In re: Public Employees for Environmental Responsibility ( 2020 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued December 9, 2019                  Decided May 1, 2020
    No. 19-1044
    IN RE: PUBLIC EMPLOYEES FOR ENVIRONMENTAL
    RESPONSIBILITY AND HAWAII COALITION MALAMA PONO,
    PETITIONERS
    On Petition for Writ of Mandamus
    Paula N. Dinerstein argued the cause and filed the briefs
    for petitioners.
    Eric Grant, Deputy Assistant Attorney General, U.S.
    Department of Justice, argued the cause for respondents. With
    him on the brief were Jeffrey Bossert Clark, Assistant Attorney
    General, Andrew C. Mergen and Ellen Durkee, Attorneys, and
    Catherine Basic, Attorney, Federal Aviation Administration.
    Before: HENDERSON, TATEL, and GRIFFITH, Circuit
    Judges.
    Opinion for the Court filed by Circuit Judge GRIFFITH.
    GRIFFITH, Circuit Judge: This case arises out of the
    underwhelming—and ultimately unsuccessful—efforts of the
    Federal Aviation Authority (FAA) and National Park Service
    (NPS) to regulate commercial sightseeing flights over national
    parks. The Air Tour Management Act of 2000 directs the FAA
    2
    and NPS to “make every effort” to establish rules governing
    such flights within two years of the first application. Although
    applications have been pending at twenty-five parks for nearly
    two decades, the agencies have fulfilled their statutory mandate
    at only two. Petitioners seek a writ of mandamus to compel the
    agencies to regulate air tours at seven parks where they have
    injured members. Because the agencies have failed to timely
    do so, we grant the petition.
    I
    A
    The Air Tour Management Act of 2000 requires vendors
    who wish to conduct commercial air tours over certain national
    parks and tribal lands to first obtain a permit from the FAA. See
    Pub. L. No. 106-181, §§ 801-809, 
    114 Stat. 61
    , 185-94
    (codified as amended at 
    49 U.S.C. § 40128
     and note). The Act
    provides that the FAA, “in cooperation with” the NPS, “shall
    establish an air tour management plan . . . whenever a person
    applies for authority to conduct a commercial air tour
    operation.” 
    49 U.S.C. § 40128
    (b)(1)(A). Management plans
    must go through notice and comment and comply with the
    National Environmental Policy Act (NEPA). See 
    id.
    § 40128(b)(2), (b)(4)(B). Management plans may “prohibit”
    air tours entirely or place certain conditions on them, such as
    “maximum or minimum altitudes,” “time-of-day restrictions,”
    “maximum number of flights per unit of time,” and “mitigation
    of noise, visual, or other impacts.” Id. § 40128(b)(3)(A)-(B).
    Congress directed the agencies to act with dispatch. The
    Act provides that the FAA “shall make every effort to act on
    [an] application . . . and issue a decision . . . not later than 24
    months after it is received or amended.” Id. § 40128(a)(2)(E).
    But because Congress recognized that this process couldn’t be
    3
    completed overnight, the Act also allowed the FAA to grant
    “interim operating authority,” id. § 40128(c)(1), (c)(3), to
    existing tour operators so they “would not be put out of
    business,” Notice of Final Opinion on the Transferability of
    Interim Operating Authority Under the National Parks Air Tour
    Management Act, 
    72 Fed. Reg. 6,802
    , 6,803 (Feb. 13, 2007).
    The agencies’ efforts to comply with the Act got off to a
    promising start. In 2000, they established the National Park
    Overflights Advisory Group, and by 2002, they had published
    a rule defining “commercial air tour operations” and launching
    a permit application system. See National Parks Air Tour
    Management, 
    67 Fed. Reg. 65,662
     (Oct. 25, 2002). But trouble
    began to brew when the agencies started to respond to the
    operators’ applications. Each agency prioritized different goals
    and sought to retain as much control over the process as
    possible. See Lusk Decl. ¶ 45; Trevino Decl. ¶¶ 21-24. The
    FAA emphasized air traffic safety; the NPS, protecting park
    resources and visitor experience. As a result, the agencies
    bickered over everything from responsibility for making
    certain NEPA determinations to the proper metric for
    measuring baseline noise levels. For example, the NPS “sought
    sole jurisdiction” over environmental “impact determinations
    on park resources,” but the FAA refused to “abdicat[e]” its role
    in that process or defer to the “park superintendent’s
    professional judgment.” Lusk Decl. ¶ 45. “The inability to
    resolve these issues” often brought “work to a standstill.” 
