New England Power Generators Ass'n v. Federal Energy Regulatory Commission , 707 F.3d 364 ( 2013 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued November 15, 2012           Decided February 15, 2013
    No. 11-1422
    NEW ENGLAND POWER GENERATORS ASSOCIATION, INC.,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    GEORGE JEPSEN, ATTORNEY GENERAL FOR THE STATE OF
    CONNECTICUT, ET AL.,
    INTERVENORS
    Consolidated with 11-1465
    On Petitions for Review of Orders of
    the Federal Energy Regulatory Commission
    John Lee Shepherd argued the cause for petitioner New
    England Power Generators Association, Inc. With him on the
    briefs was John N. Estes III. Paul F. Wight entered an
    appearance.
    John S. Wright, Assistant Attorney General, Office of the
    Attorney General for the State of Connecticut, argued the cause
    for State Petitioners. With him on the briefs were Michael C.
    2
    Wertheimer, Assistant Attorney General, Jesse S. Reyes,
    Assistant Attorney General, Office of the Attorney General for
    the Commonwealth of Massachusetts, and Lisa Fink.
    Robert H. Solomon, Solicitor, Federal Energy Regulatory
    Commission, argued the cause for respondent. With him on
    the brief was Lona T. Perry, Senior Attorney.
    Before: TATEL, BROWN, and GRIFFITH, Circuit Judges.
    BROWN, Circuit Judge: The Federal Energy Regulatory
    Commission must ensure the rates charged for electric
    generation capacity are “just and reasonable.” Federal Power
    Act (FPA) § 205(a), 16 U.S.C. § 824d(a). Until recently, only
    two types of rates were involved: tariff rates and contract rates.
    FERC’s review of tariff rates is subject to considerable
    discretion. On the other hand, unless a contract rate is
    contrary to the public interest, FERC must presume it to be just
    and reasonable under the Mobile-Sierra doctrine, a principle
    that began with two eponymous Supreme Court precedents:
    United Gas Pipe Line Co. v. Mobile Gas Serv. Corp. (Mobile),
    
    350 U.S. 332
     (1956), and Fed. Power Comm’n v. Sierra Pac.
    Power Co. (Sierra), 
    350 U.S. 348
     (1956).
    The debut of capacity auctions poses a new challenge. In
    this case FERC reviewed rates resulting from an auction
    process and concluded that though the rates are not contract
    rates, they warrant the Mobile-Sierra presumption anyway—a
    move that upset two groups of petitioners for opposite reasons.
    The New England Power Generators Association (“NEPGA”)
    likes the result but not the reasoning: it argues the auction
    results, as contract rates, must receive the Mobile-Sierra
    presumption. Another group, comprising the Maine Public
    Utilities Commission and the Attorneys General of
    Massachusetts and Connecticut (collectively, the “State
    3
    Petitioners”), supports much of FERC’s reasoning but not the
    result: they contend that because the auction results are not
    contract rates, FERC cannot presume them just and reasonable.
    We dismiss NEPGA’s petition for lack of standing and deny
    the State Petitioners’ petition on the merits.
    I
    A
    Regulated energy suppliers file compilations of their rate
    schedules, called “tariffs,” with FERC. See Morgan Stanley
    Capital Grp., Inc. v. Pub. Util. Dist. No. 1 of Snohomish Cnty.,
    
    554 U.S. 527
    , 531 (2008). Suppliers must abide by these
    tariffs when providing service to electricity purchasers, though
    they may change their tariffs if they afford FERC advance
    notice. See 16 U.S.C. § 824d(c), (d); Morgan Stanley, 
    554 U.S. at 531
    . Along with the unilateral filing of tariffs, the
    FPA also allows suppliers to set rates with individual
    purchasers via bilateral contract, though these contracts must
    also be filed with FERC before going into effect. See Morgan
    Stanley, 
    554 U.S. at 531
    . All rates, whether determined by
    tariff or contract, must be “just and reasonable.” 16 U.S.C. §
    824d(a). This standard entitles FERC to some discretion, and
    the agency “traditionally reviewed and set tariff rates under the
    ‘cost-of-service’ method, which ensures that a seller of
    electricity recovers its costs plus a rate of return sufficient to
    attract necessary capital.” Morgan Stanley, 
    554 U.S. at 532
    .
    Though bilateral contracts and unilateral tariffs offer
    separate methods of rate-setting, a seller cannot abrogate a
    contract rate simply by filing a new tariff with FERC. See
    Mobile, 
    350 U.S. at
    336–37. Nor may FERC conclude a new
    tariff supersedes a contract rate just because the latter would
    not qualify as “just and reasonable” under the cost-of-service
    4
    method; rather, FERC, pursuant to the Mobile-Sierra doctrine,
    may only upset such a contractually determined rate when “the
    rate is so low as to adversely affect the public interest—as
    where it might impair the financial ability of the public utility
    to continue its service, cast upon other consumers an excessive
    burden, or be unduly discriminatory.” Sierra, 
    350 U.S. at 355
    ; see also Morgan Stanley, 
    554 U.S. at
    533–35.
    B
    We adopt the facts as previously summarized in NRG
    Power Mktg., LLC v. Me. Pub. Utils. Comm’n, 
    130 S. Ct. 693
    (2010), and Me. Pub. Utils. Comm’n v. FERC (“MPUC I”),
    
