Natl. Parks Cons. Assoc. v. Todd Semonite , 916 F.3d 1075 ( 2019 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued December 7, 2018                Decided March 1, 2019
    No. 18-5179
    NATIONAL PARKS CONSERVATION ASSOCIATION,
    APPELLANT
    v.
    TODD T. SEMONITE, LIEUTENANT GENERAL, ET AL.,
    APPELLEES
    Consolidated with 18-5186
    Appeals from the United States District Court
    for the District of Columbia
    (No. 1:17-cv-01361)
    (No. 1:17-cv-01574)
    Matthew G. Adams argued the cause and filed the briefs
    for appellants National Trust for Historic Preservation, et al.
    William S. Eubanks II argued the cause for appellant
    National Parks Conservation Association. With him on the
    briefs was Eric R. Glitzenstein.
    J. Blanding Holman was on the brief for amici curiae The
    Lawyer’s Committee for Cultural Heritage Preservation, et al.
    in support of appellant.
    2
    Tyler Joseph Sniff was on the brief for amici curiae 18th
    Director of the National Park Service Jonathan B. Jarvis, et al.
    in support of appellant National Parks Conservation
    Association.
    Dustin J. Maghamfar, Attorney, U.S. Department of
    Justice, argued the cause for federal appellees. With him on the
    brief were Jeffrey H. Wood, Acting Assistant Attorney General,
    Eric A. Grant, Deputy Assistant Attorney General, and
    Andrew C. Mergen, Mark R. Haag, and Heather E. Gange,
    Attorneys.
    Elbert Lin argued the cause for appellee Virginia Electric
    and Power Company. With him on the brief were Eric J.
    Murdock, Harry M. Johnson, III, and Timothy L. McHugh.
    Michael J. Thompson and Brett K. White were on the brief
    for amici curiae PJM Interconnection, L.L.C. in support of
    appellees.
    Before: GARLAND, Chief Judge, and TATEL and MILLETT,
    Circuit Judges.
    Opinion for the Court filed by Circuit Judge TATEL.
    TATEL, Circuit Judge: In order to “create and maintain
    conditions under which man and nature can exist in productive
    harmony,” the National Environmental Protection Act
    (NEPA), 42 U.S.C. § 4331(a), requires any federal agency
    issuing a construction permit, opening new lands to drilling, or
    undertaking any other “major” project to take a hard look at the
    project’s environmental consequences, 
    id. § 4332(2)(C),
    including the impacts it may have on “important historic . . .
    aspects of our national heritage,” 
    id. § 4331(b).
    To this end, the
    3
    agency must develop an environmental impact statement (EIS)
    that identifies and rigorously appraises the project’s
    environmental effects, unless it finds that the project will have
    “no significant impact.” 40 C.F.R. § 1508.9(a)(1). And that is
    what happened here. The U.S. Army Corps of Engineers
    (“Corps”) granted a permit allowing a utility company to build
    a series of electrical transmission towers across the historic
    James River, from whose waters Captain John Smith explored
    the New World, and it did so without preparing an EIS because
    it found that the project would have “no significant impact” on
    the historic treasures along the river. As explained below,
    however, the Corps’s “no significant impact” finding was
    arbitrary and capricious: important questions about both the
    Corps’s chosen methodology and the scope of the project’s
    impact remain unanswered, and federal and state agencies with
    relevant expertise harbor serious misgivings about locating a
    project of this magnitude in a region of such singular
    importance to the nation’s history. Accordingly, we reverse the
    district court’s decision to the contrary and remand with
    instructions to vacate the permit and direct the Corps to prepare
    an environmental impact statement.
    I.
    Over 400 years ago, Captain John Smith arrived on the
    shores of what is now known as the Chesapeake Bay. Keen on
    learning more about the unfamiliar land, Captain Smith
    voyaged up the winding James River, passing through lush
    forests and under open skies. During his voyages, Smith
    produced “maps and writings [that] influenced exploration and
    settlement in the New World for over a century.” 152 Cong.
    Rec. 22,282 (2006) (statement of Rep. Davis). These journeys
    came to symbolize our nation’s founding and to serve as an
    equally important reminder of one of the darkest episodes in
    our history—the settlers’ devastation of Native American
    4
    populations, including the “eventual collapse of the Powhatan
    polity.” John S. Salmon, Project Historian, National Park
    Service, Captain John Smith Chesapeake National Historic
    Water Trail Statement of National Significance 2 (2006).
    Long after Smith’s voyages, the river “serv[ed] as a
    strategic transportation corridor that shaped the settlement and
    commerce of the region.” H.R. Res. 16, 110th Cong. preamble
    (2007). Indeed, “the economic, political, religious, and social
    institutions that developed during the first [nine] decades” of
    the corridor’s settlement “have profound effects on the United
    States” to this day. Jamestown 400th Commemoration
    Commission Act of 2000, Pub. L. No. 106-565, § 2(a)(3), 114
