Vecinos para el Bienestar de la Comunidad Costera v. FERC ( 2021 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued March 23, 2021                 Decided August 3, 2021
    No. 20-1045
    VECINOS PARA EL BIENESTAR DE LA COMUNIDAD COSTERA , ET
    AL.,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    RIO GRANDE LNG, LLC AND RIO BRAVO PIPELINE COMPANY,
    LLC,
    INTERVENORS
    On Petition for Review of Orders
    of the Federal Energy Regulatory Commission
    Nathan Matthews argued the cause for petitioners. With
    him on the joint briefs were Erin Gaines, Jennifer Richards
    and Gilberto Hinojosa.
    Richard L. Revesz and Jason A. Schwartz were on the
    brief for amicus curiae the Institute for Policy Integrity at
    New York University School of Law in support of petitioners.
    Robert M. Kennedy, Senior Attorney, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With him on the brief were David L. Morenoff, Acting
    General Counsel, and Robert H. Solomon, Solicitor.
    John Longstreth argued the cause for intervenors. With
    him on the joint brief were David L. Wochner, Jeremy C.
    Marwell, Matthew X. Etchemendy, James T. Dawson, James D.
    Seegers, and P. Martin Teague. Jennifer R. Rinker entered an
    appearance.
    Jeffrey R. Holmstead was on the brief for amicus curiae
    Interstate Natural Gas Association of America in support of
    respondent.
    No. 20-1093
    VECINOS PARA EL BIENESTAR DE LA COMUNIDAD COSTERA , ET
    AL.,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    TEXAS LNG BROWNSVILLE LLC,
    INTERVENOR
    Consolidated with 20-1094
    On Petitions for Review of Orders
    of the Federal Energy Regulatory Commission
    Nathan Matthews argued the cause for petitioners. With
    him on the joint briefs were Jennifer Richards and Gilberto
    Hinojosa.
    Scott Ray Ediger, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With him on
    the brief were David L. Morenoff, Acting General Counsel, and
    Robert H. Solomon, Solicitor.
    Mark R. Haskell, Brett A. Snyder, Barry M. Hartman, and
    Sandra E. Safro were on the brief for intervenor Texas LNG
    Brownsville LLC in support of respondent.
    4
    Before: SRINIVASAN , Chief Judge, WILKINS, Circuit
    Judge, and GINSBURG , Senior Circuit Judge.
    Opinion for the Court filed by Circuit Judge WILKINS.
    WILKINS, Circuit Judge: Petitioners seek review of the
    decision by the Federal Energy Regulatory Commission (“the
    Commission”) to authorize the construction and operation of
    three liquified natural gas (“LNG”) export terminals on the
    shores of the Brownsville Shipping Channel in Cameron
    County, Texas, and the construction and operation of two 135-
    mile pipelines that will carry LNG to one of those terminals.
    The petition in No. 20-1045 concerns the Commission’s
    approval of one of the terminals (the “Rio Grande terminal”)
    and the pipelines. The petitions in Nos. 20-1093 and 20-1094
    concern the Commission’s approval of the other two terminals
    (the “Annova terminal” and “Texas terminal,” respectively).
    Petitioners raise several claims under the National
    Environmental Policy Act (“NEPA”), the Administrative
    Procedure Act (“APA”), and the Natural Gas Act (“NGA”). In
    this opinion, we dismiss the petition in No. 20-1093 as moot,
    and grant the other petitions for review with respect to
    Petitioners’ claims that the Commission’s analyses of the
    projects’ impacts on climate change and environmental justice
    communities were deficient under NEPA and the APA, and
    that the Commission failed to justify its determinations of
    public interest and convenience under Sections 3 and 7 of the
    NGA. We remand without vacatur for the Commission to
    remedy those failures. In an accompanying judgment, we deny
    the petitions for review with respect to Petitioners’ remaining
    claims, which we find to be without sufficient merit to warrant
    explication in a published opinion, see, e.g., Greene v. Dalton,
    
    164 F.3d 671
    , 676 (D.C. Cir. 1999).
    5
    I.
