Missouri River Energy Services v. FERC , 918 F.3d 954 ( 2019 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued February 6, 2019               Decided March 15, 2019
    No. 18-1166
    MISSOURI RIVER ENERGY SERVICES,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    BASIN ELECTRIC POWER COOPERATIVE, ET AL.,
    INTERVENORS
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    Lawrence G. Acker argued the cause for petitioner. With
    him on the briefs were Philip W. Mone and Gabriel L. Tabak.
    Jared B. Fish, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With him on
    the brief were James P. Danly, General Counsel, and Robert H.
    Solomon, Solicitor. Carol J. Banta, Attorney, entered an
    appearance.
    2
    William D. Booth argued the cause for intervenors. With
    him on the joint brief was David D’Alessandro. Jonathan P.
    Trotta and Marie Denyse Zosa entered appearances.
    Before: GARLAND, Chief Judge, SRINIVASAN, Circuit
    Judge, and SILBERMAN, Senior Circuit Judge.
    Opinion for the Court filed by Circuit Judge SRINIVASAN.
    SRINIVASAN, Circuit Judge: In 2015, Missouri River
    Energy Services, a collection of municipal entities, became a
    member of the Southwest Power Pool. Missouri River claimed
    it should be exempt from certain charges assessed by the Pool,
    and the parties submitted the dispute to the Federal Energy
    Regulatory Commission. FERC sustained the charges, and
    Missouri River now petitions for review of FERC’s decision.
    We conclude that FERC’s determination was not arbitrary and
    capricious and thus deny Missouri River’s petition for review.
    I.
    Missouri River Energy Services is an organization of 61
    municipal utilities in the Upper Midwest. Missouri River helps
    its member municipal electric systems source power. To that
    end, in the 1970s, Missouri River teamed up with other energy-
    related entities to construct the Laramie River Station (a power
    plant) and various transmission facilities.
    In 1977, those entities entered into a contract with
    Nebraska Public Power District, under which Missouri River
    and its partners agreed to help defray Nebraska Power’s
    construction and operation costs for new transmission
    facilities. In exchange, Nebraska Power agreed to allow the
    entities to use the new facilities to transmit some of the power
    from the Laramie River Station. For the last four decades,
    3
    Missouri River has used that arrangement under the 1977
    Contract to help move electricity generated by the Laramie
    River Station part of the way from the power plant to Missouri
    River’s member utilities.
    In 2008, Nebraska Power asked to join the Southwest
    Power Pool, a Regional Transmission Organization that
    “provides transmission service to approximately 6 million
    households across portions of eight states.” Okla. Gas & Elec.
    Co. v. FERC, 
    827 F.3d 75
    , 77 (D.C. Cir. 2016). (A Regional
    Transmission Organization oversees electricity grids on a
    regional scale and coordinates transmission service to ensure
    reliable and efficient transmission. See Morgan Stanley
    Capital Grp. v. Pub. Utility Dist. No. 1, 
    554 U.S. 527
    , 535–37
    (2008).) As part of the process of accepting Nebraska Power
    into the Southwest Power Pool, the Pool filed proposed
    revisions of its bylaws and Tariff. Those revisions included
    adding the 1977 Contract to the Pool’s list of Grandfathered
    Agreements, which meant that service under the 1977 Contract
    would be exempt from certain provisions of the Tariff. In late
    2008, FERC approved the proposed revisions, Nebraska Power
    became a member of the Pool, and Missouri River’s
    transmission service under the 1977 Contract continued
    unchanged.
    Four years later, the Pool decided to implement a new
    Integrated Marketplace that included energy markets in which
    Pool members could bid for energy services. As part of that
    implementation, the Pool proposed imposing additional
    charges on its members to account for energy loss due to
    transmission and transmission congestion. A number of
    parties, including Missouri River, protested the imposition of
    those charges on transmission covered by Grandfathered
    Agreements (including the 1977 Contract).
    4
    The Pool stated that it would not impose additional charges
    on Missouri River’s reservation under the 1977 Contract
    because Missouri River was outside the footprint of the Pool.