    Stat. 2812, 2812. The same region commanded center stage
    through the nation’s infancy, bearing witness to “the British
    surrender that marked the end of the American Revolution.”
    Colonial National Historical Park Amendments, S. Rep.
    No. 104-30, at 2 (1995).
    Honoring these ties to our nation’s past, Congress and
    several federal agencies have established a series of “historic
    resources” in and around the Chesapeake Bay, including
    Jamestown, Carter’s Grove National Historic Landmark, and
    the Captain John Smith National Historic Trail (“Historic
    Trail”), the nation’s only congressionally-protected water trail.
    Due to the James River’s “extraordinary historic, economic,
    recreational, and environmental importance,” Congress
    recognizes it as “‘America’s Founding River.’” H.R. Res. 16
    §§ 1, 2. According to one representative, Congress
    “[d]esignat[ed] this [H]istoric [T]rail . . . to spur efforts to
    protect and restore the region’s historic and environmental
    assets.” 152 Cong. Rec. 22,283 (2006) (statement of Rep.
    Castle). Other members of Congress observed that the region
    “represents a lasting tribute to the American spirit of discovery
    and exploration,” 
    id. at 22,282
    (statement of Rep. Davis),
    5
    affording visitors “the opportunity to marvel at some of the
    same sites that Captain Smith and his crew beheld 400 years
    ago,” 
    id. at 22,283
    (statement of Rep. Hoyer).
    The National Park Service, an agency of the Department
    of the Interior, pursuant to its obligation “to conserve the
    scenery [and] natural and historic objects” of our national
    parks, 54 U.S.C. § 100101(a), acts as steward of these
    resources, striving to “offer[] visitors an opportunity to
    vicariously share the experience of Smith and his crew”
    through views “evocative of the seventeenth century,” Park
    Service, A Conservation Strategy for the Captain John Smith
    Chesapeake National Historic Trail Introduction 3 (2013). To
    this end, and in accordance with its conservation “management
    plan” for the Historic Trail, the Service seeks to “[m]aximize
    the visual and historical integrity of the visitor experience” by,
    among other things, ensuring that all new utility lines are
    underground. Park Service, General Management Plan:
    Colonial National Historical Park 19, 34 (1993) (“Management
    Plan”).
    Enter the demands of modernity. Although the
    approximately fifty-mile leg of the James River involved in this
    case has retained its seventeenth-century charm, the rest of
    Virginia has kept apace with modern development, which
    means it depends on electricity. Following the 2012 issuance
    of an Environmental Protection Agency rule requiring power
    generation facilities to reduce certain air pollutant emissions,
    see 77 Fed. Reg. 9304 (Feb. 16, 2012), Virginia Electric and
    Power Company (“Dominion”) determined that, in order to
    comply with the rule, it would have to retire two coal-fired
    power generators. To compensate for the resulting electricity
    shortfall, Dominion applied in 2013 to the Corps, which has
    jurisdiction over certain projects concerning “waters of the
    United States,” see 33 C.F.R. § 328.1 (internal quotation marks
    6
    omitted), for a permit to construct a new electrical switching
    station and two transmission lines. Supported by seventeen
    250-or-so-foot steel-lattice transmission towers, the line at
    issue here would stretch for eight miles, four of which would
    cross the James River and cut through the middle of the historic
    district encompassing Jamestown and other historic resources.
    See Figure 1.
    Figure 1: Overview Map of Project and Historic Properties (created by
    Industrial Economics, Inc.), Joint Appendix (J.A.) 495
    Before it could greenlight the undertaking, known as the
    Surry-Skiffes Creek-Whealton project (“Project”), the Corps
    had to satisfy several statutory obligations. First, as relevant
    here, NEPA required the Corps to consider alternatives to the
    Project and to prepare an “environmental impact statement” if
    the Project would “significantly affect[] the quality of the
    human environment,” 42 U.S.C. § 4332(2)(C)—an analysis
    which must take into account effects on historic resources, 40
    C.F.R. § 1508.8. But the Corps could bypass preparation of an
    7
    EIS if, based on a preliminary “environmental assessment,” it
    determined that the Project would have “no significant impact”
    on the environment. 40 C.F.R. § 1508.9. Second, the Clean
    Water Act required the Corps to determine that no “practicable
    alternative” existed that “would have less adverse effect on the
    aquatic ecosystem.” 
    Id. § 230.12(a)(3)(i).
    Third, the National
    Historic Preservation Act (“Preservation Act”) required the
    Corps to “take into account the effect of the undertaking on any
    historic property,” 54 U.S.C. § 306108, and, if the project
    might “directly and adversely affect any National Historic
    Landmark,” to take steps “to minimize harm to the landmark,”
    
