Sierra Club v. United States Army Corps , 803 F.3d 31 ( 2015 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued April 9, 2015              Decided September 29, 2015
    No. 14-5205
    SIERRA CLUB,
    APPELLANT
    v.
    UNITED STATES ARMY CORPS OF ENGINEERS, ET AL.,
    APPELLEES
    Appeal from the United States District Court
    for the District of Columbia
    (No. 1:13-cv-01239)
    Douglas P. Hayes argued the cause for appellant. With
    him on the briefs were Eric E. Huber and Joshua Stebbins.
    Michael T. Gray, Attorney, U.S. Department of Justice,
    argued the cause for Federal appellees. With him on the brief
    were John C. Cruden, Assistant Attorney General, and Ty
    Bair and David C. Shilton, Attorneys.
    David H. Coburn and Cynthia Taub were on the brief for
    appellee Enbridge Pipelines (FSP), L.L.C. Joshua H. Runyan
    entered an appearance.
    Before: BROWN, PILLARD and WILKINS, Circuit Judges.
    2
    Opinion for the Court filed by Circuit Judge PILLARD.
    Opinion concurring in the judgment filed by Circuit
    Judge BROWN.
    PILLARD, Circuit Judge: The central question in this
    appeal is the scope of environmental review the National
    Environmental Policy Act (NEPA) required before a
    particular oil pipeline was built. Oil pipelines help to satisfy
    national and global energy demand by pumping tens of
    millions of barrels of oil across the United States each month.
    They have also sparked intense debates about energy and
    environmental policies. The proposed Keystone XL Pipeline
    alone has generated millions of comments to the government
    on a spectrum of issues. The construction and operation of
    pipelines necessarily affect land, water, air, plants, animals,
    and human life, and carry the potential for unintended
    damage. More than a dozen pipeline accidents occur on
    average each month in the United States—most minor, some
    grave. If not transported via pipelines, oil might remain in the
    ground and never be used, or might be brought to market in
    other ways—potentially by methods less efficient and more
    harmful than pipeline transportation.
    The U.S. Secretary of State must approve oil pipelines
    that cross international borders, see Exec. Order 11,423, 33
    Fed. Reg. 11,741 (Aug. 16, 1968), but that requirement is
    inapplicable to wholly domestic pipelines. Separately, the
    Pipeline and Hazardous Materials Safety Administration
    (PHMSA) within the U.S. Department of Transportation must
    approve oil spill response plans under the Oil Pollution
    Control Act of 1990 for pipelines that might spill oil into
    navigable waters or the shoreline, see 33 U.S.C. §
    1321(j)(5)(A)(i), (C)(iv), (G); Executive Order 12,777, 56
    Fed. Reg. 54,757, 54,760 (Oct. 18, 1991), 49 C.F.R. § 194.7,
    3
    but there is no claim here PHMSA must approve a response
    plan before a pipeline can be built and begin operating.1
    Notwithstanding the absence of any general permitting
    requirement for domestic oil pipelines, federal ownership or
    control of lands and other assets, as well as resource-specific
    environmental statutes such as the Clean Water Act, often do
    call for federal approvals before an oil pipeline can be built.
    Where there is federal action, NEPA requires governmental
    review, with public input, of the full range of such action’s
    reasonably foreseeable direct or indirect environmental
    effects. Federal actions subject to NEPA include federal
    authorizations granted to private parties, such as oil pipeline
    construction companies.
    The Flanagan South oil pipeline pumps crude oil across
    593 miles of American heartland from Illinois to Oklahoma.
    Almost all of the land over which it passes is privately owned.
    As soon as Enbridge Pipelines (FSP), LLC, (Enbridge) began
    building the pipeline in 2013, the Sierra Club, a national
    environmental nonprofit organization, sued the federal
    government seeking to set aside several federal agencies’
    regulatory approvals relating to the pipeline and to enjoin the
    pipeline’s construction and operation in reliance on any such
    approvals.
    Sierra Club’s chief claim was that various federal
    easements and approvals that Enbridge obtained from the
    agencies gave necessary go-ahead to the Flanagan South
    project as a whole, and thus the entire pipeline was a
    foreseeable effect of federal action requiring public
    environmental scrutiny under NEPA. Sierra Club also
    1
    The complaint asserted a PHMSA-related NEPA claim, but the
    district court dismissed that claim for lack of final agency action
    because no oil spill response plan had been finalized.
    4
    claimed that one of the agencies, the United States Army
    Corps of Engineers (the Corps), unlawfully authorized dredge
    and fill activities at the pipeline’s nearly two thousand minor
    water crossings by verifying that they fell within the authority
    of a general permit, Nationwide Permit 12, that the Corps had
    promulgated under the Clean Water Act. Sierra Club argued
    that the Corps impermissibly conducted its analyses of the
    water crossings’ cumulative impacts by region, rather than
    considering the pipeline as a whole, and that its conclusions
    that the crossings would have only minimal adverse
    environmental effects were inadequately supported and
    conclusory. After Sierra Club filed suit, Enbridge promptly
    intervened as a defendant.           The district court denied
    preliminary injunctive relief and entered summary judgment
    in favor of the agencies and Enbridge.
    On appeal, Sierra Club principally contends that the
    district court erred by failing to require the agencies to
    analyze and invite public comment on the environmental
    impact of the whole pipeline under NEPA, including the
    lengthy portions crossing private land and not otherwise
    subject to federal approvals. Sierra Club also presses its
    challenge to the Corps’s Clean Water Act verifications of the
    pipeline’s many water crossings. Sierra Club further contends
    that the district court reversibly erred by failing to allow the
    organization to supplement and amend its complaint. Sierra
    Club’s proposed new complaint added claims that the Corps
    and the Bureau of Indian Affairs within the U.S. Department
    of the Interior (the Bureau) had, while the litigation was
    pending, completed separate NEPA analyses relating to each
    of the easements the agencies had granted for the pipeline to
    cross federally controlled land, and that those analyses were
    insufficient.
    5
    We hold that the federal government was not required to
    conduct NEPA analysis of the entirety of the Flanagan South
    pipeline, including portions not subject to federal control or
    permitting. The agencies’ respective regulatory actions—in
    the form of easements, Clean Water Act verifications, and
    authorization to harm or kill members of endangered species
    without incurring liability under the Endangered Species Act
    (ESA)—were limited to discrete geographic segments of the
    pipeline comprising less than five percent of its overall length.
    As explained below, the agencies were required to conduct
    NEPA analysis of the foreseeable direct and indirect effects of
    those regulatory actions. However, on the facts of this case,
    the agencies were not obligated also to analyze the impact of
    the construction and operation of the entire pipeline.       We
    also reject Sierra Club’s Clean Water Act challenge to the
    Corps’s verifications of Flanagan South’s water crossings
    under Nationwide Permit 12 because the Corps was
    authorized to conduct its review on a regional rather than
    nationwide basis, and the Corps’s District Managers
    adequately supported their verification decisions. Finally, we
    hold that the district court did not abuse its discretion in
    denying Sierra Club’s motion to supplement and amend its
    complaint, because the proposed new allegations would not
    have affected the dispositive legal analysis.
    I.   Background
    A.    Flanagan South Planning
    Enbridge began the planning and permitting process for
    the Flanagan South project in 2011. The 593-mile-long
    pipeline was designed to ship roughly 600,000 barrels of oil
    per day across Illinois, Missouri, Kansas, and Oklahoma. The
    new pipeline would expand Enbridge’s capacity to ship crude
    oil from Flanagan, Illinois, to a major terminal in Cushing,
    6
    Oklahoma. From Cushing, the oil was to flow to refineries on
    the Gulf Coast and elsewhere. Enbridge designed the pipeline
    to run parallel to an existing pipeline, the Spearhead pipeline,
    which had been in operation since 2006.
    Roughly four-fifths of Flanagan South would track within
    50 feet of the existing Spearhead pipeline. Most of the 36”-
    diameter Flanagan South pipeline was to be buried at least
    four feet underground in trenches dug approximately ten feet
    wide and deep. As planned, the pipeline would pass
    underneath roads and streambeds and cross approximately
    400 miles of farmland, 85 miles of forests, 68 miles of
    grasslands, 28 miles of developed land, and 10 miles of
    wetlands. Flanagan South’s construction would require
    grading, excavation, or other forms of earth-disturbing
    activities in order to erect, inspect, and maintain the pipeline
    itself and its supporting infrastructure, such as pumping
    stations, mainline valves, pipe yards and access roads. The
    construction activities would affect swaths of land as wide as
    135 feet, and ongoing maintenance would use a permanent
    50-foot-wide right of way, kept clear by cutting back
    vegetation every three to five years and possible application
    of herbicides. Of the sixty eight miles of access roads
    anticipated for the pipeline, roughly seven miles would be
    newly constructed, with most of the new roads crossing non-
    forested, agricultural areas not requiring tree removal.
    Enbridge budgeted more than $2.5 billion to build
    Flanagan South and sought to complete construction by June
    2014, only ten months after breaking ground. Before starting
    construction, Enbridge negotiated rights of way across
    approximately 2,400 tracts of land owned by approximately
    1,700 private landowners. The company conducted public
    outreach campaigns and solicited input from local officials,
    Indian nations, community groups, and landowners expected
    7
    to be affected by the project. Enbridge also sought regulatory
    authorizations from local and state governmental entities, as
    well as federal agencies.
    The parties do not dispute that, to complete construction
    of the pipeline, Enbridge required easements from the Corps
    and the Bureau to cross spans of federal and Indian lands, and
    Clean Water Act approvals from the Corps to conduct dredge
    and fill activities at water crossings. The parties also
    recognize that, in granting those permissions, the Corps and
    Bureau were required to consult with the U.S. Fish and
    Wildlife Service (the Service) pursuant to Section 7 of the
    ESA regarding the harm to endangered or threatened species
    anticipated to result from those permissions. They further
    recognize that Enbridge could not lawfully harm listed species
    unless it obtained either a safe harbor from the Section 7
    consultation process, see 16 U.S.C. § 1536, or a permit under
    Section 10 of the ESA, see 
    id. § 1539,
    discussed below.
    Enbridge urged the agencies to act quickly so that it
    could meet its construction deadlines, and the agencies did so.
    Enbridge obtained Clean Water Act verifications from the
    Corps for the pipeline to make water crossings, as well as
    easements from the Corps and the Bureau to cross federal and
    Indian lands. The Corps and Bureau also consulted with the
    Service pursuant to ESA Section 7 regarding their approvals’
    potential impact on listed species, and the Service issued a
    Biological Opinion regarding the Flanagan South project’s
    anticipated impact.
    The Biological Opinion concluded that building and
    operating Flanagan South would likely result in some
    “take”—i.e., harming or killing—of two listed, endangered
    species, the Indiana Bat and the American Burying Beetle, but
    that the take would not be so extensive as to jeopardize the
    8
    continued existence of either species.2 The Biological
    Opinion contained an Incidental Take Statement (ITS) that
    identified reasonable and prudent measures, chiefly habitat
    restoration and monitoring measures, by which Enbridge
    could minimize the anticipated take of the two species that
    would occur incidental to the project, and set forth mandatory
    terms and conditions to that end. The ITS provided Enbridge
    a conditional safe harbor from liability under the ESA for any
    taking of listed species, but that permission was limited: By
    its own terms, it was valid only insofar as the Corps or Bureau
    imposed the ITS on Enbridge by incorporating it as a binding,
    enforceable term of permits or contracts they issued to
    Enbridge to which Enbridge in fact adhered. The easements
    that the Corps and Bureau granted to Enbridge did not purport
    to incorporate and enforce the ITS, and the Corps’s
    verifications did so only within the geographic segments of
    the Corps’s Clean Water Act jurisdiction over the verified
    water crossing areas. Enbridge considered but decided
    against applying to the Service for a Section 10 permit to take
    species, instead of or in addition to obtaining the safe harbor
    resulting from the verifications’ incorporation of the Section 7
    ITS.
    The Corps conducted a NEPA analysis when it reissued
    Nationwide Permit 12, see 77 Fed. Reg. 10,184, 10,197 (Feb.
    2
    The Indiana bat is a medium-sized migratory bat found in the
    eastern United States that faces threats to its habitat for hibernation,
    roosting, forage, migration and swarming. It has been listed as an
    endangered species since 1967, when it was originally listed under
    the Endangered Species Preservation Act of 1966, a predecessor to
    the ESA. 32 Fed. Reg. 4,001 (Mar. 11, 1967). The American
    Burying Beetle is a uniquely large, colorful beetle, found chiefly in
    a few central states, whose numbers have been depleted due largely
    to the fragmentation of its habitat. It has been listed as endangered
    since 1989. 54 Fed. Reg. 29,652 (July 13, 1989).
    9
    21, 2012), and the Corps and the Bureau each completed
    geographically limited NEPA analyses in conjunction with
    the easements they granted. No agency performed a NEPA
    analysis of the full Flanagan South project.
    B. NEPA’s Environmental Review Requirement
    NEPA requires the federal government to identify and
    assess in advance the likely environmental impact of its
    proposed actions, including its authorization or permitting of
    private actions. Dep’t of Transp. v. Pub. Citizen, 
    541 U.S. 752
    , 756-57 (2004). NEPA’s mandate, which incorporates
    notice and comment procedures, serves the twin purposes of
    ensuring that (1) agency decisions include informed and
    careful consideration of environmental impact, and (2)
    agencies inform the public of that impact and enable
    interested persons to participate in deciding what projects
    agencies should approve and under what terms. 
    Id. at 768.
    The statute serves those purposes by requiring federal
    agencies to take a “hard look” at their proposed actions’
    environmental consequences in advance of deciding whether
    and how to proceed. Robertson v. Methow Valley Citizens
    Council, 
    490 U.S. 332
    , 350-51 (1989). The statute does not
    dictate particular decisional outcomes, but “merely prohibits
    uninformed—rather than unwise—agency action.” 
    Id. at 351;
    see also Pub. 
    Citizen, 541 U.S. at 756-57
    .
    At the heart of NEPA is the procedural requirement that
    federal agencies prepare and make publicly available, in
    anticipation of proposed “major Federal actions significantly
    affecting the quality of the human environment,” an
    Environmental Impact Statement (EIS) that assesses the
    action’s anticipated direct and indirect environmental effects,
    and that the agencies consider alternatives that might lessen
    any adverse environmental impact. 42 U.S.C. § 4332(C); 40
    10
    C.F.R. § 1508.11. Regulations promulgated by the Council
    on Environmental Quality (CEQ) provide common guidance
    for all federal agencies in carrying out their NEPA
    responsibilities. Pub. 
    Citizen, 541 U.S. at 757
    ; see 40 C.F.R.
    pts. 1501-02. Some agencies, such as the Corps, have
    promulgated their own, complementary NEPA regulations in
    order to provide additional guidance to their personnel to
    carry out the directives of the statute and the CEQ regulations
    in agency-specific contexts. See, e.g., 33 C.F.R. § 325 App. B
    (Corps regulations); see also 40 C.F.R. § 1500.2(a)-(b).
    The CEQ regulations explain that NEPA’s “federal
    actions” may encompass the federal government’s own
    undertakings, such as promulgating a rule or building a public
    project, as well as government authorizations or support of
    non-federal activities, such as approving private construction
    activities “by permit or other regulatory decision.” 40 C.F.R.
    § 1508.18(a), (b)(4). The CEQ regulations clarify that the
    term “major” “reinforces but does not have a meaning
    independent of significantly,” 40 C.F.R. § 1508.18, and
    explain that interpretation of the term “significantly” entails
    case-by-case consideration of the context of the action and the
    severity of its impact, 
    id. § 1508.27.
    When it is uncertain whether a proposed federal action
    will “significantly affect” the environment so as to require an
    EIS, the regulations call for the agency to prepare an
    Environmental Assessment (EA)—essentially, a preliminary
    consideration of potential environmental effects in a “concise
    public document” designed to “provide sufficient evidence
    and analysis for determining whether” an EIS is needed. 
    Id. §§ 1501.4(b)-(c),
    1508.9; see Pub. 
    Citizen, 541 U.S. at 757
    -
    58. If, informed by the EA, the agency finds no need for an
    EIS, it must prepare a “finding of no significant impact”
    (FONSI) that includes or summarizes the EA and briefly
    11
    explains why the agency believes the action will not have a
    significant effect on the environment.             40 C.F.R.
    §§ 1501.4(e), 1508.13. For example, the EAs performed by
    the Corps and the Bureau in this case assessed the anticipated
    environmental effects—on soil, water, species, air quality,
    noise, and cultural resources—of granting Enbridge’s
    requested easements to run Flanagan South across the federal
    lands. The agencies’ EAs resulted in a FONSI for each
    easement. Each form of NEPA analysis—EA/FONSI or
    EIS—requires public notice and comment, 
    id. §§ 1503.1,
    1501.4(e), 1506.6, and each is subject to judicial review, see,
    e.g., Pub. 
    Citizen, 541 U.S. at 763-64
    ; Grand Canyon Trust v.
    FAA, 
    290 F.3d 339
    , 340-42 (D.C. Cir. 2002).
    Sierra Club’s objection in this suit concerns the scope,
    not the intensiveness, of the agencies’ analyses. That is,
    Sierra Club does not complain that an agency improperly
    prepared an EA and issued a FONSI when it should have
    prepared an EIS. Rather, it complains that no agency ever
    conducted pipeline-wide NEPA analysis to any degree,
    whether an EA or an EIS.
    Sierra Club identifies three groups of federal agency
    approvals that, it contends, support its claim that federal law
    requires a pipeline-wide NEPA analysis of the Flanagan
    South project: (1) easements granted by the Corps and the
    Bureau for the pipeline to span two parcels of federally owned
    riverside land and 34 parcels of federally managed Indian
    lands; (2) Clean Water Act verifications issued by the Corps
    concluding that 1,950 water crossings complied with the
    Clean Water Act under Nationwide Permit 12; and (3)
    conditional permission for Enbridge to take endangered
    species in the course of constructing and maintaining the
    pipeline without incurring liability under the ESA—
    permission provided through an Incidental Take Statement,
    12
    issued by the Service and implemented by the Corps in its
    verifications.   Sierra Club contends that those actions
    triggered a requirement under NEPA that one of the agencies
    review the environmental impact of the entire pipeline,
    including portions outside the segments that the federal
    actions purported to address.
    1.    Easements Across Federal or Indian Lands
    Both the Corps and the Bureau granted Enbridge
    easements to cross federal and Indian lands. See 30 U.S.C.
    § 185(a) (authorizing agencies to issue rights of way for
    transportation of oil and gas across federal lands); 25 U.S.C. §
    321 (authorizing the Department of the Interior to issue rights
    of way for oil and gas transportation across Indian lands).
    The Corps easements allowed the pipeline to cross 1.3 miles
    of land in two parcels owned by the federal government along
    the Mississippi and Arkansas Rivers. The Bureau easements
    afforded rights of way across 34 tracts, or 12.3 total miles, of
    Indian lands the Bureau manages in trust for tribes. The
    Corps and Bureau prepared three discrete NEPA analyses, in
    the form of EAs, to consider the anticipated environmental
    effects of granting Enbridge rights to construct segments of
    the pipeline across those lands. Each analysis considered only
    the environmental impact anticipated within its respective
    geographic area.
    2.   Clean Water Act Verifications Under
    Nationwide Permit 12
    The next category of federal actions involved
    verifications by the Corps, which authorized the Flanagan
    South pipeline to cross minor waterways consistent with the
    Clean Water Act.        The Corps has responsibility for
    implementing the provisions of the Act relevant here,
    including by requiring permits for construction activities that
    13
    involve dredge and fill of water features (including wetlands)
    subject to the Act’s jurisdiction. See 33 U.S.C. § 1344. The
    Corps grants Clean Water Act permits in one of two ways: It
    issues individual permits that are tailored to specific projects,
    