    Id.
    To be sure, the agencies kept busy. Despite their
    infighting, they took steps to establish management plans at
    sixteen parks, holding stakeholder meetings, drafting
    documents, and conducting noise studies. But because the
    agencies “were never able to resolve a number” of their
    squabbles, 
    id.,
     they never got “beyond [the] initial stages of
    environmental review” at any park, Gov’t Br. 11, and “never
    4
    issued a draft [management plan or] NEPA document . . . for
    public review and comment,” Lusk Decl. ¶ 45.
    Twelve years passed, and the agencies still hadn’t come up
    with a single management plan. In an effort to speed things up,
    Congress amended the Act to exempt parks with fifty or fewer
    air tours per year and permit the agencies to enter into voluntary
    agreements in lieu of management plans. See FAA
    Modernization and Reform Act of 2012, Pub. L. No. 112-95,
    § 501, 
    126 Stat. 11
    , 100-03 (codified at 
    49 U.S.C. § 40128
    (b)(7)). Voluntary agreements are more flexible and
    easier to implement. The agencies need not jump through as
    many procedural hoops to create them, as they aren’t subject to
    NEPA and don’t require full-dress notice and comment. 
    49 U.S.C. § 40128
    (b)(7)(C). But there’s a catch—voluntary
    agreements must be, well, voluntary. Unlike management
    plans, voluntary agreements can’t be imposed without operator
    approval. What’s more, to substitute for a management plan,
    the voluntary agreement must be unanimous; all operators
    possessing interim operating authority must sign on. 
    Id.
    § 40128(b)(7)(A). A single holdout can force the agencies back
    to the drawing board.
    After Congress amended the Act, the agencies agreed to
    put management plans on the back burner and focus their
    efforts on voluntary agreements. They anticipated that these
    agreements would be easier to complete, and they were right—
    to some extent.
    In 2015 and 2016, the agencies finalized voluntary
    agreements with the air tour operators at Big Cypress National
    Preserve and Biscayne National Park, bringing these parks into
    compliance with the Act. But the statutory fix was no magic
    bullet. Getting air tour operators to sign on to voluntary
    agreements without the credible threat of a management plan
    5
    proved difficult. Each operator gains a competitive advantage
    by hanging on to their (largely unregulated) interim authority
    while their rivals voluntarily accept restrictions. See Sauvajot
    Decl. ¶ 7; Trevino Decl. ¶¶ 47-48. Unable to credibly threaten
    holdouts with the prospect of a stricter management plan, the
    agencies lack the necessary leverage to bring everyone to the
    table. For example, although the agencies drafted partial
    agreements for Glen Canyon National Recreation Area and
    Rainbow Bridge National Monument, those agreements don’t
    yet pass muster under the Act because two of the nine operators
    have refused to join. Still, the agencies have pressed on. They
    are currently working on voluntary agreements for Badlands
    National Park and Mount Rushmore National Memorial.
    B
    In 2018, Public Employees for Environmental
    Responsibility and the Hawaii Island Malama Pono
    Coalition—organizations      representing   national    park
    employees, visitors, and hiking guides—filed a petition for a
    writ of mandamus that would compel the agencies to establish
    management plans or voluntary agreements within two years at
    seven parks: Bryce Canyon National Park, Glacier National
    Park, Great Smoky Mountains National Park, Haleakala
    National Park, Hawaii Volcanoes National Park, Lake Mead
    National Recreation Area, and Muir Woods National
    Monument.* We dismissed that petition for lack of Article III
    standing because it listed only the FAA as respondent and
    *
    The agencies inform us that Muir Woods National Monument is
    now exempt from the Act’s requirements because it has fewer than
    fifty overflights per year and the NPS hasn’t exercised its statutory
    authority to withdraw that exemption. See Gov’t 28(j) Letter (Dec.
    4, 2019); 
    49 U.S.C. § 40128
    (a)(5)(A)-(B). Thus, we do not include
    it in the relief afforded here.