    id. § 306107.
    Pursuant to these obligations, the Corps studied the
    Project’s environmental impacts and considered nearly thirty
    alternatives. In doing so, the Corps relied on a Cultural
    Resources Effects Assessment prepared by Dominion and its
    consultants, which included a series of photo simulations that
    superimposed mockups of the proposed towers over the
    existing landscape. In its initial environmental assessment, the
    Corps determined that the Project would adversely but non-
    significantly affect historic resources, rendering an EIS
    unnecessary.
    At various points throughout the process, the Corps, as
    required by Preservation Act regulations, reached out to
    “consulting parties,” which include local governments and
    other “individuals and organizations with a demonstrated
    interest in the undertaking.” 36 C.F.R. § 800.2(c). It also
    invited other federal agencies and the public to comment on its
    NEPA process. See 42 U.S.C. § 4332(2)(C) (requiring an
    agency to “consult with . . . any Federal agency which has
    jurisdiction by law or special expertise” and to provide any
    resulting statements “to the public”).
    8
    And comment they did, to the tune of 50,000 submissions,
    many of which urged the Corps to prepare an EIS. Condensing
    the gist of thousands of comments into one simple but clear
    proposition, the Advisory Council on Historic Preservation
    (“Advisory Council”)—the independent federal agency tasked
    with the “preservation of historic propert[ies],” 54 U.S.C.
    § 306101(a)(1)—warned that the Project “threaten[s] to
    irreparably alter a relatively unspoiled and evocative landscape
    that provides context and substance for the historic properties
    encompassed within.” Letter from Advisory Council
    Chairman 1 (May 2, 2017), J.A. 414.
    Quite a few commenters also pointed to perceived errors
    in the Corps’s determination that the Project would not
    significantly impact, in the Advisory Council’s words,
    “historic properties of transcendent national significance.”
    Letter from Advisory Council Director 1 (May 2, 2017),
    J.A. 411. Writing to the Corps fully twenty times, the Park
    Service warned that the Project “would forever degrade,
    damage, and destroy the historic setting of these iconic
    resources.” Letter from Park Service Director 1 (Dec. 11,
    2015), J.A. 1829. The Virginia Department of Historic
    Resources feared “irreparabl[e] alter[ation] [of] the character
    of the area.” Letter from Virginia Department of Historic
    Resources Director 2 (Nov. 13, 2015), J.A. 1855. Others,
    including then-Interior Secretary Sally Jewell, the Council on
    Environmental Quality, and many non-governmental
    organizations, sounded similar alarms.
    Other commenters identified what they viewed as serious
    flaws in the Corps’s methodologies. To give a flavor of these
    concerns, a specialist at the Department of Energy’s Argonne
    National Laboratory (“Argonne”) found the Corps’s analyses
    “scientifically unsound” and “completely contrary to accepted
    professional practice.” Response from Robert Sullivan ¶ 1
    9
    (Jan. 10, 2017), J.A. 534. The Park Service, the Advisory
    Council, and others critiqued the Corps’s socioeconomic,
    visual, and cumulative effects analyses.
    Still other commenters criticized the Corps’s evaluation of
    alternatives. Summarizing several such concerns, the Advisory
    Council wrote that the “alternatives analysis was extremely
    problematic,” that the National Parks Conservation
    Association (“Conservation Association”) had funded a study
    “that challenged the accuracy of the data and assumptions used
    by Dominion,” and that the engineering firm retained by the
    National Trust for Historic Preservation (“National Trust”) had
    developed alternatives that “would cost less to construct, be
    built more quickly, and meet all relevant reliability standards.”
    Letter from Advisory Council Chairman 3 (May 2, 2017),
    J.A. 416. According to one of the Corps’s own specialists,
    Dominion could yet “take a harder look at the alternatives” and
    the company’s cost estimates for the alternatives were “bloated
    and excessive.” Sustainable Program Manager Review 3–4,
    J.A. 540–41.
    While this deluge poured in, the Corps consulted with
    various agencies, conducted site visits, and twice directed
    Dominion to revise its photo simulations. Upon reviewing
    these amended analyses, the Corps and Dominion still believed
    that the Project, alone among all options, met the requisite
    reliability, cost, and timing parameters.
    Commenters remained unsatisfied. Several agencies
    warned that the revised analyses, as the Park Service put it, still
    contained “fundamental flaws” that, though “repeatedly
    identified,” nonetheless “remain[ed] unresolved.” Letter from
    Park Service Acting Regional Director 1 (Jan. 12, 2017),
    J.A. 475. Indeed, the “majority of the consulting parties” found
    Dominion’s amendments “superficial and inadequate.” Letter
    10
    from Advisory Council Chairman 3 (May 2, 2017), J.A. 416.
    Underscoring that such concerns endured past the final round
    of revisions, the Park Service director during this process
    submitted an amicus brief in his now-private capacity,
    emphasizing that, since the Project will “forever . . . destroy the
    historic setting of these iconic resources,” the Park Service,
    were it the agency with permitting authority, could not approve
    the Project “because its adverse impacts are so significant.”
    18th Director of the National Park Service Jonathan B. Jarvis
    Br. 7 (internal quotation marks omitted).
    The process reached a temporary denouement in 2017.
    Following the change in administration, then-newly appointed
    (now-former) Interior Secretary Ryan Zinke met with the
    Corps, acknowledged its “thoughtful and thorough
    consideration of the issues,” and announced that he “st[ood]
    ready to sign a final agreement as a concurring party.” Letter
    from Ryan Zinke 1 (Mar. 30, 2017), J.A. 420. Shortly
    thereafter, the Corps issued a permit to Dominion. In the
    accompanying Memorandum for the Record (“Memo”), the
    Corps acknowledged that the Project would “intrude upon the
    viewsheds of historic properties and on a unique and highly
    scenic section of the James River.” Memo § 10.3.8, J.A. 257.
    Nonetheless, the Corps concluded, the effects on these
    “national treasure[s]” were “moderate at most” and “inherently
    subjective.” 
    Id. §§ 10.3.8,
    12.3, J.A. 257, 266 (internal
    quotation marks omitted). Where visible at all, it explained, the
    transmission towers would not “block[]” or “dominate” the
    view and would join existing “modern visual intrusions,” such
    as the Busch Gardens amusement park and recreational boat
    traffic. 
    Id. § 10.3.8,
    J.A. 257–58.
    The Corps also executed a Memorandum of Agreement
    with Dominion, in which the company agreed to offset the
    harm to historic resources by, among other things, periodically
    11
    reviewing the continued need for the Project and investing in
    Virginia’s historic preservation efforts. Although a few other
    participants, including Interior, signed this Memorandum, most
    declined to do so because they remained concerned “that the
    adverse effects resulting from this undertaking [could not] be
    mitigated.” Letter from Advisory Council Chairman 2 (May 2,
    2017), J.A. 415.
    The National Trust, the Association for the Preservation of
    Virginia Antiquities, and the Conservation Association
    (collectively, the “Conservation Groups”) sued in district court
    alleging that the Corps failed to satisfy its NEPA, Clean Water
    Act, and Preservation Act obligations. The district court found
    that the “Corps made a ‘fully informed and well-considered’
    decision” and granted summary judgment to the agency.
    National Parks Conservation Association v. Semonite, 311 F.
    Supp. 3d 350, 361 (D.D.C. 2018) (quoting Vermont Yankee
    Nuclear Power Corp. v. Natural Resource Defense Council,
    
