State of VT Dept. of Pub. Serv v. Nuclear Regulatory Commission , 684 F.3d 149 ( 2012 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued May 9, 2012                      Decided June 26, 2012
    No. 11-1168
    VERMONT DEPARTMENT OF PUBLIC SERVICE ET AL.,
    PETITIONER
    v.
    UNITED STATES OF AMERICA
    AND NUCLEAR REGULATORY COMMISSION,
    RESPONDENTS
    ENTERGY NUCLEAR OPERATIONS, INC.
    AND ENTERGY NUCLEAR VERMONT YANKEE, LLC,
    INTERVENORS
    Consolidated with 11-1177
    On Petition for Review of a Final Order
    of the U.S. Nuclear Regulatory Commission
    Elizabeth Miller, pro hac vice, argued the cause for the
    petitioners. Anthony Z. Roisman, John Beling and Christopher
    M. Kilian were on brief. Tricia K. Jedele entered an appearance.
    Mark D. Davis and Christopher J. Wright were on brief for
    amici curiae Riverkeeper et al. in support of the petitioners.
    Timothy J. Simeone entered an appearance.
    2
    Eric T. Schneiderman, Attorney General, Office of the
    Attorney General for the State of New York, and Barbara D.
    Underwood, Solicitor General, were on brief for amicus curiae
    State of New York in support of the petitioners. John J. Sipos
    and Lisa M. Burianek, Assistant Attorneys General, and Monica
    B. Wagner, Assistant Solicitor General, entered appearances.
    Sean D. Croston, Attorney, United States Nuclear
    Regulatory Commission, argued the cause for the respondents.
    John E. Arbab, Attorney, United States Department of Justice,
    Stephen G. Burns, General Counsel, United States Nuclear
    Regulatory Commission, and John F. Cordes, Jr., Solicitor,
    were on brief.
    Kevin P. Martin argued the cause for intervenors Entergy
    Nuclear Operations, Inc. et al. David R. Lewis and Elise N. Zoli
    were on brief.
    Adam J. White was on brief for amicus curiae Energy
    Future Coalition in support of the respondents.
    Before: HENDERSON, ROGERS and GARLAND, Circuit
    Judges.
    Opinion for the Court filed by Circuit Judge HENDERSON.
    KAREN LECRAFT HENDERSON, Circuit Judge: The Vermont
    Department of Public Service (DPS) and the New England
    Coalition (NEC) petition for review of a decision of the Nuclear
    Regulatory Commission (NRC, Commission), issuing to
    Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear
    Operations, Inc. (collectively, Entergy) a renewed license to
    operate the Vermont Yankee Nuclear Power Station (Vermont
    Yankee). The petitioners contend the license renewal was
    unlawful because Entergy failed to furnish a state Water Quality
    Certification (WQC) which they assert was required under
    section 401(a)(1) of the Clean Water Act (CWA), 
    33 U.S.C. § 1341
    (a)(1). We conclude the petitioners waived their WQC
    3
    objection because they repeatedly failed to present it directly to
    the Commission and thereby failed to exhaust their
    administrative remedies.
    I.
    The Atomic Energy Act (AEA) authorizes the NRC to issue
    an initial license to operate a nuclear power plant for a term of
    up to 40 years. 
    42 U.S.C. § 2133
    (a), (c). Pursuant to this
    authority, the Atomic Energy Commission (AEC), the NRC’s
    predecessor,1 issued a 40-year license to operate Vermont
    Yankee on March 21, 1972. Vermont Yankee Nuclear Power
    Corp.; Notice of Issuance of Facility Operating License, 
    37 Fed. Reg. 6345
     (Mar. 28, 1972). In April 1970, while the licensing
    proceeding was ongoing, the Congress amended the Federal
    Water Pollution Control Act, the precursor to the CWA, to add
    the provisions of the Water Quality Improvement Act, Pub. L.
    No. 91-224, tit. I, 
    84 Stat. 91
     (1970). Section 21(b) of the
    Federal Water Pollution Control Act required that any applicant
    for a federal license or permit to conduct an activity that might
    “result in any discharge into the navigable waters of the United
    States . . . provide a certification from the State in which the
    discharge originates or will originate . . . that there is reasonable
    assurance . . . that such activity will be conducted in a manner
    which will not violate applicable water quality standards.” 
    Id.
    § 102, 84 Stat. at 108. Accordingly, because Vermont Yankee
    planned to use water from the Connecticut River to cool its
    reactor and then discharge the water back into the river,
    Entergy’s predecessor licensee obtained a WQC from the State
    of Vermont in October 1970 to support its operating license
    application. In October 1972, after Vermont Yankee’s initial
    1
    In 1974, the Congress abolished the AEC and transferred its
    licensing and related regulatory functions to the NRC. Energy
    Reorganization Act of 1974, Pub. L. No. 93-438, §§ 104(A), 201(F),
    
    88 Stat. 1233
    , 1237, 1243 (codified at 
    42 U.S.C. §§ 5814
    (a), 5841(f)).