    Missouri River then withdrew its protest. The Pool proceeded
    to settlement negotiations with the other protesting parties, and
    those negotiations produced a Carve-Out Settlement that
    identified specific Grandfathered Agreements that were
    eligible for exemption (i.e., eligible to be carved out) from the
    congestion and marginal loss charges. In particular, § 2.2 of
    the Carve-Out Settlement stated that Schedule 1 of the Carve-
    Out Settlement “constitutes the exclusive list of eligible
    ‘Carved-Out GFAs,’ meaning that only those agreements and
    the megawatts associated with them identified on Schedule 1
    are eligible for carve-out treatment.” J.A. 377. And Schedule
    1 clarifies that, with respect to the 1977 Contract, Missouri
    River’s reservation is not “eligible for carve-out.” J.A. 385.
    The Pool filed that Carve-Out Settlement with FERC, and
    FERC approved it.
    In 2014, after the Carve-Out Settlement had been filed and
    approved, a number of Missouri River’s business partners (but
    not Missouri River) filed a request to join the Southwest Power
    Pool. The Pool, in turn, filed proposed Tariff revisions with
    FERC to allow those parties to join. Missouri River protested
    the Pool’s proposal, which did not carve out Missouri River
    from congestion and marginal loss charges for transmission
    under the 1977 Contract. In response, FERC generally
    approved the Pool’s proposed revisions but set aside the carve-
    out issue for settlement procedures. In late 2015, those parties
    became members of the Pool, as did Missouri River.
    Although Missouri River and the Pool engaged in
    extensive settlement negotiations, they were unable to reach an
    agreement on the carve-out issue. Instead, they agreed to a set
    of stipulated facts and requested a shortened hearing process
    5
    before FERC on the issue of whether Missouri River is entitled
    to carve-out treatment for its transmission reservation under the
    1977 Contract. Following that hearing process, FERC sided
    with the Pool.
    First, FERC determined that the terms of the Southwest
    Power Pool Tariff did not entitle Missouri River to carve-out
    treatment. FERC reasoned that the Tariff is ambiguous about
    which agreements are eligible for carve-out treatment and then
    looked to extrinsic evidence to resolve that ambiguity in the
    Pool’s favor with regard to Missouri River’s reservation under
    the 1977 Contract. Second, FERC determined that the
    exclusion of Missouri River from carve-out eligibility was
    permissible, rejecting Missouri River’s arguments that the
    exclusion constituted undue discrimination, that the exclusion
    impermissibly modified or abrogated the 1977 Contract, and
    that the Pool should be equitably estopped from denying
    Missouri River carve-out treatment.
    After FERC denied Missouri River’s motion for rehearing,
    Missouri River filed the present petition for review.
    II.
    We review FERC’s orders under “the arbitrary and
    capricious standard of the Administrative Procedure Act.”
    Alcoa Inc. v. FERC, 
    564 F.3d 1342
    , 1347 (D.C. Cir. 2009); see
    5 U.S.C. § 706(2). That means “[w]e affirm the Commission’s
    orders so long as FERC examined the relevant data and
    articulated a rational connection between the facts found and
    the choice made.” 
    Alcoa, 564 F.3d at 1347
    (internal quotation
    marks and alterations omitted).
    6
    Missouri River challenges FERC’s determination that it is
    ineligible for carve-out treatment on five grounds. We find
    none of Missouri River’s arguments persuasive.
    First, Missouri River argues that Southwest Power Pool’s
    Tariff unambiguously establishes that Missouri River’s
    transmission reservation under the 1977 Contract is eligible for
    carve-out treatment. The relevant language of the Tariff, in
    § 2.16 (entitled “Grandfathered Agreement [GFA] Carve
    Out”), provides that Pool members “that are a party to GFA(s)
    eligible for GFA Carve Out” may elect from among various
    options, including carve-out treatment. J.A. 415. According
    to Missouri River, because the Tariff’s list of Grandfathered
    Agreements includes the 1977 Contract, the carve-out
    provision unambiguously provides Missouri River a right to
    elect carve-out treatment. That is incorrect.