    435 U.S. 519
    , 558 (1978)).
    On appeal, the Conservation Groups present three
    arguments: that due to the significance of the Project’s impacts,
    the Corps was required to prepare an EIS; that the Corps’s
    alternatives analyses fell short of the requirements imposed by
    both NEPA and the Clean Water Act; and that the Corps failed
    to fulfill its obligations under section 110(f) of the Preservation
    Act, 54 U.S.C. § 306107, which requires an agency to
    minimize harm to any National Historic Landmark “directly
    and adversely” affected by a project. “We review the district
    court’s decision to grant summary judgment de novo.” Aera
    Energy LLC v. Salazar, 
    642 F.3d 212
    , 218 (D.C. Cir. 2011).
    12
    II.
    We begin with the Conservation Groups’ argument that
    NEPA required the Corps to prepare an EIS because, as they
    see it, the Project will significantly impact historic resources.
    “Our role in reviewing [the Corps’s] decision not to prepare an
    EIS is a limited one, designed primarily to ensure that no
    arguably significant consequences have been ignored.”
    Myersville Citizens for a Rural Community, Inc. v. FERC, 
    783 F.3d 1301
    , 1322 (D.C. Cir. 2015) (internal quotation marks
    omitted). Responsible for determining whether the Corps’s
    decision was “arbitrary, capricious, an abuse of discretion, or
    otherwise not in accordance with law,” 5 U.S.C. § 706(2)(A),
    we ask whether the Corps is “able to make a convincing case
    for its finding” of no significant impact. Sierra Club v. U.S.
    Department of Transportation, 
    753 F.2d 120
    , 127 (D.C. Cir.
    1985).
    “NEPA’s primary function is ‘information-forcing,’
    compelling federal agencies to take a hard and honest look at
    the environmental consequences of their decisions.” American
    Rivers v. FERC, 
    895 F.3d 32
    , 49 (D.C. Cir. 2018) (internal
    citations omitted). To satisfy this “hard look” requirement, the
    Corps must prepare an EIS for any project “significantly
    affecting the quality of the human environment.” 42 U.S.C.
    § 4332(2)(C). Under NEPA’s regulatory scheme, crafted by the
    Council on Environmental Quality, such effects can be, among
    others, historic, aesthetic, or cultural. 40 C.F.R. § 1508.8.
    Congress has declared that “preserv[ing] important historic,
    cultural, and natural aspects of our national heritage”
    constitutes an important goal of the statute. 42 U.S.C.
    § 4331(b)(4). And we in turn have recognized that protecting
    such resources is “an interest that NEPA’s procedural mandate
    was intended to vindicate.” Oglala Sioux Tribe v. U.S. Nuclear
    Regulatory Commission, 
    896 F.3d 520
    , 529 (D.C. Cir. 2018).
    13
    As mentioned earlier, if the Corps believes that a project may
    not require an EIS, it may first prepare an environmental
    assessment to determine whether a “no significant impact”
    determination might find support in the record. 40 C.F.R.
    § 1508.9(a).
    During the NEPA process, the Corps must consult
    agencies with “special expertise with respect to any
    environmental impact involved.” 42 U.S.C. § 4332(2)(C); see
    also 40 C.F.R. § 1501.6(a)(2) (requiring agencies to use the
    resulting analysis “to the maximum extent possible”). But, as
    the lead agency, the Corps, which “b[ears] the ultimate
    statutory responsibility” for the Project, “does not have to
    follow [other agencies’] comments slavishly—it just has to
    take them seriously.” Citizens Against Burlington, Inc. v.
    Busey, 
    938 F.2d 190
    , 201 (D.C. Cir. 1991).
    Whether a project has significant environmental impacts,
    thus triggering the need to produce an EIS, depends on its
    “context” (region, locality) and “intensity” (“severity of
    impact”). 40 C.F.R. § 1508.27. Here, because all parties agree
    that the historically-saturated “context”—i.e., this 50-mile
    stretch of the James River—qualifies as significant, our inquiry
    focuses on the “intensity” element, which enumerates ten
    factors that “should be considered.” 
    Id. § 1508.27(b).
    Implicating any one of the factors may be sufficient to require
    development of an EIS. See Grand Canyon Trust v. FAA, 
    290 F.3d 339
    , 347 (D.C. Cir. 2002), as amended (Aug. 27, 2002)
    (granting a petition for review after finding a project implicated
    one factor, without reaching additional factors). The district
    court found that “none of the significance factors weigh in
    favor of [the] contention that an EIS is required.” National
    Parks Conservation 
    Association, 311 F. Supp. 3d at 363
    . The
    Conservation Groups disagree, arguing that the Project
    implicates three such factors: “[t]he degree to which the effects
    14
    on the quality of the human environment are likely to be highly
    controversial,” 40 C.F.R. § 1508.27(b)(4); “[u]nique
    characteristics of the geographic area such as proximity to
    historic or cultural resources,” 
    id. § 1508.27(b)(3);
    and the
    “degree to which the action may adversely affect districts [or]
    sites . . . listed in or eligible for listing in the National Register
    of Historic Places,” 
    id. § 1508.27(b)(8).
    We consider each in
    turn.
    A.
    The first factor considers “[t]he degree to which the effects
    on the quality of the human environment are likely to be highly
    controversial.” 40 C.F.R. § 1508.27(b)(4). The word
    “controversial,” we held in Town of Cave Creek v. FAA, refers
    to situations where “‘substantial dispute exists as to the size,
    nature, or effect of the major federal action.’” 
    325 F.3d 320
    ,
    331 (D.C. Cir. 2003) (quoting North American Wild Sheep v.
    U.S. Department of Agriculture, 
    681 F.2d 1172
    , 1182 (9th Cir.
    1982)) (emphasis in original). And as we explained in Fund for
    Animals v. Frizzell, “certainly something more is required” for
    a highly controversial finding “besides the fact that some
    people may be highly agitated and be willing to go to court over
    the matter.” 
    530 F.2d 982
    , 988 n.15 (D.C. Cir. 1975) (per
    curiam) (emphasis added).
    According to the Conservation Groups, “[w]here, as here,
    two federal agencies have argued for years over the ‘size,’
    ‘nature,’ and ‘effect’ of the project on resources under [the Park
    Service’s] jurisdiction (as have other agencies with ‘special
    expertise’ under NEPA), the Court’s test for ‘controversy’ fits
    like a glove.” Conservation Association Br. 22 (emphasis
    omitted). For its part, the Corps asserts that, under Cave Creek
    and Frizzell, it “reasonably concluded that comments
    demanding an EIS ‘represent passion for the affected
    15
    resources’ . . . rather than substantive dispute.” Corps Br. 38
    (quoting Memo § 12.3, J.A. 266). The Conservation Groups
    acknowledge that a highly controversial finding must rest on
    more than passionate opposition, but they insist that the
    criticism of the Corps’s NEPA process rises to the requisite
    “something more.”
    The Conservation Groups first point out that much of the
    disagreement centers on perceived defects in the Corps’s
    methodology and that, as the district court observed, “[m]any
    courts have found ‘something more’ to be scientific or other
    evidence that reveals flaws in the methods or data relied upon
    by the agency in reaching its conclusions.” National Parks
    Conservation 
    Association, 311 F. Supp. 3d at 363
    (citing
    National Parks & Conservation Association v. Babbitt, 
    241 F.3d 722
    , 736–37 (9th Cir. 2001)) (internal quotation marks
    omitted); accord Biodiversity Conservation Alliance v. U.S.
    Forest Service, 
    765 F.3d 1264
    , 1275 (10th Cir. 2014) (“A
    substantial dispute can be found, for example, when other
    information in the record cast[s] substantial doubt on the
