Metso Minerals Inc. v. Terex Corporation , 594 F. App'x 649 ( 2014 )


Menu:
  •        NOTE: This disposition is nonprecedential.
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    METSO MINERALS INC.,
    Plaintiff-Appellant,
    v.
    TEREX CORPORATION,
    Defendant-Appellee,
    AND
    POWERSCREEN INTERNATIONAL
    DISTRIBUTION LIMITED, POWERSCREEN NEW
    YORK, INC., AND EMERALD EQUIPMENT
    SYSTEMS, INC.,
    Defendants.
    ______________________
    2014-1352
    ______________________
    Appeal from the United States District Court for the
    Eastern District of New York in No. 2:06-cv-01446-ADS-
    ETB, Senior Judge Arthur D. Spatt.
    ______________________
    Decided: December 3, 2014
    ______________________
    2                METSO MINERALS INC.   v. TEREX CORPORATION
    MICHAEL C. STUART, Cozen O’Connor, of New York,
    New York, for plaintiff-appellant. With him on the brief
    was LISA A. FERRARI.
    JON R. TREMBATH, Lathrop & Gage LLP, of Denver,
    Colorado, for defendant-appellee. With him on the brief
    were ALLISON S. WALLIN and ALEXANDER C. CLAYDEN.
    ______________________
    Before LOURIE, DYK, and REYNA, Circuit Judges.
    DYK, Circuit Judge.
    Metso Minerals, Inc. (“Metso”) appeals a district court
    award of bond premium costs to defendants Powerscreen
    International Distribution Limited (now known as Terex
    GB Limited), Terex Corporation, Powerscreen New York,
    Inc., and Emerald Equipment Systems, Inc. (collectively,
    “Powerscreen”). Because the award of bond premium
    costs was not precluded by this court’s mandate in the
    prior appeal, and the district court did not abuse its
    discretion in awarding those costs, we affirm.
    BACKGROUND
    The underlying facts of this case are set forth in our
    prior opinion. Metso Minerals, Inc. v. Powerscreen Int’l
    Distribution, Ltd., 526 F. App’x 988 (Fed. Cir. 2013).
    Metso sued Powerscreen alleging infringement of claims
    1, 2, 3, 7, and 9 of 
    U.S. Patent No. 5,577,618
     (“the ’618
    patent”), which is directed to industrial machines known
    as “screeners” which are used to sort rocks and other
    aggregate materials into similarly-sized piles. 
    Id.
     at 990–
    91. On March 3, 2011, the district court entered judg-
    ment of $15.8 million based on the jury verdict. On
    December 8, 2011, the district court doubled the damages
    award to $31.6 million due to willful infringement, and
    also awarded pre- and post-judgment interest to Metso.
    METSO MINERALS INC.   v. TEREX CORPORATION              3
    Powerscreen appealed, filing notices of appeal on
    January 6, 2012. On June 25, 2012, nearly six months
    after the notices of appeal, the district court entered an
    order (the “bond order”) staying execution of the judg-
    ment 1 pending appeal, and provided that “Defendants
    shall file an appeal bond in the amount of $50 million by
    July 16, 2012. If the Plaintiff does not eventually recover
    this full amount, it shall be responsible for its pro rata
    share of the cost of the bond.” J.A. 45. On August 3,
    2012, the district court entered the bond as an order,
    stating that “Plaintiff has agreed that a bond in amount
    of $50,000,000 will adequately guarantee Plaintiff of full
    payment and that if the ultimate award granted is less
    tha[n] $50,000,000, Plaintiff will reimburse Defendants
    for the cost of the bond above the amount finally award-
    ed.” J.A. 73. Metso never appealed or challenged the
    district court’s bond order. Ultimately, we reversed the
    district court’s judgment of infringement on the ground
    that the asserted claims of the ’618 patent would have
    been obvious to a person of ordinary skill in the art (
    35 U.S.C. § 103
    ). Metso, 526 F. App’x at 998. Importantly
    for the purposes of the present appeal, we also determined
    that “[n]o costs” would be awarded with respect to the
    appeal. 
    Id.
    On September 9, 2013, following the issuance of our
    mandate, Powerscreen moved for (1) release of the bond;
    and (2) reimbursement for $400,000, the amount of the
    premium paid for the bond. On September 13, 2013,
    1 It is unclear from the record why there was such a
    long delay between the March 3, 2011, judgment and the
    June 25, 2012, stay. See Fed. R. Civ. P. 62(a) (“Except as
    stated in this rule, no execution may issue on a judgment,
    nor may proceedings be taken to enforce it, until 14 days
    have passed after its entry.”).