    4
    operating license issued, the Congress enacted the Federal Water
    Pollution Control Amendments of 1972 (now the CWA),
    incorporating the section 401 WQC requirement as follows:
    Any applicant for a Federal license or permit to
    conduct any activity including, but not limited to, the
    construction or operation of facilities, which may result
    in any discharge into the navigable waters, shall
    provide the licensing or permitting agency a
    certification from the State in which the discharge
    originates or will originate . . . that any such discharge
    will comply with the applicable provisions of [
    33 U.S.C. §§ 1311
    , 1312, 1313, 1316, and 1317]. . . . No
    license or permit shall be granted until the certification
    required by this section has been obtained or has been
    waived as provided in the preceding sentence. No
    license or permit shall be granted if certification has
    been denied by the State, interstate agency, or the
    Administrator, as the case may be.
    Pub. L. No. 92-500, § 2 (§ 401(a)(1)), 
    86 Stat. 816
    , 877-78
    (1972) (codified at 
    33 U.S.C. § 1341
    (a)(1)); Vermont Yankee’s
    1970 WQC “continue[d] in full force and effect” thereafter
    pursuant to the CWA’s savings provision. 
    Id.
     § 4, 86 Stat. at
    897.
    An operating licensee may also be required to maintain a
    permit issued under the “National Pollutant Discharge
    Elimination System” (NPDES) pursuant to CWA section 402.
    Section 402 authorizes the Environmental Protection Agency
    (EPA) to “issue a permit for the discharge of any pollutant, or
    combination of pollutants . . . upon condition that such discharge
    will meet . . . all applicable requirements under [42 U.S.C. §§]
    5
    1311, 1312, 1316, 1317, 1318, and 1343.” 
    33 U.S.C. § 1342.2
    Section 402(b) allows a state to obtain EPA approval to
    administer its own NPDES program, 
    33 U.S.C. § 1342
    (b), and
    in 1974, the State of Vermont did just that. Vermont issued
    Vermont Yankee a NPDES permit in 1978 and has renewed it
    successively upon expiration or amendment. Most recently the
    Vermont Agency of Natural Resources (VANR) renewed it for
    a five-year term in 2001. See In re Entergy Nuclear Vt. Yankee
    Discharge Permit, 
    989 A.2d 563
    , 568-69 (Vt. 2009).3
    On January 25, 2006, Entergy filed an application with the
    NRC for a 20-year renewal of Vermont Yankee’s operating
    license, which was set to expire on March 21, 2012. Included
    2
    “Each permit must set out the specific conditions necessary to
    ensure that the permit holder’s discharge of pollution will comply with
    the water standards mandated by the CWA.” Lake Carriers’ Ass’n v.
    EPA, 
    652 F.3d 1
    , 3 (D.C. Cir. 2011) (citing 
    33 U.S.C. § 1342
    (a)(2)).
    3
    Although the permit expired by its terms in 2006, because
    Entergy timely filed for renewal on September 30, 2005, Vermont
    Yankee has continued to operate under the authority of the 2001
    permit pursuant to Vermont law. In re Entergy Nuclear, 
    989 A.2d at
    569 n.4 (citing 3 Vt. Stat. Ann. § 814(b) (“When a licensee has made
    timely and sufficient application for the renewal of a license or a new
    license with reference to any activity of a continuing nature, the
    existing license does not expire until the application has been finally
    determined by the agency, and, in case the application is denied or the
    terms of the new license limited, until the last day for seeking review
    of the agency order or a later date fixed by order of the reviewing
    court.”)). VANR intends to process the renewal application in
    summer 2012 after EPA issues a rule addressing effluent limitation
    standards for cool water intake structures under CWA section 316(b),
    
    33 U.S.C. § 1326
    (b). Pet’rs’ Resp. to Court Req. re: Status of Vt.
    Yankee Nuclear Power Station Discharge Permit, ex. A (filed May 21,
    2012) (March 7, 2012 letter from VANR to Vt. Pub. Serv. Bd.); see
    Hydro Res., Inc., 
    48 N.R.C. 119
     (1998).
    6
    with the application was an environmental report, as required
    under 
    10 C.F.R. § 51.45
    . In a section titled “Water Quality
    (401) Certification,” the environmental report stated:
    As reported in the [Final Environmental Statement]
    (1972), the Vermont Water Resources Board provided
    a water quality certification on October 29, 1970, as
    amended on November 26, 1971, reflecting its receipt
    of reasonable assurance that operation of Vermont
    Yankee will not violate applicable water quality
    standards. In addition, the current and effective
    NPDES permit issued by the Vermont Agency of
    Natural Resources reflects continued compliance with
    applicable CWA standards. Excerpts of this permit are
    included in Attachment D.
