United States v. Hirani Engineering & Land Surveying, PC ( 2020 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Submitted March 27, 2020              Decided June 19, 2020
    No. 19-7010
    UNITED STATES OF AMERICA, FOR THE USE AND BENEFIT OF
    AMERICAN CIVIL CONSTRUCTION, LLC,
    APPELLEE
    v.
    HIRANI ENGINEERING & LAND SURVEYING, PC,
    APPELLEE
    COLONIAL SURETY COMPANY,
    APPELLANT
    Consolidated with 19-7011, 19-7015
    Appeals from the United States District Court
    for the District of Columbia
    (No. 1:14-cv-00745)
    Michael C. Delaney and Laurence Schor were on the joint
    briefs for appellants/cross-appellees.
    Herman M. Braude was on the briefs for appellee/cross
    appellant.
    2
    Before: HENDERSON, ROGERS and GARLAND, Circuit
    Judges.
    Opinion for the Court by Circuit Judge ROGERS.
    ROGERS, Circuit Judge: American Civil Construction,
    LLC, (“ACC”) the subcontractor on a U.S. Army Corps of
    Engineers (“Corps”) flood protection project, sued the prime
    contractor, Hirani Engineering & Land Surveying, P.C.,
    (“Hirani”) for breach of contract and the providers of Hirani’s
    payment bond, Colonial Surety Company (“Colonial”), under
    the Miller Act, 40 U.S.C. § 3133, for unpaid labor and
    materials. Following a bench trial, the district court entered
    judgment in favor of ACC and awarded damages against both
    defendants. Hirani and Colonial appeal, and ACC cross
    appeals. Among the challenges to the judgment, Colonial
    contends that ACC’s lawsuit was untimely under the Miller
    Act’s one-year statute of limitations, pointing to the Corps’
    April 26 letter terminating Hirani. But the Federal Acquisition
    Regulations may render the effective date of Hirani’s
    termination to be later. Because the district court expressly
    declined to make some relevant findings, the court will remand
    the case without deciding whether the accrual of the Miller Act
    cause of action stems from the termination of the Prime
    Contract or the Subcontract. Otherwise, the court affirms the
    award of restitution against Hirani and defers ruling on other
    issues raised by the parties.
    I.
    In 2010, the Corps awarded Hirani a $3,833,097 contract
    (the “Prime Contract”) to build the “Washington, D.C. and
    Vicinity, Local Flood Protection Project, 17th Street Closure
    Structure” (the “Project”). See U.S. ex rel. Am. Civil Constr.,
    LLC v. Hirani Eng’g & Land Surveying, P.C., 
    345 F. Supp. 3d 3
    11, 22 (D.D.C. 2018) (“Hirani II”), ⁋⁋ 4–9. Under the Prime
    Contract, Hirani was to build a levee flood wall designed to
    prevent the Potomac River from flooding across the National
    Mall into downtown Washington, D.C.
    Id. ⁋ 4.
    The contract
    anticipated that the Project would be completed within one
    year, by October 12, 2011.
    Id. ⁋ 10.
    The contract also required
    Hirani to obtain a surety bond and it did so from Colonial in
    the amount of $3,833,097.
    Id. ⁋⁋ 11–12.
    A few months later,
    the Corps issued Option 1, which required Hirani to install
    stone cladding on the levee wall and increased the contract
    price by $641,369.
    Id. ⁋ 57.
    On April 4, 2011, Hirani and ACC entered into a written
    Subcontract for $2,845,600, pursuant to which ACC would
    perform the “entire scope of work” of the Project, except for
    management, quality control, and the installation of some
    specified metal structures and panels.
    Id. ⁋⁋ 13,
    16–19. The
    Subcontract provided that if a “dispute, controversy, or
    question” arose about its interpretation, ACC would not stop
    working until the dispute or controversy was resolved.
    Id. ⁋ 21
    (alteration omitted).
    The Project was beset by delays. Briefly, delays were
    attributable to Hirani’s procrastination, change orders by the
    Corps, bad weather, a misalignment between structural and
    architectural drawings, and work stoppages due to the National
    Cherry Blossom Festival.
    Id. ⁋⁋ 50–78.
    By letter of April 26, 2013, the Corps terminated Hirani
    for default.
    Id. ⁋ 92
    . 
    The district court found that Hirani was
    at fault for the termination.
