Ameren Services Company v. FERC , 893 F.3d 786 ( 2018 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued November 8, 2017              Decided June 22, 2018
    No. 16-1150
    AMEREN SERVICES COMPANY, AS AGENT FOR UNION ELECTRIC
    COMPANY D/B/A AMEREN MISSOURI, AMEREN ILLINOIS
    COMPANY D/B/A AMEREN ILLINOIS AND AMEREN
    TRANSMISSION COMPANY OF ILLINOIS, ET AL.,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    MIDCONTINENT INDEPENDENT SYSTEM OPERATOR, INC., ET
    AL.,
    INTERVENORS
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    Michael J. Thompson argued the cause for petitioners
    MISO Transmission Owners and intervenor Midcontinent
    Independent System Operator, Inc. On the joint briefs were
    Jim Holsclaw, Matthew R. Dorsett, Christopher D. Supino,
    Brooksany Barrowes, and Marcia Hook. Wendy N. Reed and
    Matthew J. Binette entered appearances.
    2
    Nicholas M. Gladd, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With him on
    the briefs were Robert H. Solomon, Solicitor, and Elizabeth E.
    Rylander, Attorney. Beth G. Pacella, Attorney, entered an
    appearance.
    Before: TATEL, GRIFFITH and SRINIVASAN, Circuit Judges.
    Opinion for the Court filed by Circuit Judge SRINIVASAN.
    In 2011, the Federal Energy Regulatory Commission
    issued Order 1000, which aims, among other things, to
    encourage the development of “interregional” electricity
    transmission projects—projects spanning more than one
    geographic region. The interregional component of Order
    1000 rested on the belief that certain interregional projects
    might meet the needs of transmission providers and customers
    more efficiently and effectively than regional projects, but that
    prevailing incentives and coordination mechanisms did not
    adequately encourage regional transmission providers to
    pursue interregional projects.
    To that end, Order 1000 calls for regional providers to
    jointly evaluate interregional projects. As part of that process,
    providers must adopt cost-allocation methodologies for
    dividing up the costs of a joint project. The primary goal of
    Order 1000’s cost-allocation provisions is to assure that the
    relative costs borne by a particular transmission provider be
    commensurate with the relative benefits gained by the provider
    from the project.
    This case concerns one transmission provider’s proposed
    interregional cost-allocation methodology.       Midcontinent
    Independent System Operator (MISO), an organization that
    operates transmission facilities on behalf of providers across
    3
    fifteen states in the Midwest, proposed to conduct cost
    allocation for interregional projects using what’s called a cost-
    avoidance method. The share of costs allocated to MISO under
    that method corresponds to the benefits to MISO of its regional
    projects that would be displaced by the interregional project.
    In identifying which regional projects should be regarded as
    displaced by an interregional project, MISO proposed to
    exclude any project that had already been approved by the
    MISO board.
    The Commission rejected MISO’s cost-allocation
    approach. In the Commission’s view, excluding approved
    regional projects from the analysis would result in a failure to
    account for the full potential benefits of an interregional
    project. The transmission providers that make up MISO filed
    a petition for review in this court. We deny the petition.
    I.
    A.
    Electric transmission in the United States is largely
    managed by regional transmission organizations (RTOs) and
    independent system operators (ISOs). Those entities operate
    the electric transmission systems for a geographic region on
    behalf of the local utilities (known as transmission providers)
    in a region. MISO operates transmission facilities in the
    midwestern United States on behalf of more than two dozen
    transmission providers, petitioners here.
    For the past several decades, the Federal Energy
    Regulatory Commission, acting under its authority to fix just
    and reasonable rates under section 206 of the Federal Power
    Act has issued orders requiring RTOs and ISOs to adopt
    practices meant to encourage competition in the market for
    4
    electricity. E.g., Transmission Planning and Cost Allocation
    by Transmission Owning and Operating Public Utilities, Order
    No. 1000, 136 FERC ¶ 61,051 at PP 1-5 (2011). Order 1000,
    among the most recent of those orders, requires ISOs and RTOs
    to consider and evaluate interregional projects—projects
    embracing more than one region—and set certain parameters
    for allocating the costs of those interregional projects among
    providers. Id. The Commission’s aim is to induce the
    construction of interregional projects “if such facilities address
    the needs of the transmission planning regions more efficiently
    or cost-effectively” than regional projects. Id. at 111.