    6
    Petitioners’ injuries weren’t redressable by the FAA alone. See
    In re Pub. Emps. for Envtl. Responsibility, No. 18-1044 (D.C.
    Cir. Nov. 13, 2018) (per curiam). Petitioners’ new filing, which
    names both the FAA and NPS as respondents, does not suffer
    from this jurisdictional defect.
    In response to this litigation, the agencies produced a
    schedule for bringing into compliance one park named in the
    petition and six other parks. This plan sets target dates for
    establishing voluntary agreements at Badlands National Park,
    Great Smoky Mountains National Park, Mount Rainier
    National Park, and Mount Rushmore National Memorial,
    ranging from January 31, 2020 to March 31, 2022. If the
    agencies can’t produce unanimous voluntary agreements at
    those parks within eighteen months, the plan calls for the
    agencies to develop management plans. The plan also calls for
    the agencies to establish management plans at Death Valley
    National Park, Glen Canyon National Recreation Area, and
    Rainbow Bridge National Monument by May 31, 2022 at the
    latest. The agencies have not offered a proposed timeline for
    Petitioners’ other parks but pledge they will “begin preparatory
    work in additional parks on a rolling basis.” Savaujot Suppl.
    Decl. ¶ 24.
    II
    Before addressing the merits of the petition, we must first
    assess our jurisdiction.
    A
    Our court has exclusive jurisdiction over mandamus
    petitions alleging unreasonable agency delay whenever a
    statute commits review of the relevant action to the courts of
    appeals. See Telecomms. Research & Action Ctr. v. FCC
    7
    (TRAC), 
    750 F.2d 70
    , 75 (D.C. Cir. 1984) (explaining that this
    statutory commitment of review, “read in conjunction with the
    All Writs Act,” gives this court jurisdiction); see also 
    28 U.S.C. § 1651
     (All Writs Act). The courts of appeals have exclusive
    jurisdiction to review the FAA’s management plans and
    voluntary agreements, including any predicate environmental
    determinations by the NPS. See 
    49 U.S.C. §§ 40128
    (b)(5),
    46110(a); cf. City of Tacoma v. FERC, 
    460 F.3d 53
    , 76 (D.C.
    Cir. 2006) (holding that a challenge to a FERC order gave us
    jurisdiction to review a predicate biological opinion prepared
    by another agency). Accordingly, we have jurisdiction over this
    mandamus petition under the All Writs Act.
    B
    Petitioners assert associational standing to seek relief.
    “[A]n association has standing to bring suit on behalf of its
    members when: (a) its members would otherwise have standing
    to sue in their own right; (b) the interests it seeks to protect are
    germane to the organization’s purpose; and (c) neither the
    claim asserted nor the relief requested requires the participation
    of individual members in the lawsuit.” Hunt v. Wash. State
    Apple Advert. Comm’n, 
    432 U.S. 333
    , 343 (1977). The
    agencies do not dispute, and we agree, that Petitioners satisfy
    the second and third elements. However, the agencies question
    whether Petitioners satisfy the first element. They do.
    To establish standing to sue in their own right, Petitioners’
    members must show injury in fact, causation, and
    redressability. See Susan B. Anthony List v. Driehaus, 
    573 U.S. 149
    , 157-58 (2014). Petitioners’ members include frequent
    hikers, whose enjoyment of the woods is marred by the
    intrusive noise of overflights. See, e.g., Contreras Decl. ¶¶ 6-7;
    Hingson Decl. ¶¶ 5-9; Plakanis Decl. ¶¶ 3-10. This is a
    cognizable aesthetic and recreational injury. See Friends of the
    8
    Earth, Inc. v. Laidlaw Envtl. Servs. (TOC), Inc., 
    528 U.S. 167
    ,
    183 (2000). It is caused by the agencies’ failure to regulate air
    tours and could be redressed by a grant of mandamus relief.
    The agencies raise two objections to redressability, but
    neither is persuasive. First, the agencies object that “there is no
    guarantee that air tour impacts would be reduced with the
    implementation of plans or voluntary agreements.” Gov’t Br.