    Id. ⁋⁋ 95–96.
    The Corps explained
    that it had “little confidence” that Hirani would finish the
    Project because Hirani had not taken the steps needed to
    improve its progress, work had stalled since March 22 “due to
    subcontractor management and nonpayment issues,” Hirani
    4
    “had not submitted periodic progress schedules” and Hirani
    had failed to “fulfill commitments to meet milestone deadlines
    necessary for completing the remainder of the Prime Contract.”
    Id. ⁋ 93
    (alterations omitted). Hirani responded by letter of
    April 30, 2013, rejecting the termination and requesting a
    meeting.
    Id. ⁋ 99.
    That same day, Ed Hollander, ACC’s field
    superintendent for the Project, learned that the Corps had
    terminated Hirani.
    Id. ⁋⁋ 67,
    98. The following day, May 1,
    Hirani told Hollander that ACC must continue working on the
    Project because it (Hirani) was fighting the termination.
    Id. ⁋ 100.
    In accordance with Hirani’s direction, ACC backfilled
    an excavated grass area on May 1.
    Id. ⁋ 102.
    The following
    day, May 2, Hirani directed ACC to immediately stop working
    on the Project.
    Id. ⁋ 104.
    The district court expressly declined to find when Hirani
    received the Corps’ termination letter.
    Id. ⁋ 92
    n.5. It did find
    that the ACC crew did not work on the Project site on Saturday,
    April 27 or Sunday, April 28, and heavy rains prevented work
    on Monday, April 29 and Tuesday, April 30.
    Id. ⁋ 97.
    But the
    district court did not make a finding of fact whether ACC
    supplied materials during this time, and it declined to decide if
    work performed by Ed Hollander or fencing and cleanup work
    performed by ACC between April 29 and May 1 were
    compensable under the Subcontract. (Having found that ACC
    last performed compensable work on May 1, the district court
    noted it “therefore need not consider [ACC’s] alternative
    arguments that work performed by Ed Hollander on the Project
    site between April 29, 2013, through May 1, 2013, as well as
    fencing work and cleanup performed by ACC during that time
    period are compensable tasks under the Subcontract and thus
    occurred within the one-year limitations period.”)
    Id. at 40
    n.8.
    ACC filed suit against Hirani and Colonial on April 29,
    2014. In a second amended complaint, ACC requested $2.07
    5
    million in damages from each defendant.           Colonial
    counterclaimed, alleging among other things that ACC had
    breached the Subcontract by failing to perform and caused
    Colonial to incur substantial costs.
    The district court denied Hirani and Colonial’s motion for
    summary judgment. See U.S. ex rel. Am. Civil Constr., LLC v.
    Hirani Eng’g & Land Surveying, P.C., 
    263 F. Supp. 3d 99
    , 101
    (D.D.C. 2017) (“Hirani I”). Following a five-day bench trial,
    the district court concluded that Colonial’s counterclaims
    failed because it had not shown that ACC breached the
    Subcontract. See Hirani 
    II, 345 F. Supp. 3d at 39
    . On ACC’s
    Miller Act claim against Colonial, the district court found that
    ACC’s lawsuit was timely because it was filed within one year
    of the last compensable work ACC had performed under the
    Subcontract.
    Id. at 43.
    And the court found that “Hirani
    breached the Subcontract by refusing to pay ACC for the work
    that it performed.”
    Id. The court
    therefore entered judgment
    on the breach of contract claim in favor of ACC,
    id., and directed
    the parties to brief how damages should be calculated,
    id. at 56.
    The district court awarded $1,544,957.29 in quantum
    meruit damages on ACC’s Miller Act claim against Colonial,
    plus more than half a million dollars in prejudgment interest.
    U.S. ex rel. Am. Civil Constr., LLC v. Hirani Eng’g & Land
    Surveying, P.C., No. 14-CV-00745 (APM), 
    2019 WL 162019
    ,
    at *3 (D.D.C. Jan. 10, 2019) (“Hirani III”). On ACC’s contract
    claim against Hirani, the district court construed ACC’s request
    for quantum meruit damages as seeking restitution because
    Hirani had breached a written contract.
    Id. Citing the
    RESTATEMENT (THIRD) OF RESTITUTION AND UNJUST
    ENRICHMENT to conclude that performance-based restitution
    must be limited by expectancy under the contract, the district
    court awarded $425,319.50 in restitution damages, plus nearly
    6
    $150,000 in prejudgment interest, inasmuch as ACC had
    already been paid over $2.5 million for its work.