    Order 1000’s cost-allocation provisions seek to further that
    goal. Establishing both a mechanism and set of principles for
    cost allocation, Order 1000 calls for neighboring ISOs and
    RTOs to reach agreements on cost allocation for interregional
    projects that avoid free rider problems, that improve
    transparency with respect to the costs of interregional projects,
    and that otherwise align regional and interregional planning
    processes. The guiding principle behind Order 1000’s cost-
    allocation provisions is that the costs of interregional projects
    should be “allocated in a way that is roughly commensurate
    with benefits.” Id. at 178.
    This court considered a petition for review raising a variety
    of challenges to Order 1000. S.C. Pub. Serv. Authority v.
    FERC, 
    762 F.3d 41
     (D.C. Cir. 2014) (per curiam). The court
    sustained Order 1000 in all respects.
    B.
    MISO submitted filings to the Commission that purported
    to comply with Order 1000’s interregional project coordination
    and cost-allocation provisions. The particular filing at issue in
    this case concerns the cost-allocation methodology MISO
    5
    proposed to use with respect to one of its neighboring
    transmission planning regions, the Southeastern Regional
    Transmission Planning organization (SERTP).
    MISO proposed to conduct cost allocation using a “cost-
    avoidance” method. Under that method, the costs allocated to
    MISO for a given interregional project would correspond to the
    costs of the regional projects MISO expects to avoid as a result
    of the interregional project—that is, the costs of the regional
    projects rendered unnecessary by the interregional project. Of
    central relevance here, MISO proposed to include in its cost
    calculation only those displaced projects that had been
    identified in the regional transmission plan but had yet to be
    approved. The costs of displaced projects already approved in
    the regional transmission plan would be excluded from the
    calculation.
    The Commission accepted MISO’s compliance filing in
    part. The Commission concluded that the cost-avoidance
    method largely complied with Order 1000’s cost-allocation
    provisions calling for the costs of an interregional project to be
    allocated in a manner roughly commensurate with the project’s
    benefits. As a general matter, the Commission said, the costs
    of regional projects that would be avoided by undertaking an
    interregional project should approximate the expected benefits
    of the interregional project.
    The Commission ultimately rejected MISO’s proposed
    cost-allocation method, however, because it excluded from its
    calculation the costs of any displaced projects that had already
    been approved in MISO’s transmission plan. By excluding
    approved projects, the Commission determined, MISO’s
    methodology would undervalue the benefits of an interregional
    project. That undervaluation, the Commission found, would
    result in an improper allocation of costs: relative to its
    6
    neighboring region (SERTP), MISO would bear a lesser share
    of costs than would be warranted based on the share of an
    interregional project’s benefits it would receive.
    In addition, the Commission concluded, inclusion of
    approved regional projects in the cost-allocation analysis
    would make it more likely that MISO would pursue a beneficial
    interregional project—i.e., one that would displace less
    efficient and less cost-effective regional projects. That is
    because, if MISO counts an approved regional project for cost-
    allocation purposes, it also includes that project when assessing
    the benefits of an interregional project for purposes of deciding
    whether to undertake the project. The inclusion of an approved
    regional project for cost-allocation purposes thus ultimately
    makes it more likely that an interregional project will be
    pursued.
    MISO filed a request for clarification and, in the
    alternative, rehearing. MISO argued that the Commission’s
    requirement to include approved regional projects in MISO’s
    cost-avoidance calculation could lead to the displacement of
    those approved projects: if, as just explained, the inclusion of
    approved regional projects increases the likelihood that an
    interregional project will be pursued, the selection of that
    project could occasion the displacement of approved regional
    projects that are rendered unnecessary. The possibility that
    already-approved regional projects could be displaced, MISO
    contended, creates uncertainty among transmission providers
    and harms investors and consumers.