    520 F.3d 464
     (D.C. Cir. 2008) (per curiam):
    In capacity markets, transmission providers pay
    generators for the option to buy a quantum of power rather than
    directly purchasing wholesale electricity. NRG, 
    130 S. Ct. at 697
    . As a failsafe, transmission providers typically purchase
    more capacity than necessary to satisfy expected demand. 
    Id.
    That way, if a spike in demand occurs, customers will not
    experience a power interruption.
    For some time, the situation in New England proved
    precarious, with capacity supplies only barely satisfying
    regional demand. 
    Id.
     To mitigate this predicament, several
    generators sought to enter into “reliability must-run” contracts
    with the New England Independent System Operator (“ISO”).1
    1
    An ISO is an independent company that “assume[s] operational
    control—but not ownership—of the transmission facilities owned by
    its member utilities . . . . [and] provide[s] open access to the regional
    transmission system to all electricity generators at rates established
    in a single, unbundled, grid-wide tariff that applies to all eligible
    users in a non-discriminatory manner.” Midwest ISO Transmission
    5
    These contracts would allow generators to recover their full
    cost of service as a means of guaranteeing their continued
    operation in areas suffering from supply shortages. See
    Devon Power LLC, 
    103 FERC ¶ 61,082
    , 61,266–68 (2003).
    FERC denied the generators’ request, limiting recovery to
    certain maintenance costs going forward. Id. at 61,266.
    FERC also directed the ISO to file a mechanism for setting
    different prices for separate subregions within New England
    depending on their capacity needs. See id. at 61,271. The
    ISO response met with some opposition, and FERC instituted
    proceedings for the parties to negotiate a settlement. See
    Devon Power LLC, 
    113 FERC ¶ 61,075
    , 61,271–72 (2005).
    A settlement agreement endorsed by all but 8 of the 115
    negotiating parties was filed in March 2006, and FERC
    adopted it. See Devon Power LLC, 
    115 FERC ¶ 61,340
    ,
    62,304, 62,306 (2006).
    Central to the settlement agreement is the “Forward
    Capacity Auction,” at which generators commit themselves to
    selling a certain amount of capacity at a particular price three
    years in advance. Id. at 62,306. The Forward Capacity
    Auction is a “descending clock auction,” in which the ISO,
    after announcing a starting price, gradually reduces its offered
    price until the capacity bids equal the amount the ISO
    determined is necessary to guarantee grid reliability. See id.
    at 62,306–07; see also PSEG Energy Res. & Trade LLC v.
    FERC, 
    665 F.3d 203
    , 206 (D.C. Cir. 2011). Transmission
    providers such as public utilities ultimately purchase the
    capacity, paying for a portion of the capacity proportionate to
    their peak loads, though transmission providers may also
    self-supply to meet their capacity obligations. Devon Power
    LLC, 115 FERC at 62,307. The settlement agreement also
    Owners v. FERC, 
    373 F.3d 1361
    , 1364 (D.C. Cir. 2004) (internal
    quotation marks omitted).
    6
    prescribed “separate but simultaneous auctions” for different
    subregions based on their unique capacity needs. 2 
    Id.
    Additionally, the settlement specified challenges to the rates
    set by the Forward Capacity Auction would be reviewed under
    Mobile-Sierra’s public interest standard, “whether the change
    is proposed by a Settling Party, a non-Settling Party, or the
    FERC acting sua sponte.” Id. at 62,333. Several objectors to
    the settlement agreement petitioned this Court for review of
    FERC’s decision.       Concluding that “the Mobile–Sierra
    doctrine is designed to ensure contract stability as between the
    contracting parties—i.e., to make it more difficult for either
    party to shirk its contractual obligations,” we held the
    settlement’s Mobile-Sierra provision inapplicable to
    noncontracting third parties. See MPUC I, 520 F.3d at 479.
    The Supreme Court reversed, however, and explained that
    Mobile-Sierra’s animating purpose—the promotion of stable
    energy supply arrangements—required application of the
    public interest standard to both contracting parties and third
    parties. See NRG, 
    130 S. Ct. at
    700–01. Rejecting an
    interpretation of Mobile-Sierra as merely an application of
    contract law, the Court wondered, “[I]f FERC itself must
    presume just and reasonable a contract rate resulting from fair,
    arms-length negotiations, how can it be maintained that
    noncontracting parties nevertheless may escape that
    presumption?” 
    Id. at 700
    . After holding the Mobile-Sierra
    presumption applicable to any party challenging a contract
    rate, the Supreme Court noted uncertainty as to whether the
    prices set by the Forward Capacity Auctions were in fact
    contract rates and remanded the case. See 
    id. at 701
    . With
    2
    Though no longer relevant in this case, because the auctions were
    set to be conducted three years before the capacity would be needed,
    a fixed payment schedule governed this initial transition period.
    See Me. Pub. Utils. Comm’n v. FERC (“MPUC II”), 
    625 F.3d 754
    ,
    757 n.1 (D.C. Cir. 2010).
    7
    the case once again before our court, FERC’s counsel declared
    that the Forward Capacity Auctions did not actually produce
    contract rates, but that the agency nevertheless had discretion
    to cloak the auction rates in Mobile-Sierra’s public interest
    mantle. See MPUC II, 
    625 F.3d at 759
    . We concluded
    FERC failed to articulate a justification for this position in the
    underlying orders and returned the case to the agency to afford
    an opportunity to address the question. 
    Id.
     at 759–60; see SEC
    v. Chenery Corp., 
    318 U.S. 80
    , 88 (1943).
    On remand, FERC endorsed the position its counsel had
    already adopted: the Forward Capacity Auction rates were not
    technically contract rates for the purpose of Mobile-Sierra, but
    because they “possess certain characteristics of contracts,” the
    agency would, as an exercise of its discretion, enforce the
    settlement agreement’s provision calling for application of the
    public interest standard when reviewing the rates. Devon
    Power LLC, 
    134 FERC ¶ 61,208
    , 62,044 (2011); see also
    Devon Power LLC, 
    137 FERC ¶ 61,073
     (2011) (Order
    Denying Rehearing). This decision appears to have satisfied
    no one.
    II
    FERC did not challenge NEPGA’s standing to bring this
    petition, but because Article III standing is a prerequisite to a
    federal court’s exercise of jurisdiction, we are obliged to raise
    the issue even when the parties do not. Am. Library Ass’n v.
    FCC, 
    401 F.3d 489
    , 492 (D.C. Cir. 2005). To have standing, a
    petitioner must, at a constitutional minimum, satisfy three
    requirements: (1) suffer an “injury in fact” that is both
    “concrete and particularized” and “actual or imminent, not
    conjectural or hypothetical”; (2) draw a causal connection
    between the injury and the agency action complained of; and
    (3) seek relief that is likely to redress the injury. Lujan v.
    8
    Defenders of Wildlife, 
    504 U.S. 555
    , 560–61 (1992) (internal
    quotation marks omitted). The injury prong is missing here.
    NEPGA may have preferred FERC’s wholehearted
    endorsement of the Forward Capacity Auction rates as contract
    rates, but its desired outcome—application of Mobile-Sierra’s
    public interest standard—has already been achieved. That
    FERC may one day attempt to alter its position is insufficient
    injury to NEPGA now, for neither a FERC decision’s legal
    reasoning nor the precedential effect of such reasoning confers
    standing unless the substance of the decision itself gives rise to
    an injury in fact. See Wis. Pub. Power Inc. v. FERC, 
    493 F.3d 239
    , 268 (D.C. Cir. 2007) (per curiam). We have recognized
    an exception to this principle under certain narrow
    circumstances where “the petitioner is not merely quibbling
    over the agency’s rationale in a case in which it has prevailed”
    but is instead arguing the agency “lacked jurisdiction even to
    consider this type of case.” Int’l Bhd. of Elec. Workers v. ICC,
    
