taken
    as part of a program. 
    Id. at 91.
    Second, the CEQ regulations specify when agencies must
    update their environmental analyses in response to changed
    conditions. Specifically, agencies must prepare a supplemental
    impact statement when there exist “significant new
    circumstances or information relevant to environmental
    concerns and bearing on the proposed action or its impacts.” 40
    C.F.R. § 1502.9(c)(1)(ii) (2017).
    Thus, to meet its NEPA obligations, an agency must
    consider the cumulative impacts of a proposed action, see 
    id. § 1508.25(a),
    and generally cannot rely on an outdated analysis
    to support its actions, see 
    id. § 1502.9(c)(1)(ii).
    2.    The Federal Coal Management Program
    The Mineral Leasing Act empowers the Department to
    lease rights to coal on public lands. 30 U.S.C. § 181 et seq.
    Prior to 1973, the Department exercised this power in a
    “reactive” manner, processing lease applications on a “case-by-
    6
    case basis.” Dep’t of the Interior, BLM, Final Envtl. Statement,
    Fed. Coal Mgmt. Program, 1-9 (1979), [hereinafter “PEIS”],
    reprinted at J.A. 113, 142. The agency gave “little
    consideration” to “total coal reserves under lease or to the need
    for additional leasing, and environmental impacts . . . were not
    addressed.” 
    Id. But in
    the 1970s, the Secretary of the Interior
    decided that the better course would be to develop a
    comprehensive planning system for future coal leasing. See 
    id. at 1-9–1-10,
    J.A. 142–43.
    To achieve this goal, the Secretary undertook a number of
    administrative actions that eventually resulted in adoption of a
    Federal Coal Management Program. Initially, the Department
    commenced notice and comment rule making on “the
    procedures that the Secretary of the Interior will use to carry
    out his authority to manage Federal coal.” Proposed
    Rulemaking, Coal Mgmt., 44 Fed. Reg. 16,800, 16,800 (March
    19, 1979). The Secretary’s “preferred program” allocated land
    for leasing based on analysis of national and regional coal
    demand. See PEIS at 3-2–3-3, J.A. 262–63. It included a
    planning system to decide which areas would be listed for coal
    production, a system for evaluating the national demand for
    coal, and procedures for conducting sales, issuing and
    enforcing leases, and complying with the agency’s NEPA
    duties. See 
    id. In 1979,
    the agency issued a PEIS to support its proposal.
    See PEIS, J.A. 113. The PEIS analyzed the Secretary’s
    preferred program, as well as several alternatives for a federal
    coal management plan. These included no new federal leasing;
    state determination of leasing levels; and emergency leasing
    only, among others. See 
    id. at v,
    J.A. 120. The PEIS considered
    the physical, ecological, socioeconomic, transportation, and
    energy impacts of the various alternatives. As part of this
    analysis, the agency acknowledged that emissions resulting
    7
    from coal mining and combustion could lead to increased
    atmospheric carbon dioxide, and explained that “there are
    indications that the rising CO2 levels in the atmosphere could
    pose a serious problem, commonly referred to as the
    greenhouse effect.” 
    Id. at 5-88,
    J.A. 486. It addressed carbon
    dioxide as a “potential pollutant,” 
    id., and predicted
    increased
    levels of emissions from coal production under the proposed
    alternatives, 
    id. at 5-107,
    J.A. 505. The agency ultimately
    stated that “there are uncertainties about the carbon cycle, the
    net sources of carbon dioxide in the atmosphere, and the net
    effects of carbon dioxide on temperature and climate,” 
    id. at 5-
    88, J.A. 486, and called for further study of the “impacts of
    increased coal utilization,” 
    id. at 5-107,
    J.A. 505.
    In July 1979, the Department officially adopted the
    Federal Coal Management Program. It published a two-part
    document approving the Secretary’s preferred program and
    discussing its rationale. See Department of the Interior,
    Secretarial Issue Document, Fed. Coal Mgmt. Program
    [hereinafter “ROD”], reprinted at J.A. 1391. This document
    served as the Record of Decision for the Program.
    The Secretary additionally promulgated a final rule setting
    forth the Program procedures. Coal Mgmt.; Federally Owned
    Coal, 44 Fed. Reg. 42,584 (July 19, 1979). The 1979 rule
    detailed the steps that BLM would take to implement the
    Program, and it also set forth the circumstances in which the
    PEIS was to be updated. 
    Id. at 42,616–20.
    The rule specified
    that the Department would supplement its environmental
    analysis if the Secretary determined that regional production
    goals and leasing targets “vary significantly from those
    analyzed,” or that the available tracts may “generate
    significantly different levels or types of environmental impacts
    than were anticipated” in the most current PEIS. 
    Id. (previously codified
    at 43 C.F.R. § 3420.3–4).
    8
    In 1982, the Secretary issued another rule purporting to
    “eliminate burdensome, outdated . . . provisions of the existing
    coal management regulations.” Amendments to Coal Mgmt.
    Program Regulations, 47 Fed. Reg. 33,114, 33,114 (July 30,
    1982). Because the rule redefined the goal for how leasing
    targets should be set, a number of commenters argued that the
    proposed rule constituted a “new program” and thus required
    its own EIS. See 
    id. The Secretary
    responded that an
    environmental assessment had been performed and it had been
    determined that no new EIS was required. See 
    id. at 33,115.
    The 1982 rule removed the provision that had been
    included in the 1979 rule addressing the procedures for
    updating or revising the PEIS. See 
    id. In response
    to comments
    suggesting that the deletion would demonstrate a lack of
    commitment to protecting the environment, the Secretary
    explained that, “[r]egardless of whether this provision [was]
    deleted or retained, the Department must revise or update the
    Program EIS when its assumptions, analyses and conclusions
    are no longer valid.” 
    Id. The Secretary
    explained further that,
    because “[t]he exact procedures necessary for compliance with
    [NEPA] at some future time are . . . difficult to predict,” the
    Department decided to delete the provision despite
    “recognizing that its obligations under [NEPA] remain
    unchanged.” 
    Id. In 1985,
    the Secretary published a supplemental PEIS for
    the Program. Fed. Coal Mgmt. Program, Final EIS Supplement
    (October 1985), reprinted at J.A. 1400. The supplemental PEIS
    claimed to “assess[] the environmental consequences of
    continuing the federal coal management program as modified
    [since the original PEIS].” 
    Id., J.A. 1404.
    The Secretary stated
    that supplementation was necessary because “[i]n the 6 years
    since the 1979 [PEIS] was published . . . economic and
    9
    environmental conditions have changed.” 
    Id. at 3,
    J.A. 1409.
    The supplemental PEIS predicted that continued coal leasing
    would have no long-term impacts on air quality. See 
    id. at 319,
    J.A. 1436.
    Although the Federal Coal Management Program has been
    modified in various ways over the years, the 1979 regulations
    and ROD largely remain in effect. Through the BLM, the
    Secretary continues to run the Program and make leasing and
    general programmatic management decisions – including how
    many, where, and to whom leases should be granted.
    In administering the Program, the Department continues to
    engage in NEPA-required environmental analysis. Each lease
    issued under the Program represents a new “federal action.”
    The Department prepares a specific EIS or environmental
    assessment for each lease before it is approved. See 43 C.F.R.
    § 3425.3 (2017). These project-specific EISs assess greenhouse
    gas emissions related to specific leases; however, they do not
    purport to consider the general climate effects of the national
    leasing Program as a whole. See CEQ, Final Guidance for Fed.
    Dep’ts & Agencies on Consideration of Greenhouse Gas
    Emissions & the Effects of Climate Change in NEPA Reviews,
    81 Fed. Reg. 51,866, 51,866–67 (Aug. 1, 2016), available at
    https://www.gpo.gov/fdsys/pkg/FR-2016-08-05/pdf/2016-
    18620.pdf; see also WildEarth Guardians v. Jewell, 
    738 F.3d 298
    , 309 (D.C. Cir. 2013).
    B. Procedural History
    Appellants Western Organization of Resource Councils
    and Friends of the Earth are nonprofit organizations whose
    members are concerned about the environmental and climate-
    related impacts of coal production and combustion. In 2014,