    adequacy of the agency’s methodology and data.” (internal
    quotation marks and citation omitted)); see, e.g., Cave 
    Creek, 325 F.3d at 332
    (no controversy where the petitioners “pointed
    to nothing casting serious doubt on [the agency’s] preferred
    model”). An expert at Argonne labeled the Corps’s analyses
    “scientifically unsound, inappropriate, and completely contrary
    to accepted professional practice,” accusing the agency of
    conflating a cultural resource analysis with the very different
    visual resource analysis. Response from Robert Sullivan ¶ 1
    (Jan. 10, 2017), J.A. 534. The Advisory Council voiced serious
    concerns about the photo simulations: “[T]here are flaws in the
    visual effects assessment. . . . [C]onsulting parties have
    repeatedly suggested that the Corps should require photographs
    and simulations from an adequate range of viewpoints . . . to
    illustrate the extent and magnitude of the effects.” Letter from
    16
    Advisory Council Assistant Director 2 (Mar. 2, 2016),
    J.A. 1483. And the Park Service believed that the visual
    analyses “d[id] not meet [its] standards,” questioning whether
    the Corps and Dominion completed “an adequate visual
    analysis,” “evaluat[ed] . . . socioeconomic impacts,” and
    undertook a “sufficient cumulative effects analysis.” Letter
    from Park Service Associate Regional Director 1 (Mar. 25,
    2016), J.A. 1357; Letter from Park Service Acting Regional
    Director 2 (Jan. 12, 2017), J.A. 476. If such comments,
    representing just a small sample of the many criticisms in the
    record, do not “cast substantial doubt on the adequacy” of the
    Corps’s methodologies, Biodiversity Conservation 
    Alliance, 765 F.3d at 1275
    (internal quotation marks omitted), then we
    are unsure what would.
    According to the Conservation Groups, the controversy
    surrounding the Project is especially intense because many of
    those raising concerns—methodological and otherwise—are
    themselves government agencies with “special expertise” over
    historic resources. 40 C.F.R. § 1501.6(a)(2). And as they also
    point out, courts regularly find that such concerns demonstrate
    that a project qualifies as highly controversial. See, e.g., North
    American Wild 
    Sheep, 681 F.2d at 1182
    (criticism from
    conservationists, biologists, two state agencies, and “other
    knowledgeable individuals” represented “precisely the type of
    ‘controversial’ action for which an EIS must be prepared”);
    Friends of the Earth, Inc. v. U.S. Army Corps of Engineers, 
    109 F. Supp. 2d 30
    , 43 (D.D.C. 2000) (project classified as
    “genuinely and extremely controversial” where three federal
    agencies, one state agency, and the public “all disputed the
    Corps evaluation”).
    Again, the Conservation Groups are correct. The Advisory
    Council questioned the Corps’s “treatment of effects on
    historic properties of transcendent national significance.”
    17
    Letter from Advisory Council Director 1 (May 2, 2017),
    J.A. 411. Interior Secretary Jewell warned that the Project
    would “introduce a major intrusion into a landscape” like “no
    other preserved locale in the Nation.” Letter from Sally
    Jewell 1 (Jan. 17, 2016), J.A. 473. The Park Service worried
    that the Project “would forever degrade, damage, and destroy
    the historic setting of these iconic resources,” admonishing that
    “[t]his is not acceptable for resources designated by Congress
    to ensure their permanent protection.” Letter from Park Service
    Director 1 (Dec. 11, 2015), J.A. 1829. As the Service observed,
    “[s]ince the 1930s, the visitor experience and interpretation of
    Jamestown has been a collective effort . . . to shift [visitors’]
    sense of place back in time,” and “[w]ithin the Historic District
    the James River is unblemished by any man-made physical
    crossing.” Letter from Park Service Associate Regional
    Director 6 (July 5, 2016), J.A. 878; Letter from Park Service
    Associate Regional Director 3 (Jan. 29, 2016), J.A. 1494. The
    Service repeatedly communicated its concerns to the Corps,
    and its own management plan requires that the “visual and
    historical integrity of the visitor experience” be “maximize[d]”
    and that all new utility lines be installed underground.
    Management Plan at 19, 34.
    And the list goes on. Industrial Economics, Inc., a
    consultant retained by the Park Service, feared that the Project
    could “have implications for successful future designation [of
    Jamestown] as a UNESCO World Heritage Site.” Industrial
    Economics, Inc. Report 9 (Jan. 2017), J.A. 499. The Virginia
    Department of Historic Resources warned of “irreparabl[e]
    alter[ation] [of] the character of the area.” Letter from Virginia
    Department of Historic Resources Director 2 (Nov. 13, 2015),
    J.A. 1855. Members of Congress, delegates to the Virginia
    Assembly, the Keeper of the National Historic Register, and
    the Council on Environmental Quality all voiced similar
    reservations. The non-profit Coalition to Protect America’s
    18
    National Parks, comprising current and former Park Service
    employees, pleaded, as did a bevy of other organizations, that
    “[t]he Corps owes . . . to this and future generations of
    Americans to protect the place where ‘America Began.’” Letter
    from Coalition to Protect America’s National Parks 1 (Dec. 23,
    2016), J.A. 464.
    These are hardly the hyperbolic cries of “highly agitated,”
    not-in-my-backyard neighbors “willing to go to court over the
    matter.” 
    Frizzell, 530 F.2d at 988
    n.15. Instead, they represent
    the considered responses—many solicited by the Corps itself—
    of highly specialized governmental agencies and organizations.
    The Advisory Council, tasked as it is with preserving
    America’s historic resources, merits special attention when it
    opines, as it did here, on “the treatment of effects on historic
    properties of transcendent national significance.” Letter from
    Advisory Council Director 1 (May 2, 2017), J.A. 411; see also
    Preservation Coalition, Inc. v. Pierce, 
    667 F.2d 851
    , 858 (9th
    Cir. 1982) (“[J]udgments of historical significance made by the
    Advisory Council . . . deserve great weight.”). Of course, as
    lead agency the Corps owes no obligation to bend to the will of
    others. See Citizens Against 
    Burlington, 938 F.2d at 201
    (a lead
    agency must only “take [other agencies’ comments]
    seriously”). But repeated criticism from many agencies who
    serve as stewards of the exact resources at issue, not to mention
    consultants and organizations with on-point expertise, surely
    rises to more than mere passion.
    The Corps argues that because the Park Service is a
    component of the Interior Department, Secretary Zinke’s letter
    approving the Project, in the district court’s words, “effectively
    withdrew” the Service’s “previous stance that an EIS was
    required.” National Parks Conservation Association, 311 F.
    Supp. 3d at 366. We disagree. For one thing, even if the Zinke
    letter did withdraw the Service’s opposition, numerous other
    19
    groups remained adamantly opposed. We are unsure,
    moreover, whether the Zinke letter actually responds to the
    Park Service’s concerns. As the Conservation Association
    points out, the letter “never even reference[s] [the Park
    Service’s] objections [or] longstanding methodological
    critiques.” Conservation Association Reply Br. 10. And most
    important, the Zinke letter says little about the only question
    before us: whether the Corps acted arbitrarily and capriciously
    in declining to prepare an EIS. Regardless of Interior’s stance,
    the Corps retained its NEPA obligation to “consider
    adequately” whether the Project is highly controversial. Cave
    