    The Commission denied MISO’s petition, reiterating its
    position that MISO’s cost-avoidance methodology failed to
    account for the full range of projects displaced by interregional
    projects, thus undervaluing the benefits of an interregional
    project. The Commission also noted that MISO’s cost-
    7
    avoidance methodology lacked adequate transparency to
    comply with Order 1000 because MISO failed to explain what
    it meant for a project to be “identified,” but not approved, in its
    current regional transmission plan. Midcontinent Indep. Sys.
    Operator, Inc., 153 FERC ¶ 61,247 at P 10 (Nov. 25, 2015).
    The transmission providers forming MISO filed a petition
    for review in this court, and MISO intervened in their support.
    The transmission providers making up SERTP intervened on
    the Commission’s side. Petitioners advance two principal
    arguments: first, that the Commission did not adequately
    respond to their contention that the mandated change in cost-
    allocation methodology would displace approved projects,
    causing harm to the providers and their customers; and second,
    that the Commission’s denial of MISO’s compliance filing did
    not comport with the Commission’s affirmative obligation
    under section 206 of the Federal Power Act, 16 U.S.C. § 824e,
    to justify its rates as just and reasonable.
    II.
    At the outset, the Commission argues that we should not
    reach the merits of petitioners’ arguments for three separate
    reasons: (i) petitioners lack standing; (ii) the issues are not ripe
    for consideration; and (iii) petitioners did not exhaust one of
    their arguments. We conclude that petitioners have standing
    and that the dispute is ripe, but that petitioners failed to exhaust
    one of their arguments before the Commission.
    A.
    We consider first whether petitioners have standing to
    challenge the Commission’s actions. To establish standing,
    petitioners must demonstrate: (i) that they have suffered or will
    imminently suffer a concrete and particularized injury, (ii) that
    8
    a causal connection exists between the injury and the
    challenged conduct, and (iii) that the injury is likely to be
    redressed by a favorable judicial decision. Lujan v. Defenders
    of Wildlife, 
    504 U.S. 555
    , 560-61 (1992).
    The Commission argues that petitioners have suffered no
    cognizable injury and that any injury bears no causal
    connection to the orders on review. In the Commission’s view,
    any injury the petitioning transmission providers suffered from
    its orders is too abstract and speculative to give rise to standing.
    We need not resolve whether the petitioners have standing,
    because we conclude that the intervenor, MISO, has standing
    as the object of the orders on review.
    “[T]he presence of one party with standing is sufficient to
    satisfy Article III’s case-or-controversy requirement.”
    Rumsfeld v. Forum for Acad. & Inst. Rights, Inc., 
    547 U.S. 47
    ,
    52 n.2 (2006). A party that has properly intervened “becomes
    a full participant in the lawsuit and is treated just as if it were
    an original party.” Schneider v. Dumbarton Developers, Inc.,
    
    767 F.2d 1007
    , 1017 (D.C. Cir. 1985). That rule applies
    equally in the contexts of an appeal and a petition for review.
    See Stringfellow v. Concerned Neighbors in Action, 
    480 U.S. 370
    , 376-77 (1987). The Supreme Court has therefore
    concluded that an intervenor may maintain an appeal even if
    the original party does not appeal, as long as the intervenor has
    standing to invoke the appellate court’s jurisdiction. See
    Diamond v. Charles, 
    476 U.S. 54
    , 68 (1986).
    It follows that an intervenor with standing to assert a claim
    on petition for review may maintain an action even if the party
    originally petitioning for review lacks standing to assert the
    claim. See Greenbaum v. Bailey, 
    781 F.3d 1240
    , 1242-43 (10th
    Cir. 2015); Bond v. Utreras, 
    585 F.3d 1061
    , 1071-72 (7th Cir.
    2009); cf. Town of Chester v. Laroe Estates, Inc., 
    137 S. Ct. 9
    1645, 1651 (2017) (stating that an intervenor of right may
    “seek[] additional relief beyond that which the plaintiff
    requests” if it has standing as to the relief it seeks). See
    generally 15A Charles Alan Wright et al., Federal Practice and
    Procedure § 3902.1 (2d ed. 2018). Although our circuit has yet
    to hold as much expressly, we have applied that understanding
    without comment. See Am. Chemistry Council v. Dep’t of
    Transp., 
    468 F.3d 810
    , 821 (D.C. Cir. 2006).