    Appellants sued the Secretary and other Department officials,
    10
    claiming that the Department’s failure to update the Federal
    Coal Management Program’s PEIS violates NEPA and the
    APA. The States of Wyoming and North Dakota and the
    Wyoming Mining Association intervened as defendants.
    The Secretary and other defendants before the District
    Court filed a motion to dismiss. The District Court granted the
    motion on August 27, 2015. W. Org. of Res. Councils, 124 F.
    Supp. 3d 7. The District Court held that, because the Program
    was established and the Department had not proposed to take
    any new action respecting the Program, the Department had no
    obligation to prepare a new or supplemental PEIS. See 
    id. at 12–13.
    Appellants then filed a timely appeal in this court.
    While this appeal was pending, then-Secretary of the
    Department of the Interior, Sally Jewell, issued an order
    pausing all activity on new leases to permit the agency to revisit
    the PEIS. Sec’y of the Interior, Order No. 3338 (Jan. 15, 2016),
    reprinted at J.A. 1438. The order explained that “[n]umerous
    scientific studies indicate that reducing [greenhouse gas]
    emissions from coal use worldwide is critical to addressing
    climate change.” 
    Id. at 4,
    J.A. 1441. Secretary Jewell therefore
    concluded that, in light of the “lack of any recent analysis of
    the Federal coal program as a whole, a more comprehensive,
    programmatic review [wa]s in order.” 
    Id. at 6,
    J.A. 1443. On
    the parties’ joint motion, this court held the case in abeyance.
    On March 29, 2017, newly appointed Secretary Zinke
    ordered an immediate halt to “[a]ll activities associated with
    the preparation of the [new] PEIS” and lifted the moratorium
    on new leasing. See Sec’y of the Interior, Order No. 3348 (Mar.
    29, 2017), reprinted at J.A. 1476–77. The court then granted
    Appellants’ motion to rescind the order holding the case in
    abeyance and to set a briefing schedule.
    11
    II.     ANALYSIS
    A. Standard of Review
    This court reviews de novo a district court decision granting
    a motion to dismiss under Federal Rule of Civil Procedure
    12(b)(6). Kim v. United States, 
    632 F.3d 713
    , 715 (D.C. Cir.
    2011). When reviewing the grant of a motion to dismiss, the
    court “must treat the complaint’s factual allegations as true, and
    must grant [the] plaintiff the benefit of all inferences that can
    be derived from the facts alleged.” Sparrow v. United Air
    Lines, Inc., 
    216 F.3d 1111
    , 1113 (D.C. Cir. 2000) (citations and
    internal quotation marks omitted).
    B. The Merits of Appellants’ Claim
    Appellants claim that NEPA requires the Secretary to issue
    a supplemental PEIS analyzing the climate impacts of federal
    coal leasing. Because NEPA does not provide a cause of action,
    we review the Secretary’s compliance with its statutory
    mandate under the APA. See Tulare Cty. v. Bush, 
    306 F.3d 1138
    , 1143 (D.C. Cir. 2002).
    Appellants’ cause of action in this case rests solely on
    § 706(1) of the APA, which states that a “reviewing court shall
    . . . compel agency action unlawfully withheld or unreasonably
    delayed.” 5 U.S.C. § 706(1). Appellants contend that NEPA
    requires the Secretary to supplement the 1979 PEIS for the
    Federal Coal Management Program, and that the Department’s
    failure to do so constitutes “agency action unlawfully
    withheld.” 
    Id. Appellants ask
    this court to compel the Secretary
    to comply with the statute as relief for the Department’s
    “failure to act.”
    12
    The seminal case on § 706(1) actions is Norton v. Southern
    Utah Wilderness Alliance (SUWA), 
    542 U.S. 55
    (2004). SUWA
    teaches that the only action a court may compel an agency to
    take under § 706(1) is discrete action that the agency has a duty
    to 
    perform. 542 U.S. at 62
    –63. The legal duty must be
    “ministerial or nondiscretionary” and must amount to “a
    specific, unequivocal command.” 
    Id. at 63–64.
    Appellants
    point to two sources that they claim require the Secretary to
    update the PEIS – (1) the supplementation requirement in the
    CEQ regulations; and (2) statements included by the Secretary
    in the initial PEIS and ROD promising to update the
    environmental analysis as circumstances changed. Because
    neither source requires the Secretary to update the PEIS for the
    Federal Coal Management Program, Appellants’ claim fails.
    1. NEPA and the CEQ Regulations
    In challenging the Secretary’s failure to act, Appellants
    first point to the requirement in the CEQ regulations that
    agencies supplement their environmental impact statements to
    take account of “significant new . . . information relevant to
    environmental concerns and bearing on the proposed action or
    its impacts.” 40 C.F.R. § 1502.9(c)(1)(ii). They claim that
    progress in climate science has produced such new
    information.
    Appellants also rely heavily on the Supreme Court’s
    decision in Marsh v. Oregon Natural Resources Council, 
    490 U.S. 360
    (1989). They contend that:
    [T]he Supreme Court explained in Marsh [that]
    NEPA’s duty to supplement an EIS applies when
    “remaining governmental action would be
    environmentally ‘significant,’” the agency retains an
    “opportunity to weigh the benefits of the project versus
    the detrimental effects on the environment,” and “new
    13
    information is sufficient to show that the remaining
    action will ‘affect the quality of the human
    environment’ . . . to a significant extent not already
    considered.” Interior’s continuing management of the
    coal-leasing program easily brings this case within that
    test because—among other things—we now know that
    continued authorization of leases to extract (and then
    burn) federal coal is “affect[ing] the quality of the
    human environment . . . to a significant extent not
    already considered.” The climate-change implications
    of that ongoing action are substantial and should now
    be informed by 38 years of research that Interior
    expressly called for in its 1979 PEIS, but has never
    considered in a supplemental programmatic analysis.
    Marsh forbids this result, as does the plain text of the
    governing regulation . . . .
    Appellants’ Br. 30–31 (quoting 
    Marsh, 490 U.S. at 371
    –74)
    (emphases removed).
    The Secretary does not contest Appellants’ assertion that
    the analyses of climate impacts of coal leasing in the PEIS and
    supplemental PEIS are outdated. Nor does the Secretary
    dispute Appellants’ claims that the availability of meaningful
    scientific research measuring greenhouse gas emissions and
    their climate impacts qualify as “significant new . . .
    information bearing on” federal coal leasing and its impacts.
    Instead, the Secretary asserts that the Department no longer has
    any NEPA obligations related to the Federal Coal Management
    Program. On this point, the Secretary contends that, because
    “BLM is not proposing to take any new action in reliance on
    the 1979 [P]EIS, . . . [the supplementation] regulation simply
    does not apply.” Sec’y’s Br. 19. And the Secretary contends
    that Marsh is inapposite because “[t]he Court in Marsh never
    14
    considered any programmatic EIS, let alone the question
    whether a programmatic EIS must be supplemented.” 
    Id. at 22.
    The Court’s decision in Marsh is a good starting point for
    our analysis. At issue in Marsh was the construction of a dam
    by the Army Corps of Engineers in the Rogue River Basin in
    southwest Oregon. Environmental groups sued to enjoin
    construction of the dam, arguing that NEPA required the Corps
    to issue a second EIS considering new information developed
    after it published its initial statement. At the time the law suit
    was filed, the dam had been approved, but construction was far
    from complete. See 
    Marsh, 490 U.S. at 363
    –70.
    The Marsh Court confirmed that preparation of
    “postdecision supplemental environmental impact statements
    . . . is at times necessary to satisfy the Act’s ‘action-forcing’
    purpose” and explained when that is the case. 
    Id. at 370–71.
    The Court indicated that, “although it would make sense to
    hold NEPA inapplicable at some point in the life of a project,”
    the law requires that agencies “file environmental impact
    statements when the remaining governmental action would be
    environmentally ‘significant.’” 
    Id. at 371–72
    (some internal
    quotation marks omitted). The Court clarified that this duty to
    supplement requires agencies to “take a ‘hard look’ at the
    environmental effects of their planned action, even after a