    Creek, 325 F.3d at 327
    . Because the facts underlying the Park
    Service’s concerns changed not at all between the Jewell and
    Zinke letters, the Corps had to either confront those facts or
    explain why the Zinke letter rendered them irrelevant. See
    Encino Motorcars, LLC v. Navarro, 
    136 S. Ct. 2117
    , 2125
    (2016) (“One of the basic procedural requirements of
    administrative rulemaking is that an agency must give adequate
    reasons for its decisions.”). Indeed, in our view, that two
    Interior Secretaries had diametrically different views about the
    same project on the same facts simply reinforces its
    controversial nature.
    The Corps next contends that it did acknowledge and try
    to address concerns raised during the NEPA process by, for
    example, instructing Dominion to revise its analyses to address
    the shortcomings identified by commenters. But that misses the
    point. The question is not whether the Corps attempted to
    resolve the controversy, but whether it succeeded. Given that
    many critical comments, including those from the Advisory
    Council and the Argonne specialist, post-dated Dominion’s
    revisions, the Corps obviously failed.
    In short, the Corps’s assessment of the scope of the
    Project’s effects has drawn consistent and strenuous
    20
    opposition, often in the form of concrete objections to the
    Corps’s analytical process and findings, from agencies
    entrusted with preserving historic resources and organizations
    with subject-matter expertise. This demonstrates the
    “something more” needed to show that “the effects on the
    quality of the human environment are likely to be highly
    controversial.” 40 C.F.R. § 1508.27(b)(4).
    B.
    The next intensity factor the Conservation Groups cite
    examines the “[u]nique characteristics of the geographic area
    such as proximity to historic or cultural resources.” 40 C.F.R.
    § 1508.27(b)(3). According to the Conservation Association,
    “[t]he Corps-approved project entails putting giant modern
    transmission towers not only in close ‘proximity to’ numerous
    highly unique historic and cultural sites that are ‘one-of-a-kind
    resources of national importance,’ but putting them directly in
    and across the nation’s only Congressionally-designated
    historic water trail.” Conservation Association Br. 19
    (emphasis in original) (citation omitted). The Corps responds
    that the Project “‘is not a blockage to viewing the river or the
    surroundings’ and ‘will not dominate the view.’” Corps Br. 27
    (quoting Memo § 10.3.8, J.A. 258). Again, the Corps misses
    the point.
    Congress has consistently “recommit[ted] itself to
    protecting and restoring the James River for the enjoyment and
    prosperity of current and future generations.” H.R. Res. 16 § 4.
    As one congressman put it, these efforts preserve “the
    opportunity [for visitors] to marvel at some of the same sites
    that Captain Smith and his crew beheld.” 152 Cong.
    Rec. 22,283 (2006) (statement of Rep. Hoyer). Of course, when
    Captain Smith sailed up the James River in the seventeenth
    century, he beheld nothing either licensed by the U.S. Army
    21
    Corps of Engineers or built by Dominion Energy. In other
    words, even without blocking the view or dominating the
    landscape from all angles, the Project undercuts the very
    purpose for which Congress designated these resources: to
    preserve their “unspoiled and evocative landscape[s].” Letter
    from Advisory Council Chairman 1 (May 2, 2017), J.A. 414.
    Insisting that the Project is nothing new, the Corps points
    to existing “modern visual intrusions” in the same region that
    represent a “successful mix of progress and history.” Corps
    Br. 28 (quoting Memo § 10.3.8, J.A. 257). This
    mischaracterizes the record. Although there is some modern
    development, including an amusement park, boat traffic, and
    resorts, the Corps itself described these as largely “low density
    intrusions that become relatively lost within the overall
    landscape.” National Register of Historic Places Eligibility 4
    (May 7, 2015), J.A. 2205. As the Conservation Association
    observes, “the record does not support the assertion . . . that
    existing intrusions are remotely comparable in size, magnitude,
    or impact to this massive project that will be the only overhead
    crossing of the James River in a fifty-one-mile stretch.”
    Conservation Association Br. 20 (emphasis in original).
    The Corps maintains that the mitigation steps contained in
    its Memorandum of Agreement with Dominion “would reduce
    [the Project’s] impacts to a minimum.” Corps Br. 42. But the
    relevance of the Memorandum is dubious given that the Corps
    declined to rely on it when making its “no significance”
    findings. To the extent the Corps leans on it now, the document
    offers little support. Except for requiring Dominion to
    “examine” alternative “coating and finishing materials” for the
    transmission towers, the enumerated mitigation measures the
    Corps cites relate not to reducing the significance of the
    Project’s visual impacts on the historic resources along the
    James River, but rather to periodic evaluation of the continued
    22
    need for the Project itself and to more general historic
    preservation efforts throughout the Commonwealth.
    Memorandum of Agreement § I.e.1, J.A. 293.
    Finally, the Corps emphasizes that the Project’s effects are
    visual and that the Seventh Circuit, citing our decision in
    Maryland-National Capital Park and Planning Commission v.
    U.S. Postal Service, 
    487 F.2d 1029
    , 1038–39 (D.C. Cir. 1973),
    stated that aesthetic “judgments are inherently subjective and
    normally can be made . . . reliably on the basis of an
    environmental assessment.” River Road Alliance, Inc. v. Corps
    of Engineers of U.S. Army, 
    764 F.2d 445
    , 451 (7th Cir. 1985).
    But “normally” is not the same as “always.” And in Maryland-
    National Capital Park, we distinguished aesthetic judgment
    calls that entail “defining what is beautiful” from situations like
    this one where Congress’s purpose in designating the resources
    was to preserve “an unencumbered view of an attractive scenic
    
