Sierra Club v. FERC , 827 F.3d 36 ( 2016 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued November 13, 2015             Decided June 28, 2016
    No. 14-1275
    SIERRA CLUB AND GALVESTON BAYKEEPER,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    AMERICAN PETROLEUM INSTITUTE, ET AL.,
    INTERVENORS
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    Nathan Matthews argued the cause for petitioners. With
    him on the briefs was Sanjay Narayan.
    Robert H. Solomon, Solicitor, Federal Energy Regulatory
    Commission, argued the cause for respondent. With him on
    the brief were David L. Morenoff, General Counsel, and Karin
    L. Larson, Attorney.
    Jonathan S. Franklin argued the cause for respondent-
    intervenors Freeport LNG Development, L.P., et al. With
    him on the brief were Lisa M. Tonery and Charles R. Scott.
    2
    Catherine E. Stetson was on the brief for intervenor
    American Petroleum Institute in support of respondent. Stacy
    R. Linden and Benjamin Norris IV entered appearances.
    Before: ROGERS, GRIFFITH, and MILLETT, Circuit Judges.
    Opinion for the Court filed by Circuit Judge MILLETT.
    MILLETT, Circuit Judge: The Sierra Club and Galveston
    Baykeeper (the “Associations”) take issue with the Federal
    Energy Regulatory Commission’s decision authorizing
    Freeport LNG Development, L.P. to redesign its liquefied
    natural gas terminal in Texas to support export operations.
    Specifically, the Associations argue that the Commission’s
    analysis of the proposal’s impact on the environment ran
    afoul of the National Environmental Policy Act of 1969
    (“NEPA”), 42 U.S.C. § 4321 et seq. We hold that the
    Associations have standing to press their challenges to the
    Commission’s orders and that their case is not moot, but we
    deny the petition for review on the merits. To the extent the
    Associations complain about the environmental consequences
    of exporting natural gas from Freeport’s terminal, those
    objections should be raised in the pending challenge to the
    Department of Energy’s order authorizing Freeport to export
    natural gas. On the narrower question of whether the
    Commission’s       analysis    of     the    non-export-related
    environmental consequences of Freeport’s proposal itself
    complied with NEPA, we find no error in the Commission’s
    analysis that would rise to the level of arbitrary or capricious
    decision-making.
    3
    I
    A
    Export authorizations for natural gas implicate a tangled
    web of regulatory processes. The Department of Energy
    maintains exclusive authority over the export of natural gas as
    a commodity. 42 U.S.C. § 7151(b). The Natural Gas Act,
    though, authorizes the exportation of natural gas from the
    United States unless the Department specifically determines
    that doing so “will not be consistent with the public interest.”
    15 U.S.C. § 717b(a). In addition, the Department of Energy’s
    determination of the public interest in the export of natural
    gas depends on the country to which the gas will be exported.
    If it is a country with which the United States has a “free trade
    agreement requiring national treatment for trade in natural
    gas,” the Natural Gas Act makes the decision for the
    Department, because the Act “deem[s]” export “to be
    consistent with the public interest, and applications for such
    * * * exportation shall be granted without modification or
    delay.” 
    Id. § 717b(c).
    On the other hand, if the gas will be
    exported to a country with which the United States does not
    have such a trade agreement, the Department must
    independently determine whether such exports would be
    inconsistent with the public interest. See 
    id. § 717b(a).
    1
    1
    Currently, the United States has natural gas free-trade agreements
    with Australia, Bahrain, Canada, Chile, Colombia, the Dominican
    Republic, El Salvador, Guatemala, Honduras, Jordan, Mexico,
    Morocco, Nicaragua, Oman, Panama, Peru, the Republic of Korea,
    and Singapore. See J.A. 302; U.S. Department of Energy, Office of
    Fossil Energy, How to Obtain Authorization to Import and/or
    Export Natural Gas and LNG, http://energy.gov/fe/services/
    natural-gas-regulation/how-obtain-authorization-import-andor-
    export-natural-gas-and-lng (last visited June 27, 2016).
    4
    The Department has delegated to the Federal Energy
    Regulatory Commission the authority to “[a]pprove or
    disapprove the construction and operation of particular
    [export] facilities, the site at which such facilities shall be
    located, and with respect to natural gas that involves the
    construction of new domestic facilities, the place of * * * exit
    for [natural gas] exports.” U.S. Department of Energy,
    Delegation Order No. 00-004.00A, § 1.21.A (May 16, 2006);
    cf. 15 U.S.C. § 717b(e)(1) (“The [Federal Power]
    Commission shall have the exclusive authority to approve or
    deny an application for the siting, construction, expansion, or
    operation of an LNG [liquefied natural gas] terminal.”). As a
    result, if an operator of a natural gas terminal like Freeport
    wants to export natural gas and has to construct or modify
    facilities to do so, it must obtain authorizations from both the
    Department of Energy (to export) and the Commission (to
    construct and to operate the necessary facilities). And if the
    export will be to a natural gas free-trade country, the only
    potential public-interest analysis ever made is the
    Commission’s when approving the “siting, construction,
    expansion or operation of an LNG terminal.” 15 U.S.C.
    § 717b(e)(1).
    In addition to those public-interest determinations,
    authorizations to export natural gas also require an
    environmental review under NEPA.              See 42 U.S.C.
    § 4332(2)(C). When, as here, the agency determines that the
    action under review is a “major Federal action[]” that will
    “significantly affect[] the quality of the human environment,”
    the agency must prepare a detailed Environmental Impact
    Statement that addresses (i) the environmental impact of the
    proposed action, (ii) any “adverse environmental effects” that
    “cannot be avoided” if the proposal is implemented, (iii)
    available alternatives to the proposed action, (iv) the
    “relationship between local short-term uses of [the]
    5
    environment and the maintenance and enhancement of long-
    term productivity,” and (v) any “irreversible and irretrievable
    commitments of resources” that “would be involved in the
    proposed action should it be implemented.” 
    Id. In analyzing
    the environmental impact of a project,
    NEPA obligates the agency to consider not just the “direct”
    environmental effects of the proposed action that “are caused
    by the action and occur at the same time and place,” but also
    the action’s “indirect” environmental effects that “are caused
    by the action and are later in time or farther removed in
    distance, but are still reasonably foreseeable.” 40 C.F.R.
    § 1508.8. The agency must also consider the action’s