    862 F.2d 330
    , 334 (D.C. Cir. 1988). This, however, is not
    such a case: the precedent going forward—that Mobile-Sierra
    applies to the Forward Capacity Auction rates—is precisely the
    outcome NEPGA desires. NEPGA simply wishes FERC had
    been more definitive in its support for this result.
    NEPGA offers a number of theories, all too hypothetical
    to support standing. First, NEPGA claims FERC’s decision
    “will increase suppliers’ costs of capital because ‘uncertainties
    regarding rate stability and contract sanctity can have a chilling
    effect on investments.’” NEPGA Br. 16 (quoting Morgan
    Stanley, 
    554 U.S. at 551
    . The argument is unavailing. In
    essence, NEPGA’s challenge to the orders is predicated not on
    any injury legitimately traceable to the order, but on the
    potential for FERC to issue future, contrary orders. And in
    any event, broad-based market effects stemming from
    regulatory uncertainty are quintessentially conjectural, and it is
    9
    difficult to imagine a FERC action that would not confer
    standing under this theory. See Shell Oil Co. v. FERC, 
    47 F.3d 1186
    , 1202 (D.C. Cir. 1995) (rejecting a party’s attempt to
    establish standing based on a conceivable yet “hypothetical”
    scenario involving future business relations).
    NEPGA has cited no factual support for its claim of
    economic harm, nor has it sought to supplement the record.
    See Sierra Club v. EPA, 
    292 F.3d 895
    , 900 (D.C. Cir. 2002)
    (“When the petitioner’s standing is not self-evident . . . the
    petitioner must supplement the record to the extent necessary
    to explain and substantiate its entitlement to judicial review.”).
    That is not to say the impact of an agency decision on a
    company’s ability to raise capital is never sufficient to ground
    standing. But that impact must be concrete, tethered to
    something more than the possibility an agency may one day
    reverse its position. Cf. CNG Transmission Corp. v. FERC,
    