    The Commission and the Department of Energy (“the
    Department”) share responsibility for regulating the domestic
    transport and export of LNG. The Department maintains
    exclusive authority over the export of LNG as a commodity.
    
    42 U.S.C. § 7151
    (b). The Department has delegated to the
    Commission the authority to approve or disapprove the siting,
    construction, expansion, or operation of an LNG terminal for
    exporting LNG. U.S. Department of Energy, Delegation Order
    No. 00-004.00A, § 1.21.A (May 16, 2006); cf. 15 U.S.C.
    § 717b(e)(1). Thus, a would-be exporter of LNG must obtain
    authorization from the Department to export LNG and
    authorization from the Commission to construct and operate
    the necessary facilities. Sierra Club v. FERC, 
    827 F.3d 36
    , 41
    (D.C. Cir. 2016). In addition, the NGA requires the
    Commission’s approval for the construction and operation of
    interstate LNG pipelines. 15 U.S.C. § 717f(c)(1)(A).
    Before authorizing the construction and operation of a
    proposed LNG facility or pipeline, the Commission must
    conduct an environmental review under NEPA. See 
    42 U.S.C. § 4332
    (2)(C). Where, as here, the Commission determines that
    approval of an LNG facility or pipeline is a “major Federal
    action[]” that will “significantly affect[] the quality of the
    human environment,” the Commission must prepare a detailed
    Environmental Impact Statement (“EIS”) that addresses (i) the
    environmental impact of the proposed action; (ii) any “adverse
    environmental effects” that “cannot be avoided” if the proposal
    is implemented; (iii) available alternatives to the proposed
    action; (iv) the “relationship between local short-term uses of
    [the] environment and the maintenance and enhancement of
    long-term productivity”; and (v) “any irreversible and
    irretrievable commitments of resources” that “would be
    involved in the proposed action should it be implemented.” 
    Id.
    6
    The purpose of the EIS is to “force[] the agency to take a ‘hard
    look’ at the environmental consequences of its actions,
    including alternatives to its proposed course,” and to “ensure[]
    that these environmental consequences, and the agency’s
    consideration of them, are disclosed to the public.” Sierra Club
    v. FERC, 
    867 F.3d 1357
    , 1367 (D.C. Cir. 2017).
    Apart from NEPA, Executive Order 12,898, § 1-101, 
    59 Fed. Reg. 7,629
     (Feb. 11, 1994), requires that, “[t]o the greatest
    extent practicable and permitted by law,” federal agencies
    “shall make achieving environmental justice part of [their]
    mission by identifying and addressing, as appropriate,
    disproportionately high and adverse human health or
    environmental effects of [their] programs, policies, and
    activities on minority populations and low-income
    populations.” 
    Id.
     To that end, the Order requires federal
    agencies to conduct “environmental justice” analyses by
    “collect[ing], maintain[ing], and analyz[ing] information on
    the race, national origin, income level, and other readily
    accessible and appropriate information for areas surrounding
    facilities or sites expected to have a substantial environmental,
    human health, or economic effect on the surrounding
    populations.” 
    Id.
     § 3-302(b).
    Finally, the NGA requires the Commission to determine
    whether a proposed project comports with the public interest.
    The NGA’s requirements differ depending on whether the
    proposed project is an LNG facility or pipeline. The
    Commission must authorize the construction and operation of
    a proposed LNG facility unless it determines that the facility
    “will not be consistent with the public interest.” 15 U.S.C.
    § 717b(a). By contrast, the Commission may not authorize the
    construction and operation of a proposed interstate LNG
    pipeline unless it determines that the pipeline “is or will be
    7
    required by the present or future public convenience and
    necessity.” Id. § 717f(e).
    II.