    Id. at *4–5.
    II.
    Hirani and Colonial appeal. In their joint brief, they
    contend that the district court erred in interpreting the Miller
    Act, arguing that ACC was not entitled to recover any damages
    because ACC failed to bring its Miller Act claim within one
    year after the last day ACC performed compensable work on
    the Project. They also contend that the district court erred by
    awarding quantum meruit damages because breach of contract
    damages could be calculated, by inadequately explaining the
    damages award, by allowing double recovery to ACC, and by
    admitting documents containing hearsay.
    ACC cross appeals, contending that it was entitled to
    Miller Act damages for the services performed by Ed
    Hollander, its field superintendent, and to quantum meruit
    damages against Hirani.
    A.
    The court reviews de novo the district court’s denial of
    summary judgment and its statutory interpretation. See Validus
    Reinsurance, Ltd. v. United States, 
    786 F.3d 1039
    , 1042 (D.C.
    Cir. 2015); Draim v. Virtual Geosatellite Holdings, Inc., 
    522 F.3d 452
    , 455 n.3 (D.C. Cir. 2008). “Findings of fact, whether
    based on oral or other evidence, must not be set aside unless
    clearly erroneous, and the reviewing court must give due regard
    to the trial court’s opportunity to judge the witnesses’
    credibility.” Fed. R. Civ. P. 52(a)(6); see also United States v.
    AT&T, Inc., 
    916 F.3d 1029
    , 1033 (D.C. Cir. 2019).
    7
    In enacting the Miller Act, Congress sought to “place[]
    subcontractors to government contractors on substantially
    equal footing with subcontractors to private contractors” by
    providing them with a security interest. See U.S. ex rel. Heller
    Elec. Co. v. William F. Klingensmith, Inc., 
    670 F.2d 1227
    , 1232
    (D.C. Cir. 1982). “The Miller Act, like [its predecessor,] the
    Heard Act, is highly remedial in nature” and therefore “is
    entitled to a liberal construction and application in order
    properly to effectuate the Congressional intent to protect those
    whose labor and materials go into public projects.” Clifford F.
    MacEvoy Co. v. U.S. ex rel. Calvin Tomkins Co., 
    322 U.S. 102
    ,
    107 (1944). The Miller Act requires government contractors
    to obtain both a performance bond to protect the government
    and a payment bond to protect “all persons supplying labor and
    material in carrying out the work provided for in the contract.”
    40 U.S.C. § 3131(b).         The Act also provides that a
    subcontractor who is not paid by the contractor may file an
    action on the Payment Bond:
    Every person that has furnished labor or material in
    carrying out work provided for in a contract for which
    a payment bond is furnished under section 3131 of
    this title and that has not been paid in full within 90
    days after the day on which the person did or
    performed the last of the labor or furnished or
    supplied the material for which the claim is made may
    bring a civil action on the payment bond for the
    amount unpaid at the time the civil action is brought
    and may prosecute the action to final execution and
    judgment for the amount due.
    Id. § 3133(b)(1).
    But Miller Act claims must be brought within
    a one-year statute of limitations: “An action brought under this
    subsection must be brought no later than one year after the day
    on which the last of the labor was performed or material was
    8
    supplied by the person bringing the action.”
    Id. § 3133(b)(4)
    (emphasis added).
    Neither the Supreme Court nor this court have addressed
    when a Miller Act cause of action accrues. Upon canvassing
    federal district and appellate court cases, the district court
    observed that the “courts have taken three approaches in
    determining when the statute of limitations begins to run on a
    claim under the Miller Act.” Hirani 
    I, 263 F. Supp. 3d at 109
    .
    The majority of courts had held that only labor and materials
    furnished for the original contract (as opposed to corrective or
    repair work performed after final inspection) were “labor” or
    “materials” for purposes of the statute of limitations.
    Id. at 109–10.
    Other courts had held that the statute of limitations
    began to run when the contract was substantially completed.
    Id. at 110.
    And a third group of courts had “applied a multi-
    factor analysis” to determine when the statute of limitations
    began to run.
    Id. This court
    need not resolve the Miller Act
    issue at this time.
