PSEG Energy Resources & Trade LLC v. Federal Energy Regulatory Commission , 665 F.3d 203 ( 2011 )


Menu:
  • United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued September 22, 2011          Decided December 23, 2011
    No. 10-1103
    PSEG ENERGY RESOURCES & TRADE LLC AND PSEG POWER
    CONNECTICUT LLC,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    ISO NEW ENGLAND INC., ET AL.,
    INTERVENORS
    On Petition for Review of Orders of
    the Federal Energy Regulatory Commission
    John Lee Shepherd, Jr. argued the cause for petitioner.
    With him on the briefs were Kenneth R. Carretta and Sally
    Brown Richardson.
    Jennifer S. Amerkhail, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With her on the
    brief was Robert H. Solomon, Solicitor.
    Kerim P. May and Sherry A. Quirk were on the brief for
    intervenor ISO New England Inc.
    2
    John S. Wright and Michael C. Wertheimer, Assistant
    Attorneys General, Office of the Attorney General for the State
    of Connecticut, and Joseph A. Rosenthal and Randall L. Speck
    were on the brief for intervenors George C. Jepsen, Attorney
    General, et al.
    Before: GARLAND and KAVANAUGH, Circuit Judges, and
    WILLIAMS, Senior Circuit Judge.
    Opinion for the Court filed by Circuit Judge GARLAND.
    GARLAND, Circuit Judge: In this petition for review, PSEG
    Energy Resources & Trade LLC and PSEG Power Connecticut
    LLC (collectively, PSEG) challenge orders of the Federal
    Energy Regulatory Commission (FERC) accepting the results of
    an auction for electric generation capacity conducted by ISO
    New England Inc. In those orders, FERC approved ISO New
    England’s determination that, unlike other resources in the
    region, PSEG’s resources in Connecticut could not reduce their
    capacity supply obligation because doing so would endanger the
    system’s reliability. Importantly, it also held that ISO New
    England could reduce the per unit price paid to PSEG for that
    capacity. Because the latter holding was based on tariff
    provisions that the Commission thought were clear but now
    concedes are ambiguous, and because in the course of
    construing those provisions it failed to respond to PSEG’s
    facially legitimate objections, we grant the petition and remand
    the orders for further consideration.
    I
    PSEG is one of many generators that participate in New
    England’s “forward capacity market.” In this market, electricity
    providers purchase from generators options to buy quantities of
    3
    energy three years in advance. NRG Power Mktg., LLC v. Me.
    Pub. Utils. Comm’n, 
    130 S. Ct. 693
    , 697 (2010). In setting
    prices, the market eschews the traditional regulatory approach,
    which sets utility rates based on the cost of production, in favor
    of an auction. Managing the auction is the responsibility of ISO
    New England, which is a “‘private, non-profit entity [that]
    administer[s] New England energy markets and operate[s] the
    region’s bulk power transmission system.’” Blumenthal v.
    FERC, 
    552 F.3d 875
    , 878 (D.C. Cir. 2009) (quoting NSTAR
    Elec. & Gas Corp. v. FERC, 
    481 F.3d 794
    , 796 (D.C. Cir.
    2007)). ISO New England’s tariff implements the market’s
    auction mechanism, which originated in a FERC-approved
    settlement among more than 100 stakeholders. See Blumenthal,
    
