Public Serv. Elec. and Gas Co. v. FERC , 783 F.3d 1270 ( 2015 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued January 7, 2014                 Decided April 14, 2015
    No. 12-1382
    PUBLIC SERVICE ELECTRIC AND GAS COMPANY, ET AL.,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    JERSEY CENTRAL POWER & LIGHT COMPANY, ET AL.,
    INTERVENORS
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    John Lee Shepherd Jr. argued the cause for petitioners.
    With him on the briefs were Jodi L. Moskowitz, Gary E. Guy,
    John Longstreth, Donald A. Kaplan, and William M. Keyser.
    Randall B. Palmer, Kenneth G. Jaffe, and Michael E.
    Ward were on the reply brief for intervenors Jersey Central
    Power & Light Company, et al. in support of petitioners.
    2
    Lona T. Perry, Senior Attorney, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With her on the brief were David L. Morenoff, Acting General
    Counsel, and Robert H. Solomon, Solicitor.
    Before: SRINIVASAN, Circuit Judge, and SENTELLE and
    RANDOLPH, Senior Circuit Judges.
    Opinion for the Court filed by Senior Circuit Judge
    SENTELLE.
    SENTELLE, Senior Circuit Judge: Petitioners are fourteen
    electrical transmission companies operating as members of
    the regional transmission organization PJM Interconnection,
    LLC. As incumbent members of the organization, petitioners
    contend that PJM’s governing agreements afford them a right
    of first refusal for proposed transmission facility expansions
    or upgrades within their zones.         The Federal Energy
    Regulatory Commission (“FERC”) held that no such right of
    first refusal exists and that PJM may designate third-party
    developers to construct transmission facilities within
    incumbent members’ zones. The incumbent transmission
    owners petition for review, arguing that the Commission lacks
    jurisdiction over transmission facility development and that
    the Commission’s interpretation of PJM’s governing
    agreements is arbitrary, capricious, or otherwise not in
    accordance with law under the Administrative Procedure Act,
    
    5 U.S.C. § 706
    (2).
    We held this case in abeyance pending the decision in
    South Carolina Public Service Authority v. FERC, 
    762 F.3d 41
     (D.C. Cir. 2014). Now that there is a final decision in that
    case, we remove this case from abeyance. After reviewing
    the original and supplemental briefing, and with the benefit of
    oral argument, we dismiss the petition for review because
    3
    Article III of the Constitution does not permit us to issue an
    advisory opinion.
    I.
    Petitioners are members of PJM Interconnection, LLC, a
    regional transmission organization “to which transmission
    providers . . . transfer operational control of their facilities for
    the purpose of efficient coordination.” Morgan Stanley
    Capital Grp. Inc. v. Pub. Util. Dist. No. 1 of Snohomish Cnty.,
    Wash., 
    554 U.S. 527
    , 536 (2008). Regional transmission
    organizations like PJM combine multiple utility power grids
    into a single transmission system to “reduce technical
    inefficiencies caused when different utilities operate different
    portions of the grid independently.” 
    Id.
     Formed in 1927,
    PJM is the oldest and largest regional transmission
    organization. Atlantic City Elec. Co. v. FERC, 
    295 F.3d 1
    , 5
    (D.C. Cir. 2002). Today, PJM coordinates the movement of
    wholesale electricity in thirteen mid-Atlantic states and the
    District of Columbia. Maryland Pub. Serv. Comm’n v. FERC,
    
    632 F.3d 1283
    , 1284 (D.C. Cir. 2011) (per curiam).
    “Among its duties, PJM is responsible for preventing
    interruptions to the delivery of electricity . . . by ensuring that
    its system has sufficient generating capacity.” 
    Id.
     PJM
    fulfills this duty in part by upgrading and enhancing its
    system in accordance with procedures set forth in its
    governing agreements, which include:                 the Regional
    Transmission Expansion Plan in PJM’s Operating Agreement,
    the Consolidated Transmission Owners Agreement (“Owners
    Agreement”), and the PJM Open Access Transmission Tariff
    (“Tariff”).
    Petitioners seek review of four FERC orders from two
    proceedings. In both proceedings, non-incumbent developers
    4
    argued that no right of first refusal existed within PJM’s
    governing agreements for incumbent transmission owners.
    A.
    The first proceeding arose on a petition to the
    Commission by Primary Power, LLC, a non-incumbent
    developer hoping to build the Grid Plus project, a proposed
    expansion project comprised of four installations within the
    PJM system. Primary Power sought FERC’s assurance that if
    it were selected for the project, it would be eligible to employ
    cost-based rate recovery in the operation of the project.