    40 F.3d 1289
    , 1293 (D.C. Cir. 1994) (finding injury where
    FERC’s decision required the petitioner “to record a $7.1
    million loss in its 1993 financial statements, adversely
    affecting the company’s bottom line, reducing the earnings
    available for dividend payments and investment, and damaging
    the company’s standing in the financial markets by reducing
    company value and making it more difficult (and more costly)
    to raise capital.”). It would be a strange thing indeed if
    uncertainty were a sufficiently certain harm to constitute an
    injury in fact.
    Next, NEPGA complains the FERC orders “deny market
    participants their long-recognized right to determine for
    themselves the standard of review that will apply to their
    commercial arrangements.” NEPGA Br. 16. This is an
    argument on the merits, not a basis for standing. Missing here
    is an explanation of how the supposed alteration to existing
    doctrine has in fact injured NEPGA.
    10
    Finally, NEPGA asserts that FERC’s decision “voids the
    fundamental concomitant rights of contract holders to sue on
    the contract, either at FERC for jurisdictional claims or in the
    courts for other claims, and to enforce their claims in
    bankruptcy courts.” NEPGA Br. 16–17 (internal citations
    omitted). Aside from the fact that a regulatory decision’s
    precedential effect does not confer standing, NEPGA
    exaggerates the impact of FERC’s orders. That FERC has
    decided the auction rates are not contract rates for
    Mobile-Sierra purposes does not, of its own force, foreclose
    any contract or bankruptcy claim NEPGA’s members may one
    day choose to bring. To bolster its point, NEPGA cites
    Consumers Energy Co. v. FERC, 
    428 F.3d 1065
     (D.C. Cir.
    2005), but while that case also involved issues related to
    standing and contracts, the similarities to NEPGA’s
    circumstances end there. In Consumers Energy Co., we held
    that a petitioner could have standing to challenge an agency
    decision concerning another party when, because of a private
    contractual relationship, the petitioner’s interests were directly
    implicated by that decision. See 
    id. at 1069
    . The case said
    nothing of a party’s standing to challenge an agency decision
    because it expressed doubt as to the existence of an underlying
    contract.
    NEPGA’s asserted injuries are overly speculative and so
    inadequate to establish standing.       We therefore lack
    jurisdiction to review NEPGA’s petition and must dismiss it.
    III
    Agreeing with FERC that the Forward Capacity Auction
    results are not contract rates, the State Petitioners nevertheless
    object to FERC’s decision to review the rates under
    Mobile-Sierra’s public interest standard. Assuming, without
    11
    deciding, that the auction rates are not contract rates, we
    conclude the State Petitioners are wrong. Their argument
    boils down to a single misconception: because the existence of
    a contract rate mandates application of the Mobile-Sierra
    presumption, the absence of a contract rate precludes it. An
    example of the logical fallacy “denying the antecedent,”3 the
    State Petitioners’ reasoning is invalid.
    As the Supreme Court has clarified, Mobile-Sierra’s
    public interest standard is an instance of (rather than an
    exception to) the FPA’s just and reasonable standard.
    Morgan Stanley, 
    554 U.S. at 545
    . Application of public
    interest review is simply one method by which FERC may
    assure itself a rate is just and reasonable, just as the
    cost-of-service method, which the State Petitioners dub
    “ordinary” just and reasonable review, is another. Typically,
    reasonable agency interpretations of ambiguous statutory
    terms like “just and reasonable” are already subject to judicial
    deference under the regime set forth in Chevron, U.S.A. Inc. v.
    NRDC, Inc., 
    467 U.S. 837
     (1984). And, just in case there
    existed any uncertainty whether Chevron applied here, the
    Supreme Court has also explained, “The statutory requirement
    that rates be ‘just and reasonable’ is obviously incapable of
    precise judicial definition, and we afford great deference to the
    Commission in its rate decisions. We have repeatedly
    emphasized that the Commission is not bound to any one
    ratemaking formula.” Morgan Stanley, 
    554 U.S. at 532
    (internal citations omitted). In challenging FERC’s decision,
    therefore, the presumption the State Petitioners must rebut is a
    daunting one.
    The only question, then, is whether FERC exceeded the
    bounds of its considerable discretion by adopting the public
    3
    “P ⊃ Q” does not mean “¬P ⊃ ¬Q.”
    12
    interest standard for deciding whether a given Forward
    Capacity Auction rate is just and reasonable. There is no
    reason to believe it has. FERC offered ample reasoning in
    support of its position, recognizing that the auction rates
    exhibit many of the indicia of contract rates: not only did
    FERC conclude the rates “provide a market-based mechanism
    to appropriately value capacity resources based on their
    location,” but, as FERC explained, “rates disciplined by a
    market are consistent with the FPA’s requirements.” Devon
    Power LLC, 134 FERC at ¶ 62,045. Whether the auction
    results are contract rates or not, FERC’s determination that the
    logic of Mobile-Sierra still applied is “a reasonable choice
    within a gap left open by Congress” and so within the purview
    of the agency’s discretion under § 205(a) of the FPA.
    Chevron, 
    467 U.S. at 866
    . We reject the State Petitioners’
    argument to the contrary.
    IV
    Because NEPGA lacks standing, we dismiss its petition
    for review.      Having rejected the merits of the State
    Petitioners’ arguments, we deny their petition for review.
    So ordered.
    