    Vermont Yankee Nuclear Power Station, Applicant’s
    Environmental Report, Operating License Renewal Stage
    § 9.2.1, at 9-1 (Jan. 25, 2006) (Environmental Report).
    Appended to its application was a table setting out Vermont
    Yankee’s “Environmental Permits and Compliance Status,”
    which identified a 2001 section 402 NPDES permit issued by
    VANR, set to expire on March 31, 2006, but made no mention
    of any section 401 WQC. Id. app. E.
    On March 27, 2006, the NRC published a notice
    announcing it had accepted the Vermont Yankee license renewal
    application and planned to prepare a site-specific environmental
    impact statement therefor as a supplement to its Generic
    Environmental Impact Statement for License Renewal of
    Nuclear Power Plants (May 1996) (GEIS) pursuant to the
    National Environmental Policy Act of 1979 (NEPA), 
    42 U.S.C. §§ 4321
     et seq., and the NRC’s NEPA regulations, 10 C.F.R. pt.
    7
    51.4 Notice of Acceptance for Docketing of the Application and
    Notice of Opportunity for Hearing Regarding Renewal of
    Facility Operating License, 
    71 Fed. Reg. 15,220
    , 15,220 (Mar.
    27, 2006). The notice declared that “any person whose interest
    may be affected” by the proceeding and who wished to
    participate as a party therein should file a “written request for a
    hearing and a petition for leave to intervene . . . in accordance
    with the Commission’s ‘Rules of Practice for Domestic
    Licensing Proceedings’ in 10 C.F.R. Part 2.” 
    Id. at 15,221
    . The
    notice further directed that any petition to intervene set forth the
    petitioner’s interest and “the specific contentions which the
    petitioner/requestor seeks to have litigated at the proceeding”
    pursuant to 
    5 C.F.R. § 2.309
    (a). 
    Id.
     Four parties, including DPS
    and NEC, filed timely motions for a hearing or to intervene and
    an Atomic Safety and Licensing Board (Board)5 was established
    to preside over the renewal proceeding.
    DPS and NEC filed, respectively, three and six contentions
    challenging Entergy’s application, only one of which is relevant
    here.    NEC’s “Contention 1” asserted that “Entergy’s
    4
    The GEIS, initially promulgated in 1996, addresses issues that
    “are common to all nuclear power plants, or to a sub-class of plants[;
    a]s such, the NRC does not analyze [them] afresh with each individual
    plant operating license application.” Massachusetts v. United States,
    
    522 F.3d 115
    , 120 (1st Cir. 2008); see Environmental Review for
    Renewal of Nuclear Power Plant Operating Licenses, 
    61 Fed. Reg. 28,467
     (June 5, 1996). Instead, the Commission addresses only
    “non-generic issues that require site-specific analysis for each
    individual licensing proceeding.” Massachusetts, 
    522 F.3d at 120
    .
    5
    “[T]he Commission is authorized to establish one or more
    atomic safety and licensing boards, each comprised of three members,
    . . . to conduct such hearings as the Commission may direct and make
    such intermediate or final decisions as the Commission may authorize
    with respect to the granting, suspending, revoking or amending of any
    license or authorization . . . .” 
    42 U.S.C. § 2241
    (a).
    8
    environmental report (ER) failed to ‘sufficiently assess[]’ the
    environmental impacts of the license renewal, specifically the
    impacts of increased thermal discharges into the Connecticut
    River over the 20-year license renewal period.” Entergy
    Nuclear Vt. Yankee, LLC, 
    64 N.R.C. 131
    , 175 (Sept. 22, 2006)
    (alteration in original). NEC contended in particular:
    Entergy’s reliance solely on its NPDES permit is not
    sufficient because the permit is under appeal and, even
    if issued, will only be valid for 5 years, (2006-2011),
    and thus will not cover the cumulative impacts of
    thermal discharges over the 20-year period of the
    license renewal term (2012-2032).
    
    Id.
     Entergy answered, inter alia, that once it provided a valid
    Vermont NPDES permit, “no further analysis” was required. 
    Id. at 176
    . In its reply, NEC asserted, for the first time, that Entergy
    was “also obligated to obtain a state water certification under
    section 401 . . . and that Entergy had not done so.” 
    Id. at 177
    .
    Entergy moved to strike portions of NEC’s reply, including
    “NEC’s new claims regarding 401 certification” which were not
    “related to the purported bases for the original contention.”
    Entergy’s Mot. to Strike Portions of NEC’s Reply 10 (July 10,
    2006). Entergy explained that “the allegations concerning
    Contention 1 in NEC’s Petition related solely to whether the
    Environmental Report had adequately addressed the impacts of
    a 1° increase in the thermal effluent limitations recently
    approved in an amendment to the NPDES permit” and neither
    Contention 1 nor Entergy’s response “had anything to do with
    the need for a section 401 certification,” which was “newly
    alleged.” 