    552 F.3d at 879
    ; ISO New England Inc., 
    119 FERC ¶ 61,045
    ,
    61,162 (2007).
    Under the settlement and tariff, a descending auction sets
    the price that capacity suppliers like PSEG receive. The basic
    mechanism is straightforward. After the auctioneer, ISO New
    England, announces a starting price, suppliers respond with bids
    for how much capacity they are willing to provide at that price.
    The auctioneer gradually reduces the price, and suppliers reduce
    their capacity bids accordingly. The auction ends when the
    suppliers’ bids just equal the amount of capacity that ISO New
    England has determined to be necessary to maintain the
    reliability of the regional system. This amount is known as the
    “installed capacity requirement,” or ICR. Each supplier is then
    committed to provide capacity equal to its bid. See Conn. Dep’t
    of Pub. Util. Control v. FERC, 
    569 F.3d 477
    , 480 (D.C. Cir.
    2009).
    But the forward capacity market has a twist: a price floor
    that halts the auction if the floor is reached. The problem is that
    the auction may reach the price floor at a point where the
    suppliers’ capacity bids still exceed the ICR; hence, absent
    4
    correction, purchasers would end up buying too much power.
    The capacity market’s solution is proration. The basic idea is
    that each supplier has its capacity obligation, and the payment
    it receives, reduced proportionally. The Proration Rule of ISO
    New England’s tariff implements this solution in a somewhat
    roundabout way. See Tariff § III.13.2.7.3(b) (J.A. 178); infra
    note 1. Although the rule’s full complexity need not detain us,
    the key mechanism is as follows: the rule calculates the “total
    payment cap” by multiplying the floor price by the ICR, then
    proportionately reduces the amount each supplier receives so
    that the total does not exceed the cap (“price proration”), and
    then gives each supplier the option to reduce its capacity
    obligation an equivalent amount (“quantity proration”). For
    example, if the ICR were 50 units, and two suppliers each bid 30
    units at a floor price of $1, the total payment cap would be $50.
    Each supplier would receive a proportionate amount of $25
    (price proration), and each could then reduce its capacity
    obligation to 25 units (quantity proration).
    In 2007, without specific comment, FERC approved ISO
    New England’s addition of the following caveat as a new last
    sentence of the Proration Rule: “Any proration shall be subject
    to reliability review.” Tariff § III.13.2.7.3(b); see ISO New
    England Inc., 
    122 FERC ¶ 61,016
    , 61,049 (2008); see also ISO
    New England Inc., FERC No. ER07-1388, Various Revisions to
    FCM Rules, attach. 1 at 1st Rev. Sheet No. 7314Q (Aug. 31,
    2007) (J.A. 239). This case is about the meaning of that caveat.
    In ISO New England’s view, it means that when it determines
    that a supplier’s resources are needed for local reliability, it can
    bar quantity proration but force the supplier to accept price
    proration. Thus, the supplier is effectively required to accept a
    per unit price lower than the floor price. In the example above,
    this would require a supplier to provide the full 30 units but still
    accept only $25, an effective price of $0.83 per unit rather than
    $1.00. PSEG -- whose attempt to prorate the capacity of its
    5
    Connecticut resources was barred as a consequence of the
    reliability review for the 2008 New England auction -- believes
    that it should receive the full (unprorated) floor price for all its
    resources that it could not prorate. In the example above that
    would be $30, which PSEG says cashes out to an extra $2.8
    million in this case.1
    1
    The full Proration Rule, with the reliability caveat italicized,
    states as follows:
    The Capacity Clearing Price shall not fall below 0.6 times
    CONE [Cost of New Entry]. Where the Capacity Clearing
    Price reaches 0.6 times CONE, offers shall be prorated such
    that no more than the Installed Capacity Requirement is
    procured in the Forward Capacity Auction, as follows: the
    total payment to all listed capacity resources during the