    proposal has received initial approval” when (1) “there remains
    ‘major Federal action’ to occur,” and (2) “the new information
    is sufficient to show that the remaining action will ‘affect the
    quality of the human environment’ in a significant manner or
    to a significant extent not already considered.” 
    Id. at 374.
    The
    Court concluded that the construction work that remained to be
    completed on the dam satisfied the first part of this test, but it
    deferred to the Corps’ determination that the newly identified
    information was insufficient to merit a new EIS. See 
    id. at 385.
                                   15
    Although the decision in Marsh lends some support for
    Appellants’ position in this case, the Court’s subsequent
    decision in SUWA does not. In SUWA, environmental groups
    sought to compel BLM to supplement an EIS it had issued in
    advance of approving a federal land-use 
    plan. 542 U.S. at 60
    –
    61. The groups argued that NEPA required BLM to take
    account of increased use of off-road vehicles in certain parts of
    the managed land. 
    Id. Rejecting this
    argument, the Court
    concluded that NEPA imposed no such requirement. Although
    it recognized that a supplemental EIS is sometimes necessary,
    the Court held that “approval of a land use plan” was the
    “major Federal action” triggering NEPA’s EIS requirement,
    and that “action [wa]s completed when the plan [wa]s
    approved.” 
    Id. at 72–73.
    Because there were no proposed
    amendments or revisions to the plan, there remained “no
    ongoing ‘major Federal action’ that could require
    supplementation’” under the first prong of the Marsh test. 
    Id. at 73.
    The SUWA Court reconciled its decision with Marsh. In
    Marsh, the Court explained, the dam’s construction was the
    “major Federal action” triggering NEPA, so there remained
    “action” to occur because construction was incomplete. 
    Id. By contrast,
    in SUWA, the approval of the land management plan
    was the relevant “major Federal action.” 
    Id. The action
    thus
    terminated with the plan’s approval, and there was no duty to
    supplement the EIS after that point. It did not matter that the
    plan continued to govern actions that took place after the
    approval. See 
    id. These cases
    make clear that the supplementation inquiry
    turns on how the “propos[ed] . . . Federal action” is defined. 42
    U.S.C. § 4332(2)(C). The Secretary argues that the relevant
    actions here were the 1979 and 1982 final rules, and that they
    – like the plan in SUWA – were completed when promulgated.
    16
    Appellants, in turn, argue that the action should be viewed as
    encompassing the Program broadly, including the leases and
    orders that the Department issues on an ongoing basis. On this
    view, there remains sufficient activity to occur as part of the
    Program to require supplementation.
    We agree with the Secretary that SUWA controls the
    disposition of this case. The Program here is functionally
    identical to the plan the Court evaluated in SUWA. In both
    cases, the agency established an approach for managing
    resources in the future. Under both the SUWA plan and the
    Federal Coal Management Program that is at issue in this case,
    the agency continued to engage in activities governed by the
    overarching scheme for which the initial EIS was prepared. As
    SUWA makes clear, the fact that actions continue to occur in
    compliance with the Program does not render the original
    action incomplete. Accordingly, the Department’s NEPA
    obligation for the Federal Coal Management Program
    terminated with its adoption in 1979.
    Appellants argue that because the Program is properly
    viewed as ongoing, it was not complete when approved. They
    point out that “environmentally significant decisions plainly
    remained” to be made in carrying out the Program, including
    in pricing future leases, allocating new leases, and issuing
    guidance and manuals. Appellants’ Br. 34–35. Because
    “[t]hese responsibilities . . . lead directly to the mining and
    burning of federal coal,” Appellants argue, the “myriad
    ‘environmentally significant’ steps the agency continues to
    take” demonstrate that there remains ongoing “major Federal
    action” under the Program. 
    Id. at 36.
    This argument cannot be squared with the governing
    precedent. Neither Marsh nor SUWA looked to decisions made
    pursuant to the relevant action in determining whether the duty
    17
    to supplement applied. They looked instead to the status of the
    action itself. Appellants have failed to identify any specific
    pending action, apart from the Program’s continued existence,
    that qualifies as a “major Federal action” under NEPA. So the
    only pertinent action for purposes of the court’s analysis is the
    one for which that document was prepared – the adoption of
    the Federal Coal Management Program. That action was
    completed when the Secretary issued the ROD and
    promulgated the final rule in 1979.
    Appellants urge us to read SUWA narrowly, claiming that
    its holding applies only where, as there, a regulation
    specifically indicates that the approval of a plan is the relevant
    action for NEPA purposes. 
    See 542 U.S. at 73
    (citing 43 C.F.R.
    § 1601.0–6). They claim that because there is no similar
    regulation here, SUWA does not control. Appellant’s view of
    the record is mistaken. The Secretary’s 1979 Final Rule
    referred to “the adoption of the Federal coal management
    program on June 1 and 2, 1979” as “a major Federal action
    significantly affecting the quality of the human environment”
    for which the 1979 EIS was published. 44 Fed. Reg. at 42,608
    (emphasis added). And the PEIS identified the proposed action
    as “the adoption of the . . . Federal coal management program.”
    PEIS at iv, J.A. 119 (emphasis added). Appellants provide no
    persuasive reason to treat the agency’s definition of the action
    here differently than the regulation in SUWA.
    Appellants also assert that by deeming the Program’s
    adoption to be the relevant “major Federal action,” we
    foreclose any challenge to the agency’s failure to consider the
    cumulative climate impacts of federal coal leasing. They argue
    that doing so allows the Department to avoid its duty to study
    the impacts of its actions and justify its decision to the public.
    In Appellants’ view, this outcome “render[s] NEPA review [a]
    ‘paperwork’ formality,” Appellants’ Br. 34, and allows the
    18
    Department to “hide the ball indefinitely, leaving the public to
    guess at both the environmental costs of one of the Nation’s
    predominant sources of carbon pollution and the agency’s
    views on what many voting citizens believe to be the defining
    environmental-protection issue of our time,” 
    id. at 69.
    We understand that Appellants’ claims are not frivolous.
    As noted above, Appellants have pointed to significant
    scientific studies that have identified the causes and
    consequences of continued atmospheric warming and showed
    that coal combustion is the single greatest contributor to the
    growing concentration of greenhouse gases in the atmosphere.
    Given that these studies were not available when the Secretary
    issued the 1979 PEIS and the 1985 supplement, Appellants
    raise a compelling argument that the Secretary should now
    revisit the issue and adopt a new program or supplement its
    PEIS analysis.
    Appellants have several avenues to raise their claims
    regarding the climate-change implications of coal leasing.
    First, as the Department points out in its brief, see Sec’y’s Br.
    17, Appellants may petition the Secretary for a rule making,
    seeking to have the coal management regulations take into
    account the serious environmental impacts of any coal leasing
    program. If the Secretary denies the petition for rule making,
    Appellants may seek judicial review of that determination. See
    Massachusetts v. EPA, 
    549 U.S. 497
    , 527–28 (2007).
    Second, Appellants may, when appropriate, challenge
    specific licensing decisions on the ground that the EIS prepared
    in support of any such decision fails to satisfy NEPA’s mandate
    to consider the cumulative environmental impacts of coal
    leasing. Such a claim might challenge any attempt by BLM to
    rely on (or tier to) the 1979 PEIS on the ground that it is too
    outdated to support new federal action. See 40 C.F.R.
    19
    § 1508.28; 
    id. § 1502.9(c)(1)(ii).
    NEPA compels the
    Department to include a complete environmental analysis in its
    proposal for any new major Federal action – even actions taken
    pursuant to the Federal Coal Management Program. See
    