    id. § 1344(a),
    or it promulgates general permits, such as
    Nationwide Permit 12, and later “verifies” that specific
    manifestations of a generally approved type of project, such
    as crossings by pipelines and other utility lines, qualify
    thereunder, see 
    id. § 1344(e);
    see also Reissuance of
    Nationwide Permits, 77 Fed. Reg. 10,184, 10,271-72 (Feb. 21,
    2012).
    General permits authorize categories of actions that will,
    alone and together, cause only minimal adverse
    environmental effects. 33 U.S.C. § 1344(e). They may
    extend to activities throughout a state, a region, or the nation;
    must be reevaluated at least every five years if they are to be
    reissued; and may contain general conditions applicable to all
    projects subject to approval thereunder. See 
    id. Nationwide Permit
    12 “addresses the construction, maintenance, repair,
    and removal of all utility lines throughout the nation,”
    including lines “carrying resources (like water, fuel, and
    electricity), facilitating communication (like telephone lines,
    internet connections, and cable television), and removing
    waste.” Sierra Club, Inc. v. Bostick, 
    787 F.3d 1043
    , 1058
    (10th Cir. 2015); see also 77 Fed. Reg. at 10,271-72 (broadly
    defining “utility line” to include “any pipe or pipeline for the
    transportation of any gaseous, liquid, liquescent, or slurry
    substance, for any purpose, and any cable, line, or wire for the
    transmission for any purpose of electrical energy, telephone,
    and telegraph messages, and radio and television
    communication”). There is no dispute that the Flanagan
    South oil pipeline qualifies as a “utility line” under
    Nationwide Permit 12. Nationwide Permit 12 authorizes
    utility line construction activities that affect no more than a
    14
    half-acre of jurisdictional waters at any single crossing. See
    77 Fed. Reg. at 10,271, 10,290.
    After the Corps has promulgated a general permit, with
    public notice and an opportunity for a hearing, regional staff
    members consider requests for “verifications” of projects
    thereunder. For a project to qualify for verification under a
    general permit, a Corps District Engineer must conclude that
    it complies with the general permit’s conditions, will cause no
    more than minimal adverse effects on the environment, and
    will serve the public interest. 33 C.F.R. §§ 330.1(e)(2),
    330.6(a)(3)(i).     Because the Corps cannot accurately
    anticipate the effects of thousands of future activities at the
    time it promulgates a general permit, the general permit’s
    basic terms may later be supplemented by a Corps District
    Engineer’s decision to attach additional, project-specific
    conditions at the verification stage. 33 C.F.R. §§ 330.1(e)(2),
    330.6(a)(3)(i); see also Ohio Valley Envtl. Coal. v. Bulen, 
    429 F.3d 493
    , 501 (4th Cir. 2005). If a District Engineer deems a
    project inappropriate for verification under a general permit,
    the engineer may require that the project instead proceed
    under an individual permit. 33 C.F.R. § 330.6(a)(2), (d).
    In this case, four regional Corps offices each issued
    verifications of the Flanagan South project for their respective
    regions under Nationwide Permit 12. The 1,950 crossings the
    Corps verified here collectively comprise about 13.7 miles, or
    roughly 2.3 percent, of the Flanagan South pipeline’s 593-
    mile route. The Corps did not require any separate permits. It
    did, however, impose conditions on the verifications to ensure
    compliance with the Endangered Species Act, as
    contemplated by the Clean Water Act’s minimal-adverse-
    impacts requirement.
    15
    The Corps performed a NEPA analysis when it
    promulgated Nationwide Permit 12, and Sierra Club does not
    here challenge the adequacy of the Corps’s analysis at that
    stage. See 77 Fed. Reg. at 10,187. The Corps did not conduct
    any further NEPA analysis of its verifications of Flanagan
    South under the nationwide permit. The Corps’s practice is to
    perform NEPA analysis for general permits in advance of
    their promulgation, and not to conduct additional NEPA
    analysis when it verifies specific activities under the general
    permits. See, e.g., 
    Bostick, 787 F.3d at 1054
    ;3 Snoqualmie
    Valley Pres. All. v. U.S. Army Corps of Eng’rs, 
    683 F.3d 1155
    , 1158 (9th Cir. 2012). The Corps represented to this
    court that it is very common for domestic oil pipelines to be
    constructed without any whole-pipeline NEPA analysis, and
    estimates that 180 oil pipelines have been constructed
    primarily over private lands without analysis of the
    environmental effects of the pipeline as a whole.
    3. Endangered Species Act
    Consultation and Authorization
    The third type of federal action at issue is the conditional,
    limited authorization of the Flanagan South pipeline under the
    Endangered Species Act. Following interagency consultation
    required by Section 7 of the ESA in connection with federal
    agency actions, the Service issued and the Corps implemented
    3
    For thoughtful analysis of the scope of the Corps’s obligations
    under NEPA, see 
    Bostick, 787 F.3d at 1062
    (McHugh, J.,
    concurring). To the extent that the Corps, both in Bostick, see 
    id. at 1062-63,
    and in this case, see Oral Arg. Rec. (Apr. 9, 2015) 30:20-
    31:37, understood its NEPA obligations as confined to considering
    environmental effects on CWA jurisdictional waters, its view
    misapprehends the obligations of any agency taking action subject
    to NEPA to do a comprehensive analysis of all types of foreseeable
    environmental effects. See 40 C.F.R. §§ 1508.8, 1508.27.
    16
    an Incidental Take Statement to minimize the project’s impact
    on two endangered species, the Indiana Bat and the American
    Burying Beetle, and to authorize incidental take of those
    species.
    When Congress enacted the ESA, it “intended
    endangered species to be afforded the highest of priorities.”
    Tenn. Valley Auth. v. Hill, 
    437 U.S. 153
    , 174 (1978); see
    generally 16 U.S.C. § 1531. The ESA generally prohibits the
    “take” of any members of endangered animal species,
    defining “take” as “to harass, harm, pursue, hunt, shoot,
    wound, kill, trap, capture, or collect, or to attempt to engage
    in any such conduct.” 16 U.S.C. §§ 1532(19), 1538(a)(1)(B).
    Notwithstanding that prohibition, private parties such as
    Enbridge may obtain authorization for incidental take of
    species where the take is not the project’s objective and is
    sufficiently limited that it does not jeopardize the survival of
    the species. See 
    id. §§ 1536(a)(2),
    1539(a)(2)(B). A party
    may obtain such limited permission for the incidental take of
    species in either of two ways.
    First, a party may apply to the Service for a permit under
    Section 10 of the ESA, and the Service may issue a permit
    directly to that party to take members of listed species “if
    such taking is incidental to, and not the purpose of, the
    carrying out of an otherwise lawful activity.”             
    Id. § 1539(a)(1)(B);
    see, e.g., Gerber v. Norton, 
    294 F.3d 173
    , 175
    (D.C. Cir. 2002) (Service issuing Section 10 permit to a
    developer to take endangered fox squirrels incidental to
    constructing a residential housing project). A Section 10
    permit application must include a conservation plan that
    specifies the likely impact of the anticipated take as well as
    steps for minimizing and mitigating such impact (with
    identified funding sufficient to implement those steps), and
    that identifies which potentially less harmful alternatives were
    17
    considered and why they are not being used. 16 U.S.C.
    § 1539(a)(2)(A). Enbridge considered and decided against
    seeking a Section 10 permit, as detailed below.
    Second, and less directly, a private party may take listed
    species by complying with an ITS issued by the Service
    pursuant to ESA Section 7. Section 7 requires other federal
    agencies to consult with the Service whenever they have
    reason to believe that listed species or critical habitats may be
    affected by their planned actions, including authorizations of
    private parties’ actions. 
    Id. § 1536(a).
    Accordingly, in this
    case the Corps and the Bureau, as “action agencies,”
    consulted with the Service in light of the Clean Water Act
    verifications that the Corps was issuing and the easements
    that both agencies were granting to Enbridge. See id.; see
    generally U.S. Fish & Wildlife Serv. & Nat’l Marine
    Fisheries Serv., Endangered Species Consultation Handbook
    (March 1998) (hereinafter “Section 7 Handbook”),
    http://www.fws.gov/endangered/esa-library/pdf/
    esa_section7_handbook.pdf. The Service allows private
    parties to participate in a Section 7 consultation when the
    contemplated action involves the action agency’s approval of
    private-party conduct, see 16 U.S.C. § 1536(b); 50 C.F.R. §
    402.14, and Enbridge actively participated in the ESA Section
    7 consultation relating to Flanagan South.
    In a Section 7 consultation, the Service prepares a
    Biological Opinion identifying the project and any likely
    impact on listed species or their habitat. 16 U.S.C. § 1536(a)-
    (c); 50 C.F.R. §§ 402.02, 402.14(e), (g)-(h). The Service
    cannot approve proposed actions that are likely to jeopardize
    the continued existence of listed species or critical habitats.
    16 U.S.C. §§ 1536(a)(2), (b)(4). If an action will likely result
    in at most a limited take that is incidental to the project, the
    Service provides the consulting agency and private party with
    18
    an ITS as part of the Biological Opinion. Id.; 50 C.F.R.
    § 402.14(i). An ITS identifies reasonable and prudent
    measures—such as mitigation, monitoring, and reporting—
    necessary or appropriate to minimize the impact on species
    likely to be incidentally affected by the project, and terms and
    conditions required to implement those measures. 16 U.S.C.
    § 1536(b)(4); 50 C.F.R. § 402.14(i)(1)(ii), (iv); see, e.g., San
    Luis & Delta-Mendota Water Auth. v. Jewell, 
    747 F.3d 581
    ,
    597-99 (9th Cir. 2014), cert. denied, 
    135 S. Ct. 948
    (2015).
    It is up to an action agency that has consulted with the
    Service under Section 7 to determine whether and how to
    proceed with its proposed action (including permitting private
    activity) in light of an ITS issued by the Service. 50 C.F.R. §
    402.15(a); see 16 U.S.C. § 1536(b)(4). However, the action
    agency and private party (unless it has obtained a Section 10
    permit) must comply with the Service’s ITS if they wish to be
    insulated from ESA liability for taking species incidental to
    the project. 16 U.S.C. § 1536(o)(2); 50 C.F.R. § 402.14(i)(5);
    see, e.g., Bennett v. Spear, 
    520 U.S. 154
    , 169-70 (1997).
    In this case, the Service consulted with the Corps and the
    Bureau, and Enbridge participated.           The agencies and
    Enbridge negotiated for more than a year over several
    questions, including whether Enbridge would seek a Section
    10 permit or a Section 7 ITS; whether the Biological Opinion
    and its ITS would cover only the verification and easement
    areas or the whole Flanagan South project; and the geographic
    extent to which the Corps was responsible for incorporating
    the ITS in its verifications and enforcing it outside those
    jurisdictional areas. The Service ultimately prepared a
    Biological Opinion that examined the entire length of the
    pipeline. See 50 C.F.R. § 402.02 (“Action area means all
    areas to be affected directly or indirectly by the Federal action
    and not merely the immediate area involved in the action.”).
    19
    Neither the Service nor the Corps or Bureau prepared any
    NEPA analysis of the issuance or implementation of the ITS.
    The Service determined that, if Enbridge took certain
    mitigation measures and performed onsite monitoring for five
    decades, the project would result in a tolerable degree of
    incidental take of the two identified endangered species and
    their critical habitat. The Service so specified in the ITS it
    issued pursuant to Section 7. If the ITS were made a binding
    condition of a contract, permit, lease or easement, and
    Enbridge complied with those terms and conditions, the ITS
    specified that it would provide Enbridge a safe harbor from
    ESA liability for incidentally taking those species within the
    geographic scope of any area in which Enbridge was bound
    to, and did, comply.
    C. Procedural History
    Sierra Club filed suit against the Corps in August 2013,
    on the day Enbridge began construction of Flanagan South.
    The organization amended its complaint soon thereafter to
    add new claims and name new federal-agency defendants.
    The amended complaint asserted that NEPA analysis was
    required in light of requested easements over federal lands,
    Clean Water Act verifications, and the issuance of the ITS.
    Sierra Club claimed that those actions, “individually and
    collectively, constituted major federal action that triggered
    defendants’ NEPA obligations” to prepare NEPA analysis of
    “the entire Project.” Compl. ¶ 5. Sierra Club contended that
    a “massive pipeline has been authorized . . . without any
    NEPA review of the extensive environmental impacts of the
    entire pipeline.” 
    Id. ¶ 7.4
    Sierra Club also asserted a Clean
    4
    Sierra Club also alleged that the agencies failed to designate a
    “lead agency,” preferably the Corps, to oversee the NEPA analysis.
    Compl. ¶¶ 40, 187; see 40 C.F.R. § 1501.5(c).
    20
    Water Act claim against the Corps, alleging that the
    verifications the Corps issued under Nationwide Permit 12
    were unlawful because, as relevant here, the agency failed to
    evaluate the pipeline’s cumulative impacts. 
    Id. ¶ 192.
    Sierra
    Club asserted its NEPA and Clean Water Act claims in
    conjunction with the Administrative Procedure Act, seeking a
    declaration that the alleged federal actions were all unlawful
    and an order “enjoining Enbridge from conducting any
    activities in reliance on” them.
    Sierra Club moved for a preliminary injunction, Enbridge
    intervened as a defendant, and the district court denied
    preliminary relief. Later, on cross-motions for summary
    judgment, the district court ruled in favor of the defendants,
    observing that the agencies had “permitting authority over
    only small segments of this private pipeline project and none
    of the defendant agencies, alone or in combination, ha[d]
    authority to oversee or control the vast portions of the []
    Pipeline that traverse private land.” Sierra Club v. Army
    Corps of Eng’rs, 
    64 F. Supp. 3d 128
    , 133-34 (D.D.C. 2014).
    The court also ruled against Sierra Club on its Clean Water
    Act claim, holding that the Corps lawfully conducted region-
    based analyses of the adverse cumulative effects of the water
    crossings it verified under Nationwide Permit 12. 
    Id. at 155-
    57. On the same day that it entered summary judgment, the
    district court entered a separate order denying Sierra Club’s
    two pending motions to supplement and amend its first
    amended complaint. Sierra Club timely appealed.
    II. Mootness
    At the threshold, we must confirm our subject matter
    jurisdiction. North Carolina v. Rice, 
    404 U.S. 244
    , 246
    (1971). Enbridge contends that, as a prudential matter, we
    should dismiss this appeal as moot because the agencies have
    21
    already granted the various authorizations at issue and
    construction of the pipeline is now complete. In Enbridge’s
    view, the court cannot now remedy any injuries that might
    stem from the claimed NEPA violations because NEPA’s goal
    of requiring the federal government to study and publicly
    explain anticipated environmental effects before taking action
    would not be furthered by post-construction NEPA review.
    At this point, Enbridge argues, there is “no real opportunity
    for any of the Defendants to reconsider their decisions,” and
    “any further public comment could have no impact on the
    Defendants’ decision-making, since the agencies could not
    effectively act on the input provided.” Enbridge Br. 13, 16.
    Enbridge likewise argues that Sierra Club’s Clean Water Act
    claim is moot because “the minimal impacts to jurisdictional
    waters under [Nationwide Permit 12] at stake in this litigation
    have already occurred” and “[t]here are no ongoing
    unmitigated impacts.” 
    Id. at 16-17.
    This case is not moot because an order wholly or partly
    enjoining operation of the pipeline, pending further analyses
    of the pipeline’s environmental impact, would provide some
    degree of “effectual relief.” See Church of Scientology of
    Cal. v. United States, 
    506 U.S. 9
    , 12-13 (1992). “Even
    though it is now too late to prevent or to provide a fully
    satisfactory remedy for” the harms Sierra Club identifies, the
    court has the “power to effectuate a partial remedy,” and that
    “is sufficient to prevent this case from being moot.” 
    Id. at 13.
    “[T]his case presents a live controversy” because, were this
    court to hold that the agencies’ NEPA analysis was
    inadequate or their decisions otherwise arbitrary and
    capricious, they “would have to correct the decision-making
    process.”      Columbia Basin Land Protection Ass’n v.
    Schlesinger, 
    643 F.2d 585
    , 591 n.1 (9th Cir. 1981). If the
    NEPA analysis were legally inadequate, “we could order that
    the [pipeline] be closed or impose restrictions on its use,” at
    22
    least on federally authorized segments, “until [the agencies]
    complied with NEPA.” Airport Neighbors All., Inc. v. United
    States, 
    90 F.3d 426
    , 429 (10th Cir. 1996).
    More extensive environmental analysis could lead the
    agencies to different conclusions, with live remedial
    implications.    If a broader NEPA analysis uncovered
    additional environmental harms, the removal of the
    challenged project, at least from certain areas, “could be
    required.” 
    Schlesinger, 643 F.2d at 591
    n.1. Even assuming
    claims “relating to the construction of” the pipeline were
    moot, “we still may consider whether [the agencies] complied
    with NEPA by adequately addressing the environmental
    impacts resulting from the enhanced use of” it. Airport
    Neighbors 
    All., 90 F.3d at 429
    . The agencies could call for
    additional mitigation and monitoring, or could decide not to
    renew their respective authorizations. See, e.g., 33 C.F.R.
    § 330.5(d). There is no basis for Enbridge’s contentions that
    none of the types of environmental effects that agencies must
    investigate under NEPA could be avoided, undone, or more
    robustly mitigated and monitored.
    This case is thus distinguishable from those in which the
    court could not provide any of the relief sought. In Sierra
    Club v. U.S. Army Corps of Engineers, for example,
    environmental challenges to the Corps filling wetlands to
    construct a sports complex were moot once the construction
    was fully completed because it was undisputed that the
    wetlands could not be restored, and the wetlands were the
    only resource in which the plaintiffs claimed an interest. 277
    F. App’x 170, 173 (3rd Cir. 2008). The completion of the
    project and the limited nature of the plaintiffs’ asserted
    interest in that case eliminated “the opportunity for any
    meaningful relief to Plaintiffs’ alleged injuries.”         
    Id. (emphasis added).
                                  23
    This case presents a live controversy, and we reject
    Enbridge’s suggestion that we dismiss the appeal for
    prudential reasons.       That conclusion comports with
    Congress’s objective in the various federal laws at issue here
    that require environmental review and authorization in
    advance. “If the fact that [projects] are built and operating
    were enough to make [a] case nonjusticiable,” agencies and
    private parties “could merely ignore the requirements of
    NEPA” as well as other statutes requiring pre-construction
    authorization or review, “build [their] structures before a case
    gets to court, and then hide behind the mootness doctrine.”
    