    associated Capacity Commitment Period shall be equal to
    0.6 times CONE times the Installed Capacity Requirement
    applicable in the Forward Capacity Auction. Payments to
    individual listed resources shall be prorated based on the
    total number of MWs [megawatts] of capacity clearing in
    the Forward Capacity Auction (receiving a Capacity Supply
    Obligation for the associated Capacity Commitment Period).
    Suppliers may instead prorate their bid MWs of
    participation in the Forward Capacity Market by partially
    de-listing one or more resources (e.g., proration may be
    done by reducing, through bilateral contracts, the capacity
    of one resource by the amount equal to the entire prorated
    amount of the Market Participant). Regardless of any such
    proration, the full amount of capacity that cleared in the
    Forward Capacity Auction will be ineligible for treatment as
    new capacity in subsequent Forward Capacity Auctions
    (except as provided under Section III.13.1.1.1.2). Any
    proration shall be subject to reliability review.
    Tariff § III.13.2.7.3(b) (J.A. 178) (emphasis added).
    6
    PSEG filed its objections with FERC, which must review
    and approve ISO New England’s auction results under the
    settlement and § 205 of the Federal Power Act (FPA), 16 U.S.C.
    § 824d(d). See Devon Power LLC, 
    115 FERC ¶ 61,340
    , 62,309
    (2006). After FERC sided with ISO New England, see ISO New
    England Inc., 
    123 FERC ¶ 61,290
    , 62,925 (2008) [hereinafter
    Initial Order], PSEG sought rehearing. In its rehearing request,
    PSEG contended that FERC’s interpretation, in addition to
    violating the tariff’s express terms, resulted in “undue
    discrimination” against the resources most necessary for
    reliability, by paying them less per unit than resources that were
    permitted to prorate quantity. PSEG also argued that FERC’s
    interpretation contradicted what PSEG contended were the
    forward capacity market’s “basic policy goals”: to provide
    incentives for existing resources to remain in, and for new
    resources to be constructed in, areas subject to resource
    constraints. Request for Rehearing at 3, 9-11 (July 21, 2008)
    (J.A. 104, 110-12).
    On rehearing, FERC again rejected PSEG’s interpretation.
    ISO New England Inc., 
    130 FERC ¶ 61,235
     (2010) [hereinafter
    Rehearing Order]. FERC held that when reliability review
    precludes quantity proration, the tariff still requires ISO New
    England to impose price proration to avoid violating the total
    payment cap, which it regarded as sacrosanct. Rehearing Order,
    130 FERC at 62,147. FERC did note, however, that ISO New
    England and its stakeholders “have made a filing with the
    Commission that may result in revised market rules on this
    issue.” 
    Id.
     And so it did: less than a month later, FERC
    approved a revision to the Proration Rule that adopted PSEG’s
    position -- for prospective application only. FERC “agree[d]
    that this proposed solution is an improvement and addresses an
    inconsistency between the compensation provided to resources
    that are denied the ability to prorate megawatts at the price floor
    and other cleared capacity.” ISO New England Inc., 
    131 FERC
                                7
    ¶ 61,065, 61,345 (2010). Meanwhile, PSEG petitioned for
    review of FERC’s orders, which had denied PSEG’s request for
    relief in the instant case.
    II
    Under § 313(b) of the FPA, 16 U.S.C. § 825l(b), we have
    jurisdiction to review FERC’s orders, which we assess to
    determine whether they are “arbitrary, capricious, an abuse of
    discretion, or otherwise not in accordance with law.” 
    5 U.S.C. § 706
    (2)(A); see TNA Merchant Projects, Inc. v. FERC, 
    616 F.3d 588
    , 591 (D.C. Cir. 2010). To survive this review, FERC
    “must ‘examine the relevant data and articulate a satisfactory
    explanation for its action including a rational connection
    between the facts found and the choice made.’” PPL
    Wallingford Energy LLC v. FERC, 
    419 F.3d 1194
    , 1198 (D.C.
    Cir. 2005) (quoting Motor Vehicle Mfrs. Ass’n of the United
    States, Inc. v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43