    SUWA, 542 U.S. at 73
    . Indeed, the Secretary admits that any
    deficiencies in the PEIS “may affect the ability of BLM to ‘tier’
    to that document when making individual leasing decisions.”
    Sec’y’s Br. 24. Our decision in WildEarth Guardians v. Jewell,
    
    738 F.3d 298
    (D.C. Cir. 2013), is not to the contrary. In that
    case, the court rejected a challenge to the sufficiency of the
    climate impacts analysis provided in the EIS for a specific
    licensing decision. 
    Id. at 308–11.
    But the appellants in that case
    did not argue that tiering to the PEIS was inadequate because
    the PEIS had not been supplemented, and the court did not
    address that issue. See 
    id. Our holding
    in this case is also limited to the record before
    us. We are bound by established law holding that NEPA
    requires an agency to update its EIS only when it has proposed
    major federal action that is not yet complete. As explained
    above, the adoption of the Federal Coal Management Program
    was the relevant action in this case, and it was completed in
    1979. Therefore, no “major Federal action” remains as part of
    that action, and NEPA does not provide a legal duty to
    supplement the PEIS.
    2. The Department’s Alleged Prior Statements that It
    Was Obliged Under NEPA to Revise or Update the
    1979 PEIS
    In further support of their claims in this case, Appellants
    rely on statements that the Secretary included in the original
    regulatory materials for the Program. In the PEIS, the
    Department stated that the first level of environmental
    “analysis would be contained in this [PEIS], updated when
    20
    necessary.” PEIS at 3-68, J.A. 328 (emphasis added). And in
    both the PEIS and ROD, the Department stated that “[n]ational
    and interregional impacts of the Federal coal management
    program are analyzed in [the PEIS, which] would be updated
    when conditions change sufficiently to require new analyses of
    those impacts.” 
    Id. at 3-9,
    J.A. 269; ROD at 98, J.A. 1399
    (emphasis added). Appellants contend that these statements
    committed the agency to update the PEIS, even if NEPA does
    not require it.
    These cited statements might have created a binding duty
    on the agency at one point. See 40 C.F.R. § 1505.3 (stating that
    “conditions established in the [EIS] or during its review and
    committed as part of the decision shall be implemented”); Tyler
    v. Cisneros, 
    136 F.3d 603
    , 608 (9th Cir. 1998) (citing 40 C.F.R.
    § 1505.3 for the proposition that, where an agency commits to
    a measure in its EIS, the agency is required to implement the
    measure). In 1982, however, as part of its final rule amending
    the coal leasing regulations, the Department removed the
    provision explaining the circumstances in which the PEIS
    should be updated. See 47 Fed. Reg. at 33,115. In doing so, the
    Department made clear that it did not intend to bind itself to
    any supplementation duty beyond that imposed by NEPA.
    To be sure, the agency indicated in its discussion of the
    revision that, at the time, it believed NEPA required periodic
    updates to the PEIS apart from any new proposed action. See
    