    We conclude that MISO has standing to challenge the
    Commission’s denial of its compliance filing, and that we thus
    can consider petitioners’ claims that the denial is arbitrary and
    capricious and contrary to law: MISO has joined petitioners’
    arguments in full and those arguments are identical in
    substance and scope to MISO’s claims. See Town of Chester,
    137 S. Ct. at 1651. MISO, unlike petitioners, is the direct
    “object of the action” being challenged. Defenders of Wildlife,
    504 U.S. at 561. The Commission denied MISO’s compliance
    filing on the ground that it did not comply with Order 1000’s
    cost-allocation provisions. That denial requires MISO not only
    to resubmit its compliance filing but also to revise its tariff. In
    those circumstances, “there is ordinarily little question” that the
    government’s action causes the regulated party an “injury, and
    that a judgment preventing . . . that action will redress it.” Id.
    at 561-62.
    The principle that a regulated party generally has standing
    to challenge an agency action regulating its behavior holds true
    here. The challenged orders require MISO to revise its tariff,
    and that revision could require MISO to pay a greater
    proportion of the costs of certain interregional projects jointly
    undertaken by MISO and its neighboring region SERTP. A
    favorable decision from our court is likely to prevent the
    challenged revision to MISO’s tariff. Accordingly, as the
    Commission itself acknowledged in oral argument, Oral
    10
    Argument at 25:28-25:38, even if petitioners lack standing,
    MISO, as the object of the agency’s action, has standing.
    B.
    The Commission next argues that we cannot consider
    petitioners’ claims at this time because they are not ripe for our
    review. In the Commission’s view, petitioners’ claims are
    unripe because it is unclear at this point whether the
    Commission’s orders will in fact result in the displacement of
    any approved regional project. The Commission notes that, in
    the event any displacement were to occur, petitioners could
    seek rehearing and judicial review then. We conclude that
    petitioners’ claims are ripe for our review.
    We defer review of administrative decisions on ripeness
    grounds “where (1) delay would permit better review of the
    issues while (2) causing no significant hardship to the parties.”
    N. Ind. Pub. Serv. Co. v. FERC, 
    954 F.2d 736
    , 738 (D.C. Cir.
    1992). If a claim “rests ‘upon contingent future events that may
    not occur,’” it is unripe. N.Y. State Elec. & Gas Corp. v. FERC,
    
    177 F.3d 1037
    , 1040 (D.C. Cir. 1999) (quoting Texas v. United
    States, 
    523 U.S. 296
    , 300 (1998)).
    Here, review is appropriate now. Contrary to the
    Commission’s suggestion, we need not know with certainty
    whether approved projects will in fact be displaced by the
    Commission’s orders to assess whether the orders adequately
    addressed petitioners’ concerns. The actual displacement of
    approved projects tells us little about the adequacy of the
    Commission’s explanation, especially when the Commission
    justified its decision on grounds that acknowledge the
    possibility that displacement will occur. Nor would further
    factual development aid the determination whether the
    Commission failed to make the requisite finding of just and
    11
    reasonable rates under section 206 of the Federal Power Act.
    The claim that the Commission failed to make an affirmative
    finding under section 206 does not depend on factual questions
    about the displacement of projects.
    C.
    Finally, the Commission argues that we cannot reach the
    merits of one of petitioners’ claims because it was not properly
    presented to the agency in a request for rehearing. We agree.
    Under 16 U.S.C. § 825l(b), parties seeking judicial review
    of the Commission’s orders under the Federal Power Act must
    “first petition for rehearing of those orders and must
    themselves raise in that petition all of the objections urged on
    appeal,” unless they can show “reasonable grounds” for their
    failure to do so. Wabash Valley Power Ass’n v. FERC, 
    268 F.3d 1105
    , 1114 (D.C. Cir. 2001) (formatting modified and
    citations omitted). Whether petitioners have complied with
    this “unusually strict [exhaustion] requirement,” id., hinges on
    whether their request for rehearing “alerted the Commission to
    the legal arguments” they now raise on judicial review, Save
    Our Sebasticook v. FERC, 
    431 F.3d 379
    , 381 (D.C. Cir. 2005).
    Petitioners must raise each argument with “specificity,” Wis.
    Power & Light Co. v. FERC, 
    363 F.3d 453
    , 460 (D.C. Cir.