    (1983)). Among other things, “[a]n agency’s ‘failure to respond
    meaningfully’ to objections raised by a party renders its decision
    arbitrary and capricious.” 
    Id.
     (quoting Canadian Ass’n of
    Petroleum Producers v. FERC, 
    254 F.3d 289
    , 299 (D.C. Cir.
    2001)).
    In reviewing FERC’s tariff interpretation, we use “a
    two-step, Chevron-like analysis.” Colorado Interstate Gas Co.
    v. FERC, 
    599 F.3d 698
    , 701 (D.C. Cir. 2010) (citing Old
    Dominion Elec. Coop., Inc. v. FERC, 
    518 F.3d 43
    , 48 (D.C. Cir.
    2008)). At step 1, “[w]e first ‘consider de novo whether the
    [tariff] unambiguously addresses the matter at issue. If so, the
    language . . . controls for we must give effect to the
    unambiguously expressed intent of the parties.’” 
    Id.
     (quoting
    Ameren Servs. Co. v. FERC, 
    330 F.3d 494
    , 498 (D.C. Cir.
    2003)). At step 2, “‘[i]f the tariff language is ambiguous, we
    defer to the Commission’s construction of the provision at issue
    8
    so long as that construction is reasonable.’” 
    Id.
     (quoting Koch
    Gateway Pipeline Co. v. FERC, 
    136 F.3d 810
    , 814-15 (D.C. Cir.
    1998)). See generally Chevron U.S.A. Inc. v. Natural Res. Def.
    Council, Inc., 
    467 U.S. 837
     (1984).
    According to FERC’s Rehearing Order, the last sentence of
    the Proration Rule, “[a]ny proration shall be subject to reliability
    review,” allows ISO New England to bar resources from
    reducing their capacity obligation, yet still requires them to
    accept a prorated price. The Commission stated its view that the
    total payment cap provision of the Proration Order is inviolate,
    even during reliability review, and that paying resources that
    were precluded from prorating quantity at the unprorated floor
    price could violate that cap. Rehearing Order, 130 FERC at
    62,147. PSEG raises a host of arguments challenging this
    interpretation. But it also argues (1) that FERC wrongly read
    the tariff’s text as compelling the conclusion FERC reached, and
    (2) that FERC wrongly failed to respond to its discrimination
    and policy arguments. Because we agree with these latter two
    points, we need not address PSEG’s other arguments.
    1. In rejecting PSEG’s arguments, FERC spoke the
    language of textual clarity. In its Initial Order, FERC explained
    that “the [forward capacity market] rules are clear” that
    resources prevented from prorating quantity must still receive a
    prorated price. Initial Order, 123 FERC at 62,925. And on
    rehearing, FERC declared that “the current tariff language does
    not allow” PSEG’s interpretation. Rehearing Order, 130 FERC
    at 62,147.
    On appeal, however, FERC’s counsel conceded that the
    relevant provision of the Proration Rule is ambiguous. FERC
    Br. 28 (“The final sentence of the Proration Rule . . . is
    ambiguous.”); Oral Arg. Tr. 24 (acknowledgment by FERC
    counsel that the provision is ambiguous); cf. ISO New England
    9
    Br. 14 (“It is necessary to acknowledge that the rule language at
    issue here contains some ambiguity.”). We agree. As FERC’s
    brief acknowledges, the rule’s final sentence “does not explain
    how ISO New England will conduct its review or what the ISO’s
    next step will be if it determines that reliability is in peril.”
    FERC Br. 28. In particular, the rule does not unambiguously
    proclaim FERC’s position that the total payment cap is
    sacrosanct even during reliability review, as compared to
    PSEG’s view that “[a]ny proration shall be subject to reliability
    review” means there should not be “any” proration -- whether of
    quantity or of price -- for any resources that are required to
    preserve system reliability.
    When a text is ambiguous under Chevron step 1, we
    normally proceed to determine whether the agency’s
    interpretation is reasonable under Chevron step 2. But when “an
    agency erroneously contends that Congress’ intent has been
    clearly expressed and has rested on that ground, we remand to
    require the agency to consider the question afresh in light of the
    ambiguity we see.” Cajun Elec. Power Coop., Inc. v. FERC,
    