    The district court, considering the approaches in light of
    the text of the Miller Act and its broad remedial purpose,
    concluded that in order to avoid engaging in a “subjective line-
    drawing exercise,” it would “simply look to the contract to
    determine” the tasks for which “the parties agreed the
    subcontractor would be compensated, then determine the last
    date on which the subcontractor supplied materials or labor for
    one of those tasks.”
    Id. at 110–11
    (citing U.S. ex rel. GE
    Supply v. C & G Enters., Inc., 
    212 F.3d 14
    , 17–18 (1st Cir.
    2000)). The district court rejected Colonial’s proposed
    interpretation, under which the last labor performed or
    materials supplied before the April 26 date of the Corps’
    termination letter triggered the statute of limitations.
    Id. at 111–12.
    The court reasoned that the “relevant contract” under
    § 3133(b)(1) was “the subcontract — the contract that
    9
    obligated the prime contractor to secure a bond under Section
    3131.”
    Id. at 111.
    Upon reviewing conflicting evidence and
    making credibility determinations, the court found that ACC
    last worked on the Project on May 1, 2013. Hirani II, 345 F.
    Supp. 3d at 31, ⁋⁋ 101–02. Therefore, ACC’s Miller Act claim
    was timely because it was filed on April 29, 2014, which was
    within a year of when ACC last furnished labor and materials
    for the Project.
    Id. at 43.
    B.
    On appeal, Colonial renews its position, contending that
    the district court misinterpreted when the Miller Act’s statute
    of limitations is triggered. Because the one year limitations
    period begins to run on the last day that the subcontractor
    carried out work provided for in the bonded contract, Colonial
    maintains that cannot be after the bonded contract (here, the
    Prime Contract) has been terminated and so ACC’s suit was
    untimely. In Colonial’s view, ACC’s last day of work was
    April 26, 2013, the day Colonial asserts that the Corps
    terminated the Prime Contract.           For its part, ACC
    acknowledges, but offers nothing to defend, the district court’s
    interpretation of the Miller Act. Rather than explaining how it
    thinks the statute should be interpreted, ACC contends only
    that Colonial’s position is unsupported, relying primarily on
    the factual argument that the Prime Contract was not
    terminated on April 26.
    “The statute of limitations is an affirmative defense that
    [a] defendant must prove.” Firestone v. Firestone, 
    76 F.3d 1205
    , 1210 (D.C. Cir. 1996). Here, even assuming for the sake
    of argument that Colonial’s interpretation of when the Miller
    Act claim accrues is correct, Colonial has not carried its burden
    to prove that the last day ACC performed labor or supplied
    materials under the Prime Contract was prior to April 29, 2013.
    10
    Contrary to Colonial’s assertion, it is far from “undisputed that
    . . . the Government terminated the Prime Contract on April 26,
    2013.” See Appellants’ Br. at 26. Although the Corps’
    termination letter was indeed dated April 26, that is not the end
    of the inquiry.
    The Federal Acquisition Regulations require that the
    government’s notice of termination include the “effective date
    of termination.” 48 C.F.R. § 49.102(a)(2). The Corps’
    termination purported to be “effective immediately.” See
    Hirani 
    I, 263 F. Supp. 3d at 106
    . The applicable regulations
    provide, however, that “[i]f the contractor receives the
    termination notice after the date fixed for termination, then the
    effective date of termination means the date the contractor
    receives the notice.” 48 C.F.R. § 2.101. The district court
    expressly declined to find when Hirani received the Corps’
    termination letter. See Hirani 
    II, 345 F. Supp. 3d at 30
    , ⁋ 92
    n.5. Not until April 30 did Hirani attempt to reject the Corps’
    termination by letter or ACC learn through its field
    superintendent Hollander that Hirani been terminated. Thus,
    the record is consistent with Hirani having received the
    termination letter — and hence the Prime Contract being
    terminated — on any of the five days spanning April 26 to 30.
    The court need not resolve the disagreement over when
    ACC’s Miller Act claim accrued because, depending on further
    factual findings by the district court upon remand, “[i]f we do
    not decide it now, we may never need to.” Nat’l Treasury
    Emps. Union v. United States, 
    101 F.3d 1423
    , 1431 (D.C. Cir.