    Incumbent members of PJM, petitioners before us, opposed
    the petition, arguing that Section 1.5.6 of the Regional
    Transmission Expansion Plan created a right of first refusal
    which would be violated by the grant of rights to the
    newcomer. Section 1.5.6(f) states, in pertinent part:
    For each enhancement or expansion that is included in
    the recommended plan, the plan shall consider [a
    number of selection factors] . . . and designate one or
    more Transmission Owners or other entities to
    construct, own and, unless otherwise provided, finance
    the recommended transmission enhancement or
    expansion.     To the extent that one or more
    Transmission Owners are designated to construct, own
    and/or finance a recommended transmission
    enhancement or expansion, the recommended plan
    shall designate the Transmission Owner that owns
    transmission facilities located in the Zone where the
    particular enhancement or expansion is to be located.
    FERC rejected the incumbent transmission owners’
    arguments in Primary Power, LLC, 
    131 FERC ¶ 61,015
    5
    (2010) (order on petition for declaratory order). Interpreting
    PJM’s Operating Agreement, FERC explained that Sections
    1.5.7(c)(iii) and 1.5.6(f) of the Agreement allowed non-
    incumbent developers to compete for and construct projects
    under the expansion protocol. 
    Id.
     PP 62-65. FERC held that
    “the PJM Tariff permits, but does not require, PJM to
    designate Primary Power, an entity other than an incumbent
    transmission owner, as the entity to build Grid Plus.” 
    Id.
    P 62. FERC concluded that Section 1.5.6(f) did not create a
    right of first refusal for incumbent transmission owners
    because the “shall designate” clause requiring PJM to assign
    projects to transmission owners who own facilities in the zone
    where the project is located only “applies by its own terms ‘to
    the extent that one or more Transmission Owners are
    designated.’” 
    Id.
     P 65 (quoting Operating Agreement
    § 1.5.6(f)). The “shall designate” clause, FERC further
    explained, does not apply when PJM designates non-
    incumbent “other entities” to construct the project. Id. P 64.
    Addressing the recovery of development costs, FERC
    acknowledged that merchant transmission facilities are not
    eligible for cost-based rates under the PJM Tariff. Id. P 68.
    But if PJM includes the Grid Plus project in its expansion
    plan, FERC explained that Primary Power “would be eligible
    to seek cost-based rate recovery as would any other
    transmission owner.” Id. P 70. In other words, FERC noted
    that the “PJM’s Tariff contains no prohibition on a non-
    incumbent party becoming a transmission owner to receive
    cost-based rates.” Id.
    Incumbent transmission owners timely sought rehearing.
    Among other things, they argued that FERC ignored their
    exclusive right to build and operate all non-merchant projects
    in their own zones, and FERC misinterpreted the “other
    entity” language from Section 1.5.6(f) of the PJM Operating
    Agreement. Incumbent transmission owners also suggested
    6
    that FERC exceeded its statutory authority when it required
    them to give up rights that they did not cede to PJM.
    FERC denied the rehearing request and affirmed its
    previous order. Primary Power, LLC, 
    140 FERC ¶ 61,052
    (2012) (order denying rehearing). Although the language
    from the expansion protocol is ambiguous, FERC reiterated
    that it neither established a right of first refusal for incumbent
    transmission owners nor precluded a non-incumbent
    developer from recovering cost-based rates if selected for a
    project under PJM’s expansion plan. 
    Id.
     P 35. In light of
    PJM’s obligation to operate in a non-discriminatory manner,
    FERC interpreted PJM’s expansion protocol as “provid[ing]
    an opportunity for a wide variety of participants and different
    business models.” 
    Id.
     FERC stressed that, while incumbent
    transmission owners may participate in the process, PJM’s
    protocol neither guaranteed incumbent owners the right to
    construct projects in their zones nor required them to
    undertake such construction. 
    Id.
    B.
    In the second proceeding under review, non-incumbent
    developer Central Transmission, LLC, filed a complaint
    pursuant to Section 206 of the Federal Power Act (“FPA”),
    alleging that the PJM Tariff is unjust and unreasonable
    because it prevents Central Transmission from constructing a
    proposed transmission project and receiving cost-based rate
    recovery for it. Incumbent transmission owners protested,
    arguing that the complaint should be dismissed because
    Central Transmission did not satisfy the burden of proof
    under Section 206. The right of first refusal, incumbent
    owners explained, did not create a barrier to entry because
    non-incumbent developers like Central Transmission were
    free to build PJM expansion projects as merchant developers.