    “cumulative impact”—that is, the impact on the environment
    that would result “from the incremental impact of the action
    when added to other past, present, and reasonably foreseeable
    future actions regardless of what agency (Federal or non-
    Federal) or person undertakes such other actions.” 
    Id. § 1508.7.
    Notwithstanding the limited scope of the Commission’s
    delegated authority under the Natural Gas Act, that Act
    designates the Commission to be “the lead agency for the
    purposes of coordinating all applicable Federal authorizations
    and for the purposes of complying with the National
    Environmental Policy Act.” 15 U.S.C. § 717n(b)(1); see also
    42 U.S.C. § 7172(a)(2)(B). As a result, the Department of
    Energy participates in the NEPA process only as a
    “cooperating agency,” 40 C.F.R. § 1501.6(b), while the
    Commission is ultimately responsible for “supervis[ing] the
    preparation of [the] environmental impact statement,” 
    id. § 1501.5.
    That arrangement makes it possible for the
    Department to adopt the Commission’s environmental
    analysis as its own for purposes of any additional NEPA
    review triggered by an export-authorization request. But the
    6
    Department must independently review the Commission’s
    work and conclude that the Department’s own “comments and
    suggestions have been satisfied.” 
    Id. § 1506.3(c).
    B
    In 2004, the Commission authorized Freeport to site,
    construct, and operate a liquefied natural gas import terminal
    on Quintana Island in Brazoria County, Texas. That facility
    was placed into service in 2008.
    As it happens, an increase in the availability of cheap
    domestic natural gas during the last decade caused the market
    for importing gas to decline. As a result, Freeport shifted its
    operations toward exporting and, in 2009, obtained
    authorization from the Commission to operate its existing
    terminal facility for both exporting and importing natural gas
    on a short-term basis. In 2011 and 2012, Freeport sought
    authorization from the Commission both to modify its
    facilities to better support gas exports, and to construct
    additional gas liquefaction facilities to supplement its export
    operations. (Throughout this opinion, we refer to those two
    projects collectively as the “Freeport Projects.”).
    As required by the Natural Gas Act and NEPA, the
    Commission undertook an extensive environmental review of
    the Freeport Projects. Deeming the two projects to be
    “connected actions,” 40 C.F.R § 1508.25, the Commission
    prepared a single Environmental Impact Statement. The
    Department of Energy, the Environmental Protection Agency,
    the Department of Transportation, the U.S. Army Corps of
    Engineers, and the National Oceanic and Atmospheric
    Administration all participated in that consolidated review as
    “cooperating agencies.” J.A. 679.
    7
    Meanwhile, in 2010 and 2011, Freeport separately sought
    authorization from the Department of Energy to export natural
    gas. The Department approved Freeport’s request for free-
    trade agreement countries in February 2011, and conditionally
    approved Freeport’s application with respect to non-free trade
    agreement countries in May and November 2013. The
    conditional order explained that the Department of Energy
    would participate in the Commission’s ongoing
    environmental review of the Freeport Projects as a
    cooperating agency, and that the Department’s final
    authorization would be contingent on satisfactory completion
    of that environmental review process.
    The Commission released its Final Environmental Impact
    Statement in June 2014. That Statement found that the
    Freeport Projects “would result in some adverse
    environmental impacts,” but that those impacts would be
    “mostly temporary and short-term” as long as Freeport
    implemented mitigation procedures proposed by the
    Commission.      The following month, the Commission
    conditionally authorized both Freeport Projects.      After
    considering the Final Environmental Impact Statement and all
    substantive public comments, the Commission determined
    that, if Freeport complied with specified environmental
    conditions, the Projects would not be inconsistent with the
    public interest.
    The Associations intervened in the Commission’s
    proceeding and timely sought rehearing. As relevant here,
    they argued that the Commission failed (i) to consider the
    indirect environmental effects of a possible increase in
    domestic natural gas production being induced by the
    Freeport Projects, and (ii) to analyze the cumulative
    environmental effects of those Projects with “the many
    proposed export projects” across the country, including, “at a
    8
    minimum,” those already authorized and “all other export
    projects to have received conditional authorization from” the
    Department of Energy. J.A. 1250, 1273.
    The Commission denied the Associations’ petition for
    rehearing. The Commission rejected the argument that
    increased domestic natural gas production was a causally
    related or reasonably foreseeable indirect effect of the
    Freeport Projects. The Commission also determined that the
    cumulative impact of all other authorized or pending export
    projects nationwide fell beyond the regulatory definition of
    “cumulative impact.”
    The next day, the Department of Energy issued its final
    order authorizing Freeport to export natural gas to non-free
    trade agreement countries. The Department reconfirmed its
    findings from the earlier conditional order, and also addressed
    “the remaining issue: the potential environmental impacts”
    from Freeport’s export proposals.          J.A. 1403.      The
    Department concluded that “the proposed exports have not
    been shown to be inconsistent with the public interest.” 
    Id. The Department
    subsequently denied the Associations’
    petitions for reconsideration. 2
    II
    We start where we must always start: “with the question
    of our jurisdiction.” Brotherhood of Locomotive Eng’rs and
    Trainmen v. Surface Transp. Bd., 
    457 F.3d 24
    , 27 (D.C. Cir.
    2006). The Commission argues that we lack jurisdiction
    because the Associations do not have standing, and because
    2
    The Associations’ petition for review of the Department’s
    decision is pending before this court. See Sierra Club v.
    Department of Energy, No. 15-1489.
    9
    their NEPA claim has been mooted by additional
    environmental analyses conducted by the Department of
    Energy as part of its own public-interest review. Neither
    argument succeeds.
    A
    An association will have standing if “(1) at least one of
    its members would have standing to sue in [its] own right, (2)
    the interests the association seeks to protect are germane to its
    purpose, and (3) neither the claim asserted nor the relief
    requested requires that an individual member of the
    association participate in the lawsuit.” Sierra Club v. EPA,
    