    In March 2016, Texas LNG Brownsville LLC (“Texas
    LNG, LLC”) applied to the Commission for authorization to
    construct and operate an LNG export terminal (the “Texas
    terminal”) on a 635-acre site on the northern shore of the
    Brownsville Shipping Channel in Cameron Country, Texas. In
    May 2016, Rio Grande LNG, LLC (“Rio Grande, LLC”)
    applied to the Commission for authorization to construct and
    operate an LNG export terminal (the “Rio Grande terminal”)
    on a 750-acre site on the same shore. Also in May 2016, Rio
    Bravo Pipeline Company (“Rio Bravo Co.”) applied to the
    Commission for authorization to construct and operate a new
    interstate natural gas pipeline system to supply gas to the Rio
    Grande export terminal. (Both Rio Grande, LLC and Rio
    Bravo Co. are wholly-owned subsidiaries of NextDecade LNG,
    LLC, a U.S. energy project development and management
    company.).       In July 2016, Annova LNG Common
    Infrastructure, LLC (“Annova, LLC”) and three affiliate
    entities applied to the Commission for authorization to
    construct and operate an LNG export terminal (the “Annova
    terminal”) on a 731-acre site on the southern shore of the
    Brownsville Shipping Channel. Each company had previously
    received authorization from the Department to export LNG.
    The Commission completed an EIS for each project in the
    spring of 2019 and issued final orders approving the projects
    later that year. See Order Granting Authorization Under
    Section 3 of the Natural Gas Act, 
    169 FERC ¶ 61,130
     (Nov. 22,
    2019) (“Texas Order”); Order Granting Authorizations Under
    Sections 3 and 7 of the Natural Gas Act, 
    169 FERC ¶ 61,131
    (Nov. 22, 2019) (“Rio Grande and Rio Bravo Order”); Order
    8
    Granting Authorizations Under Section 3 of the Natural Gas
    Act, 
    169 FERC ¶ 61,132
     (Nov. 22, 2019) (“Annova Order”).
    Petitioners—residents, environmental groups, and a nearby
    city—intervened in the Commission’s proceedings and timely
    sought rehearing of the orders. In all of their requests for
    rehearing, Petitioners argued that the Commission’s analyses
    of the projects’ ozone emissions and impacts on climate change
    and environmental justice communities were deficient under
    NEPA and the APA, and that the Commission failed to justify
    its determinations of public interest and convenience under
    Sections 3 and 7 of the NGA. In their request for rehearing of
    the Commission’s order authorizing the Rio Grande and Rio
    Bravo projects, Petitioners also argued that the Commission
    violated NEPA by failing to adequately analyze alternative
    project designs.
    The Commission denied Petitioners’ requests for
    rehearing in early 2020. See Order on Rehearing and Stay, 
    170 FERC ¶ 61,046
     (Jan. 23, 2020) (Rio Grande terminal and Rio
    Bravo pipeline system); Order on Rehearing and Stay, 
    170 FERC ¶ 61,139
     (Feb. 21, 2020) (Texas terminal); Order on
    Rehearing and Stay, 
    170 FERC ¶ 61,140
     (Feb. 21, 2020)
    (Annova terminal). Petitioners timely sought review from this
    Court, and Texas LNG, LLC, Rio Grande, LLC, Rio Bravo
    Co., and Annova, LLC intervened as respondents. Prior to oral
    argument, Annova, LLC informed the Commission that it was
    abandoning its project, and sought permission from this Court
    to withdraw as an intervenor, which we granted. Because the
    Annova project will not go forward, we dismiss the petition in
    No. 20-1093 as moot. See, e.g., Oregon v. FERC, 
    636 F.3d 1203
    , 1206 (9th Cir. 2011). We have jurisdiction over the other
    petitions under 15 U.S.C. § 717r(b).
    9
    III.
    In this opinion, we address Petitioners’ claims that the
    Commission’s analyses of the projects’ impacts on climate
    change and environmental justice communities were deficient
    under NEPA and the APA, and that the Commission failed to
    justify its determinations of public interest and convenience
    under Sections 3 and 7 of the NGA.
    A.
    We begin with the Commission’s analyses of the projects’
    greenhouse gas emissions.