    Id.
     In reply, NEC stated it was “important to note that
    §[ ]401 Water Quality Certification is jurisdictional and imposes
    an independent obligation on Entergy and the NRC, regardless
    of whether the need for certification is raised as a contention.”
    NEC’s Opp’n to Entergy’s Mot. to Strike Portions of NEC’s
    Reply 7 (July 20, 2006).
    9
    Following oral argument before the Board in August 2006,
    NEC filed a “Late Contention or, Alternatively, Request for
    Leave to Amend or File a New Contention” (Late
    Contention/Req. to Amend) (Aug. 7, 2006), which attempted to
    add the section 401 objection as a further basis for Contention 1:
    Further basis demonstrating the inadequacy of
    Entergy’s amended environmental report is the absence
    of a CWA § 401 Water Quality Certification. Entergy
    is on notice that its requested license extension cannot
    issue without a § 401 Certification. Yet Entergy’s
    amended environmental report makes no mention of
    any effort to seek and obtain § 401 Certification.
    Late Contention/Req. to Amend, at 4-5. After Entergy and NRC
    staff responded in opposition, NEC filed a reply stating:
    Based on NEC’s prior filings in this matter, Entergy
    is on notice that its requested license extension cannot
    issue without a Clean Water Act § 401 certification.
    Astonishingly, Entergy’s Amendment 6 to its
    Environmental Report nonetheless makes no mention
    of this issue. . . .1
    ________________________
    1
    Additionally, Entergy has an independent obligation to
    obtain a §[ ]401 certification, and the NRC is
    jurisdictionally limited to acting in conformity with §[ ]401
    requirements. 
    33 U.S.C. § 1341
    ; S.D. Warren v. State of
    Maine, 547 U.S. [370, 373] (2006).
    NEC’s Reply to Entergy & NRC Staff’s Answers to NEC’s Late
    Contention/Req. to Amend, at 5-6 & n.1 (Aug. 28, 2006).
    On September 22, 2006, the Board admitted for hearing
    several of NEC’s contentions, including Contention 1, but
    granted Entergy’s motion to strike the “portions of NEC’s Reply
    that relate[d] to certification under 401,” “agree[ing] with
    Entergy that NEC’s attempt to introduce an entirely new
    10
    argument regarding the alleged need for a section 401
    certification is not permissible in a reply.” Entergy Nuclear Vt.
    Yankee, LLC, 
    64 N.R.C. 131
    , 182 (Sept. 22, 2006).6 On October
    2, 2006, the Board denied NEC’s Late Contention/Request for
    Leave to Amend as moot because “the Board “s[aw] no
    difference between NEC Contention 1, as admitted, and the
    proposed amended contention.” Mem. and Order, at 6, Entergy
    Nuclear Vt. Yankee, LLC, Docket No. 50-271-LR (Oct. 30,
    2006). With regard to the absence of a new section 401 permit,
    the Board rejected the assertion by its staff and Entergy that
    NEC’s objection was “too late” but agreed with Entergy that
    “the need for a CWA § 401 certification is simply irrelevant to
    NEC’s contention that Entergy failed to assess impacts to water
    quality.” Id. at 7. The Board explained: “A CWA § 401
    certification is a document issued by the State certifying that a
    proposed discharge satisfies the State’s water quality standards
    and criteria. But a CWA § 401 certification is simply an
    independent statutory requirement, and neither NEPA nor 10
    C.F.R. Part 51 incorporates or requires it.” Id. at 7-8.
    In December 2006, the NRC published a Draft
    Supplemental Environmental Impact Statement (Draft SEIS).
    Generic Envtl. Impact Statement for License Renewals of
    Nuclear Plants, Supp. 30 (Regarding Vt. Yankee Nuclear Power
    Plant) (Dec. 2006) (Draft Report for Comment). An appendix
    to the Draft SEIS enumerated the required governmental
    approvals, pursuant to 
    10 C.F.R. § 51.71
    , citing Entergy’s 2001
    NPDES permit but making no mention of a section 401 WQC.
    
    Id.
     app. E. Both the Draft SEIS text and a separate Federal
    6
    The NRC subsequently reversed the Board’s order insofar as it
    agreed to hear Contention 1 on the ground that Vermont had already
    addressed effluent limitations in its NPDES permit and the AEA
    precludes the Commission from “second-guessing the conclusions in
    NPDES permits or imposing [its] own effluent limitations.” Entergy
    Nuclear Vt. Yankee, LLC, 
    65 N.R.C. 371
    , 376-77 (Apr. 11, 2007).