    7
    FERC dismissed the complaint, concluding that the
    Section 206 proceeding was unnecessary. See Central
    Transmission, LLC v. PJM Interconnection, LLC, 
    131 FERC ¶ 61,243
     (2010) (order on complaint). Applying its decision
    in Primary Power, 
    131 FERC ¶ 61,015
     (2010), FERC
    explained that PJM’s governing agreements allowed non-
    incumbent parties like Central Transmission to become
    transmission owners eligible for cost-based rates. Central
    Transmission, LLC, 
    131 FERC ¶ 61,243
    , P 46. Consequently,
    FERC saw no need to revise the PJM Tariff or Operating
    Agreement. 
    Id.
     P 48.
    Petitioner Public Service Electric and Gas Company
    (“PSEG”) timely sought rehearing. Taking no issue with the
    ultimate result (dismissal of the complaint), PSEG instead
    objected to the Commission’s reliance on the Primary Power
    order. The Central Transmission and Primary Power orders,
    PSEG argued, ignored incumbent transmission owners’
    exclusive right to build projects in their own zones.
    According to PSEG, the Commission’s reading of PJM’s
    governing agreements was simply wrong.
    The Commission denied PSEG’s rehearing request on the
    same day that it denied rehearing in Primary Power. See
    Central Transmission, LLC v. PJM Interconnection, LLC, 
    140 FERC ¶ 61,053
     (2012) (order on rehearing). Consistent with
    its Primary Power order, the Commission reiterated that
    PJM’s expansion protocol does not grant incumbent
    transmission owners a right of first refusal that would prevent
    non-incumbent transmission developers from building an
    economic project. 
    Id.
     P 17.
    C.
    As noted above, we held this case in abeyance pending
    the decision in South Carolina Public Service Authority v.
    FERC because we hoped to “benefit from resolution of the
    8
    question of FERC’s authority to prohibit a regional
    transmission organization’s tariff from including a right of
    first refusal for incumbent transmission owners to build and
    operate transmission facilities.” Pub. Serv. Elec. & Gas Co.,
    et al. v. FERC, No. 12-1382 (D.C. Cir. Jan. 15, 2014) (order
    holding case in abeyance). In South Carolina Public Service
    Authority v. FERC, petitioners challenged the Commission’s
    authority to adopt Order No. 1000, which required
    transmission providers to remove from their “jurisdictional
    tariffs and agreements any provisions that establish a federal
    right of first refusal for an incumbent transmission developer
    to construct new regional transmission facilities included in a
    regional transmission plan.” Transmission Planning and Cost
    Allocation by Transmission Owning and Operating Public
    Utilities, Order 1000, 
    76 Fed. Reg. 49,842
    , 49,846 (Aug. 11,
    2011).
    The South Carolina petitioners argued that Section 206
    of the FPA prevented FERC from removing rights of first
    refusal under Order No. 1000 because the rights of first
    refusal were too attenuated from a “practice” “affecting . . .
    rate[s].” S.C. Pub. Serv. Auth., 762 F.3d at 84. This Court
    applied the familiar two-step framework of Chevron U.S.A.
    Inc. v. Natural Resources Defense Council, Inc., 
    467 U.S. 837
    (1984), rejected petitioners’ argument, and held “that the
    removal mandate is a legitimate exercise of the Commission’s
    authority.” S.C. Pub. Serv. Auth., 762 F.3d at 72.
    While this petition was pending, FERC directed PJM to
    comply with Order No. 1000 and remove or revise “any
    provision that could be read as supplying a federal right of
    first refusal for any type of transmission project that is
    selected in the regional transmission plan for purposes of cost
    allocation.” PJM Interconnection, LLC, 
    142 FERC ¶ 61,214
    ,
    P 222. PJM complied, and, as of the January 1, 2014
    effective date, PJM’s governing agreements no longer contain
    9
    language that could be read to create a right of first refusal for
    incumbent transmission owners. PJM Interconnection, LLC,
    
    147 FERC ¶ 61,128
    , P 29. Because we are now left
    interpreting superseded language from PJM’s governing
    agreements, FERC contends that this case no longer presents
    a live controversy and any decision at this time would
    constitute an impermissible advisory opinion. Resp’t Supp’l
    Br. 12 (citing Princeton Univ. v. Schmid, 
    455 U.S. 100
    , 103
    (1982)). For the reasons explained below, we agree.
    II.
    “‘[T]he oldest and most consistent thread in the federal
    law of justiciability is that the federal courts will not give
    advisory opinions.’” Flast v. Cohen, 
    392 U.S. 83
    , 96 (1968)
    (quoting C. Wright, Federal Courts 34 (1963)). To satisfy the
    firmly established Article III case or controversy requirement,
    “there must be a live controversy at the time” we review the
    case. Sosna v. Iowa, 
    419 U.S. 393
    , 402 (1975). It is not
    enough that there may have been a live controversy when the
    petitioners first filed their appeal. See Burke v. Barnes, 
    479 U.S. 361
    , 363 (1987); Chamber of Commerce v. EPA, 
    642 F.3d 192
    , 199 (D.C. Cir. 2011).