    id. (stating the
    Department’s view that “[r]egardless of whether
    th[e] provision [was] deleted or retained, the Department must
    revise or update the Program EIS when its assumptions,
    analyses and conclusions are no longer valid”). But intervening
    case law indicates that NEPA imposes no such requirement.
    See 
    SUWA, 543 U.S. at 72
    –73.
    21
    III.   CONCLUSION
    On the record before us, neither NEPA nor the
    Department’s own documents create a legal duty for the
    Secretary to update the Federal Coal Management Program’s
    PEIS. Therefore, this court has no authority to compel the
    Department to supplement its analysis. The decision of the
    District Court is hereby affirmed.
    So ordered.
    KAREN LECRAFT HENDERSON, Circuit Judge, concurring
    in part and concurring in the judgment: I concur in all but a
    small portion of the opinion. I write separately to express where
    and why I separate myself. I also explain why, in my view, the
    majority correctly does not reach the issue addressed by Judge
    Edwards in his concurrence.
    First, I do not join the portion of the opinion that identifies
    alternative avenues by which the plaintiffs might press their
    claim. See Maj. Op. 18–19. Although I do not necessarily
    disagree with my colleagues’ reflections, I think it is neither
    necessary nor appropriate to advise parties on potential avenues
    of relief not before us. See, e.g., Republic of Venezuela v.
    Phillip Morris Inc., 
    287 F.3d 192
    , 199–200 (D.C. Cir. 2002)
    (court should not “declare, for the government of future cases,
    principles . . . which cannot affect the result as to the thing in
    issue in the case before it” (quoting California v. San Pablo &
    Tulare R.R. Co., 
    149 U.S. 308
    , 314 (1893))). I would leave it
    up to a future court to decide whether the alternatives discussed
    are sufficient to pursue the claim we reject in this appeal.
    Second, I briefly explain why, in my view, the majority
    properly declines to address the Government’s argument that
    the failure to prepare a supplemental Environmental Impact
    Statement (EIS) is not “final agency action” under section 704
    of the Administrative Procedure Act (APA). Although my
    colleague believes we should address the “very important
    issue” raised by the Government, Concurring Op. 1, I think we
    should “confine ourselves to deciding only what is necessary
    to the disposition of the immediate case,” Whitehouse v. Ill.
    Cent. R.R. Co., 
    349 U.S. 366
    , 373 (1955). In Norton v.
    Southern Utah Wilderness Alliance (SUWA), 
    542 U.S. 55
    (2004), the United States Supreme Court approached the same
    two issues we face here: whether the National Environmental
    Policy Act (NEPA), 42 U.S.C. § 4332, imposed a duty to
    supplement an EIS and whether the agency’s failure to do so
    was actionable under the 
    APA. 542 U.S. at 72
    –73. It set forth
    2
    the order of operations in mandatory terms: “Before addressing
    whether a NEPA-required duty is actionable under the APA,
    we must decide whether NEPA creates an obligation in the first
    place.” 
    Id. at 72
    (emphasis added). After holding that NEPA
    did not require a supplemental EIS, the Supreme Court went no
    further; it did not decide whether the claim was actionable
    under the APA. 
    Id. at 72–73.
    In deciding this appeal, the
    majority follows the Supreme Court’s—rather than the
    Government’s—roadmap. Cf. Yousuf v. Samantar, 
    451 F.3d 248
    , 255 (D.C. Cir. 2006) (stating general proposition that “we
    follow the guidance of the Supreme Court”); Broudy v. Mather,
    