    11
    Register notice published concurrently solicited comments on
    the Draft SEIS. The petitioners submitted no responsive
    comment objecting to the lack of a section 401 WQC. The NRC
    issued its Final Supplemental Environmental Impact Statement
    (Final SEIS) in August 2007, again listing the section 402
    approval but not mentioning section 401. Again, the petitioners
    made no response to section 401’s absence.
    The Board held an evidentiary hearing in July 2008 and, on
    November 24, 2008, issued a Partial Initial Decision resolving
    all but one of the remaining admitted contentions. Entergy
    Nuclear Vt. Yankee, LLC, 
    68 N.R.C. 763
     (2008). The order
    stated:
    With the exception of [two contentions resolved in
    favor of NEC and DPS and the one unresolved
    contention] and the opportunity to seek reconsideration
    of facts officially and judicially noticed, this Partial
    Initial Decision shall constitute the final decision of the
    Commission forty (40) days after the date of its
    issuance, unless, within fifteen (15) days of its service,
    a petition for review is filed in accordance with 
    10 C.F.R. §§ 2.1212
     and 2.341(b). Filing a petition for
    review is mandatory for a party to exhaust its
    administrative remedies before seeking judicial review.
    
    10 C.F.R. § 2.341
    (b)(1).
    
    Id. at 897
    . Both of the regulations the Board’s decision cited—
    
    10 C.F.R. §§ 2.1212
     and 2.341—plainly state: “Unless otherwise
    authorized by law, a party to an NRC proceeding must file a
    petition for Commission review before seeking judicial review
    of an agency action.”7
    7
    Regulation 2.1212, titled “Petitions for Commission review of
    initial decisions,” states in its entirety:
    Parties may file petitions for review of an initial decision
    12
    On March 10, 2011, the Commission issued a Memorandum
    and Order affirming a Board rejection of a contention litigated
    by NEC (but unrelated to section 401) and purporting to
    “terminate this proceeding.” Entergy Nuclear Vt. Yankee,
    L.L.C., Docket No. 50-271-LR, CLI-11-02, 
    2011 WL 864757
    ,
    at *8 (Mar. 10, 2011 NRC) (emphasis omitted). Accordingly,
    on March 21, 2011, the Commission issued a renewed license to
    operate Vermont Yankee for a twenty-year term. Entergy
    Nuclear Operations, Inc.; Vermont Yankee Nuclear Power
    Station; Notice of Issuance of Renewed Facility Operating
    License No. DPR-28 for an Additional 20-Year Period; Record
    of Decision, 
    76 Fed. Reg. 17,162
     (Mar. 28, 2011). NEC and
    DPS petitioned for review and Entergy intervened.
    II.
    The court has jurisdiction under the Hobbs Act, 
    28 U.S.C. §§ 2341
     et seq., to review “all final orders” of the NRC that are
    “made reviewable by section 2239 of title 42.” 28 U.S.C. §§
    under this subpart in accordance with the procedures set out
    in § 2.341. Unless otherwise authorized by law, a party to an
    NRC proceeding must file a petition for Commission review
    before seeking judicial review of an agency action.
    
    10 C.F.R. § 2.1212
    . Regulation 2.341in turn provides in relevant part:
    (b)(1) Within fifteen (15) days after service of a full or
    partial initial decision by a presiding officer, and within
    fifteen (15) days after service of any other decision or action
    by a presiding officer with respect to which a petition for
    review is authorized by this part, a party may file a petition
    for review with the Commission on the grounds specified in
    paragraph (b)(4) of this section. Unless otherwise authorized
    by law, a party to an NRC proceeding must file a petition
    for Commission review before seeking judicial review of an
    agency action.
    
    10 C.F.R. § 2.341
    (b)(1).
    13
    2342(4); see Honeywell Int’l, Inc. v. NRC, 
    628 F.3d 568
    , 575
    (D.C. Cir. 2010).8 We nonetheless decline to exercise
    jurisdiction because the petitioners failed to exhaust their
    administrative remedies and accordingly waived their section
    401 argument.
    We have recognized two distinct species of exhaustion
    requirements: (1) “non-jurisdictional exhaustion,” which is “a
    judicially created doctrine requiring parties who seek to
    challenge agency action to exhaust available administrative
    remedies before bringing their case to court”; and (2)
    “jurisdictional exhaustion,” which “arises when Congress
    requires resort to the administrative process as a predicate to
    judicial review.” Avocados Plus Inc. v. Veneman, 
    370 F.3d 1243
    , 1247 (D.C. Cir. 2004) (internal quotation marks omitted).
    “We presume exhaustion is non-jurisdictional unless ‘Congress
    states in clear, unequivocal terms that the judiciary is barred
    from hearing an action until the administrative agency has come
    8
    Section 2239 makes “subject to judicial review . . . [a]ny final
    order entered in any proceeding” under the AEA, 42 U.S.C. ch. 23,
    “for the granting, suspending, revoking, or amending of any license.”