    924 F.2d 1132
    , 1136 (D.C. Cir. 1991). We do so because, under
    step 2, we examine whether the agency has reasonably exercised
    its discretion. But when the agency’s decision “was not based
    on [its] own judgment but rather on the unjustified assumption
    that it was Congress’ judgment that such [an outcome is]
    desirable or required,” the agency has not exercised that
    discretion at all. Transitional Hospitals Corp. of La., Inc. v.
    Shalala, 
    222 F.3d 1019
    , 1029 (D.C. Cir. 2000) (internal
    quotation marks omitted). The same analysis applies to FERC’s
    interpretation of a tariff. Because “discretion must be exercised
    through the eyes of one who realizes she possesses it,” 
    id.,
     we
    must remand to permit the Commission to determine “whether
    [it] wishes to retain [its interpretation] knowing that other
    options are permissible,” 
    id. at 1021
    .
    10
    Indeed, this is a particularly appropriate case for remand.
    Although FERC denied PSEG the relief it sought, it
    subsequently described the petitioners’ position as “an
    improvement” that “addresses an inconsistency,” and it revised
    the tariff language to make it applicable in future situations. 131
    FERC at 61,345. A remand will permit the Commission to
    determine whether, knowing that it has more discretion than it
    thought it had, PSEG’s position would be an appropriate way to
    interpret the unrevised language as well.
    2. There is a second problem with FERC’s orders.
    “‘[U]nless the [agency] answers objections that on their face
    seem legitimate, its decision can hardly be classified as
    reasoned.’” PPL Wallingford, 419 F.3d at 1198 (quoting
    Canadian Ass’n, 
    254 F.3d at 299
    ). This applies as strongly to
    agency interpretations under Chevron step 2 as to other agency
    actions. TNA, 
    616 F.3d at 593
    ; see NorAm Gas Transmission
    Co. v. FERC, 
    148 F.3d 1158
    , 1165 (D.C. Cir. 1998).
    PSEG raised two such objections below. First, PSEG
    argued that FERC’s interpretation would result in “undue
    discrimination” because “some resources will involuntarily be
    paid less than other resources” on a per unit basis. Rehearing
    Request at 9-10 (J.A. 110-11). “[M]oreover, the resources
    receiving the lower unit payments are located in the regions
    where the megawatts make the largest contribution to system
    reliability.” Id. at 10 (J.A. 111).2 Second, PSEG contended that
    2
    Before the Commission, it was not clear whether PSEG’s “undue
    discrimination” argument was a reference to § 205 of the FPA, which
    prohibits public utilities from (inter alia) “subject[ing] any person to
    any undue prejudice or disadvantage” or “maintain[ing] any
    unreasonable difference in rates,” 16 U.S.C. § 824d(b), or whether it
    was simply an appeal to policy or fairness as a guide in reading the
    11
    FERC’s interpretation was “inconsistent with the fundamental
    policy goals” of the forward capacity market. Id. In PSEG’s
    view, those goals were “to provide incentives for existing
    resources to remain in constrained areas and for new entry
    resources to be constructed in those areas.” The goals were
    undermined, PSEG maintained, by an interpretation that barred
    such resources from receiving the floor price when they were
    not permitted to prorate quantity. Id. at 11 (J.A. 112).
    As these are “objections that on their face seem legitimate,”
    the Commission was required to answer them.                 PPL
    Wallingford, 419 F.3d at 1198. Yet, it did not do so. It is true,
    as FERC’s counsel pointed out, that the Commission noted the
    objections and -- without more -- characterized them as “more
    broadly” supporting PSEG’s position. Rehearing Order, 130
    FERC at 62,146. To characterize objections, however, is not to
    answer them.
    Counsel for FERC also contended that the Commission
    effectively responded to these objections by referencing two
    other proceedings that, in counsel’s view, were where “the
    discrimination and equity claims . . . more properly [should have
    been] raised.” FERC Br. 32-33. The first was the 2007
    proceeding in which FERC had accepted the addition of the
    “reliability review” language; the second was the parallel
    stakeholder process for changing the market rules prospectively.
    Although we doubt that either of those proceedings could have
    rendered PSEG’s instant filing untimely or an impermissible
    collateral attack,3 the important point is that the Commission
    tariff. Either way, as we discuss in the following text, FERC erred in
    failing to respond to it.
    3
    As to the 2007 proceeding, when an agency interprets an existing
    rule in a new way (or for the first time), a challenge constitutes an
    12
    itself -- as distinguished from its appellate counsel -- never
    suggested that they did. “We, of course, ‘cannot accept
    appellate counsel’s post hoc rationalizations for agency action.’”
    TNA, 
    616 F.3d at 593
     (quoting Fed. Power Comm’n v. Texaco,
    Inc., 
    417 U.S. 380
    , 397 (1974)). Rather, “an agency’s order
    must be upheld, if at all, ‘on the same basis articulated in the
    order by the agency itself.’” 
    Id.
     (quoting Texaco, 
    417 U.S. at 397
    ).
    The same problem bars our reliance on another argument of
    appellate counsel. In FERC’s brief, counsel called our attention
    to a footnote in the Rehearing Order, which states that the
    purpose of the Proration Rule’s price floor is to “‘ensure relative
    market stability during the initial years of the Forward Capacity
    Market.’” FERC Br. 31 (quoting Rehearing Order, 130 FERC
    at 62,147 n.40). But once again, the order does nothing more
    than make the quoted statement; it does not suggest that -- let
    alone explain how -- it was a response to PSEG’s undue
    discrimination or policy arguments. On remand, FERC must
    respond to both.
    impermissible collateral attack “only if a reasonable firm . . . would
    have perceived a very substantial risk that the [provision] meant what
    [the agency] now says it meant.” Dynergy Midwest Generation, Inc.
    v. FERC, 
    633 F.3d 1122
    , 1126 (D.C. Cir. 2011) (internal quotation
    marks omitted). Given the Proration Rule’s conceded ambiguity, it is
    unlikely that PSEG’s challenge meets this standard. As to the
    stakeholder proceeding, it was concerned only with prospective
    revision, an outcome that could not remedy the $2.8 million loss that
    PSEG alleges was caused by the orders under review.
    13
    III
    For the foregoing reasons, the petition for review is granted,
    and FERC’s orders are remanded for further proceedings
    consistent with this opinion.
    So ordered.
    