    We review an agency’s NEPA analysis under the arbitrary
    and capricious standard of the APA. Nevada v. Dep’t of
    Energy, 
    457 F.3d 78
    , 87 (D.C. Cir. 2006). Our mandate is not
    to “‘flyspeck’ an agency’s environmental analysis,” id. at 93,
    but “simply to ensure that the agency has adequately
    considered and disclosed the environmental impact of its
    actions,” WildEarth Guardians v. Jewell, 
    738 F.3d 298
    , 308
    (D.C. Cir. 2013) (quoting City of Olmsted Falls v. FAA, 
    292 F.3d 261
    , 269 (D.C. Cir. 2002)). “Accordingly, we ask
    whether the agency examined the relevant data and articulated
    a satisfactory explanation for its action, including a rational
    connection between the facts found and the choice made.”
    Birckhead v. FERC, 
    925 F.3d 510
    , 515 (D.C. Cir. 2019) (per
    curiam) (internal quotation marks and alterations omitted)
    (quoting Motor Vehicle Mfrs. Ass’n, Inc. v. State Farm Mut.
    Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983)). We also ask whether
    the agency addressed “opposing viewpoints.” Nevada, 457
    F.3d at 93; cf. 
    40 C.F.R. § 1502.9
    (c) (“At appropriate points in
    the final statement, the agency shall discuss any responsible
    opposing view that was not adequately discussed in the draft
    10
    statement and shall indicate the agency’s response to the issues
    raised.”).
    In its EIS for each project, the Commission quantified the
    greenhouse gas emissions associated with the construction and
    operation of the project, described “existing and potential
    cumulative climate change impacts in the Project area,” No.
    20-1045 J.A. 663 (Rio Grande terminal and Rio Bravo pipeline
    system); No. 20-1094 J.A. 1035 (Texas terminal), and
    explained that “[c]onstruction and operation of the Project
    would increase the atmospheric concentration of [greenhouse
    gases] in combination with past, current, and future emissions
    from all other sources globally and contribute incrementally to
    future climate change impacts,” No. 20-1045 J.A. 664; No. 20-
    1094 J.A. 1036.
    In each EIS, however, the Commission concluded that it
    was “unable to determine the significance of the Project’s
    contribution to climate change.” No. 20-1045 J.A. 665; No.
    20-1094 J.A. 1036. The Commission explained that “there is
    no universally accepted methodology to attribute discrete,
    quantifiable, physical effects on the environment to [the]
    Project’s incremental contribution to [greenhouse gas
    emissions],” and that therefore “it is not currently possible to
    determine localized or regional impacts from [greenhouse gas]
    emissions from the Project.” No. 20-1045 J.A. 664–65; No.
    20-1094 J.A. 1036.
    Petitioners contend that the Commission was required to
    do more. Specifically, Petitioners argue that 
    40 C.F.R. § 1502.21
    (c) (codified at the time the Commission completed
    its EIS’s at 
    40 C.F.R. § 1502.22
    (b)), required the Commission
    to use the “social cost of carbon” protocol or some other
    generally accepted methodology to evaluate the impact of each
    project’s contribution to climate change. That regulation
    11
    provides that “[i]f . . . information relevant to reasonably
    foreseeable significant adverse impacts cannot be obtained . . .
    because the means to obtain it are not known, the agency shall
    include within the environmental impact statement . . . [t]he
    agency’s evaluation of such impacts based upon theoretical
    approaches or research methods generally accepted in the
    scientific community.” 
    40 C.F.R. § 1502.21
    (c). The “social
    cost of carbon” protocol, which Petitioners suggest as one
    generally accepted method for evaluating the significance of
    the projects’ contributions to climate change, is a tool for
    estimating the cost of climate change caused by greenhouse gas
    emissions, developed by a federal interagency working group
    in 2010, and “withdrawn as no longer representative of
    governmental policy” by executive order in 2017. See
    Executive Order 13,783, 
    82 Fed. Reg. 16,093
     (Mar. 28, 2017).