    
    42 U.S.C. § 2239
    (b)(1), (a). Entergy contends the court lacks Hobbs
    Act jurisdiction here because the petitioners failed to timely petition
    for review within 60 days following the NRC’s March 10, 2011 order,
    which “resolved all challenges brought by DPS and NEC and
    terminated the proceeding.” Intervenor’s Br. 2 (citing Entergy
    Nuclear Vt. Yankee, LLC, CLI-11-02, 
    2011 WL 864757
    , at *8); see 
    28 U.S.C. § 2344
     (“Any party aggrieved by the final order may, within
    60 days after its entry, file a petition to review the order in the court
    of appeals wherein venue lies.”). The cited order, however, which was
    unrelated to the petitioners’ section 401 objection, is not the “final
    order” the petitioners claim aggrieved them. Their claimed
    aggrievement is the absence of a section 401 WQC when the license
    renewal itself issued ten days later, on March 21, 2011; the petitions
    for review were timely filed within 60 days thereafter, on May 20,
    2011.
    14
    to a decision.’ ” 
    Id. at 1248
     (quoting I.A.M. Nat’l Pension Fund
    Benefit Plan C v. Stockton Tri Indus., 
    727 F.2d 1204
    , 1208 (D.C.
    Cir. 1984)). The language of the Hobbs Act offers no such
    unequivocal bar. Cf. Daniels v. Union Pac. R.R. Co., 
    530 F.3d 936
    , 941 n. 9 (D.C. Cir. 2008) (relying in part on exhaustion’s
    non-jurisdictional presumption in declining to affirm district
    court’s dismissal of Hobbs Act action based on jurisdictional
    failure to exhaust). Precedent, however, counsels against our
    reviewing the petitioners’ unexhausted section 401 claim.
    In Sims v. Apfel, the United States Supreme Court observed
    that when “an agency’s regulations [] require issue exhaustion
    in administrative appeals[,] . . . courts reviewing agency action
    regularly ensure against the bypassing of that requirement by
    refusing to consider unexhausted issues.” 
    530 U.S. 103
    , 108
    (2000). In Environmentel, LLC v. FCC, relying on Sims, we
    concluded the petitioner had waived two issues it urged on
    appeal—one it had presented to a Federal Communications
    Commission (FCC) bureau but not to the FCC itself and one it
    had not raised at all at the administrative level. 
    661 F.3d 80
    , 84
    (D.C. Cir. 2011). We based our conclusion on an FCC
    regulation which (1) authorizes a “person aggrieved by any
    action taken pursuant to delegated authority [to] file an
    application requesting review of that action by the [FCC],” (2)
    requires a party seeking review by the full Commission of a
    decision by a delegated bureau to “concisely and plainly state
    the questions presented for review” and (3) provides that the
    “filing of an application for review shall be a condition
    precedent to judicial review of any action taken pursuant to
    delegated authority.” 
    47 C.F.R. § 1.115
    (a), (b)(1), (k); see
    Environmentel, 
    661 F.3d at 83-84
    . Under the regulation, we
    determined, “the full FCC must have the opportunity to review
    all cases and all aspects of those cases before parties may
    exercise their statutory right to appeal to this Court.” 
    661 F.3d at 84
    . We find the NRC regulations applicable here are
    materially indistinguishable from the FCC regulations in
    15
    Environmentel. In combination, 
    10 C.F.R. §§ 2.341
     and 2.1212
    (1) authorize “a party [to] file a petition for review with the
    Commission” of an initial decision or action by “the presiding
    officer”—here the Board; (2) require that the petition contain a
    “concise statement why in the petitioner’s view the decision or
    action is erroneous” and (3) provide that “[u]nless otherwise
    authorized by law, a party to an NRC proceeding must file a
    petition for Commission review before seeking judicial review
    of an agency action.” 
    10 C.F.R. § 2.341
    (b)(1), (b)(2)(iii),
    § 2.1212. Thus, like the petitioner in Environmentel, the
    petitioners here were required under agency regulations to afford
    the full Commission an opportunity to pass on the section 401
    issue before seeking judicial review. And they had repeated
    opportunities to do so.