    Schlesinger, 643 F.2d at 591
    n.1. But “[s]uch a result is not
    acceptable.” Id.; see also West v. Sec’y of Dep’t of Transp.,
    
    206 F.3d 920
    , 925 (9th Cir. 2000). We thus proceed to the
    merits of Sierra Club’s challenge.
    III. NEPA
    Sierra Club contends that the agencies should have
    conducted NEPA review of the pipeline as a whole. The only
    alleged federal action that, by its terms, addressed the entire
    pipeline was the Service’s ITS in its Biological Opinion.
    Sierra Club argues that either the Service’s issuance of the
    ITS during Section 7 consultation with the Corps and Bureau,
    or the Corps’s implementation of the ITS as a condition of the
    Clean Water Act verifications it issued to Enbridge,
    constituted federal action encompassing all of Flanagan
    South, thereby mandating whole-pipeline NEPA review. The
    Bureau also consulted with the Service in light of the
    easements it was granting to Enbridge, but Sierra Club does
    not invoke the Bureau or its easements in arguing that the ITS
    triggered NEPA—perhaps because the easements, unlike the
    Corps’s verifications, contained no explicit terms
    implementing the ITS.
    24
    We conclude, on the facts of this case, that the Service’s
    issuance of the ITS was not, standing alone, federal action
    triggering NEPA review.         By contrast, the Corps’s
    implementation of the ITS as a condition of its Clean Water
    Act verifications was federal action, but with geographic
    scope far more limited than the NEPA review Sierra Club
    seeks. In advocating for review of the entire pipeline, Sierra
    Club unsuccessfully invokes the doctrine against
    impermissible segmentation of NEPA review in an effort to
    trigger NEPA’s connected- and cumulative-actions doctrines
    and the Corps’s agency-specific NEPA regulations. Sierra
    Club did not preserve a claim for NEPA analysis limited to
    the verification and easement areas, so we have no occasion
    to consider it. We must therefore reject Sierra Club’s NEPA
    arguments on appeal.
    A. Implementation of the ITS as Federal Action
    An ITS, as explained above, is a set of terms and
    conditions that the Service provides under Section 7 of the
    ESA to other federal agencies planning actions likely to affect
    listed species. In this case, Section 7 required the Corps and
    the Bureau—action agencies—to consult with the Service and
    the Service to render a Biological Opinion regarding the
    Corps’s anticipated Clean Water Act verifications and the
    Corps and the Bureau’s grants of easements. See 16 U.S.C.
    § 1536; 50 C.F.R. § 402.14. The Biological Opinion
    examined the entire Flanagan South project and set forth in
    the ITS measures to mitigate, monitor, and report take of
    endangered species incident to the project. The Corps
    implemented the ITS in its Clean Water Act verifications,
    although only to a limited geographic extent. Compliance
    with the ITS, insofar as action agencies made it binding and
    enforceable, provided Enbridge with a safe harbor from ESA
    liability.
    25
    The Service’s development and issuance of the Section 7
    ITS, standing alone, was not federal action. But, as explained
    below, the Corps’s implementation of the ITS was federal
    action, albeit of confined scope. An agency’s advice to
    another agency on how that agency should proceed with its
    permitting actions does not amount to federal action under
    NEPA. The Service could, in a different context, be held to
    be an “action agency” for NEPA purposes. See San 
    Luis, 747 F.3d at 644
    (explaining that, in Ramsey v. Kantor, 
    96 F.3d 434
    (9th Cir. 1996), the National Marine Fisheries Service, a
    consulting agency, also was an action agency when its
    conduct was, in substance, identical to the process for issuing
    a permit). But the record in this case makes clear that the Fish
    and Wildlife Service acted only in its consultative role,
    “merely offering its opinions and suggestions to [the Corps],
    which, as the action agency, ultimately decides whether to
    adopt or approve the [ITS].” 
    Id. at 642.
    In that respect, the
    Service and the Corps’s relationship here is analogous to that
    between the Service and the U.S. Bureau of Reclamation in
    San Luis, in which the Service had issued an ITS to
    Reclamation regarding the effect of a major water works
    project on the endangered Delta Smelt. See 
    id. at 592.
    The
    Service’s role in San Luis was to consult, and Reclamation
    was the action agency implementing the ITS. Here, similarly,
    it was the Corps’s action, by way of adopting and
    incorporating the ITS in the verifications of Flanagan South’s
    water crossings under the Clean Water Act, that qualified as
    federal action under NEPA. See 40 C.F.R. § 1508.18(b).
    The Service was not obligated in San Luis or in this case
    to complete a NEPA analysis, because an agency need not
    complete such analysis “where another agency will authorize
    or implement the action that triggers 
    NEPA.” 747 F.3d at 644
    ; accord Miccosukee Tribe of Indians of Fla. v. United
    States, 
    430 F. Supp. 2d 1328
    , 1335 (S.D. Fla. 2006). This
    26
    case is thus unlike Ramsey, in which the National Marine
    Fisheries Service issued a Biological Opinion and ITS and
    was, under the particular circumstances of that case, also the
    agency that authorized the species-taking action, thus making
    the Service’s Section 7 ITS, standing alone, “functionally
    equivalent to a 
    permit.” 96 F.3d at 444
    ; see also San 
    Luis, 747 F.3d at 643-45
    (distinguishing Ramsey on that basis).
    The defendants are only partly correct that the ITS in this
    case was not the functional equivalent of a permit. Agency
    Br. 44; Enbridge Br. 37, 39; see also Sierra Club, 
    64 F. Supp. 3d
    at 149-50 (drawing that conclusion). The Service’s
    issuance of the ITS was not the functional equivalent of a
    permit, but the Corps’s incorporation of the ITS was. When
    the Service issues an ITS in its consultative role, Enbridge
    correctly notes, it “do[es] not allow or authorize (formally
    permit) incidental take under section 7.” Enbridge Br. 38
    (quoting Section 7 
    Handbook, supra, at x
    ). When the Service
    issues a Section 10 permit directly to a private party, it
    functions as an action agency. Before it began construction,
    Enbridge considered applying to the Service for a private
    Section 10 permit. Once the Service estimated that the
    Section 10 process could “take years to complete,” Enbridge
    decided against the Section 10 route. Enbridge instead opted
    only to participate in the speedier Section 7 process and
    settled for a much more limited authorization of anticipated
    take. It was only when the Corps formally incorporated the
    ITS into its Clean Water Act verifications that it gave
    Enbridge permission to take species free from the threat of
    ESA liability. The Corps-implemented ITS is the functional
    equivalent of a permit and thus constitutes federal action
    subject to NEPA. See 40 C.F.R. § 1508.18(b)(4). But
    because its permission is limited to the areas subject to the
    verifications, it is federal action of much more limited scope
    27
    than Sierra Club contends; contrary to Sierra Club’s claim, it
    does not require NEPA review of the whole pipeline.
    The district court concluded that the Corps’s
    incorporation of the ITS in its verifications did not trigger
    NEPA because, the court reasoned, a verification is “not a
    major federal action in and of itself” and thus cannot be
    “transformed” into cognizable action on account of
    incorporating an ITS. Sierra Club, 
    64 F. Supp. 3d
    at 149.
    The court’s conclusion was based in part on the assumption
    that the Corps had already made a “fully-informed decision to
    authorize certain activities . . . ex ante under the nationwide
    permitting system.” 
    Id. at 147.
               That assumption is
    unfounded in this context, however: Nationwide Permit 12
    and Corps regulations make clear that the Corps did not assess
    effects on specific listed species when it authorized categories
    of actions through promulgation of the general permit; rather,
    it deferred any consideration of species impacts and
    authorization of species take until the verification stage, in the
    context of specific projects. See 33 C.F.R. § 330.4(f); 77 Fed.
    Reg. at 10,187; App. 327 (Decision Document for Nationwide
    Permit 12).
    The defendants contend that the ITS, even as
    implemented by the Corps, did not constitute action triggering
    NEPA because its requirements are “modest” and “limited to
    monitoring.” Agency Br. 46. They note that, under the
    regulations, “reasonable and prudent measures” that an ITS
    requires “cannot significantly modify the proposed action.”
    Id.; see 50 C.F.R. § 402.14(i)(2). The defendants thereby
    seek to distinguish this case from those in which NEPA
    analysis is triggered by ITS conditions that “substantially
    modify” the action, Agency Br. 48, or “substantially alter the
    status quo,” Enbridge Br. 43.
    28
    The defendants fail their own test. The “status quo” is
    not, as their argument assumes, a fully approved and
    constructed Flanagan South pipeline; rather, the baseline
    against which the significance of the federal action must be
    measured is no pipeline approved and no species killed or
    habitat disturbed. Authorizing take of endangered species in
    connection with pipeline construction and operation across
    jurisdictional waters, and doing so only on the conditions that
    Enbridge take mitigating conservation measures and monitor
    species impact for the anticipated useful life of the pipeline,
    was regulatory approval amounting to significant federal
    action requiring environmental review under NEPA. See 40
    C.F.R. § 1508.18(b)(4); see also San 
    Luis, 747 F.3d at 642
    -
    45; cf. Tenn. 
    Valley, 437 U.S. at 172-73
    (reflecting that,
    although “[i]t may seem curious to some that the survival of a
    relatively small number of three-inch fish . . . would require
    the permanent halting of a virtually completed dam for which
    Congress has expended more than $100 million,” the plain
    language of the ESA “require[d] precisely that result”).
    B. Limited Scope of the ITS
    The Corps’s implementation of the ITS through its Clean
    Water Act verifications was federal action that required
    NEPA review, but the NEPA obligations arising out of that
    action extended only to the segments under the Corps’s
    asserted Clean Water Act jurisdiction. The verifications
    purported to enforce the ITS against Enbridge only with
    respect to the water-crossing segments that the Corps verified
    under Nationwide Permit 12; they did not purport to permit
    any take of species (or authorize any other action, for that
    matter) outside those segments along the rest of the pipeline.
    Indeed, the Corps explicitly disclaimed that it would enforce