    2004); objections may not be preserved either “indirectly,”
    Office of the Consumers’ Counsel v. FERC, 
    914 F.2d 290
    , 295
    (D.C. Cir. 1990), or “implicitly,” Kelley ex rel. Mich. Dep’t of
    Nat’l Res. v. FERC, 
    96 F.3d 1482
    , 1488 (D.C. Cir. 1996).
    In this case, petitioners raise two objections to the
    Commission’s orders. First, they argue that the Commission
    failed to respond adequately to their concerns about the
    displacement of approved regional projects and the harms to
    transmission providers and customers resulting therefrom.
    12
    Petitioners adequately raised that argument in their petition for
    rehearing.
    Second, petitioners contend that the Commission’s orders
    impermissibly shifted to them the burden of proving that the
    rates proposed in MISO’s compliance filing were just and
    reasonable. In their view, section 206 of the Federal Power Act
    required the Commission first to prove that the proposed rates
    were unjust and unreasonable, and then determine new rates
    that would be just and reasonable. But that argument, as the
    Commission points out, appeared nowhere in petitioners’
    requests for rehearing. Petitioners’ rehearing requests instead
    focused on the harms they would suffer as a result of the
    Commission’s orders, not on whether the Commission had
    improperly shifted the burden of proving just and reasonable
    rates to the petitioners.
    Petitioners respond that the question whether the
    Commission has complied with its statutory obligation to
    ensure just and reasonable rates ultimately inheres in every
    challenge to the Commission’s rate orders, and thus can never
    be considered a new argument raised for the first time in a
    petition for review. Petitioners misunderstand the Federal
    Power Act’s exhaustion requirement. To bring a particular
    claim in a petition for review, a petitioner needs to have alerted
    the Commission to the specific “legal argument[]” presented
    on rehearing (absent a reasonable ground for not doing so).
    Save Our Sebasticook, 431 F.3d at 381. Petitioners failed to do
    so here.
    If we were to accept petitioners’ rationale, parties would
    never need to raise specific legal arguments before the
    Commission as long as they broadly challenge the justness and
    reasonableness of rates under section 206 before the court of
    appeals. Such a holding would undermine the Federal Power
    13
    Act’s exhaustion requirement as to a class of claims, and would
    contravene our precedents requiring that parties specifically—
    rather than implicitly or indirectly—raise claims before the
    Commission on rehearing. Here, petitioners failed to satisfy
    that requirement with regard to their contention that the
    Commission did not comply with section 206 of the Federal
    Power Act.
    III.
    On the merits, petitioners argue that the Commission failed
    to give adequate consideration to their concerns about the
    effects of displacing approved regional projects. We disagree.
    We set aside the Commission’s actions if they are
    “arbitrary, capricious, an abuse of discretion, or otherwise not
    in accordance with law.” 5 U.S.C. § 706(2)(A). “An agency’s
    failure to respond meaningfully to objections raised by a party
    renders its decision arbitrary and capricious.”             PPL
    Wallingford Energy LLC v. FERC, 
    419 F.3d 1194
    , 1198 (D.C.
    Cir. 2005) (internal quotation marks omitted). But if “FERC
    ‘has considered the relevant factors and articulated a rational
    connection between the facts found and the choice made,’ we
    will uphold its decision.” Aera Energy LLC v. FERC, 
    789 F.3d 184
    , 190 (D.C. Cir. 2015) (quoting Transcon. Gas Pipe Line
    Corp. v. FERC, 
    518 F.3d 916
    , 919 (D.C. Cir. 2008)). That is
    the case here.
    Petitioners contend that the Commission failed to give
    adequate consideration to four concerns they had raised in their
    request for rehearing. We conclude that the Commission
    adequately addressed each of petitioners’ concerns.
    First, petitioners argued generally that the Commission’s
    orders could require them to replace an already-approved
    14
    regional project with a new interregional project. In response,
    the Commission acknowledged that possibility, noting that
    “displacing a selected regional transmission project with a
    more efficient or cost-effective interregional transmission
    solution” would not be “inconsistent with MISO’s regional
    transmission planning process.” Midcontinent Indep. Sys.