    4                METSO MINERALS INC.   v. TEREX CORPORATION
    Powerscreen amended the motion, seeking an additional
    $100,000 to reflect an increased invoice from the surety.
    On November 27, 2013, the district court granted Pow-
    erscreen’s motion for reimbursement in the amount of
    $400,000, because Metso was “liable for its pro rata share,
    100%, of the cost of the appeal bond, $400,000.” J.A. 18.
    Because the bond orders “were never appealed, and
    therefore, in the Court’s view, were not before the Federal
    Circuit,” the court “construe[d] the Federal Circuit [“no
    costs”] order as applying to costs on appeal other than
    bond premiums.” J.A. 18. On January 29, 2014, the
    district court granted Powerscreen’s motion to correct the
    judgment due to a “clerical mistake” pursuant to Federal
    Rule of Civil Procedure 60(a), and amended the judgment
    to reflect the additional amount of $100,000, for a total of
    $500,000.
    Metso appeals. We have jurisdiction pursuant to 
    28 U.S.C. § 1295
    (a)(1). We review the district court’s inter-
    pretation of our mandate de novo under Federal Circuit
    law. TecSec, Inc. v. Int’l Bus. Machs. Corp., 
    731 F.3d 1336
    , 1341 (Fed. Cir. 2013) (citing Laitram Corp. v. NEC
    Corp., 
    115 F.3d 947
    , 950 (Fed. Cir. 1997)). Apart from the
    mandate issue, the district court’s award of costs is not an
    issue unique to patent law, so we apply the law of the
    regional circuit, in this case the Second Circuit. A district
    court’s determination under Rule 60 is reviewed for abuse
    of discretion. See Robinson v. Sanctuary Music, 383 F.
    App’x 54, 57 (2d Cir. 2010).
    METSO MINERALS INC.   v. TEREX CORPORATION               5
    DISCUSSION
    Metso argues that the district court’s award of bond
    premium costs to Powerscreen contravened this court’s
    mandate of “[n]o costs” in the prior appeal. 2
    2  Federal Rule of Appellate Procedure 39 provides
    that the cost of a supersedeas bond is taxable as a cost on
    appeal. It states, in pertinent part, that:
    (a) Against Whom Assessed. The following rules
    apply unless the law provides or the court orders
    otherwise:
    ...
    (3) if a judgment is reversed, costs are taxed
    against the appellee;
    ...
    (e) Costs on Appeal Taxable in the District Court.
    The following costs on appeal are taxable in the
    district court for the benefit of the party entitled
    to costs under this rule:
    ...
    (3) premiums paid for a supersedeas bond or other
    bond to preserve rights pending appeal[.]
    Fed. R. App. P. 39. Contrary to Metso’s argument, there
    is no requirement that the cost of a supersedeas bond be
    included in the bill of costs in the court of appeals. 16AA
    Charles Alan Wright & Arthur R. Miller, Federal Practice
    and Procedure: Jurisdiction & Related Matters § 3985.1,
    at 589–90 (3d ed. 2008) (“Certain of the appeal costs, such
    as . . . the paying of appeal-bond premiums . . . are in-
    curred only at the district-court level and hence are
    taxable only in the district court. Such items should not
    be submitted to the clerk of the court of appeals as part of
    the bill of costs in that court . . . .”).
    6                METSO MINERALS INC.   v. TEREX CORPORATION
    “[T]he scope of the . . . mandate, and thus the scope of
    the matters removed from the district court’s jurisdic-
    tion,” is “coterminous with the scope of the issues deemed
    presented to the court on appeal.” Engel Indus., Inc. v.
    Lockformer Co., 
    166 F.3d 1379
    , 1382 (Fed. Cir. 1999)
    (citing Sprague v. Ticonic Nat’l Bank, 
    307 U.S. 161
    , 168
    (1939)). And “[t]he scope of the issues presented to this
    court on appeal must be measured by the scope of the
    judgment appealed from.” 
    Id.
     Thus, “[o]nly the issues
    actually decided—those within the scope of the judgment
    appealed from, minus those explicitly reserved or re-
    manded by the court—are foreclosed from further consid-
    eration.” Id. at 1383; see also Exxon Chem. Patents, Inc. v.