    460 F.3d 106
    , 118 (D.C. Cir. 2006) (noting that parties’ “briefs
    [do not] follow the approach of the Supreme Court . . . to
    specifically identify claims as ‘backward-looking’ or ‘forward-
    looking’” and identifying claims based on Supreme Court
    precedent). We first address whether NEPA required a
    supplemental EIS. Answering that question in the negative, we
    need not and do not proceed further—an outcome I believe
    proper under SUWA and judicial restraint principles.
    EDWARDS, Senior Circuit Judge, concurring: In opposing
    Appellants’ claim in this case, the Department pressed two
    arguments: (1) Declining to prepare a supplemental EIS is not,
    by itself, a “failure to act” that qualifies as reviewable “final
    agency action” under § 704 of the APA; and (2) The NEPA
    regulations do not require the Department to supplement its
    PEIS in this case. Because we agree with the Department on
    the second point, the majority has declined to address the first
    point. I write separately to address the first point. Why?
    Because the Department’s argument raises a very important
    issue regarding the scope of § 706(1) of the APA, and, in my
    view, the Department’s argument regarding the reach of § 704
    is both wrong and mischievous.
    Appellants’ cause of action in this case rests solely on
    § 706(1) of the APA, which states that a “reviewing court shall
    . . . compel agency action unlawfully withheld or unreasonably
    delayed.” 5 U.S.C. § 706(1). Appellants contend that NEPA
    requires the Secretary to supplement the 1979 PEIS for the
    Federal Coal Management Program, and that the Department’s
    failure to do so constitutes “agency action unlawfully
    withheld.” 
    Id. Appellants ask
    this court to compel the Secretary
    to comply with the statute as relief for the Department’s
    “failure to act.”
    As noted in the opinion for the court, the seminal case on
    § 706(1) actions is Norton v. Southern Utah Wilderness
    Alliance (SUWA), 
    542 U.S. 55
    (2004). The District Court
    correctly explained that “[a] claim under the ‘unlawfully
    withheld’ provision of § 706(1) can proceed only if it contends
    that the ‘agency failed to take a discrete agency action that it is
    required to take.’” W. Org. of Res. Councils v. Jewell, 124 F.
    Supp. 3d 7, 10 (D.D.C. 2015) (quoting 
    SUWA, 542 U.S. at 64
    ).
    In SUWA, the Court also explained how § 706(1) fits into the
    APA review framework:
    2
    The APA authorizes suit by “[a] person suffering legal
    wrong because of agency action, or adversely affected
    or aggrieved by agency action within the meaning of a
    relevant statute.” 5 U.S.C. § 702. Where no other statute
    provides a private right of action, the “agency action”
    complained of must be “final agency action.” § 704
    (emphasis added). “[A]gency action” is defined in
    § 551(13) to include “the whole or a part of an agency
    rule, order, license, sanction, relief, or the equivalent or
    denial thereof, or failure to act.” (Emphasis added.)
    The APA provides relief for a[n] [agency’s] failure to
    act in § 706(1): “The reviewing court shall . . . compel
    agency action unlawfully withheld or unreasonably
    delayed.”
    