    292 F.3d 895
    , 898 (D.C. Cir. 2002). There is no dispute that
    the environmental claims the Associations assert are germane
    to their institutional purposes, or that the relief sought under
    the Administrative Procedure Act does not require the
    participation of individual members.           The question of
    individual-member injury is where the rub is.
    It is settled law that “an agency’s failure to prepare (or
    adequately prepare) an [Environmental Impact Statement]
    before taking action with adverse environmental
    consequences” constitutes the “archetypal procedural injury”
    redressable under Article III. WildEarth Guardians v. Jewell,
    
    738 F.3d 298
    , 305 (D.C. Cir. 2013); see Florida Audubon
    Society v. Bentsen, 
    94 F.3d 658
    , 665 (D.C. Cir. 1996) (en
    banc). The bottom-line standing question in this case, then, is
    whether one of either Association’s members faces a concrete
    injury that is “tethered to” the Commission’s decision to
    authorize the Freeport Projects’ construction or operation
    notwithstanding the Commission’s allegedly inadequate
    NEPA review, WildEarth 
    Guardians, 738 F.3d at 305
    . See
    also Florida Audubon 
    Society, 94 F.3d at 668
    .
    10
    At least one Sierra Club member has risen to that task,
    and that is all that Article III requires. See Massachusetts v.
    EPA, 
    549 U.S. 497
    , 518 (2007) (“Only one of the petitioners
    needs to have standing to permit us to consider the petition for
    review.”); Americans for Safe Access v. DEA, 
    706 F.3d 438
    ,
    443 (D.C. Cir. 2013). Teresa Cornelison is a member of the
    Sierra Club and lives “approximately 0.5 miles from the
    Freeport LNG facility.” Pet. Add. A-18. She has attested that
    “the additional noise made during construction will * * *
    hinder [her] enjoyment of [her] home,” and that “[i]f the
    terminal were built, [she] would not go outside to relax or
    walk on the beach as frequently because of the noise from
    * * * the construction of the facility[.]” 
    Id. at A-19.
    Such
    credible claims of exposure to increased noise and its
    disruption of daily activities, backed up by specific factual
    representations in an affidavit or declaration, are sufficient to
    satisfy Article III’s injury-in-fact requirement.            See
    Communities Against Runway Expansion, Inc. v. FAA, 
    355 F.3d 678
    , 684–685 (D.C. Cir. 2004). That aesthetic injury,
    moreover, is linked directly to the Commission’s
    authorizations of the Freeport construction projects. See, e.g.,
    J.A. 1192 (Order Granting Authorizations) (“Land access
    within the Phase II Modification Project site * * * would
    require development of an approximately 7,000-foot-long
    plant road system [and] * * * 3,180 feet [of the plant road
    system] would require new construction.”). That satisfies
    Article III.
    The Commission says that is not enough, and that the
    Associations also must tie their injury to the specific
    “increase[]” in “natural gas production that was [allegedly]
    caused by the challenged FERC orders.” Resp. Br. 24. That
    argument “slice[s] the salami too thin.”              WildEarth
    