    compliance with the ITS with respect to the pipeline as a
    whole.
    29
    The record contextualizes and confirms the geographic
    limitation of the verifications’ implementation of the ITS.
    The Corps, the Service, and Enbridge debated jurisdictional
    issues in the course of their Section 7 consultation. The
    Service and Enbridge sought a pipeline-wide ITS, while the
    Corps emphatically disclaimed responsibility outside the
    verification areas. Enbridge requested that the Corps consult
    with the Service under Section 7 “on the entire pipeline route
    instead of the areas tied to Corps jurisdiction/regulatory
    control,” perhaps because it envisioned that would be
    tantamount to a shortcut Section 10 process. App. 402-403;
    see also App. 382. The Corps suggested that the Service
    issue a Section 10 permit covering non-Corps areas, but the
    Service responded that it could not do so because Enbridge
    had chosen not to apply for a Section 10 permit. App. 403.
    The Corps continued to maintain that it had authority over “a
    very small percentage” of the pipeline and that it would “only
    initiate Section 7 ESA consultation, as appropriate, for the
    limited activities associated with this project that it has
    sufficient control and responsibility to evaluate,” noting the
    Service might “provide authorization for any take . . . outside
    of the Corps permit area under Section 10.” 
    Id. The fact
    that the Service’s Biological Opinion assessed
    the entire Flanagan South project does not undermine our
    holding concerning the limited scope of NEPA-triggering
    implementation of the ITS via the verifications. The ITS
    provided that “the Corps . . . must insure that the [ITS’s
    measures] become binding conditions of any contract or
    permit issued [to Enbridge] to carry out the proposed action
    for the exemption in section 7(o)(2) to apply.” App. 296. It
    further provided that the ITS’s safe harbor could lapse if the
    Corps failed to “implement the terms and conditions” or
    “require any contracted group to adhere to the terms and
    30
    conditions of the [ITS] through enforceable terms that are
    added to the permit.” 
    Id. The four
    regional Corps offices, in turn, issued
    verifications defining the limited scope of the ITS’s “binding
    conditions,” see 
    id., by “authoriz[ing]
    [Enbridge’s] work . . .
    conditional upon [Enbridge’s] compliance with the mandatory
    terms and conditions associated with the incidental take that
    may occur within the Corps delineated permit areas,” App.
    176 (emphasis added); see App. 385, 421 (other verifications
    with same language); see also App. 225-26 (biological
    opinion delimiting the Corps’s jurisdictional areas as the
    verified water crossings and the two easements). The
    verifications reiterate that “[f]ailure to comply with the terms
    and conditions [of the ITS] within the Corps permit areas
    (i.e., separate and distant [sic: distinct] waterbody crossings,
    where work is verified by the Corps under Nationwide Permit
    Number 12), where take of the listed species occurs or
    adverse effects to designated critical habitat occurs, would
    constitute an unauthorized take, and it would also constitute
    non-compliance with your Corps permit.”               App. 176
    (emphasis added).        The verifications explicitly advised
    Enbridge that the ITS does not constitute authorization for
    Enbridge to take endangered species beyond the verified
    crossings. In particular, “in order to legally take a listed
    species,” the Corps emphasized that Enbridge “must have
    separate authorization under the Endangered Species Act (e.g.
    an ESA Section 10 permit, or a Biological Opinion [] under
    ESA 7, with ‘incidental take’ provisions with which
    [Enbridge] must comply).” 
    Id. Sierra Club’s
    claim for whole-pipeline NEPA analysis
    based solely on the ITS therefore fails because, per the terms
    of the ITS and the verifications themselves, the Corps had not
    bound Enbridge to comply with the ITS beyond those
    31
    segments of the pipeline subject to the Corps’s Clean Water
    Act jurisdiction. Moreover, Enbridge did not obtain a Section
    10 permit to take listed species on the balance of the pipeline
    outside the scope of the ITS-implementing verifications.
    Given that NEPA-triggering federal action occurred with
    regard to the segments of the pipeline subject to the
    verifications by virtue of the ITS being incorporated with
    respect to those sections, we need not separately consider
    whether the Corps’s verification of the pipeline’s water
    crossings under Nationwide Permit 12, standing alone, would
    have required NEPA analysis.           Even assuming the
    verifications, by themselves, did warrant NEPA analysis, the
    verifications do no more than the ITS to extend the
    geographic scope of the federal action; it remains limited to
    the verified segments.
    C. Failure to Preserve NEPA Claims for Less Than
    Whole-Pipeline Review
    Sierra Club has failed to preserve its claim that the
    several easement actions, verifications and ITS, taken
    together, amount to a single federal action that requires its
    own NEPA analysis. We assume arguendo that the Corps’s
    and Bureau’s discrete easement actions and verifications
    incorporating the ITS were all component parts of the same
    federal action, but Sierra Club has failed to preserve an
    argument that the government was required to perform a
    unified NEPA analysis on anything less than the entire
    Flanagan South pipeline. As discussed below, Sierra Club
    has consistently argued only that some agency should have
    conducted a pipeline-wide NEPA assessment. In the district
    court, Sierra Club’s contention that the easements,
    verifications, and ITS should have been considered together
    under NEPA was an intermediate step in its argument that
    32
    there should have been one, coordinated NEPA review that
    encompassed the balance of the pipeline—including sections
    not otherwise subject to federal review or authorization.
    The district court record makes clear that whole-pipeline
    review was the only theory of NEPA deficiency that Sierra
    Club pursued. Sierra Club’s claim that the agencies were
    required to assess the entire Flanagan South project underlay
    all the NEPA claims in its complaint. See, e.g., Compl. ¶ 5
    (objecting that the alleged actions “triggered Defendants’
    NEPA obligations,” but “none of the Defendant agencies
    prepared either an [EA] or an [EIS] for the entire Project
    pursuant to NEPA”), ¶ 7 (“In short, . . . this massive pipeline
    has been authorized . . . without any NEPA review of the
    extensive environmental impacts of the entire pipeline . . . .”).
    In seeking preliminary relief, Sierra Club argued that the crux
    of its NEPA claims was that the federal government was
    obligated to scope a NEPA analysis to the entire pipeline.5
    The district court remarked in its preliminary injunction ruling
    that the gravamen of Sierra Club’s NEPA claims was that the
    agencies had a collective obligation to perform environmental
    5
    In its briefing in support of its motion for a preliminary injunction,
    Sierra Club contended that the “Flanagan South Pipeline is a major
    federal action” and framed the agencies’ alleged NEPA violations
    as stemming from a failure to assess the impacts of Flanagan South
    as a whole. Mot. for Prelim. Inj., No. 1:13-cv-1239 KBJ (Sept. 4,
    2013), ECF No. 14, at 13. Sierra Club repeatedly objected that no
    agency had prepared NEPA analysis scoped to the “entire” project.
    E.g., 
    id. at 5,
    8, 19-21, 28, 38; Pls. Reply (Sept. 23, 2013), ECF No.
    34, at 1-2, 7-10, 19-21. At the preliminary injunction hearing, too,
    Sierra Club underscored its position that “[t]he question is whether
    any federal agency has to look at the entire oil pipeline in its
    [NEPA analysis].” Tr. of Prelim. Inj. Hr’g (Sept. 27, 2013), ECF
    No. 91, at 11; see also 
    id. at 12
    (“The law. . . requires an agency to
    consider the entire [pipeline] . . . .”).
    33
    review of the entire pipeline. Sierra Club v. U.S. Army Corps
    of Engineers, 
    990 F. Supp. 2d 9
    , 13 (D.D.C. 2013). Later,
    aware of the court’s framing of its case, Sierra Club continued
    at the summary judgment phase to press the same theory
    exclusively.6
    We will not reverse the judgment of the district court
    based on the argument, not advanced below, that an agency
    unlawfully failed to perform NEPA analysis on sections of
    Flanagan South short of the entire length of the pipeline. See,
    e.g., Potter v. District of Columbia, 
    558 F.3d 542
    , 547 (D.C.
    Cir. 2009) (limiting our review to “only those arguments that
    were made in the district court, absent exceptional
    circumstances”). That claim is forfeited. Therefore, the only
    NEPA question preserved for our consideration is whether the
    federal actions of verifying the Pipeline’s water crossings
    under Nationwide Permit 12, incorporating the ITS, and
    granting the easements to cross federal lands required NEPA
    analysis of the entire Flanagan South pipeline.
    D. Inapplicability of the Connected Actions, Cumulative
    Actions, and Corps-Specific NEPA Regulations
    In contending that the federal actions within the
    verification and easement areas required the government also
    to assess the rest of the pipeline under NEPA, Sierra Club
    invokes the doctrines of “connected actions” and “cumulative
    actions” delineated in the CEQ regulations. See 40 C.F.R.
    §§ 1508.25(a)(1)-(2), 1508.7.7 It also invokes Corps-specific
    6
    See, e.g., Pls. Mot. for Summ. J., No. 1:13-cv-1239 KBJ (Dec 9,
    2013), ECF No. 61, at 2, 13, 15-16, 45; Pls. Reply (Jan. 27, 2014),
    ECF No. 75, at 1, 3, 7.
    7
    Those regulations dictate the appropriate scope of EAs as well as
    EISs. See Del. Riverkeeper Network v. FERC, 
    753 F.3d 1304
    , 1314
    34
    NEPA scoping regulations. See 33 C.F.R. § 325 App. B.
    None of those bases supports Sierra Club’s claim.
    1.     Connected Actions.       The connected actions
    regulation, on which Sierra Club relies most heavily, does not
    dictate that NEPA review encompass private activity outside
    the scope of the sum of the geographically limited federal
    actions. The regulation provides, as relevant here, that
    “actions” must be analyzed together in the same assessment if
    they “[a]utomatically trigger other actions which may require
    environmental impact statements,” “[c]annot or will not
    proceed unless other actions are taken previously or
    simultaneously,” or if they are “interdependent parts of a
    larger action and depend on the larger action for their
    justification.” 40 C.F.R. § 1508.25(a)(1). The point of the
    connected actions doctrine is to prevent the government from
    “segment[ing]” its own “federal actions into separate projects
    and thereby fail[ing] to address the true scope and impact of
    the activities that should be under consideration.” Del.
    