    Operator, Inc., 153 FERC ¶ 61,247 at P 12.
    Second, petitioners contended that the displacement of
    approved regional projects would harm certain stakeholders in
    various ways. For instance, developers might have already
    expended significant sums of money on approved projects that
    would be subject to displacement by a new interregional
    project. And on a prospective basis, developers might find it
    more difficult to gain access to financing for an approved
    project if it might be displaced. That could in turn have the
    effect of raising rates for consumers.
    The Commission offered several responses.                The
    Commission’s central response was that failing to account for
    approved regional projects that would be displaced by an
    interregional project would undervalue the benefits of the
    interregional project. The cost-avoidance method could
    approximate the benefits of an interregional project, the
    Commission explained, if it captured all the regional benefits
    gained by the ISO or RTO, including the efficiency and public-
    policy benefits of the interregional project. But it could capture
    all the regional benefits only if it included all regional projects
    that stood to be displaced by an interregional project. Indeed,
    the Commission noted, approved projects tend to be the most
    efficient and cost-effective projects. So by excluding them
    from the calculation of benefits of an interregional project,
    MISO would disregard the most beneficial projects. The result
    would be a significant undervaluation of the benefits of the
    interregional project.
    15
    Undervaluing the benefits, the Commission explained,
    would violate Order 1000’s core cost-allocation principle: that
    an interregional project’s costs be allocated in a manner
    “roughly commensurate” with the project’s benefits.
    Midcontinent Indep. Sys. Operator, Inc., 153 FERC ¶ 61,247
    at P 10. As a result, MISO would be allocated a smaller
    proportion of an interregional project’s costs, relative to its
    neighbor SERTP, than would be appropriate had the benefits
    been properly calculated. In addition, MISO would be less
    likely to pursue “more efficient or cost-effective” interregional
    projects. Id. As explained, undervaluation of an interregional
    project’s benefits for cost-allocation purposes would result in
    an under-appreciation of the project’s benefits for purposes of
    deciding whether to undertake the project.
    In short, the Commission, while not disputing the
    possibility that the harms raised by petitioners could come to
    pass, determined that the interest in an appropriate allocation
    of the costs of an interregional project (and the resulting
    implications for undertaking interregional projects) required
    MISO to account for already-approved regional projects in its
    cost-allocation methodology. We see no basis for setting aside
    that determination by the Commission.
    Third, petitioners argued in their request for rehearing that,
    “in the interests of certainty and fairness to potential [project]
    bidders,” there “must be some point at which the comparisons
    of different regional and interregional projects concludes.”
    J.A. 277. In petitioners’ view, the logical point to make that
    comparison is after the identification of projects but before
    their approval. The Commission permissibly disagreed,
    concluding that petitioners could properly account for the
    benefits of an interregional project only if they considered the
    benefits of approved projects, not merely of identified ones.
    That might lead to the displacement of approved regional
    16
    projects only when it is appropriate to do so—i.e., when an
    interregional project is selected in a region’s own transmission
    planning process as the more efficient or cost-effective solution
    to a transmission need. The Commission further noted that
    other regions had adopted the same approach without protest.
    Fourth, petitioners contended that their existing tariff did
    “not contemplate removing projects from [their] bid
    solicitation process.” J.A. 276. In response, the Commission
    pointed out that MISO’s tariff already contained provisions
    allowing for the removal of bids under certain circumstances,
    including cost increases or changes in developer qualifications.
    In light of those provisions, the Commission explained, it
    would not be inconsistent with MISO’s transmission planning
    process to allow the displacement of approved regional projects
    when those projects are rendered unnecessary by a more
    optimal interregional project.
    In the end, we conclude that the Commission adequately
    responded to petitioners’ concerns about the possible effects of
    including approved regional projects in the cost-allocation
    calculation.     Petitioners ultimately disagree with the
    Commission’s policy judgment about whether the importance
    of properly calculating an interregional project’s benefits
    outweighs the effects of potentially displacing approved
    regional projects.      Petitioners’ disagreement with the
    Commission’s resolution of that issue does not render the
    Commission’s explanation any less thorough or reasoned.
    *    *   *    *   *
    For the foregoing reasons, we deny the petition for review.
    It is so ordered.