Document Info

Docket Number: 11-1422, 11-1465

Citation Numbers: 404 U.S. App. D.C. 66, 707 F.3d 364

Judges: Brown, Griffith, Tatel

Filed Date: 2/15/2013

Precedential Status: Precedential

Modified Date: 8/6/2023

Authorities (15)

Sierra Club v. Environmental Protection Agency , 292 F.3d 895 ( 2002 )

Midwest Iso Transmission Owners v. Federal Energy ... , 373 F.3d 1361 ( 2004 )

Cng Transmission Corporation v. Federal Energy Regulatory ... , 40 F.3d 1289 ( 1994 )

Maine Public Utilities Commission v. Federal Energy ... , 625 F.3d 754 ( 2010 )

Wisconsin Public Power Inc. v. Federal Energy Regulatory ... , 493 F.3d 239 ( 2007 )

shell-oil-company-shell-pipe-line-corporation-v-federal-energy-regulatory , 47 F.3d 1186 ( 1995 )

Securities & Exchange Commission v. Chenery Corp. , 63 S. Ct. 454 ( 1943 )

international-brotherhood-of-electrical-workers-v-interstate-commerce , 862 F.2d 330 ( 1988 )

Consumers Energy Company v. Federal Energy Regulatory ... , 428 F.3d 1065 ( 2005 )

United Gas Pipe Line Co. v. Mobile Gas Service Corp. , 76 S. Ct. 373 ( 1956 )

Federal Power Commission v. Sierra Pacific Power Co. , 76 S. Ct. 368 ( 1956 )

Lujan v. Defenders of Wildlife , 112 S. Ct. 2130 ( 1992 )

Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. ... , 128 S. Ct. 2733 ( 2008 )

NRG Power Marketing, LLC v. Maine Public Utilities ... , 130 S. Ct. 693 ( 2010 )

Chevron U. S. A. Inc. v. Natural Resources Defense Council, ... , 104 S. Ct. 2778 ( 1984 )

View All Authorities »