Western Surety Company v. U.S. Engineering Construction ( 2020 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued January 9, 2020                 Decided April 7, 2020
    No. 19-7033
    WESTERN SURETY COMPANY,
    APPELLEE
    v.
    U.S. ENGINEERING CONSTRUCTION, LLC,
    APPELLANT
    Appeal from the United States District Court
    for the District of Columbia
    (No. 1:15-cv-00327)
    Stephen B. Sutton, pro hac vice, argued the cause for
    appellant. With him on the briefs were Adam S. Caldwell and
    Patrick J. Curran, Jr.
    Thomas J. Moran argued the cause and filed the brief for
    appellee.
    Before: PILLARD and KATSAS, Circuit Judges, and
    SENTELLE, Senior Circuit Judge.
    Opinion for the Court filed by Senior Circuit Judge
    SENTELLE.
    2
    SENTELLE, Senior Circuit Judge:          Western Surety
    Company (“Western Surety”) brought this action against U.S.
    Engineering Construction, LLC (“U.S. Engineering”) in the
    district court seeking declaratory and injunctive relief
    regarding its potential liability under a construction
    performance bond. Western Surety moved for summary
    judgment asserting that its obligations under the bond were
    discharged because U.S. Engineering failed to comply with a
    condition precedent, thereby relieving Western Surety of any
    liability. The district court granted Western Surety’s motion.
    U.S. Engineering filed the instant appeal. For the following
    reasons, we affirm the district court’s grant of summary
    judgment.
    I.
    Turner Construction Company (“Turner”), not a party to
    this action, contracted with the Republic of South Africa to
    construct a new South African embassy in Washington, D.C.
    On January 25, 2012, Turner and U.S. Engineering, the
    appellant in this case, entered into a subcontract in which U.S.
    Engineering would complete a range of work on the embassy.
    On February 15, 2012, U.S. Engineering and United Sheet
    Metal, also not a party to this action, entered into a subcontract
    in which United Sheet Metal would complete work on the
    embassy related to the installation of sheet metal.
    The contract price for the U.S. Engineering and United
    Sheet Metal subcontract was $585,000. U.S. Engineering also
    paid $7,940 in premiums to obtain a construction performance
    bond from Western Surety, the appellee in this case, in which
    Western Surety and United Sheet Metal jointly and severally
    bound themselves to ensure the work under the U.S.
    Engineering and United Sheet Metal subcontract was
    3
    completed. This performance bond is the subject of the
    underlying dispute.
    By agreement of the parties, the bond form used was the
    American Institute of Architects (“AIA”) Document A312-
    2010 bond form, a standardized form commonly used in the
    construction industry. The bond refers to United Sheet Metal
    as the “Contractor,” U.S. Engineering as the “Owner,” and
    Western Surety as the “Surety.” J.A. 144.
    Section 3 of the bond outlines what must occur to trigger
    Western Surety’s obligations in the event that United Sheet
    Metal is in default and the subcontract is terminated. Under
    section 3.1, U.S. Engineering must first provide notice to
    United Sheet Metal and Western Surety that it is considering
    declaring United Sheet Metal in default. If U.S. Engineering
    fails to provide such notice, section 4 excuses that failure
    except to the extent that Western Surety demonstrates actual
    prejudice. Under section 3.2, if U.S. Engineering officially
    decides to end its contractual relationship with United Sheet
    Metal, it must
    declare[] a Contractor Default, terminate[] the
    Construction Contract and notif[y] the Surety.
    J.A. 145. Section 3.3 provides that U.S. Engineering must also
    agree to pay the balance of the contract price to Western Surety
    or to a contractor selected to perform the subcontract.
    Under section 5,
    [w]hen the Owner has satisfied the conditions
    of Section 3, the Surety shall promptly and at
    the Surety’s expense take one of the following
    actions:
    4
    § 5.1 Arrange for the Contractor, with the
    consent of the Owner, to perform and complete
    the Construction Contract;
    § 5.2 Undertake to perform and complete the
    Construction Contract itself, through its agents
    or independent contractors;
    § 5.3 Obtain bids or negotiated proposals from
    qualified contractors acceptable to the Owner
    for a contract for performance and completion
    of the Construction Contract . . . and pay to the
    Owner the amount of damages as described in
    Section 7 in excess of the Balance of the
    Contract Price incurred by the Owner as a result
    of the Contractor’s Default; or
    § 5.4 Waive its right to perform and complete,
    arrange for completion, or obtain a new
    contractor and with reasonable promptness
    under the circumstances:
    .1   After investigation, determine the
    amount for which it may be liable to
    the Owner and, as soon as practicable
    after the amount is determined, make
    payment to the Owner; or
    .2   Deny liability in whole or in part and
    notify the Owner, citing the reasons
    for denial.