    Petitioners raised their argument concerning 
    40 C.F.R. § 1502.21
    (c) in comments responding to the Commission’s
    draft EIS’s and in their rehearing requests, but the Commission
    at no point addressed the significance of that regulation. The
    Commission did, however, explain that it would not use the
    social cost of carbon protocol for three reasons: (1) no
    consensus exists as to the appropriate discount rate to use for
    analyses spanning multiple generations; (2) the tool does not
    measure the actual incremental impacts of a project on the
    environment; and (3) there are no established criteria
    identifying the monetized values that are to be considered
    “significant” for the purpose of a NEPA analysis. No. 20-1045
    J.A. 158; No. 20-1094 J.A. 710.
    To the extent that the Commission failed to respond to
    Petitioners’ argument that 
    40 C.F.R. § 1502.21
    (c) required it to
    use the social cost of carbon protocol or some other generally
    accepted methodology to assess of the impact of the projects’
    greenhouse gas emissions, we agree with Petitioners that the
    12
    Commission failed to adequately analyze the impact of the
    projects’ greenhouse gas emissions. The regulation appears
    applicable on its face; the Commission determined that the
    projects would “contribute incrementally to future climate
    change impacts,” No. 20-1045 J.A. 664–65; No. 20-1094 J.A.
    1036, but it could not obtain “information relevant to [those]
    impacts . . . because the means to obtain it [were] not known,”
    
    40 C.F.R. § 1502.21
    (c). Therefore, 
    40 C.F.R. § 1502.21
    (c)
    would seem to have required the Commission to “evaluat[e]
    . . . such impacts based upon theoretical approaches or research
    methods generally accepted in the scientific community.” 
    Id.
    § 1502.21(c)(4). Yet the Commission did not discuss, or even
    cite, 
    40 C.F.R. § 1502.21
    (c) in its rehearing order. Nor did it
    do so in its briefing in this case. Nor did it cite any previous
    decision by this Court or the Commission addressing the
    significance of the regulation in any detail. Because the
    Commission failed to respond to significant opposing
    viewpoints concerning the adequacy of its analyses of the
    projects’ greenhouse gas emissions, we find its analyses
    deficient under NEPA and the APA. See, e.g., TransCanada
    Power Mktg. Ltd. v. FERC, 
    811 F.3d 1
    , 12–13 (D.C. Cir. 2015).
    The Commission’s discussion of the social cost of carbon
    protocol does not excuse its failure to address the significance
    of 
    40 C.F.R. § 1502.21
    (c). Although we have previously held
    that the Commission was not required to use the social cost of
    carbon protocol where the Commission gave the same three
    reasons for not using the protocol that it gave in its orders
    denying Petitioners’ rehearing requests, see EarthReports, Inc.
    v. FERC, 
    828 F.3d 949
    , 956 (D.C. Cir. 2016), the petitioners in
    that case presented no argument concerning 
    40 C.F.R. § 1502.21
    (c), and so our decision did not address the
    significance of that regulation to the Commission’s refusal to
    use the social cost of carbon protocol. Moreover, if the
    protocol is a generally accepted method for estimating the
    13
    impact of greenhouse gas emissions—as the Commission has
    previously declined to dispute, see Order Denying Rehearing,
    
    164 FERC ¶ 61,099
    , at *10 (Aug. 10, 2018)—and if
    Petitioners’ reading of 
    40 C.F.R. § 1502.21
    (c) is correct, then
    the Commission may have been obligated to use the social cost
    of carbon protocol in its EIS, notwithstanding its concerns that
    no consensus exists as to an appropriate discount rate, that the
    tool provides a dollar estimate but does not measure the actual
    incremental impacts of a project on the environment, and that
    there are no established criteria for evaluating whether a given
    monetary cost is “significant.” For instance, as Petitioners
    suggest, the Commission might have chosen a discount rate
    according to recommendations by the Office of Management
    and Budget in 2013, see Office of Mgmt. & Budget, Office of
    the President, OMB Circular A–4, at 30–35, or else used a
    range of rates, and articulated its own criteria for assessing the
    significance of the projected costs of the projects’ greenhouse
    gas emissions. Of course, we do not hold that the Commission
    was indeed required to do any of that. But we do hold that the
    Commission was required to address Petitioners’ argument
    concerning the significance of 
    40 C.F.R. § 1502.21
    (c), and that
    its failure to do so rendered its analyses of the projects’
    greenhouse gas emissions deficient. On remand, the
    Commission must explain whether 
    40 C.F.R. § 1502.21
    (c) calls
    for it to apply the social cost of carbon protocol or some other
    analytical framework, as “generally accepted in the scientific
    community” within the meaning of the regulation, and if not,
    why not.