    SUWA, 542 U.S. at 61
    –62.
    SUWA’s reference to “final agency action” under 5 U.S.C.
    § 704 is perplexing insofar as it may pertain to actions under
    § 706(1) for “failure to act.” There is a well-recognized two-
    part test to determine whether an action is a “final agency
    action” under § 704. “First, the action must mark the
    ‘consummation’ of the agency’s decisionmaking process—it
    must not be of a merely tentative or interlocutory nature.”
    Bennett v. Spear, 
    520 U.S. 154
    , 177–78 (1997). “And second,
    the action must be one by which ‘rights or obligations have
    been determined,’ or from which ‘legal consequences will
    flow.’” 
    Id. Obviously, this
    test does not easily accommodate an
    agency’s failure to act. If an agency has failed to act with
    respect to a matter that a complaining party seeks to compel
    under § 706(1), it is hard to comprehend the contested inaction
    as “final action” as that term is defined in Bennett v. Spear.
    And, yet, the Court’s decision in SUWA leaves no doubt that an
    agency’s failure to act may be challenged under § 706(1) if the
    3
    action is discrete and one that the agency is required to take.
    
    See 542 U.S. at 64
    .
    The lower courts have remained a bit at sea over how to
    interpret the words in SUWA referring to § 704 and § 706(1).
    Judge Ebel’s discussion of this issue in the Tenth Circuit case
    leading to the Supreme Court’s decision in SUWA is
    illuminating:
    Courts have implicitly recognized that unlawfully
    withheld actions are considered final under § 704. Some
    emphasize, for example, that an agency must carry out
    nondiscretionary duties required by law, without
    discussing whether the withheld duty would be
    considered a final agency action. Courts have
    sometimes described § 706(1) as an exception to the
    APA “finality” requirement. This description may be
    slightly inaccurate, however, for § 704 of the APA
    defines the type of agency actions subject to judicial
    review and, in relevant part, limits judicial review to
    final agency actions. 5 U.S.C. § 704. Section 706(1), by
    contrast, defines the “scope” of judicial review over
    reviewable agency actions. 
    Id. § 706.
    S. Utah Wilderness All. v. Norton, 
    301 F.3d 1217
    , 1229 n.9
    (10th Cir. 2002) (citations omitted), rev’d, 
    542 U.S. 55
    (2004).
    The Supreme Court’s decision in SUWA does not directly
    address the concerns raised by Judge Ebel. Nevertheless, the
    case law remains clear that a party may pursue a claim under 5
    U.S.C. § 706(1) without satisfying the test of Bennett v. Spear.
    See, e.g., Arizona v. Inter Tribal Council of Ariz., Inc., 
    570 U.S. 1
    , 19–20, 19 n.10 (2013) (noting, without discussion of Bennett
    v. Spear’s final agency action requirement, that a litigant
    “would be free to seek a writ of mandamus” under § 706(1));
    Pub. Citizen Health Research Grp. v. Comm’r, FDA, 
    740 F.2d 4
    21, 32 (D.C. Cir. 1984) (holding that “the court can undertake
    review [under § 706(1)] as though the agency had denied the
    requested relief and can order an agency to either act or provide
    a reasoned explanation for its failure to act”).
    SUWA says that Ҥ 706(1) empowers a court . . . to compel
    an agency to perform a ministerial or non-discretionary act, or
    to take action upon a matter, without directing [how] it shall
    