    expanse.” 487 F.2d at 1038
    & n.5.
    C.
    The foregoing largely demonstrates why the Project
    implicates the final intensity factor invoked by the
    Conservation Groups: the “degree to which the action may
    adversely affect districts [or] sites . . . listed in or eligible for
    listing in the National Register of Historic Places.” 40 C.F.R.
    § 1508.27(b)(8). Indeed, the Corps itself gets us much of the
    way there. It concedes that the Project’s “close proximity” to
    Carter’s Grove, an eighteenth-century Georgian-style
    plantation, “would detract from the resource’s characteristics
    of setting and feeling which are integral to the resource’s
    qualifications for listing on the [National Register of Historic
    Places].” Cultural Resources Effects Assessment § 3.9.4
    (Sept. 15, 2015), J.A. 2024. And it is hardly just Carter’s
    Grove. By the Corps’s own count, the region boasts fifty-seven
    23
    sites on the National Register or eligible for inclusion on it—a
    concentration of historic resources found “[i]n no other place
    in [the] United States.” Letter from Park Service Regional
    Director 1 (Oct. 22, 2015), J.A. 1911.
    The Corps’s findings, paired with the record’s “robust,
    well-supported analyses, from agencies with Congressionally-
    delegated authority and recognized expertise,” National Trust
    Br. 16, satisfy this intensity factor. The out-of-circuit cases
    cited by the Corps—concerning the construction of a golf
    clubhouse near another, historic one, Presidio Golf Club v.
    National Park Service, 
    155 F.3d 1153
    , 1156 (9th Cir. 1998),
    and the refurbishment of an existing railroad to provide
    commuter service, Advocates for Transportation Alternatives,
    Inc. v. U.S. Army Corps of Engineers, 
    453 F. Supp. 2d 289
    ,
    294–95 (D. Mass. 2006)—are easily distinguishable, as they
    implicate neither comparably sized infrastructure nor equally
    august historic resources.
    D.
    The Corps has thus failed to make a “convincing case” that
    an EIS is unnecessary. Myersville 
    Citizens, 783 F.3d at 1322
    .
    Three intensity factors demonstrate not only that the Project
    will significantly impact historic resources, but also that it
    would benefit from an EIS. Indeed, Congress created the EIS
    process to provide robust information in situations precisely
    like this one, where, following an environmental assessment,
    the scope of a project’s impacts remains both uncertain and
    controversial. See, e.g., Grand Canyon 
    Trust, 290 F.3d at 345
    –47 (remanding for further proceedings when an agency,
    analyzing noise impacts on a national park “identified [by the
    Park Service] as among the nine national parks of ‘highest
    priority,’” considered those impacts “in a vacuum” without
    sensitivity to the park’s “natural quiet”); American Rivers, 
    895 24 F.3d at 50
    (ordering an EIS based on concerns that the agency
    “just shrugged off” potentially significant impacts based on
    “estimates entirely unmoored from any empirical, scientific, or
    otherwise verifiable study or source”).
    III.
    In preparing its EIS, the Corps will have to revisit its
    theories about alternatives under NEPA, which in turn will
    require it to reevaluate its Clean Water Act and Preservation
    Act analyses. Accordingly, we see no reason to address most
    of the remaining questions raised by the Conservation Groups.
    See American Iron & Steel Institute v. EPA, 
    115 F.3d 979
    , 1008
    (D.C. Cir. 1997) (“see[ing] no profit” in addressing remaining
    argument where an agency was “already committed to agency
    revision”). Though taking no position on the adequacy of the
    Corps’s alternatives analyses, we urge it to give careful
    consideration to its sister agencies’ concerns that the prior
    iterations were “superficial,” “inadequate,” and “extremely
    problematic.” Letter from Advisory Council Chairman 3
    (May 2, 2017), J.A. 416.
    There is, however, one issue whose resolution would
    facilitate further proceedings before the Corps. Specifically,
    the parties disagree about the meaning of section 110(f) of the
    Preservation Act, which provides that for any project “directly
    and adversely affect[ing] any National Historic Landmark,” the
    agency must “to the maximum extent possible undertake such
    planning and actions as may be necessary to minimize harm to
    the landmark.” 54 U.S.C. § 306107. The debate centers on the
    word “directly” as it relates to Carter’s Grove, the National
    Historic Landmark at issue. According to the Corps and the
    district court, because the Project does not “physically” intrude
    on the plantation’s grounds—several towers are instead visible
    from them—section 110(f) does not apply. See National Parks
    25
    Conservation 
    Association, 311 F. Supp. 3d at 379
    (“The Court
    is persuaded that the meaning of ‘directly’ in Section 110(f)
    refers to physical impacts . . . .”). The National Trust disagrees,
    equating “directly” with having “no intervening cause.”
    National Trust Br. 9 (internal quotation marks omitted).
    Because we “owe no deference to [the Corps’s]
    interpretation of a statute it does not administer,” Amax Land
    Co. v. Quarterman, 
    181 F.3d 1356
    , 1368 (D.C. Cir. 1999),
    “[w]e begin our analysis with the language of the statute,”
    United States v. Wilson, 
    290 F.3d 347
    , 352 (D.C. Cir. 2002).
    Although section 110(f) clearly encompasses physical effects,
    nothing in the statute’s text so limits its reach. According to the
    dictionary, both now and at the time section 110(f) was passed,
    “direct” means “free from extraneous influence” or
    “immediate.” Black’s Law Dictionary (10th ed. 2014); see also
    Black’s Law Dictionary (5th ed. 1979) (“direct” defined as
    “without any . . . intervening influence” or “[i]mmediate”).
    And had Congress wished to restrict section 110(f)’s reach to
    physical impacts, “it could have easily done so by using the
    word” physically. Marx v. General Revenue Corp., 
    568 U.S. 371
    , 384 (2013). Finally, although no agency has provided
    binding guidance, the two actually responsible for
    administering this statute—the Park Service, 54 U.S.C.
    § 306101(b), and the Advisory Council, 
    id. § 304108(a)—both
    understand “directly” to “refer[] to causation and not
    physicality.” Letter from Advisory Council Assistant
    Director 4 (Mar. 2, 2016), J.A. 1485; see also Lawyers’
    Committee for Cultural Heritage Preservation Br. 19, Ex. A,
    Letter from Park Service Acting Associate Director 2 (Sept. 21,
    2017) (“The [Park Service] does not agree with the Corps’
    position that Section 110(f) applies only when an undertaking
    may physically impact a National Historic Landmark.”). On
    remand, therefore, the Corps must reconsider its Preservation
    Act analysis using this proper definition.
    26
    IV.
    For the foregoing reasons, we reverse and remand to the
    district court with instructions to vacate Dominion’s permit and
    direct the Corps to prepare an environmental impact statement.
    So ordered.
    