    Guardians, 738 F.3d at 307
    . As we have held before, we hold
    again: it is sufficient for standing purposes that the “aesthetic
    11
    injury follows from an inadequate [Environmental Impact
    Statement] whether or not the inadequacy concerns the same
    environmental issue that causes their injury.” 
    Id. In NEPA
    procedural-injury cases, an “adequate causal chain” contains
    two links: “one connecting the omitted EIS to some
    substantive government decision that may have been wrongly
    decided because of the lack of an [adequate] EIS,” and “one
    connecting that substantive decision to the plaintiff’s
    particularized injury.” Florida Audubon 
    Society, 94 F.3d at 668
    .
    That is to say, regardless of how the Commission
    allegedly failed to discharge its NEPA obligation, that failure
    led directly to authorization of the Freeport Projects, which in
    turn is the source of Cornelison’s injury. The proof is in the
    pudding: if we were to vacate the Commission’s order
    authorizing the Freeport Projects for violating NEPA, not
    only would Cornelison’s injuries be redressed, the remedy
    would also be “‘limited to the inadequacy’—here, a deficient
    [Environmental Impact Statement]—‘that produced the injury
    in fact that the [petitioners] ha[ve] established.’” WildEarth
    
    Guardians, 738 F.3d at 307
    (quoting DaimlerChrysler Corp.
    v. Cuno, 
    547 U.S. 332
    , 353 (2006)).
    The Commission’s reliance on National Committee for
    the New River, Inc. v. FERC, 
    433 F.3d 830
    (D.C. Cir. 2005),
    fares no better. That case, which did not involve NEPA, held
    that the environmental and aesthetic harms alleged had to be
    linked to “the route realignments themselves” because route
    realignments were what the challenged agency action
    authorized. 
    Id. at 832.
    Here, the specific agency action being
    challenged is the NEPA analysis. And Cornelison has
    grounded her injury in that flawed NEPA analysis and its end
    product that injures her: construction of the projects.
    12
    B
    Next is mootness. In 2014, the Department of Energy,
    “in response to challenges raised by Sierra Club and other
    commenters in the Freeport LNG Export proceeding and other
    export proceedings pending at the Department of Energy,”
    issued two informational reports that “evaluated specific
    environmental aspects of the LNG production and export
    chain.” Resp. Br. 28–29. On that basis, the Commission
    asserts that the Associations’ petition is moot.
    That     argument      woefully    misunderstands     the
    Associations’ claim. They do not seek some quantum of
    additional environmental information for its own sake, nor are
    they, in this case, challenging the Department of Energy’s
    analysis of environmental consequences. Their argument is
    that the Commission bungled its NEPA review by failing to
    consider the specific indirect and cumulative effects that the
    Associations identified.      The Department of Energy’s
    additional reports do not remedy that problem. See Pet. Reply
    Br. 9 (“The Department of Energy’s reports played no part in
    the Commission’s decision-making, and did not include the
    procedures and substance required under NEPA to ensure that
    environmental considerations inform such decision-
    making.”). The Associations’ hope is that, if the Commission
    were to consider those factors, perhaps it would reach a
    different conclusion on whether the Freeport Projects are
    consistent with the public interest. After all, “[t]he idea
    behind NEPA is that if the agency’s eyes are open to the
    environmental consequences of its actions and if it considers
    options that entail less environmental damage, it may be
    persuaded to alter what it proposed.” Lemon v. Geren, 
    514 F.3d 1312
    , 1315 (D.C. Cir. 2008).
    13
    In short, because the Commission’s NEPA analysis was
    an integral component of authorizing the export construction
    projects—without which the Department of Energy’s separate
    export authorization would be pointless—and because, if error
    occurred, the Commission might come to a different result on
    remand, the lawfulness of the Commission’s action remains
    very much a live legal issue.
    III
    Before addressing the merits of the Associations’ NEPA
    claim, we pause to underscore what we are not deciding in
    this case. Because the Associations do not challenge the
    propriety or scope of the Commission’s delegated authority
    under the Natural Gas Act, or the interplay between the
    Commission and the Department of Energy when the former
    is acting as the “lead agency” in reviewing the environmental
    effects of a natural gas export operation under NEPA, we take
    those agency roles as we find them. See 15 U.S.C.
    § 717n(b)(1); see also 42 U.S.C. § 7172(a)(2)(B). Nor have
    the Associations argued that the Commission impermissibly
    “segmented” its review of the Freeport Projects from the
    larger inter-agency export authorization process, and “thereby
    fail[ed] to address the true scope and impact of the activities
    that should be under consideration,” Delaware Riverkeeper
    Network v. FERC, 
    753 F.3d 1304
    , 1313 (D.C. Cir. 2014); 
    id. at 1314
    (“[T]he rule against segmentation * * * ‘prevent[s]
    agencies from dividing one project into multiple individual
    actions each of which individually has an insignificant
    environmental impact, but which collectively have a
    substantial impact.’”) (alteration in original) (quoting Natural
    Resources Defense Council, Inc. v. Hodel, 
    865 F.2d 288
    , 297
    (D.C. Cir. 1988)).
    14
    We also express no opinion on whether (i) the
    Commission’s environmental analysis would have been
    adequate to satisfy the Department of Energy’s own
    independent NEPA obligation in authorizing Freeport to
    export natural gas; or (ii) the Commission’s construction
    authorizations and the Department’s export authorizations
    qualified as “connected actions” for purposes of NEPA
    review, see 40 C.F.R. § 1508.25(a)(1). As the Associations
    acknowledged at oral argument, Tr. of Oral Arg. at 20–21
    (Nov. 13, 2015), objections concerning the environmental