    They could have petitioned the Commission for
    interlocutory review of the Board’s denial of their Late
    Contention/Request to Amend pursuant to 
    10 C.F.R. § 2.341
    (f)(2). Or they could have filed a new, separate
    contention limited to their section 401 objection either
    immediately after the Board’s denial (which advised that,
    although the objection was not “too late,” it involved “an
    independent statutory requirement” that was “simply irrelevant
    to [Contention 1]”) or upon discovering that neither the Draft
    nor the Final SEIS mentioned a section 401 WQC, see 
    10 C.F.R. § 2.309
    (c), (f)(2)—and, if the Board rejected the contentions,
    they could have petitioned the NRC for review. Or they could
    have submitted a comment for the Commission’s review in
    response to the December 2006 Draft SEIS and the
    Commission’s express solicitation of comment thereon. Or,
    they could have filed a petition for Commission review
    following the Board’s November 24, 2008 Partial Initial
    Decision (which omitted any mention of section 401) pursuant
    to 
    10 C.F.R. § 2.341
    (b)(1). Yet, notwithstanding all of these
    opportunities to fulfill the exhaustion requirement—and the
    Board’s admonition that “[f]iling a petition for review is
    16
    mandatory for a party to exhaust its administrative remedies
    before seeking judicial review[,] 
    10 C.F.R. § 2.341
    (b)(1),”
    Entergy Nuclear Vt. Yankee, LLC, 68 N.R.C. at 897—the
    petitioners sat silent for two and one-half years thereafter,
    raising their section 401 objection only after the Commission
    issued the license renewal in March 2011. In so doing, the
    petitioners undermined the functions exhaustion serves: “giving
    agencies the opportunity to correct their own errors, affording
    parties and courts the benefits of agencies’ expertise, and
    compiling a record adequate for judicial review.” Avocados
    Plus, 
    370 F.3d at 1247
     (quotation marks and brackets omitted).
    By failing to exhaust their section 401 argument, they waived
    judicial consideration thereof. See Environmentel, 
    661 F.3d at 83
     (“Environmentel waived its right to raise the ex parte and
    public notice issues because it failed to raise those issues before
    the full Commission . . . .”).
    The petitioners contend it would have been futile to raise
    the section 401 issue before the Commission, which “has clearly
    held that the issue of whether an applicant possesses a required
    CWA authorization is not appropriate for consideration as a
    contention in NRC licensing proceedings.” Reply Br. 19-20.
    None of the decisions they cite, however, supports their
    contention the Commission would have refused to decide the
    issue here, namely, whether an applicant for license renewal has
    obtained the requisite section 401 WQC before a license issues.
    Rather, in each of the decisions, the Commission (or the Board)
    declined either to undertake to evaluate for itself whether a
    particular permit was needed, to second guess the EPA or state
    agency’s decision to issue an environmental permit or to
    postpone conducting an application proceeding until a required
    permit or certification had been obtained.9 As the petitioners
    9
    See Hydro Res., Inc., 
    48 N.R.C. 119
    , 120 (1998) (“Whether
    non-NRC permits are required is the responsibility of bodies that issue
    17
    acknowledge, the NRC’s obligation to insure that operators
    obtain a § 401 WQC is purely “ministerial”—it does not require
    the NRC “to adjudicate substantive compliance issues under
    § 401 or state law, including the state law determinations of
    whether water quality standards will be met.” Pet’rs’ Br. 23.
    There is no reason to believe the NRC would have refused to
    carry out its obligation to ensure compliance with section 401’s
    WQC requirement.10 Cf. Commonwealth of Kentucky ex rel.
    such permits . . . .”); Va. Elec. & Power Co., 
    68 N.R.C. 294
    , 329
    (2008) (“evaluat[ing] whether [cooling unit] will comply with CWA
    or state and local permitting requirements” was “outside the scope of
    th[e] proceeding”); Dominion Nuclear Conn. Inc., 
    67 N.R.C. 421
    , 447
    & n.151 (2008) (whether applicant “has a valid NPDES permit is
    outside the scope of this [Board] proceeding” (citing Dominion
    Nuclear Conn., Inc., 
    60 N.R.C. 81
    , 92-93 (2004) (“While 
    10 C.F.R. § 51.45
    (d) requires an applicant seeking a license renewal to ‘list all
    Federal permits, licenses, approvals, and other entitlements which
    must be obtained in connection with the proposed action,’ it does not
    impose a requirement that the applicant actually possess such permits
    at the time of application.”) (emphasis added))); Pub. Serv. Co. of
    N.H., 
    2 N.R.C. 693
    , 693 (1975) (Board declined to stay NRC
    proceeding pending outcome of EPA review of its previous
    determinations, noting “Board, in its discretion, should proceed
    simultaneously with EPA so that each will reach its conclusions or
    decision in due course and with all reasonable dispatch”); Wis. Elec.
    Power Co., 
    8 A.E.C. 928
    , 930 (1974) (denying request to delay NRC
    proceeding as “premature” because state environmental agency had
    not yet issued section 401 WQC, noting “[a]s a general rule it is the
    practice of the Commission to pursue its administrative procedures
    while other state and local proceedings are under way”).
    10
    Indeed, the Commission took the position in its GEIS that the
    section 401 WQC requirement may be satisfied if an applicant has a
    NPDES permit because “issuance of an NPDES permit by a state
    water quality agency implies certification under Section 401.” GEIS
    § 4.2.1.1, at 4-4. The NRC asserts this is the rationale it would have
    18
    Stephens v. NRC, 
    626 F.2d 995
     (D.C. Cir. 1980) (upholding
    NRC construction work authorization based on Indiana WQC
    and NRC’s determination Ohio WQC was not needed because
    section 401(a)(1) discharge originated in Indiana rather than
    Ohio).