Document Info

Docket Number: 10-1103

Citation Numbers: 398 U.S. App. D.C. 423, 665 F.3d 203

Judges: Garland, Kavanaugh, Williams

Filed Date: 12/23/2011

Precedential Status: Precedential

Modified Date: 8/5/2023

Authorities (16)

Colorado Interstate Gas Co. v. FERC , 599 F.3d 698 ( 2010 )

Transtn Hosp Corp LA v. Shalala, Donna E. , 222 F.3d 1019 ( 2000 )

Connecticut Department of Public Utility Control v. Federal ... , 569 F.3d 477 ( 2009 )

NSTAR Electric & Gas Corp. v. Federal Energy Regulatory ... , 481 F.3d 794 ( 2007 )

NorAm Gas Transmission Co. v. Federal Energy Regulatory ... , 148 F.3d 1158 ( 1998 )

Ameren Services Co. v. Federal Energy Regulatory Commission , 330 F.3d 494 ( 2003 )

Blumenthal v. Federal Energy Regulatory Commission , 552 F.3d 875 ( 2009 )

Dynegy Midwest Generation, Inc. v. Federal Energy ... , 633 F.3d 1122 ( 2011 )

canadian-association-of-petroleum-producers-v-federal-energy-regulatory , 254 F.3d 289 ( 2001 )

TNA Merchant Projects, Inc. v. Federal Energy Regulatory ... , 616 F.3d 588 ( 2010 )

cajun-electric-power-cooperative-inc-v-federal-energy-regulatory , 924 F.2d 1132 ( 1991 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... , 103 S. Ct. 2856 ( 1983 )

Old Dominion Electric Cooperative, Inc. v. Federal Energy ... , 518 F.3d 43 ( 2008 )

Federal Power Commission v. Texaco Inc. , 94 S. Ct. 2315 ( 1974 )

NRG Power Marketing, LLC v. Maine Public Utilities ... , 130 S. Ct. 693 ( 2010 )

Chevron U. S. A. Inc. v. Natural Resources Defense Council, ... , 104 S. Ct. 2778 ( 1984 )

View All Authorities »