    18. But Petitioners need not show that relief is “certain,” Int’l
    Ladies’ Garment Workers’ Union v. Donovan, 
    722 F.2d 795
    ,
    811 (D.C. Cir. 1983) (internal quotation marks omitted), only
    that it is “substantial[ly] likel[y],” Vt. Agency of Nat. Res. v.
    U.S. ex rel. Stevens, 
    529 U.S. 765
    , 771 (2000) (internal
    quotation marks omitted). Management plans may prohibit air
    tours altogether or establish certain conditions, including noise
    mitigation, 
    49 U.S.C. § 40128
    (b)(3)(A)-(B), and plans “shall
    include incentives . . . for the adoption of quiet aircraft
    technology,”      
    id.
        § 40128(b)(3)(D);      see     also     id.
    § 40128(b)(7)(B) (similar for voluntary agreements). Plans and
    agreements are thus substantially likely to mitigate the noise
    impact of air tours.
    Second, the agencies object that Petitioners’ injuries aren’t
    redressable because the agencies haven’t violated a
    nondiscretionary duty, so mandamus relief is inappropriate.
    See Gov’t Br. 18-22. But that argument confuses standing with
    the merits, which we address next. See Consol. Edison Co. of
    N.Y. v. Ashcroft, 
    286 F.3d 600
    , 604-06 (D.C. Cir. 2002)
    (finding standing but denying mandamus relief on the merits).
    III
    “Our consideration of any and all mandamus actions starts
    from the premise that issuance of the writ is an extraordinary
    remedy, reserved only for the most transparent violations of a
    9
    clear duty to act.” In re Bluewater Network, 
    234 F.3d 1305
    ,
    1315 (D.C. Cir. 2000). This is the rare case in which mandamus
    relief is appropriate. For nineteen years, the agencies have
    failed to comply with their statutory mandate despite
    Congress’s command to “make every effort” to do so within
    two years of an application. 
    49 U.S.C. § 40128
    (a)(2)(E). And
    the agencies’ latest proposed schedule is too little, too late. At
    some point, promises are not enough; judicial intervention is
    needed.
    A
    Before granting mandamus relief, we must “satisfy
    ourselves that the agenc[ies] ha[ve] a duty to act.” In re Am.
    Rivers & Idaho Rivers United, 
    372 F.3d 413
    , 418 (D.C. Cir.
    2004). The agencies argue that they do not. In their view,
    “completion of a management plan [or voluntary agreement] is
    not a ministerial, clear-cut, or non-discretionary duty” because
    they must exercise their “discretion” over “the environmental
    analyses and action [that they] will approve.” Gov’t Br. 20.
    This argument confuses the creation of the plans with their
    content. While the latter may be discretionary, the former is
    not. As the agencies concede, “the Air Tour Management Act
    generally requires [the] establishment of plans or voluntary
    agreements for non-exempt parks.” 
    Id.
     (emphasis added). The
    Act provides that the agencies “shall establish an air tour
    management plan . . . whenever a person applies for authority
    to conduct a commercial air tour operation.” 
    49 U.S.C. § 40128
    (b)(1)(A) (emphasis added). The agencies may not
    ignore this clear command. Petitioners do not seek to control
    the content of the plans; they “simply seek[] to compel the
    [agencies] to make decisions within the statutory time frames.”
    10
    Am. Hosp. Ass’n v. Burwell, 
    812 F.3d 183
    , 191 (D.C. Cir.
    2016). That is an appropriate subject for mandamus relief.
    B
    In evaluating a petition for mandamus relief based on
    unreasonable agency delay, we consider six factors:
    (1) the time agencies take to make decisions must be
    governed by a rule of reason; (2) where Congress has
    provided a timetable or other indication of the speed with
    which it expects the agency to proceed in the enabling
    statute, that statutory scheme may supply content for this
    rule of reason; (3) delays that might be reasonable in the
    sphere of economic regulation are less tolerable when
    human health and welfare are at stake; (4) the court should
    consider the effect of expediting delayed action on agency
    activities of a higher or competing priority; (5) the court
    should also take into account the nature and extent of the
    interests prejudiced by delay; and (6) the court need not
    find any impropriety lurking behind agency lassitude in
    order to hold that agency action is unreasonably delayed.