    B.
    We now turn to the Commission’s environmental justice
    analyses.
    14
    Although the executive order requiring agencies to assess
    the environmental effects of their actions on environmental
    justice communities expressly states that it does not create a
    private right to judicial review, Executive Order 12,898, § 6-
    609, 59 Fed. Reg. at 7,632–33, a petitioner may challenge an
    agency’s environmental justice analysis as arbitrary and
    capricious under NEPA and the APA. See Cmtys Against
    Runway Expansion, Inc. v. FAA, 
    355 F.3d 678
    , 689 (D.C. Cir.
    2004).
    To assess the environmental justice impacts of each
    project, the Commission examined the project’s impacts on
    communities in census block groups within a two-mile radius
    of the project site, but not on communities farther afield. The
    Commission found that all communities within those census
    blocks were minority or low-income. No. 20-1045 J.A. 564
    (Rio Grande terminal and Rio Bravo pipeline system); No. 20-
    1094 J.A. 691–92 (Texas terminal). The Commission
    proceeded to examine “whether any of the Project impacts
    would disproportionately affect those communities due to
    factors unique to those populations like inter-related
    ecological, aesthetic, historical, cultural, economic, social, or
    health factors.” No. 20-1045 Resp’t’s Br. at 53 (internal
    quotation marks and alterations omitted) (quoting No. 20-1045
    J.A. 140–42); see also No. 20-1094 Resp’t’s Br. at 44–45.
    Finding the answer to be no, the Commission concluded that
    the Rio Grande terminal and Rio Bravo pipeline system “would
    not have disproportionate adverse effects on minority and low-
    income residents in the area,” No. 20-1045 J.A. 566, and that
    the Texas terminal would have “negligible impacts on
    environmental justice communities,” No. 20-1094 J.A. 968.
    Petitioners argue that the Commission’s decision to
    analyze the projects’ impacts on environmental justice
    communities only in census blocks within two miles of the
    15
    project sites was arbitrary, given its determination that
    environmental effects from the projects would extend well
    beyond two miles from the project sites.
    We agree. When conducting an environmental justice
    analysis, an agency’s delineation of the area potentially
    affected by the project must be “reasonable and adequately
    explained,” Cmtys Against Runway Expansion, 
    355 F.3d at 689
    , and include “a rational connection between the facts found
    and the decision made,” 
    id. at 685
     (quoting State Farm, 
    463 U.S. at 43
    ). Elsewhere in its EIS for each project, the
    Commission determined that the environmental effects of the
    project would extend beyond the census blocks located within
    a two-mile radius of the project site. For instance, the
    Commission determined that impacts on air quality from each
    project could occur within 31 miles. No. 20-1045 J.A. 610; No.
    20-1094 J.A. 1008. The Commission has offered no
    explanation as to why, in light of that finding, it chose to
    delineate the area potentially affected by the projects to include
    only those census blocks within two miles of the project sites
    for the purposes of its environmental justice analyses. Because
    the Commission has offered no “rational connection between
    the facts found and the decision made,” State Farm, 
    463 U.S. at 43
    , we find its decision to analyze the projects’ impacts only
    on communities in census blocks within two miles of the
    project sites to be arbitrary. On remand, the Commission must
    explain why it chose to analyze the projects’ impacts only on
    communities in census blocks within two miles of the project
    sites, or else analyze the projects’ impacts on communities
    within a different radius of each project site. Additionally, it
    must explain whether its finding that “all project-affiliated
    populations are minority or low-income populations,” No. 20-
    1045 J.A. 142; No. 20-1094 J.A. 691–92, is still justified, and,
    if so, whether its conclusion that the projects “would not have
    disproportionate adverse effects on minority and low-income
    16
    residents in the area,” No. 20-1045 J.A. 566; see also No. 20-
    1094 J.A. 968, still holds.
    C.