    consequences stemming from the actual export of natural gas
    from the Freeport terminal, including increased emissions and
    induced production, are raised in their parallel challenge to
    the Department of Energy’s order authorizing Freeport to
    export natural gas to non-free trade countries. Because the
    Natural Gas Act places export decisions squarely and
    exclusively within the Department of Energy’s wheelhouse,
    any such challenges to the environmental analysis of the
    export activities themselves must be raised in a petition for
    review from the Department’s decision to authorize exports.
    Accordingly, we limit our analysis in this case solely to
    whether the Commission discharged its NEPA duty to
    adequately consider the indirect and cumulative
    environmental effects of authorizing the “siting, construction,
    expansion, [and] operation” of the Freeport Projects. 15
    U.S.C. § 717b(e)(1). On that front, the Associations argue
    that the Commission’s NEPA analysis fell short in three
    respects. First, they contend that the Commission failed
    adequately to consider the Freeport Projects’ indirect effect of
    inducing increased domestic gas production and prompting
    greater reliance on coal as a fuel source. Second, they
    contend that the Commission failed adequately to analyze the
    cumulative environmental effects of the Freeport Project
    when combined with other export projects nationwide that
    15
    either recently had been approved or were still pending.
    Third, the Associations claim that, by measuring certain
    emissions in pounds per megawatt-hour rather than tons per
    year, the Commission understated the full extent of the
    Projects’ emissions. Pet. Br. 38.
    In reviewing the Associations’ challenges, our task is not
    to “flyspeck” the Commission’s environmental analysis for
    “any deficiency no matter how minor.” Theodore Roosevelt
    Conservation Partnership v. Salazar, 
    661 F.3d 66
    , 75 (D.C.
    Cir. 2011). Our job is “simply to ensure that the agency has
    adequately considered and disclosed the environmental
    impact of its actions and that its decision is not arbitrary or
    capricious.” Baltimore Gas & Elec. Co. v. Natural Resources
    Defense Council, Inc., 
    462 U.S. 87
    , 97–98 (1983); see also
    Natural Resources Defense Council, Inc. v. Hodel, 
    865 F.2d 288
    , 294 (D.C. Cir. 1988) (If an agency’s NEPA analysis is
    “fully informed and well considered, it is entitled to judicial
    deference and a reviewing court should not substitute its own
    policy judgment.”). None of the Associations’ challenges can
    survive that deferential standard of review.
    A
    NEPA obligated the Commission to factor into its
    environmental analysis not just the direct, but also the
    indirect, environmental effects of the Freeport Projects’
    construction and operation—that is, those effects that are
    “later in time or farther removed in distance,” yet “reasonably
    foreseeable.” Department of Transp. v. Public Citizen, 
    541 U.S. 752
    , 764 (2004); see 40 C.F.R. § 1508.8. That does not
    mean that the Commission had to examine everything for
    which the Projects could conceivably be a but-for cause. See
    Public 
    Citizen, 541 U.S. at 767
    ; Village of Bensenville v.
    FAA, 
    457 F.3d 52
    , 65 (D.C. Cir. 2006) (“Even under NEPA, a
    16
    ‘but for’ causal relationship is insufficient to make an agency
    responsible for a particular effect.”) (internal quotation marks
    omitted). Instead, the effect must be “‘sufficiently likely to
    occur that a person of ordinary prudence would take it into
    account in reaching a decision.’” City of Shoreacres v.
    Waterworth, 
    420 F.3d 440
    , 453 (5th Cir. 2005) (quoting
    Sierra Club v. Marsh, 
    976 F.2d 763
    , 767 (1st Cir. 1992)).
    NEPA thus “requires a reasonably close causal relationship’
    between the environmental effect and the alleged cause,”
    which is analogous to “the ‘familiar doctrine of proximate
    cause from tort law.’” Public 
    Citizen, 541 U.S. at 767
    .
    Additionally, the Commission’s NEPA analysis did not
    have to address the indirect effects of the anticipated export of
    natural gas. That is because the Department of Energy, not
    the Commission, has sole authority to license the export of
    any natural gas going through the Freeport facilities. In the
    specific circumstances where, as here, an agency “has no
    ability to prevent a certain effect due to” that agency’s
    “limited statutory authority over the relevant action[],” then
    that action “cannot be considered a legally relevant ‘cause’ of
    the effect” for NEPA purposes. Public 
    Citizen, 541 U.S. at 771
    .
    The Associations argue that the Commission should have
    factored in the increase in domestic natural gas production
    that, in their view, the Freeport Projects would induce. But
    that challenge again focused on the impact of natural gas
    exports from the Freeport Projects on domestic production,
    and export effects do not fall within the Commission’s
    bandwidth. To the extent that the Associations’ argument
    focuses on induced production from domestic operations, we
    disagree. The Commission reasonably explained that the
    asserted linkage was too attenuated to be weighed in its
    particular NEPA analysis.
    17
    In particular, the Commission found no evidence that the
    Projects by themselves would lead to increased gas
    production because “no specific shale-play [had] been
    identified as a source of natural gas for” the Projects. J.A.
    1209. More importantly, there was no evidence suggesting
    that the gas to be processed in the Freeport facility,
    independent of the export authorization, would “come from
    future, induced natural gas production, as opposed to from
    existing production, particularly in light of the longtime,
    extensive natural gas development that has already occurred
    in Texas, including in its shale areas.” 
    Id. at 1270
    (emphasis
    in original). Accordingly, the Commission concluded that the
    “potential environmental effects associated with additional
    natural gas production [were not] sufficiently causally related
    to the Freeport LNG Projects to warrant a detailed analysis.”
    