    J.A. 145.
    5
    While working to complete the embassy, the parties began
    to encounter problems caused by United Sheet Metal. On
    February 6, 2013, Turner sent a formal notice to U.S.
    Engineering stating that any additional costs incurred from
    delays caused by U.S. Engineering and its subcontractors—
    namely, United Sheet Metal—would be back charged to U.S.
    Engineering. Turner highlighted that United Sheet Metal
    “lack[ed] materials, manpower, and completely ignore[d]
    direction given to them by U.S. Engineering Company or
    Turner.” J.A. 201.
    U.S. Engineering forwarded those concerns to United
    Sheet Metal in a “formal ‘notice to correct’” letter, advising
    United Sheet Metal that it had “failed to comply with its
    obligations under the Subcontract” and that the company had
    “72 hours [to] demonstrate performance improvement.” J.A.
    202. Nevertheless, the problems persisted. Finally, on
    September 9, 2013, U.S. Engineering formally terminated its
    subcontract with United Sheet Metal.
    The parties do not dispute that U.S. Engineering declared
    United Sheet Metal in default and terminated the subcontract.
    Nor do they dispute that U.S. Engineering failed to notify
    Western Surety that it was considering declaring United Sheet
    Metal in default and terminating the subcontract. In fact, the
    record is clear that U.S. Engineering did not notify Western
    Surety of the default and termination until June 9, 2014, when
    it sent a notice of claim against the bond, nearly nine months
    after the termination occurred. On June 13, 2014, Western
    Surety acknowledged receipt of the letter.
    In the meantime, United Sheet Metal and U.S. Engineering
    began arbitration to settle various disputes related to the
    termination of the subcontract. On March 4, 2015, U.S.
    6
    Engineering attempted to join Western Surety in that dispute.
    In response, Western Surety brought this action in the district
    court. In Count I, Western Surety sought declaratory relief that
    it was “not required to arbitrate any disputes or controversies
    regarding its rights, liabilities, or obligations under the Bond.”
    Complaint at 11, W. Sur. Co. v. U.S. Eng’g Co., No.
    15-cv-0327-TSC (D.D.C. Mar. 6, 2015). In Count II, it sought
    injunctive relief “prohibiting U.S. Engineering from
    participating in any arbitration proceedings which purport to
    determine or affect Western Surety’s rights, liabilities, or
    obligations under the Bond.” Id. Finally, in Count III, it sought
    declaratory relief that its obligations under the Bond had been
    discharged, “rendering the bond null and of no further force or
    effect.” Id. On this third count, Western Surety specifically
    maintained that U.S. Engineering did not have a right to make
    a claim under the bond because of its “extreme delay in
    providing notice to Western Surety of United Sheet Metal’s
    alleged default and termination.” Id. at 10.
    Western Surety moved for summary judgment on the first
    two counts. The district court granted the motion, leaving only
    the question of whether Western Surety’s obligations under the
    bond had been discharged by U.S. Engineering’s failure timely
    to comply with the notice provision of section 3.2. U.S.
    Engineering then filed its answer, asserting that section 3.2
    required it only to provide notice of the default and termination
    without any specific time limitation. U.S. Engineering thus
    argued that Western Surety was obligated to perform under
    section 5 of the bond.
    On March 2, 2017, Western Surety filed a new motion for
    summary judgment on its remaining claim and U.S.
    Engineering’s counterclaims. The district court granted
    Western Surety’s motion on all claims. The court held that,
    “although Section 3.2 [of the bond] does not explicitly state
    7
    that U.S. Engineering must notify Western Surety within a
    certain amount of time, the explicit grant to Western Surety of
    a right to remedy the default necessarily implies that timely
    notice is required to trigger Western Surety’s obligation under
    the Bond because Section 5 operates only if timely notice is
    given.” W. Sur. Co. v. U.S. Eng’g Co., 
    375 F. Supp. 3d 1
    , 6
    (D.D.C. 2019) (emphasis added). Specifically, the district
    court relied on this court’s decision in Hunt Construction
    Group v. National Wrecking Corporation, 
    587 F.3d 1119
     (D.C.
