400 E Street SW, LLC v. Chevron U.S.A. Inc. ( 2022 )


Menu:
  •                    United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    No. 21-7075                                                   September Term, 2021
    FILED ON: JULY 12, 2022
    400 E STREET SW, LLC,
    APPELLANT
    v.
    CHEVRON U.S.A. INC.,
    APPELLEE
    Appeal from the United States District Court
    for the District of Columbia
    (No. 1:20-cv-03396)
    Before: WILKINS and WALKER, Circuit Judges, and RANDOLPH, Senior Circuit Judge.
    JUDGMENT
    This appeal was considered on the record from the United States District Court for the
    District of Columbia and on the briefs filed by the parties. See FED. R. APP. P. 34(a)(2); D.C. CIR.
    R. 34(j). The Court has accorded the issues full consideration and determined that they do not
    warrant a published opinion. See FED R. APP. P. 36; D.C. CIR. R. 36(d). For the reasons set out
    below, it is
    ORDERED AND ADJUDGED that the judgment of the District Court be AFFIRMED.
    Between 1957 and 1994, Appellee Chevron U.S.A. Inc. (“Chevron”) operated a gas station
    on a parcel lot in Southwest Washington, D.C. In October 2013, Appellant 400 E Street SW, LLC
    (“Developer”) leased that property from the District of Columbia. In February and March 2014,
    Developer discovered three underground storage tanks and petroleum-contaminated soil on the
    property. On April 9, 2014, the District of Columbia Department of the Environment,
    Underground Storage Tank Branch (“UST Branch”) issued a letter directing Chevron, “the former
    owner and operator of an underground storage tank system at the Property,” to excavate and
    remove the contaminated soil, test the soil for environmental contaminants, and take other
    corrective actions. J.A. 18–19. The UST Branch copied Developer on the letter. The letter noted
    that “some of the . . . [corrective] actions may have already commenced or are currently being
    completed” by Developer. Id. at 19.
    1
    On October 27, 2020, Developer sued Chevron in the Superior Court of the District of
    Columbia, alleging injury to real property from toxic substances (count one) and violations of
    District of Columbia underground storage tank regulations (count two). In the complaint,
    Developer alleges that it took corrective actions on the property, pursuant to the UST Branch’s
    directive letter, and incurred nearly $4 million in property restoration costs. Though Chevron was
    responsible for property restoration costs, Developer alleged Chevron refused to reimburse it for
    these costs.
    Chevron removed the case to the U.S. District Court for the District of Columbia and
    moved to dismiss the complaint on the grounds that Developer’s lawsuit is time-barred and for
    failure to state a claim under Federal Rule of Civil Procedure 12(b)(6). The District Court granted
    the motion and entered judgment in favor of Chevron. The District Court reasoned that the statute
    of limitations on Developer’s claims started to run in April 2014, when the UST Branch’s directive
    letter “gave [Developer] notice of the injury (the contaminated soil), as well as its cause and some
    evidence of wrongdoing (that the tanks used for Chevron’s gas station may have caused the soil’s
    contamination).” 400 E Street SW, LLC v. Chevron U.S.A., Inc., No. 20-CV-3396, 
    2021 WL 2682285
    , at *2 (D.D.C. June 30, 2021). But Developer did not sue Chevron until October 2020,
    six-and-a-half years after it discovered injury to the property. 
    Id.
     Accordingly, the District Court
    held that Developer’s claims are time-barred by the five-year statute of limitations for damages
    from injury to real property from toxic substances. See 
    D.C. Code § 12-301
    (10). The District
    Court also rejected Developer’s argument that a tolling order issued by the Superior Court on
    March 18, 2020—which tolled statutes of limitations that were set to expire during the pandemic—
    saved Developer’s late filing. The District Court noted that the statute of limitations on
    Developer’s claims expired nearly a year before the Superior Court paused statutes of limitations
    in connection with the COVID-19 pandemic. 400 E Street SW, 
    2021 WL 2682285
    , at *2 n.3.
    Finally, the District Court concluded that neither of Developer’s claims stated a cause of action
    upon which relief can be granted. Developer timely appealed, and we affirm the District Court’s
    dismissal of the complaint because it is conclusively time-barred.
    “This court reviews de novo the dismissal of a complaint.” Commonwealth Land Title Ins.
    Co. v. KCI Techs., Inc., 
    922 F.3d 459
    , 464 (D.C. Cir. 2019). “‘[C]ourts should hesitate to dismiss
    a complaint on statute of limitations grounds based solely on the face of the complaint’ because
    ‘statute of limitations issues often depend on contested questions of fact.’” 
    Id.
     (alteration in
    original) (quoting Firestone v. Firestone, 
    76 F.3d 1205
    , 1209 (D.C. Cir. 1996)). “[D]ismissal is
    appropriate only if the complaint on its face is conclusively time-barred.” Firestone, 
    76 F.3d at 1209
    .
    The D.C. Code provides that actions “for the recovery of damages for an injury to real
    property from toxic substances” “may not be brought” after “5 years from the date the injury is
    discovered or with reasonable diligence should have been discovered.” 
    D.C. Code § 12-301
    (10).