    Id. The Associations
    level two objections to the
    Commission’s reasoning, but neither surmounts the high
    hurdle of demonstrating arbitrary and capricious decision-
    making.
    First, the Associations says it is “self-evident” under
    “[b]asic economic principles” that authorizing the Freeport
    Projects will lead to the Department of Energy granting an
    export license, which in turn will increase domestic gas
    production and the price of domestic natural gas, which next
    will drive consumers toward cheaper energy sources,
    including more environmentally harmful products like coal.
    That increase in both gas production and coal use will,
    according to the Associations, cause domestic greenhouse gas
    and ozone emissions to rise. Pet. Br. 23; see 
    id. at 21–23.
    Perhaps. But critical to triggering that chain of events is
    the intervening action of the Department of Energy in
    18
    granting an export license. The Department’s independent
    decision to allow exports—a decision over which the
    Commission has no regulatory authority—breaks the NEPA
    causal chain and absolves the Commission of responsibility to
    include in its NEPA analysis considerations that it “could not
    act on” and for which it cannot be “the legally relevant
    cause.” Public 
    Citizen, 541 U.S. at 769
    .
    The Associations rely on the Eighth Circuit’s decision in
    Mid States Coalition for Progress v. Surface Transportation
    Board, 
    345 F.3d 520
    (2003). In that case, the court found
    inadequate the Surface Transportation Board’s Environmental
    Impact Statement analyzing the construction and
    rehabilitation of hundreds of miles of railroad lines for the
    transportation of coal. 
    Id. at 532.
    The project was anticipated
    to make an additional 100 million tons of coal available for
    annual usage, yet the Board failed to factor the environmental
    effects of that known increase in coal usage into its analysis.
    The Eighth Circuit concluded that, even if the full extent of
    the environmental impact of the increased coal usage was not
    known, the nature of the ensuing environmental effects
    plainly was—indeed, it had been identified by the Board
    itself. 
    Id. at 549.
    “[W]hen the nature of the effect is
    reasonably foreseeable but its extent is not,” the court
    concluded, an agency “may not simply ignore the effect” in
    its NEPA review. 
    Id. (emphasis in
    original).
    Even assuming the correctness of a decision that does not
    bind this circuit, this case looks nothing like Mid States.
    Here, the Associations have not identified any specific and
    causally linear indirect consequences that could reasonably be
    foreseen and factored into the Commission’s environmental
    analysis that exist apart from the intervening Department of
    Energy decision to authorize exports.
    19
    Second, the Associations say the Commission acted
    arbitrarily and capriciously by not taking sufficient account of
    the Energy Information Administration’s 2012 report on the
    “Effect of Increased Natural Gas Exports on Domestic Energy
    Markets,” which (according to the Associations) “specifically
    predicted the extent to which LNG exports from the Gulf
    Coast would increase gas production and coal use.” Pet. Br.
    23; see generally U.S. ENERGY INFORMATION ADMIN., EFFECT
    OF INCREASED NATURAL GAS EXPORTS ON DOMESTIC ENERGY
    MARKETS 1, 3 (Jan. 2012) (“2012 Report”). Again, that
    argument treads on environmental consequences tied to the
    Department of Energy’s export authorization that, under
    Public Citizen, fall outside the Commission’s NEPA
    wheelhouse.
    In rejecting the Associations’ challenges, we are mindful
    that “[t]he grounds upon which an administrative order must
    be judged are those upon which the record discloses that its
    action was based,” SEC v. Chenery Corp., 
    318 U.S. 80
    , 87
    (1943), and that the Commission did not explicitly consider
    the extent to which Public Citizen placed the Associations’
    asserted export-intertwined effects outside of the
    Commission’s NEPA duties. But Chenery’s restriction on our
    review of an agency’s order “‘is to be understood with a
    qualification; the order must be judged upon the grounds upon
    which the action was based, unless the appellate court
    concludes that the decision ‘already made * * * should
    properly be based on another ground within the power of the
    appellate court to formulate’”—that is, one that “does not
    depend upon a factual determination or a policy judgment that
    [the agency] alone is authorized to make.” Shea v. Director,
    Office of Workers’ Comp. Programs, United States Dep’t of
    Labor, 
    929 F.2d 736
    , 739 n.4 (D.C. Cir. 1991) (quoting Chae-
    Sik Lee v. Kennedy, 
    294 F.2d 231
    , 234 (D.C. Cir.), cert.
    denied sub nom., Lee v. Kennedy, 
    368 U.S. 926
    (1961)); see
    20
    Canonsburg Gen. Hosp. v. Burwell, 
    807 F.3d 295
    , 304 (D.C.
    Cir. 2015) (Chenery applies only to “determinations
    specifically entrusted to an agency’s expertise,” not “legal
    principles” of the sort “that a court usually makes”).
    Our decision here follows not from de novo factual
    findings or independent policy judgments, but from our
    interpretation of NEPA and binding Supreme Court
    precedent—neither of which trenches upon a “determination
    specially entrusted to [the Commission’s] expertise.”
    Canonsburg Gen. 
    Hosp., 807 F.3d at 304
    ; see New York New
    York, LLC v. NLRB, 
    313 F.3d 585
    , 590 (D.C. Cir. 2002) (“We
    are not obligated to defer to an agency’s interpretation of
    Supreme Court precedent under Chevron or any other
    principle.”) (internal quotation marks omitted); Grand
    Canyon Trust v. FAA, 
    290 F.3d 339
    , 342 (D.C. Cir. 2002)
    (“[T]he court owes no deference to [an agency’s]
    interpretation of NEPA * * * because NEPA is addressed to
    all federal agencies and Congress did not entrust
    administration of NEPA to [any one agency] alone.”).
    The Supreme Court’s decision in Public Citizen is
    explicit that the Commission was not obligated to consider
    those effects of the Freeport Projects that could only occur
    after intervening action by the Department of Energy or
    Congress and that only those actors—and not the
    Commission—had the authority to prevent. Based on the
    record before us and the Associations’ arguments, we cannot
    conclude that the Commission’s analysis of the Projects’
    indirect effects, separate and apart from exporting, was
    arbitrary or capricious.
    B
    In addition to addressing reasonably foreseeable indirect
    effects, NEPA obligated the Commission to consider the
    21
    “cumulative impact[s]” on the environment—that is, “the
    incremental impact of the [Freeport Projects] when added to
    other past, present, and reasonably foreseeable future
    actions[.]” 40 C.F.R. § 1508.7. To that end, a cumulative-
    impact analysis must identify (i) the “‘area in which the
    effects of the proposed project will be felt’”; (ii) the impact
    expected “‘in that area’”; (iii) those “‘other actions—past,
    present, and proposed, and reasonably foreseeable’” that have
    had or will have impact “‘in the same area’”; (iv) the effects
    of those other impacts; and (5) the “‘overall impact that can
    be expected if the individual impacts are allowed to
    accumulate.’” TOMAC, Taxpayers of Michigan Against
    Casinos v. Norton, 
    433 F.3d 852
    , 864 (D.C. Cir. 2006)
    (quoting Grand Canyon 
    Trust, 290 F.3d at 345
    ).
    The Commission identified the relevant geographic area
    for its cumulative-impact analysis as Brazoria County, Texas,
    the 1,600-square-mile county in which the Freeport Projects
    would be located and in which “the predominance of
    environmental impacts” associated with the Projects’
    construction and operation would occur. J.A. 978. Such a
    determination of the size and location of the relevant
    geographic area “requires a high level of technical expertise,”
    and thus “is a task assigned to the special competency of” the
    Commission. Kleppe v. Sierra Club, 
    427 U.S. 390
    , 412, 414
    (1976). The Commission then catalogued and analyzed the
    cumulative environmental effects of the Freeport Projects
    with “[m]ajor current and proposed developments” in the
    County, including industrial, port and harbor channel,
    pipeline, oil and gas field, land and air transportation,
    commercial,      residential,   and     other   miscellaneous
    developments. J.A. 980.
    The Associations voice no complaint about the analysis
    of the Projects’ cumulative impact within Brazoria County.
    22
    Their objection, instead, is that the Commission should have
    undertaken a nationwide analysis that included applications
    for several other liquefied natural gas export terminals that
    were pending or had already been granted across the United
    States. Pet. Br. 35 & n.21.
    That draws the NEPA circle too wide for the
    Commission. A NEPA cumulative-impact analysis need only
    consider the “effect of the current project along with any other
    past, present or likely future actions in the same geographic
    area” as the project under review. 
    TOMAC, 433 F.3d at 864
    (emphasis added); Grand Canyon 
    Trust, 290 F.3d at 345
    (NEPA “cumulative impacts” applies to “impacts in the same
    area”).
    The Associations point to the Supreme Court’s direction
    in Kleppe that, “when several proposals for * * * related
    actions that will have cumulative or synergistic environmental
    impact upon a region are pending concurrently before an
    agency, their environmental consequences must be considered
    