    TRAC, 
    750 F.2d at 80
     (internal citations and quotation marks
    omitted). No one factor is determinative, and “[e]ach case must
    be analyzed according to its own unique circumstances.” Air
    Line Pilots Ass’n, Int’l v. Civil Aeronautics Bd., 
    750 F.2d 81
    ,
    86 (D.C. Cir. 1984). Our analysis of the six TRAC factors
    convinces us mandamus relief is warranted.
    1
    The majority of the TRAC factors favor granting relief.
    Time is “[t]he first and most important factor.” In re Core
    Communications, Inc., 
    531 F.3d 849
    , 855 (D.C. Cir. 2008). The
    11
    Act directs the agencies to “make every effort” to rule on
    applications within two years, 
    49 U.S.C. § 40128
    (a)(2)(E), but
    after nineteen, the agencies have little to show for their labors.
    Although “[t]here is no per se rule as to how long is too long,”
    a “reasonable time for agency action is typically counted in
    weeks or months, not years.” In re Am. Rivers, 
    372 F.3d at 419
    (internal quotation marks omitted); see also Midwest Gas
    Users Ass’n v. FERC, 
    833 F.2d 341
    , 359 (D.C. Cir. 1987) (“[A]
    reasonable time for an agency decision could encompass
    months, occasionally a year or two, but not several years or a
    decade.” (internal quotation marks omitted)). Indeed, we have
    found far shorter delays than nineteen years to be “nothing less
    than egregious.” In re Am. Rivers, 
    372 F.3d at 419
     (six years);
    see also In re Bluewater Network, 
    234 F.3d at 1316
     (nine
    years); Air Line Pilots Ass’n, 750 F.2d at 85-86 (five years); cf.
    Nader v. FCC, 
    520 F.2d 182
    , 206 (D.C. Cir. 1975) (“[N]ine
    years should be enough time for any agency to decide almost
    any issue.” (citation omitted)).
    The agencies argue that the Act’s timeline is aspirational.
    See Gov’t Br. 23-25. But even the lack of a hard deadline “does
    not give government officials carte blanche to ignore their legal
    obligations.” Cobell v. Norton, 
    240 F.3d 1081
    , 1096 (D.C. Cir.
    2001). Although the Act does not impose a rigid schedule, it
    provides a ruler against which the agencies’ progress must be
    measured. And that progress simply doesn’t measure up.
    The agencies further insist that their task is complicated
    and time intensive. See Gov’t Br. 28-29. Of course, a
    reasonable time for action depends on “the complexity of the
    task at hand, the significance (and permanence) of the outcome,
    and the resources available to the agency.” Mashpee
    Wampanoag Tribal Council, Inc. v. Norton, 
    336 F.3d 1094
    ,
    1102 (D.C. Cir. 2003). But the failure to meet the timeline in
    this case is primarily attributable to interagency conflict, not
    12
    financial or personnel shortages. Mandamus relief can’t make
    money grow on trees, but it can end an interagency turf war.
    Most of the remaining TRAC factors either favor granting
    relief or are neutral. “[T]ak[ing] into account the nature and
    extent of the interests prejudiced by delay,” 750 F.2d at 80, we
    note that park visitors are among the Act’s intended
    beneficiaries and the ones most harmed by the agencies’ listless
    pace. Granting relief will aid these visitors by reducing the
    disruptive impacts of air tours. See 
    49 U.S.C. § 40128
    (b)(1)(B)
    (stating that an “objective of any air tour management plan”
    should be to mitigate “adverse impacts” on “visitor
    experiences”). Moreover, “delays that might be reasonable in
    the sphere of economic regulation are less tolerable when
    human health and welfare are at stake.” TRAC, 750 F.2d at 80.
    Though this is not a case where inaction risks life and limb, see
    Pub. Citizen Health Research Grp. v. Auchter, 
    702 F.2d 1150
    ,
    1157 (D.C. Cir. 1983), the agencies’ failure to regulate air tours
    harms visitor welfare to some extent by exposing visitors to
    unmitigated noise pollution, see H.R. REP. NO. 106-167, at 95
    (1999) (noting that the FAA has “responsibility for . . .
    protecting the public health and welfare from aircraft noise.”).
    Thus, these factors are at least neutral toward Petitioners.