    Of course, the 1977 Contract is a GFA. But § 2.16 of the
    Tariff provides that only GFAs “eligible for GFA Carve Out”
    may receive carve-out treatment, which implies that some
    GFAs are eligible for such treatment and others are not. And
    neither § 2.16 nor any other provision of the Tariff explains
    what makes a GFA carve-out eligible. For that reason, FERC
    understandably found the Tariff ambiguous with respect to the
    eligibility of Missouri River’s transmission reservation for
    carve-out treatment. We thus reject Missouri River’s argument
    that the Tariff unambiguously confers carve-out eligibility on
    its transmission reservation under the 1977 Contract.
    Second, Missouri River argues that, even if the Tariff is
    ambiguous, FERC erred by relying on extrinsic evidence—in
    the form of § 2.2 and Schedule 1 of the Carve-Out Settlement—
    to resolve the ambiguity. In Missouri River’s view, FERC
    instead should have resolved the ambiguity by reference to the
    doctrine of contra proferentem, under which ambiguities are
    7
    resolved against the drafter. Missouri River contends that
    FERC has previously adhered to a policy favoring use of contra
    proferentem to resolve ambiguities and it therefore must
    explain its decision to depart from that policy and to rely
    instead on extrinsic evidence.
    Missouri River’s argument fails at the threshold: FERC
    has not adhered to a policy of resolving ambiguities with the
    contra proferentem canon rather than with extrinsic evidence.
    Although Missouri River identifies a number of cases in which
    FERC has relied on the contra proferentem canon, see Missouri
    River Br. 34–35 (collecting cases), in none of those cases did
    the agency turn to contra proferentem in the face of available
    extrinsic evidence.
    By contrast, FERC has repeatedly relied on extrinsic
    evidence to resolve ambiguities even in the face of arguments
    from a party to use the contra proferentem canon. See, e.g.,
    Cent. N.Y. Oil & Gas Co., 152 FERC ¶ 61,097, at pp. 20–37
    (2015) (using extrinsic evidence to help resolve an ambiguity
    in a service agreement even though one party urged FERC to
    apply the contra proferentem canon); Miss. River Transmission
    Corp., 96 FERC ¶ 61,185, at p. 61,189 (2001) (rejecting a
    party’s assertion that a tariff ambiguity should, as a matter of
    law, be resolved against the drafter and instead scheduling an
    evidentiary hearing to allow the parties to introduce extrinsic
    evidence of intent); cf. KN Energy, Inc., 59 FERC ¶ 61,332, at
    p. 62,219 (1992) (applying contra proferentem but only
    because the objecting party had “offer[ed] no evidence, nor
    describe[d] any surrounding circumstances, that would
    indicate” the intent behind the relevant ambiguous provision).
    Because FERC has had no policy of favoring contra
    proferentem over extrinsic evidence as a means of resolving
    ambiguities, we reject Missouri River’s argument that FERC
    8
    improperly changed course by relying on extrinsic evidence in
    this case.
    We note, moreover, the strength of the extrinsic evidence
    on which FERC relied. Section 2.2 of the Carve-Out
    Settlement, filed on the same day as the Tariff revision at issue,
    states that Schedule 1 of the Carve-Out Settlement “constitutes
    the exclusive list of eligible ‘Carved-Out GFAs,’ meaning that
    only those agreements and the megawatts associated with them
    identified on Schedule 1 are eligible for carve-out treatment.”
    J.A. 377 (emphasis added). FERC reasonably concluded that
    the concurrently filed Carve-Out Settlement, which identified
    “eligible ‘Carved-Out GFAs,’” gives meaning to which GFAs
    are “eligible for GFA Carve Out” under § 2.16 of the Tariff.
    J.A. 415. And because Missouri River’s reservation under the
    1977 Contract is not identified on that “exclusive list,” it is,
    under the Carve-Out Settlement, not “eligible for carve-out.”
    J.A. 385.
    Third, Missouri River argues that excluding its
    transmission reservation from carve-out eligibility amounts to
    undue discrimination in violation of the Federal Power Act.