    together,” 427 U.S. at 410
    . But the key language there is
    “upon a region.” 
    Id. There is
    no dispute that the Commission
    considered the cumulative effects of the Freeport Projects that
    it was authorizing within its designated county-wide region.
    Importantly, the Supreme Court went on in Kleppe to confirm
    that an agency’s NEPA obligations are not uncabined:
    “[P]ractical considerations of feasibility might well
    necessitate restricting the scope” of an agency’s analysis. 
    Id. at 414.
    That is not to say that the nature of a particular agency
    action would never warrant a nationwide cumulative-impact
    analysis. See Grand Canyon 
    Trust, 290 F.3d at 345
    (cumulative impact analyses must identify “the area in which
    the effects of the proposed project will be felt”). But given
    23
    the scant record evidence identifying any reasonably
    foreseeable and proximate effects of the Freeport Projects
    themselves (separate from their exports) on national energy
    markets or emission levels, we hold that the Associations
    have not shown that the Commission acted arbitrarily or
    capriciously in analyzing the cumulative effects of the
    Freeport Projects. See Minisink Residents for Environmental
    Preservation and Safety v. FERC, 
    762 F.3d 97
    , 113 (D.C. Cir.
    2014) (upholding cumulative-impact analysis finding “no
    significant cumulative impacts were expected” where the
    “[p]roject itself was expected to have minimal impacts”).
    C
    Lastly, the Associations fault the Commission for
    quantifying emissions from the Projects’ electricity use in
    pounds per megawatt-hour instead of in tons per year. We
    lack jurisdiction to entertain that argument.
    The Natural Gas Act is explicit that “[n]o objection to the
    order of the Commission shall be considered by the court
    unless such objection shall have been urged before the
    Commission in the application for rehearing unless there is
    reasonable ground for failure so to do.”            15 U.S.C.
    § 717r(b). That requirement is a “‘jurisdictional prerequisite[]
    to judicial review.’” Moreau v. FERC, 
    982 F.2d 556
    , 562–
    563 (D.C. Cir. 1993) (quoting Public Serv. Comm’n v.
    Federal Power Comm’n, 
    543 F.2d 757
    , 774 n.116 (D.C. Cir.
    1974)); see also NO Gas Pipeline v. FERC, 
    756 F.3d 764
    ,
    768–769 (D.C. Cir. 2014).
    That obligation to raise objections before the
    Commission first is redoubled under NEPA because
    “[p]ersons challenging an agency’s compliance with NEPA
    must structure their participation so that it * * * alerts the
    agency to the [parties’] position and contentions,” and failure
    24
    to do so “forfeit[s] any objection” to the environmental
    analysis on that ground. Public 
    Citizen, 541 U.S. at 764
    (internal quotation marks omitted).
    At no point in the proceedings below, including the
    rehearing stage, did the Associations contend that the
    Commission should use the tons-per-year metric. In fact, in
    its comments to the Commission’s draft statement, Sierra
    Club specifically directed the Commission to a database that
    “conveniently” quantified emission rates using the same
    pounds-per-megawatt-hour metric that it now faults the
    Commission for employing. J.A. 432. Because the “tons per
    year vs. pounds per megawatt-hour” argument was not raised
    before the Commission, it cannot be considered here.
    IV
    In sum, we hold that at least one of the Associations’
    members has standing, and that the case is not moot. On the
    merits, we reject the Associations’ challenges to the
    Commission’s NEPA review of the Freeport Projects,
    separate and apart from any environmental effects associated
    with the Department of Energy’s independent decision to
    authorize exports.
    It is so ordered.
    