    Cir. 2009), in which we held that a party’s failure to provide
    notice to the surety of default and termination before
    completing the work through other subcontractors was a failure
    of a condition precedent and discharged the surety’s
    obligations under a similar AIA bond. See 
    id.
     at 1121–22. As
    the district court noted in this case, “[we] reasoned that
    sureties’ options to remedy the default would be ‘nonsensical’
    without the inference that the sureties should be given timely
    notice of the declaration of default.” W. Sur. Co., 375 F. Supp.
    3d at 6 (quoting Hunt Constr. Grp., 
    587 F.3d at 1121
    ).
    The district court also held that Western Surety only had
    to prove actual prejudice in the event of U.S. Engineering’s
    failure to provide notice to Western Surety that it was
    considering declaring United Sheet Metal in default under
    section 3.1, not in the event of U.S. Engineering’s failure to
    provide notice that it had actually declared United Sheet Metal
    in default and terminated the subcontract under section 3.2.
    U.S. Engineering filed the instant appeal challenging both
    holdings.
    II.
    We review the district court’s grant of summary judgment
    de novo. Mayo v. Reynolds, 
    875 F.3d 11
    , 19 (D.C. Cir. 2017).
    Summary judgment is appropriate if, viewing the facts in the
    8
    light most favorable to the nonmoving party, there is no
    genuine dispute as to any material fact. Fed. R. Civ. P. 56. The
    parties agree that D.C. law applies.
    A.
    U.S. Engineering primarily argues that the plain language
    of the bond simply requires notice of default and termination,
    not notice sufficiently early to enable every potential option to
    cure, to trigger Western Surety’s obligations under the bond.
    In the alternative, it argues that if the bond’s language is
    ambiguous as to whether timely notice is required, the court
    should construe any ambiguous language with due regard for
    the bond’s purpose to protect U.S. Engineering from United
    Sheet Metal’s default and to avoid a forfeiture.
    Like the district court, we conclude that Hunt is
    controlling. Hunt involved AIA Document A311, which
    expressly provides that, if the contractor is declared to be in
    default, the surety has an opportunity to “promptly remedy”
    that default. Hunt Constr. Grp., 
    587 F.3d at 1120
    . It also
    allows the owner to remedy the default on its own terms “after
    reasonable notice” to the surety. 
    Id.
     The owner in that case
    declared the contractor in default and terminated the
    construction contract but did not notify the surety of the default
    and termination until five months later. 
    Id.
     In the meantime,
    the owner employed another contractor to finish the remaining
    work without consulting the surety. 
    Id.
     Construing the A311
    bond, we determined that timely notice was a condition
    precedent to the surety’s obligations under the bond. 
    Id.
     at
    1120–22. As the district court noted in this case, we explained
    that accepting Hunt’s contrary argument “would gut rights
    specifically afforded the surety”—namely, the bond’s “explicit
    grant to the surety of a right to remedy the default itself.” 
    Id.
    at 1121–22.
    9
    The A312 bond at issue in this case states that, in order to
    trigger Western Surety’s obligations under the bond, U.S.
    Engineering must declare a United Sheet Metal default,
    terminate the subcontract, and notify Western Surety. Similar
    to the A311 bond, the A312 bond provides four alternative
    methods by which the surety can respond to the default. By
    unilaterally completing United Sheet Metal’s remaining
    contract obligations before notifying Western Surety, U.S.
    Engineering deprived Western Surety of its contractually
    agreed-upon opportunity to participate in remedying United
    Sheet Metal’s default.
    To be sure, under several provisions of the bond, Western
    Surety could not have responded to the default without U.S.
    Engineering’s consent. But even so, that limitation did not give
    U.S. Engineering the right to address the situation without
    consulting Western Surety and then recover under the bond
    nine months later. In other words, despite the bond’s lack of
    an explicit timely notice requirement, the performance bond is
    properly read as requiring U.S. Engineering to notify Western
    Surety of the default before engaging in self-help remedies.
    Otherwise, “the explicit grant to the surety of a right to remedy
    the default itself would be operative only if the obligee chose
    to give it notice,” thereby rendering the options in section 5
    “nearly meaningless.” 
    Id. at 1121
    . Accordingly, because the
    bond expressly provides the surety with the opportunity to
    participate in curing the subcontractor’s default, we hold that it
    is a condition precedent to the surety’s obligations under the
    bond that the owner must provide timely notice to the surety of
    any default and termination before it elects to remedy that
    default on its own terms. In light of U.S. Engineering’s failure
    to provide such timely notice, Western Surety was not
    obligated to perform under the bond.