    Under the Act, no public utility may “make or grant any undue
    preference or advantage to any person or subject any person to
    undue prejudice or disadvantage” nor may a public utility
    “maintain any unreasonable difference in rates, charges,
    service, facilities, or in any other respect, either as between
    localities or as between classes of service.” 16 U.S.C.
    § 824d(b). A mere difference in the treatment of two entities
    does not violate that provision; instead, undue discrimination
    occurs only if the entities are “similarly situated,” State Corp.
    Comm’n v. FERC, 
    876 F.3d 332
    , 335 (D.C. Cir. 2017) (internal
    quotation marks omitted), such that “there is no reason for the
    difference,” Transmission Access Policy Study Grp. v. FERC,
    
    225 F.3d 667
    , 721 (D.C. Cir. 2000) (per curiam). FERC has
    9
    “wide discretion . . . to determine what constitute[s]” undue
    discrimination. 
    Id. Here, Missouri
    River’s claim of undue discrimination rests
    on the Pool’s grant of carve-out treatment to a transmission
    reservation owned by Lincoln Electric System pursuant to the
    same 1977 Contract. FERC acknowledged that excluding
    Missouri River’s transmission reservation from carve-out
    resulted in a disparity in treatment between Missouri River and
    Lincoln Electric. FERC, though, concluded that there was no
    undue discrimination because Missouri River and Lincoln
    Electric are not similarly situated with respect to the Pool’s
    congestion and marginal loss charges. Specifically, FERC
    explained that Lincoln Electric was a member of the Pool when
    the Pool changed its Tariff to impose those charges (and was
    therefore “subject to a forced transition” to a Tariff with the
    charges), whereas Missouri River joined the Pool after the
    Tariff was changed to incorporate those charges. Sw. Power
    Pool, Inc., 160 FERC ¶ 61,115, at pp. 61–63 (2017), J.A. 645–
    46. In light of that difference, FERC determined, it was
    permissible to treat the two entities differently. 
    Id. The distinction
    between pre-existing and new members is
    well-supported in FERC precedent. In one case, the Midwest
    Independent System Operator (MISO) sought to revise its
    Tariff to eliminate the possibility of carve-out treatment for
    certain Grandfathered Agreements held by prospective
    members and also to remove five of Dairyland’s Grandfathered
    Agreements from eligibility for carve-out treatment. See
    Dairyland Power Coop. v. MISO, 131 FERC ¶ 61,163, at pp.
    7–9 (2010). FERC approved in part and rejected in part those
    changes.
    On the one hand, FERC allowed MISO to eliminate the
    availability of carve-out treatment for some agreements held by
    10
    prospective members because a “prospective transmission
    owner,” unlike an existing member, “can analyze the costs of
    converting its GFAs to tariff service prior to integration, and
    weigh those costs against the benefits of [MISO] membership.”
    Dairyland Power Coop. v. MISO, 129 FERC ¶ 61,221, at pp.
    39–41 (2009). On the other hand, FERC rejected MISO’s
    proposal to remove Dairyland’s GFAs from the list of carve-
    out eligible agreements. 
    Id. at pp.
    42–44. FERC thereby drew
    exactly the distinction that it drew here, allowing different
    treatment of (i) prospective members seeking new carve-out
    treatment and (ii) members seeking to preserve pre-existing
    carve-out eligibility. In light of that precedent, Missouri River
    has not met its burden of showing that FERC acted arbitrarily
    and capriciously in determining that Missouri River and
    Lincoln Electric are not similarly situated. We therefore reject
    Missouri River’s undue discrimination claim.
    Fourth, Missouri River argues that imposing congestion
    and marginal loss charges on its transmission reservation
    improperly modifies the 1977 Contract. In rejecting that
    argument, FERC determined that “the assessment of
    congestion and marginal loss charges associated with GFA
    treatment do not represent a modification of the 1977 Contract
    because these charges are associated with new services
    available to [Missouri River] as a result of joining SPP,
    including access to the Integrated Marketplace and the ability
    to hedge congestion costs.” Sw. Power Pool, 160 FERC
    ¶ 61,115, at p. 81, J.A. 653–54. Because FERC’s “analysis
    hinges on interpretation of utility contracts, our review of that
    analysis is deferential.” Wis. Pub. Power, Inc. v. FERC, 
    493 F.3d 239
    , 271 (D.C. Cir. 2007) (per curiam). Missouri River
    provides us with no reason to reject FERC’s conclusion.