    Riverkeeper, 753 F.3d at 1313
    .
    Delaware Riverkeeper illustrates the connected actions
    regulation’s anti-segmentation principle, and why it does not
    accomplish all that Sierra Club asks of it. Under Delaware
    Riverkeeper, an agency cannot segment NEPA review of
    projects that are “connected, contemporaneous, closely
    related, and interdependent,” when the entire project at issue
    is subject to federal review. 
    Id. at 1308.
    In this case, the oil
    pipeline is undoubtedly a single “physically, functionally, and
    financially connected” project, but one in which less than five
    per cent is subject to federal review. See 
    id. The Natural
    Gas
    Act requirement that natural gas pipelines be pre-certified for
    (D.C. Cir. 2014); Grand Canyon 
    Trust, 290 F.3d at 346
    ; Kern v.
    U.S. Bureau of Land Mgmt., 
    284 F.3d 1062
    , 1076 (9th Cir. 2002).
    35
    public convenience and necessity made the whole pipeline in
    Delaware Riverkeeper the subject of major federal action
    triggering NEPA. We held that FERC unlawfully segmented
    the requisite NEPA analysis by reviewing in separate portions
    a pipeline that “function[ed] together seamlessly.” 
    Id. at 1307,
    1311. Here, the project is an oil pipeline, however, so
    not subject to any such overall pipeline precertification.8
    Sierra Club argues, in effect, that applying the connected
    actions regulation to the sum of other approvals Flanagan
    South did require draws into NEPA review the balance of the
    pipeline project that is not otherwise subject to agency action,
    thus subjecting it to the connected actions doctrine to the
    same extent as was the case in Delaware Riverkeeper. Sierra
    Club adds a step that the regulation does not support: The
    connected actions regulation requires agencies to review the
    picture as a whole rather than conduct separate NEPA reviews
    on pieces of an agency-action jigsaw puzzle; it does not add a
    multitude of private pieces to the puzzle and so require review
    of a much larger picture. That limitation is highlighted by the
    connected actions rule’s lack of reference to private parties—
    a reference present in the cumulative action regulation, which
    directs agencies to consider the cumulative impact of action
    by an “agency (Federal or non-Federal) or person.” Compare
    40 C.F.R. § 1508.25(a)(1), with 
    id. § 1508.7
    (emphasis
    added). Background, private action is expressly encompassed
    in the cumulative action analysis in a way that it is not for
    connected action.
    8
    Pipelines transporting oil within the United States are not subject
    to any general requirement of federal governmental evaluation and
    approval. In that way, oil pipelines are less regulated than natural
    gas pipelines, which must be supported by a certificate of public
    convenience and necessity from the Federal Energy Regulatory
    Commission before they may be built. 15 U.S.C. § 717f(c)(1)(A).
    See Del. 
    Riverkeeper, 753 F.3d at 1307-10
    .
    36
    Sierra Club also invokes Karst Environmental Education
    & Protection, Inc. v. EPA, 
    475 F.3d 1291
    , 1296 (D.C. Cir.
    2007), for the proposition that full-project NEPA review is
    required where federal agencies have substantial involvement
    in a private project such that it would not have been
    undertaken without the federal action. In Karst, we noted our
    dictum in Macht v. Skinner, 
    916 F.2d 13
    , 19 (D.C. Cir. 1990),
    approving of the Fourth Circuit’s approach in Maryland
    Conservation Council v. Gilchrist, 
    808 F.2d 1039
    (4th Cir.
    1986), to the “federalization theory.” See 
    Karst 475 F.3d at 1296-97
    (citing 
    Macht, 916 F.2d at 14
    , 19). We went on in
    Karst, however, to observe that “we have no binding
    precedent adopting the federalization theory,” and we did not
    there apply 
    it. 475 F.3d at 1297
    . Indeed, Macht, too, came
    out the other way, undercutting Sierra Club’s argument. The
    rail project in Macht was not subject to whole-project NEPA
    analysis because federal agencies had regulatory control over
    “only a negligible portion of the entire 
    project.” 916 F.2d at 19
    . The same is true here.
    Sierra Club offers no persuasive explanation why the
    portions of the pipeline outside the verification and easement
    areas constitute “federal actions” and thus “should be under
    consideration.” Del. 
    Riverkeeper, 753 F.3d at 1313
    . Rather,
    Sierra Club’s more modest claim at oral argument was that
    Delaware Riverkeeper and the connected action regulation
    require that “the federal actions in this case—the easements,
    the other areas within federal jurisdiction—those are
    connected” and so should have been analyzed together. Oral
    Arg. Rec. at 7:33-40.9 That is the accurate statement of the
    9
    See also Oral Arg. Rec. at 7:57-8:11 (similar concession by Sierra
    Club, recognizing the same limited holding in Hammond v. Norton,
    