Document Info

Docket Number: 18-5179

Citation Numbers: 916 F.3d 1075

Filed Date: 3/1/2019

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (16)

River Road Alliance, Inc. v. Corps of Engineers of United ... , 764 F.2d 445 ( 1985 )

the-preservation-coalition-inc-v-samuel-r-pierce-jr-secretary-of-the , 667 F.2d 851 ( 1982 )

citizens-against-burlington-inc-v-james-b-busey-iv-administrator , 938 F.2d 190 ( 1991 )

presidio-golf-club-v-national-park-service-an-agency-of-the-united-states , 155 F.3d 1153 ( 1998 )

national-parks-conservation-association , 241 F.3d 722 ( 2001 )

foundation-for-north-american-wild-sheep-a-corporation-society-for-the , 681 F.2d 1172 ( 1982 )

Grand Canyon Trust v. Federal Aviation Administration , 290 F.3d 339 ( 2002 )

Maryland - National Capital Park and Planning Commission a ... , 487 F.2d 1029 ( 1973 )

Amax Land Company v. Quarterman, Cynthia , 181 F.3d 1356 ( 1999 )

Town of Cave Creek v. Federal Aviation Administration , 325 F.3d 320 ( 2003 )

Aera Energy LLC v. Salazar , 642 F.3d 212 ( 2011 )

american-iron-and-steel-institute-v-environmental-protection-agency-and , 115 F.3d 979 ( 1997 )

sierra-club-a-nonprofit-california-corporation-v-the-united-states , 753 F.2d 120 ( 1985 )

Friends of the Earth, Inc. v. United States Army Corps of ... , 109 F. Supp. 2d 30 ( 2000 )

Vermont Yankee Nuclear Power Corp. v. Natural Resources ... , 98 S. Ct. 1197 ( 1978 )

Advocates for Transportation Alternatives, Inc. v. U.S. ... , 453 F. Supp. 2d 289 ( 2006 )

View All Authorities »