    Missouri River notes that FERC once previously found,
    and we agreed, that excluding a Grandfathered Agreement
    11
    from carve-out eligibility constituted a modification of that
    agreement. See Missouri River Br. 19–20 (citing MISO, 121
    FERC ¶ 61,166 (2007); and Wis. Pub. Power, 
    493 F.3d 239
    ).
    In that case, however, FERC determined that subjecting the
    parties to the new Tariff “would impose significant changes in
    the manner in which transmission service is provided for”
    because there was a “direct collision between GFA scheduling
    practices and the MISO Tariff’s scheduling requirements.”
    Wis. Pub. 
    Power, 493 F.3d at 272
    –73 (internal quotation marks
    omitted). Here, by contrast, FERC found no such “direct
    collision” between the 1977 Contract and the Pool’s Tariff
    because the marginal loss and congestion charges related to
    additional services provided by Southwest Power Pool, such as
    “access to the Integrated Marketplace and the ability to hedge
    congestion costs,” which were not provided for by (and the
    costs of which thus were not covered by the rates set in) the
    1977 Contract. Sw. Power Pool, 160 FERC ¶ 61,115, at p. 81,
    J.A. 653–54; cf. E. Ky. Power Coop., Inc. v. FERC, 
    489 F.3d 1299
    , 1306–08 (D.C. Cir. 2007) (affirming FERC’s
    determination that MISO may impose certain costs to account
    for various services and benefits that were not provided under
    the Grandfathered Agreements but that are provided by MISO).
    We see no reason to reject FERC’s conclusion that the
    congestion and marginal loss charges at issue here pay for new
    services not provided for in the 1977 Contract.
    Fifth, Missouri River argues that Southwest Power Pool
    should be equitably estopped from denying it carve-out
    treatment. Missouri River relies on the Pool’s representation
    in 2013 that, “because [Missouri River’s] reservation is not
    associated with an SPP Settlement Location or SPP
    transmission service, and is not tagged by SPP, it will not be
    subject to the rules and tariff requirements of SPP’s proposed
    Integrated Marketplace” and “will not be assessed congestion
    costs or marginal losses.” J.A. 819. Missouri River’s
    12
    equitable-estoppel argument is forfeited because Missouri
    River has failed to fully develop it. See SEC v. Banner Fund
    Int’l, 
    211 F.3d 602
    , 613–14 (D.C. Cir. 2000). The argument is
    unpersuasive in any event.
    The “traditional elements of” equitable estoppel include
    “false representation, a purpose to invite action by the party to
    whom the representation was made, ignorance of the true facts
    by that party, and reliance, as well as a showing of an injustice
    and lack of undue damage to the public interest.” ATC Petrol.,
    Inc. v. Sanders, 
    860 F.2d 1104
    , 1111 (D.C. Cir. 1988) (internal
    quotation marks and alterations omitted). Here, FERC
    concluded that if Missouri River relied on Southwest Power
    Pool’s 2013 statement “to mean that [its] reservation under the
    1977 Contract would be eligible for carve out treatment after
    [it] joined SPP, such reliance was unreasonable.” Sw. Power
    Pool, 160 FERC ¶ 61,115, at p. 75, J.A. 651. That is because
    the language used by the Pool—that Missouri River would not
    be subject to the charges “because” it was not within the Pool’s
    footprint—cannot reasonably be interpreted to mean that, if
    Missouri River were to come within SPP’s footprint in the
    future, then the Pool would not impose charges at that time.
    And that is exactly what happened. The Pool did not seek to
    impose congestion and marginal loss charges on the 1977
    reservation until Missouri River subsequently came within the
    Pool’s footprint. We thus reject Missouri River’s argument, to
    the extent it is not forfeited, that the Pool should be equitably
    estopped from imposing congestion and marginal loss charges
    against Missouri River.
    *    *   *    *   *
    For the foregoing reasons, we deny the petition for review.
    It is so ordered.