    370 F. Supp. 2d 226
    (D.D.C. 2005), upon which it also relies).
    37
    connected actions doctrine, but, as noted above, the claim
    resting on it was not preserved.
    2. Cumulative Actions. The cumulative actions
    regulation is no more helpful to Sierra Club. “Cumulative
    actions” are those that must be assessed together because they
    have “cumulatively significant impacts.” 40 C.F.R. §
    1508.25(a)(2). A cumulative impact is that “which results
    from the incremental impact of the action when added to other
    past, present, and reasonably foreseeable future actions
    regardless of what agency (Federal or non-Federal) or person
    undertakes such other actions.” 
    Id. § 1508.7.
    The cumulative
    actions doctrine is not concerned with geographic
    segmentation; if it were, it would be wholly redundant of the
    connected actions doctrine. See Coal. on Sensible Transp.,
    Inc. v. Dole, 
    826 F.2d 60
    , 70-71 (D.C. Cir. 1987). Instead, it
    prevents agencies from ignoring the environmental effects of
    other actions, without regard to whether their author was
    federal, because those effects set the baseline state of affairs
    and thus the context in which the significance of proposed
    federal action must be evaluated. An agency deciding
    whether to approve construction of a replacement airport, for
    example, must consider the prospective impact of the airport’s
    added noise in the context of noise from other sources—
    including private sources not traceable to agency action. See
    Grand Canyon 
    Trust, 290 F.3d at 346
    . Sierra Club’s
    argument is not, however, that the agencies’ NEPA analyses
    ignored the environmental impacts of cumulative actions on
    discrete swaths of the pipeline, but that they failed to analyze
    the entire length of the pipeline. The cumulative actions
    doctrine therefore does not advance Sierra Club’s case.
    3. Corps Regulations. Appendix B of the Corps’s
    agency-specific NEPA scoping regulations provides that
    when a party requires a Clean Water Act permit to conduct a
    38
    specific activity that is part of a larger project, the Corps’s
    NEPA analysis should encompass not only the specific
    activity, but also “those portions of the entire project over
    which the [Corps] has sufficient control and responsibility.”
    33 C.F.R. § 325 App. B(7)(b)(1); see also 
    id. § 325
    App.
    B(7)(b)(2)-(3). Sierra Club asserts that the Corps had the
    requisite control and responsibility over all of Flanagan
    South, citing the Corps’s jurisdiction over the verified water
    crossings and the easement areas. The agencies respond that
    Appendix B is categorically inapplicable to verifications (or
    easements). As they interpret the text, structure, and history
    of the Corps’s Appendix B, it applies only to NEPA analysis
    triggered by issuance of individual Clean Water Act permits,
    as opposed to general permits and verifications thereunder.
    We owe deference to the Corps’s interpretation of its own
    NEPA regulations, see, e.g., 
    Bostick, 787 F.3d at 1054
    ;
    Kentuckians for the Commonwealth v. U.S. Army Corps of
    Eng’rs, 
    746 F.3d 698
    , 708 n.3 (6th Cir. 2014), and conclude
    that the Corps’s interpretation of its own NEPA-implementing
    regulations in that regard is a permissible one, see 
    Bostick, 787 F.3d at 1054
    ; cf. Save Our Sonoran, Inc. v. Flowers, 
    408 F.3d 1113
    , 1121 (9th Cir. 2005) (consulting Appendix B for
    scope review based on an individual permit). As the Tenth
    Circuit has stated, “in adopting Appendix B, the Corps
    indicated that [it] would not apply to nationwide permits (or
    verifications of permit coverage),” as the “appendix was
    apparently designed to guide Corps officials in evaluating
    permit applications for individual projects.” 
    Bostick, 787 F.3d at 1054
    .10
    10
    We hold today only that the agencies were not required to
    perform a pipeline-wide NEPA review; we do not opine on whether
    an agency lawfully could have conducted such a review, had it so
    chosen.
    39
    IV. Clean Water Act
    As detailed above, the Flanagan South pipeline makes
    approximately 1,950 discrete crossings of waters subject to
    the Clean Water Act, and those water crossings involved
    dredge and fill activity that required Enbridge to obtain
    authorization from the Corps of its compliance with the Act.
    Enbridge sought and obtained that authorization in the form
    of verifications issued by four regional offices of the Corps
    pursuant to Nationwide Permit 12. Sierra Club argues that the
    Corps regional offices’ assessments of the cumulative effects
    of the water crossings verified under Nationwide Permit 12
    were unlawfully narrow and conclusory. See 33 U.S.C. §
    1344(e)(1); 33 C.F.R. §§ 330.1(e)(2), 330.6(a); 77 Fed. Reg.
    at 10,287. We review Sierra Club’s Clean Water Act claim
    de novo, Sierra Club v. Van Antwerp, 
    661 F.3d 1147
    , 1150
    (D.C. Cir. 2011), and hold that it lacks merit.
    Sierra Club first faults the Corps for assessing cumulative
    effects on a regional basis, as opposed to a pipeline-wide
    basis. It relies on Nationwide Permit 12’s instruction that the
    district engineer’s decision shall “include an evaluation of the
    individual crossings . . . as well as the cumulative effects
    caused by all of the crossings authorized by the [Nationwide
    Permit].” 77 Fed. Reg. at 10,287 (emphasis added). That,
    Sierra Club asserts, means regional Corps staff must assess
    the water crossings across the entire pipeline. Sierra Club
    ignores, however, Nationwide Permit 12’s explication that
    “cumulative effects are evaluated on a regional basis” and that
    “[c]umulative effects analysis may be done on a watershed
    basis, or by using a different type of geographic area, such as
    an ecoregion.” 
    Id. at 10,264.
    Sierra Club also faults the Corps for what Sierra Club
    sees as inadequately explained conclusions. It asserts that the
    40
    District Managers merely parroted the language of the statute
    and the general permit at the end of each verification
    memorandum: “The proposed activity would result in only
    minor individual and cumulative adverse environmental
    effects and would not be contrary to the public interest.” E.g.,
    App. 449. Such bare incantations, Sierra Club contends,
    provide no insight into how or on what basis the agency
    reached its decision.
    As the district court recognized, however, the District
    Managers’ conclusions were not unsupported boilerplate; they
    were “made at the end of a lengthy memorandum explaining,
    among other things, the details concerning the scope of the
    proposed project in each respective district, the expected
    effect of the project on [jurisdictional] waters . . . within that
    district, and specific mitigation techniques to be employed in
    response . . . .” 
    64 F. Supp. 3d
    at 157. In light of the
    surrounding context, we conclude that the Corps’s cumulative
    effects conclusions were adequately supported and reasoned.
    See 
    Snoqualmie, 683 F.3d at 1163
    .
    V. Motion to Supplement and Amend
    Sierra Club also appeals the district court’s order denying
    the organization’s motions to supplement and amend its
    complaint. The defendants assert that Sierra Club failed to
    appeal that order, pointing out that Sierra Club’s notice of
    appeal explicitly referred only to the district court’s summary
    judgment order. The district court issued both orders
    concurrently, however, and we are satisfied that Sierra Club’s
    notice of appeal adequately expressed its intent to appeal both
    orders. Further, the defendants suffer no prejudice from our
    consideration of the order denying the motions to supplement
    and amend. See, e.g., Martinez v. Bureau of Prisons, 
    444 F.3d 620
    , 623 (D.C. Cir. 2006).
    41
    Reviewing the district court’s denial of the motions to
    amend and supplement for an abuse of discretion, Hall v. CIA,
    