    The petitioners further assert their failure to exhaust should
    be excused under Avocados Plus. There, we noted a court “may,
    in its discretion, excuse exhaustion if ‘the litigant’s interests in
    immediate judicial review outweigh the government’s interests
    in the efficiency or administrative autonomy that the exhaustion
    doctrine is designed to further.’ ” 
    370 F.3d at 1247-48
     (quoting
    McCarthy v. Madigan, 
    503 U.S. 140
    , 146 (1992)). We find no
    such exculpatory circumstances here. The petitioners proffer
    proffered had the petitioners sought review of the Board’s decision as
    required. Appellee’s Br. 33-39. In addition, VANR suggested in both
    its scoping comments and its Draft SEIS comments that a section 402
    NPDES permit is sufficient to allay cooling system concerns. See
    VANR Memo. to NRC 1 (June 23, 2006) (“As we understand it, these
    issues are associated with intake structures and thermal discharge
    issues which require a NPDES permit. The requirements of the Clean
    Water Act and the NPDES permit will provide assurance that the
    impacts of permitted intake structures and discharges meet the
    applicable federal and state requirements.”); VANR Memo. to NRC
    5-6 (Mar. 8, 2007) (“[B]ecause the [CWA] requires that the discharge
    and the cooling water operations and structures comply with stringent
    standards that ensure the protection and propagation of a balanced
    indigenous community of shellfish, fish and wildlife[,] VANR concurs
    with the NRC conclusion that the impacts of the thermal discharge and
    fish impingement and entrainment [are] likely to be small. This is
    true, in large part, because the process associated with the NPDES
    permit is iterative in that it entails ongoing monitoring and review, and
    allows VANR to adjust the permit conditions regarding the cooling
    system operations and thermal regime. . . . The applicable state and
    federal standards under the CWA are protective of water quality and
    the environment and must be renewed every five years.”).
    19
    three reasons why “the instant dispute is the ‘occasional[]’ case
    in which ‘exhaustion will not fulfill these ends’ and is
    unnecessary”: (1) there are “ ‘no facts in dispute,’ . . . regarding
    the gravamen of Petitioners’ §401 claim”; (2) “ ‘the disputed
    issue[s]’ in this case are purely legal ones, and thus lie ‘outside
    the agency’s expertise’ ”; and (3) the petitioners “gave NRC
    numerous ‘opportunit[ies] to correct [its] own errors’ . . . by
    timely presenting the undisputed fact that, on this record,
    [Entergy] did not possess a §401 certification and that no license
    could be issued without such a certification.” Reply Br. 25-28
    (quoting Avocados Plus, 
    370 F.3d at 1247
    ). Addressing the last
    point first, the petitioners did not at any point in the
    administrative proceedings squarely present the section 401
    issue to the Commission itself, as the regulations require—only
    to the Board. See 
    10 C.F.R. §§ 2.1212
    , 2.341(b)(1). Moreover,
    while it is true that the facts are not in dispute, the Commission
    was deprived of the opportunity to advance and explain its
    position that Entergy’s NPDES permit may “impl[y]”
    certification under section 401, see supra note 10, or to consider
    Entergy’s claim that the 1970 WQC put it in compliance with
    the section 401 requirement, see Environmental Report § 9.2.1,
    supra p. 6. Under these circumstances, we do not find that any
    interest of the dilatory petitioners outweighs the Commission’s
    interest in efficiently administering its own statutory
    responsibilities and, accordingly, decline to exercise our
    discretion to excuse the failure to exhaust. See Woodford v.
    Ngo, 
    548 U.S. 81
    , 90 2006) (“[A]s a general rule[,] courts
    should not topple over administrative decisions unless the
    administrative body not only has erred, but has erred against
    objection made at the time appropriate under its practice.”
    (emphasis in original; quotation marks omitted)); Malladi Drugs
    & Pharm., Ltd. v. Tandy, 
    552 F.3d 885
    , 891, 384 (D.C. Cir.
    2009) (“Consistent with the concerns underlying exhaustion and
    waiver of claims, [appellants’] failure ‘to pursue normal
    administrative remedies’ here allowed it to ‘side-step[ ] a
    20
    corrective process which might have cured or rendered moot the
    very defect later complained of in court.’ ” (quoting McGee v.
    United States, 
    402 U.S. 479
    , 483 (1971)) (first alteration
    added)).
    For the foregoing reasons, we conclude that the petitioners
    failed to exhaust their administrative remedies before the
    Commission and thereby waived the right to raise their section
    401 objection on judicial review. Accordingly, we deny their
    petitions for review.
    So ordered.