    1996); cf. VanderKam v. VanderKam, 
    776 F.3d 883
    , 888–89
    (D.C. Cir. 2015). For instance, if Hirani received the Corps’
    termination letter of Friday, April 26, 2013, on Monday or
    Tuesday, April 29 or 30, and ACC furnished labor or materials
    on those days, then ACC’s lawsuit (which was filed on April
    29 of the following year) is timely regardless whether the
    11
    Miller Act’s statute of limitations is tied to the Prime Contract
    or the Subcontract. On the other hand, if Hirani received the
    termination letter on April 26, 27, or 28, then the interpretation
    of the Miller Act will determine whether ACC’s suit was
    timely. Given that timeliness may turn on the unresolved
    factual questions of when the Prime Contract was terminated
    and whether ACC performed labor or supplied materials on
    that day, the court need not reach a novel issue of statutory
    interpretation. Rather, it suffices to remand the case to the
    district court for additional fact-finding, where Hirani and
    Colonial, as proponents of the statute of limitations defense,
    will bear the burden of showing that Hirani received the
    termination letter before Monday, April 29 or that ACC
    performed no labor and supplied no materials on April 29 and
    30.
    Deferring a decision on the statutory question is
    particularly appropriate given the lack of helpful authority cited
    by the parties. Colonial argues that United States ex rel. T.M.S.
    Mechanical Contractors, Inc. v. Millers Mutual Fire Insurance
    Co. of Texas, 
    942 F.2d 946
    , 953 (5th Cir. 1991), establishes
    that a subcontractor cannot recover on the payment bond for
    work performed after the government terminates the prime
    contract. But the statute of limitations was not at issue in that
    case; instead, that case concerned whether the subcontractor
    could recover on the payment bond for costs it incurred due to
    the termination. See
    id. In addition,
    Colonial relies upon
    United States ex rel. American Bank v. C.I.T. Construction Inc.
    of Texas, 
    944 F.2d 253
    , 256 (5th Cir. 1991), for the proposition
    that the Miller Act cause of action accrued when the prime
    contract was terminated. But in that case, unlike here, the
    government had not terminated the prime contract, and thus the
    discussion of the statute of limitations is dictum having little
    persuasive value. See
    id. Furthermore, in
    a case not cited by
    any party, the Ninth Circuit held that the statute of limitations
    12
    was not triggered until the prime contractor terminated the
    agreement with its subcontractor. See U.S. ex rel. Pippin v. J.R.
    Youngdale Constr. Co., 
    923 F.2d 146
    , 150 (9th Cir. 1991). In
    sum, the authority that the parties have presented to the court
    is of little aid in resolving a novel statutory question.
    Therefore, the court remands the case to the district court
    to make findings of fact as to when the Prime Contract was
    terminated and whether ACC performed labor or supplied
    material on April 29 and/or April 30. In the event that Colonial
    and Hirani cannot meet their burden to show that ACC’s Miller
    Act claim was untimely, then this court can resolve the parties’
    other Miller Act contentions: those by Hirani and Colonial that
    quantum meruit damages were improper, that ACC obtained
    double recovery, and that admitting documents containing
    hearsay was an abuse of discretion, and that by ACC that Ed
    Hollander’s services were compensable. To the contrary, if
    Hirani and Colonial show that termination occurred before
    April 29 or that ACC performed no labor or supplied no
    material on April 29 or 30, the court can then address the Miller
    Act statute of limitations issue.
    III.
    On cross appeal, ACC contends that it was entitled to
    quantum meruit relief totaling more than $2 million against
    Hirani, instead of the restitution damages that the district court
    awarded. The court affirms the award of restitution damages
    to compensate ACC for the services it provided to Hirani.
    Damage awards are “findings of fact governed by Federal
    Rule of Civil Procedure 52(a), which will not be disturbed
    unless clearly erroneous.” Bucheit v. Palestine Liberation
    Org., 
    388 F.3d 346
    , 350 (D.C. Cir. 2004) (internal quotations
    omitted). That said, “an appellate court has the ‘power to
    13
    correct errors of law, including those that may infect a so-called
    mixed finding of law and fact, or a finding of fact that is
    predicated on a misunderstanding of the governing rule of
    law.’” United States v. Castle, 
    825 F.3d 625
    , 635 (D.C. Cir.
    2016) (quoting Bose Corp. v. Consumers Union of
    U.S., Inc., 
    466 U.S. 485
    , 501 (1984)).