    437 F.3d 94
    , 101 (D.C. Cir. 2006), we affirm the district court
    for substantially the same reasons explained in the challenged
    order. Sierra Club sought to add to its complaint allegations
    meant chiefly to show that the agencies had taken actions that,
    the agencies recognized, required NEPA review as to some
    portions of the pipeline. Specifically, Sierra Club sought to
    allege that the Corps and Bureau issued EAs for the easement
    areas—developments Sierra Club believed confirmed the
    ripeness of its NEPA claims and provided a stronger foothold
    for its arguments that the agency actions effectively
    federalized the entire pipeline. Sierra Club also sought to add
    allegations that EPA had commented to the Corps in
    December 2013 that the Corps’s NEPA analysis of the
    Arkansas River easement was deficient because it failed to
    assess the entire pipeline.
    The district court did not abuse its discretion in denying
    Sierra Club’s motion as futile. As the court explained, its
    summary judgment analysis assumed that the grants of the
    federal easements were ripe federal actions triggering some
    degree of NEPA review. App. 633-34; see 
    also 64 F. Supp. at 133
    n.1. The completion of those EAs did not affect the
    NEPA inquiry before the court, which concerned only the
    scope of the NEPA analysis Sierra Club claims was required,
    not the intensiveness of that review. Sierra Club’s own
    motion advised that the proposed newly styled claims and
    new allegations did “not involve any new . . . legal arguments
    that [were] not already before [the] court.” And the existing
    claims concerned only the breadth, not depth, of the agencies’
    NEPA analysis. See, e.g., Compl. ¶¶ 5, 7. The proposed
    supplement and amendment would not, for instance, have
    added a new claim that the agencies should have performed
    EISs rather than EAs on account of the easements. The
    42
    district court never had occasion to opine on such a claim, nor
    do we.
    *   *    *
    For the reasons stated, we affirm the judgment of the
    district court.
    So ordered.
    BROWN, Circuit Judge, concurring in the judgment: This
    is not a close case. As the district court aptly noted, three
    basic facts decide it: “a private company is constructing the
    [Flanagan South] pipeline largely on privately-owned land;
    the federal agencies that have been consulted about aspects of
    the pipeline project have control over only a small portion of
    the land and waterways that the pipeline traverses; and no
    statute authorizes the federal government to regulate or
    oversee the construction of a domestic oil pipeline.” Sierra
    Club v. U.S. Army Corps of Eng’rs, 
    64 F. Supp. 3d 128
    , 157
    (D.D.C. 2014). NEPA requires agency environmental review
    when the agency undertakes a major federal action defined as
    an action that significantly affects the human environment and
    is subject to federal control and responsibility. 42 U.S.C. §
    4332(2)(C); 40 C.F.R. § 1508.18; see also Winnebago Tribe
    of Neb. v. Ray, 
    621 F.2d 269
    , 273 (8th Cir. 1980) (“As for
    federal involvement, the fact that part of the line will cross the
    Winnebago Reservation does not suffice to turn this
    essentially private action into federal action. . . . Thus we
    conclude that the Corps did not have sufficient control and
    responsibility to require it to study the entire project.”).
    Little more ink needs to be spilled to conclude that — given
    federal control over less than 20 miles of the 600-mile
    pipeline — NEPA cannot compel federal review of the entire,
    essentially private, pipeline.
    Sierra Club has put forward several claims, all of them a
    variation on the theme that NEPA requires some federal
    agency, if not all of them collectively, to review the entire
    pipeline as a connected action. The likelihood of Sierra
    Club’s success on the merits was briefed, argued, and
    thoroughly considered by the district court when it dismissed
    their motion for preliminary injunction. See Sierra Club v.
    U.S. Army Corps of Eng’rs, 
    990 F. Supp. 2d 9
    , 44 (D.D.C.
    2
    2013). After a second perusal when federal defendants 1 filed
    motions to dismiss and both parties cross-motioned for
    summary judgment, the district court again concluded that
    “[p]laintiffs are wrong to insist that any federal agency had an
    obligation under NEPA or any other statute to conduct an
    environmental review of the impact of the entire FS Pipeline
    . . . given that the Federal Defendants have permitting
    authority over only small segments of this private pipeline
    project and none of the defendant agencies, alone or in
    combination, have authority to oversee or control the vast
    portions of the FS pipeline that traverse private land.” Sierra
    