    2
    Only one TRAC factor—competing agency priorities—
    seems to favor the agencies. Precedent directs us to “consider
    the effect of expediting delayed action on agency activities of
    a higher or competing priority.” TRAC, 750 F.2d at 80. The
    agencies argue that (1) regulating commercial air tours is only
    one “small component” of their missions, which must compete
    for resources with other projects; and (2) we should not upset
    the agencies’ newly proposed schedule, which prioritizes some
    parks over others. Gov’t Br. 29-31.
    13
    But the agencies’ competing obligations cannot justify
    their nineteen-year holdup. See Cobell, 
    240 F.3d at 1097
    (“[N]either a lack of sufficient funds nor administrative
    complexity, in and of themselves, justify extensive delay.”).
    Although we appreciate that it may be difficult for the agencies
    to complete management plans or voluntary agreements at all
    of the outstanding parks in the two years that Petitioners
    request, that doesn’t make mandamus relief inappropriate.
    Recognizing that the agencies have legitimate resource-based
    concerns, we order the agencies to propose a schedule for
    bringing all parks into compliance. In crafting this schedule,
    the agencies should bear in mind that Congress expected them
    to complete the task in two years.
    Moreover, while we will not grant mandamus relief that
    serves only to put the petitioner “at the head of the queue”
    while “mov[ing] all others back one space,” In re Barr
    Laboratories, Inc., 
    930 F.2d 72
    , 75 (D.C. Cir. 1991), we need
    not reorder the agencies’ priorities to grant relief here.
    Petitioners “are not asking to jump the line.” Oral Arg. Tr.
    13:6-7. By ordering the agencies to produce a schedule, we do
    not require them to address any particular park first. The
    agencies remain free to choose the order, provided they bring
    all parks into compliance within a reasonable timeframe.
    Finally, the agencies implore us to allow them to try out
    their new plan before granting mandamus relief. Had the
    agencies submitted a plan imposing reasonable deadlines for
    all parks, we might agree. But they did not. The agencies’ plan
    covers only seven of the twenty-three outstanding parks. And
    while many of these parks have partial voluntary agreements
    or low levels of air tours, the agencies still anticipate that their
    plan will take up to four years to complete. That is too long.
    14
    In any event, the agencies have already missed some of the
    target dates they’ve set for themselves. For example, the
    agencies promised to publish final voluntary agreements with
    fixed-wing operators at Badlands National Park and Mount
    Rushmore National Memorial by January 31, 2020. Sauvajot
    Supp. Decl. ¶¶ 15, 17. It’s now May, and the agencies still have
    not published either agreement. See National Park Units
    Requiring      Air    Tour     Management      Plans,      FAA,
    https://www.faa.gov/about/office_org/headquarters_offices/ar
    c/programs/air_tour_management_plan/park_specific_plans;
    see also Gov’t 28(j) Letter (Dec. 6, 2019) (explaining that the
    agencies were also “unable to meet [their] target” for
    publishing “notices of draft voluntary agreements” at these
    parks). If the agencies can’t stick to their own plan with the
    threat of judicial supervision hanging over them, how can we
    expect them to do so when the threat is gone?
    IV
    Left to their own devices, the agencies have failed to
    comply with their statutory mandate for the past nineteen years.
    Accordingly, we grant the petition for a writ of mandamus and
    order the agencies to produce a schedule within 120 days of the
    issuance of this opinion for bringing all twenty-three parks into
    compliance. See In re United Mine Workers of Am. Int’l Union,
    
    190 F.3d 545
    , 554-56 (D.C. Cir. 1999) (ordering an agency to
    produce a schedule in response to a mandamus petition and
    retaining jurisdiction); MCI Telecomms. Corp. v. FCC, 
    627 F.2d 322
    , 343-46 (D.C. Cir. 1980) (same); Nader, 
    520 F.2d at 207
     (same).
    We fully expect that the agencies will make every effort to
    produce a plan that will enable them to complete the task within
    two years, as Congress directed. If the agencies anticipate that
    15
    it will take them more than two years, they must offer specific,
    concrete reasons for why that is so in their proposal.
    The court will retain jurisdiction to approve the plan and
    monitor the agencies’ progress. After the plan is approved, the
    agencies are directed to submit updates on their progress every
    ninety days until their statutory obligations are fulfilled.
    So ordered.