    Because the Commission’s analyses of the projects’
    impacts on climate change and environmental justice
    communities were deficient, the Commission must also revisit
    its determinations of public interest and convenience under
    Sections 3 and 7 of the NGA.
    We review the Commission’s orders approving LNG
    facilities and pipelines, like its NEPA analyses, under the
    arbitrary and capricious standard of the APA. Minisink
    Residents for Envt’l Pres. & Safety v. FERC, 
    762 F.3d 97
    , 105–
    106 (D.C. Cir. 2014); Midcoast Interstate Transmission, Inc. v.
    FERC, 
    198 F.3d 960
    , 967 (D.C. Cir. 2000). Where the
    Commission rests a decision, at least in part, on an infirm
    ground, we will find the decision arbitrary and capricious.
    Williams Gas Processing-Gulf Coast Co. v. FERC, 
    475 F.3d 319
    , 330 (D.C. Cir. 2006).
    In its orders approving the projects, the Commission
    explained its finding that the pipeline project was “required by
    the present or future public convenience and necessity,” 15
    U.S.C. § 717f(e), and its refusal to find that the LNG facilities
    were “not . . . consistent with the public interest,” Id. § 717b(a),
    by relying on its NEPA analyses of the projects’ impacts on
    climate change and environmental justice communities. In
    each order, the Commission explained that it concluded in its
    EIS that it “could not determine whether a project’s
    contribution to climate change would be significant,” Texas
    Order at 61,857; Rio Grande and Rio Bravo Order at 61,899,
    and that the projects would not disproportionately affect
    environmental justice communities, Texas Order at 61,855;
    17
    Rio Grande and Rio Bravo Order at 61,896–97. In light of “the
    conclusions presented in [each] EIS,” the Commission further
    concluded that the LNG terminals were “not inconsistent with
    the public interest,” and that the pipeline project was “in the
    public convenience and necessity.” Texas Order at 61,860; Rio
    Grande and Rio Bravo Order at 61,903. As explained above,
    the Commission’s NEPA analyses of the projects’ impacts on
    climate change and environmental justice communities were
    deficient under the APA. The Commission’s determinations of
    public interest and convenience under the NGA were therefore
    deficient to the extent that they relied on its NEPA analyses of
    the projects’ impacts on climate change and environmental
    justice communities. See Williams Gas, 
    475 F.3d at 330
    . On
    remand, the Commission must reconsider its determinations of
    public interest and convenience under Sections 3 and 7 of the
    NGA, along with its NEPA analyses of the projects’ impacts
    on climate change and environmental justice communities.
    IV.
    Intervenors argue that the appropriate remedy for any
    agency error in this case is to remand the Commission’s orders
    approving the projects without vacating the orders, because the
    Commission is likely to remedy any deficiencies in its orders
    on remand, and because vacating the orders would imperil
    Intervenors’ ability to obtain funding necessary to complete the
    projects in a timely fashion.
    We agree. “The decision to vacate depends on two factors:
    the likelihood that ‘deficiencies’ in an order can be redressed
    on remand, even if the agency reaches the same result, and the
    ‘disruptive consequences’ of vacatur.” Black Oak Energy, LLC
    v. FERC, 
    725 F.3d 230
    , 244 (D.C. Cir. 2013) (quoting Allied-
    Signal v. Nuclear Regul. Comm’n, 
    988 F.2d 146
    , 150–51 (D.C.
    Cir. 1993)). Here both factors weigh against vacatur. We find
    18
    it reasonably likely that on remand the Commission can redress
    its failure of explanation with regard to its analyses of the
    projects’ impacts on climate change and environmental justice
    communities, and its determinations of public interest and
    convenience under Sections 3 and 7 of the NGA, while
    reaching the same result. See 
    id.
     And we credit Intervenors’
    assertion that vacating the orders would needlessly disrupt
    completion of the projects. We therefore remand to the
    Commission without vacatur for further proceedings
    consistent with this opinion.
    So ordered.