    Lubrizol Corp., 
    137 F.3d 1475
    , 1478 (Fed. Cir. 1998)
    (“Even without the express disclaimer in the court’s
    opinion, it would be incorrect to conclude that the court’s
    mandate encompassed an issue that was not presented to
    the court.”); Laitram, 
    115 F.3d at
    951–52 (issues that
    were not appealed, and “neither presented to us nor
    discussed in our opinion, nor necessary to our disposition
    of the appeal,” were not within the scope of the court’s
    mandate).
    Here, the bond orders at issue were not, and could not
    have been, “within the scope of the judgment appealed
    from,” Engel, 
    166 F.3d at 1383
    , because the notices of
    appeal were filed almost six months before the district
    court’s June 25, 2012, entry of the first bond order. Thus,
    the bond orders were not “presented to the court on ap-
    peal,” 
    id. at 1382
    , and it “would be incorrect to conclude
    that the court’s mandate encompassed an issue that was
    not presented to the court,” Exxon, 
    137 F.3d at 1478
    .
    Metso argues that references to the bond order in Pow-
    erscreen’s briefs in the prior appeals “affirmatively added
    the appellate bond cost issue into the scope and compass”
    of the prior mandate. Appellant’s Reply Br. 2–3. The
    existence of passing references to the bond in briefs in the
    METSO MINERALS INC.   v. TEREX CORPORATION              7
    prior appeal does not establish that the bond premium
    payments were within the scope of our mandate.
    Metso argues, based on a colloquy during a July 22,
    2012, hearing on the bond, that there was an agreement
    that Metso would not bear the full cost of the bond in the
    event of a reversal. But as the district court correctly
    found, this contention is without merit. The parties made
    no agreement to vary the terms of Federal Rule of Appel-
    late Procedure 39 or the terms of the court’s order.
    “Metso’s obligation to bear its pro rata share of the bond
    premium stems from [the district court’s] June 25, 2012
    and August 3, 2012 orders and the plain terms of the bond
    itself, not from any agreement or contract entered into by
    the parties on the record.” J.A. 19. The bond order is
    clear on its face and provides that “[i]f [Metso] does not
    eventually recover this full [$50 million] amount, it shall
    be responsible for its pro rata share of the cost of the
    bond.” J.A. 45. The August 3, 2012, order reiterates that
    “if the ultimate award granted is less tha[n] $50,000,000,
    Plaintiff will reimburse Defendants for the cost of the
    bond above the amount finally awarded.” J.A. 73. Metso
    ultimately recovered nothing, so it was liable for its pro
    rata share, or 100%, of the bond premium cost.
    Finally, Metso argues that the district court abused
    its discretion in modifying the judgment to add $100,000
    pursuant to Federal Rule of Civil Procedure 60(a) because
    the change “was not a clerical mistake or typographical
    error.” Appellant’s Br. 31. Although the additional
    $100,000 bond premium cost was included in Pow-
    erscreen’s September 13, 2013, supplemental declaration
    to its September 9, 2013, motion, the district court’s
    November 27, 2013, order did not account for that
    amount. Rule 60(a) provides that “[t]he court may correct
    a clerical mistake or a mistake arising from oversight or
    omission whenever one is found in a judgment, order, or
    other part of the record.” Fed. R. Civ. P. 60(a). Here, the
    8                METSO MINERALS INC.   v. TEREX CORPORATION
    district court expressly found that “the omission of the
    additional $100,000 payment in the November 27, 2013
    decision constituted a ‘clerical mistake’ correctable under
    Fed. R. Civ. P. 60(a).” J.A. 9. The court further noted
    that it “ma[de] this correction to reflect its ‘contempora-
    neous intent’ at the time of the initial decision.” J.A. 11
    (citation omitted). The interpretation of its own orders is
    within the sound discretion of the district court, and we
    decline to accept Metso’s invitation to disturb the court’s
    explicit finding that the omission of the $100,000 in its
    initial order was a clerical mistake subject to correction
    under Rule 60(a). See Cnty. of Suffolk v. Stone & Webster
    Eng’g Corp., 
    106 F.3d 1112
    , 1117 (2d Cir. 1997) (“It is
    peculiarly within the province of the district court . . . to
    determine the meaning of its own order, and even if we
    regarded the opinion or judgment as ambiguous, we
    would not disturb the issuing judge’s interpretation
    absent a clear abuse of discretion.” (citations and quota-
    tion omitted)). We see no merit in Metso’s contention that
    Powerscreen failed to appropriately mitigate its damages.
    AFFIRMED
    COSTS
    Costs to appellee.