    Club, 64 F. Supp. at 134
    .
    The majority opinion retreads this familiar ground but
    with considerably more angst. This case is wholly removed
    from the contexts of San Luis & Delta Mendota Water
    Authority v. Jewell, 
    747 F.3d 581
    (9th Cir. 2014), and
    Ramsey v. Kantor, 
    96 F.3d 434
    (1996) — cases the opinion
    devotes several pages to distinguishing. See Maj. Op. 25-27.
    Here, no instance of federal involvement (alone or
    collectively) amounted to the “functional equivalent” of a
    permit nor was this a circumstance in which one federal
    agency was advising another. And no amount of artful
    pleading can convert these minor federal engagements into a
    “connected action” that subjects the 580 miles of private
    pipeline to NEPA review. See Delaware Riverkeepers v.
    FERC, 
    753 F.3d 1304
    (D.C. Cir. 2014).
    While the majority ultimately arrives at the same
    destination, its route is needlessly circuitous, creating the
    1
    “Federal defendants” here refers collectively to the United States
    Corps of Engineers, the Department of Transportation Pipeline and
    Hazardous Materials Safety Administration, the Fish and Wildlife
    Service, the Department of Interiors Bureau of Indian Affairs, and
    the Environmental Protection Agency.
    3
    impression that Sierra Club’s challenges fail by a hairsbreadth
    rather than a hectare. Because I favor the district court’s
    direct approach, I concur only in the judgment.
    

Document Info

Docket Number: 14-5205

Citation Numbers: 419 U.S. App. D.C. 416, 803 F.3d 31

Filed Date: 9/29/2015

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (24)

airport-neighbors-alliance-inc-a-new-mexico-corporation-v-united-states , 90 F.3d 426 ( 1996 )

ohio-valley-environmental-coalition-coal-river-mountain-watch-natural , 429 F.3d 493 ( 2005 )

Save Our Sonoran, Inc. v. Flowers , 408 F.3d 1113 ( 2005 )

arthur-s-west-an-individual-v-secretary-of-the-department-of , 206 F.3d 920 ( 2000 )

columbia-basin-land-protection-association-etc-and-south-columbia-basin , 643 F.2d 585 ( 1981 )

winnebago-tribe-of-nebraska-v-col-james-w-ray-district-engineer-omaha , 621 F.2d 269 ( 1980 )

Karst Env Educ Inc v. EPA , 475 F.3d 1291 ( 2007 )

Gerber, John E. v. Norton, Gale A. , 294 F.3d 173 ( 2002 )

Sierra Club v. Van Antwerp , 661 F.3d 1147 ( 2011 )

Grand Canyon Trust v. Federal Aviation Administration , 290 F.3d 339 ( 2002 )

Hall v. Central Intelligence Agency , 437 F.3d 94 ( 2006 )

Martinez, Robert v. Bureau of Prisons , 444 F.3d 620 ( 2006 )

hugh-r-kern-leigh-ann-lipscomb-oregon-natural-resources-council-v-united , 284 F.3d 1062 ( 2002 )

james-a-ramsey-elf-atochem-north-america-aluminum-company-of-america , 96 F.3d 434 ( 1996 )

Coalition on Sensible Transportation, Inc. v. Elizabeth Dole , 826 F.2d 60 ( 1987 )

Potter v. District of Columbia , 558 F.3d 542 ( 2009 )

Department of Transportation v. Public Citizen , 124 S. Ct. 2204 ( 2004 )

Tennessee Valley Authority v. Hill , 98 S. Ct. 2279 ( 1978 )

Miccosukee Tribe of Indians of Fla. v. United States , 430 F. Supp. 2d 1328 ( 2006 )

Hammond v. Norton , 370 F. Supp. 2d 226 ( 2005 )

View All Authorities »