    This is consistent with the “discovery rule,” which “provides that a claim does not accrue until a
    plaintiff knows, or by the exercise of reasonable diligence should know, of (1) an injury, (2) its
    cause, and (3) some evidence of wrongdoing.” See Wagner v. Sellinger, 
    847 A.2d 1151
    , 1154
    (D.C. 2004). In the District of Columbia, statutes of limitations “are strictly construed in
    accordance with their terms.” Atiba v. Wash. Hosp. Ctr., 
    43 A.3d 940
    , 941 (D.C. 2012).
    2
    On appeal, Developer raises several challenges to the District Court’s determination that
    the complaint is time-barred. First, Developer insists that the statute of limitations on its claims
    did not begin to run in April 2014. Rather, in Developer’s view, the clock started in May 2015, at
    which point Developer “believed it was . . . entitled to recover the costs it incurred for performing
    the remediation work [Chevron] was legally obligated to perform.” Opening Br. at 9. Relatedly,
    Developer contests the District Court’s conclusion that the “contaminated soil” was Developer’s
    “injury.” See 400 E Street SW, 
    2021 WL 2682285
    , at *2. Developer contends that the injury was
    not the contaminated soil, but rather Chevron’s “failure to be financially responsible for [the]
    costs” incurred in removing the soil. Opening Br. at 10. Developer insists that this injury “did not
    arise until mid-2015 when [Chevron] first rejected [Developer]’s request for reimbursement.” 
    Id.
    Next, Developer maintains that the Superior Court’s March 2020 COVID-19 tolling order paused
    the statute of limitations on its claims against Chevron. Finally, Developer argues that the doctrine
    of equitable tolling should apply in this case and excuse its tardy filing. We hold that none of
    Developer’s arguments can avoid the inescapable conclusion that its lawsuit is time-barred.
    Based on the factual allegations and the documents attached to the complaint, there is no
    question that Developer discovered the injury to the property, or “with reasonable diligence, should
    have . . . discovered” it, see 
    D.C. Code § 12-301
    (10), by April 9, 2014, the date it received the
    UST Branch’s letter. That letter (1) explicitly stated that Chevron was responsible for the release
    of toxic substances on the property, (2) directed Chevron to perform corrective actions, (3) “put
    [Developer] on notice” of “hazardous condition[s]” on the property, see Minkoff v. Clark Transfer,
    Inc., 
    841 F. Supp. 424
    , 428 (D.D.C. 1993), and (4) acknowledged that Developer was currently
    undertaking efforts to restore the property. Indeed, “the plaintiff need not be fully informed about
    the injury for the statute to begin running; she need only have some knowledge of some injury.”
    Wagner, 
    847 A.2d at 1154
     (emphasis in original). “In short, knowledge is deemed sufficient if the
    plaintiff has reason to suspect that the defendant did something wrong, even if the full extent of
    the wrongdoing is not yet known.” 
    Id.
    Furthermore, Developer’s argument—that the injury accrued in mid-2015, when Chevron
    refused to reimburse Developer for property remediation costs, not when Developer discovered
    contaminated soil on the property, see Opening Br. at 10—is unsupported by the law. It is well
    settled that where the complaint alleges that the defendant damaged real property, the “injury” for
    statute of limitations purposes is the property damage itself, not the failure to reimburse the cost
    of repairing the property damage, see District of Columbia Armory Bd. v. Volkert, 
    402 F.2d 215
    ,
    219 (D.C. Cir. 1968) (construing 
    D.C. Code § 12-301
    ), and “a claim accrues for purposes of the
    statute of limitations at the time the injury actually occurs,” Colbert v. Georgetown Univ., 
    641 A.2d 469
    , 472 (D.C. 1994) (en banc). Cf. 3M Co. v. Browner, 
    17 F.3d 1453
    , 1460–63 (D.C. Cir.
    1994) (court should look to the nature of the cause of action specified as covered by the statute of
    limitations to determine when the claim accrued). All in all, Developer’s own allegations and the
    directive letter entirely undermine the assertion that the statute of limitations for Developer’s
    claims did not start to run until May 2015.
    Developer’s remaining arguments similarly lack merit. First, Developer’s reliance on the
    Superior Court’s tolling order is misguided because the statute of limitations on Developer’s
    claims expired in April 2019, nearly a year before the Superior Court’s COVID-19 tolling order
    paused statutes of limitations that were set to expire during the pandemic. Furthermore, Developer
    3
    did not raise its “equitable tolling” argument in the District Court and it is therefore forfeited.
    Woodruff v. Peters, 
    482 F.3d 521
    , 525 (D.C. Cir. 2007) (“It is the general rule, of course, that a
    federal appellate court does not consider an issue not passed upon below.”) (internal quotation
    marks and citations omitted).
    Consistent with the foregoing, we affirm the judgment of the District Court.
    Pursuant to D.C. Circuit Rule 36, this disposition will not be published. The Clerk is
    directed to withhold issuance of the mandate herein until seven days after resolution of any timely
    petition for rehearing or petition for rehearing en banc. See FED. R. APP. P. 41(b); D.C. CIR. R.
    41(a)(1).
    Per Curiam
    FOR THE COURT:
    Mark J. Langer, Clerk
    BY:    /s/
    Daniel J. Reidy
    Deputy Clerk
    4