    The parties and the district court assumed that District of
    Columbia law applies to ACC’s breach of contract cause of
    action against Hirani, as will this court. Hirani III, 
    2019 WL 162019
    , at *3 n.3; see also Ideal Elec. Sec. Co. v. Int’l Fid. Ins.
    Co., 
    129 F.3d 143
    , 147 (D.C. Cir. 1997). Three terms, as
    defined by D.C. law, are pertinent: quantum meruit, unjust
    enrichment, and restitution. First, “[q]uantum meruit may refer
    to either an implied contractual or a quasi-contractual duty
    requiring compensation for services rendered.” TVL Assocs. v.
    A & M Constr. Corp., 
    474 A.2d 156
    , 159 (D.C. 1984). A
    plaintiff’s “request for quantum meruit . . . is a measure of
    damages and not a legal theory of recovery.” Fred Ezra Co. v.
    Pedas, 
    682 A.2d 173
    , 176 (D.C. 1996) (internal quotation
    omitted). Second, “[u]njust enrichment occurs when a person
    retains a benefit . . . which in justice and equity belongs to
    another.” Harrington v. Trotman, 
    983 A.2d 342
    , 346 (D.C.
    2009) (quoting Jordan Keys & Jessamy, LLP v. St. Paul Fire
    & Marine Ins. Co., 
    870 A.2d 58
    , 63–64 (D.C. 2005)). Unjust
    enrichment is an equitable claim that typically lies when there
    is not a valid contract between the parties. See Falconi-Sachs
    v. LPF Senate Square, LLC, 
    142 A.3d 550
    , 556 (D.C. 2016);
    see also In re APA Assessment Fee Litig., 
    766 F.3d 39
    , 45–46
    (D.C. Cir. 2014). Third, “[a]lthough the phrases restitution
    and quantum meruit are sometimes used interchangeably in
    regard to the measure of recovery, since both refer to unjust
    enrichment, restitution is properly limited to recovery where
    there is an express contract.” Lee v. Foote, 
    481 A.2d 484
    , 486
    n.4 (D.C. 1984). “[A]n action for restitution is an alternative
    14
    remedy to an action for damages when there has been a
    repudiation or material breach of the contract.” Ingber v. Ross,
    
    479 A.2d 1256
    , 1263 (D.C. 1984). Thus, “[r]estitution is
    available [under D.C. law] for partial performance by a
    plaintiff of services under an express contract which has been
    breached by a defendant.” 
    Lee, 481 A.2d at 486
    ; see also
    
    Harrington, 983 A.2d at 347
    –48.
    ACC contends that the district court “ignored the election
    made by ACC to seek restitution (quantum meruit) based on
    the reasonable value of the performance without regard to the
    limitations of the contract.” Appellee’s Br. at 67. It relies on
    W.F. Magann Corp. v. Diamond Manufacturing Co., 
    775 F.2d 1202
    (4th Cir. 1985), several articles written by its own
    counsel, and, in reply, Blake Construction Co. v. C.J. Coakley
    Co., 
    431 A.2d 569
    (D.C. 1981). ACC does not explain why the
    ability of the subcontractor in W.F. Magann Corp. to recover
    in quantum meruit on its Miller Act claim provides a basis to
    displace the district court’s conclusion that D.C. law does not
    allow ACC to recover in quantum meruit on its contract claim.
    And in Blake, the D.C. Court of Appeals allowed the
    subcontractor to recover damages for delay despite a
    contractual clause prohibiting such damages because the delays
    were due to the contractor’s “active interference” with the
    contract, although the court declined to distinguish between
    contract and quantum meruit theories of recovery because the
    result was the same. Blake Constr. 
    Co., 431 A.2d at 578
    –79,
    579 n.8. Here, by contrast, ACC points to no finding of active
    interference and, more fundamentally, the theories lead to
    different amounts of damages. In short, ACC has not provided
    the court with any basis to deviate from the principle of D.C.
    law that restitution, not quantum meruit, is the proper remedy
    where there is an express contract between the parties. See 
    Lee, 481 A.2d at 486
    . The court therefore affirms the district court’s
    award of contract damages against Hirani.
    15
    Accordingly, the court remands the case to the district
    court for additional fact-finding on ACC’s Miller Act claim
    against Colonial, affirms the restitution damages award against
    Hirani on ACC’s contract claim, and defers addressing other
    issues raised by the parties.