    act.” 542 U.S. at 64
    (emphasis added). There is no doubt that
    SUWA means to endorse “failure to act” claims under § 706(1)
    so long as a complaining party has sufficiently alleged “that an
    agency failed to take a discrete agency action that it is required
    to take.” 
    Id. And “legally
    required” “discrete” actions that have
    not been performed, as in the context of a § 706(1) claim,
    cannot satisfy the finality requirements of Bennett v. Spear. In
    opposing Appellants’ action in this case, the Secretary seems
    not to understand this point.
    The Secretary argues that “the decision not to prepare a
    supplemental EIS is not a ‘final agency action’ as that term is
    defined in section 704 and is therefore not by itself subject to
    direct judicial review.” Sec’y’s Br. 13. However, this is
    irrelevant to any assessment of the viability of a claim under
    § 706(1). The Secretary also contends that “[a] completed EIS
    is . . . not, by itself, final agency action that is subject to review,
    so the failure to complete one is not a ‘failure to act’ that may
    be independently reviewed under the APA in the absence of
    some challenge to a substantive final agency action for which
    an EIS or supplemental EIS should have been prepared.” 
    Id. at 14–15
    (emphasis removed). This argument finds no support in
    the language of § 706(1) and it completely distorts the Court’s
    holding in SUWA.
    In an apparent effort to overcome the obvious frailties in its
    argument, the Department makes much of the fact that an EIS
    5
    is merely “a procedural prerequisite to a decision by the agency
    to undertake a ‘major Federal action.’” 
    Id. at 15
    (emphasis
    added). According to the Secretary, “[a]s a procedural
    prerequisite to some other final agency action, an EIS is not
    directly reviewable under the APA, but is subject to review on
    the review of the final agency action.” 
    Id. at 16.
    The fact that the preparation of an EIS may be a
    “procedural” matter is irrelevant to whether Appellants have
    raised a viable claim under § 706(1). The Secretary seems not
    to comprehend that “procedural rights” claims may be viable
    without regard to whether they result in any enforceable
    substantive rights.
    The Supreme Court’s discussion of standing to vindicate
    “procedural rights” reinforces this point. In Lujan v. Defenders
    of Wildlife, 
    504 U.S. 555
    (1992), the Court offered the
    following example:
    [U]nder our case law, one living adjacent to the site for
    proposed construction of a federally licensed dam
    has standing to challenge the licensing agency’s failure
    to prepare an environmental impact statement, even
    though he cannot establish with any certainty that the
    statement will cause the license to be withheld or
    altered, and even though the dam will not be completed
    for many years.
    
    Id. at 572
    n.7. Lujan did not address the scope of § 706(1)
    review, but the Court’s discussion is instructive. As that
    decision suggests, the right to challenge an agency’s failure to
    act in preparing an EIS is not diminished by the fact that such
    a suit protects merely a plaintiff’s “procedural right” to have
    the EIS issued, rather than any “substantive right” regarding
    the action the agency will ultimately take.
    6
    In any event, I find no merit in the Secretary’s attempt to
    limit the scope of judicial review under § 706(1). In assessing
    claims under § 706(1) – even in cases in which the claimants
    have lost – this court has never followed the approach the
    Secretary suggests in this case. See, e.g., Anglers Conservation
    Network v. Pritzker, 
    809 F.3d 664
    , 670–72 (D.C. Cir. 2016)
    (analyzing the scope of § 706(1) without regard to the test of
    “final agency action” under § 704); El Paso Nat. Gas Co. v.
    United States, 
    750 F.3d 863
    , 890 (D.C. Cir. 2014) (explaining
    that claims under § 706(1) are viable when the allegedly
    withheld action is (1) “legally required” and (2) “discrete”).
    Our decision in Public Citizen v. Office of U.S. Trade
    Representatives, 
    970 F.2d 916
    (D.C. Cir. 1992), on which the
    Secretary purports to rely, is inapposite because it says nothing
    about the scope of § 706(1).
    The Secretary’s position is flawed because it conflates the
    question regarding the scope of § 706(1) with the question
    relating to the merits of Appellants’ “failure to act” claim. The
    Secretary’s line of reasoning finds no support in SUWA or in
    other decisions that have addressed the scope of § 706(1).
    

Document Info

Docket Number: 15-5294

Citation Numbers: 892 F.3d 1234

Filed Date: 6/19/2018

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (17)

southern-utah-wilderness-alliance-a-utah-non-profit-corporation-the , 301 F.3d 1217 ( 2002 )

james-b-tyler-mary-ann-hartman-james-f-durfee-edward-a-johnson-andrew-l , 136 F.3d 603 ( 1998 )

Yousuf, Bashe Abdi v. Samantar, Mohamed , 451 F.3d 248 ( 2006 )

Broudy, Alice P. v. Mather, Susan H. , 460 F.3d 106 ( 2006 )

Sparrow, Victor H. v. United Airlines Inc , 216 F.3d 1111 ( 2000 )

Public Citizen v. Office of the United States Trade ... , 970 F.2d 916 ( 1992 )

Kim v. United States , 632 F.3d 713 ( 2011 )

Republic of Venezuela v. Philip Morris Incorporated , 287 F.3d 192 ( 2002 )

California v. San Pablo & Tulare Railroad , 13 S. Ct. 876 ( 1893 )

Department of Transportation v. Public Citizen , 124 S. Ct. 2204 ( 2004 )

Whitehouse v. Illinois Central Railroad , 75 S. Ct. 845 ( 1955 )

Marsh v. Oregon Natural Resources Council , 109 S. Ct. 1851 ( 1989 )

Lujan v. Defenders of Wildlife , 112 S. Ct. 2130 ( 1992 )

Bennett v. Spear , 117 S. Ct. 1154 ( 1997 )

Norton v. Southern Utah Wilderness Alliance , 124 S. Ct. 2373 ( 2004 )

Massachusetts v. Environmental Protection Agency , 127 S. Ct. 1438 ( 2007 )

Baltimore Gas & Electric Co. v. Natural Resources Defense ... , 103 S. Ct. 2246 ( 1983 )

View All Authorities »