    Petitioners concede that their jurisdictional argument fails
    under South Carolina Public Service Authority v. FERC, yet
    suggest that there is still a live controversy because nothing
    from that case impacted petitioners’ argument that FERC’s
    interpretation of PJM’s governing agreements was arbitrary
    and capricious. Pet’rs Supp’l Br. 4–5. If we do not address
    the merits of their argument, petitioners explain, any future
    challenge to the Central Transmission and Primary Power
    orders will amount to an impermissible collateral attack on
    those orders. Pet’rs Reply Br. 17 (citing Pacific Gas & Elec.
    Co. v. FERC, 
    533 F.3d 820
    , 825 (D.C. Cir. 2008); Wisc.
    Public Power, Inc. v. FERC, 493 F3d 239, 265-66 (D.C. Cir.
    2007)). While petitioners are no doubt correct that our
    10
    decision today ends any direct review of the FERC decisions
    before us, that does not inherently preclude this court from
    answering similar questions should they arise in the future in
    a live controversy.
    Indeed, petitioners are involved in ongoing litigation
    challenging FERC’s compliance orders that required them to
    remove any provision that could be read as supplying a right
    of first refusal from PJM’s governing agreements. See
    American Transmission Systems, Inc., et al. v. FERC, Nos.
    14-1085 & 14-1136 (D.C. Cir. filed May 27, 2014). That case
    involves the interpretation of the same language from the
    now-superseded agreements at issue in this case. See PJM
    Interconnection, LLC, 
    142 FERC ¶ 61,214
    , PP 221-24; PJM
    Interconnection, LLC, 
    147 FERC ¶ 61,128
    , PP 94-103.
    Petitioners explain: “The chief question presented in that case
    is whether FERC violated the Mobile-Sierra doctrine by
    directing PJM and the PJM Transmission Owners (including
    the Petitioners in this case) to remove or change the same
    provisions of PJM’s governing agreements and PJM Tariff
    whose meaning is disputed in this petition for review.” Pet’rs
    Supp’l Br. 5.
    The Mobile-Sierra doctrine requires FERC to presume
    “that a rate set by a freely negotiated wholesale-energy
    contract meets the just and reasonable requirement” from the
    FPA, 16 U.S.C. § 824d(a). NRG Power Marketing, LLC v.
    Maine Pub. Util. Comm’n, 
    558 U.S. 165
    , 167 (2010) (internal
    quotation marks omitted). When it clarified the impact of
    Order No. 1000, FERC explained that it would not require
    “transmission providers to eliminate a federal right of first
    refusal before the Commission makes a determination
    regarding whether an agreement is protected by a Mobile-
    Sierra provision.”       Transmission Planning and Cost
    Allocation, 
    77 Fed. Reg. 32,184
    , 32,245 (May 31, 2012). In
    South Carolina Public Service Authority v. FERC, this Court
    11
    deferred consideration of “whether or how Mobile-Sierra will
    ultimately apply to particular contracts” because the effects of
    the order had not been felt by the parties. 762 F.3d at 81
    (citing Associated Gas Distribs. v. FERC, 
    824 F.2d 981
    , 1007
    (D.C. Cir. 1987)).
    Unlike the petitioners in South Carolina, petitioners in
    this case have felt the effects of the order because FERC
    concluded that the disputed provisions from PJM’s governing
    agreements were “not in compliance with Order No. 1000’s
    requirement to eliminate any federal right of first refusal” and
    directed PJM to remove the provisions in its compliance
    order. PJM Interconnection, LLC, 
    142 FERC ¶ 61,214
    ,
    P 221. FERC’s interpretation of PJM’s governing agreements
    as they existed before January 1, 2014 only presents a live
    controversy to the extent that it is coupled with, and thus
    impacts, petitioners’ ongoing Mobile-Sierra challenge. But
    petitioners’ Mobile-Sierra challenge is not directly before
    us—instead, it is present in American Transmission Systems,
    Inc., et al. v. FERC. Consequently, we conclude that the issue
    before us (the proper interpretation of the superseded
    language from PJM’s governing agreements) does not present
    a live controversy.
    ***
    With no live controversy between adverse parties, we
    conclude that any decision issued at this time would constitute
    an impermissible advisory opinion. We must therefore
    dismiss incumbent transmission owners’ petition for review.
    So ordered.