    10
    We note separately that at least one other court construing
    the A312 bond reached a similar conclusion. Although not
    dealing with a failure of notice under section 3.2, the Eleventh
    Circuit determined that if an obligee hires a new subcontractor
    before the surety has an opportunity to respond to the
    termination, the surety’s obligations under the bond are
    discharged. Int’l Fid. Ins. Co. v. Americaribe-Moriarty JV, 681
    F. App’x 771, 776–77 (11th Cir. 2017). The Eleventh Circuit
    emphasized that such an action “thwart[s] [the surety’s] ability
    to choose among the options it had for remedying [the
    subcontractor’s] default under § 5 of the bond.” Id.
    Because we do not conclude that the bond is ambiguous,
    we need not address U.S. Engineering’s arguments that surety
    bonds should be construed liberally in favor of the beneficiary
    and to avoid a forfeiture. See, e.g., St. Paul Fire & Marine Ins.
    Co. v. VDE Corp., 
    603 F.3d 119
    , 123 (1st Cir. 2010)
    (“Although ‘[t]he prevailing doctrine is that [a surety bond]
    should be liberally interpreted in favor of its beneficiary,’ that
    principle ‘is not a blank check to the judicial power to rule out
    the pacts and agreements between the parties.’” (alterations in
    original) (quoting Citibank v. Grupo Cupey, Inc., 
    382 F.3d 29
    ,
    31–32 (1st Cir. 2004))); Wash. Props., Inc. v. Chin, Inc., 
    760 A.2d 546
    , 549 (D.C. 2000) (“As a general rule of contract
    interpretation, there is a presumption in favor of construing
    doubtful language in a contract as language of promise rather
    than as language of condition.” (emphasis added)).
    B.
    U.S. Engineering also contends that section 4 of the bond
    requires Western Surety to demonstrate actual prejudice in
    order to avoid liability under the bond if there is a failure to
    provide notice under any section. It argues that section 4
    expressly referenced a failure to give notice only under section
    11
    3.1 because that was the only notice requirement the parties
    intended to include in the bond. To the extent the court implies
    a timely notice requirement under section 3.2, U.S.
    Engineering asserts that the requirement to demonstrate actual
    prejudice to avoid liability under the bond should equally apply
    to any such implied condition.
    Section 4 states, “Failure on the part of the Owner to
    comply with the notice requirement in Section 3.1 shall not
    constitute a failure to comply with a condition precedent to the
    Surety’s obligations, or release the Surety from its obligations,
    except to the extent the Surety demonstrates actual prejudice.”
    J.A. 145 (emphasis added). By its plain language, the
    requirement to demonstrate actual prejudice clearly applies to
    a failure to give notice only under section 3.1. There is no
    similar requirement when U.S. Engineering fails to give timely
    notice of the default and termination under section 3.2. U.S.
    Engineering’s assertion that the parties intended section 3.1 to
    be the only notice requirement in the bond makes little, if any,
    sense. By its express terms, section 3.2 clearly provides that
    U.S. Engineering must “notify” Western Surety of the default
    and termination in order to trigger Western Surety’s obligation
    to act under section 5. J.A. 145. Accordingly, we conclude
    that the plain language of the bond is unambiguous that the
    surety is not required to demonstrate actual prejudice to avoid
    liability under the bond if the obligee fails to provide notice of
    default and termination under section 3.2.
    Even assuming we agreed with U.S. Engineering that
    Western Surety must demonstrate actual prejudice to avoid
    liability in this situation, it would not change the outcome. By
    failing to provide notice under section 3.2, U.S. Engineering
    robbed Western Surety of its contractually agreed-upon
    opportunity to participate in the mitigation process entirely.
    Although not necessary to our opinion, it would seem that is
    12
    inherently prejudicial. Thus, even if we required Western
    Surety to demonstrate actual prejudice, it would not be liable
    under the bond due to the inherent prejudice it suffered.
    Again, another court interpreting the A312 bond agrees
    with our interpretation. The Nevada district court determined
    that “failure to comply with section 3.2 is a condition precedent
    to [the surety’s] obligations arising under the bond, and the
    parties contractually agreed that [the surety] need not show
    prejudice from that failure to relive it of its obligations.”
    United States ex rel. Agate Steel, Inc. v. Jaynes Corp., No.
    2:13-CV-01907-APG-NJK, 
    2016 WL 8732302
    , at *7 (D. Nev.
    June 17, 2016).
    III.
    Because U.S. Engineering failed to comply with the
    condition precedent to provide timely notice of default and
    termination under section 3.2, Western Surety was not
    obligated to perform under the bond. Additionally, the bond is
    clear that Western Surety is not required to demonstrate actual
    prejudice to avoid liability under these circumstances. We thus
    affirm the district court’s grant of summary judgment.