Document Info

Docket Number: 14-1275

Citation Numbers: 423 U.S. App. D.C. 394, 827 F.3d 36

Filed Date: 6/28/2016

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (19)

Sierra Club and William O'Neil v. John O. Marsh, Jr. , 976 F.2d 763 ( 1992 )

city-of-shoreacres-city-of-shoreacres-city-of-taylor-lake-village-texas , 420 F.3d 440 ( 2005 )

Commty Agnst Runway v. FAA , 355 F.3d 678 ( 2004 )

TOMAC v. Norton, Gale A. , 433 F.3d 852 ( 2006 )

Lemon v. Geren , 514 F.3d 1312 ( 2008 )

Theodore Roosevelt Conservation Partnership v. Salazar , 661 F.3d 66 ( 2011 )

Sierra Club v. Environmental Protection Agency , 292 F.3d 895 ( 2002 )

NY NY v. NLRB , 313 F.3d 585 ( 2002 )

Grand Canyon Trust v. Federal Aviation Administration , 290 F.3d 339 ( 2002 )

Natural Resources Defense Council, Inc. v. Donald P. Hodel, ... , 865 F.2d 288 ( 1988 )

National Committee for the New River, Inc. v. Federal ... , 433 F.3d 830 ( 2005 )

judith-b-moreau-n-robert-moreau-clara-lawrence-and-walter-lawrence-v , 982 F.2d 556 ( 1993 )

Securities & Exchange Commission v. Chenery Corp. , 63 S. Ct. 454 ( 1943 )

shea-s-m-ball-company-and-seaboard-fire-marine-insurance-company-v , 929 F.2d 736 ( 1991 )

Department of Transportation v. Public Citizen , 124 S. Ct. 2204 ( 2004 )

Kleppe v. Sierra Club , 96 S. Ct. 2718 ( 1976 )

DaimlerChrysler Corp. v. Cuno , 126 S. Ct. 1854 ( 2006 )

Massachusetts v. Environmental Protection Agency , 127 S. Ct. 1438 ( 2007 )

Baltimore Gas & Electric Co. v. Natural Resources Defense ... , 103 S. Ct. 2246 ( 1983 )

View All Authorities »